State Renewable Energy Action Plan for Assam · State Renewable Energy Action Plan for Assam 5 2...
Transcript of State Renewable Energy Action Plan for Assam · State Renewable Energy Action Plan for Assam 5 2...
State Renewable Energy Action Plan for
Assam
Final Report
2017
State Renewable Energy Action Plan for Assam
1
TABLE OF CONTENTS
1 BACKGROUND .......................................................................................................................................... 3
1.1 TERMS OF REFERENCE .................................................................................................................................... 3 1.2 STRUCTURE OF THE REPORT ............................................................................................................................. 3
2 INTRODUCTION ......................................................................................................................................... 5
2.1 POWER SECTOR OVERVIEW ............................................................................................................................. 5 2.2 RENEWABLE ENERGY OVERVIEW ...................................................................................................................... 6
3 ENERGY OUTLOOK - ASSAM .................................................................................................................... 13
3.1 ENERGY OUTLOOK OF ASSAM ........................................................................................................................ 13 3.2 INSTITUTIONAL FRAMEWORK ......................................................................................................................... 15 3.3 RENEWABLE ENERGY IN ASSAM...................................................................................................................... 15
4 EXISTING RE PROMOTION FRAMEWORK - ASSAM .................................................................................. 17
4.1 POLICY FRAMEWORK FOR PROMOTION OF RE IN ASSAM ..................................................................................... 17 4.2 REGULATORY FRAMEWORK FOR PROMOTION OF RE IN ASSAM............................................................................. 18
5 GAP ANALYSIS ......................................................................................................................................... 23
6 RE TARGETS FOR ASSAM ......................................................................................................................... 22
6.1 RE TARGETS OF ASSAM AS PER MNRE FOR 2022 ............................................................................................. 22 6.2 RE TARGETS OF ASSAM FOR 2030 .................................................................................................................. 23
7 STATE RENEWABLE ENERGY ACTION PLAN ............................................................................................. 25
7.1 INTERVENTIONS REQUIRED AT STATE LEVEL....................................................................................................... 25 7.2 INTERVENTIONS REQUIRED AT NATIONAL LEVEL ................................................................................................. 29
8 ANNEXURE 1: NATIONAL LEVEL RE TARGETS........................................................................................... 32
9 REFERENCES ............................................................................................................................................ 36
List of Figures
Figure 1 : Power Installed Capacity Mix .................................................................................................................. 5 Figure 2 : Per capita electricity consumption trend ............................................................................................... 5 Figure 3 : RE Capacity addition trend ..................................................................................................................... 6 Figure 4: Policy & Regulatory framework for RE .................................................................................................... 7 Figure 5 : Solar Potential ......................................................................................................................................... 9 Figure 6 : State wise rooftop solar targets - 2022 ................................................................................................ 10 Figure 7: Wind Energy Potential of India .............................................................................................................. 11 Figure 8: Annual wind energy capacity addition targets ...................................................................................... 11 Figure 9 : SHP Capacity addition trend ................................................................................................................. 12 Figure 5: Assam Installed Capacity Mix (%) .......................................................................................................... 13 Figure 6 : Assam Energy Supply Scenario ............................................................................................................. 13 Figure 7: Institutional framework of Assam ......................................................................................................... 15 Figure 8: Growth of RE in Assam (MW) ................................................................................................................ 15 Figure 9: Regulatory framework for promotion of RE in Assam ........................................................................... 18 Figure 10: RPO Compliance by APDCL .................................................................................................................. 19 Figure 11: Summary of Gaps ................................................................................................................................. 24 Figure 12 : RE Targets for Assam as per MNRE ..................................................................................................... 22 Figure 13: Assam RPO target under different scenarios....................................................................................... 22
State Renewable Energy Action Plan for Assam
2
Figure 14: Pillars of RE State Action Plan .............................................................................................................. 25 Figure 15: Regional balancing capacity required by FY 2022 ....................................................... 29 Figure 16 : Solar Potential..................................................................................................................................... 32 Figure 17 : State wise rooftop solar targets - 2022 .............................................................................................. 33 Figure 18: Wind Energy Potential of India ............................................................................................................ 34 Figure 19: Annual wind energy capacity addition targets .................................................................................... 34 Figure 20 : SHP Capacity addition trend ............................................................................................................... 35
List of Tables
Table 1: Achievement status of RE projects ........................................................................................................... 7 Table 2: Yearly target for achieving 100 GW of PV installation by 2022 ................................................................ 9 Table 2: RE Planning of Assam .............................................................................................................................. 16 Table 3: Salient features of Assam SHP policy, 2007 ............................................................................................ 17 Table 4: RPO target of Assam (%) ......................................................................................................................... 19 Table 5: Revised RPO target by AERC ................................................................................................................... 19 Table 6: Salient features of AERC RE tariff Regulations, 2012 .............................................................................. 20 Table 7: Salient features of AERC (Co-generation and Generation of Electricity from Renewable Sources of
Energy) Regulations, 2015 .................................................................................................................................... 20 Table 8: Gap Analysis ............................................................................................................................................ 23 Table 9: CEA Projections on Electricity Generation (BU) – National level ............................................................ 24 Table 10: National RPO for 2030 (%) .................................................................................................................... 24 Table 11: RPO target for Assam ............................................................................................................................ 24 Table 12: Yearly target for achieving 100 GW of PV installation by 2022 ............................................................ 32
State Renewable Energy Action Plan for Assam
3
1 Background
In recent years, the Indian Renewable Energy (RE) sector has witnessed high grow rate – driven by the
Government of India (GOI) commitment to increase RE capacity to 175 GW in 2022 and the assurance to increase
the proportion of non-fossil fuel in India’s fuel mix to 40 percent by 2030 (as part of India’s NDCs target). In view
of this, a number of policies & regulatory initiatives for promotion of RE have been undertaken and in response,
the RE sector has grown rapidly in last five year.
To achieve the target in set timeframe, there is an urgent need to review various issues that are impacting the
achievement of RE capacity addition target. RE potential is highly location specific and variability in power
generation increases the complexity in its operation. Hence, it is necessary to examine all the associated
challenges, including high RE variability issues. It is important that the issues are analysed from State perspective
and initiatives taken at early stage to address them.
In November 2013, the NITI Aayog, erstwhile Planning Commission of India, initiated a stakeholder-driven
analysis to identify the opportunities and barriers to rapid deployment of RE in India. The study concluded that
India needs new policies, program and operational rules to enable power flows from point of generation to load
centers; ensure fair compensation to generators; and offer reliability to consumers at affordable price.
The target of 175 GW by 2022 set by the Government of India can be achieved by harnessing the potential in RE
rich states, while states with limited potential act as support centers such that costs and benefits of
implementing RE are distributed equally among all states.
The CII and Shakti Sustainable Energy Foundation are assisting NITI Aayog towards implementation of the
recommendations of the Roadmap Report and enabling the country to achieve the national target of 2022 and
the NDCs target of 2030. NITI Aayog has constituted an implementation assembly, a two-tier structure consisting
of an Advisory Group (AG) and a Steering Committee (SC). The AG would be chaired by the Vice Chairman of the
NITI Aayog with state energy ministers and Minister of Power as its members, while the SC would be chaired by
CEO NITI Aayog, with state energy secretaries as its members.
This study is aimed to assist State Government in preparation of a State level Action plan for Renewable energy.
The action plan shall enable the state achieving the targets and supporting national target of RE capacity addition
by 2022 and the NDCs target of 2030.
1.1 Terms of Reference
The objective of this study is to prepare a State Renewable Energy capacity addition roadmap—an action plan
for 2022. The action plan to meet the 2022 target must clearly identify and suggest the potential actions agenda,
incentives, regulatory and policy framework, institutional framework (indicating the role of different
stakeholders), intra states evacuation infrastructure and balancing requirements to be undertaken by the
identified state to meet the target capacity.
1.2 Structure of the report
This report highlights key challenges in the area of policy & regulatory, program management, institutional
capacity, grid integration, market interventions etc. that, Assam is likely to face, in achieving RE capacity addition
target. Under this study a detail review of state’s power sector, RPO compliance, renewable energy policy and
regulatory framework has been undertaken. Based on this analysis, required interventions at National & State
level, are proposed as a part of the RE action plan.
The second chapter provides an overview of the power as well as renewable energy sector in India. The third
chapter of this report provides the overview of the Assam power sector detailing existing institutional
framework, conventional & renewable generation capacity, transmission planning for RE evacuation, RE
programs undertaken by state agencies.
State Renewable Energy Action Plan for Assam
4
In fourth chapter, details of existing renewable energy policies, regulatory framework to promote renewable
energy in the state has been covered. Detailed gaps in policy, regulatory, grid integration, institutional capacity
and funding areas have been identified in fifth chapter.
The sixth chapter provides details of RPO targets for different demand scenarios for year 2022. The RE targets
are identified for the State of Assam for year 2022 and year 2030. Based on the analysis across different chapters,
chapter seven provides key actionable points, interventions required to achieve the target capacity addition.
State Renewable Energy Action Plan for Assam
5
2 Introduction
2.1 Power Sector Overview
With a GDP growth of 7.1%1 per annum, India is one of the fastest growing economies in the world. India relies
heavily on conventional fuels to meet the energy demand. Out of the total installed capacity of 326 GW2, the
share of coal, gas and diesel power projects is close to 67% in the overall capacity mix, while the share of
renewable energy in the overall capacity mix is 18% (~ 57 GW) as of March 2017.
Figure 1 : Power Installed Capacity Mix
Source: CEA (as on 31.03.2017)
Ensuring adequate availability of energy is a crucial requirement for sustaining economic growth. There have
been significant investments in power generation in the last few years, which resulted in reducing the energy
and power demand deficit. In March 2017, country witnessed energy deficit of 0.3% and power demand deficit
of 0.5%3. The per-capita electricity consumption has also increased steadily over the years. The figure below
indicates the increase in country level per-capita electricity consumption.
Figure 2 : Per capita electricity consumption trend
1 GDP Forecast FY 2017, RBI - Dec 2016
2 http://cea.nic.in/reports/monthly/executivesummary/2016
3 http://cea.nic.in/reports/monthly/executivesummary/2017/March
14%
59%
8%
0.26% 2%
18%
0%
10%
20%
30%
40%
50%
60%
70%
-
50,000
1,00,000
1,50,000
2,00,000
2,50,000
Hydro Coal Gas Diesel Nuclear RES
% o
f Tota
l In
sta
lled
Genera
tion C
apacity (
MW
)
Source Type
Generation Capacity % of Total Installed Capacity
465559
672
884 914 9571010
1075
0
200
400
600
800
1000
1200
CO
NSU
MPTIO
N (
KW
H)
State Renewable Energy Action Plan for Assam
6
Both energy requirement and energy availability are increasing with time but India’s per capita consumption is
low, compared to world average. In view of the growing need of the Indian economy, the Government has
embarked upon a massive programme to provide 24x7 power across the country by 2019. Providing 24x7 power
also means lot of other innovative steps. Conscious of this fact, several landmark decisions have already been
taken in thermal power generation, hydel and more importantly in solar, wind and other green energy, besides
strengthening of transmission and distribution, separation of feeder and metering of power to consumers.
In the reform and restructuring front, various amendments are being brought in the Electricity Act and Tariff
policy. Comprehensive State-specific action plans for 24x7 power to all homes are being prepared in partnership
with respective states, encompassing generation, transmission and distribution. The Power Ministry has already
signed a memorandum of understanding with various State Governments under its 'Power for all' initiative that
aims to cover the entire country4. Out of the 18,452 un-electrified villages in April 2015, the Govt. has already
electrified 13,469 villages. Electrification of around 3,856 villages in under progress.
2.2 Renewable Energy Overview
With energy security and climate change concerns taking center stage in the policy arena, Renewable Energy
(RE) has become an important part of the energy sector initiatives in India. To this effect the government has
set aggressive targets and has put in place several incentives and policy initiatives (for both grid connected and
off-grid).
The installed capacity mix for electricity generation has undergone significant change in recent years, with the
share of RE capacity reaching 18% by March 2017. Growth of renewable energy across different technologies is
given in the figure below:
Figure 3 : RE Capacity addition trend
Source: CEA/MNRE
It can be observed that growth of renewable energy technologies has been exponential mainly led by two
technologies viz solar and wind power. Wind energy continues to be having highest capacity installation within
RE sources.
4 Source: PIB
0
10000
20000
30000
40000
50000
60000
FY 02 FY 03 FY 04 FY 05 FY 06 FY 07 FY 08 FY 09 FY 10 FY 11 FY 12 FY 13 FY 14 FY 15 FY 16 FY 17
Insta
lled C
apacity (
MW
)
Year
Wind Solar Bio- Mass WTE SHP
State Renewable Energy Action Plan for Assam
7
The current progress as mentioned of these targets are as below:
Table 1: Achievement status of RE projects
Source: MNRE
The Govt. of India targets for achieving 175 GW by year 2022. The target comprises of 100 GW of solar power,
60 GW of wind power, 10 GW of biomass power, and 5 GW of small hydro power (SHP). The past three years
have seen exponential growth and paradigm shift in India's renewable energy sector. At the same time one is
also witnessing substantial decline in the price of procurement of solar and wind power. Each and every segment
of renewable energy i.e. solar, wind, biomass, hydropower, biomass, waste to energy are being harnessed to
their full potential as the government aims to fulfil its objective of providing 24x7 power to all households by
2022.
The growth of 91.57% has been achieved with capacity addition of 22.5 GW grid renewable power during last
three years (2014-15 to 2016-17), as compared to 11.7 GW installations during preceding three years (2011-12
to 2013-14)5.
2.2.1 Key Drivers for RE
It is well recognized globally that early commercialization of RE technologies is highly dependent on support
from the government through a mix of policy and regulatory instruments. Over the years, the Government of
India has introduced a number of policy and regulatory initiatives for promoting RE. Some of the key initiatives
have been illustrated in the figure below:
Figure 4: Policy & Regulatory framework for RE
Year Instrument/ Initiative Key Features
1982 Creation of Department of
Non-conventional Energy
Sources
An independent department for development, demonstration
and application of RE. RE sources were recognized as potential
alternative energy sources and received special consideration.
1992 Creation of MNRE The Department of Non-Conventional energy Sources was
upgraded into a full-fledged ministry.
1993 MNRE Policy and Tariff
Guidelines
Introduction of RE tariff guidelines by MNRE - states to purchase
RE power at Rs 2.25/kWh with 5% annual escalation on 1993 as
base year. Introduction of Tariff guidelines offered relatively
higher price for RE than what was prevailing, and thus triggered
development of RE sector, especially wind.
5 Source : MNRE
Sr. No. RE technology Cumulative Achievement in MW
(as on 31.03.2017)
1 Grid Interactive Solar Power 12,288
2 Grid Interactive Wind Power 32,279
3 Bio Power 8,181
4 Waste to Power 114
5 Small Hydro Power 4,379
Total 57,244
State Renewable Energy Action Plan for Assam
8
1993-94 Introduction of Accelerated
Depreciation
Introduction of Accelerated Depreciation (100% AD) for
promotion of wind projects (altered to 80% AD in 1999). This
program led to the successful commercial development by
involving the private sector in wind equipment manufacturing as
well as its application.
2002-03 Electricity Act 2003 Recognizes the role of RE for supplying power to the utility grid
as well as in standalone systems. Provides an overall framework
for preferential tariff and quotas for RE.
2004
onwards
Preferential Tariffs for RE
from SERCs
Following the enactment of the EA-2003, states adopted
preferential tariff mechanisms to promote RE. Since it provides
differential tariffs for the development of different RETs, it
brought in a balanced approach to RE development across
states.
2005-06 National Tariff Policy Directed SERCs to fix a minimum percentage of purchase of
energy consumption from RE sources (RPO). This created a
demand side stimulus for RE development.
2005-06 Integrated Energy Policy
Report 2006
Suggested a path to meet energy needs in an integrated manner.
Recommended special focus on RE development and set specific
targets for capacity addition through RE sources.
2008-09 Introduction of Generation
Based Incentives (GBI) for
solar and wind energy
This scheme offers fiscal incentives along with tariff on power
generation from solar and wind. It shifted investment interest
from installation to generation.
2008 National Action Plan on
Climate Change (NAPCC)
NAPCC has advised that starting 2009-10, RPO’s be set at 5% of
total grids purchase, and be increased by 1% each year for 10
years.
2010 Jawaharlal Nehru National
Solar Mission (JNNSM)
Targets 20,000 MW of grid-connected solar power capacity and
2,000 MW of off-grid solar power capacity by 2022.
2010 REC regulation Introduction of REC mechanism in which sale and purchase of
solar and non-solar renewable energy certificates can be traded
in an open market for meeting the RPO (renewable purchase
obligations) by designated entities.
2015 Revision of National RE
capacity addition targets till
FY 2022
India’s RE target revised to 175 GW capacity by year 2022
2016 Amendment to National
Electricity Tariff Policy, 2016 • National electricity tariff policy 2016 mandates
solar RPO targets of 8% (excluding hydro power)
• Renewable Generation Obligation on conventional
power projects
• No inter-state transmission charges for wind &
solar power.
Source: MNRE & secondary research
State Renewable Energy Action Plan for Assam
9
2.2.2 Solar Energy
India is endowed with vast solar energy potential. About 5,000
trillion kWh per year energy is incident over India land area with
most parts receiving 4-7 kWh per sq. m per day.
According to National Institute of Solar Energy (NISE), country is
having solar energy potential of around 750 GW. India is a tropical
nation and receives solar energy around 300 days in a year.
Solar power target capacity of 100 GW by 2022 has been divided
into two main parts - with 40 GW for rooftop and 60 GW of ground
mounted PV projects.
The year wise targets are as follows:
Table 2: Yearly target for achieving 100 GW of PV installation by 2022
Source: MNRE *3743 MW Commissioned up to 2014-15
1. Solar Parks
Solar parks have emerged as a preferred option to add large scale solar capacity in the country. The scheme for
“Development of Solar Parks and Ultra Mega Solar Power Projects” was rolled out by Ministry of New &
Renewable Energy on 12-12-2014. This scheme envisaged supporting the States in setting up solar parks at
various locations in the country with a view to create required infrastructure for setting up of Solar Power
Projects. The solar parks provides suitable developed land with all clearances, transmission system, water
access, road connectivity, communication network, etc. This scheme aimed to facilitate and speed up installation
of grid connected solar power projects for electricity generation on a large scale.
Approvals have been accorded to 34 Solar Parks of aggregate capacity of 20,000 MW to be set up in 21
States. After the success of solar park framework, the MNRE has now increased the capacity to be installed under
scheme for “Development of Solar Parks and Ultra Mega Solar Power Projects” from 20,000 MW to 40,000 in
year 2017. These solar parks would be set up by year 2019-20, with an estimated Central Financial Assistance
(CFA) of Rs 8100 crores.
2. Solar Rooftops
The unutilized space on rooftops provides a large potential for generating solar power. Small quantities of power
generated by each individual household, industrial building, commercial buildings or any other type of building
Year Target
(Ground Mounted)
Target (Rooftop) Total
2015-16 1800 200 2000
2016-17 7200 4800 12000
2017-18 10000 5000 15000
2018-19 10000 6000 16000
2019-20 10000 7000 17000
2020-21 9500 8000 17500
2021-22 8500 9000 17500
Total 47000 40000 97000*
(~100 GW including 3743
Commissioned up to 2014-15)
Figure 5 : Solar Potential
State Renewable Energy Action Plan for Assam
10
can be used to fully / partially fulfil the requirement of the building occupants and surplus, if any, can be fed into
the grid.
Rooftop solar PV systems have the advantage of low installation time, providing clean source of energy. They
can also improve the reliability of power supply for rooftop owners, eliminate the need for long-distance
transmission lines associated with large-scale solar generation plants and save on network losses associated
with large-scale plants wheeling power to load centers.
The solar rooftop is highly attractive
segment and Govt. of India has set an
overall target of 40 GW by 2022. The
MNRE is providing upto 30 percent
support for capital subsidy support to
the residential and institutions (college,
hospital etc.) under the ongoing Central
Financial Assistance (CFA) program.
In order to promote solar roof top,
IREDA also has dedicated financing
scheme for solar rooftop projects for
industrial, commercial and institutional
consumers. The figure details the targets
allocated to different States by MNRE to
achieve 40 GW rooftop capacity by
2022.
2.2.3 Wind Energy
India is blessed with high wind potential
in most parts of the country. As per
National Institute of Wind Energy, wind energy potential in the country is 302 GW.
In terms of potential, Gujarat has the maximum wind energy potential of 84 GW followed by Karnataka (55 GW),
Maharashtra (45GW), Andhra Pradesh (44 GW) and Tamil Nadu (33 GW). In addition to these State, Rajasthan
(18GW) and Madhya Pradesh (10 GW) also has high wind potential sites.
In the recent years, majority of the wind installations have happened in the states of Rajasthan, Madhya Pradesh,
Maharashtra and Andhra Pradesh by large IPPs.
Figure 6 : State wise rooftop solar targets - 2022
State Renewable Energy Action Plan for Assam
11
Out of the 302 GW of wind potential, India
as of now have been able to achieve ~32.2
GW (by March 2017). This is largely due to
concertation of wind potential in few
states. The state like Andhra Pradesh,
Gujarat, Karnataka, Maharashtra, Tamil
Nadu, Rajasthan etc. accounts for more
than 85% of the overall potential of the
country.
The Government of India has set a target
of achieving 60 GW of installed wind
energy capacity by 2022. In order to
achieve this target, both Central and State
government are working together and
providing various support in terms of
conducive policy framework,
identification of land banks, providing
incentives etc. The following figure shows
the roadmap of Government of India to
reach 60 GW target
Figure 8: Annual wind energy capacity addition targets
Source: Ministry of New and Renewable Energy
In addition to the 60 GW target for standalone wind projects, the country is also aiming to exploit the potential
through Wind-solar Hybrid policy with the help of hybrid projects. Under the recently notified policy, the
Ministry of New and Renewable energy envisages to achieve the target of 10 GW of solar wind hybrid energy by
2022.
2.2.4 Biomass
Biomass is one of the dominant sources of energy in India with a large population relying on biomass to meet
their primary energy need. As per MNRE’s estimates, the availability of biomass in India is estimated at about
500 million metric tons per year, out of which surplus biomass availability at about 120 – 150 million metric tons
per annum covering agricultural and forestry residues. Based on this availability, the assessed potential for
biomass based generation capacity is 18 GW. In addition, the power generation potential from the bagasse
based projects is around 7 GW.
Figure 7: Wind Energy Potential of India
State Renewable Energy Action Plan for Assam
12
The biomass power sector has experienced a gradual growth in the capacity additions with installed capacity
increasing from 3,135 MW in 2011-12 to 4,831 MW in 2015-16. Cumulative annual growth rate of capacity
addition during this period is around 11 percent.
2.2.5 Small Hydro
In India, hydro projects up to 25 MW station capacities have been categorized as Small Hydro Power (SHP)
projects. While Ministry of Power, Government of India is responsible for development of large hydro projects,
the mandate for the subject small hydro power (up to 25 MW) is given to Ministry of New and Renewable Energy
(MNRE).
India has potential of generating more than 19 GW of small hydro power (upto 25 MW). Out of the 19 GW
potential of SHP, States of Karnataka, Himachal Pradesh, Uttarakhand, and North East constitute 50% of this
potential.
The growth trend of SHP in India is shown in the figure below.
By March, 2017 India’s total installed capacity in Small Hydro Power has reached 4,379 MW. The State of
Karnataka has the highest capacity of SHP with 1,177 MW, Himachal Pradesh 754 MW. Since 2010, SHP capacity
in India has grown at a rate of 8% annually and contributes to approximately 7% of the installed renewable
energy capacity of India (In March 2017).
Figure 9 : SHP Capacity addition trend
State Renewable Energy Action Plan for Assam
13
3 Energy Outlook - Assam
3.1 Energy Outlook of Assam
Assam is one of the seven states in the North Eastern
Region (NER) of India, surrounded by six sister states of
the NER and shares international boundaries with
Bhutan and Bangladesh. The State connects the NER to
the rest of the country through the Chicken Neck – A
narrow corridor of land surrounded by Bhutan on North
and Bangladesh on the south.
As per 2011 census, the household (HH) level
electrification in Assam was 37% compared to national
average of 67.2%. Only 28% of the rural HHs in Assam
were having access to electricity in 2011. Recurring
floods, insurgency and inaccessible terrains have
created hurdles in electrification of HHs and associated
economic development in the State.
The poor level of electricity access is due to several
factors, including difficulties associated with large
sections of the HHs being located in the hilly districts that are not easily reachable. The areas in the Brahmaputra
basin such as Dhemaji are prone to floods resulting in several HHs frequently shifting from one place to another.
While districts like Kokrajhar, Chirang and Baksa have been subject to various forms of law and order related
disturbances.
The State is currently facing multiple issues, including the following most prominent ones – (i) delays in
commissioning of new thermal power plants in the State; and (ii) fuel shortages in gas-based plants. The power
shortage situation is further aggravated by constraints in the inter-regional transmission network.
In terms of the capacity mix, Assam has total installed capacity of 1446 MW. The share of conventional power
in the overall capacity mix is more than 65%, followed by hydropower that is ~30%. The share of renewables in
the installed capacity mix is ~ 3%.
The power supply position of the State is poor but improving. The state has power deficit of 3.9% i.e. 276 MUs
and peak demand deficit is 2.4% i.e. 40 MW for the period of April 2016 to Dec, 2016i.
Figure 11 : Assam Energy Supply Scenario
Source: CEA
As per Power for All report for Assam, the city of Guwahati has an average supply of 20 hours while other urban
& rural areas get an average supply of only up to about 15 hours & 12 hours respectively. Projected energy
requirement & peak power demand of Assam is expected to increase to 15 BUs, & 2,417 MW by FY19. The
Coal
13%
Gas
54%
Hydro
30%
RES
3%
Figure 10: Assam Installed Capacity Mix (%)
State Renewable Energy Action Plan for Assam
14
energy & peak power requirement of the State has grown at CAGR of 10% & 9% respectively. Based on the
consumption trend, energy requirement & peak power demand will grow to 11.7 BUs & 1,929 MW respectively
by FY 19.
The State has achieved 96.8% village level electrification by March, 2015. However, large section of the
population including 36.36 lakh rural HHs and 1.74 lakh urban HHs are still un-electrified.
The electrification plan is aimed towards achieving 100% electrification of rural HHs by FY22 and 100% urban HH
by FY19. In addition to grid extension, 75 villages are proposed to be electrified by solar PV under remote village
electrification programii.
APDCL serves electricity to over 33 Lakh consumers in the State (FY15). The domestic consumer category
comprises over 92% of APDCL’s consumer base and contributes to over 47% of its energy sales. Other categories
comprising over 2.8 lakh consumers contributes to around 53% of energy sales.
Commercial and Industrial categories have also seen robust growth over the last 5 years. It is reported that
APDCL has not been able to meet the power demand from industrial consumers in several regions during the
previous years due to various constraints.
While the tea estates form one of the most significant economic activities in the State, giving employment to
over 35 lakh people, the power supply to the estates has been significantly constrained due to network
inadequacies. Energy sales to tea estates has marginally declined over the period and consumers have been
forced to use alternate sources of power. It is reported that power supply deficit to tea estates ranges from 40%
to 50% across various regionsiii.
State Renewable Energy Action Plan for Assam
15
3.2 Institutional Framework
Since 2004, the Assam State Electricity Board has
undergone a process of unbundling to form into
following five entities to carry out functions of
generation, transmission and distribution of electricity.
1. Assam Power Generation Corporation Limited
(APGCL) (Generating Company)
2. Assam Electricity Grid Corporation Limited
(AEGCL) (Transmission Company)
3. Lower, Central and Upper Assam Distribution
Company Limited (Three Electricity
Distribution Companies)
Assam Electricity Regulatory Commission (AERC) is the
State regulatory Commission and was established on
August, 2001. AERC has been regulating the electricity
sector in the State in accordance with the provisions of
the Electricity Act 2003.
In July 2002, Assam Energy Development Energy
(AEDA) had been formed under the Societies
Registration Act (1860) to act independently as the
nodal agency for new and renewable sources of energy
under the Ministry of New & Renewable Energy, Govt.
of India for the state of Assam.
3.3 Renewable Energy in Assam
The total installed capacity as on Jan 2017 (including allocated share in Joint & Central Sector plants) was 1445.56
MW including 45 MW from renewable energy sources. Over the past five years, the growth of RE in the States
has been around 8%. Below graph is showing the growth of RE in the recent times
Figure 13: Growth of RE in Assam (MW)
Source: CEA
In terms of the potential, State has an overall RE potential of 45 GW, wherein the solar energy is maximum with
potential of over 13 GW i.e. 96%. State has decent potential for SHP, Bio-mass & Wind projects. To explore the
available potential of RE, APGCL, APDCL & AEDA has planned various renewable energy program in grid
connected & off-grid segment. MNRE has proposed RE capacity addition of 688 MW (663 MW solar & 25 MW
SHP) in the state by the year 2022.
Renewable energy planning of Assam is summarised in the below table
31 31 31 34 3445
FY 12 FY 13 FY 14 FY 15 FY 16 FY 17*
Figure 12: Institutional framework of Assam
State Renewable Energy Action Plan for Assam
16
Table 3: RE Planning of Assam
Agency Segment Target Budget
AEDA Grid Connected Solar Roof Top 117 MW -
Off-grid Solar Roof Top 18 MW -
Total 135 MW
APDCL Grid connected solar roof top on
government buildings, educational
institutions in rural and semi-urban
areas
1 MW 90% CFA from MNRE & 10% financial
assistance from GoA
Development of ground mounted
solar plant at an identified vacant
land with the support of state
government
25 MW Investment of Rs. 153 Crores from GoA
Grid connected solar power plant
through IPPs
80 MW By IPPS
Grid connected solar power plant
under the Viability Gap Funding (VGF)
mechanism of MNRE
50 MW (40 MW Open
Category and 10 MW
under DCR)
Proposed VGF Open Category 40 CR &
DCR 13.1 Cr.
APDCL Installation of off-grid standalone
solar street lighting system
2,500 Nos. GoA funding support of 22.5 Cr
Promotion of solar wind hybrid
systems
0.9275 MW GoA funding support of 23.33 Cr
Promotion of solar pump-sets for
agriculture/micro irrigation in the
state (Under MNRE Scheme)
150 nos 30% CFA from MNRE
Electrification of un-electrified &
remote villages/ hamlets through
DDG under, RGGVY/DDUGJY
75 remote un-
electrified villages/
hamlets covering
6,881 HHs
90% CFA amounting to Rs. 47.25 crores
from MNRE, GOI and 10% assistance
amounting to Rs. 5.25 crores from
Government of Assam
Source: Assam, Power for All
State Renewable Energy Action Plan for Assam
17
4 Existing RE promotion framework - Assam
The energy requirement of the State of Assam is predominantly fulfilled by thermal (gas based) generating plants
and large hydro plants. The role of renewable energy sources like small hydro, solar and biomass etc. in the
energy mix of Assam is not significant as of now and the government needs to emphasize on accelerating
development of renewable energy resources.
Due to low level of RE potential, State’s installed capacity in RE is also quite less. In addition to this, State also
has issue in terms of land availability which is also restricting the growth of RE in Assam. This section focuses on
review of promotional framework renewable energy in Assam with focus on RE policies and regulatory
framework for different RE technologies.
4.1 Policy Framework for promotion of RE in Assam
State’s policy framework in terms of RE promotion is quite weak, primarily due to low potential. Considering the
decent potential of Small Hydro in the State, State government in March 2007 issued one policy for Small
Hydropower Development. Since then, there has been no development on the policy framework. Following
section covers the salient features of Assam’s SHP policy.
4.1.1 Policy for SHP development, 2007
Assam has a potential of generating 541 MW from small hydro power developmentiv, to harness this potential
Government of Assam notified its first Small Hydro Policy as Policy for development of Small Hydro Power, 2007
on March 2007. The policy identified potential of 117 MW for development of small hydropower (SHP) projects
at about 88 identified locations. Salient features of the policy are as follows
Table 4: Salient features of Assam SHP policy, 2007
Policy Tittle • Policy for development of Small Hydro Power,2007
Date of Notification • March,2017
Control Period • Not Mentioned
Policy Target • Not Mentioned
Focused Segments • Project for sale to discom
• Projects for Captive use/ 3rd Party sale/ Open Access within or outside
state
• Renovation and Modernisation of existing projects
Power Evacuation • The ASEB/GENCO will carry out the implementation of evacuation
facilities at charges to be mutually negotiated.
• The cost of transmission lines in excess of 5 km shall be borne by the
IPPs/Users society and ASEB/GENCO on mutually agreed terms and
conditions.
Incentive framework • No wheeling charges are applicable in cases of sales to the ASEB
• Banking facility will be available
• Priority for dispatch into the grid
• For projects up to 5 MW - No Royalty, On entire energy generated and
sold within the State
• No further levies, taxes, charges
State level Empowered
Committee (SLEC)
• Not Mentioned
Source: Government of Assam
State Renewable Energy Action Plan for Assam
18
4.2 Regulatory Framework for promotion of RE in Assam
Assam Electricity Regulatory Commission (AERC) is responsible for providing Operational and Commercial
framework for development of renewable energy in the State. AERC has defined regulatory framework for
promotion of small as well as large RE projects through proactively issuing tariff orders and regulations
pertaining to RPO, OA etc. in the State. Some of the key regulatory initiatives taken by AERC for promotion of RE
in the State is show below in the figure.
Figure 14: Regulatory framework for promotion of RE in Assam
Salient features of these Regulations/Orders are covered under following sections
1. Renewable Purchase Obligation Regulation
Renewable Purchase Obligation (RPO) encourages development of renewable energy through enforcing a
purchase obligation on large consumers of electricity such as distribution utilities, Open Access and Captive
Consumers called as Obligated Entities (OE) to procure certain percentage of their electricity consumption from
RE sources. In case of shortfall in RPO compliance, OE are required to bear penalties as determined by the state
electricity regulatory commission (SERC)
In line to this, AERC notified ((Renewable Purchase Obligation and its Compliance) Regulation 2010, in November
2010. Later, AERC also issued amendment to this regulation in February, 2015. The regulations mandated
Obligated Entities such as DISCOMs, CPP, OA Consumer to procure certain percentage of their consumption
from RE. Further, AERC has also determined separate RPO target for Solar and Non Solar RE sources. As per the
recent amendment in February, 2015, the RPO targets approved by the regulatory commission are as follows:
State Renewable Energy Action Plan for Assam
19
Table 5: RPO target of Assam (%)
Financial Year Solar (%) Non Solar (%) Total (%)
2015-16 0.50% 6.75% 7.25%
2016-17 0.75% 6.75% 7.50%
2017-18 1.00% 6.75% 7.75%
2018-19 1.25% 6.75% 8.00%
2019-20 1.50% 7.00% 8.50%
Source: AERC
Further, AERC on 15th October, 2015 amended the regulation to reduce the RPO targets for Obligated Entities.
As per the latest amendment AERC reduced the RPO target for FY 2016-17 from 7% to 4% and RPO target for FY
2017-18 and 2018-19 were also revised. New RPO target for Assam are as follows
Table 6: Revised RPO target by AERC
Financial Year Solar (%) Non Solar (%) Total (%)
2015-16 0.25% 6.75% 7.00%
2016-17 1.00% 3.00% 4.00%
2017-18 1.25% 3.25% 4.50%
2018-19 1.50% 3.50% 5.00%
Source: AERC
In terms of the compliance of RPO; APDCL is continuously falling short in meeting the RPO target, DISCOMs
didn’t met their RPO targets under both the categories (Solar and Non Solar). RPO target for Bio-mass has not
met by discom. Other OEs such as CPP and OA consumers are also not complying their RPO targets.
As per CAG, shortfall of 3672 MUs has been reported in RPO compliance, from year 2010-14, which amounts to
an estimated penalty of INR 550.8 Cr on obligated entities. However, AERC has not levied any penalty to OEs for
short falling RPO target. As per CAG, estimated penalty of 62.66 Cr. can be levied on OEs for non- compliance of
RPO from FY 2010-14.
Figure 15: RPO Compliance by APDCL
Source: AERC
2. Renewable Energy Tariff Regulations
To promote Renewable energy in the States, Assam Electricity Regulatory Commission had issued regulation for
RE tariff determination in September 2012. There regulations are called AERC (Terms and Conditions for tariff
-27%
-97% -96%-92%
-75% -62%
-150%
-100%
-50%
0%
0
200
400
600
FY 11 FY 12 FY 13 FY 14 FY 15 FY 16
RPO Target (MUs) RPO Target Achieved (MUs) % Shortfall in RPO Target Achieving
State Renewable Energy Action Plan for Assam
20
Determination of Renewable Energy Sources), Regulations 2012. Salient features of these regulations are as
follows
Table 7: Salient features of AERC RE tariff Regulations, 2012
Tittle • AERC (Terms and Conditions for tariff Determination of Renewable Energy
Sources), Regulations 2012
Date of Notification • 10th September 2012
Eligible Technologies • Wind, Bio-Mass, SHP, Solar PV, Solar Thermal, Cogen
Control Period • Five years from the date of notification
Capital Cost for FY 2012-
13
• Wind Projects - ₹ 575 Lakh/MW
• SHP below 5 MW - ₹ 770 Lakh/MW
• SHP above 5 MW to 25 MW – ₹ 700 Lakh/MW
• Bio-Mass - ₹ 475 Lakh/MW
• Cogeneration - ₹ 475 Lakh/MW
• Solar PV – ₹ 1,000 Lakh/MW
• Solar Thermal - ₹ 1,300 Lakh/MW
• Bio-Mass Gasifier - ₹ 550 Lakh/MW
Capacity utilisation
Factor (CUF)
• Wind Projects – 20% (up-to 200 W/m^2)
• SHP above 45%
• Bio-Mass - 80% (from 2nd Year Onwards)
• Cogeneration – 53%
• Solar PV – 19%
• Solar Thermal – 23%
• Bio-Mass Gasifier – 85%
Source: AERCv
Above regulations provides the benchmark cost for different RE technologies and financial parameters for
computation of tariff for the same. However, since the notification of these regulations, there has been no Order
on revision in the capital cost or tariff determination issued by AERC. As of now AERC has been approving tariff
on case to case basis for RE projects.
3. Regulations to promote sale of RE through OA transactions
In line with the Electricity Act, 2003, Section 62 clauses (a), (b) and (e) of sub-section (1) of section 86 and sub-
section (1) of section 181 SERCs are responsible to provide commercial and regulatory framework for
development of RE projects for different technologies. In pursuance of the same, AERC has issued AERC (Co-
generation and Generation of Electricity from Renewable Sources of Energy) Regulations, 2015. Salient features
of the regulation are given below
Table 8: Salient features of AERC (Co-generation and Generation of Electricity from Renewable Sources of Energy)
Regulations, 2015
Tittle • AERC (Co-generation and Generation of Electricity from Renewable Sources of
Energy) Regulations, 2015
Date of Notification • 2nd May 2015
Eligible Technologies • All technologies approved by MNRE
Grid Connectivity • DISCOM/TRANSCO will construct the interface line if the line is 5 Km or less
• Cost of interface line in excess of 5 km shall be borne by the DISCOM/TRANSCO
and generators on 50: 50 basis
• Maintenance of these lines will be responsibility of DISCOM/TRANSCO
State Renewable Energy Action Plan for Assam
21
Sale to 3rd party • Sale of 3rd Party within or outside the state is allowed by paying applicable
charges
OA Charges • Transmission Charges : for RE, Two-third of the charges applicable to other
consumers
• Wheeling Charges : for RE, One-third of the wheeling charges applicable to
other consumers
• Solar plant COD by May 02, 2018 shall be exempted from transmission,
wheeling, CSS & banking charges for selling & captive consumption of power
within state for the period of 10 years
• No Wheeling/ Transmission charges are applicable in case all of sale of power
to State DISCOM/TRANSCO
Banking • All RE generator, except SHP can bank power for one calendar year
• SHP projects are allowed to bank power for 6 Months
• Banking charge for wind and small hydro 2% energy injected.
• For solar power generation- there will be no banking charges
Scheduling • All RE projects except the following shall be treated as ‘MUST RUN’ power
plants and shall not be subjected to ‘merit order dispatch’ principles.
• Bio-Mass projects of 10 MW and above
• Non-fossil fuel based cogeneration plants
• Wind power project of 10 MW and above
• Solar power project of 5 MW and above
Source: AERCvi
4. Net Metering Regulations
Net Metering mechanism is essentially to promote distributed solar rooftop projects, It allows utility consumers
buy or sell electricity to utility grid through their rooftop systems with the help of a bi-directional energy meter.
To promote the capacity of distributed solar generation in States, AERC has also issued Regulations for Grid
Interactive Solar PV Systems, 2015.
As per the regulations, eligible consumers are allowed to set up solar rooftop systems up-to 40% of the
sanctioned load/contract demand, subject to the feasibility of interconnection. Further, the capacity of the
rooftop project shall not be less than 1 kWp and more than 1 MWp. There is no restriction on State power
utilities to install bigger plant.
Commercial settlement of excess generation, in case the export electricity is higher than electricity consumed,
will be in the form of energy credits. Which will be carried forward to next month billing cycle for settlement. If
there is any energy credit left at the end of the settlement period, the same will be settled on APPC by the
distribution licensee. Settlement period for energy credits will be same as financial year i.e. 1st April to 31st
March.
Solar rooftop projects are exempted from banking, wheeling charges and cross subsidy surcharge. In terms of
the applicability of RPO, distribution licensee shall be eligible for fulfilling their RPO target from generation from
solar rooftop if the rooftop consumer is not Obligated Entity.
5. Open Access Regulations
Open Access regulation enables sale of RE by allowing generator to sale its power outside discoms to third party
by paying some OA charges. To enable this, AERC notified Terms & Conditions for Open Access Regulations in
2005. These Regulations shall apply to open access for use of intra-State transmission system and / or the
distribution systems of licensees in the State.
State Renewable Energy Action Plan for Assam
22
Under the OA regulations AERC defines two of Open Access
Short Term OA – for a period of less than five years
Long Term OA - for a period of equal to or more than five years
This allows, consumers having connected load of 3 WM and above to be eligible to avail Open Access. Open
Access allocation shall be done on first come first serve basis. OA Users are liable to pay the charges for open
access services for the entire capacity contracted regardless of the actual usage.
State Renewable Energy Action Plan for Assam
23
5 Gap Analysis
Based on the review and analysis of existing RE promotional framework in the state of Assam, gap analysis has
been carried out. Gap Analysis focuses on the gaps particularly in the area of in Policy, Regulatory, Institutional,
Grid integration, Funding framework. Below table summarizes all the gaps in different thematic areas.
Table 9: Gap Analysis
Sr. No Thematic Areas Gaps
Policy Gaps
1. Policy for development of
solar power
• Assam has a potential of developing 13 GW of solar power,
while the current installed capacity in the state is only 11 MW
as of Dec,2016
• MNRE has allocated 663 MW solar capacity target to Assam,
wherein 250 MW is for solar rooftop which is to be achieved
by 2022
• Lack of policy on in solar power is restricting investment in this
sector
2. Small Hydro Policy • Assam has good potential of developing over 500 MW of
power from small hydro power
• Small Hydro Policy of Assam was notified in 2007, since than
there has been no development on policy front for
development of SHP projects
• SHP policy needs to be revised with new incentives and
promotional measures to attract private investment in the
State
3. Biomass • Assam has a good biomass potential, which can utilities for
installation of power plant to be connected at tail end of the
grid.
• Low Awareness of the Concept, financing and PPP framework
is limiting the replication of these applications
Regulatory Gaps
1. Determination of FIT for RE • AERC has approved capital cost benchmarking for different RE
technologies on 2012 under AERC (terms & conditions for tariff
determination from renewable energy sources) regulations
2012
• Further, due to low capacity of RE in the State, AERC
determines project specific tariff for various RE technologies in
the State
• Lack of Visibility in terms of FIT and Capital Cost is restricting
investors for developing RE projects in Assam.
2. RPO Target and Compliance • RPO Compliance in Assam is very low, for FY 15-16 the
compliance was only 13.3%vii
• AERC during the recent amendment in RPO regulations,
reduced the RPO target for FY 2016-17 from 7% to 4%
• This was done primarily due to the low capacity of RE in the
State. While RPO target can also be met though purchase of
RECs
• As per CAG reportviii, an estimated penalty of ₹ 62 Cr. could
have been levied for non-compliance of RPO by SERCs from
2011-13, which was not done by AERC.
State Renewable Energy Action Plan for Assam
24
3. Forecasting and Scheduling
regulation
• AERC has not defined any framework for forecasting and
scheduling of RE.
• Due to this generators are not complying with the rules and
generation forecast is not accurate, which could be affect grid
stability.
4. Must run status for RE • As per the AERC (Co-generation and Generation of Electricity
from Renewable Sources of Energy) Regulations, 2015. RE
projects up-to a certain capacity (5-10 MW) are only eligible
for must run Status
• Large RE projects will be entitled for merit order dispatch,
which is also a negative signal for investors and impacting the
growth of RE in Assam.
Grid Integration
1. Low capacity of existing
network
• Existing capacity of evacuation system is not sufficient to
match up with MNRE targets.
2. No Communication link
between RE pooling SS and
SLDC
• RE pooling sub-station are not connected with SLDCs to have
real time visibility of RE
• This is causing problems for system operators moreover,
system security is also been compromised
Institutional Capacity
1. State Agencies are lacking in
implementing solar rooftop
projects
• Lack of capacity of State agencies like SNA, Discom are
impacting the growth of distributed generation in the State.
• Engineers at division/sub-division level are not well conversant
with the process of interconnection, subsidy registration
process etc.
• Lack of IT Infrastructure is restricting SNAs capability in
monitoring and tracking the progress of project and subsidy
disbursement
Funding
1. Lack of financial support for
de-centralised solar
applications
• Installation cost of small scale solar projects in north east is
high in comparison to other parts of the country due to
geographical constraints, due to lack of incentives and market,
private players are not participating in the States
2. Financial Health of State
discoms
• Financial health of State discoms is not good, which needs to
take care by the State and Central government for promotion
of RE.
Based on the gaps identified above, a summary of the findings of gap analysis across different technologies and
different parameters is developed under the following figure. The Color coding indicates priority of gaps under
low, medium and high category. The gaps identified under high category needs to be taken on high priority to
achieve national targets within specified timelines. Further, the graph also illustrates the attractiveness of
different RE technologies based on different parameters for potential investors.
Figure 16: Summary of Gaps
State Renewable Energy Action Plan for Assam
25
State Renewable Energy Action Plan for Assam
- 22 -
6 RE targets for Assam
This sections analysis the renewable energy target trend for Assam for year 2022 and year 2030. MNRE has
allocated targets to Assam for FY 2022 under 175 GW national target. The approach has been to understand the
level of RE penetration based on the RE capacity added by year 2022.
One of the important considerations has been the varying electricity demand level. Different studies have
projected varying level of electricity demand, which in turn will impact the level of RE penetration in the overall
power portfolio (if the RE Targets are met).
The aspects considered for analysis are:
• Renewable Energy targets for Assam are computed based on the following parameters
• MNRE’s RE capacity addition targets for Assam for FY 2022
• Capacity requirement to meet RPO target for FY 2018-19
• To compute yearly RE capacity addition target, CAGR has been computed by considering FY 2019
as base year and FY 2022 as the target year
• Based on CAGR, annual capacity addition targets proposed for FY 20 & FY 21
• RPO targets for upcoming years, calculated on the basis of the projected energy requirement from different
sources,
• CAGR of past energy consumption (from FY 2011-12 to FY 2015-16)
• 18th Electric Power Survey (CEA)
• Power for All (MOP, GoI)
• Finally, State RPO has been computed to achieve the RE capacity addition target as specified by MNRE
• State RPO target computed based on the energy projections under three different scenarios i.e.
Past Consumption Growth Rate, 18th EPS (draft), Power for All
• Capacity Utilisation Factor (CUF) for different RE technologies is considered based on AERC RE tariff
Regulations
6.1 RE targets of Assam as per MNRE for 2022
Considering low potential in Wind and Bio-Power, MNRE has not allotted any target for Wind and Bio mass to
Assam. Assam’s current installed capacity of 34 MW including SHP capacity of 34 MW and zero from solar by
March 2016 is taken as the base for projections. The capacity addition in solar and SHP has been increased to
meet the targets specified by MNRE for Assam based on CAGR approach. The same is shown in the figure below:
Figure 17 : RE Targets for Assam as per MNRE
The figure below details the energy projections under different scenarios and RPO requirement to meet the
MNRE RE target under different energy projection scenarios.
Figure 18: Assam RPO target under different scenarios
172
296
445 516
599 697
FY 17 FY 18 FY 19 FY 20 FY 21 FY 22
SHP
Solar
State Renewable Energy Action Plan for Assam
- 23 -
It can be seen that the RPO target requirement to meet MNRE targets vary based on the energy demand
projections. With increase in the energy requirement, RPO target for FY 2022 will reduce.
6.2 RE targets of Assam for 2030
Under Nationally Determined Contribution (NDC) of Government of India, share of non-fossil fuel in the total
installed capacity is projected to change from 30% in 2015 to about 40% by 2030. In order to achieve this target,
India is running one of the largest renewable capacity expansion programs in the world.
To accelerate development and deployment of renewable energy in the country, the Government is taking a
number of initiatives like up-scaling of targets for renewable energy capacity addition from 50GW in year 2016
to 175 GW by year 2021-22.The renewable power target of 175 GW by 2022 is expected to result in abatement
of 326.22 million tons of CO2 eq. /year.
With a view to meet the India’s share of non-fossil fuel in the total installed capacity to about 40 % by 2030, it is
important that each state support the achievement of these targets. The RE targets for Assam for year 2030 has
been analyzed from this perspective.
The key steps considered for estimation of RE capacity addition
targets are indicated below:
As per draft National Electricity Plan (NEP) 2016, India’s
total installed capacity shall be 684 GW by 2027 (under
Base case scenario) and the share of RE shall be 40.2%
in capacity terms and 24.2% in energy terms.
• As per draft NEP 2016, 100 GW RE capacity to be added
between year 2022 to 2027.
The NDC targets aims to achieve 40% share of non-
fossil fuel in the total installed capacity by 2030. As per
Draft NEP 2016, share of RE shall be 40.2% in capacity
terms and 24.2% in energy terms in year 2027. We
have assumed for year 2030 the % capacity and energy contribution of RE will remain same in the
overall portfolio (as indicated for year 2027 in draft NEP 2016) and is aligned towards achievement of
NDC targets by year 2030.
State Renewable Energy Action Plan for Assam
- 24 -
• It is assumed the 24.2% RE penetration level can be considered as a national level RE penetration level
(or RPO target) for year 2030. Based on this assumption, we have considered the same RE penetration
target for the state of Assam.
• The energy requirement for Assam has been considered as 22.092 BU in year 2030, assumed as per 18th
EPS projections.
The approach results in the below results at all India level:
Table 10: CEA Projections on Electricity Generation (BU) – National level
Projected RE Generation (BUs)
in 2021-22#
Projected RE Generation (BUs)
in 2026-27#
Solar 162 243
Wind 112 188
Biomass 38 64
SHP 15 21
Total Energy requirement 1611 2132
Share of RE 20.3% 24.2%
Source: CEA, Draft NEP, 2016 (Under Base Case Scenario)
As per the approach, India’s RE share is assumed to be around 24.2% in the overall energy mix by 2030. To
achieve this capacity, national RE penetration target can be considered as follows:
Table 11: National RPO for 2030 (%)
S.No. National RE Share (%) for FY 2030
1.0 RE Total 24.20%
1.1 • Solar 11.40%
1.2 • Non Solar 12.80%
If the national RE penetration target of 24.2% is also assumed to be met at State level, then Assam’s estimated
required RE capacity for year 2030 will be as given below.
Table 12: RPO target for Assam
S.No. Assam RE target for 2030 Capacity (MW)
1.0 Total RE target 2680
1.1 • Solar 1507
1.2 • Non Solar
• Wind 1005
• Biomass 144
• SHP 25
State Renewable Energy Action Plan for Assam
- 25 -
7 State Renewable Energy Action Plan
Assam is among the states with low RE potential, hence the growth of RE sector is not comparable with other
parts of the country. Renewable Energy Action Plan for Assam focuses on exploiting maximum RE potential of
the state and contribute India in meeting national targets. With this objective, State RE action plan is developed
(RE-SAP) focusing on development of renewable energy though interventions in six key areas.
Figure 19: Pillars of RE State Action Plan
Action plan is developed on the basis of the as-is analysis of existing RE promotional framework of Assam, gaps
identified and inputs with officials of state agencies. RE State Action Plan aims to address the following issues
that state is facing, through interventions both at national and state level
• Lack of RE capacity to meet RPO targets
• Lack of land availability for developing large RE projects
• Limited forecasting available for RE projects, REMC still to be developed
• Constrained to trade with other states and agencies – no established framework
• Lack of subsidy/commercial models for promotion of de-centralised and distributed RE generation
• Discoms financial health is deteriorating
•
Following sections will discuss in detail how these issues can be address with the help of interventions in the
form of Policy, Regulatory, Market framework etc.
7.1 Interventions required at State Level
This section focuses on bringing out state level issues and provide recommendation to resolve them to develop
the capacity on RE in the State.
1. FOCUS ON DEVELOPMENT OF DISTRIBUTED SOLAR PROJECTS THROUGH INNOVATION BUSINESS MODELS Existing Solar rooftop capacity of Assam is only 1.179 MW (14 MW capacity is approved), while the MNRE target
is 250 MW by 2022. Further, due to land availability issue feasibility of large scale RE projects is also very limited
in the State. In view of this, there is a need to develop distributed solar projects though adoption of innovative
business models. This would help the State in meeting the targets and at the same time reduction of technical
State Renewable Energy Action Plan for Assam
- 26 -
losses and also minimising the cost of developing evacuation infrastructure for large scale solar projects. Some
of the recommendations in this area are as follows:
• Announce a strong policy on Rooftop and small scale solar projects with good incentives for
investors
• Encourage Govt. offices, institutes, hospitals etc. to install solar rooftops through city wide rooftop
programs (RESCO – Rooftop aggregation model)
• Focus on development of 5-10 MW distributed solar projects near sub-stations to minimize land
requirement and cost of developing additional infrastructure
• Encourage private sector participation through JVs and MOU route.
2. BUILD CAPACITY OF DISCOMS AND SNAS FOR DEVELOPMENT OF ROOFTOP PROJECTS
Rooftop market is relatively new in India in comparison to utility scale solar projects. State discom and AEDA
plays an important role in implementation of rooftop projects as discoms are responsible for providing
connectivity and SNAs are responsible for disbursement of incentives/subsidy for development of these projects.
Capacity building of these two holds the key for development of rooftop market in the State.
State government in support with central government should organise knowledge exchange programs with
state’s having good experience in rooftop implementation. Further best practice shall also be adopted for
implementation of solar rooftops to minimise the time for approval of interconnection request and
administrative burden on distribution utilities.
3. DEVELOP FRAMEWORK TO ENCOURAGE INTER-STATE PURCHASE OF RE POWER
The State of Assam receives limited solar irradiation and clear sunny day in comparison to other states located
in western and central India. Lower irradiation results in lower yield and hence per unit cost of generation will
be relatively higher in the state as compared to projects located in states that receives higher irradiation.
Therefore, procuring RE power either directly from resource rich states or through SECI based bidding can be an
attractive option for Assam to meet its RPO. The State Govt. shall develop a clear policy framework to encourage
obligated entities to procure from resource rich states and benefit from low cost RE power available in these
States.
4. ENCOURAGE HARNESSING OF RE POTENTIAL IN THE TEA SECTOR
Solar Energy & Bio-mass gasifier can play a major role for processing of tea in:
• Withering, Thermal process ( Pre heating of air)
• Drying, Thermal process( Pre heating of air )
• Solar photovoltaic (Factory lighting/ Home Lighting)
• Hot Water Systems (Bunglows & Quarters )
The State Govt. should enhance awareness w.r.t technology options, financing support and piloting PPP
framework to establish commercial viability of these applications. Implementation of pilot projects, with Govt.
Support, shall assist in popularising the concept.
5. ENHANCE LOCAL EMPLOYMENT TAPPING ELECTRIFICATION THROUGH BIOMASS GASIFIER
With large population in the State not having access to electricity, the state should encourage electrification of
villages using small biomass gasifier system. Such villages could be provided electricity for 4-6 hours in the
evening for lighting and other uses and 5-6 hours in day time for irrigation and other small commercial activities.
These projects to be set up by entrepreneurs based on sustainable business model. The State Govt. should
develop a PPP framework with clear framework on contracting, incentives etc.
State Renewable Energy Action Plan for Assam
- 27 -
6. BIOMASS THROUGH DEDICATED ENERGY PLANTATION
The State Govt. should explore development of biomass through dedicated energy plantation. The key benefits
of the initiative can be:
• These will be small 1-2 MW tail end plants
• Save transmission losses by 7% better power factor
• Facilitate electricity supply to rural areas
• Bamboo forests regularly harvested would capture carbon efficiently (12 tonne/ha/yr against 0.5
to 1.5 tonne/ha/yr for other species)
The State Govt. should develop a PPP framework with clear framework on contracting, incentives etc.
Implementation of pilot projects shall assist in popularising the concept.
7. INSTITUTIONAL CAPACITY BUILDING IN NEW AREAS
The State Govt. shall focus on developing capacity building of state agencies and stakeholders in the following
areas:
• Training professionals on RE applications to target stakeholders (like tea industry) by introducing
short term courses in technical educational institutions,
• Capacity building of the technician (like electrician) on RE applications and its uses,
• RE awareness campaign through mass media and other means of communication.
• Generation of awareness in all sections of the society regarding energy, renewable energy sources
and its uses,
• Sensitization and capacity building of SHGs for propagation of improved chullas and biogas plants.
8. REAL TIME MONITORING OF GENERATION FROM RE FOR GRID MANAGEMENT
With increase in RE penetration, Real time monitoring of RE will be needed to manage the grid. To enable this,
the state could:
• Implement communication channel to connect pooling stations with REMCs
• Utilize NCEF grant to strengthen local infrastructure such as ABT meters, RTU/DC, Pooling station
across states etc.
• Empower and prepare SLDC for real time monitoring of output from RE projects
9. MANDATORY IMPLEMENTATION OF RE GENERATION FORECASTING TOOLS
Due to errors in RE generation schedule and output, it is difficult to manage for system operators to ensure grid
safety. This forces system operators to back down RE generators in view grid management. To resolve this, there
is a need to mandate RE generation forecasting tools at generator end. In view of this some of the
recommendations are as follows
• Promote implementation of weather monitoring units at every wind or solar projects
• AERC to notify forecasting and scheduling regulations and deviation and settlement mechanism for
RE projects
• Outline forecasting methodology to ensure consistency of process
10. STRENGTHEN TECHNICAL DEMONSTRATION AND RESEARCH AREAS
The State Govt. shall focus on the following areas:
• Assessment of renewable energy resources availability, technology options for Assam and mapping
cost benefits.
State Renewable Energy Action Plan for Assam
- 28 -
• Create database on issues such as bio resources assessment and mapping on bio energy resource
is recommended.
• Map best practices adopted elsewhere in the country on renewable energy application be analyzed
in view of the geo-climatic condition of the state and adopted wherein possible. Disseminate
results of demonstration projects.
• Technological status (existing as well as prospective up-gradation) and R & D requirements
particularly in biomass, solar, hydro in independent as well as in hybrid mode (based on locally
available prospective resources viz. crop residue biomass, woody biomass including forests and
bamboo biomass with provision for re-plantation.
State Renewable Energy Action Plan for Assam
- 29 -
7.2 Interventions required at National level
1. DEVELOPING FRAMEWORK FOR BALANCING MARKET
India has set an ambitious target of adding 175 GW of RE by 2022, while country’s present capacity is ~57 GW
by March, 2017. This indicates 118 GW of RE required to be added to the system in coming five years. This will
require planning in terms of developing adequate transmission system to facilitate the evacuation of power from
RE projects and manage the grid with high RE penetration.
Though, forecasting and scheduling initiatives are now being carried out seriously in the country, but still clarity
on balancing capacity and commercial arrangement will be required. In view of this, CEA under the draft NEP
2016, Transmission plan covers detailed exercise on computation of balancing capacity required at regional
levels in an interval of 15 minutes to 6-7 Hrs for FY 2022. Illustrated in the figure below6
Figure 20: Regional balancing capacity required by FY 2022ix
Managing 160 GW of RE (Solar and Wind) generation will require high balancing capacity. At India level, there
will be a need of ~45 GW of balancing capacity to respond within 3 hours' time interval (Source - CEA). Hence,
there is a need to develop larger balancing zones (or Load-Frequency Control areas) and more frequent re-
calculation of balancing capacity. This will result in lowering required reserve capacity while at the same time, it
will give utilities access to more balancing resources.
However, arranging such capacity at state level would be quite difficult, hence there is a need of developing
balancing framework at regional/national level – large balancing will be helpful in better management of
variability. This will ensure maximum utilization of available resource through pooling of power projects.
The key recommendations to address balancing specific issues are:
• Layout a roadmap and identify timelines for operationalizing the national or regional reserve market
6 Balancing Capacity Illustrated for 3 Hour time interval
State Renewable Energy Action Plan for Assam
- 30 -
• Establish methodology for estimation and allocation of costs between RE rich and RE deficit states
• Issue technical guidelines covering
Retrofitting of thermal power plants
Revision of technical minimum for operating thermal plants
Use of stranded gas based plants
CEA to conduct Technical studies to identify power plants that will be used as balancing
reserve at regional or national level
• CERC and SERCs to agree and develop regulation for balancing at regional level
• Define regional clusters for balancing, identification of capacity available
• Technical and Commercial settlement framework
• Framework re-calculation of balancing capacity across different time blocks (day-ahead, real
time)
• Roles and responsibilities of RLDCs, SLDCs needs to be defined :
• Suitable incentives for states to share their resources for balancing capacity
• Establishment of a functioning regional balancing market
• State should be mandated to have proper scheduling and forecasting and DSM
framework for RE
2. Developing dedicated platform for RE Trading
In India, renewable energy potential is confined to few states only, which are facing huge difficulties in managing
high RE generation. In view of meeting MNRE targets by 2022, country needs a trading platform to provide
competitive avenue to RE buyers/sellers. To enable this, following are the recommendations
• Allow exclusive RE trading platform – to provide competitive avenue to RE buyers/sellers
• Need of regulatory clarity and operational framework by CERC
• Market rules for participation – buy-in from SERCs
• Introduce measures to better interconnect short-term markets and to pull all flexible distributed
resources into the market
3. Develop a common platform to build consensus on Policy matters between State and Central
government
MNRE has allocated 175 GW of RE target to all the states. Many of these states have their own policy targets,
which are not in line with MNRE targets. Further, states have no incentive of achieving MNRE targets in addition
to their policy targets. This creates communication gap among state and central government and impact
investment in the sector. Hence, there is a need to create a platform where consensus on policy matters can be
built among State and Central Government. This will also ensure policy certainty in the whole country and will
help in achieving targets in a collective manner.
• Platform such as Association of Renewable Energy Agencies of States (AREAS) which is already in place can
be used for this purpose
• AREAS under the leadership of MNRE can be strengthen to take decision on policy matters, which
are uniform across the country
• State’s will also have the responsibility in achieving targets, if they were involved in target setting
• This platform can also be used for knowledge exchange and develop best practices for
implementation of RE and other key areas like Scheduling and forecasting etc.
4. Re-negotiating PPA with existing projects having balancing capacity
There are many hydro, coal and gas based projects which can be utilised for balancing capacity, but are being
utilised as base load. The MOP/MNRE should facilitate re-structuring PPAs of these projects with procuring
states to arrange balancing capacity or provide incentives to bring them to balancing market. The CERC should
come out with commercial settlement and operation framework to enable this initiative.
State Renewable Energy Action Plan for Assam
- 31 -
5. Discoms should be allowed to trade excess generation at trading platforms
Regulatory commissions (CERC and SERCs) should empower state Discoms to trade the excess generation
capacity available with them in open market (define operational & pricing guidelines). This would reduce the
back down of RE and conventional generators due to low demand (primarily during night time). The CERC
through FOR should develop market rules to enable this framework and facilitate separate RE trading platform
to address pricing related issues.
6. Incentive for existing conventional plants
As per CEA, PLF of thermal plants is expected to drop to 45.5% by 2022 to accommodate RE. Majority of these
projects are not designed to run on low PLF. Further, it will also have commercial implication on project
developers. Hence, there is a need to incentivise these projects to compensate them for loss of generation due
to low PLF (below the technical limits). Also, technical feasibility of operating these projects at low levels need
to analyse.
7. Explore retrofitting of the existing thermal plants for balancing capacity
To increase the ramping capacity and backing down capacity, it is important to develop market mechanism
through regulatory intervention. The market must provide proper incentives to key stakeholders in the grid to
willingly participate in the balancing market. It is important to explore retrofitting in existing thermal plants to
bring additional balancing capacity to market.
State Renewable Energy Action Plan for Assam
- 32 -
8 Annexure 1: National level RE Targets
8.1.1 Solar Energy
India is endowed with vast solar energy potential. About 5,000 trillion kWh per year energy is incident over India
land area with most parts receiving 4-7 kWh per sq. m per day.
According to National Institute of Solar Energy (NISE), country
is having solar energy potential of around 750 GW. India is a
tropical nation and receives solar energy around 300 days in a
year.
Solar power target capacity of 100 GW by 2022 has been
divided into two main parts - with 40 GW for rooftop and 60
GW of ground mounted PV projects.
The year wise targets are as follows:
Table 13: Yearly target for achieving 100 GW of PV installation by 2022
Source: MNRE *3743 MW Commissioned upto 2014-15
8.1.1.1 Solar Parks
Solar parks have emerged as a preferred option to add large scale solar capacity in the country. The scheme for
“Development of Solar Parks and Ultra Mega Solar Power Projects” was rolled out by Ministry of New &
Renewable Energy on 12-12-2014. This scheme envisaged supporting the States in setting up solar parks at
various locations in the country with a view to create required infrastructure for setting up of Solar Power
Projects. The solar parks provides suitable developed land with all clearances, transmission system, water
access, road connectivity, communication network, etc. This scheme aimed to facilitate and speed up installation
of grid connected solar power projects for electricity generation on a large scale.
Approvals have been accorded to 34 Solar Parks of aggregate capacity of 20,000 MW to be set up in 21
States. After the success of solar park framework, the MNRE has now increased the capacity to be installed under
scheme for “Development of Solar Parks and Ultra Mega Solar Power Projects” from 20,000 MW to 40,000 in
Year Target
(Ground Mounted)
Target (Rooftop) Total
2015-16 1800 200 2000
2016-17 7200 4800 12000
2017-18 10000 5000 15000
2018-19 10000 6000 16000
2019-20 10000 7000 17000
2020-21 9500 8000 17500
2021-22 8500 9000 17500
Total 47000 40000 97000*
(~100 GW including 3743
Commissioned upto 2014-15)
Figure 21 : Solar Potential
State Renewable Energy Action Plan for Assam
- 33 -
year 2017. These solar parks would be set up by year 2019-20, with an estimated Central Financial Assistance
(CFA) of Rs 8100 crores.
8.1.1.2 Solar Rooftops
The unutilized space on rooftops provides a large potential for generating solar power. Small quantities of power
generated by each individual household, industrial building, commercial buildings or any other type of building
can be used to fully / partially fulfil the requirement of the building occupants and surplus, if any, can be fed into
the grid.
Rooftop solar PV systems have the advantage of low installation time, providing clean source of energy. They
can also improve the reliability of power supply for rooftop owners, eliminate the need for long-distance
transmission lines associated with large-scale solar generation plants and save on network losses associated
with large-scale plants wheeling power to load centers.
The solar rooftop is highly attractive
segment and Govt. of India has set an
overall target of 40 GW by 2022. The
MNRE is providing upto 30 percent
support for capital subsidy support to
the residential and institutions
(college, hospital etc.) under the
ongoing Central Financial Assistance
(CFA) program.
In order to promote solar roof top,
IREDA also has dedicated financing
scheme for solar rooftop projects for
industrial, commercial and
institutional consumers. The figure
details the targets allocated to
different States by MNRE to achieve
40 GW rooftop capacity by 2022.
8.1.2 Wind Energy
India is blessed with high wind potential in most parts of the country. As per National Institute of Wind Energy,
wind energy potential in the country is 302 GW.
In terms of potential, Gujarat has the maximum wind energy potential of 84 GW followed by Karnataka (55 GW),
Maharashtra (45GW), Andhra Pradesh (44 GW) and Tamil Nadu (33 GW). In addition to these State, Rajasthan
(18GW) and Madhya Pradesh (10 GW) also has high wind potential sites.
In the recent years, majority of the wind installations have happened in the states of Rajasthan, Madhya Pradesh,
Maharashtra and Andhra Pradesh by large IPPs.
Figure 22 : State wise rooftop solar targets - 2022
State Renewable Energy Action Plan for Assam
- 34 -
Out of the 302 GW of wind potential, India
as of now have been able to achieve ~32.2
GW (by March 2017). This is largely due to
concertation of wind potential in few
states. The state like Andhra Pradesh,
Gujarat, Karnataka, Maharashtra, Tamil
Nadu, Rajasthan etc. accounts for more
than 85% of the overall potential of the
country.
The Government of India has set a target
of achieving 60 GW of installed wind
energy capacity by 2022. In order to
achieve this target, both Central and State
government are working together and
providing various support in terms of
conducive policy framework, identification
of land banks, providing incentives etc.
The following figure shows the roadmap of
Government of India to reach 60 GW
target
Figure 24: Annual wind energy capacity
addition targets
Source: Ministry of New and Renewable Energy
In addition to the 60 GW target for standalone wind projects, the country is also aiming to exploit the potential
through Wind-solar Hybrid policy with the help of hybrid projects. Under the recently notified policy, the
Ministry of New and Renewable energy envisages to achieve the target of 10 GW of solar wind hybrid energy by
2022.
8.1.3 Biomass
Biomass is one of the dominant sources of energy in India with a large population relying on biomass to meet
their primary energy need. As per MNRE’s estimates, the availability of biomass in India is estimated at about
500 millions metric tonnes per year, out of which surplus biomass availability at about 120 – 150 million metric
tonnes per annum covering agricultural and forestry residues. Based on this availability, the assessed potential
for biomass based generation capacity is 18 GW. In addition, the power generation potential from the bagasse
based projects is around 7 GW.
The biomass power sector has experienced a gradual growth in the capacity additions with installed capacity
increasing from 3,135 MW in 2011-12 to 4,831 MW in 2015-16. Cumulative annual growth rate of capacity
addition during this period is around 11 percent.
Figure 23: Wind Energy Potential of India
State Renewable Energy Action Plan for Assam
- 35 -
8.1.4 Small Hydro
In India, hydro projects up to 25 MW station capacities have been categorized as Small Hydro Power (SHP)
projects. While Ministry of Power, Government of India is responsible for development of large hydro projects,
the mandate for the subject small hydro power (up to 25 MW) is given to Ministry of New and Renewable Energy
(MNRE).
India has potential of generating more than 19 GW of small hydro power (upto 25 MW). Out of the 19 GW
potential of SHP, States of Karnataka, Himachal Pradesh, Uttarakhand, and North East constitute 50% of this
potential.
The growth trend of SHP in India is shown in the figure below.
By March, 2017 India’s total installed capacity in Small Hydro Power has reached 4,379 MW. The State of
Karnataka has the highest capacity of SHP with 1,177 MW, Himachal Pradesh 754 MW. Since 2010, SHP capacity
in India has grown at a rate of 8% annually and contributes to approximately 7% of the installed renewable
energy capacity of India (In March 2017).
Figure 25 : SHP Capacity addition trend
State Renewable Energy Action Plan for Assam
- 36 -
9 References
1. i CEA – Monthly Report, Jan 2017
(http://www.cea.nic.in/reports/monthly/executivesummary/2017/exe_summary-01.pdf)
2. ii Ministry of Power – PFA, Assam
(http://powermin.nic.in/sites/default/files/uploads/joint_initiative_of_govt_of_india_and_assam.pdf)
3. iii Ministry of Power – PFA, Assam
4. iv Assam – SHP Policy
(http://www.ireda.gov.in/writereaddata/CompendiumStatePolicyRE/P%20Original/Assam.pdf)
5. v AERC - (Terms and Conditions for tariff Determination of Renewable Energy Sources), Regulations 2012)
(http://aerc.gov.in/AERC_RE_Tariff_Regulations_2012.pdf)
6. vi AERC – (Co-generation and Generation of Electricity from Renewable Sources of Energy) Regulations, 2015
(http://mnre.gov.in/file-manager/Compendium/Final/ASSAM%203.pdf)
7. vii MNRE - National Review Meeting (http://solarrooftop.gov.in/notification/Notification-09012017.pdf)
8. viii CAG – Report on RE Sector, Annexure V
(http://www.cag.gov.in/sites/default/files/audit_report_files/Union_Civil_Performance_Renewable_Ener
gy_Report_34_2015.pdf )
1. ix CEA – Draft National Electricity Plan (Transmission), Chapter-11
(http://www.cea.nic.in/reports/others/ps/pspa2/draft_nep_trans_2016.pdf)
State Renewable Energy Action Plan for Assam
- 37 -
Deloitte refers to one or more of Deloitte Touche
Tohmatsu Limited, a UK private company limited by
guarantee (“DTTL”), its network of member firms,
and their related entities. DTTL and each of its
member firms are legally separate and independent
entities. DTTL (also referred to as “Deloitte Global”)
does not provide services to clients. Please see
www.deloitte.com/about for a more detailed
description of DTTL and its member firms.
This material has been prepared by Deloitte Touche
Tohmatsu India LLP (“DTTILLP”), a member of
Deloitte Touche Tohmatsu Limited, on a specific
request from you and contains proprietary and
confidential information. This material may contain
information sourced from publicly available
information or other third party sources. DTTILLP
does not independently verify any such sources and
is not responsible for any loss whatsoever caused
due to reliance placed on information sourced from
such sources. The information contained in this
material is intended solely for you. Any disclosure,
copying or further distribution of this material or its
contents is strictly prohibited.
Nothing in this material creates any contractual
relationship between DTTILLP and you. Any
mutually binding legal obligations or rights may only
be created between you and DTTILLP upon
execution of a legally binding contract. By using this
material and any information contained in it, the
user accepts this entire notice and terms of use.
©2017 Deloitte Touche Tohmatsu India LLP.
Member of Deloitte Touche Tohmatsu Limited
Deloitte Touche Tohmatsu India Private Limited
(U74140MH199 5PTC093339), a private company
limited by shares, was converted into Deloitte
Touche Tohmatsu India LLP, a limited liability
partnership (LLP Identification No. AAE-8458), with
effect from October 1, 2015.