State Bridge Program2010-2013 STIP Development Process

Oregon Department of Transportation

October 3, 2007

Page 2: State Bridge Program 2010-2013 STIP Development Process Oregon Department of Transportation October 3, 2007.

State Bridge Program Goals

Our investment decisions will be based on these goals:

Improve state bridges by eliminating• Freight Mobility Restrictions (Load, Width, or Vertical Clearance) • Poor structural condition (Deterioration, Damage, Scour)

Maximize investment by building bridges that• Require less maintenance with longer life expectancy• Meet standards and community expectations well into the future

Page 3: State Bridge Program 2010-2013 STIP Development Process Oregon Department of Transportation October 3, 2007.

State Bridge Program Goals

To accomplish this, the State Bridge Program will:

• Concentrate STIP projects for state bridges on freight and NHS routes to address load capacity and safety issues.

• Give priority of remaining funding to achieve and 80% functional and structural condition on the NHS.

• Preserve high value structures, such as major river crossings and movable bridges.

Page 4: State Bridge Program 2010-2013 STIP Development Process Oregon Department of Transportation October 3, 2007.

2010-2013 STIP Development Process Outline

• Identify Problem Bridges (January – March)

• Initial Review and Prioritization by Bridge Section (April – May)

• Review of Draft Problem Bridge Lists by Regions/Areas/Districts (June)

• Second Stage Review and Prioritization by Bridge Section including Region Adds (July)

• Development of Preliminary Projects (Desk Scopes and Estimates) by Bridge Section (July – August)

• Joint Bridge Section/Bridge Leadership Team Review of Proposed Field Scoping List l(September)

• Region Review of Proposed Field Scoping List (October)

• Field Scoping by Regions (November – February)

• Bridge Section Review of Field Scoping (March – April)

• Preliminary Program Identified (April)

• BLT/Region Input (April – May)

• Final Draft Program (May)

• Data Entry and Reports (June)

• Submittal/Review of Draft Program to HFO (June – July)

• Draft STIP Public Review Process (August – November)

Page 5: State Bridge Program 2010-2013 STIP Development Process Oregon Department of Transportation October 3, 2007.

Problem Bridge Selection Criteria

Page 6: State Bridge Program 2010-2013 STIP Development Process Oregon Department of Transportation October 3, 2007.

State Bridge Program Elements

Page 7: State Bridge Program 2010-2013 STIP Development Process Oregon Department of Transportation October 3, 2007.

State Bridge Program Summary

• It is our intent to optimize bridge condition within the limits of available funding.

• Bridge Program Funding Levels (not including OTIA, OTIA debt service, SAFETEA Earmarks, or MBM). 06-07 $136M target 08-09 $94.6M target & Dec ’05 Revisions ($62M) 10-11 $102.2M target 12-13 OTC sets in Dec ’07