Statement of Work For Engineering Services...Statement of Work for Engineering Services RFP No....
Transcript of Statement of Work For Engineering Services...Statement of Work for Engineering Services RFP No....
![Page 1: Statement of Work For Engineering Services...Statement of Work for Engineering Services RFP No. 330237, Rev. 0 Project L-839, 12-in. Potable Water Loop-Line to WTP Page 6 of 37 Updated](https://reader030.fdocuments.net/reader030/viewer/2022041106/5f08f08a7e708231d424755d/html5/thumbnails/1.jpg)
Statement of Work for Engineering Services RFP No. 330237, Rev. 0
Project L-839, 12-in. Potable Water Loop-Line to WTP
Page 1 of 37
Updated January 9, 2018
Statement of Work
For
Engineering Services
Title: Engineering Services for Project L-839, 12-in. Potable Water Loop-Line to Waste
Treatment Plant (WTP)
Date: July 29, 2019
Revision Number: 0
![Page 2: Statement of Work For Engineering Services...Statement of Work for Engineering Services RFP No. 330237, Rev. 0 Project L-839, 12-in. Potable Water Loop-Line to WTP Page 6 of 37 Updated](https://reader030.fdocuments.net/reader030/viewer/2022041106/5f08f08a7e708231d424755d/html5/thumbnails/2.jpg)
Statement of Work for Engineering Services RFP No. 330237, Rev. 0
Project L-839, 12-in. Potable Water Loop-Line to WTP
Page 2 of 37
Updated January 9, 2018
TABLE OF CONTENTS
1.0 Introduction / Background......................................................................................... 4
2.0 Objective .................................................................................................................... 4
3.0 Description of Work - Specific ................................................................................... 4
3.1 Task 1 – 30% Design Package............................................................................. 5
3.2 Task 2 – 60% Design Package............................................................................. 6
3.3 Task 3 – 90% Design Package............................................................................. 6
3.4 Task 4 – 100% Final Design Package .................................................................. 6
3.5 Task 5 – Engineering Support to Construction (Bid Option) ................................. 7
3.6 Task 6 – Testing / Startup / Commissioning (Bid Option) ..................................... 8
3.6.1 Testing Documentation .................................................................................... 8
3.6.2 Operations and Maintenance Manuals .............................................................. 9
3.7 Task 7 – As-Built Drawings (Bid Option) ........................................................... 9
4.0 Submittals................................................................................................................... 9
5.0 Acceptance Criteria.................................................................................................. 10
6.0 Configuration Management and Standards ............................................................. 10
6.1 Design Team Task Lead Expectations ................................................................10
6.2 Design Process ..................................................................................................11
6.3 Design Interfaces ...............................................................................................11
6.4 Documentation ..................................................................................................11
6.5 Design Reviews .................................................................................................13
6.6 Design Verification............................................................................................13
6.7 As-Built Process ................................................................................................14
7.0 Requirements ........................................................................................................... 14
7.1 Engineering Requirements .................................................................................14
7.2 Environment, Safety, and Health (ES&H) Requirements .....................................15
7.3 Quality Assurance (QA) Requirements ...............................................................16
7.4 Government Property .........................................................................................17
7.5 Commercial Off the Shelf Software ....................................................................17
7.6 Procurement Of or Specification For New Electrical Equipment or Components ..18
8.0 Personnel Requirements........................................................................................... 18
![Page 3: Statement of Work For Engineering Services...Statement of Work for Engineering Services RFP No. 330237, Rev. 0 Project L-839, 12-in. Potable Water Loop-Line to WTP Page 6 of 37 Updated](https://reader030.fdocuments.net/reader030/viewer/2022041106/5f08f08a7e708231d424755d/html5/thumbnails/3.jpg)
Statement of Work for Engineering Services RFP No. 330237, Rev. 0
Project L-839, 12-in. Potable Water Loop-Line to WTP
Page 3 of 37
Updated January 9, 2018
8.1 Required Qualifications .....................................................................................19
8.2 Training Requirements .......................................................................................22
8.3 Security and Badging Requirements ...................................................................22
8.4 Work Location / Potential Access Requirements .................................................23
8.5 Site Access and Work Hours ..............................................................................23
9.0 Meetings ................................................................................................................... 23
9.1 Subcontract Kick-Off Meeting ...........................................................................24
9.2 Design Progress Meetings ..................................................................................24
9.3 Design Review Meetings ...................................................................................24
9.4 Construction Progress Meetings .........................................................................25
10.0 Deliverables and Performance Schedule Requirements........................................... 25
10.1 Deliverables ...................................................................................................25
10.2 Schedule ........................................................................................................25
10.3 Payment Schedule ..........................................................................................25
11.0 Special Requirements ............................................................................................... 26
APPENDIX A – Submittal Register .................................................................................... 27
APPENDIX B - 30/60/90 Design Deliverables ..................................................................... 31
APPENDIX C – Drawing and/or Document List ................................................................ 35
APPENDIX D – Preconceptual Line Routing ..................................................................... 37
![Page 4: Statement of Work For Engineering Services...Statement of Work for Engineering Services RFP No. 330237, Rev. 0 Project L-839, 12-in. Potable Water Loop-Line to WTP Page 6 of 37 Updated](https://reader030.fdocuments.net/reader030/viewer/2022041106/5f08f08a7e708231d424755d/html5/thumbnails/4.jpg)
Statement of Work for Engineering Services RFP No. 330237, Rev. 0
Project L-839, 12-in. Potable Water Loop-Line to WTP
Page 4 of 37
Updated January 9, 2018
1.0 INTRODUCTION / BACKGROUND
The Department of Energy/200W (200W) public water system supplies sanitary water (SW) to facilities on Hanford’s Central Plateau. The 200W system is owned by the Department of Energy,
under the management of the Richland Operations Office (DOE-RL). Under the authority of the Water Purveyor, MSA Water and Sewer Utilities (W&SU) Operations manages the 200W system. The various systems, facilities, and plants supporting the Hanford Site Cleanup Mission require a safe and reliable SW supply into the Long-Term Stewardship period. The 200W system exists to
support the Cleanup Mission at the Hanford Site and provides SW to the Central Plateau as well as fire protection water supply.
In the operational configuration, the Waste Treatment Plant (WTP) is supplied by one (1) SW line at the southern complex boundary. This creates a single point of failure should a break in this line
occur, which could place WTP in a state of impairment. The WTP is an integral component to the effort to cleanup contamination on the Hanford site.
Project L-839 will eliminate a single point failure and provide a redundant sanitary water (SW) supply to the Waste Treatment Plant (WTP).
2.0 OBJECTIVE
Through this Statement of Work (SOW), Mission Support Alliance, LLC (MSA) is requesting Architectural/Engineering Firm (A/E) services for design, construction support,
startup/testing/commissioning support and as-built/closeout support.
The A/E shall provide all aspects of engineering including civil, mechanical, electrical, fire protection, and instrumentation and controls. Deliverables shall be stamped by a currently licensed professional engineer (PE) and will include drawings, construction specifications,
procurement specifications, calculations, Washington State Department of Health (WDOH) approved project documents, and as-built drawings as well as general engineering support, in accordance with the requirements of this SOW and document HNF-FRDC-62970, Functional Requirements and Design Criteria, 12-in. Potable Water Loop-Line to WTP.
3.0 DESCRIPTION OF WORK - SPECIFIC
The A/E shall provide all aspects of engineering services including management, administration, coordination, and development of design documents required to support construction,
installation, testing, startup and commissioning associated with the Project in accordance with the requirements of this SOW and HNF-FRDC-62970.
![Page 5: Statement of Work For Engineering Services...Statement of Work for Engineering Services RFP No. 330237, Rev. 0 Project L-839, 12-in. Potable Water Loop-Line to WTP Page 6 of 37 Updated](https://reader030.fdocuments.net/reader030/viewer/2022041106/5f08f08a7e708231d424755d/html5/thumbnails/5.jpg)
Statement of Work for Engineering Services RFP No. 330237, Rev. 0
Project L-839, 12-in. Potable Water Loop-Line to WTP
Page 5 of 37
Updated January 9, 2018
Tasks shall include but are not limited to:
Design routing of roughly 13,000-ft. of 12-in C900 PVC pipe.
Determine location of new sampling stations to monitor water quality, water meter and pressure transducer.
Determine locations for new drain/vent valve stations and concrete encasements/thrust blocks for new loop-line as required.
Develop plans for tie-in and testing of new loop-line to existing system.
The A/E shall prepare and submit to MSA a current Washington State licensed PE stamped Project Report in accordance with WAC 246-290-110 using the Water Treatment Facilities Checklist in Appendix A, Section VIII of the Water System Design Manual, Washington State
Department of Health (WDOH), Publication No. 331-123 Rev. 12/09. Phasing of the installation shall be coordinated to minimize downtime of the water system.
NOTE: This SOW includes seven (7) tasks described below. All tasks, one (1) through seven (7) are to be included as itemized pricing.
Table 1. Task Descriptions
Task No. Description
Base Bid
1 30% Design Package
2 60% Design Package
3 90% Design Package
4 100% Final Design Package
Bid Option 5 Engineering Support to Construction
6 Testing/Startup/Commissioning Support
7 As Built Drawings
3.1 Task 1 – 30% Design Package
See Appendix B, 30/60/90 Design Deliverables for minimum deliverables expected with the 30% design package.
Native Files shall be submitted with the 30% design package or within four business days of
submittal (Word, Excel, AutoCAD, etc.).
![Page 6: Statement of Work For Engineering Services...Statement of Work for Engineering Services RFP No. 330237, Rev. 0 Project L-839, 12-in. Potable Water Loop-Line to WTP Page 6 of 37 Updated](https://reader030.fdocuments.net/reader030/viewer/2022041106/5f08f08a7e708231d424755d/html5/thumbnails/6.jpg)
Statement of Work for Engineering Services RFP No. 330237, Rev. 0
Project L-839, 12-in. Potable Water Loop-Line to WTP
Page 6 of 37
Updated January 9, 2018
During the development of the 30% design package deliverables, the A/E shall conduct a subsurface scan and topographical survey. If additional information is required beyond the 30%, then a geotechnical report shall be performed and generated by the A/E.
The A/E shall disposition the MSA comments submitted on the 30% design package and submit to MSA for approval. Task 1 shall not be complete until comment dispositions are approved by MSA. If no resubmit is required, the A/E shall incorporate comments and submit with the 60%
design package.
3.2 Task 2 – 60% Design Package
See Appendix B, 30/60/90 Design Deliverables for minimum deliverables expected with the
60% design package. WAC 246-290-110 Project Report shall not require a PE stamp at this deliverable.
Native Files shall be submitted with the 60% design package or within four business days of submittal (Word, Excel, AutoCAD, etc.).
The A/E shall disposition the MSA comments submitted on the 60% design package and submit to MSA for approval. Task 2 shall not be complete until comment dispositions are approved by MSA. If no resubmit is required, the A/E shall incorporate comments and submit with the 90% design package.
3.3 Task 3 – 90% Design Package
See Appendix B, 30/60/90 Design Deliverables for minimum deliverables expected with the 90% design package. WAC 246-290-110 Project Report shall not require a PE stamp at this
deliverable.
Native Files shall be submitted with the 90% design package or within four business days of submittal (Word, Excel, AutoCAD, etc.).
The A/E shall disposition the MSA comments submitted on the 90% design package and submit
to MSA for approval. Task 3 shall not be complete until comment dispositions are approved by MSA. If no resubmit is required, the A/E shall incorporate comments and submit with the final design package.
3.4 Task 4 – 100% Final Design Package
The 100% design package deliverable shall incorporate any final comments submitted during the 90% review and be fully checked and ready for issue and release (including the DCN cover
![Page 7: Statement of Work For Engineering Services...Statement of Work for Engineering Services RFP No. 330237, Rev. 0 Project L-839, 12-in. Potable Water Loop-Line to WTP Page 6 of 37 Updated](https://reader030.fdocuments.net/reader030/viewer/2022041106/5f08f08a7e708231d424755d/html5/thumbnails/7.jpg)
Statement of Work for Engineering Services RFP No. 330237, Rev. 0
Project L-839, 12-in. Potable Water Loop-Line to WTP
Page 7 of 37
Updated January 9, 2018
sheets and information required for the Engineering Package [EP]). The 100% package should not include new information, unless it was identified and required at the 90% review.
WAC 246-290-110 Project Report shall require a PE stamp and be completed with this
deliverable.
The 100% design documents shall be PE stamped/signed and include native files (Word, Excel, AutoCAD, etc.).
3.5 Task 5 – Engineering Support to Construction (Bid Option)
The A/E shall provide engineering services during construction. This will include reviewing and approving submittals, responding to Request for Clarification/Information (RCI), creating Design Change Notices (DCN), Facility Modification Packages (FMP), submitting Washington Department of Health (WDOH) Project Report updates to MSA if/when significant design
changes are needed to be implemented, site visits to inspect construction and attending meetings. An Employee Job Task Analysis (EJTA) will be required to address potential issues/hazards related to construction site visits.
The basis for the cost of this work shall include:
The A/E shall assign an individual to be the Task Lead (TL) (See Section 6.1 for more details on the expectations of the TL). The TL shall work closely with MSA Buyer’s Technical Representative (BTR), MSA Project Engineer and the MSA Project Manager.
Reviewing and approving technical submittals – Estimated quantity of 20.
Responding to RCIs from the construction subcontractor or other entities– Estimated quantity of 10.
Major design changes – Estimated quantity of 3.
A major design change requires the A/E to perform additional design or design rework, review, and approval documented in a DCN and/or FMP.
o DCNs may be required during construction when field conditions or RCIs result in one of the following: design rework, additional drawing sheet(s), or a design
change. The A/E is expected to create new drawings or perform the necessary drawing changes, and fully check and verify design additions/changes.
o FMP revisions may be required during construction when field conditions or RCIs result in one of the following: design rework or a design change. The A/E is
expected to perform the necessary drawing changes, and fully check and verify the design changes.
NOTE: Calculations may require updating depending on the extent design change.
![Page 8: Statement of Work For Engineering Services...Statement of Work for Engineering Services RFP No. 330237, Rev. 0 Project L-839, 12-in. Potable Water Loop-Line to WTP Page 6 of 37 Updated](https://reader030.fdocuments.net/reader030/viewer/2022041106/5f08f08a7e708231d424755d/html5/thumbnails/8.jpg)
Statement of Work for Engineering Services RFP No. 330237, Rev. 0
Project L-839, 12-in. Potable Water Loop-Line to WTP
Page 8 of 37
Updated January 9, 2018
MSA engineers retain the ability to perform minor design changes throughout the duration of construction. Minor design changes do not affect the intent or function of the original design. Minor changes may include things such as equivalent part substitution,
slight relocation of utilities due to field interferences, etc. These changes are performed and tracked with DCNs and/or FMPs. Copies of the DCNs/FMPs will be sent to the A/E as they are issued/released for tracking purposes.
Site Visits – Estimated quantity of 3.
o Site visits will include site reviews with MSA and the construction subcontractor to identify any work that is incomplete or requires correction prior to achieving Substantial Completion. The A/E may choose to include additional site visits to ensure construction is meeting project requirements and expectations at their
discretion and noted in the proposal.
The Engineer of Record shall be required to stamp and submit any partial, as required, and final WDOH Construction Completion Report(s) within 60 days of completion of the Project, and prior to use.
3.6 Task 6 – Testing / Startup / Commissioning (Bid Option)
3.6.1 Testing Documentation
The A/E shall develop the following test documentation using MSC-PRO-ENG-286, Testing of Equipment and Systems (Table 2, Testing Documentation provides high-level
expectations for each type of testing document).
Test Plan – Higher level document defining the required tests, extent of testing, test boundary, testing sequence/schedule, testing methods, rationale for testing,
relationships among items tested and other systems, test or inspection controls to be applied, and review and approval requirements.
o The Test Plan shall also identify the need for Factory Acceptance Testing (FAT), Construction Acceptance Testing (CAT), and/or Operational
Acceptance Testing (OAT) documentation to support system startup and commissioning. The A/E will be responsible to produce the testing documentation required for FAT, CAT, and/or OAT.
Test Specification(s) – Identifies specific tests to be performed, test requirements
and parameters for each test, and test criteria. Testing may be included as part of the Construction Specification or as a standalone Test Specification.
Test Procedure(s) – Provides detailed instructions for performing tests, the acceptance/success criteria, records results; includes prerequisites, precautions,
special equipment, test sequence; identifies hold points; assurance that the scope
![Page 9: Statement of Work For Engineering Services...Statement of Work for Engineering Services RFP No. 330237, Rev. 0 Project L-839, 12-in. Potable Water Loop-Line to WTP Page 6 of 37 Updated](https://reader030.fdocuments.net/reader030/viewer/2022041106/5f08f08a7e708231d424755d/html5/thumbnails/9.jpg)
Statement of Work for Engineering Services RFP No. 330237, Rev. 0
Project L-839, 12-in. Potable Water Loop-Line to WTP
Page 9 of 37
Updated January 9, 2018
and objectives defined by the associated test requirements are satisfied; and objective evidence and confirmation of successful acceptance or success criteria.
Test Report(s) – Provides a summary of the test results, activities undertaken, and
a conclusion of the test results. The A/E shall develop the final outline and format of the Test Report for review and approval by MSA. The construction subcontractor will perform the testing, fill in the required test results, and provide additional documentation as required. The construction subcontractor will submit
the final Test Report to MSA for approval.
Test documents may be standalone documents or may be imbedded within a DCN or FMP. For standalone test documents, suggested outlines are provided in MSC-STD-ENG-60816, Engineering Test Documentation.
3.6.2 Operations and Maintenance Manuals
The A/E shall compile necessary vendor supplied operations and maintenance manuals and design documentation to develop draft procedures for MSA to be able to properly operate, maintain, and troubleshoot the system/equipment/component. See Section 6.4
for more information on MSA procedures.
3.7 Task 7 – As-Built Drawings (Bid Option)
The A/E shall provide as-built drawings and specification(s) at the end of the project. Following construction completion, the A/E is expected to update the drawings and specifications to
incorporate all DCNs and FMPs into the final as-built documentation (including those generated by MSA as a minor change described in Section 3.6). The drawings shall depict the final configuration of the work performed and the specification shall be updated to reflect any changes made during construction. The signed and PE stamped as-built drawings and specifications shall
be submitted to MSA along with the native files. As-built deliverables will be provided in the form of a DCN and FMP.
4.0 SUBMITTALS
See Appendix A, Submittal Register for details related to submittal format, type, review cycles,
etc. All submittals listed on the Submittal Register shall be submitted to MSA Project Document Control at [email protected] using the Subcontractor Document Submittal Form (Site Form A-6003-061) and carbon copy (CC) the Buyer’s Technical Representative (BTR) and Contract Specialist (CS). All transmittal subject headings shall contain, at a minimum, the subcontract
number, task Release number, submittal number, and submittal description.
Forms are available at the following web address under the “Subcontractor Document Forms” link: http://www.hanford.gov/pmm/page.cfm/ContractorForms
![Page 10: Statement of Work For Engineering Services...Statement of Work for Engineering Services RFP No. 330237, Rev. 0 Project L-839, 12-in. Potable Water Loop-Line to WTP Page 6 of 37 Updated](https://reader030.fdocuments.net/reader030/viewer/2022041106/5f08f08a7e708231d424755d/html5/thumbnails/10.jpg)
Statement of Work for Engineering Services RFP No. 330237, Rev. 0
Project L-839, 12-in. Potable Water Loop-Line to WTP
Page 10 of 37
Updated January 9, 2018
A/E deliverables shall be submitted electronically and may include a hard copy. Electronic files must be non-password protected in one of the following formats:
Microsoft® Office Compatible
Primavera P6 (XER)
Microsoft Project (MMP)
Adobe® Reader or Acrobat® (PDF)
Joint Photographic Experts Group (JPEG)
Mathcad Prime 3.1
AutoCAD® (DWG) – 2013 to 2017 version (if later than 2017, back save to 2017
version)
Windows Media Video (WMV).
Electronic submittals may be sent to Project Document Control or delivered via a
MSA-designated File Transfer Protocol (FTP) site.
All engineering submittals must be peer reviewed/quality checked to ensure completeness and accuracy prior to submittal.
Native files for all deliverables shall be provided as noted in the Submittal Register or as
requested by the BTR at any point during subcontract performance.
Requests for Clarification/Information are to be provided to the Project Document Control, CC the BTR and the CS, using the Request for Clarification or Information Form (A-6003-063).
5.0 ACCEPTANCE CRITERIA
A/E work products and services shall meet applicable standards as defined in this SOW and HNF-FRDC-62970. All final design documents shall be approved/stamped by the A/E’s current Washington State licensed PE, if required under Section 3, Description of Work – Specific; Appendix A, 30/60/90 Engineering Deliverables; or Appendix A, Submittal Register.
At the BTR’s discretion, design submittals that are not accepted may only require resubmittal of the Comment Response Form with acceptable comment dispositions to be incorporated into subsequent design submittals.
6.0 CONFIGURATION MANAGEMENT AND STANDARDS
6.1 Design Team Task Lead Expectations
The A/E shall establish a single point of contact to fulfill the role of Task Lead (TL) (e.g., the A/E’s Project Manager). The TL is responsible for coordinating the engineering efforts of the multi-disciplined team in the execution of this subcontract. The TL shall work closely with the
MSA Project Manager and the MSA Engineering Manager (or their delegate), as applicable, to
![Page 11: Statement of Work For Engineering Services...Statement of Work for Engineering Services RFP No. 330237, Rev. 0 Project L-839, 12-in. Potable Water Loop-Line to WTP Page 6 of 37 Updated](https://reader030.fdocuments.net/reader030/viewer/2022041106/5f08f08a7e708231d424755d/html5/thumbnails/11.jpg)
Statement of Work for Engineering Services RFP No. 330237, Rev. 0
Project L-839, 12-in. Potable Water Loop-Line to WTP
Page 11 of 37
Updated January 9, 2018
monitor the design budget and schedule. The TL is responsible for preparation of work plans or assisting in preparation of the deliverables.
The TL is the point of contact for the effort and has overall responsibility for adequacy of design
inputs, for establishing technical interfaces and integration of disciplines, and for ensuring that the job is completed in accordance with the specified engineering and quality requirements, procedures, and schedule.
The TL is accountable to:
The MSA Design Authority/Engineer(s) to ensure the design products are developed in accordance with the design requirements and criteria.
The MSA Project Manager and Engineering Manager, as applicable, for integration of
technical work with the project or task scope, schedule, and budget and to ensure the design meets technical requirements, specifications, and quality requirements.
6.2 Design Process
The A/E shall develop design content in accordance with their internal, qualified engineering
program, process and procedures, except where noted in this SOW.
The A/E shall establish and control design interfaces in accordance with Section 6.3.
The design content shall be documented in accordance with Section 6.4.
The A/E shall perform an internal design review of their generated designs in accordance with
Section 6.5.
6.3 Design Interfaces
Design interfaces shall be identified, documented, and controlled in a specification or on an MSA drawing and be uniquely identified.
6.4 Documentation
Work produced as part of this SOW shall be documented and meet the MSA standards listed in Section 7.1, Engineering Requirements, the statements below, and HNF-FRDC-62970.
Specifications and other Technical Documents . New or revised specifications or other
technical documents shall be prepared in accordance with the A/E’s internal procedures. Appropriate editorial and presentation standards shall be employed. Specifications and technical documents received by MSA will be reviewed, approved and released by MSA using the Engineering Package (EP) electronic approval process in accordance with MSC-PRO-ENG-440,
Engineering Package Process. The A/E shall prepare and finalize the document, and then MSA will initiate the EP and process the package for approval and release. Each document will have a
![Page 12: Statement of Work For Engineering Services...Statement of Work for Engineering Services RFP No. 330237, Rev. 0 Project L-839, 12-in. Potable Water Loop-Line to WTP Page 6 of 37 Updated](https://reader030.fdocuments.net/reader030/viewer/2022041106/5f08f08a7e708231d424755d/html5/thumbnails/12.jpg)
Statement of Work for Engineering Services RFP No. 330237, Rev. 0
Project L-839, 12-in. Potable Water Loop-Line to WTP
Page 12 of 37
Updated January 9, 2018
unique document number obtained through the Hanford Document Numbering System (HDNS). The A/E shall submit a list of specifications and/or technical documents, and then MSA will request and supply the document numbers.
Design Analysis. The A/E shall develop design analyses in accordance with their own internal processes. Design analysis documentation shall include:
1. Definition of the objective of the analysis;
2. Definition of analysis inputs and their sources;
3. Results of literature searches or other applicable background data;
4. Identification of assumptions and indication of those that must be verified as the design proceeds;
5. Identification of any computer calculation including computer type, computer program
(e.g., name), revision identification, inputs, outputs, evidence of or reference to computer program verification and validation and the bases (or reference hereto) supporting application of the computer program to the specific physical problem;
6. Review and approval.
Native files are submitted with the design package submittals for each analysis and subsequent revision.
Standalone design analyses received by MSA (i.e., those not incorporated into a Facility Modification Package or Design Change Notice) will be reviewed, approved, and released using
the EP process. Design analyses incorporated into an EP shall use Form A-6007-113, Calculation Peer Review Checklist.
Engineering Calculations. New or revised engineering calculations shall be prepared and issued in accordance with MSC-PRO-ENG-8259, MSC Calculation Preparation and Issue.
Standalone calculations will be assigned a document number from the HDNS and released by MSA using the EP electronic approval process. Calculations shall be submitted with Form A-6007-113, Calculation Peer Review Checklist. The A/E shall prepare and finalize the calculation, and then MSA will initiate the EP and process the package for approval and release.
Engineering Drawings. New or revised Engineering Drawings to be released into MSA document control system shall be prepared in accordance with HNF-14660 Offsite Vendor Instructions for Preparation and Control of Engineering Drawings. Drawings submitted as vendor information are exempt from this requirement. See Appendix C for list of existing
essential, support, reference drawings and other relevant documents.
Facility Modification Packages (FMP). A FMP shall be used for modifications to existing drawings affected by the design. The FMP shall be prepared in accordance with
![Page 13: Statement of Work For Engineering Services...Statement of Work for Engineering Services RFP No. 330237, Rev. 0 Project L-839, 12-in. Potable Water Loop-Line to WTP Page 6 of 37 Updated](https://reader030.fdocuments.net/reader030/viewer/2022041106/5f08f08a7e708231d424755d/html5/thumbnails/13.jpg)
Statement of Work for Engineering Services RFP No. 330237, Rev. 0
Project L-839, 12-in. Potable Water Loop-Line to WTP
Page 13 of 37
Updated January 9, 2018
MSC-PRO-ENG-2001, Facility Modification Package Process. The A/E shall prepare the attached drawings, documents, etc. and then MSA will initiate the EP and process the package for approval and release. Standard AutoCAD borders for FMP continuation pages can be
provided to the A/E upon request.
Design Change Notices (DCN). The DCN shall be used to issue new and authorize changes to engineering drawings to be “Approved for Construction.” New or revised DCNs shall be prepared and submitted in accordance with MSC-PRO-ENG-8016, Design Change Notice
Process and Form A-6003-324, Design Change Notice. The form also includes instructions along with copies of the forms used for sketches supporting DCN (both portrait and landscape).
Test Documentation. Testing documentation including Test Plan, Test Specification(s), Test Procedures(s), and Test Report(s) in support of FAT, CAT, and OAT shall be developed in
accordance with MSC-PRO-ENG-286. Outlines for each of the document types are included in MSC-STD-ENG-60816. Templates provided by MSA and the procedure outlines can serve as a starting point; the A/E can make additions/deletions as necessary to meet requirements of the Project.
MSA Procedures. New or revised procedures for Operations and Maintenance shall be developed or modified per MSC-PLN-MN-56352, Maintenance Management Plan and in accordance with MSC-PRO-MS-589, Mission Support Contract Management System Documents.
6.5 Design Reviews
The preparation, checking, verification, review, approval and release of all design media needed for the design is included in this SOW. MSA may conduct design reviews on design packages developed under this subcontract in accordance with internal MSA procedures and guides. MSA
Engineering will conduct formal design reviews at the 30%, 60%, and 90% design stages. The MSA-conducted design reviews are not be construed as design verification approval.
Each design product shall be checked, reviewed, and approved internally by the A/E prior to providing the design package to MSA for review, comment, and subsequent approval. Accuracy
of the content and checking for technical adequacy should be appropriate for the stage of design unless otherwise requested by the MSA Design Authority and/or Project Engineer. Design products submitted shall be so noted by watermark or stamp that clearly reflects the stage of design completion (e.g., “30% preliminary,” etc.). In all cases, the deliverable package shall
include an index of the information provided, placeholders for “planned” additions, and be a complete, accurate, and quality conscious representation of the design effort conducted to date.
6.6 Design Verification
The A/E shall submit a design verification plan for all designs as part of the detailed work
execution plan (see Section 7.0) to MSA for review and approval. The design verification plan shall describe the method of implementing and documenting reviews to the extent possible,
![Page 14: Statement of Work For Engineering Services...Statement of Work for Engineering Services RFP No. 330237, Rev. 0 Project L-839, 12-in. Potable Water Loop-Line to WTP Page 6 of 37 Updated](https://reader030.fdocuments.net/reader030/viewer/2022041106/5f08f08a7e708231d424755d/html5/thumbnails/14.jpg)
Statement of Work for Engineering Services RFP No. 330237, Rev. 0
Project L-839, 12-in. Potable Water Loop-Line to WTP
Page 14 of 37
Updated January 9, 2018
understanding that the design has not yet been developed and refinement of the plan may be required as the design progresses.
The A/E shall fully check the final design stage (90%) products in accordance with their
approved Quality Assurance Program and internal implementing procedures. MSA considers 90% design products to be ready for final issue and/or construction. In addition to technical adequacy, checking shall address drafting standard compliance (where applicable as defined in Section 6.4), editorial errors, and overall workmanship.
The A/E shall submit evidence of final design verification documenting the design verification method(s) used (e.g., peer review, alternate calculation, etc.), completed checklists, required verification matrices, etc.
6.7 As-Built Process
The subcontractor shall have a documented as-built process as part of their engineering program procedures that will ensure that as-building activities will depict the post-installation physical facility conditions. The as-built documentation shall be submitted to MSA in the form of a DCN and/or FMP as described in Section 6.4.
7.0 REQUIREMENTS
The A/E shall provide a detailed work execution plan that includes design approach, design development description and rationale, conceptual design schedule, design verification strategy (see Section 6.6), design review meetings (see Section 9.3), and key support personnel. The
design approach shall provide a detailed understanding of the entire scope of this SOW. The schedule shall include a Work Breakdown Structure (WBS) and associated WBS descriptions as necessary.
General
For any work performed on the Hanford Site or any MSA controlled facility, the provisions of the Special Provisions – On-Site, https://www.hanford.gov/pmm/page.cfm/Provisions, will apply to A/E personnel.
7.1 Engineering Requirements
The A/E shall follow the applicable engineering procedures listed in below.
![Page 15: Statement of Work For Engineering Services...Statement of Work for Engineering Services RFP No. 330237, Rev. 0 Project L-839, 12-in. Potable Water Loop-Line to WTP Page 6 of 37 Updated](https://reader030.fdocuments.net/reader030/viewer/2022041106/5f08f08a7e708231d424755d/html5/thumbnails/15.jpg)
Statement of Work for Engineering Services RFP No. 330237, Rev. 0
Project L-839, 12-in. Potable Water Loop-Line to WTP
Page 15 of 37
Updated January 9, 2018
Table 2. Additional MSA Procedures
Number Rev. Title
EU-PRO-ENG-60779 1-3 Equipment and Component Labeling
HNF-14660 4 Off-Site Vendor Direction for Preparation and Control of Engineering Drawings
MSC-PLN-MN-56352 4 Maintenance Management Program
MSC-PRO-ENG-286 4 Testing of Equipment and Systems
MSC-PRO-ENG-440 3 MSC Engineering Package Process
MSC-PRO-ENG-2001 3-1 Facility Modification Package Process
MSC-PRO-ENG-8016 4 Design Change Notice Process
MSC-PRO-ENG-8259 4 MSC Calculation Preparation and Issue
MSC-PRO-ENG-16406 1 Vendor Information (VI) Process
MSC-PRO-MS-589 16 Mission Support Contract Management System Documents
MSC-STD-ENG-097 2 MSC Engineering Design Codes, Standards and Site Specific Design Parameters
MSC-STD-ENG-60816 0-1 Engineering Test Documentation
WSU-PRO-OP-60412 8-4 Equipment and Piping Labeling
The A/E shall follow the applicable codes, standards, regulations, etc. listed in
HNF-FRDC-62970, Section 5.0 for the Project Code of Record.
7.2 Environment, Safety, and Health (ES&H) Requirements
A/E personnel attending meetings or performing walk downs of general office facilities on the Hanford Site receive coverage under the MSA General Hazards Analysis (GHA). The GHA
covers hazards commonly encountered during the performance of daily routine activities.
A/E personnel and lower-tier subcontractors shall be responsible to complete an Employee Job Task Analysis (EJTA) in accordance with MSC-PRO-WP-11058, Occupational Medical Qualification and Monitoring using EJTA for any of the following situations:
a. For any A/E or lower-tier subcontractor employee who will be on the Hanford Site for
more than 30 days in a year
b. For any A/E or lower-tier subcontractor employee who may potentially be exposed to
hazards (e.g. radiological, beryllium, hazardous wastes, noise) while performing in accordance with the subcontract SOW
![Page 16: Statement of Work For Engineering Services...Statement of Work for Engineering Services RFP No. 330237, Rev. 0 Project L-839, 12-in. Potable Water Loop-Line to WTP Page 6 of 37 Updated](https://reader030.fdocuments.net/reader030/viewer/2022041106/5f08f08a7e708231d424755d/html5/thumbnails/16.jpg)
Statement of Work for Engineering Services RFP No. 330237, Rev. 0
Project L-839, 12-in. Potable Water Loop-Line to WTP
Page 16 of 37
Updated January 9, 2018
c. For any A/E or lower-tier subcontractor employee enrolled in a medical or exposure monitoring program required by 10 CFR 851, and/or any other applicable federal, state or local regulation or other obligation.
If any of the above conditions exist, the A/E and its lower-tier subcontractor employee are to have a current approved EJTA prior to that employee beginning work on the Hanford Site.
The MSA Safety Professional shall review any changes to the scope or associated activities for any potential impacts to the Subcontractor or lower-tier subcontractor employees.
MSA’s Safety and Health Procedures are available on the internet at http://www.hanford.gov/pmm/page.cfm/Construction. The documents on this site are kept current and are available for the A/E use.
The A/E shall flow down all ES&H requirements to the lowest tier subcontractor performing
work in support of this SOW and associated activities.
7.3 Quality Assurance (QA) Requirements
The work activities for this SOW have been designated as General Service, Quality Level 3.
The A/E shall document, implement, and maintain a Quality Assurance Program (QAP) that utilizes a national or international voluntary consensus standard or equivalent (i.e. International Standards Organization (ISO) 9001, etc.) that include the following requirements, as a minimum:
Organizational structure, including a description of roles and responsibilities
QAP which describes the process to control items and activities
Indoctrination, training, and qualification and/or certification of project personnel
Design control, including design verification/validation, change control, and software
quality requirements to ensure software produces correct results
Implementing procedures and/or instructions that describe step by step activities
Document control to ensure only correct documents are being used
Corrective action management to identify and correct issues that lead to process improvements
Quality records which are protected from loss or deterioration and are submitted.
![Page 17: Statement of Work For Engineering Services...Statement of Work for Engineering Services RFP No. 330237, Rev. 0 Project L-839, 12-in. Potable Water Loop-Line to WTP Page 6 of 37 Updated](https://reader030.fdocuments.net/reader030/viewer/2022041106/5f08f08a7e708231d424755d/html5/thumbnails/17.jpg)
Statement of Work for Engineering Services RFP No. 330237, Rev. 0
Project L-839, 12-in. Potable Water Loop-Line to WTP
Page 17 of 37
Updated January 9, 2018
Upon award of the subcontract (see Attachment 1, Submittal Register for due date), the QAP document and implementing procedures are required to be reviewed and approved by the MSA Quality Assurance Organization. If the Subcontractor’s QAP has been previously submitted and
approved by MSA, and is current, the Subcontractor may submit a statement to this effect with the proposal and for the submittal requirement. If the Subcontractor’s QAP has been previously submitted and approved by MSA, but is not current, the updated QAP shall undergo resubmission to MSA for review and approval. The Subcontractor shall submit proposed
changes to the QAP and implementing procedures to the Buyer/QAE/CS for review and approval prior to implementation during the performance of this Subcontract.
The A/E shall be responsible for performing quality workmanship and shall conduct the quality control measures necessary to ensure that all work confirms to referenced codes, standards, and
other requirements as defined by this SOW.
If the A/E subcontracts any portion of this work scope to lower tier subcontractors, the A/E shall be responsible for the flow down of applicable portions of this SOW to their lower-tier subcontractors, including engineering and quality assurance requirements, pertaining to services
and activities for which they are responsible.
All A/E activities are subject to oversight by MSA’s QAE and/or Engineering representative(s) at the A/E’s facilities, including lower-tier facilities if applicable. Access to the A/E’s or lower-tier’s facilities shall be requested through the A/E’s contract representative and MSA’s
CS. The visit may be performed jointly with the A/E.
7.4 Government Property
Government property is not required to be used by the A/E in the performance of this SOW.
7.5 Commercial Off the Shelf Software
The A/E shall submit the following documentation for all engineering analysis/design, data analysis/reduction, and engineering/environmental modeling commercial-off-the-shelf (COTS) software1 (application) used in the performance of work activities. Documentation shall be provided even if the applications are verified through manual verification/independent
calculations and/or analyses.
NOTE: If the same COTS product is utilized for a range of calculations this documentation only needs to be submitted once, but documents/calculations shall be traceable back to number 1 specified below and is subject to oversight activities.
1 COTS software refers to an existing application which will be implemented on a standard operating system without
the need for modification of its executable/object code.
![Page 18: Statement of Work For Engineering Services...Statement of Work for Engineering Services RFP No. 330237, Rev. 0 Project L-839, 12-in. Potable Water Loop-Line to WTP Page 6 of 37 Updated](https://reader030.fdocuments.net/reader030/viewer/2022041106/5f08f08a7e708231d424755d/html5/thumbnails/18.jpg)
Statement of Work for Engineering Services RFP No. 330237, Rev. 0
Project L-839, 12-in. Potable Water Loop-Line to WTP
Page 18 of 37
Updated January 9, 2018
1. Description of the COTS software including:
a. Manufacturer’s name and address
b. COTS application’s title and version identifier
c. Operating system and hardware platform that will be used
d. Manufacturer’s Technical Specifications or other published description of the COTS.
2. Standard data set(s) used to verify operation of the COTS application
a. Data sets shall cover each function or mode of operation which will be used during the performance of the work activities.
b. When the COTS application’s range of operation cannot be verified by a single data set, the A/E shall submit, as a minimum, data sets covering the upper and
lower thirds of its range.
3. A/E shall notify MSA of any software errors related to COTS deliverables.
COTS requirements are also detailed in the Contract Documents. Should a conflict exist between this SOW and the Contract Documents, the Contract Documents shall be followed.
7.6 Procurement Of or Specification For New Electrical Equipment or Components
All new electrical equipment and/or components procured as part of this SOW shall meet the following requirements:
Unless otherwise approved by MSA, all electrical equipment and industrial control panels
[a general term including material, fittings, devices, appliances, luminaires (fixtures), apparatus, and the like, used as a part of, or in connection with, an electrical installation] delivered or brought onto the site in performance of a subcontract must be labeled by an organization currently recognized by OSHA as a nationally recognized testing laboratory
(NRTL).
All electrical equipment installed as part of a subcontract must comply with the National Electric Code (NEC), NFPA 70 and where applicable ANSI C2 (NESC).
8.0 PERSONNEL REQUIREMENTS
A/E personnel performing engineering services shall have, appropriate training, experience, qualification and/or certification(s) to perform the work required for this SOW. Documentation/certification of personnel qualifications shall be maintained by the A/E and
provided to MSA upon request. A/E personnel qualifications/certifications may be verified by
![Page 19: Statement of Work For Engineering Services...Statement of Work for Engineering Services RFP No. 330237, Rev. 0 Project L-839, 12-in. Potable Water Loop-Line to WTP Page 6 of 37 Updated](https://reader030.fdocuments.net/reader030/viewer/2022041106/5f08f08a7e708231d424755d/html5/thumbnails/19.jpg)
Statement of Work for Engineering Services RFP No. 330237, Rev. 0
Project L-839, 12-in. Potable Water Loop-Line to WTP
Page 19 of 37
Updated January 9, 2018
MSA prior to performing work in order to provide reasonable assurance that the A/E has assigned the personnel with sufficient documented training, education, and experience to satisfy the specified requirements.
It is expected that the A/E will identify and apply an appropriate mix of resources and experience to each task to ensure MSA is receiving the best value possible for the engineering services being requested.
The A/E shall notify the BTR of any changes to key personnel submitted with the bid proposal
and/or approved by MSA. New personnel will require a resubmit of their resume/qualifications for review and approval by MSA.
8.1 Required Qualifications
A/E shall ensure that its personnel meet and maintain the appropriate training, qualification and
certification requirements.
A/E shall provide current Washington State licensed Professional Engineers in each discipline.
It is expected that the A/E will identify and apply an appropriate mix of resources and experience to each task to ensure that MSA is receiving the best value possible for the engineering services
being requested.
Table 3. Engineering Services Staff Qualifications
Discipline Progression2 Experience Level/Qualifications3
Principal Engineer Applies advanced engineering techniques and analyses for problems and
methods. Has extensive experience in general engineering.
Minimum Qualifications: Bachelors of Science (BS) degree in Engineering
discipline PLUS 15 or more years engineering experience, or equivalent
combination of education and experience related directly to the tasks/design defined within this SOW.
2 The entries for Principle Engineer, Senior Engineer, Advanced Engineer, and Entry -Level Engineer should be
interpreted to include the following engineering disciplines: Electrical, Mechanical, Civil, Structural, Architectural, HVAC, and Fire Protection.
3 Education and experience equivalencies are expected to meet the requirements of DOE O 426.2, Personnel Selection, Training, Qualification, and Certification Requirements for DOE Nuclear Facilities. It is the
responsibility of the A/E to develop and submit these equivalencies.
![Page 20: Statement of Work For Engineering Services...Statement of Work for Engineering Services RFP No. 330237, Rev. 0 Project L-839, 12-in. Potable Water Loop-Line to WTP Page 6 of 37 Updated](https://reader030.fdocuments.net/reader030/viewer/2022041106/5f08f08a7e708231d424755d/html5/thumbnails/20.jpg)
Statement of Work for Engineering Services RFP No. 330237, Rev. 0
Project L-839, 12-in. Potable Water Loop-Line to WTP
Page 20 of 37
Updated January 9, 2018
Discipline Progression2 Experience Level/Qualifications3
Senior Engineer Performs conventional design engineering and analysis. Plans and
conducts independent evaluation, selection, and adaptation of engineering
techniques, procedures, and criteria. When assigned, may provide
managerial and/or technical direction to other engineers.
Minimum Qualifications: BS degree in Engineering discipline PLUS 10 to 14 years engineering experience, or equivalent combination of education and experience related directly to the tasks/design defined within this SOW.
Advanced Engineer Under general supervision, evaluates, selects, and applies standard
engineering techniques, procedures, and criteria.
Minimum Qualifications: BS degree in Engineering discipline PLUS 4 to 9
years engineering experience, or equivalent combination of education and experience related directly to the tasks/design defined within this SOW.
Entry-Level Engineer Under supervision, performs standardized assignments using standard
engineering techniques, procedures, and criteria.
Minimum Qualifications: BS degree in Engineering discipline PLUS 0 to 3
years engineering experience, or equivalent combination of education and experience.
Senior Designer/CAD
Technician
Experienced and proficient in providing direction to designers producing
AutoCAD drawings, performing drawing revisions, engineering changes
documents, and performing field walk downs to obtain dimensions and equipment layout. Responsible for site, facility, system, equipment and
product research to produce design drawings under the direction of design
engineers.
Minimum Qualifications: Associates (AA) degree, minimum of 12 years
progressive responsible experience, and/or equivalent technical/trade school degree plus additional years of progressive experience as a designer in an infrastructure and/or utility service environment.
Designer/CAD
Technician
Experienced and proficient in producing AutoCAD drawings, performing
drawing revisions, engineering changes documents, and performing field walk downs to obtain dimensions and equipment layout. Responsible for
limited site, facility, system, equipment and product research to produce
design drawings under the direction of design engineers.
Minimum Qualifications: AA degree, minimum of 5 to 11 years of
experience or equivalent technical/trade school degree or additional progressive experience.
![Page 21: Statement of Work For Engineering Services...Statement of Work for Engineering Services RFP No. 330237, Rev. 0 Project L-839, 12-in. Potable Water Loop-Line to WTP Page 6 of 37 Updated](https://reader030.fdocuments.net/reader030/viewer/2022041106/5f08f08a7e708231d424755d/html5/thumbnails/21.jpg)
Statement of Work for Engineering Services RFP No. 330237, Rev. 0
Project L-839, 12-in. Potable Water Loop-Line to WTP
Page 21 of 37
Updated January 9, 2018
Discipline Progression2 Experience Level/Qualifications3
Project Manager Responsible for management and execution of assigned project(s) in
accordance with the requirements of the subcontract between the
Subcontractor and MSA, and the A/E’s operating policies and principles.
Responsible for execution of the work in accordance with the quality
standards and requirements specified for the project.
Minimum Qualifications: Bachelor’s degree PLUS 15 or more years related experience.
Technical Writer/Editor Researches, writes, edits, and proofreads technical data for use in
documents or sections of documents such as manuals, procedures, and
specifications. Ensures technical documentation is accurate, complete,
meets editorial and government specification, and adheres to standards for
quality, graphics, coverage, format, and style.
Minimum Qualifications: AA degree in an applicable technical field and 2 years related experience, or an equivalent combination of education and experience.
Clerk/Administrative
Assistant
Handles with minimum supervision and technical assistance standard
clerical work related directly to the assigned subcontract Release. Activities typically performed include typing, report preparation, and
record keeping.
Minimum Qualifications: Graduation from high school and 2 years clerical experience.
Project
Controls/Scheduler
Prepares or assists in preparation of estimating, scheduling, or cost
engineering requirements for a project or assignment. Reviews work for
completeness as required by project specifications and scope definition.
Applies standard cost and/or scheduling data to departmental programs or
systems.
Minimum Qualifications: Bachelor’s degree in Business or related field and
5 or more years related experience, or a combination of education and experience.
Cost Estimator Prepares estimates (i.e., fair cost, conceptual, definitive design). Reviews
specifications and drawings/sketches for the preparation of the cost
estimate(s). Performs detailed quantity takeoff of drawings or sketches.
Applies appropriate cost elements (e.g., overhead, escalation, contingency,
profit) as applicable to the contract type.
Minimum Qualifications: Bachelor’s degree in Business, Engineering or
related field and 5 or more years related experience, or a combination of education and experience.
![Page 22: Statement of Work For Engineering Services...Statement of Work for Engineering Services RFP No. 330237, Rev. 0 Project L-839, 12-in. Potable Water Loop-Line to WTP Page 6 of 37 Updated](https://reader030.fdocuments.net/reader030/viewer/2022041106/5f08f08a7e708231d424755d/html5/thumbnails/22.jpg)
Statement of Work for Engineering Services RFP No. 330237, Rev. 0
Project L-839, 12-in. Potable Water Loop-Line to WTP
Page 22 of 37
Updated January 9, 2018
Discipline Progression2 Experience Level/Qualifications3
QA Engineer Defines and develops quality standards for receiving, in-process and final
inspection in accordance with company and contractual requirements.
Reviews and evaluates complex in-process rejections and implements
corrective actions as needed. Interfaces with customers, vendors, and
company departments to resolve quality problems and provide information. Participates in and may lead audits. Provides technical support to
inspection personnel and feedback to management on inspection and test
trends, returns, and vendor performance.
Minimum Qualifications: Bachelor’s degree in Engineering or related field and 5 or more years related experience.
8.2 Training Requirements
The table below includes the training requirements associated with this SOW.
Table 4. Training Requirements
Hours Course Number Description
4 000001 HGET* – Computer-Based Training (CBT)
4 110001 MSA General Employee Training (MGET) - CBT *In lieu of HGET, employees may complete the Hanford Site Orientation (HSO) which is sent to the A/E at their location.
Some courses may only require a limited number of employees, not ALL employees, to attend in order to complete a specific task for the scope and associated activities.
The A/E shall be responsible for all wages of their employees or lower-tier subcontractor
employees while attending any required training courses. MSA will schedule and furnish Hanford Site-specific training courses at no cost to the A/E.
CBT training may be coordinated through Vivid Learning Systems, 372-0335.
Any changes to the scope or associated activities shall be reviewed by the MSA Safety and
Training Professionals for any potential impacts to the A/E or lower-tier subcontractor employees.
The A/E shall flow down all training requirements, as applicable, to the lowest tier subcontractor performing work in support of this SOW and associated activities.
8.3 Security and Badging Requirements
A/E personnel attending meetings, performing walk downs on the Hanford Site, or accessing a controlled access facility shall obtain a standard or temporary badge.
![Page 23: Statement of Work For Engineering Services...Statement of Work for Engineering Services RFP No. 330237, Rev. 0 Project L-839, 12-in. Potable Water Loop-Line to WTP Page 6 of 37 Updated](https://reader030.fdocuments.net/reader030/viewer/2022041106/5f08f08a7e708231d424755d/html5/thumbnails/23.jpg)
Statement of Work for Engineering Services RFP No. 330237, Rev. 0
Project L-839, 12-in. Potable Water Loop-Line to WTP
Page 23 of 37
Updated January 9, 2018
A standard badge shall be obtained by filling out and sending a Badge Request Form to the CS. Once authorized, present two forms of identification or the enhanced identification at the MSA Central Badging Office.
For a temporary badge, send the name, company (who they work for) and if they are a U.S citizen to the CS. Once authorized, present two forms of identification or the enhanced identification at the MSA Central Badging Office. If the employee was not born in the U.S. (the place of birth is outside of the U.S.) then the naturalization paperwork must also be provided.
For more information on badging, please see the MSA Procurement Website at: https://www.hanford.gov/pmm/page.cfm/safetyandsecurity
A/E personnel attending meetings, performing walk downs on the Hanford Site, or accessing any Hanford facility shall be familiar with Hanford Site emergency management requirements and
response expectations to Hanford Site Emergency Alerting System warnings or sirens. A/E personnel shall also participate in any emergency preparedness drill or exercise that may be taking place unless otherwise exempted by the Drill/Exercise Coordinator.
A/E employees will be required to submit to vehicle searches and not personally carry or
transport certain prohibited articles.
8.4 Work Location / Potential Access Requirements
A majority of work activities will be performed at the A/E’s facilities. Project meetings and/or field walk downs may be performed on the Hanford Site. MSA anticipates the A/E will not
access any radiological controlled areas for which additional radiological training is required.
It is not anticipated, but the A/E shall coordinate with the Buyer if the work scope requires access to the Waste Treatment Plant (WTP) boundary.
8.5 Site Access and Work Hours
Hanford personnel at the Hanford Site work a standard 4/10 schedule. The standard work week consists of ten (10) hours of work between 6:00 am and 4:30 pm, with one-half hour designated as an unpaid period for lunch, Monday through Thursday.
Work performed outside normal operating hours shall be coordinated and/or approved through
the BTR and/or the CS prior to performing the work.
9.0 MEETINGS
A/E shall participate in all meetings as required by the BTR.
General purpose of meetings is for the coordination, control, and direction of the work. In
addition to meetings addressed by this Section, the A/E may be required by other Sections and
![Page 24: Statement of Work For Engineering Services...Statement of Work for Engineering Services RFP No. 330237, Rev. 0 Project L-839, 12-in. Potable Water Loop-Line to WTP Page 6 of 37 Updated](https://reader030.fdocuments.net/reader030/viewer/2022041106/5f08f08a7e708231d424755d/html5/thumbnails/24.jpg)
Statement of Work for Engineering Services RFP No. 330237, Rev. 0
Project L-839, 12-in. Potable Water Loop-Line to WTP
Page 24 of 37
Updated January 9, 2018
other Subcontract documents to conduct special-purpose meetings and various safety meetings and briefings.
MSA will issue meeting notices and prepare an agenda and minutes for each meeting addressed
in this Section unless otherwise specified. When applicable, minutes will identify action items, assigned actionees, and due dates.
Table 5. Meeting Attendance
Task
No.
Attendance in Person
Description Mandatory Optional
N/A X Design Kick-Off Meeting
N/A X Design Progress Meetings
1 X 30% Design Package 2 X 60% Design Review Meeting
3 X 90% Design Review Meeting
4 X 100% Design Package
5 X Construction Support
6 X Testing/Startup/Commissioning, Meet with Operations
7 X As-Built Drawings
9.1 Subcontract Kick-Off Meeting
Prior to the start of work, a kick-off meeting will be held between MSA and the A/E at a time and location agreed to by both parties. Invited attendees will include MSA, A/E, and others
having an interest in the work. The purpose of the meeting is to coordinate the start or work, discuss the A/E’s scope, deliverable due dates, information transfer, reviews, meetings, reporting, etc.
9.2 Design Progress Meetings
MSA and the A/E shall meet on a regular basis to status progress at a time, location and frequency determined by MSA. Invited attendees will include MSA, A/E, and others having an interest in the work. The purpose of the meeting is to discuss issues and proposed resolutions, review schedule, discuss comments, and provide on-the-spot answers.
9.3 Design Review Meetings
Design review meeting will be held to ensure the design objectives are achieved. The meeting will be held after the design packages have been received by MSA, and prior to MSA submitting comments. The design review meeting shall be included in the A/E’s Work Execution Plan,
including the proposed method of implementing and documenting the review meeting. The final time and location will be determined by MSA, but within the A/E’s Work Execution Plan. Attendees will include MSA Project personnel and the A/E. Other invitees may include MSA
![Page 25: Statement of Work For Engineering Services...Statement of Work for Engineering Services RFP No. 330237, Rev. 0 Project L-839, 12-in. Potable Water Loop-Line to WTP Page 6 of 37 Updated](https://reader030.fdocuments.net/reader030/viewer/2022041106/5f08f08a7e708231d424755d/html5/thumbnails/25.jpg)
Statement of Work for Engineering Services RFP No. 330237, Rev. 0
Project L-839, 12-in. Potable Water Loop-Line to WTP
Page 25 of 37
Updated January 9, 2018
personnel from Operations, Maintenance, Safety, Environmental, Quality Assurance, Facilities, Procurement, and Engineering.
9.4 Construction Progress Meetings
The A/E shall participate in the construction progress meetings with MSA and the construction subcontractor. Invited attendees will include MSA, A/E, construction subcontractor, and others having an interest in the work. The purpose of the meeting is to discuss issues and proposed resolutions, review schedule, discuss comments, and provide on-the-spot answers. The A/E may
attend the meetings via conference call.
10.0 DELIVERABLES AND PERFORMANCE SCHEDULE REQUIREMENTS
10.1 Deliverables
All deliverables associated with this SOW have been identified in Appendix A, Submittal
Register. The A/E shall maintain a project schedule to ensure completion of design deliverables. On a weekly basis, the A/E shall be prepared to report progress on the MSA Project Schedule maintained by the MSA Project Team. Status reporting is expected to include the completion date(s) and percent complete for each deliverable.
10.2 Schedule
The period of performance for this scope of work is established as:
Start Date: Date of Subcontract Award Completion Date Task(s) 1-4: See Subcontract Award
Completion Date Task(s) 5-7: See Bid Option Subcontract Award
A project schedule shall be submitted for approval by MSA covering activities for the duration of the subcontract. The schedule shall be in the form of a bar chart (P3, P6, or Microsoft Project
preferred, but not required) and shall identify logical sequence and relationship of activities for design, submittals, comment incorporation/disposition, and milestones. Activity durations shall be in working days (Monday through Thursday).
10.3 Payment Schedule
Milestone payments are as shown in Table 6 and Table 7 and released with final MSA approval of each task.
![Page 26: Statement of Work For Engineering Services...Statement of Work for Engineering Services RFP No. 330237, Rev. 0 Project L-839, 12-in. Potable Water Loop-Line to WTP Page 6 of 37 Updated](https://reader030.fdocuments.net/reader030/viewer/2022041106/5f08f08a7e708231d424755d/html5/thumbnails/26.jpg)
Statement of Work for Engineering Services RFP No. 330237, Rev. 0
Project L-839, 12-in. Potable Water Loop-Line to WTP
Page 26 of 37
Updated January 9, 2018
Table 6. Milestone Payments Tasks 1-4
At the Completion of: Percent of Payment
Task 1 35%
Task 2 26% Task 3 18%
Task 4 21%
Total 100%
Table 7. Milestone Payments Tasks 5-7 (Bid Option)
At the Completion of: Percent of Payment
Task 5 33%
Task 6 40%
Task 7 27%
Total 100%
11.0 SPECIAL REQUIREMENTS
Reporting Administration
Status reports shall be submitted at the request of the BTR. The A/E shall provide status at the progress meetings.
Under no circumstances shall the Subcontractor interact directly with regulatory agencies prior to
notifying and obtaining the concurrence of the CS, the BTR, and the Director of Water and Sewer
Utilities.
![Page 27: Statement of Work For Engineering Services...Statement of Work for Engineering Services RFP No. 330237, Rev. 0 Project L-839, 12-in. Potable Water Loop-Line to WTP Page 6 of 37 Updated](https://reader030.fdocuments.net/reader030/viewer/2022041106/5f08f08a7e708231d424755d/html5/thumbnails/27.jpg)
Statement of Work for Engineering Services RFP No. 330237, Rev. 0
Project L-839, 12-in. Potable Water Loop-Line to WTP
Page 27 of 37
Updated January 9, 2018
APPENDIX A – SUBMITTAL REGISTER
Submittal Register Definitions
1. Numerical submittal sequence number: Example: 1, 2, 3, 4 … (or organized by topics and
project assigned coding structure).
2. Number of Copies and electronic and/or hard copy: Example: E (Electronic only), 6 (Six Hard
Copies), or Hard, 1: E, 1 (One Hard Copy, and Electronic).
3. Format: Describes the type of submittal required:
DWG An AutoCAD drawing using the Hanford standard formatting
(See MSC-PRO-ENG-16406, Off-Site Vendor Directions of the Preparation and Control of Engineering Drawings).
MFC Microsoft Format Compatible application (Word, Excel, Access, PowerPoint)
P3 A Primavera Project Planner schedule
PDF Adobe Acrobat (Portable Document Format)
4. Submittal Type:
APW = Approval Required Prior to Work (Buyer must approve the A/E’s submittal prior to the A/E being authorized to proceed with any activity/work associated with the submittal).
AP = Approval Required (Buyer must approve the A/E’s submittal, however, work
associated with the submittal may proceed prior to Buyer approval).
5. Description / Document Title: Title or general description of the document.
6. Submittal Date: Actual date or number of Work Days before or after a milestone that a submittal
is due from the A/E: Example: June 1, 2005 or A + 24d [24 work days or 6 weeks after Award
of the Subcontract]
A Date of Award
KO Kickoff Meeting
30%/60%/90% Design Package Complete
SC Start of Construction
CC Construction Complete
7. Buyer Review Time (Work Days): Example: 8 Days
8. Subcontract Reference: Cross reference to the Subcontract requirement that defines this
submittal: Example: SOW 3.1.2.
9. Insert name of submittal approvers (after subcontract award).
![Page 28: Statement of Work For Engineering Services...Statement of Work for Engineering Services RFP No. 330237, Rev. 0 Project L-839, 12-in. Potable Water Loop-Line to WTP Page 6 of 37 Updated](https://reader030.fdocuments.net/reader030/viewer/2022041106/5f08f08a7e708231d424755d/html5/thumbnails/28.jpg)
Statement of Work for Engineering Services RFP No. 330237, Rev. 0
Project L-839, 12-in. Potable Water Loop-Line to WTP
Page 28 of 37
Updated January 9, 2018
Master Submittal Register:
The A/E shall meet the required schedule and provide the documents specified in accordance with the following submittals.
Subcontract Number: TBD Revision: 0
1. No.
2. No. of
Copies* (See End
Note)
3. Format
4. Type
5. Description / Document Title
6. Target
Submittal Dates (Work Days)
7. Buyer
Review Time
(Work
Days)
8. Subcontract
Paragraph or Requirement
Reference
1 1 PDF, MFC
AP Quality Assurance Program A + 4 4 SOW 7.3
2 1 P3, PDF,
MFC AP Design Schedule A + 8 4 SOW 10.2
3 1 PDF, MFC
AP Personnel Qualifications A + 8 4 SOW 8.1
4 1 PDF, MFC
AP Engineering Work Plan A + 8 6 SOW 6.6,
7.0
5 1 PDF, MFC
AP Commercial-off-the-Shelf Documentation A + 8 4 SOW 7.5
6 1 DWG, PDF,
MSC
APW Task 1 – 30% Design Package including native files
KO + 24 10 SOW 3.1
7 1 MFC, PDF
AP Task 1 – 30% Design Requirements Compliance Matrix
KO + 24 4 SOW
App. B
8 1 DWG, PDF,
MFC
APW Task 2 – 60% Design Package including native files
30% + 28 12 SOW 3.2
9 1 MFC, PDF
AP Task 2 – 60% Design Requirements Compliance Matrix
30% + 28 4 SOW 3.2
![Page 29: Statement of Work For Engineering Services...Statement of Work for Engineering Services RFP No. 330237, Rev. 0 Project L-839, 12-in. Potable Water Loop-Line to WTP Page 6 of 37 Updated](https://reader030.fdocuments.net/reader030/viewer/2022041106/5f08f08a7e708231d424755d/html5/thumbnails/29.jpg)
Statement of Work for Engineering Services RFP No. 330237, Rev. 0
Project L-839, 12-in. Potable Water Loop-Line to WTP
Page 29 of 37
Updated January 9, 2018
Subcontract Number: TBD Revision: 0
1.
No.
2.
No. of Copies* (See End
Note)
3.
Format
4.
Type
5.
Description / Document Title
6.
Target Submittal Dates
(Work Days)
7.
Buyer Review Time
(Work Days)
8.
Subcontract Paragraph or Requirement
Reference
10 1 MFC,
PDF AP Task 2 – 60% WDOH Project Report 30% + 28 8 SOW 3.2
11 1 DWG, PDF, MFC
APW Task 3 – 90% Design Package including native
files 60% + 32 10 SOW 3.3
12 1 MFC,
PDF AP
Task 3 – 90% Design Requirements Compliance
Matrix 60% + 32 4 SOW 3.3
13 1 MFC, PDF
AP Task 3 – 90% WDOH Revised Project Report 60% + 32 8 SOW 3.3
14 1
DWG,
PDF, MFC
APW Task 4 – 100 % Final Design Package including native files
90% + 24 8 SOW 3.4
15 1 MFC, PDF
APW Task 4 – Construction Submittal Register 90% + 24 8 SOW 3.4
16 1 MFC,
PDF AP Task 4 – Final Stamped WDOH Project Report 90% + 24 4 SOW 3.4
17 1 MFC, PDF
AP Task 4 – Design Verification Documentation 90% + 24 4 SOW 6.6
![Page 30: Statement of Work For Engineering Services...Statement of Work for Engineering Services RFP No. 330237, Rev. 0 Project L-839, 12-in. Potable Water Loop-Line to WTP Page 6 of 37 Updated](https://reader030.fdocuments.net/reader030/viewer/2022041106/5f08f08a7e708231d424755d/html5/thumbnails/30.jpg)
Statement of Work for Engineering Services RFP No. 330237, Rev. 0
Project L-839, 12-in. Potable Water Loop-Line to WTP
Page 30 of 37
Updated January 9, 2018
Bid Option
Subcontract Number: TBD Revision: 0
1. No.
2. No. of
Copies*
(See End Note)
3. Format
4. Type
5. Description / Document Title
6. Target
Submittal Dates
(Work Days)
7. Buyer Review
Time (Work
Days)
8. Subcontract
Paragraph or
Requirement Reference
18 1 MFC, PDF
AP Task 5 – EJTA** Bid Option Award + 8
4 SOW 7.2
19 1 MFC, PDF
AP Task 6 – Test Documentation, O&M Manuals **
Bid Option Award + 24
8 SOW 3.6
20 1 DWG, PDF, MFC
AP Task 7 – As-Built Drawings including native
files** CC + 21 12
SOW 3.7,
6.4, 6.7
* For electronic submittals, the number of hard copies can be negotiated with the Contract Specialist and approved by the
BTR.
** Submittals not required until Bid Option is authorized for the A/E to proceed.
![Page 31: Statement of Work For Engineering Services...Statement of Work for Engineering Services RFP No. 330237, Rev. 0 Project L-839, 12-in. Potable Water Loop-Line to WTP Page 6 of 37 Updated](https://reader030.fdocuments.net/reader030/viewer/2022041106/5f08f08a7e708231d424755d/html5/thumbnails/31.jpg)
Statement of Work for Engineering Services RFP No. 330237, Rev. 0
Project L-839, 12-in. Potable Water Loop-Line to WTP
Page 31 of 37
Updated January 9, 2018
APPENDIX B - 30/60/90 DESIGN DELIVERABLES
General Expectations
30% Design Package – The A/E shall demonstrate their understanding of the FRDC and overall
objective of the project. The design documentation shall include the level of information required for MSA to evaluate whether the design is meeting project expectations, if a course correction may be required, or if the project requirements need re-evaluated. The documentation shall also demonstrate what additional information (drawings/documents)
will be required to complete the design and what MSA can expect to see in future design packages.
60% Design Package – MSA expects the 60% design package to be “biddable” and “buildable.” This means the package contains a sufficient amount of detail for a construction
subcontractor to estimate and bid the project, and build the project in the field. The 60% package should include, at minimum, a draft of each drawing sheet, specification, or calculation in a form that allows reviewers to understand how the design meets the FRDC and overall project intent. If certain details or information is omitted, a placeholder and
explanation shall be included.
90% Design Package – As stated in Section 6.6, MSA expects the 90% design package to be fully checked and ready for final issue/release and/or construction. In addition to technical adequacy, checking shall address drafting standard compliance, editorial errors,
and overall workmanship.
100% Design Package – MSA should not see any new information in the 100% design package. This deliverable shall incorporate any final comments submitted during the 90% review and be fully ready for issue and release including PE stamps as required.
General Order of Drawings:
1. Cover Sheet / Title Sheet 2. Plans / P&IDs / Electrical One-Line (high level view) 3. Elevations / Plan and Profile
4. Sections 5. Details 6. Schedules / Panel Schedules
NOTE: The below table represents the minimum expected deliverables to be included with each of the 30%, 60% and 90% design packages. The list may not be an all-inclusive list, as the design progresses additional deliverables may be identified by the project team and/or A/E.
![Page 32: Statement of Work For Engineering Services...Statement of Work for Engineering Services RFP No. 330237, Rev. 0 Project L-839, 12-in. Potable Water Loop-Line to WTP Page 6 of 37 Updated](https://reader030.fdocuments.net/reader030/viewer/2022041106/5f08f08a7e708231d424755d/html5/thumbnails/32.jpg)
Statement of Work for Engineering Services RFP No. 330237, Rev. 0
Project L-839, 12-in. Potable Water Loop-Line to WTP
Page 32 of 37
Updated January 9, 2018
30 60 90 Description of Deliverable
DRAWINGS
Drawing Lists, Design Package Cover Sheets and Title Sheets Complete List of Drawings for Final Package – The list of drawings,
specifications, calculations, etc. provided with the 30% design package will be used to obtain H-series drawing numbers, calculation and specification document numbers from the Hanford Document Numbering System
(HDNS). The numbers obtained through HDNS post-30% shall appear on the 60% design package.
Existing Drawings – 30% identify list of drawings to be modified and provide FMP drawings for drafting approach.
New Drawings – Existing drawings will be released using the FMP process. New drawings will be issued with a DCN. New and existing drawings shall appear in a format that will support the design package that will
issue/release them (e.g. Existing drawings may use the WAS/IS format with the typical FMP border, while new drawings will appear as full size sheets with the standard drawing border in accordance with HNF-14660). (See Section 6.4, MSC-PRO-ENG-2001 for FMPs and
MSC-PRO-ENG-8016 for DCNs).
FMP EP Information – MSA will initiate the EP and route the package for approval, but will require information from the A/E to complete the electronic form (see MSC-PRO-ENG-440 for information required for the EP).
DCN Cover Sheets – Current revision of Form A-6003-324 filled out completely and accurately. Form instructions are available.
Title Sheet / Drawing Index / General Notes and Legend
Civil Civil General Notes, Legend, Abbreviations, and List of Civil Drawings
Civil Site Plan – including project boundary, call-outs for alignments, references to plan / profile drawing sheets, etc.
Enlarged Site Plan as needed
Plan / Profiles – Including any utilities (new and existing), invert elevations, profile slopes, grade (existing / proposed), separation distances, minimum cover requirements, pipe fittings and structures, stationing, bollards,
signage, etc.
Civil Details – Including schedules, cross sections, bollards, fire hydrant, signage, thrust blocks, etc.
Electrical Electrical General Notes, Legend, Abbreviations, List of Electrical Drawings
One-Line Diagram(s)
![Page 33: Statement of Work For Engineering Services...Statement of Work for Engineering Services RFP No. 330237, Rev. 0 Project L-839, 12-in. Potable Water Loop-Line to WTP Page 6 of 37 Updated](https://reader030.fdocuments.net/reader030/viewer/2022041106/5f08f08a7e708231d424755d/html5/thumbnails/33.jpg)
Statement of Work for Engineering Services RFP No. 330237, Rev. 0
Project L-839, 12-in. Potable Water Loop-Line to WTP
Page 33 of 37
Updated January 9, 2018
30 60 90 Description of Deliverable List Identifying Major Electrical Equipment / Components
Equipment Schedule – Incorporate 30% Electrical Equipment/Component
Electrical Equipment Label Schedule – Ref. EU-PRO-ENG-60779, Rev 1 Change 3, Equipment and Component Labeling
Conduit and Wire Schedule(s) – Include conduit fill.
Conduit Routing
Panel Schedule(s) – Including three-phase balance calculations.
IT / Telecommunications IT / Telecommunication General Notes, Legend and Abbreviations, List of IT
Drawings
Telecommunications Plan
Initial Telecommunication Equipment Schedule
Final Telecommunication Equipment Schedule
Drafting Preliminary Drafting Review – Provide at least one AutoCAD file per
discipline for review by MSA CAD organization for compliance with HNF-14660.
Detailed Drafting Review
Long Lead Procurement Items Identify Long Lead Procurement Items
Identify Major Pieces of Equipment
SPECIFICATIONS Draft Construction Specification – Construction specification shall follow the
CSI format. The 30% submittal shall be a fully annotated outline including as much standard information as available such as: applicable codes and standards, submittals, industry standard quality requirements, industry
standard testing and inspection requirements and other “boilerplate” information.
Construction Specification – The 60% construction specification should appear close to the final product. The 60% submittal will be reviewed for completeness and project-specific requirements and information.
Identify List of Procurement Specifications
Initial Draft of Long Lead Item Procurement Specification
Final Procurement Specification for Long Lead Procurement Items
![Page 34: Statement of Work For Engineering Services...Statement of Work for Engineering Services RFP No. 330237, Rev. 0 Project L-839, 12-in. Potable Water Loop-Line to WTP Page 6 of 37 Updated](https://reader030.fdocuments.net/reader030/viewer/2022041106/5f08f08a7e708231d424755d/html5/thumbnails/34.jpg)
Statement of Work for Engineering Services RFP No. 330237, Rev. 0
Project L-839, 12-in. Potable Water Loop-Line to WTP
Page 34 of 37
Updated January 9, 2018
30 60 90 Description of Deliverable Master Submittal Register for Construction – A submittal register in the
standard MSA format to be included in the construction SOW that is fully aligned with the final project construction specification.
CALCULATIONS Identify List of Calculations(s) (e.g. arc flash, electrical load, thrust block, pipe
supports, fire alarm battery and voltage drop, lighting level,
heating/cooling loads, heat dissipation, etc.)
Lightning Protection Risk Assessment in accordance with NFPA 780
Perform Calculation(s)
Draft Hydraulic Analysis
Final Hydraulic Analysis
Calculation Checklists – Submit Calculation Checklist Form A-6007-113 required to accompany each calculation for release. (See Section 6.4 and
MSC-PRO-ENG-8259 for more information)
TESTING DOCUMENTATION Test Plan Annotated Outline
Test Plan
Draft Test Procedure(s)
Draft Test Report
OTHER Design Requirements Compliance Matrix – Matrix of project design
requirements, which may come from a number of sources, such as: FRDC, specifications, codes, standards, environmental permits, etc. The matrix shall include, at a minimum, identification of each requirement, source of
the requirement, methodology used to verify the requirement (inspection, test, calculation, drawing, etc.), and ensure acceptance criteria has been established.
WDOH Project Report – To be developed and submitted to MSA in accordance with WAC 246-290-110. The final WDOH document will
require a PE stamp/signature.
NATIVE FILES Native Drawing Files –30/60
Native Drawing Files –90
Other Native Files - Native files for Word documents (.doc, .docx), excel (.xls, .xlsx), MathCAD, and any other native files. Native files (especially Word
files) assist MSA in the review process by allowing reviewers to provide tracked changes type comments.
![Page 35: Statement of Work For Engineering Services...Statement of Work for Engineering Services RFP No. 330237, Rev. 0 Project L-839, 12-in. Potable Water Loop-Line to WTP Page 6 of 37 Updated](https://reader030.fdocuments.net/reader030/viewer/2022041106/5f08f08a7e708231d424755d/html5/thumbnails/35.jpg)
Statement of Work for Engineering Services RFP No. 330237, Rev. 0
Project L-839, 12-in. Potable Water Loop-Line to WTP
Page 35 of 37
Updated January 9, 2018
APPENDIX C – DRAWING AND/OR DOCUMENT LIST
Existing Essential Drawings
Drawing No. Sht. Rev. Description Rel. Date
1. H-2-830460 001 02 Site Map Potable Water System 200 East Area Key Map 02/22/2018
2. H-2-830460 013 23 Site Map Potable Water System 200 East Enlarged Plan 06/03/2019
3. H-2-830460 014 04 Site Map Potable Water System 200 East Enlarged Plan 12/27/2016
4. H-2-830460 015 03 Site Map Potable Water System 200 East Enlarged Plan 05/06/2015
Existing Reference Drawings
Drawing No. Sht. Rev. Description Rel. Date
1. H-2-834005 001 01 Civil Site Plan & Drawing List 03/21/2011
2. H-2-834130 002 02 Civil Utility Plan 01/8/2015
3. H-2-834130 004 02 Civil Utility Plan 01/8/2015
![Page 36: Statement of Work For Engineering Services...Statement of Work for Engineering Services RFP No. 330237, Rev. 0 Project L-839, 12-in. Potable Water Loop-Line to WTP Page 6 of 37 Updated](https://reader030.fdocuments.net/reader030/viewer/2022041106/5f08f08a7e708231d424755d/html5/thumbnails/36.jpg)
Statement of Work for Engineering Services RFP No. 330237, Rev. 0
Project L-839, 12-in. Potable Water Loop-Line to WTP
Page 36 of 37
Updated January 9, 2018
Other
Document Number Rev. Description Rel. Date
1. HNF-FRDC-62970 00 Functional Requirements and Design Criteria, 12-in. Potable Water Loop-Line to WTP
05/2/2019
NOTE: This is not an all-inclusive list, there may be additional drawings and documents identified as the design progresses.
![Page 37: Statement of Work For Engineering Services...Statement of Work for Engineering Services RFP No. 330237, Rev. 0 Project L-839, 12-in. Potable Water Loop-Line to WTP Page 6 of 37 Updated](https://reader030.fdocuments.net/reader030/viewer/2022041106/5f08f08a7e708231d424755d/html5/thumbnails/37.jpg)
Statement of Work for Engineering Services RFP No. 330237, Rev. 0
Project L-839, 12-in. Potable Water Loop-Line to WTP
Page 37 of 37
Updated January 9, 2018
APPENDIX D – PRECONCEPTUAL LINE ROUTING