Statewide Strategic Transportation SystemTwo-Lane Operational Improvement Study Methodology - Final
VAR-STW-STS 2-Lane Operational Improvement StudyPID No. 97881
February 3, 2017
![Page 2: Statewide Strategic Transportation System Two-Lane ... · VAR-STW-STS 2-Lane Operational Improvement Study – Study Methodology Page 1 INTRODUCTION As part of ODOT’s implementation](https://reader034.fdocuments.net/reader034/viewer/2022042612/5f5403000b47641988551dd7/html5/thumbnails/2.jpg)
VAR-STW-STS 2-Lane Operational Improvement Study – Study Methodology Page i
StatewideStrategicTransportationSystemTwo‐LaneOperationalImprovementStudyMethodology
Final
February3,2017
VAR‐STW‐STS2‐LaneOperationalImprovementStudyPIDNo.97881
Preparedfor:
OhioDepartmentofTransportationOfficeofStatewidePlanningandResearch
Preparedby:
![Page 3: Statewide Strategic Transportation System Two-Lane ... · VAR-STW-STS 2-Lane Operational Improvement Study – Study Methodology Page 1 INTRODUCTION As part of ODOT’s implementation](https://reader034.fdocuments.net/reader034/viewer/2022042612/5f5403000b47641988551dd7/html5/thumbnails/3.jpg)
VAR-STW-STS 2-Lane Operational Improvement Study – Study Methodology Page ii
CONTENTSLISTOFACRONYMS....................................................................................................................................................................iii
INTRODUCTION.............................................................................................................................................................................1
TASK1–STAKEHOLDEROUTREACHANDPARTICIPATION.................................................................................................3
TASK2–DATACOLLECTION/EVALUATIONCRITERIA.......................................................................................................4
TASK3–EXISTINGANDFUTURECORRIDORASSESSMENT.................................................................................................6
TASK4–EVALUATEPOTENTIALIMPROVEMENTS................................................................................................................8
TASK5–STRATEGICPLAN......................................................................................................................................................13
LISTOFFIGURES
FIGURE1‐STUDYMETHODOLOGYFLOWCHART...................................................................................................................1
FIGURE2‐B/CANALYSISFLOWCHART................................................................................................................................12
APPENDICES
APPENDIXA‐LISTOFDELIVERABLES
APPENDIXB‐STAKEHOLDERINTERVIEWSUMMARY
APPENDIXC‐STAKEHOLDEROUTREACHSUMMARYOUTLINE
APPENDIXD‐DATACOLLECTIONCHECKLIST
APPENDIXE‐EXISTINGCONDITIONSREPORTOUTLINE
APPENDIXF‐NEEDSANDCONDITIONSREPORTOUTLINE
APPENDIXG‐GOODSMOVEMENTACTIVITYMODEL
APPENDIXH‐BENEFITCOSTANALYSISOUTLINE
APPENDIXI‐STRATEGICPLANOUTLINE
APPENDIXJ‐EVALUATIONMATRIXTOOL
![Page 4: Statewide Strategic Transportation System Two-Lane ... · VAR-STW-STS 2-Lane Operational Improvement Study – Study Methodology Page 1 INTRODUCTION As part of ODOT’s implementation](https://reader034.fdocuments.net/reader034/viewer/2022042612/5f5403000b47641988551dd7/html5/thumbnails/4.jpg)
VAR-STW-STS 2-Lane Operational Improvement Study – Study Methodology Page iii
LISTOFACRONYMS ADT AverageDailyTraffic
B/C Benefit/Cost
ECAT EconomicCrashAnalysisTool
EIM EconomicImpactModel
ESRI EnvironmentalSystemsResearchInstitute
FASTAct FixingAmerica'sSurfaceTransportationAct
FIPS FederalInformationProcessingStandards
GIS GeographicInformationSystem
HCS HighwayCapacitySoftware
LOS LevelofService
MAP‐21 MovingAheadforProgressinthe21stCenturyAct
NPV NetPresentValue
PCR PavementConditionRating
QEIM QuickEconomicImpactModule
ROI ReturnonInvestment
ODPS OhioDepartmentofPublicSafety
OSTM OhioStatewideTravelModel
STS StrategicTransportationSystem
QA/QC QualityAssurance/QualityControl
TAZ TransportationAnalysisZones
TIMS TransportationInformationManagementSystem
![Page 5: Statewide Strategic Transportation System Two-Lane ... · VAR-STW-STS 2-Lane Operational Improvement Study – Study Methodology Page 1 INTRODUCTION As part of ODOT’s implementation](https://reader034.fdocuments.net/reader034/viewer/2022042612/5f5403000b47641988551dd7/html5/thumbnails/5.jpg)
VAR-STW-STS 2-Lane Operational Improvement Study – Study Methodology Page 1
INTRODUCTION AspartofODOT’simplementationofanAccessOhio2040recommendation,OperationalStudieswillbeperformedalongeachofthe2‐LanehighwaycorridorsidentifiedontheStatewideStrategicTransportationSystem(STS)network.Thegoalofthesestudiesistoanalyzeportionsofthe2‐laneSTSthatarecriticaltofreightmovement.Recognizingtheimportantrolethesehighwaysplayinmovingfreightandascriticaltruckroutes,ODOTwishestolearnmoreabouttheiroperation,identifyfreight“bottlenecks”anddevelopandprioritizeneededimprovements.
Towardthisend,thisstudymethodologyisaimedatprovidingarepeatableframeworktoconductdetailedneedsassessmentsonall2‐LaneSTScorridorfreightroutes,withafocusonidentifyingincrementalsystemimprovementsthatwillenhancetheflowoffreighttrafficandfacilitateeconomicdevelopmentintheStateofOhio.
Figure1‐StudyMethodologyFlowchart
![Page 6: Statewide Strategic Transportation System Two-Lane ... · VAR-STW-STS 2-Lane Operational Improvement Study – Study Methodology Page 1 INTRODUCTION As part of ODOT’s implementation](https://reader034.fdocuments.net/reader034/viewer/2022042612/5f5403000b47641988551dd7/html5/thumbnails/6.jpg)
VAR-STW-STS 2-Lane Operational Improvement Study – Study Methodology Page 2
AsdetailedhereinandsummarizedinFigure 1,themethodologywillbeconductedinfivetasks:(1)StakeholderOutreach,(2)DataCollection/EvaluationCriteria,(3)Existing&FutureConditionsAssessment,(4)EvaluationofPotentialImprovementsand(5)DevelopmentofaStrategicPlan.Thisdocumentwillbeheavilyutilizedtodevelopacorridor‐specificStudyMethodologyduringTask1.4.
ODOT’sin‐houseexpertiseandplanningtoolswillbereliedupontohelpshapeanddeliverseveralcriticalcomponentsofthestudythroughuseoftheOhioStatewideTravelModel(OSTM)anditsassociatedstandalonemodulesincludingUCost2,EconomicImpactModel(EIM),andtheQuickEconomicImpactModule(QEIM).OSTMoutputforecastdata,forthecurrentyearand2040horizon,willbeusedasthebasisfortheTask2operationalanalysis.
Consistentwiththemethodologycontainedherein,theintentforimprovementsthatarelargeenoughtofitwithintheparametersofEIMandUCost2,istoutilizeEIMandUCost2outputdataduringtheevaluationphase(Task4).Forsmallerimprovementsand/orwhereEIMandUCost2outputisnotavailable,anevaluationwillbenecessarytoincorporateacombinationofofflinecalculationsandtheQEIM,whereapplicable,asdescribedunderTask4.
![Page 7: Statewide Strategic Transportation System Two-Lane ... · VAR-STW-STS 2-Lane Operational Improvement Study – Study Methodology Page 1 INTRODUCTION As part of ODOT’s implementation](https://reader034.fdocuments.net/reader034/viewer/2022042612/5f5403000b47641988551dd7/html5/thumbnails/7.jpg)
VAR-STW-STS 2-Lane Operational Improvement Study – Study Methodology Page 3
TASK 1 – STAKEHOLDER OUTREACH AND PARTICIPATION DuringTask1,kick‐off,mobilizeandorganizethestudy,performstakeholderoutreachanddevelopamethodologyspecifictothecorridorbeingstudiedusingthisdocumentasaframework.1.1Kick‐offMeetingArrangeandconductaprojectkick‐offmeetingamongtheprojectteam.Presentanddiscussthescope,issuesandopportunities,milestonedates,communicationprotocols,teamresponsibilities,deliverables,andotherexpectations.Provideameetingagendaandprepareminutesforelectronicdistributiontoallattendees. 1.2DevelopProjectScheduleDevelopaMasterStudySchedule,includingadetailedtask/sub‐taskworksequence.ThescheduleshouldalsoidentifyallmajordeliverablesandreviewtimesforODOTandotheragencystakeholders.1.3StakeholderInterviewsODOT’spublicoutreacheffortsduringtheAccessOhio2040studywereconsiderableandwillbeincorporatedintotheSTS2‐LaneOperationalImprovementStudy,asapplicable.ForthismorefocusedlookatfreightalongtheindividualSTScorridor,identify“targeted”freightusers,andotherstakeholders,includingODOTdistrictpersonnel,truckinglogisticspersonnelfrombusinessesandindustries,andpublicagencies(e.g.economicdevelopmentcorporationsandportauthorities)familiarwiththerouteanditsoperations.Theseinteractions,eitherbyphoneorin‐personasappropriate,withselectshippers,agriculturalrepresentatives,manufacturers,andlogisticsprofessionalsareaimedatgaininganunderstandingoftheirsystemperformanceneeds(e.g.,importanceofcost,velocity,reliability,etc.);modalusagepatterns;andchangingregional/national/internationaltradepatterns.Itisassumedthatten(10)interviewswillbeconducted.PrepareandmaintainacontactlistofstakeholderstobeapprovedbyODOT.Serviceswillincludeidentifyingstakeholders,preparingforandconductingindividualinterviews,inadditiontodocumentingallstakeholdermeetings.Developastakeholdersurveyinstrumentcontainingalist(s)ofquestionsthatwillserveasaframeworkforguidingtheinterviews.AsampleStakeholderInterviewSurveyisprovidedinAppendixB.Provide,intheformofaStakeholderOutreachSummary,aconciseoverviewofthemostpertinentstakeholderfeedback,includingexistingoperationalandsafetyissuesandanypotentialcountermeasuresputforward.AStakeholderSummaryOutlinehasbeenincludedasAppendixC.1.4StudyMethodology(Corridor‐specific)UsingthisVAR‐STW‐STS2‐LaneOperationalImprovementStudy–StudyMethodologyasaframework,prepareacorridor‐specificmethodologytailoredtomeetthespecificneedsofthecorridor.Oncethedraftcorridor‐specificmethodologyisready,itwillbepresentedtoODOTCentralOffice,District(asapplicable),andotherappropriateprojectteampersonnel.Afterreviewcommentsarereceived,allcommentswillbeaddressedandincorporatedintothefinalcorridor‐specificmethodology.
![Page 8: Statewide Strategic Transportation System Two-Lane ... · VAR-STW-STS 2-Lane Operational Improvement Study – Study Methodology Page 1 INTRODUCTION As part of ODOT’s implementation](https://reader034.fdocuments.net/reader034/viewer/2022042612/5f5403000b47641988551dd7/html5/thumbnails/8.jpg)
VAR-STW-STS 2-Lane Operational Improvement Study – Study Methodology Page 4
TASK 2 – DATA COLLECTION / EVALUATION CRITERIA DuringTask2,beginimplementationofthecorridor‐specificmethodologydevelopedduringTask1.4.Collectanddistilldata,determinetheevaluationcriteriatogaugeproposedimprovements,developaninitiallistofpotentialimprovements,andsupplementgapsinexistingavailabledatabyconductingadditionalturningmovementtrafficcountsatstrategiclocations.2.1CollectionofExistingDataBegingatheringexistingdatabytakingfulladvantageoftheabundanceofsecondarysourcedatathatisalreadyavailablethroughODOT,includingavailableGeographicInformationSystem(GIS)mapping,theEnvironmentalSystemsResearchInstitute(ESRI)StateRouteInventory,andTransportationInformationManagementSystem(TIMS).AsummaryofavailabledatasourcesisprovidedinAppendixD–DataCollectionChecklist.Inaddition,researchandobtainapplicable,plans,studiesandreportsandseekoutadditionaldatarelatedtooperationalanalysis,levelofservice(LOS),triporiginsanddestinations,traveltime/delaystudies,crashrates,safetyassessments,truckfuelingstationandovernightparkinglocations,diversionanalysis,historicalanalysis,androadwaystandards.Tohelplimitthenumberoftrafficcountlocationsandextentofthedatacollectioneffort,performawindshieldsurveyofpotentialoperational“hotspots”alongthecorridor,includingintersections,segments,andotherindividuallocations.Maintainanongoingregisterofdatacollectioneffortsandprepareamemosummarizingthesourcesexamined,contactsmadeanddatagathered.2.2SiteVisitsTosupplementtheODOT‐availabledataandthealready‐performedwindshieldsurvey,performsitevisitsalongtheSTScorridortoclarifyobservationsandidentifyadditionalopportunitiesnotdiscernabledirectlyfromthedata.SitevisitswillincludequickexaminationsofTrafficControl/Signage,AccessPoints,ObservedOperations,andNon‐InventoryGeometrics(e.g.curveradiiandsightdistance).2.3DevelopEvaluationCriteriaDevelopevaluationcriteriaforthestudy.ThesecriteriawillthenbeusedinevaluationofproposedimprovementsandwillberevisitedaspartofTask4(EvaluatePotentialImprovements)andTask5(StrategicPlan)andincorporatedintothequantitative(i.e.Benefit/Cost(B/C))evaluationprocesstoensuretheprojectgoalsandobjectivesarebeingmet.Thesetofcorridor‐specificevaluationcriteriawillbederivedfromthesevennationalperformancegoalsestablishedinMAP‐21andcarriedforwardintheFASTAct,including:(1)Safety,(2)InfrastructureCondition,(3)CongestionReduction,(4)SystemReliability,(5)FreightMovementandEconomicVitality,(6)EnvironmentalSustainability,and(7)ReducedProjectDeliveryDays.TheevaluationcriteriawillbedocumentedinaSummaryMemo. 2.4ListofPotentialImprovementsWorkingwithODOT,includinglocalDistrictstaff,developapreliminarylistofpotentialprojectsforincrementalimprovementswithintheSTScorridor.ODOTwillprovideastatusupdateforallprogrammedprojectsunderdevelopmentalongthestudycorridor.ThelistwillbefurthersupplementedbyknowledgegainedduringTask1.3(StakeholderInterviews),Task2.1(Data
![Page 9: Statewide Strategic Transportation System Two-Lane ... · VAR-STW-STS 2-Lane Operational Improvement Study – Study Methodology Page 1 INTRODUCTION As part of ODOT’s implementation](https://reader034.fdocuments.net/reader034/viewer/2022042612/5f5403000b47641988551dd7/html5/thumbnails/9.jpg)
VAR-STW-STS 2-Lane Operational Improvement Study – Study Methodology Page 5
Collection),andTask2.2(SiteVisits).ThispreliminarylistwillserveasthestartingpointforpotentialimprovementsthatareconsideredandanalyzedinTask3.2.5CollectionofNewTrafficDataItisanticipatedthattherewillbeaneedtosupplementtheabovedatawithlocal,more‐detailedtrafficcountdatainordertoconducttheoperationalanalyses.Afterareviewofdataalreadycollectedandthewindshieldsurvey,identifythenumberandlocationofturningmovementcountsthatarerequired.Turningmovementsaretoincludeindividualcountsfortrucksandpassengervehicles.PerformthenecessaryQualityAssurance/QualityControl(QA/QC)andprovidethecompletedcountstoODOT,forincorporationintotheOSTM.ODOTwillrunthefullOSTM(orasub‐area)andprovidebothcurrentyearandhorizonyear(2040)trafficforecastsfortheno‐buildcondition,andtheseforecastedvolumeswillbeusedduringtheTask3operationalanalysis.
![Page 10: Statewide Strategic Transportation System Two-Lane ... · VAR-STW-STS 2-Lane Operational Improvement Study – Study Methodology Page 1 INTRODUCTION As part of ODOT’s implementation](https://reader034.fdocuments.net/reader034/viewer/2022042612/5f5403000b47641988551dd7/html5/thumbnails/10.jpg)
VAR-STW-STS 2-Lane Operational Improvement Study – Study Methodology Page 6
TASK 3 – EXISTING AND FUTURE CORRIDOR ASSESSMENT DuringTask3,performananalysisofexistingandfutureconditions,developadraftlistofneedsandimprovements,developconceptualplansandcostsforselectcountermeasures/improvements,calculateaninitial“litmustest”B/Cforthesediscreteimprovementsanddetermineacategorizationoftheimprovementsbasedonthescaleoftheirimpactsonthetransportationsystem.Theanalysis,atthisstage,islargelybasedontrafficoperations.Freightconsiderationsandeconomicimpacts,whileconsidered,willbeincorporatedviaexaminationofEIMoutputandqualitativeevaluationcriteriaduringTask4EvaluationofPotentialImprovements.Severalinterimdeliverableswillbeproducedduringthistask,andtheoverallfindingswillbesummarizedina“NeedsandConditions”report.3.1ExistingCorridorAssessment
Asafirststep,reviewOSTMforecastoutputdataforboththecurrentyearandfutureyear(2040)conditions.Then,toserveasaverificationmechanismandlaythegroundworkforthemore“finite”analysisrequiredtoanalyzetheimpactsofproposedimprovementsinTask3.2,performanoperationalanalysisforexistingconditionsusingtheappropriate,ODOT‐approvedanalysissoftware(i.e.HighwayCapacitySoftware(HCS),Synchro,etc.)forboththecurrentyearandfutureyear(2040)conditions.UsingOSTMdatasuppliedbyODOTasabasis,performanoperationalanalysisofboththeintersectionsandroadwaysegments,includingthefollowing:existingyearAMandPMpeakhourturningmovementsatidentified“hotspot”projectstudyareaintersections,existingyearADTforadjacentroadwaysegments,andexistingyearcapacityanalysisforstudyareaintersectionsandroadwaysegments.Inadditiontotheoperationsanalyses,performaSafetyAssessment,andaStandards(Roadway)review.Determineandsummarizeroadwaysegmentandintersectiondeficiencies.PrepareaDraftExistingConditionsReportforreviewandincorporatecommentsintotheFinalExistingConditionsReport.AnExistingConditionsReportOutlinehasbeenincludedasAppendixE.3.2ProposedCorridorAssessmentExamineandreviewdataforthefuture(build)conditionsanalysis,includingafurtherreviewoftheOSTMtobecomemorefamiliarwiththeinputdatarelatedtotheSTScorridor.ThereviewwillalsoconsidertheOSTMinputandrefinementsthattheprojectteammightsuggesttoeithermoreaccuratelydepictconditionsalongtheSTScorridororincorporatemorecurrentdata.ProvideODOTwiththeTask3.1operationalanalysisoutput.ODOT,attheirdiscretion,maywanttoincorporatethefindingsintotheOSTMandre‐runthemodel(orasub‐area),withtheintentofgettingupdatedfuturecondition/no‐buildoutput.StartingwiththeinitiallistofimprovementsdevelopedduringTask2.4,performoperationaltrafficanalysestodeterminethetrafficbehaviorassociatedwitheachdiscreteimprovement,foreithercurrentyearorfutureyear(2040)conditions,asappropriate.Likewithexistingconditions,performacapacityanalysisofboththeintersectionsandroadwaysegments,includingthefollowing:existingyearAMandPMpeakhourturningmovementsatidentified“hotspot”projectstudyareaintersections,existingyearADTforadjacentroadwaysegments,andexistingyearcapacityanalysisforstudyareaintersectionsandroadwaysegments.Proposedimprovementswillbeanalyzedtoensurethattheirimplementationdoesnotadverselyimpactadjacentroutesormerelyrelocateissuesontoothersectionsofthecorridor.Theimprovementswillberefinedbasedontheresultsoftheinitialanalysisandcapacityanalysis.
![Page 11: Statewide Strategic Transportation System Two-Lane ... · VAR-STW-STS 2-Lane Operational Improvement Study – Study Methodology Page 1 INTRODUCTION As part of ODOT’s implementation](https://reader034.fdocuments.net/reader034/viewer/2022042612/5f5403000b47641988551dd7/html5/thumbnails/11.jpg)
VAR-STW-STS 2-Lane Operational Improvement Study – Study Methodology Page 7
Forthoseresultantimprovements,developconceptplans,asummaryfeaturesdescriptionandplanning‐levelcosts.TolimittheextentofthesubsequentworkinTasks4and5,performabasicB/Cevaluationofeachpotentialimprovementbasedonbenefitsderivedfromtraveltimesavingsandcrashreductions. 3.3IdentifyNeedsandImprovements(DraftList)ProvidealistofrecommendedimprovementsalongtheSTScorridor.Improvementswilllargelyfocusonoperationalenhancementstotheinfrastructureandmayinclude,butarenotlimitedtoitemssuchas:improvedsignage,signalcoordination,additionalsignals,shoulderexpansion,laneexpansion,turnlaneadditionsandlengthening,increasedbridgeclearance,increasedloadcapacity,intersectionreconfiguration,safety‐typeimprovementsanddataintegration(e.g.OHGO).Eachrecommendedimprovementwillincludeabriefdescription,costandB/Cratio.Recommendedimprovementswillbecategorizedintofourgroupsbasedonthescaleoftheirimpactsonthetransportationsystem:
GroupA–“Larger‐scale”Improvementsthataddcapacityand/ordiverttraffic(e.g.addingthrulanes;constructionofabypass)
GroupB–“Smaller‐scale”Improvementswheretraveltimesavingscanbequantified(e.g.additionofturnlane(s);installationofatrafficsignal;adjustingtrafficsignaltimings)
GroupC–“Smaller‐scale”Improvementswheretraveltimesavingscannotbequantified,butsafetybenefitscanbequantified(e.g.installingsignage;wideningshoulderwidths)
GroupD–“Smallerscale”Improvementswhereneithertraveltimesavingsnorsafetybenefitscanbequantified(e.g.increasingturnradii;wideningstructures)
PrepareaDraftNeedsandConditionsReportforreviewandincorporatecommentsintotheFinalNeedsandConditionsReport.ANeedsandConditionsReportOutlinehasbeenincludedasAppendixF.
![Page 12: Statewide Strategic Transportation System Two-Lane ... · VAR-STW-STS 2-Lane Operational Improvement Study – Study Methodology Page 1 INTRODUCTION As part of ODOT’s implementation](https://reader034.fdocuments.net/reader034/viewer/2022042612/5f5403000b47641988551dd7/html5/thumbnails/12.jpg)
VAR-STW-STS 2-Lane Operational Improvement Study – Study Methodology Page 8
TASK 4 – EVALUATE POTENTIAL IMPROVEMENTS DuringTask4,beginbyreviewingtheevaluationcriteria,confirmingtheirapplicability,andmakingadditions,revisions,andadjustments,asneeded.TheevaluationofproposedimprovementsrecommendedinTask3.3willvarybasedontheircategorization(GroupA,GroupB,GroupC,orGroupD),asfollows:
GroupA–evaluatedusingEIM/UCost2. GroupB–evaluatedusingacombinationofECAT,QEIMandothertools. GroupC–evaluatedusingacombinationofECAT,othertoolsandqualitativemethods. GroupD–evaluatedusingacombinationofothertoolsandqualitativemethods.
MuchliketheOSTMinputsandparametersexaminedinTask3,reviewtheEIM/QEIMdefaultvaluesforinputsandparametersandrecommendedrefinementsoradjustments,asnecessary.Whereapplicable,ODOTwillperformthedirectentry,preparethenecessaryEIM/QEIMinputs(e.g.traveltime,cost,andphysicallayout)foreachimprovementandeachmodelrun.Uponreceipt,reviewtheEIM/QEIMfinaloutputs,forboththeindividualproject(i.e.incremental)andtheentiresystem(i.e.cumulative).Withthisinformationinhand,performtheeconomicdevelopmentanalysisandevaluategoodsmovementforGroupAandGroupBimprovements,utilizetheGoodsMovementActivityModel(seeAppendixG)tomakequalitativedeterminationsregardinggoodsmovementforallGroupCandGroupDimprovements.PerformareviewofB/CoutputfromEIM/QEIM,makingadjustmentstotheB/Cdataorperformingseparate,individualB/CanalysisforimprovementsthatcannotbeaccuratelymodelledinEIM/QEIM.Task4willculminateinpreparationofaB/CAnalysisSummaryReport.ABenefitCostAnalysis(BCA)ReportOutlinehasbeenincludedasAppendixH.4.1ReviewEvaluationCriteriaRevisittheTask2.3EvaluationCriteriaSummaryMemotoensuretheirutilityduringevaluationoftheneteconomicimpactsofvariousprojectalternativesandtheB/CAnalysis.Reviewthetrafficoperationalmetricssuchasdelay,LOS,traveltimesavings,alongwithsafety,mobility,access,andjobs/commerceevaluationcriteria.Atthisjuncture,considerreducing,weighting,andcombiningmeasurestodevelopODOT‐specificindicesasappropriate.Anattemptwillbemadetoascribeaquantitativefactororcosttoeachevaluationcriteria. 4.2ReviewEconomicImpactModel(EIM/QEIM)DefaultValuesForGroupAimprovements,reviewtheEIMdefaultvaluesforinputsandparametersandrecommendrefinementsoradjustments,asnecessary.ReviewEIMparameterfiles,includingFederalInformationProcessingStandards(FIPS)andTransportationAnalysisZones(TAZ),demographicdatafiles,employmentdatafilesandterminalsfilestodeterminewhichfactorsareused,theirsource,howtheyinformtheEIMmodeloutputandifanyadjustmentsarerequiredthatwouldprovidemorerefinedresults.ForGroupBimprovements,reviewQEIMparameterfilestodeterminewhichfactorsareused,theirsource,howtheyinformtheQEIMmodeloutputandifanyadjustmentsarerequiredthatwouldprovidemorerefinedresults. 4.3InputstoEIM/UCost2&QEIM,perImprovementPreparethenecessaryEIM/QEIMinputsforeachproposedimprovementandeachmodelrunbasedontheirTask3.3categorizationasfollows:
![Page 13: Statewide Strategic Transportation System Two-Lane ... · VAR-STW-STS 2-Lane Operational Improvement Study – Study Methodology Page 1 INTRODUCTION As part of ODOT’s implementation](https://reader034.fdocuments.net/reader034/viewer/2022042612/5f5403000b47641988551dd7/html5/thumbnails/13.jpg)
VAR-STW-STS 2-Lane Operational Improvement Study – Study Methodology Page 9
GroupA‐Foreachoftheidentified“larger‐scale”potentialimprovements,providerepresentativeinputdataforuseintheEIMmoduleandobtaining“improvement‐specific”EIMoutput.Theinputdatawillincludecost,physicallayout,andtraveltimesavingsdata,byapproach,separatedbypassengervehiclesandheavytrucks,andforfourtimeperiods:AM(6AM–9AM),MD(9AM–2PM),PM(2PM–6PM)andNT(6PM–6AM).Whetherindirectly,viaAgeAssetorUCOST2,ordirectly,providethefollowinginputdatainaccordancewithODOT’sEIMUtilityUserGuide(dated8/11/2014)foreachoftheproposedimprovements:ProjectInformation,Costs(Project&Agency),andTraffic/Operations"Manual"DataAdjustments.GroupB‐Foreachoftheidentified“smaller‐scale”potentialimprovementswhereatraveltimesavingscanbequantified,providerepresentativeinputdataforuseintheQEIMmoduleandobtaining“improvement‐specific”QEIMoutput.Theinputdatawillincludecost,physicallayout,andtraveltimesavingsdata,byintersection,separatedbypassengervehiclesandheavytrucks,andforfourtimeperiods:AM(6AM–9AM),MD(9AM–2PM),PM(2PM–6PM)andNT(6PM–6AM).TheinputdatawillalsoincludeProjectLocation(i.e.County),ProjectCosts,andDailyTravelTimeSavings.GroupCandGroupD‐Foreachoftheidentified“smaller‐scale”potentialimprovementswheretraveltimesavingscannotbequantified,EIMandQEIMwillnotbeapplicable.PrepareaqualitativeassessmentofeconomicvitalityandgoodsmovementasdescribedinTask4.6andTask4.7.
4.4EIM/UCost2&QEIMModelRuns(ODOT)ODOTwilldirectlyinteractwiththeEIM/UCost2andQEIMmodulestomake“manual”datainputadjustments,runtheEIM/UCost2andQEIM,andprovideoutputdata.ApplicabilityoftheEIM/UCost2orQEIMtoaproposedimprovementwilldependonitsTask3.3categorizationasfollows:
GroupA‐ODOTwilldirectlyinteractwiththeEIMandUCost2modulestomake“manual”datainputadjustments,runtheEIM/UCost2,andprovideoutputdata.RelyuponthisEIM/UCost2outputdata,includingbutnotlimitedto,incremental(project)andcumulative(overall)impacts,economicmeasures(earnings,businessoutputs,jobscreated,valueadded,production,consumption,employment,andhouseholds,etc.)asthebasisoftheeconomicanalysis.RelyupontheEIMandUCost2modulesforexistingandforecasttraveldataandotheroutputrelatedtoB/C,andEconomicandFreightAnalysis.Provideassistance,asneeded,andrefineorcorrectinputdata,astherunsaremade.GroupB‐ODOTwilldirectlyinteractwiththeQEIMmoduletomake“manual”datainputadjustments,runtheQEIMandprovideoutputdatawhichwillinclude,forbothhouseholdsandfreight:Income,Employment(jobscreated),andEconomicOutput(summaryoftotaleconomicactivity(i.e.servicesprovidedandgoodproduced)generatedbytheimprovement).GroupCandGroupD‐EIMandQEIMwillnotbeapplicable.PrepareaqualitativeassessmentofeconomicvitalityandgoodsmovementasdescribedinTask4.6andTask4.7.
![Page 14: Statewide Strategic Transportation System Two-Lane ... · VAR-STW-STS 2-Lane Operational Improvement Study – Study Methodology Page 1 INTRODUCTION As part of ODOT’s implementation](https://reader034.fdocuments.net/reader034/viewer/2022042612/5f5403000b47641988551dd7/html5/thumbnails/14.jpg)
VAR-STW-STS 2-Lane Operational Improvement Study – Study Methodology Page 10
4.5ReviewofEIM&QEIMOutputPerformareviewofB/CoutputfromEIM/QEIM,makingadjustmentstotheB/Cdataorperformingseparate,individualB/CanalysisforimprovementsthatcannotbeaccuratelymodelledinEIM/QEIM:
GroupA‐ReviewandanalyzetheoutputEIMdata,asavailable.Theoutputdatawillprovidethebasisformuchoftheevaluationandanalysisofeachproposedimprovement.Examinetheincrementalimpactsthatcanbeassociatedwitheachindividualproject,includingtheOperational,MarketAccessandConstructionoutputfiles.Fromthese,deriveearnings,businessoutput,jobscreatedandvalue‐addedoutput.Examinethetotalcumulativeimpactsofeachproject,asprovidedviaEIM,intheProduction,Consumption,Employment,Households,andSummarydata.TheseforecastsincludebaselineeconomicforecastdatafromTREDISandMoody’s.Usingthisdata,makefurtherdeterminationsasnecessaryregardingearnings,businessoutputandjobcreation.GroupB‐ReviewtheQEIMoutputdatawhichwillinclude:Income,Employment(jobscreated),andEconomicOutput(summaryoftotaleconomicactivity(i.e.servicesprovidedandgoodproduced)generatedbytheimprovement).GroupCandGroupD‐EIMandQEIMwillnotbeapplicable.PrepareaqualitativeassessmentofeconomicvitalityandgoodsmovementasdescribedinTask4.6andTask4.7.
4.6EconomicDevelopmentEvaluation
Evaluatetheeconomicanddemographicimplicationsofvariousprojectalternatives,includinginterpretationofEIM/QEIMandselectimprovement‐specificevaluations:
GroupA‐TakeadvantageofthevariousdataandgraphicaloutputsgenerateddirectlyfromEIM,withtheaimofmakingimprovement‐specificdeterminationsofthefollowingeconomicimpacts:Geography/Region,Sector&Industry,Labor/Jobs,Productivity/Operations/Efficiency,Development,andTax/AgencyBenefits.ThefindingsofTask4.6willbeincorporatedintotheoverallevaluation.PrepareanEconomicDevelopmentEvaluationMemo,andsummarizeeconomicdevelopmentevaluationlanguagefordirectinsertionintheTask5StrategicPlan.GroupB‐UtilizeQEIMtoevaluateeconomicbenefits.GroupCandGroupD‐Provideaqualitativeevaluationofeconomicvitalityandgoodsmovement,intandem,usingtheGoodsMovementActivityTool.Usingthetool,aweightedGoodsMovementIndexwillbeassignedtoeachpotentialimprovement.ThisqualitativemeasureprovidesarepresentationofthesignificanceofthegoodsmovementsectorandhowanimprovementalongthecorridormayaffecteconomicactivitywithinagivenCounty.ThequalitativeevaluationwillalsoincludeanyinformationprovidedbystakeholdersduringTask1.3andconsiderhowproposedimprovementsmayaffecteconomicactivity.
ThefindingsofTask4.6willbeincorporatedintotheevaluation.DevelopsummaryeconomicdevelopmentevaluationlanguagefordirectinsertionintheTask5StrategicPlan.
![Page 15: Statewide Strategic Transportation System Two-Lane ... · VAR-STW-STS 2-Lane Operational Improvement Study – Study Methodology Page 1 INTRODUCTION As part of ODOT’s implementation](https://reader034.fdocuments.net/reader034/viewer/2022042612/5f5403000b47641988551dd7/html5/thumbnails/15.jpg)
VAR-STW-STS 2-Lane Operational Improvement Study – Study Methodology Page 11
4.7GoodsMovementEvaluationEvaluatethefreightandgoodsmovementimplicationsofvariousprojectalternatives,includinginterpretationofEIM/QEIMandselectimprovement‐specificevaluations:
GroupA‐ReviewEIMoutputandidentifytheexistingandemergingindustriesthataredrivingthestate’stradebasedeconomy.GroupB‐Identifytheexistingandemergingindustriesthataredrivingthestate’stradebasedeconomytosupplementthereviewofQEIMoutput.GroupCandGroupD‐For“smaller‐scale”improvementswheretraveltimesavingscannotbequantified,provideaqualitativeevaluationofeconomicvitalityandgoodsmovement,intandem,usingtheGoodsMovementActivityTool.Usingthetool,aweightedGoodsMovementIndexwillbeassignedtoeachpotentialimprovement.ThisqualitativemeasureprovidesarepresentationofthesignificanceofthegoodsmovementsectorandhowanimprovementalongthecorridormayaffecteconomicactivitywithinagivenCounty.ThisqualitativeevaluationwillincorporatestakeholderinputgatheredinTask1.3andconsiderhowincrementalproposedimprovementsaffectindustriesandnoteanyinfrastructuredeficienciesinthemovementoffreightalongthecorridor.
ThefindingsofTask4.7willbeincorporatedintotheevaluation.DevelopsummarygoodsmovementevaluationlanguagefordirectinsertionintheTask5StrategicPlan. 4.8B/CAnalysis
DevelopaB/CAnalysisforeachproposedimprovementassummarizedinFigure 2onpage12.Foreachimprovement,determine:NetPresentValue(NPV)oftheimprovementcost,NPVofthebenefit,andaB/Cratio.Wheredataisavailable,monetizebenefitsinthefollowingcategories:Safety(e.g.crashesbytype‐fatal,injury,andpropertydamage),Mobility(e.g.traveltimesavings,traveltimereliability),Access(e.g.tojobsandnon‐workactivities),JobsandCommerce(e.g.changesinemploymentandvalue‐addedoutput,changesinfreighttonnage),environmental(e.g.emissionreduction,improvedairquality,habitatimpacts)andInfrastructurePreservation(lifecyclecosts).DevelopaB/CAnalysisforeachproposedimprovementbasedonitsTask3.3categorizationasfollows:
GroupA‐EntireB/CAnalysiswillbeprovideddirectlyfromEIMandUCost2output.GroupB‐EconomicbenefitswillbeprovidedbyQEIMoutput.ThisoutputwillthenbeincorporatedintotheoverallB/CAnalysis.Transportationuserbenefits(e.g.fuelsavings)andsafetybenefits(e.g.crashreduction)for“smaller‐scale”improvementswillbecalculatedusingtrafficanalysissoftwareandODOT’sEconomicCrashAnalysisTool(ECAT),respectively.CompiletheindividualB/Ccomponentsprovidedbyeachmodel/tool(e.g.QEIM,Synchro,ECAT)intoaspreadsheettoprovideanoverallB/CAnalysis.GroupC‐SafetybenefitswillbecalculatedusingECATtoquantifyaB/Cratio.TransportationuserbenefitsandeconomicbenefitswillbeassessedqualitativelytosupplementthequantifiedB/Cfortheseimprovements.GroupD‐B/Cwillnotbedeveloped,andbenefitswillbeassessedqualitatively.
![Page 16: Statewide Strategic Transportation System Two-Lane ... · VAR-STW-STS 2-Lane Operational Improvement Study – Study Methodology Page 1 INTRODUCTION As part of ODOT’s implementation](https://reader034.fdocuments.net/reader034/viewer/2022042612/5f5403000b47641988551dd7/html5/thumbnails/16.jpg)
VAR-STW-STS 2-Lane Operational Improvement Study – Study Methodology Page 12
PrepareaDraftBenefitCostAnalysis(BCA)SummaryReportforreviewandincorporatecommentsintotheFinalBenefitCostAnalysis(BCA)SummaryReport.TheBenefitCost(BCA)AnalysiswillserveasthebasisforevaluatingeachproposedimprovementandtoassistODOTindeterminingaprioritizationofimprovementsduringTask5.
Figure2‐B/CAnalysisFlowchart
![Page 17: Statewide Strategic Transportation System Two-Lane ... · VAR-STW-STS 2-Lane Operational Improvement Study – Study Methodology Page 1 INTRODUCTION As part of ODOT’s implementation](https://reader034.fdocuments.net/reader034/viewer/2022042612/5f5403000b47641988551dd7/html5/thumbnails/17.jpg)
VAR-STW-STS 2-Lane Operational Improvement Study – Study Methodology Page 13
TASK 5 – STRATEGIC PLAN DuringTask5,developaStrategicPlanandgroupimprovementsintocategories,byimprovementtype,tohelpguidedecisionmakingforvariousprogramsandfundingsources.Prepareareportdocumentingtheworkperformedandrecommendationsmade.Thereportwillincludeaneasy‐to‐read,stand‐aloneoverviewmatrix/chartofproposedimprovementscompletewithcategorization,approximatecosts,andBenefitCostratio.ThevarioustechnicalmemosandreportsdevelopedinTasks1through4willbeincludedasappendices.TheStrategicPlan,excludingappendices,shouldbelimitedtoapproximately40pages.PreparetheStrategicPlanandpresent,includingfindingsandrecommendations,toODOTataStrategicPlanworkshop.AStrategicPlanOutlineisincludedasAppendixI.5.1PrepareDraftPlanandEvaluation
RevisittheTask2.3EvaluationCriteriaSummaryMemotoensuretheirutilityduringdevelopmentoftheStrategicPlan.AdraftStrategicPlan,incorporatingallfindingsandrecommendations,willbeprepared.ThedraftStrategicPlanwillprovideasummaryoverviewoftheindividualdeliverables,includingthestudymethodology,stakeholderoutreach,existingconditions,conceptdevelopment,analysis,andevaluation.Thereportwilldemonstratehowcriteriawereapplied,discussdatasources,analyticaltoolsandmethods,andprovideanoverviewoftheevaluationprocess.AcomprehensiveEvaluationMatrixwillbeincludedalongwithanarrativedescriptionofthemetricsandevaluationcriteriausedtoevaluateproposedimprovements.Improvementswillbegroupedintocategoriesaccordingtoprojecttype(e.g.,intersections,signals,signingandpavementmarking,bridges,pavement,andrailroadcrossings).TofacilitatefurtherevaluationanddecisionmakingbyODOT,theevaluationmatrixwillincludeallbenefits(quantitativeandqualitative).Thematrixwillbeprovidedinadigital,sortableformattoallowODOTplannersanddecisionmakerstodynamicallysortandviewinformationtosuitaparticularprogramneedorfundingsource,whetheraccordingtoprojecttype,cost,B/C,oranyindividualfactororsub‐factor.Thematrixwillalsoincludeaprioritizationofimprovementsintothreecategories:short‐term(1to3yrs.),medium‐term(3to10yrs.),andlong‐term(>10yrs.).AsampleEvaluationMatrixisincludedasAppendixJ.Asappropriate,thedraftplanwilladdressMAP‐21fundingrequirements.PresentthedraftStrategicPlanandEvaluationMatrixatahalf‐dayworkshoptobeheldatCentralOffice.Recognizingthatindividualprojectimplementationisdependentuponfundingavailability,need,projectdevelopmenttimeandotherfactors,projectprioritizationwillbediscussedduringtheworkshop.5.2SubmitFinalPlanIncorporateallcommentsmadeattheTask5.1workshopandsubmitarevisedfinalreporttoODOT.TheStrategicPlanwillbecomprisedoftwoparts:anexecutivesummaryandamainbody.Theexecutivesummaryshouldbestructuredtoserveasastand‐alonesynopsisoftheStrategicPlan.Themainbodywillincludesectionsthatspeaktoallelementsofthestudyprocess,asfollows:
Background Corridor‐SpecificMethodology StakeholderOutreach EvaluationCriteria ExistingConditions
FutureConditions NeedsAndImprovements BenefitCostAnalysis Evaluation
Theevaluationwillincludeastand‐alonematrixandsummarytablesforeachprojectcategorytypeand/orscenario.
![Page 18: Statewide Strategic Transportation System Two-Lane ... · VAR-STW-STS 2-Lane Operational Improvement Study – Study Methodology Page 1 INTRODUCTION As part of ODOT’s implementation](https://reader034.fdocuments.net/reader034/viewer/2022042612/5f5403000b47641988551dd7/html5/thumbnails/18.jpg)
VAR-STW-STS 2-Lane Operational Improvement Study – Study Methodology
APPENDIXA
LISTOFDELIVERABLES
![Page 19: Statewide Strategic Transportation System Two-Lane ... · VAR-STW-STS 2-Lane Operational Improvement Study – Study Methodology Page 1 INTRODUCTION As part of ODOT’s implementation](https://reader034.fdocuments.net/reader034/viewer/2022042612/5f5403000b47641988551dd7/html5/thumbnails/19.jpg)
AppendixA
VAR-STW-STS 2-Lane Operational Improvement Study – Study Methodology
Deliverable
StakeholderListing
DraftStudyMethodology
FinalStudyMethodology
EvaluationCriteriaSummaryMemo
DataCollectionSummaryMemo
DraftExistingConditionsReport
FinalExistingConditionsReport
DraftNeedsandConditionsReport
FinalNeedsandConditionsReport
CostBenefitAnalysisSummaryReport
DraftStrategicPlan
FinalStrategicPlan
EvaluationMatrixTool
![Page 20: Statewide Strategic Transportation System Two-Lane ... · VAR-STW-STS 2-Lane Operational Improvement Study – Study Methodology Page 1 INTRODUCTION As part of ODOT’s implementation](https://reader034.fdocuments.net/reader034/viewer/2022042612/5f5403000b47641988551dd7/html5/thumbnails/20.jpg)
VAR-STW-STS 2-Lane Operational Improvement Study – Study Methodology
APPENDIXB
STAKEHOLDERINTERVIEWSURVEY
![Page 21: Statewide Strategic Transportation System Two-Lane ... · VAR-STW-STS 2-Lane Operational Improvement Study – Study Methodology Page 1 INTRODUCTION As part of ODOT’s implementation](https://reader034.fdocuments.net/reader034/viewer/2022042612/5f5403000b47641988551dd7/html5/thumbnails/21.jpg)
AppendixB
VAR-STW-STS 2-Lane Operational Improvement Study – Study Methodology
US250FREIGHTSTUDY‐STAKEHOLDERINTERVIEWQUESTIONS
INTRODUCTION:TheOhioDepartmentofTransportation(ODOT)isconductinganeedsassessmentonUS250focusedonidentifyingincrementalsystemimprovementstoenhancefreightflows.ToensureODOTunderstandshowUS250isbeingutilizedforfreightmovement,theprojectteamisreachingouttoanumberofbusinessandpublicagenciesalongthecorridortogaintheirinsights.Wehaveafewquestionswewouldliketoaskyou.
QUESTIONSFORCOMMISSIONS/PORTAUTHORITIES:1. Haveyoureceivedanyfeedbackfromorganizations/companiesexpressinganyissuesorconcernswithtransportingtheirgoodsalongUS250?
2. Areyouawareofanypotentialorganizations/companiesthathaveexpressedinterestinlocatinginthisregionthatcouldhaveanimpactonthefreightflowalongtheUS250corridor?
3. Hasanorganization/companyindicatedtoyouthattheydecidednottolocatetothisregionbecauseofissues/concernswithlogistics,specificallyasitrelatestoUS250?
4. Basedonyourexperienceinthisregion,areyouawareofanyincrementalsystemimprovementsthatcouldbemadealongtheUS250corridorthatmightenhancefreightflows?
QUESTIONSFORPRIVATECOMPANIES:1. Business‐‐Whatdoesyourbusiness/agencydo?Whatdoyoumake/whatservicesdoyou
provide?Howmanytrucksdoesyourcompanyhave?Howmanydeliveriesperday/week?2. Shipping‐‐Howdoesyourcompanygetitsgoodstomarket‐‐Rail,truck,water?Doyouhave
truckingin‐house?Ifnotin‐house,whoareyourfreightforwarders,logisticspartners?3. Arethereanybottlenecks?Howmanytrucksadayarrive/departfromyourfacility?Whatare
thecommoditytypes?Wheredotheyenter/exitthecorridor?4. Inputs–Wheredoyoursuppliesandmaterialscomefrom?Fromwhatradiusisyoursupply
chaincomingfrom?Internationalvs.domesticshipments?Whichsegment(s)oftheUS‐250corridordoesyourfreighttrafficmostfrequentlytravel?Arethereanybottlenecksorconcernsthatyouhaveexperiencedorsuppliershavenotedlikeroadwayroughness,etc.?
5. Permitting–Doesyourcompany/constituentsrequirespecialhaulingpermitsforoversize/overweightloads?Haveyouexperiencedlimitationswithverticalclearances,bridgeloadlimits,pavementwidth,geometricswerefindingssuitableroutingisanissueonUS250?
6. DeliveryTimes–Whattime(s)ofdaydoyourdeliveriestypicallyarrive/depart?Dothesetimescoincidewithmorningandevening“rushhours”?Doesyourcompanyutilizejust‐in‐timedeliveryforfreight?Ifso,approximatelywhatpercentageofyourfreightutilizesjust‐in‐timeorjust‐in‐sequencedelivery?Aredriversabletomaketheirdoortimesconsistently?Ifnotwhy?
7. TruckSize/Configuration–Whatisthetypicallengthortypeofyoursemitrailers?Whatisthetypicalnumberofaxels(5or6)onyourtrucks?DoyouutilizeTruckTractor‐Semitrailer‐Trailer(DoubleTrailer)combinations?
8. WithrespecttoUS250inparticular,pleasedescribeindetailthenatureandlocationofany:a. Capacity/recurringcongestionissues.b. Signage–candriversfindyourfacilitywithoutissue?c. Operationalissues–e.g.segmentsorjunctionswheretruckmovementsareimpededd. Safetyissues–accidentsorotherincidentsthatcausehazardsanddelayse. Reliabilityissues–somedaysittakeslongerthanotherstotravelthesamesegments
9. Employees–Howmanyemployeestraveltoyourlocation?Wheredotheycomefrom?
10. OtherBenefits‐‐CanyouthinkofanyimprovementstoUS250thatmaybenefityourcompany/constituents?
![Page 22: Statewide Strategic Transportation System Two-Lane ... · VAR-STW-STS 2-Lane Operational Improvement Study – Study Methodology Page 1 INTRODUCTION As part of ODOT’s implementation](https://reader034.fdocuments.net/reader034/viewer/2022042612/5f5403000b47641988551dd7/html5/thumbnails/22.jpg)
VAR-STW-STS 2-Lane Operational Improvement Study – Study Methodology
APPENDIXC
STAKEHOLDEROUTREACHSUMMARYOUTLINE
![Page 23: Statewide Strategic Transportation System Two-Lane ... · VAR-STW-STS 2-Lane Operational Improvement Study – Study Methodology Page 1 INTRODUCTION As part of ODOT’s implementation](https://reader034.fdocuments.net/reader034/viewer/2022042612/5f5403000b47641988551dd7/html5/thumbnails/23.jpg)
AppendixC
VAR-STW-STS 2-Lane Operational Improvement Study – Study Methodology
STAKEHOLDEROUTREACHSUMMARYOUTLINE
1. Overview
2. IndividualStakeholderSummaries
2.1. PublicAgencies
2.2. Trucking/Logistics
2.3. Manufacturing
2.4. Retail
2.5. EconomicDevelopment
2.6. Intermodal
2.7. Oil&GasExploration
2.8. ODOTCountyManagers
2.9. Tourism
2.10. LawEnforcement
3. SummaryofIdentifiedOperationalandSafetyIssues
3.1. Map/FigureofIdentifiedOperationalandSafetyIssues
4. Appendices
StakeholderMeetingMinutes
![Page 24: Statewide Strategic Transportation System Two-Lane ... · VAR-STW-STS 2-Lane Operational Improvement Study – Study Methodology Page 1 INTRODUCTION As part of ODOT’s implementation](https://reader034.fdocuments.net/reader034/viewer/2022042612/5f5403000b47641988551dd7/html5/thumbnails/24.jpg)
VAR-STW-STS 2-Lane Operational Improvement Study – Study Methodology
APPENDIXD
DATACOLLECTIONCHECKLIST
![Page 25: Statewide Strategic Transportation System Two-Lane ... · VAR-STW-STS 2-Lane Operational Improvement Study – Study Methodology Page 1 INTRODUCTION As part of ODOT’s implementation](https://reader034.fdocuments.net/reader034/viewer/2022042612/5f5403000b47641988551dd7/html5/thumbnails/25.jpg)
AppendixD
VAR-STW-STS 2-Lane Operational Improvement Study – Study Methodology
Data Source InstructionsDate
Collected
ExistingTrafficData
TransportationInformationMappingSystem(TIMS)&Transportation
DataManagementSystem
(TDMS)
SelectLayers>RoadwayInformation>TrafficCountStationsIdentifydesiredTrafficCountStationonmapandfollowResultsweblinktoTrafficReportsforavailabledataatlocation
ForecastedTrafficData OhioStatewideTravelDemandModel(OSTM)&SimplifiedHighwayForecastingTool(SHIFT)
ContactGregGiamoGreg.Giaimo@dot.ohio.govatODOTOfficeofStatewidePlanning&Research
Safety/CrashData GISCrashAnalysisTool
(GCAT)&OhioDepartment
ofPublicSafety(ODPS)
GCAT:https://gcat.dot.state.oh.us/SSL/Login.aspx
OPDSCrashStatistics:
https://ext.dps.state.oh.us/crashstatistics/crashreports.asp
x
SpeedData INRIX RequestODOTProjectManagertocoordinatewiththeODOTOfficeofTrafficOperationstocontactTedTrepanierted@inrix.comatINRIXtoobtainprojectusagerightsforconsultant
BridgeConditionRatings TIMS/BridgeManagementSystem
SelectAssets>BridgeInventory
ForBMRP‐191/BR‐86:
http://bmsreports.dot.state.oh.us//bmsreports/jsp/de
faultFrames.jsp
BridgeLoadRatings/BridgeClearances
BridgeManagementSystem
http://bmsreports.dot.state.oh.us//bmsreports/jsp/defaultFrames.jsp
PavementConditionRatings(PCR)
TIMS SelectLayers>RoadwayInformation>PCR(State)
Oversize/OverweightLoads ODOTSpecialHaulingPermits
Section
ContactMikeMorelandMike.Moreland2@dot.state.oh.usSupervisorofPermits
Geometrics(forlocationsindicatingasignificant
safetyoroperational
issueonly)
RecordPlans/AerialMapping/TIMS
RecordPlans:SelectLayers>ProjectsinTIMSorContactLocalODOTDistrictMapRoom
AerialMapping:availablefordownloadbyCountyat
http://ogrip.oit.ohio.gov/ProjectsInitiatives/OSIPData
Downloads.aspx
HistoricalProjectActivity/AnticipatedFutureProjects
TIMS SelectLayers>Projects
EconomicData OSTMEconomicImpactModel(EIM)
ContactRebekahAndersonRebekah.Anderson@dot.ohio.govatODOTOfficeofStatewidePlanning&Research
GoodsMovementConsumption
2010IMPLANdata ContactGregGiamoGreg.Giaimo@dot.ohio.govatODOTOfficeofStatewidePlanning&Research
GoodsMovementEmployment
2014LongitudinalEmployer‐HouseholdDynamics(LEHD)
data&2016CoStar*data
http://lehd.ces.census.gov/data/
http://www.costar.com/
GoodsMovementTruckTrips
OSTM ContactGregGiamoGreg.Giaimo@dot.ohio.govatODOTOfficeofStatewidePlanning&Research
![Page 26: Statewide Strategic Transportation System Two-Lane ... · VAR-STW-STS 2-Lane Operational Improvement Study – Study Methodology Page 1 INTRODUCTION As part of ODOT’s implementation](https://reader034.fdocuments.net/reader034/viewer/2022042612/5f5403000b47641988551dd7/html5/thumbnails/26.jpg)
VAR-STW-STS 2-Lane Operational Improvement Study – Study Methodology
APPENDIXE
EXISTINGCONDITIONSREPORTOUTLINE
![Page 27: Statewide Strategic Transportation System Two-Lane ... · VAR-STW-STS 2-Lane Operational Improvement Study – Study Methodology Page 1 INTRODUCTION As part of ODOT’s implementation](https://reader034.fdocuments.net/reader034/viewer/2022042612/5f5403000b47641988551dd7/html5/thumbnails/27.jpg)
AppendixE
VAR-STW-STS 2-Lane Operational Improvement Study – Study Methodology
EXISTINGCONDITIONSREPORTOUTLINE
1. Overview
2. Methodology
3. LocationswithIssuesIdentified
3.1. Traffic
3.2. Safety
3.3. Geometry
3.4. PhysicalConditions
4. IndividualLocationAssessments(ModularSummaries)
Foreachlocationstudied:
4.1. LocationOverview
4.2. ExistingConditions
4.3. ProblemStatement
4.4. PotentialCountermeasures
5. ExistingCorridorAssessmentSummary
6. AppendicesOperationalAnalysisOutput(CurrentYear–AMPeakHour)OperationalAnalysisOutput(CurrentYear–PMPeakHour)OperationalAnalysisOutput(DesignYear–AMPeakHour)OperationalAnalysisOutput(DesignYear–PMPeakHour)
![Page 28: Statewide Strategic Transportation System Two-Lane ... · VAR-STW-STS 2-Lane Operational Improvement Study – Study Methodology Page 1 INTRODUCTION As part of ODOT’s implementation](https://reader034.fdocuments.net/reader034/viewer/2022042612/5f5403000b47641988551dd7/html5/thumbnails/28.jpg)
VAR-STW-STS 2-Lane Operational Improvement Study – Study Methodology
APPENDIXF
NEEDSANDCONDITIONSREPORTOUTLINE
![Page 29: Statewide Strategic Transportation System Two-Lane ... · VAR-STW-STS 2-Lane Operational Improvement Study – Study Methodology Page 1 INTRODUCTION As part of ODOT’s implementation](https://reader034.fdocuments.net/reader034/viewer/2022042612/5f5403000b47641988551dd7/html5/thumbnails/29.jpg)
AppendixF
VAR-STW-STS 2-Lane Operational Improvement Study – Study Methodology
NEEDSANDCONDITIONSREPORTOUTLINE
1. ExecutiveSummary
2. Overview
3. ExistingCorridorAssessment
3.1. Traffic
3.2. Safety
3.3. Geometry
3.4. PhysicalConditions
4. ProposedCorridorAssessment
4.1. Traffic
4.2. Safety
4.3. Geometry
4.4. PhysicalConditions
4.5. Cost/PreliminaryIndications
5. IndividualLocationAssessments(ModularSummaries)
Foreachlocationstudied:
5.1. LocationOverview
5.2. ExistingConditions
5.3. ProblemStatement
5.4. PotentialCountermeasures
5.5. ConceptsandCountermeasuresConsidered
5.6. OperationalAnalysis
5.7. Cost
5.8. PreliminaryIndications
6. ExistingCorridorAssessmentSummary
7. ProposedCorridorAssessmentSummary
8. SummaryofProposedCountermeasures
9. NextSteps/Actions
10. Appendices
ProposedCountermeasuresConsidered
EvaluationDataInputsSummary
OperationalAnalysisOutput(CurrentYear–AMPeakHour&PMPeakHour)
OperationalAnalysisOutput(DesignYear–AMPeakHour&PMPeakHour)
![Page 30: Statewide Strategic Transportation System Two-Lane ... · VAR-STW-STS 2-Lane Operational Improvement Study – Study Methodology Page 1 INTRODUCTION As part of ODOT’s implementation](https://reader034.fdocuments.net/reader034/viewer/2022042612/5f5403000b47641988551dd7/html5/thumbnails/30.jpg)
VAR-STW-STS 2-Lane Operational Improvement Study – Study Methodology
APPENDIXG
GOODSMOVEMENTACTIVITYMODEL
![Page 31: Statewide Strategic Transportation System Two-Lane ... · VAR-STW-STS 2-Lane Operational Improvement Study – Study Methodology Page 1 INTRODUCTION As part of ODOT’s implementation](https://reader034.fdocuments.net/reader034/viewer/2022042612/5f5403000b47641988551dd7/html5/thumbnails/31.jpg)
AppendixG
VAR-STW-STS 2-Lane Operational Improvement Study – Study Methodology
GOODSMOVEMENTACTIVITYMODELGUIDE
ODOThasdevelopedasetofmetricsdesignedtoassessthesizeandeconomicsignificanceofGoodsMovementsectorsineachofOhio’s88counties.TheinformationispresentedasananalyticaltooltosupporttheODOTasitconsidersfutureinfrastructureimprovementsalongvarioustransportationcorridorsintheState.
ThismodelproduceskeymetricsofGoodsMovementactivitiesandthesignificanceofGoodsMovementsectorsineachofOhio’s88counties.
TheGoodsMovementActivityModelsummarizesthepreliminaryscoringforall88countiesintheState.Thetoolincludesaweightingsystemtoallowforvaryingtheweightsofthevariablesandprovideflexibilityonacorridor‐by‐corridorbasis.Theinitialweightsaresetacrossallvariablestoadefaultweightof5.0.Attheirdiscretion,ODOTstaffmaycalibratetheweightforeachvariablewithavaluebetween1.0(lowimportance)and5.0(highimportance).
TheGoodsMovementActivityModelintheaccompanyingMicrosoftExcelworkbookprovidesODOTstaffwiththeabilitytocalibratetheweightsforeachofthevariablesaccordingtoimportanceandtotoggletheresultsaccordingly.ThefirstsheetoftheworkbookpresentstheTableofContents:
1 Goods Movement Rank
2 Goods Movement Summary
3 Weight Methodology (Calibration Tab)
4 Summary of Consumption
5 Summary of Employment
6 Summary of Real Estate
7 Summary of Truck Trips
8 Measure Definitions
9 Data Tabs
TheGoodsMovementRankandGoodsMovementSummarytabsprovideanoverviewoftheoutputs.TheTab3WeightMethodology(CalibrationTab)iswherestaffcancalibratetheweights.Tab3istheonlytabthroughwhichstaffwillalterinputs,asnotedintheensuringnarrative.TheSummaryofConsumption,Employment,RealEstate,andTruckTripstabsprovideconsolidatedinformationforeachoftheGoodsMovementmetriccategoriesandtheirinputderivations.TheMeasureDefinitionstabisareferencepageforeachofthevariablesconsideredinthisstudy,andTab9DataTabsisacoverpageprecedingallrawinputdatausedforthisstudy.
![Page 32: Statewide Strategic Transportation System Two-Lane ... · VAR-STW-STS 2-Lane Operational Improvement Study – Study Methodology Page 1 INTRODUCTION As part of ODOT’s implementation](https://reader034.fdocuments.net/reader034/viewer/2022042612/5f5403000b47641988551dd7/html5/thumbnails/32.jpg)
AppendixG
VAR-STW-STS 2-Lane Operational Improvement Study – Study Methodology
WEIGHTMETHODOLOGY(CALIBRATIONTAB)
AcopyoftheCalibrationTool(Tab3)belowshowsthevariablesthatwereassignedweightsversusthevariablesthatwereexcludedfromthescoringsystem.Asmentionedabove,adefaultweightof5.0wasassignedtoeachoftherelevantvariablesandistobecalibratedbyODOTstaffaccordingtosignificanceofvariable.Aweightingsystemhasbeenintroducedforeachoftherelevantvariables,usingascaleof1(lowest)to5(highest)intheorderoflowesttohighestdegreeofrelevancetoprevalenceoftheGoodsMovementsectorinthecounty.Therelevantcountyattributeisthenmultipliedbytheweightestablishedforthatvariabletoproduceavariablescore.Allvariablescoresarethentotaledforanoverallcountyscore.Amaximumscoreof40.0ispossibleifallattributesarethehighestpossiblevalueandifitisdeterminedbystaffthatallvariablesshouldbegivenaweightof5.0
ODOTandthestudyteamshouldassignindividualweightstoeachvariableallowstoaccountforcorridor‐specificconditions.Forexample,ifConsumptionandRealEstatearehighlyrelatedtoGoodsMovementsize,variablesinthosecategoriesshouldbegivenahigherweight(4.0‐5.0)thanthevariablesinEmploymentandTruckTrips(2.5),oranyvariationthereof.Ifanyvariablesarelowpriorities,theymaybeassignedalesserweight(<2.5).
Calibration Tool (Tab 3)
VariableWeight (1 (low)
to 5 (high))2
MIN WEIGHT
MAX WEIGHT
MIN ATTRIBUTE
MAX ATTRIBUTE
MIN OUTPUT
AVG OUTPUT
MAX OUTPUT
Goods Movement ConsumptionPercentile Rank against all sectors in county 1.0 1.0 5.00 0.01 1.00 0.01 5.00Percentile Rank against other counties in State 3.0 1.0 5.00 0.01 1.00 0.01 5.00
0.00 0.00Goods Movement Employment 0.00 0.00
County Pct. of Total Employment/State Pct. of Total Employment 1 4.0 1.0 5.00 0.17 1.00 0.17 5.00
0.00 0.00Goods Movement Related Real Estate 0.00 0.00
County GM Inventory Pct. of Total/State GM Inventory Pct. of Total 1 1.0 1.0 5.00 0.02 1.00 0.02 5.00
County GM Sq. Ft. per Resident/State GM Sq. Ft. per Resident 1 1.0 1.0 5.00 0.00 1.00 0.00 5.00
County GM Sq. Ft. per Employee/State GM Sq. Ft. per Employee 1 5.0 1.0 5.00 0.01 1.00 0.01 5.00
Truck DestinationPercentile (of 88 Ohio Counties) 1.0 1.0 5.00 0.01 1.00 0.01 5.00
County Trips per Employee/State Trips per Employee 1 1.0 1.0 5.00 0.01 1.00 0.01 5.00
Total (max= 40.0 | average= 20.0) 0.25 20.1 40.00[1] If the ratio of county to state is greater than 1.0, the county is attributed with a maximum score of 1.0.[2] Used as a multiplier for county attribute to weight importance of measure against all other measures. The lowest possible weight is 1.0 (not important); the highest possible weight is 5.0 (very important). The default for each of the attributes is set to 5.0; to be calibrated with input from ODOT staff.
![Page 33: Statewide Strategic Transportation System Two-Lane ... · VAR-STW-STS 2-Lane Operational Improvement Study – Study Methodology Page 1 INTRODUCTION As part of ODOT’s implementation](https://reader034.fdocuments.net/reader034/viewer/2022042612/5f5403000b47641988551dd7/html5/thumbnails/33.jpg)
VAR-STW-STS 2-Lane Operational Improvement Study – Study Methodology
APPENDIXH
BENEFITCOSTANALYSISOUTLINE
![Page 34: Statewide Strategic Transportation System Two-Lane ... · VAR-STW-STS 2-Lane Operational Improvement Study – Study Methodology Page 1 INTRODUCTION As part of ODOT’s implementation](https://reader034.fdocuments.net/reader034/viewer/2022042612/5f5403000b47641988551dd7/html5/thumbnails/34.jpg)
AppendixH
VAR-STW-STS 2-Lane Operational Improvement Study – Study Methodology
BENEFITCOSTANALYSISOUTLINE
1. Overview
1.1. Purpose
1.2. StudyEvaluationGroups
2. Costs
2.1. CostEstimatingTechniques
2.2. NetPresentValueandDiscountRate
3. Benefits
3.1. Mobility
3.2. Safety
3.3. Economic
4. BenefitCostAnalysis
4.1. InterpretationofBenefitCostAnalysis
4.2. ResultsforStudyCorridor
5. NextSteps
6. Appendices
MobilityAnalysis
SafetyAnalysis
EconomicAnalysis
BenefitCostAnalysisMatrix
![Page 35: Statewide Strategic Transportation System Two-Lane ... · VAR-STW-STS 2-Lane Operational Improvement Study – Study Methodology Page 1 INTRODUCTION As part of ODOT’s implementation](https://reader034.fdocuments.net/reader034/viewer/2022042612/5f5403000b47641988551dd7/html5/thumbnails/35.jpg)
VAR-STW-STS 2-Lane Operational Improvement Study – Study Methodology
APPENDIXI
STRATEGICPLANOUTLINE
![Page 36: Statewide Strategic Transportation System Two-Lane ... · VAR-STW-STS 2-Lane Operational Improvement Study – Study Methodology Page 1 INTRODUCTION As part of ODOT’s implementation](https://reader034.fdocuments.net/reader034/viewer/2022042612/5f5403000b47641988551dd7/html5/thumbnails/36.jpg)
AppendixI
VAR-STW-STS 2-Lane Operational Improvement Study – Study Methodology
STRATEGICPLANOUTLINE
1. ExecutiveSummary
2. Introduction
3. StudyMethodology
4. StakeholderOutreach
5. EvaluationCriteria
6. NeedsandConditions
7. BenefitCostAnalysis
8. Evaluation
9. Appendices(AllReferencedReports)
StudyMethodology
StakeholderOutreachSummary
EvaluationCriteriaSummaryMemo
NeedsandConditionsReport
BenefitCostAnalysisSummary
![Page 37: Statewide Strategic Transportation System Two-Lane ... · VAR-STW-STS 2-Lane Operational Improvement Study – Study Methodology Page 1 INTRODUCTION As part of ODOT’s implementation](https://reader034.fdocuments.net/reader034/viewer/2022042612/5f5403000b47641988551dd7/html5/thumbnails/37.jpg)
VAR-STW-STS 2-Lane Operational Improvement Study – Study Methodology
APPENDIXJ
EVALUATIONMATRIXTOOL
![Page 38: Statewide Strategic Transportation System Two-Lane ... · VAR-STW-STS 2-Lane Operational Improvement Study – Study Methodology Page 1 INTRODUCTION As part of ODOT’s implementation](https://reader034.fdocuments.net/reader034/viewer/2022042612/5f5403000b47641988551dd7/html5/thumbnails/38.jpg)
AppendixJ
VAR-STW-STS 2-Lane Operational Improvement Study – Study Methodology
EVALUATIONMATRIXTOOL
Tofacilitateevaluation,anevaluationmatrixtool,intheformofaMicrosoftExcelworkbookwillbedeveloped.Thetoolnotonlysummarizestheevaluationcriteriaassessmentsbutalsocanbeusedtodynamicallysortandviewdataandaidinfurtherevaluation.Asshownintheexamplebelow,thematrixincludesbothnumericalratingandgraphicalratingscalestoclearlydepictratingsandlevelsofbenefits.Thematrixcanbesortedusingvariouscriteriasuchasby:location(county,district),locationtype(bridge/culvert,intersection,roadwaysegment),estimatedprojectcost,evaluationgroup(A,B,C,orD),countermeasuretype,B/Cratio,andestimatedprojecttimeframe.Givenvariouscriteria,thematrixallowsdifferentusesforvariousendusers,fordifferentperspectivesandforfundingpurposes.Awiderangeofusers,includingplanners,programmers,funders,local,ODOTdistrictandcentralofficepersonnelcansorttheimprovementsaccordingtotheirparticularneedorenduse,asappropriate.
Evaluation Matrix (Example)
Thetoolispopulatedwithlocationswhereaproposedcountermeasurewasidentified.Anysub‐factorsfromeachoftheevaluationcriteriaareinputintothetool.ThematrixincludesthecostandbenefitcalculationsfromtheB/CAnalysis.BeyondtheB/CAnalysis,additionalevaluationcriteriacategoriessuchasInfrastructureCondition(PCR,BridgeRating,VerticalClearance,HorizontalClearance),GoodsMovement(fromtheGoodsMovementActivityModeldescribedinAppendixE),andSystemReliabilityareincluded.
Replace Structure / Inc. Vert. Clear. $1,630,000 D n/a n/a ●
Adjust signal clearance timings $3,000 C 45.6 44.6 ●
Adjust signal clearance timings $3,000 C 21.0 20.0 ●
Widen Shoulders $5,857,000 C 0.5 ‐0.5 ●
Replace & Widen Structure $151,000 D n/a n/a ●
Widen Pavement $65,000 D n/a n/a ●
Estimated
Project Cost Congestion Reduction
Evaluation Group
Safety
Proposed Countermeasures Infrastructure Condition
System reliability
B/C
Ratio
Freight movement and
economic vitality
Environmental Sustainability
Return on Investment (ROI)
Short Term
Medium Term
Long Term