Standarized Work Presentation
Transcript of Standarized Work Presentation
4/22/2009 @2008 Performing Better & Better, All rights reserved 1
Standardized WorkLine Balancing
Line Staffing
4/22/2009 @2008 Performing Better & Better, All rights reserved 24/22/2009 @2008 Performing Better & Better, All rights reserved 2
Today’s Agenda:Standardized Work (SW)
Intro to SW;Elements of SW
Takt Time (TT)Work Sequence
Standardized Work Combination (SWC) ChartStandardized Work Diagram (SWD)Standardized Work Instructions
Standardized Work in Process (SWIP)
Balancing the LineStaffing the LineGeorge’s “End-of-the-Talk” Question…Q&A 55 Slides in 75 minutes which means…
Takt Time = 81.81818181818181 sec.!
4/22/2009 @2008 Performing Better & Better, All rights reserved 34/22/2009 @2008 Performing Better & Better, All rights reserved 3
Standardized Work
the foundation for consistent and stable quality.
This consistency and stability is the first step toward Continuous
Improvement (Kaizen).
is...
4/22/2009 @2008 Performing Better & Better, All rights reserved 44/22/2009 @2008 Performing Better & Better, All rights reserved 4
Why Standardized Work?
• Creates efficient production sequence with less waste.
• Guarantees quality for the customer.
• Maintains safety.
• Prevents equipment damage.
• Achieves better efficiency.
The System which can be easily understood
4/22/2009 @2008 Performing Better & Better, All rights reserved 54/22/2009 @2008 Performing Better & Better, All rights reserved 5
Standardized Work
• Built for and around people and is thefoundation for all
processes. • Safest Most Efficient
Method to do the Process Next Team member in the
process will not have to go through the same growing and learning
challenges
The System enables everyone to find problems
4/22/2009 @2008 Performing Better & Better, All rights reserved 64/22/2009 @2008 Performing Better & Better, All rights reserved 6
Standardized Work
Objective or Purpose• Performing standardized work allows for a clear and visible 'standard'
operation. Deviation from standardized work indicates an abnormality, which is then an opportunity for improvement.
When to Use ItApplicable almost anywhere!
What is It?• Standardized Work is the
most efficient combination of person, machine, and material.
• The three elements of standardized work are:
1) Takt time2) Work sequence
Standardized Work Combination (SWC) ChartStandardized Work Diagram (SWD)Standardized Work Instructions
3) Standardized work-in-process
5S
TPS
JidokaJIT
Communication Problem Solving
Heijunka Standardized Work
Kaizen(Leveling & Sequencing)
Goal:•Highest quality•Lowest cost•Shortest lead time
4/22/2009 @2008 Performing Better & Better, All rights reserved 74/22/2009 @2008 Performing Better & Better, All rights reserved 7
Focuses on experienced employees
Comes from the office/ factory
Builds teamwork vs. individual incentive
Provides game plan (playbook)
Standard Work
Documents the current best process
Defines expectations in quality, safety and Takt time
Used as training aid (for new employees)
4/22/2009 @2008 Performing Better & Better, All rights reserved 84/22/2009 @2008 Performing Better & Better, All rights reserved 8People using standardized processes get defined results
People
Defined Results
StandardizedWork
People using different processes get different results
Process 1
Process 3Process 2
TraditionalMethod
To Reduce Variation In The Process
People
StandardizedProcess
4/22/2009 @2008 Performing Better & Better, All rights reserved 94/22/2009 @2008 Performing Better & Better, All rights reserved 9
TIME
IMP
RO
VEM
EN
T
KK
K
K
K
K
K
K
K
S
S
SS
K = KaizenS = Standardized Work
Standardization Sustains Results
4/22/2009 @2008 Performing Better & Better, All rights reserved 104/22/2009 @2008 Performing Better & Better, All rights reserved 10
Work Standards:• Set by experts to determine fair
pay and performance standards• Used to motivate people to desired
output levels
Problems:• Competitive game • Anxiety/animosity• Kid ourselves – “one best way”
Standardized Work vs. Work Standards- Not The Same!
4/22/2009 @2008 Performing Better & Better, All rights reserved 114/22/2009 @2008 Performing Better & Better, All rights reserved 11
Elements of Standardized Work
1. Takt Time – Set the pace to meet the customer demand
2. Work Sequence – Everyone performs the work using a standard method
Standardized Work Combination (SWC) ChartStandardized Work Diagram (SWD)Standardized Work Instructions
3. Standardized Work-In-Process Establish the minimum running stock to be kept at the work stations
Consistent performance of a task by all employees in same job classification, with respect to:
Establish and Document Flow
Establish and Document Inventory Standards
4/22/2009 @2008 Performing Better & Better, All rights reserved 124/22/2009 @2008 Performing Better & Better, All rights reserved 12
Standardized Work In Process (SWIP)
Work Sequence
Takt Time
• Determine Takt Time
• Establish Flow
First Element Of Standardized Work
4/22/2009 @2008 Performing Better & Better, All rights reserved 134/22/2009 @2008 Performing Better & Better, All rights reserved 13
Available Time
Daily DemandTakt Time
Takt Definition
From the German word Taktzeit (clock cycle), Takt refers to the measure, meter or beat of movement.
For the Lean enterprise, Takt time is the pace at which items need to be produced in order to satisfy customer demand. It is the heartbeat of the market and the drumbeat of production.
=
4/22/2009 @2008 Performing Better & Better, All rights reserved 154/22/2009 @2008 Performing Better & Better, All rights reserved 15
Takt time is…• The heartbeat of the
process• The time interval at which
a finished product MUST come off the line to meet the customer’s needs
• The voice of the customer
Cycle time is…• The time between two
consecutive parts produced in a particular process
• The voice of the process
Takt Time vs Cycle Time
Takt time and Cycle Time are NOT the same. TT is driven by the customer; CT by the process. Also, CT is not the same as Processing Time. For example, we might have multiple parts processed simultaneously – e.g. painting process -; Each enters and exits the process every “x” seconds while the Processing Time for each part is longer.
4/22/2009 @2008 Performing Better & Better, All rights reserved 164/22/2009 @2008 Performing Better & Better, All rights reserved 16
Customer Demand160 trucks/week = 32 trucks/day
Time Available (per shift)510 min (8.5 hr x 60 min/hr)
- 30 min (Lunch)- 20 min (2 - 10 min breaks)- 15 min (Ergonomic stretch)- 15 min (5S)
430 min/day
430 min/dayTakt Time = = 13.4 min/truck
32 trucks/day
Takt Time Determination
Available Time
Customer DemandTakt Time =
Time
Unit=
4/22/2009 @2008 Performing Better & Better, All rights reserved 174/22/2009 @2008 Performing Better & Better, All rights reserved 17
Standardized Work In Process (SWIP)
Takt Time
Work Sequence
A. Standard Work Combination (SWC) Chart
B. Standard Work Diagram
C. Standard Work Instructions
Documentation of the Standard Process
Second Element Of Standardized Work
4/22/2009 @2008 Performing Better & Better, All rights reserved 184/22/2009 @2008 Performing Better & Better, All rights reserved 18
• Establishes a routine for work to be performed
• Establishes a relationshipbetween employee and equipment
• Provides a basis for improvement by making waste visual
A. Standardized Work Combination (SWC) Charts
4/22/2009 @2008 Performing Better & Better, All rights reserved 194/22/2009 @2008 Performing Better & Better, All rights reserved 19
Time (Min) 1 2 3 4 5 6 7 8 9 1
011
2
3
1
5
2 Min
3 Min
1 Min
5 Minutes
Operator WaitsAnswer call & find record in computer
Type Updates
End Call
Wait for confirmation of updated record
Waste of WaitingCall Center Operator Call Time = 6 Minutes
Total Process Cycle Time = 11 Minutes
• What is the Phone Operator Work Time?• What is the Total Cycle Time?• Where is the Waste?
Idle TimeHuman Time
Computer Time
TaktTime
Example – Call Center Process
4/22/2009 @2008 Performing Better & Better, All rights reserved 204/22/2009 @2008 Performing Better & Better, All rights reserved 20
The Standard Work Diagram Illustrates How the Cell is Operated
Takt Time =181 Sec
B. The Standardized Work Diagram
4/22/2009 @2008 Performing Better & Better, All rights reserved 214/22/2009 @2008 Performing Better & Better, All rights reserved 21
Drill
Insp & Label Mill
1
1
1
Standard Work in Process (SWIP)
Safety Device
2
3 1Operation Number
100
100
100 Raw Stock
Operator Flow
Quality Check or Poka Yoke
100
100
100
Finished Goods Takt Time 181 Sec
Material Flow
How To Read The Standard Work Diagram
4/22/2009 @2008 Performing Better & Better, All rights reserved 224/22/2009 @2008 Performing Better & Better, All rights reserved 22
C. Standardized Work Instructions
Objective or Purpose
• The best, easiest, safest way you know today to perform the work
• Only one standard at a time• Documentation of know-how• Objective, simple, conspicuous• Consistent with quality, delivery,
cost requirements• Based on the skilled employee
When to Use ItImplementation of all formal processes.
What is It?
Simple combination of text and graphics creating a step by step work reference on how to do our job – the same way – the right way every time.
4/22/2009 @2008 Performing Better & Better, All rights reserved 234/22/2009 @2008 Performing Better & Better, All rights reserved 23
Area Reserved for Photos and Illustrations
Operation Step No. per SWC Chart
Description of Element Based on SWC Chart
Time & Frequency of Elements
Safety Information
C. Standard Work Instructions
Toyota Format
4/22/2009 @2008 Performing Better & Better, All rights reserved 244/22/2009 @2008 Performing Better & Better, All rights reserved 24
Standard Work InstructionsStandardized Work Instructions
TPM
Page 1: Generalized Instructions for Operation
Subsequent Tabs for Specific Instructions for Operation like Inspection
Specifics
First Page for General Instructions… Back-up Tabs for More Specific Instructions
STANDARDIZED WORKSHEET DEPARTMENT \ LINE \ SECTION Takt TIME
WORKSHEET #:REVISION: PROCESS
COACH:
MAINTENANCE: PART NAME
ENGINEER:SAFETY: PART #
TIME ELEMENTS (Sec)WORK SEQUENCE LAYOUT STEP # WORK STEPS FREQ. MAN. AUTO WALK POSSIBLE
1 Inspect Light Curtain at beginning and mid shift 22 Unload Part and aside it to shelf WIP 1 5 Burn3 Get & Load Part to mold 1 10 Burn4 Cycle Start machine by pressing 1 palm switch 1 55 Machine Mold Cycle A 1 1206 Walk to Trim 1 57 Trim Part to Trim Specifications # xyz 1 358 Inspect to Trim and Mold Standard XYZ & aside 1 10 Cuts
1
Change Blades 2 x per shift
TOTALS
LOCK(S)
CC T
PM
IN-PROCESSSTOCK
SAFETYERGONOMICS
CRITICALCHARACTERISTICS
QUALITYCHECK
QUICKCHANGEOVER
VISUALFACTORY
TOTAL PROD.MAINTENANCE
ZERODEFECTS
TPMWIP = 1 Piece
C/C
TPM
WIP = 1 Piece
Picture of Trim
Show Detail Trim or Quality Standards
Standardized Work Instructions
4/22/2009 @2008 Performing Better & Better, All rights reserved 254/22/2009 @2008 Performing Better & Better, All rights reserved 25
IN-PROCESS
STOCK
SAFETYERGONOMICS
CRITICAL
CHARACTERISTIC CHECK
QUICKCHANGEOVER
VISUALFACTORY
TOTAL PROD.
MAINTENANCE
ZERO
DEFECTS
QUALITY
C
C TP
M
Standardized Work Instructions – Toyota Format (Work Sequence Symbols)
Special Material(lube, computer program, etc.)
Safety hazards, checks & notations
Customer critical process, settings: Process Control
Quality checks against a specific standard or SPC
Single Minute Exchange of Die (SMED)
Visual instruc.: Place container Kanbancard, Taktboard
TPM Instruc. or elements,
Mistake-Proofing in place
4/22/2009 @2008 Performing Better & Better, All rights reserved 264/22/2009 @2008 Performing Better & Better, All rights reserved 26
Standard Method Sheet Example
4/22/2009 @2008 Performing Better & Better, All rights reserved 274/22/2009 @2008 Performing Better & Better, All rights reserved 27
Takt Time
Work Sequence
Standardized Work In Process (SWIP)
• Standardized Work In Process (SWIP)
Third Element Of Standardized Work
4/22/2009 @2008 Performing Better & Better, All rights reserved 284/22/2009 @2008 Performing Better & Better, All rights reserved 28
Obtain Documentation
Review Credit
Prepare Loan Application
1
1
1
2
3 1
111111
The inventory level required at each workstation to support continuous flow in loan approval process.
SWIP
Standardized Work-in-Process
4/22/2009 @2008 Performing Better & Better, All rights reserved 294/22/2009 @2008 Performing Better & Better, All rights reserved 29
Total Processing TimeTakt TimeSWIP Goal =
Standardized Work-in-Process Calculation
Processing Time = Manual + Automatic
4/22/2009 @2008 Performing Better & Better, All rights reserved 30
Operation #Auto & Manual
1 502 503 404 205 306 3007 108 80
580 / 100 = 6 SWIP
580
Takt Time = 100 minutes
Calculating SWIP
4/22/2009 @2008 Performing Better & Better, All rights reserved 314/22/2009 @2008 Performing Better & Better, All rights reserved 31
Operation #Auto & Manual SWIP
1 502 503 404 205 306 3007 108 80
Calculating SWIP (con’t)
4/22/2009 @2008 Performing Better & Better, All rights reserved 324/22/2009 @2008 Performing Better & Better, All rights reserved 32
3rd Level –SOP Located at Cell to Support Instructions1st Level - Standardized Work
Diagram Posted At Cell Level. Shows How Cell is Run, Takt, Pull, Flow.
Std Work Instructions
2nd Level -Standardized Work Posted at Activity Level
Three Levels of Standardized Work
•Takt Time = 181 Secs
4/22/2009 @2008 Performing Better & Better, All rights reserved 334/22/2009 @2008 Performing Better & Better, All rights reserved 33
Who Establishes Standardized Work?
Team Members &Team Leaders
It is the team in charge of the area that determines the Standardized
Work and improves it.
4/22/2009 @2008 Performing Better & Better, All rights reserved 344/22/2009 @2008 Performing Better & Better, All rights reserved 34
Results of Following Standardized work
Constant Cycle Time
Safe Workplace
Equipment Damage Minimized
Quality Requirements Achieved
Balancing the Lineand
Creating Continuous Flow
4/22/2009 @2008 Performing Better & Better, All rights reserved 364/22/2009 @2008 Performing Better & Better, All rights reserved 36
Load Chart
Objective or Purpose
• Break the Total Work Content (TWC) into manageable pieces that can be assigned in a way that meets customer need.
• Optimize task assignments within a cell based on resource availability.
When to Use ItDevelopment or improvement of a product/process cell.
What is It?A method of scheduling, associating and assigning tasks to optimize the cell and meet Takt time.
4/22/2009 @2008 Performing Better & Better, All rights reserved 374/22/2009 @2008 Performing Better & Better, All rights reserved 37
0102030405060708090
100
Bill Mary Tom
95 m T/T
Operators
Tim
e
OP 1
OP 2OP 4
OP 3OP 5 OP 6
OP 7
OP 8
OP 9
1. Rough Turn2. Finish Turn3. Deburr
4. Mill Slots
5. Deburr
6. Drill Holes 9. Inspect
8. Wash
7. Grind
0102030405060708090
100
Bill Mary Tom
95 m T/T
Operators
Tim
e
OP 1
OP 2OP 4
OP 3OP 5 OP 6
OP 7
OP 8
OP 9
1. Rough Turn2. Finish Turn3. Deburr
4. Mill Slots
5. Deburr
6. Drill Holes 9. Inspect
8. Wash
7. Grind
Line Balancing Example
Before balancing:9 OperatorsSignificant difference in workloads
0102030405060708090
100 95 m T/T
Operators
Tim
e
OP1
OP2
OP4
OP3
OP5
OP6
OP7
OP8
OP9
Rough
Turn
Finish
TurnDeburr
Mill
SlotsDeburr
Drill
HolesInspectWashGrind
0102030405060708090
100 95 m T/T
OP1
OP1
OP2
OP2
OP4
OP4
OP3
OP3
OP5
OP5
OP6
OP6
OP7
OP7
OP8
OP8
OP9
OP9
Rough
Turn
Rough
Turn
Finish
Turn
Finish
TurnDeburr
Mill
Slots
Mill
SlotsDeburr
Drill
Holes
Drill
HolesInspectWashGrind
After balancing:• 3 Operators• Workloads closely matched
http://www.reuters.com/article/domesticNews/idUSTRE51G0WE20090217
http://www.detnews.com/apps/pbcs.dll/article?AID=/20090124/AUTO01/901240355
http://www.mysanantonio.com/news/top_news/Toyota_plant_cuts_hours_freezes_pay.html
4/22/2009 @2008 Performing Better & Better, All rights reserved 384/22/2009 @2008 Performing Better & Better, All rights reserved 38
What if CT is greater than TT… is this an issue?
What if CT is less than TT?
Questions
4/22/2009 @2008 Performing Better & Better, All rights reserved 394/22/2009 @2008 Performing Better & Better, All rights reserved 39
Identifying Constraints
Throughput is the rate at which you produce your desired output.It is one of your critical measurements.
Throughput should not exceed customer demand rate. This is controlled through Takt time.
The constraint (bottleneck) is the process step with the highest cycle time and is greater than the required Takt time for the desired customer output.Constraints can be identified by identifying processes with: longest cycle times, late parts, backlogs, excess WIP, defects, etc.There is only ONE BOTTLENECK at a time.
You must maximize the output of your constraint.
4/22/2009 @2008 Performing Better & Better, All rights reserved 404/22/2009 @2008 Performing Better & Better, All rights reserved 40
The Detroit Metropolitan Airport
You fly from Frankfurt to DetroitYou rush to get off the planeYou rush to get to passport controlYou rush to the shortest line in passport controlYou rush through passport controlYou rush to get to baggage claimYou wait 20 minutes for your luggage
You are only as fast as your fastest “constraint.”
4/22/2009 @2008 Performing Better & Better, All rights reserved 414/22/2009 @2008 Performing Better & Better, All rights reserved 41
Payment GoesOut
Step F Step E
Invoice Comes
In
Step A Step B
Step C
Step D
CT=21 CT=36
CT=33
CT=15
CT=23CT=17
Required Takt Time = 32
ExampleWhere is the greatest constraint for the accounts payable process?
4/22/2009 @2008 Performing Better & Better, All rights reserved 424/22/2009 @2008 Performing Better & Better, All rights reserved 42
Payment GoesOut
Step F Step E
Invoice Comes
In
Step A Step B
Step C
Step D
CT=21 CT=36
CT=33
CT=15
CT=23CT=17
Required Takt Time = 32
Example
Total Process Time = 145m
Where is the greatest constraint for the accounts payable process?
4/22/2009 @2008 Performing Better & Better, All rights reserved 434/22/2009 @2008 Performing Better & Better, All rights reserved 43
A B C D E F0
10
20
30
40Min.
Takt Time = 32 Min.
Cycle Time
Questions to Ask:• Is this line
balanced or unbalanced?
• What methods could we use to balance this line?
• Where is the bottleneck?
Load Chart Example
Person/OperationGoal = Balance the Line…Cycle Time < Takt
4/22/2009 @2008 Performing Better & Better, All rights reserved 444/22/2009 @2008 Performing Better & Better, All rights reserved 44
Person/OperationA B C D E F
0
10
20
30
40Min.
First Constraint
Second Constraint
Cycle time includes any setup time at the operation.
Takt Time = 32 Min.
Goal: Cycle Time < Takt Time
4/22/2009 @2008 Performing Better & Better, All rights reserved 454/22/2009 @2008 Performing Better & Better, All rights reserved 45
Once the constraint has been identified• Reduce your constraint time by applying Lean Six Sigma
tools such as:
- Standardized Work, SMED, TPM, Kanbans, Line Balancing, 5S, 7 Wastes, etc.
• Continue to improve until constraint time is below Takttime.
• If constraint time cannot reach desired Takt time:
– Apply buffer inventory in front of process
– Add additional equipment
– Add additional people
You must maximize the output of your constraint!!!
Constraint Management
4/22/2009 @2008 Performing Better & Better, All rights reserved 464/22/2009 @2008 Performing Better & Better, All rights reserved 46
Items in a process that may not be changed or moved such as:Large machineryComputer System
Always challenge the idea that it’s really a monument.If it cannot be changed, be creative about ways to work around the monument.Over time your project improvements can become monuments. Six months from now process owners may not want to make further improvements.
Be aware of these and don’t let them stop the progress of your effort.
Constraint ManagementBoulders / Monuments
4/22/2009 @2008 Performing Better & Better, All rights reserved 474/22/2009 @2008 Performing Better & Better, All rights reserved 47
Completed Load ChartTakt Time vs. Cycle TimeRebalance Work Load
A B C D E F0
5
10
15
20
25
30
35Min
Person/Operation
Takt Time = 32 Min.
Note: The ideal situation is to put the least loaded station/position at the end of the line and “pull” the material through.
This provides for continuous cycle time improvement to eventually eliminate the final position and use that person for other efforts.
Line Balancing
Balanced Line Cycle Time < Takt Time
Staffing the Line
4/22/2009 @2008 Performing Better & Better, All rights reserved 494/22/2009 @2008 Performing Better & Better, All rights reserved 49
( 3 + 3 ) + ( 10 ) + ( 5 ) =21
People Required = 21
10.5= 2
0.0
2.0
4.0
6.0
8.0
10.0
12.0
LATHE # 1 LATHE # 2 DRILL D-BURR
MINUTES
SETUP LOAD MACHINE RUN
MACHINE RUN TIME ( no people required )
ALL REQUIRE A PERSON TO PERFORM
t/t = 10. 5 min
Total Manual Cycle Time
Takt Time
# of Employees Required
=
Staffing Requirements Example
Machine run time is excluded from the calculation.
MANUAL PROCESSING
4/22/2009 @2008 Performing Better & Better, All rights reserved 504/22/2009 @2008 Performing Better & Better, All rights reserved 50
Product Process Flow Analysis
4/22/2009 @2008 Performing Better & Better, All rights reserved 514/22/2009 @2008 Performing Better & Better, All rights reserved 51
Another one of George’s “End-of-the-Talk” Questions…
4/22/2009 @2008 Performing Better & Better, All rights reserved 524/22/2009 @2008 Performing Better & Better, All rights reserved 52
Previous Talks’ Qs
4/22/2009 @2008 Performing Better & Better, All rights reserved 534/22/2009 @2008 Performing Better & Better, All rights reserved 53
Isn’t THIS, in fact, The Challenge?
4/22/2009 @2008 Performing Better & Better, All rights reserved 544/22/2009 @2008 Performing Better & Better, All rights reserved 54
So, we talked – briefly! - about:
Standardized Work (SW)Elements of SW
Takt Time (TT)Work Sequence
Standardized Work Combination (SWC) ChartStandardized Work Diagram (SWD)Standardized Work Instructions (SWI)
Standardized Work in Process (SWIP)
Balancing the LineStaffing the Line
Q&A … if any!
4/22/2009 @2008 Performing Better & Better, All rights reserved 564/22/2009 @2008 Performing Better & Better, All rights reserved 56
http://www.youtube.com/watch?v=1SNa-jTRSY4http://www.youtube.com/watch?v=U0_ktNqbQyU&feature=relatedhttp://www.msnbc.msn.com/id/21134540/vp/16639525#16639525