Star Symposium 2013 The Changing Reality of Energy Development
description
Transcript of Star Symposium 2013 The Changing Reality of Energy Development
Star Symposium 2013 The Changing Reality of Energy
Development
Jeffery LaFleur, Vice President Generation Assets APCO/KYPCO
October 22, 2013
2011 2012 2013 2014 2015 2016 2017 2018
Time From Rule Finalization to Compliance
Effluent Limit Guidelines (water discharge limits)
Coal Combustion Residuals
MATS (mercury & air toxics)
2012 & 2014 Compliance PhasesRule Vacated pending Supreme Court Appeal
Environmental Rules Development
CSAPR (SO2 & NOx)
20202019
316(b) Rule (water intake structures)
New Source CO2 NSPS
Existing Source CO2 NSPS
Pro
po
sed
an
d/o
r F
inal
ized
Ru
les
An
tici
pa
ted
R
ule
s
Potential for One Year Compliance Extension
Compliance Timeline Contingent on Permit Renewal Cycle
Compliance Timeline Contingent on State Implementation Plans
Compliance Required from Rule Proposal DateRe-Proposal of Rule Expected
Compliance Timeline Will Vary
20222021
Historic AEP Emission Reductions
Since 1980, AEP’s TOTAL generating fleet has reduced:
SO2 emissions by more than 77 percent
NOx emissions by about 80 percent
0.0
0.4
0.8
1.2
1.6
2.0
1980 1985 1990 1995 2000 2005 2010
SO
2
(mill
ion
s o
f U
.S. t
on
s)
0.0
0.2
0.4
0.6
0.8
NO
x(m
illio
ns
of
U.S
. to
ns)
SO2 Emissions
NOx Emissions
Global CO2 Emissions
4
Global CO2 Emissions
• 2012 global CO2 emissions totaled
32.2 billion metric tons.
• Of that, China accounted for 28 percent.
• The U.S. accounted for 17 percent.
• Global emissions have increased
15 percent since 2005.
• 80 percent of the increase is because of growth in China.
• By 2040, emissions from developing countries will rise by more than 70 percent.
5
U.S. Greenhouse Emissions
6
• In 2011, EGU CO2 emissions were 10 percent below 2005 levels.
• Preliminary 2012 EIA data indicates EGU emissions were 15 percent below 2005 levels.
7
U.S. Greenhouse Emissions
Proposed CO2 Regs
• 1,100 lbs. per MWh for new coal plants.
– CCS would be required to meet goal.
• 1,000 lbs. per MWh for new natural gas plants.
• New Turk plant is 1,800 lbs. per MWh.
8
Cost to Build
9
Installation Cost Per kW
Coal vs. Natural Gas
10
MMBTU
IGCC Status
• Duke Edwardsport IGCC– Began commercial operation June 2013.
– 618 MW facility without CO2 capture.
– Estimated Cost: $3.4 billion or $5,500/kW.
• Southern Company Kemper IGCC– Under construction (expected COD mid-2014).
– 582 MW facility with 65 percent CO2 capture (3.5 million tonnes per year).
– Estimated Cost: $4.7 billion to date or $8,000/kW (original estimate about $2.4 billion).
• By comparison, the Turk plant is a 620 MW ultra-supercritical and was completed at a cost of about $1.8 billion, or $2,900/kW.
A Customer’s Bill
12
7%Transmission
25%Distribution
Recent Rate Activity
The Appalachian Power ExperienceThe Effect on Customers
• Low per capita income
– West Virginia - $23,697.
– Virginia - $21,636 (our service area).
• Unemployment remains high
– West Virginia – 6.3 percent.
– Virginia – 5.8 percent (our service area).
• 54 percent of customers have electric heat.
• 25 percent of customers are behind on their bills.
• 400 percent increase in uncollectibles.
14
Customer Data