Standard Protective Coatings

60
This document is protected by copyright. No part of this document may be reproduced, adapted, transmitted, or stored in any form by any process (electronic or otherwise) without the specific written consent of Woodside. All rights are reserved. Controlled Ref No. W1000SM002 DRIMS No. 3205381 Revision : 1 Page I DRIMS Classification/No. Uncontrolled when printed, unless stamped in Red to the contrary. CONTROLLED DOCUMENT STANDARD – PROTECTIVE COATINGS Document Type: PROCEDURES / STANDARDS Controlled Ref No: W1000SM002 DRIMS Classification: COR/INF/085/v01 Revision: 1 REVISION HISTORY Revision Description WEL Approval Status Date 0 Complete rewrite of WEL’s protective coating standard. Document to supersede W9000SM001. Issued for PAN WEL use. Engineering Services Manager Jan 2007 1 Revised to align with WEL Project group requirements Engineering Services Manager Jul 2007 Operations / Projects Use Only Key TAG No’s: Operating Facility System: Operating Facility Sub System: Operating Facility Area: Operating Facility Unit: Engineering Data Classification: Project: Function: System: Sub System: RELEASE STATEMENT (Check one box only) REVIEW STATUS (Check one box only) PREPARED (Check one box only) Unclassified (Shared without Restrictions) Review Period 1 Year By WEL Restricted (Freely Shared within Woodside and Associated Companies) Review Period 3 Years For WEL Under PO/Contract No: Confidential (Shared With Selected Personnel) Review Not Required Most Confidential (Strict Need-to-Know Basis)

Transcript of Standard Protective Coatings

Page 1: Standard Protective Coatings

This document is protected by copyright. No part of this document may be reproduced, adapted, transmitted, or stored in any form by any process (electronic or otherwise) without the specific written consent of Woodside. All rights are reserved.

Controlled Ref No. W1000SM002 DRIMS No. 3205381 Revision : 1 Page I

DRIMS Classification/No. Uncontrolled when printed, unless stamped in Red to the contrary.

CONTROLLED DOCUMENT

STANDARD – PROTECTIVE COATINGS

Document Type:

PROCEDURES / STANDARDS

Controlled Ref No: W1000SM002 DRIMS Classification: COR/INF/085/v01 Revision: 1

REVISION HISTORY

Revision Description WEL Approval Status Date

0 Complete rewrite of WEL’s protective coating standard. Document to supersede W9000SM001. Issued for PAN WEL use.

Engineering Services Manager

Jan 2007

1 Revised to align with WEL Project group requirements Engineering Services Manager

Jul 2007

Operations / Projects Use Only Key TAG No’s:

Operating Facility System: Operating Facility Sub System:

Operating Facility Area: Operating Facility Unit:

Engineering Data Classification: Project:

Function: System: Sub System:

RELEASE STATEMENT (Check one box only) REVIEW STATUS

(Check one box only) PREPARED

(Check one box only)

Unclassified (Shared without Restrictions)

Review Period 1 Year

By WEL

Restricted (Freely Shared within Woodside and Associated Companies)

Review Period 3 Years

For WEL Under PO/Contract No:

Confidential (Shared With Selected Personnel)

Review Not Required

Most Confidential (Strict Need-to-Know Basis)

Page 2: Standard Protective Coatings
Page 3: Standard Protective Coatings

This document is protected by copyright. No part of this document may be reproduced, adapted, transmitted, or stored in any form by any process (electronic or otherwise) without the specific written consent of Woodside. All rights are reserved.

Controlled Ref No. W1000SM002 DRIMS No. 3205381 Revision : 1 Page 3

DRIMS Classification/No. Uncontrolled when printed, unless stamped in Red to the contrary.

PREFACE Woodside Energy Ltd. (WEL) has developed a suite of Engineering and Technical Standards and Guidelines. It is intended that these reflect the most suitable engineering practices for use on all new WEL facilities as well as the modification of existing facilities. The application of the Standards is mandatory. The application of Guidelines is to support the implementation of the Standards. They are considered best practice, but are not mandatory. The Standards are based on the experience acquired by WEL personnel and contractors during WEL’s involvement with the design, construction, operation and maintenance of WEL processing units and facilities. Where appropriate, the Standards are based on or make reference to national and international standards and codes of practice. The objective of this publication is to ensure the overall integrity of engineering design and to achieve maximum technical and economic benefits through the standardisation of engineering and technical practices. The use by WEL contractors or manufacturers/suppliers of the Engineering and Technical Standards contained in this publication does not relieve them of any responsibility whatsoever for the quality of design, materials and workmanship that they have been engaged to provide. Where the standards to be used for a certain application are not provided for in this publication, WEL expects that the standards that are used will achieve the same level of integrity as reflected in this publication. If WEL contractors or manufacturers/suppliers have any doubt as to the relevant standard to use, then they must consult WEL, however they will remain responsible at all times for the use of the most appropriate standard. Specific requirements may be added as an addendum to these Standards and Guidelines for various projects. Project specific requirements must not depart from the requirements of the Engineering and Technical Standards contained in this publication. Where changes or additions to these Standards are required, they must be raised as a deviation and presented to the WEL Technical Authority for consideration. WEL grants the right to use these Standards and Guidelines to WEL’s consultants, contractors and suppliers who are contractually authorised to do so and to any tier of contractor to its consultants, contractors and suppliers who are contractually required to comply with them. DISCLAIMER WEL and its joint venture partners disclaim any liability of whatsoever nature for any damage (including injury or death) suffered by any company or person whomsoever as a result of or in connection with the use, application or implementation of any standard, combination of standards or any part thereof contained in this publication.

Page 4: Standard Protective Coatings

This document is protected by copyright. No part of this document may be reproduced, adapted, transmitted, or stored in any form by any process (electronic or otherwise) without the specific written consent of Woodside. All rights are reserved.

Controlled Ref No. W1000SM002 DRIMS No. 3205381 Revision : 1 Page 4

DRIMS Classification/No. Uncontrolled when printed, unless stamped in Red to the contrary.

1 INTRODUCTION ....................................................................................................... 6

1.1 SCOPE ............................................................................................................................ 6 1.2 EXCLUSIONS ................................................................................................................. 7 1.3 REGULATORY CONSIDERATIONS .............................................................................. 7 1.4 DEFINITIONS.................................................................................................................. 8 1.5 ABBREVIATIONS............................................................................................................ 8

2 STANDARD .............................................................................................................. 9 2.1 WARRANTY .................................................................................................................... 9 2.2 REVISIONS TO STANDARD .......................................................................................... 9 2.3 DEVIATION FROM STANDARD................................................................................... 10

3 PAINTING CONTRACTOR RESPONSIBILITY ...................................................... 10 3.1 GENERAL ..................................................................................................................... 10 3.2 HEALTH, SAFETY, ENVIRONMENT & QUALITY ........................................................ 10

3.2.1 Personnel Qualifications........................................................................................... 10 3.2.2 Pre-qualification of Products .................................................................................... 13 3.2.3 Qualification Records ............................................................................................... 14 3.2.4 Coating Manufacturer............................................................................................... 14 3.2.5 Coordination Meetings ............................................................................................. 14 3.2.6 Compatibility of Fabrication and Construction Site Conditions................................. 14 3.2.7 Handling of Chemicals ............................................................................................. 15 3.2.8 Pressure Equipment................................................................................................. 15 3.2.9 Earthing .................................................................................................................... 15 3.2.10 Breathing Apparatus ............................................................................................. 15 3.2.11 Access................................................................................................................... 15 3.2.12 Work Permits......................................................................................................... 16 3.2.13 Selection of Coatings and Application Methods.................................................... 16

4 SURFACE PREPARATION .................................................................................... 17 4.1 GENERAL ..................................................................................................................... 17 4.2 PRETREATMENT ......................................................................................................... 17 4.3 ABRASIVE BLAST CLEANING..................................................................................... 18

4.3.1 Grades of Surface Finish.......................................................................................... 18 4.3.2 Dry Abrasive Blast Cleaning..................................................................................... 18 4.3.3 Wet Abrasive Blast Cleaning.................................................................................... 19

4.4 ULTRA HIGH PRESSURE WATER CLEANING (MAINTENANCE ONLY) .................. 19 4.5 OTHER CLEANING METHODS FOR CARBON STEEL SURFACES.......................... 20 4.6 GALVANISED STEEL SURFACES............................................................................... 20 4.7 ALUMINIUM & STAINLESS STEEL SURFACES ......................................................... 20 4.8 CONCRETE SURFACES.............................................................................................. 20

5 COATING APPLICATION....................................................................................... 22 5.1 INTRODUCTION ........................................................................................................... 22 5.2 APPLICATION - PROCEDURES CONSTRAINTS AND QUALITY CONTROL............ 22

5.2.1 Ambient Conditions .................................................................................................. 23 5.2.2 Mixing and Thinning ................................................................................................. 24 5.2.3 Compatibility With Existing Coating Systems........................................................... 24 5.2.4 Over Coating ............................................................................................................ 24 5.2.5 Handling ................................................................................................................... 24

5.3 APPLICATION METHODS............................................................................................ 25 5.3.1 Repair/Reinstatement............................................................................................... 26

5.4 COATING OF FLANGE BOLTS AND NUTS................................................................. 27

Page 5: Standard Protective Coatings

This document is protected by copyright. No part of this document may be reproduced, adapted, transmitted, or stored in any form by any process (electronic or otherwise) without the specific written consent of Woodside. All rights are reserved.

Controlled Ref No. W1000SM002 DRIMS No. 3205381 Revision : 1 Page 5

DRIMS Classification/No. Uncontrolled when printed, unless stamped in Red to the contrary.

6 INSPECTION AND TESTING ................................................................................. 28

6.1 GENERAL ..................................................................................................................... 28 6.1.1 Rejected Work and Equipment................................................................................. 28 6.1.2 Quality Plan .............................................................................................................. 28 6.1.3 Reporting.................................................................................................................. 29 6.1.4 Inspection Personnel and Equipment....................................................................... 29

6.2 SURFACE PREPARATION INSPECTION.................................................................... 31 6.2.1 Surface Profile.......................................................................................................... 31 6.2.2 Surface Cleanliness ................................................................................................. 31 6.2.3 Ambient Conditions .................................................................................................. 31

6.3 COATING APPLICATION INSPECTION & TESTING................................................... 31 6.3.1 Dew Point, Air Humidity and Substrate Temperature............................................... 31 6.3.2 General Coating Appearance................................................................................... 31 6.3.3 Wet Film Thickness (WFT)....................................................................................... 32 6.3.4 Dry Film Thickness (DFT) ........................................................................................ 32 6.3.5 Primer Cure .............................................................................................................. 33 6.3.6 Detection of Pinholes ............................................................................................... 33 6.3.7 Adhesion .................................................................................................................. 33 6.3.8 Antiskid System for Helidecks .................................................................................. 34 6.3.9 Final Inspection ........................................................................................................ 34

6.4 COMMISSIONING / HANDOVER ................................................................................. 34 7 CONTRACTOR RECORDS .................................................................................... 36

7.1 RESPONSIBILITIES...................................................................................................... 36 7.2 SAFETY......................................................................................................................... 36

8 COATING SYSTEMS FOR NEW CONSTRUCTION AND MODIFICATIONS ........ 37 8.1 COATING SYSTEM DESIGNATION............................................................................. 37

8.1.1 Base Material (first 2 digits)...................................................................................... 37 8.1.2 System Code (second 2 digits) ................................................................................ 37 8.1.3 Application................................................................................................................ 37

8.2 EQUIVALENTS TABLE ................................................................................................. 37 8.3 COATING SYSTEMS FOR NEW CONSTRUCTION AND MODIFICATIONS .............. 40

8.3.1 Carbon and Low alloy Steels – External .................................................................. 40 8.3.2 Stainless Steels – External....................................................................................... 42 8.3.3 Non-Ferrous Materials - External ............................................................................. 42

8.4 COATING SYSTEMS FOR MAINTENANCE ................................................................ 43 8.4.1 Carbon and Low alloy Steels – External .................................................................. 43 8.4.2 Stainless Steels – External....................................................................................... 45 8.4.3 Non-Ferrous Materials – External ............................................................................ 45

9 PRODUCT CODE AND APPROVAL LIST AT DECEMBER 2006 ......................... 46 10 OFFSHORE COLOUR CODE................................................................................. 48

10.1 OFFSHORE – TYPICAL STRUCTURES .................................................................... 48 10.2 OFFSHORE – HVAC DUCTING ................................................................................. 49 10.3 OFFSHORE – MISCELLANEOUS ITEMS .................................................................. 49 10.4 OFFSHORE – BULK PRODUCT LOADING HOSE ENDS & MANIFOLD .................. 50 10.5 OFFSHORE – PIPING................................................................................................. 50 10.6 OFFSHORE – EQUIPMENT ....................................................................................... 53

11 ONSHORE COLOUR CODES ................................................................................ 55 12 REFERENCES ........................................................................................................ 56 13 APPENDICES ......................................................................................................... 59

APPENDIX 1 – SUPERCEDED HISTORICAL STANDARDS.................................................. 60

Page 6: Standard Protective Coatings

This document is protected by copyright. No part of this document may be reproduced, adapted, transmitted, or stored in any form by any process (electronic or otherwise) without the specific written consent of Woodside. All rights are reserved.

Controlled Ref No. W1000SM002 DRIMS No. 3205381 Revision : 1 Page 6

DRIMS Classification/No. Uncontrolled when printed, unless stamped in Red to the contrary.

1 INTRODUCTION 1.1 SCOPE

This standard covers organic/inorganic and thermal spray protective coatings as well as passive fire protection of all Woodside equipment and structures for both new construction and maintenance situations for both offshore and onshore. It includes the requirements with respect to protection against corrosion of both ferrous and non-ferrous materials. It covers facilities such as fixed leg production platforms, floating production, storage and offloading (FPSO) facilities and facilities on the coastline such as jetties, quays and onshore plant. This document supersedes those historical standards listed in Appendix 1 including previous versions of W9000SM001. The standard defines the minimum acceptable surface preparation, coating application and quality assurance and control for the application of surface coatings and is applicable for new construction, modifications and maintenance of WEL facilities. All paint and coating systems to be used shall meet the qualification requirements and the minimum coating system requirements as specified in this document. It is the responsibility of the Principal to carry out the review and acceptance of the project and quality plan in order to ensure that the painting work is executed in accordance with this specification To achieve long term service life of the protective coating system, it is essential that full attention shall be given to:

• Using qualified and fully tested coating systems

• The quality of surface preparation

• Application of the coating system.

• Quality assurance, quality control and the professional skill of painters are essential for this process.

For installations with a design life of 25 years or more, unmanned offshore installations and parts difficult to access for maintenance after installation, special ‘life time’ coatings such as thermal sprayed aluminium shall be considered in consultation with the Materials, Inspection & Corrosion Engineering discipline. TSA is generally recommended for primary and secondary structural steel. The application of TSA to tertiary steel and pressure vessels and piping would be on an as needs basis. For facility design lives less than 20 years conventional 3 coat systems comprising zinc rich primers, high build epoxy second coats and a gloss topcoat are recommended. These coatings are expected to require maintenance programmes commencing within 5 – 7 years of first application and on an on-going basis thereafter through to end of facility life. Topics of a general nature regarding painting and coating such as the supply of labour, equipment, personnel safety gear or the use of sub-contractors have not been included in this document. They should be included under the General Terms and Conditions of a contract.

Page 7: Standard Protective Coatings

This document is protected by copyright. No part of this document may be reproduced, adapted, transmitted, or stored in any form by any process (electronic or otherwise) without the specific written consent of Woodside. All rights are reserved.

Controlled Ref No. W1000SM002 DRIMS No. 3205381 Revision : 1 Page 7

DRIMS Classification/No. Uncontrolled when printed, unless stamped in Red to the contrary.

The standard defines minimum application parameters and procedures for each specification. It is considered that specialist applicators and the paint supplier are familiar with these requirements. The surface preparation standards and coating film thickness presented are the minimum requirements acceptable to Woodside Energy Ltd. Woodside and other users recommend the systems and applicable coating products as detailed in Sections 8, 9 & 10 on the basis of laboratory trials and many years of in-service experience. They have provided cost effective corrosion protection. Alternative systems are permitted through the deviation process.

NOTE: Many coating systems require time to cure before being available for service. This period should be recognised when preparing delivery schedules.

1.2 EXCLUSIONS This specification is not applicable to:

• Subsea pipelines

• Subsea structures (wellheads, manifolds, PLEMs etc)

• Risers of offshore pipelines being coated with a special coating (e.g. Monel or Cu impregnated heat cured chloroprene rubber) except those parts of the riser above the special riser coating

• Temporary construction items for which only a zinc rich primer is to be applied

• Internal coatings of tubing, drill pipe or pipelines (including flow coatings)

• Fusion bonded powder coating

• Equipment and components with a service temperature below minus 170 oC and over 450 oC.

• Galvanised items except handrails and other items specifically specified to be painted

• Valve stems, flange faces and machined contact surfaces

• Stainless steel and non ferrous materials specifically specified without coatings

• Anodes

• Architectural finishes

• Rubber and special purpose linings

1.3 REGULATORY CONSIDERATIONS If international and/or regional regulations exist in which some of the requirements may be more stringent than in this Standard an assessment shall be made to determine which of the requirements are the more stringent and which combination of requirements will be acceptable as regards safety, environmental, economic and legal aspects. In all cases the Contractor shall inform the WEL Technical Authority.

Page 8: Standard Protective Coatings

This document is protected by copyright. No part of this document may be reproduced, adapted, transmitted, or stored in any form by any process (electronic or otherwise) without the specific written consent of Woodside. All rights are reserved.

Controlled Ref No. W1000SM002 DRIMS No. 3205381 Revision : 1 Page 8

DRIMS Classification/No. Uncontrolled when printed, unless stamped in Red to the contrary.

1.4 DEFINITIONS The definitions below shall apply:

• The Contractor is the party that carries out all or part of the scoping, budgeting, procurement, access, surface preparation, coating application, quality control and touch ups as identified in this specification. The Principal may undertake all or part of the duties of the contractor.

• The Manufacturer/Supplier is the party that manufactures or supplies equipment, materials, coatings and services to perform the duties specified by the Contractor.

• The Principal is the party that initiates the project and ultimately pays for its design and construction. The Principal will generally specify the technical requirements. The Principal may also include an agent or consultant authorised to act for, and on behalf of, the Principal.

• The words shall / must / will indicate a mandatory requirement. • The word should indicates a recommended course of action. • The words may / can indicate one acceptable course of action. • WEL Technical Authority (TA) in this document refers to the Materials/Inspection/Corrosion

TA. Authority to deviate from these standards is delegated to the custodian(s) indicated on the document details page of this document.

1.5 ABBREVIATIONS WEL Woodside Energy Ltd.

TA Technical Authority

SMS Safety Management System

QCR Quality Control Representative

TSA Thermally Sprayed Aluminium

PFP Passive Fire Protection

QC Quality Control

MTR Manufacturers’ Technical Representative

PPE Personal Protection Equipment

C Celsius

IZS Inorganic Zinc Silicate

DFT Dry Film Thickness

WFT Wet Film Thickness

NDFT Nominal Dry Film Thickness

QA Quality Assurance

FPSO Floating Production Storage Offloading

Page 9: Standard Protective Coatings

This document is protected by copyright. No part of this document may be reproduced, adapted, transmitted, or stored in any form by any process (electronic or otherwise) without the specific written consent of Woodside. All rights are reserved.

Controlled Ref No. W1000SM002 DRIMS No. 3205381 Revision : 1 Page 9

DRIMS Classification/No. Uncontrolled when printed, unless stamped in Red to the contrary.

2 STANDARD 2.1 WARRANTY

Contractors, undertaking painting and/or coating work, which are to be carried out in accordance with this standard, shall guarantee the quality of their coating work. Before any painting or coating work commences, warranty period and coating condition shall be agreed with the Principal. Usually a warranty period of five (5) years or ten (10) years is required for special coatings such as thermally sprayed aluminium. The use of coating systems as described in this standard and approved by the Principal shall not affect the warranties to be agreed by the contract parties involved. If reference areas are proposed and agreed, they shall be in accordance with requirements as specified in ISO 12944-7 Clause 7 and ISO 12944-8 Table 1, No.1.13. Surfaces that have deteriorated beyond the acceptable level of breakdown within the warranty period shall be repaired by the Contractor and he/she shall bear the cost for materials, equipment, labour, onshore transport, onshore lodging and onshore storage necessary for the repair. Only surfaces that have suffered from mechanical damage or chemical spillage as a result of operational activities fall outside this warranty. Initial acceptance of any new coating work by the Principal will not relieve the Contractor of his obligations under this section until the final inspection has been carried out and acceptance of the completed work has been agreed in writing. A final inspection shall be carried by a party to be agreed between the Contractor and the Principal before expiry of the period of a warranty agreement regarding the coating work. In case of a dispute on the condition of the coating work that has been inspected, an agreed independent expertise body shall conduct a review inspection at the Contractor’s cost. Both the Principal and the Contractor shall accept the findings of the inspection by this independent consultant.

2.2 REVISIONS TO STANDARD As paint technology advances paint formulations and application techniques and procedures change. When such changes or other requested modifications affect this standard, single page revisions will be issued to all holders of a controlled copy. (NB Persons using uncontrolled copies should check the current status of their document). A complete review of this standard shall be carried out, as a minimum, at 5 years intervals.

Page 10: Standard Protective Coatings

This document is protected by copyright. No part of this document may be reproduced, adapted, transmitted, or stored in any form by any process (electronic or otherwise) without the specific written consent of Woodside. All rights are reserved.

Controlled Ref No. W1000SM002 DRIMS No. 3205381 Revision : 1 Page 10

DRIMS Classification/No. Uncontrolled when printed, unless stamped in Red to the contrary.

2.3 DEVIATION FROM STANDARD Any change or variation to the requirements within this standard shall be submitted in writing to the TA for review and approval a minimum 2 weeks prior to any work commencing. This shall include substitution of other coating systems or colours not included in the standard or any change or relaxation to surface preparation, coating application, extent of application or quality control.

3 PAINTING CONTRACTOR RESPONSIBILITY 3.1 GENERAL

The Contractor is, in addition to his responsibilities under the general conditions of the contract, responsible for the quality of the work which shall be performed in strict accordance with this standard and all other relevant documents, such as site regulations, safety rules and requirements, product data sheets, referenced standards and codes. The Contractor is fully responsible for all Quality Assurance and Control activities. The Contractor shall schedule a pre-job meeting to ensure that job and quality requirements are fully understood. Attendees should be a representative of the Principal, Contractor’s job superintendent and coating supervisor, the coating inspector and the coating manufacturer’s representative. The Contractor shall submit for any major coating work an appropriate work planning and a quality plan for implementing this coating standard for review to the Principal. Copies of this standard, work planning and of the quality plan shall be made available to the Coating Contractor's representative at the site and she/he shall be familiar with their contents. The obligations of the Contractor are explained in more detail in section 5 Inspection and Testing.

3.2 HEALTH, SAFETY, ENVIRONMENT & QUALITY Work conducted for or on behalf of Woodside shall be carried out in accordance with the Woodside Occupational Health, Safety & Environment requirements and statutory regulations. Contractors, manufacturers and suppliers will make themselves aware of all Woodside requirements specific to the location where the work is being carried out. All coating contractors using this standard shall have a section in their Safety Management System (SMS) devoted to industrial coating applications. This section shall include, but will not be limited to:

3.2.1 Personnel Qualifications 3.2.1.1 Quality Control Representative (QCR)

The Contractor coating process QCR for fabrication contracts shall be a NACE Level II Coating Inspector in possession of a valid certification card to that effect. They shall have extensive experience with the application of the systems being applied by the Contractor and/or subcontractors. This shall be demonstrated in the curriculum vitae or other documentation submitted with the tender.

Page 11: Standard Protective Coatings

This document is protected by copyright. No part of this document may be reproduced, adapted, transmitted, or stored in any form by any process (electronic or otherwise) without the specific written consent of Woodside. All rights are reserved.

Controlled Ref No. W1000SM002 DRIMS No. 3205381 Revision : 1 Page 11

DRIMS Classification/No. Uncontrolled when printed, unless stamped in Red to the contrary.

3.2.1.2 Blasting and Painting Personnel Only professional skilled blasters and painters shall be used. Blasters and painters working on every painting job should be qualified in accordance with a scheme approved by the Principal. A skills matrix shall be submitted to the Principal prior to job commencement to demonstrate a suitable mix of skills exists within the painting crew to meet all the job requirements. An experienced foreman should supervise the blasters and painters. Before commencing any work or awarding a contract the qualifications and experience including any certification should be submitted to the Principal. If not certified, the skill of all blasting and painting personnel shall be verified before commencing any painting or coating work. Each blasters shall blast a representative structural steel part (min. 2m²) using the equipment to be used for the actual surface cleaning. Each painter shall coat a representative structural steel part (min. 2m2) with an agreed coating system including geometrically complex shapes such as pipes, bends, welds etc. The test area shall be coated with all coats of the agreed coating system visible for reference (e.g. primer, primer + intermediate coat and primer, intermediate and topcoat) using the tools and equipment to be used for the actual coating work. The painted test area shall be maintained for the duration of the project as a reference. The Principal shall witness all tests and acceptance criteria as per section 5.3 shall apply. As an alternative to the above, qualification of coating personnel to ASTM D4228 is acceptable. Operators failing to meet the requirements shall not be allowed to carry out any work.

3.2.1.3 Metal Spray Operators All operators shall be familiar with (and preferably qualified to) AWS C2.16 (Guide for Thermal Spray Operator Qualification) TSOQT No. AS-1 or approved equivalent. Prior to commencement of work in accordance with this standard, the operator shall pass the pre-qualification test described in Table 3.1 using arc spray unless it can be documented that he has been working on similar work within the last six months. The results from the qualification test specified below are valid for maximum 6 months without proof of regular coating work.

Table 3.1: Qualification of Metal Spray Operators.

Test Acceptance criteria Visual examination of TSA coating All test panels shall be examined without magnification and with 10X magnification.

As per this section and Section 5

Film thickness 250 ± 50 μm on all specimen surfaces Adhesion (Note 2) ASTM D 4541. All test panels shall be tested with a minimum 3 adhesion tests. Examination of the test specimens shall be conducted after rupture to determine the

No single measurement less than 9.0 MPa. Re-testing is required if the failure occurred at the adhesive/coating interface. If failure occurs in the coating, 3 random tests shall be carried out on the companion structure.

Page 12: Standard Protective Coatings

This document is protected by copyright. No part of this document may be reproduced, adapted, transmitted, or stored in any form by any process (electronic or otherwise) without the specific written consent of Woodside. All rights are reserved.

Controlled Ref No. W1000SM002 DRIMS No. 3205381 Revision : 1 Page 12

DRIMS Classification/No. Uncontrolled when printed, unless stamped in Red to the contrary.

cause of failure. Failure of subsequent testing shall require the structure to be abrasive blasted and re-coated.

Bend Test as per AWS C2.18-93R annex C As per AWS C2.18-93R annex C section C6 acceptance criteria

NOTE 1: General: Test materials shall be of a comparable grade to be used in production. The coating shall be applied in accordance with this document and the proposed procedure. NOTE 2: Specimens for adhesion test: Five specimens for the adhesion test shall be prepared according to the requirements of ISO 4624 using minimum 5 mm thick plates.

Equipment for application of TSA should follow the guidelines given in DIN EN 1395 for the electric arc and flame spraying techniques. A production test panel shall be prepared for each structure, marine equipment or component to be coated. The panel shall be made from a similar substrate material with a surface area of 1 m2. The test panel shall be blast cleaned and TSA at the same time and manner as the companion structure but without sealer or overcoat. TSA shall be 250 ± 50 μm. No single reading less than 180 microns shall be accepted. The test panel shall be permanently marked to identify the test sample, the companion structure and applicator for future reference. Coupons for bend test shall be prepared from carbon steel sheet approx 50 x 150 x 1.25 mm and attached to the test panel or structure during TSA application. Spray 200 – 250 μm thick TSA in crossing passes laying down approx 75 – 100 μm per pass. The coupon shall be bent 180 degrees longitudinally around a 13mm diameter mandrel. After bending the coupon shall be free of significant cracking showing exposed substrate and shall conform to the requirements of bend test coupons described by AWS C2.18-93 annex C. Surface preparation for all TSA shall be abrasive blast clean to Class 3 in accordance with AS 1627.4. This quality of cleanliness may only be achieved with clean, unused abrasive, and may require two stages of abrasive blasting. The final stage being typically with GL-40 hardened steel grit, aluminium oxide or garnet.

• Blasting abrasive shall be such that the surface amplitude or anchor pattern is 75-125 μm for arc spray and > 100 μm for flame spray.

Surface preparation for stainless steel to be TSA coated shall be with aluminium oxide only. Surface cleanliness (dust rating) shall conform to ISO 8502-3 rating 2 or better at the time of application of TSA. Thermally sprayed aluminium (TSA) shall be applied with 50% overlapping passes with not less than two passes at any one point on the surface. The contractor shall ensure that the equipment and applications methods are capable of achieving the specified thickness, which shall be firmly adherent with a smooth, regular surface and free of loosely adherent particles.

• This system is subject to test plate adhesion testing as above.

• The second coat shall be applied within two hours of application of the TSA.

Page 13: Standard Protective Coatings

This document is protected by copyright. No part of this document may be reproduced, adapted, transmitted, or stored in any form by any process (electronic or otherwise) without the specific written consent of Woodside. All rights are reserved.

Controlled Ref No. W1000SM002 DRIMS No. 3205381 Revision : 1 Page 13

DRIMS Classification/No. Uncontrolled when printed, unless stamped in Red to the contrary.

• Site repairs shall be carried out in accordance with Section 4.9. After TSA has been applied, inspected and approved, the sealer coat shall be applied immediately to the clean, dry surface. Sealer application shall take place within 8 hours of the final application of TSA unless environmental conditions can be maintained within an acceptable range (e.g. steel temp > 15 oC, Humidity < 50% and ambient temp > 20 oC and under cover). Sealer shall be thinned, mixed and applied in a mist coat followed by a full coat as per the standard (system CS-04N). The sealer shall be of low viscosity, thinned as necessary to penetrate into the TSA coating and have an extensive documented track record of use in sealing TSA for the intended service application. The sealer shall thoroughly seal the porosity inherent in the TSA. The principal may require the porosity to be verified by metallographic sectioning of the coating to verify porosity < 10%. The Contractor shall demonstrate to the satisfaction of the Principal the actual spreading rate of the sealer to verify adequate sealing of porosity.

3.2.1.4 Passive Fire Protection Applicators PFP Applicators shall have a minimum 3 years relevant experience with the application of protective coatings for offshore and onshore hydrocarbon facilities. Only Contractor personnel trained by the PFP Manufacturer shall apply PFP. The Contractor personnel (site supervisor, quality control representative, foreman and painters) shall have completed a formal qualification and training programme run by the PFP Manufacturer and be in possession of the Manufacturer’s training certificate. Prior to initiation of work, the Contractor shall demonstrate the required passive fire protection (PFP) system on a length of H/I beam. In particular the surface preparation of intact/damaged primer shall be agreed. Sufficient samples shall be provided to show every stage of the process. The samples shall serve as a guide to the design details and as acceptance criteria for surface finish. PFP supervisors and QC personnel shall be qualified as Inspector in accordance with NACE or equivalent Principal approved qualification.

3.2.2 Pre-qualification of Products Generic coating products as part of the specified systems are identified in section 8. Nominated products from approved vendors to suit the specified systems can be found in section 9. The coating manufacturers shall review these products and provide test data and supporting documentation as confirmation that they comply with the following requirements for the identified key products:

• Preference will be given to products that are part of a global product range from the coating manufacturer in order that test data & track records can be referred to and data sheets can be accessed from coating manufacturer’s website.

• Inorganic and organic zinc primers zinc dust contents shall conform to SSPC Paint 20 or the equivalent Australian standard AS 3750 .

• Self priming epoxy mastics ( product code1c), high build epoxies (2c), ultra high build epoxies (4c), high build, high solids epoxies (5c) high build solvent free epoxies(7c) and aluminium loaded pure epoxies (11c) shall be immersion grade materials that are pre-qualified to NORSOK M-CR-501 Table 11.1 pre-

Page 14: Standard Protective Coatings

This document is protected by copyright. No part of this document may be reproduced, adapted, transmitted, or stored in any form by any process (electronic or otherwise) without the specific written consent of Woodside. All rights are reserved.

Controlled Ref No. W1000SM002 DRIMS No. 3205381 Revision : 1 Page 14

DRIMS Classification/No. Uncontrolled when printed, unless stamped in Red to the contrary.

qualification testing or approved equivalent including cyclic testing and cathodic disbondment testing.

• Epoxy phenolic ( 2h) shall be an immersion grade product that has long term (> 6 months) heat stability test data in seawater at 130 oC.

3.2.3 Qualification Records Records of operator qualification test results shall be submitted with a summary sheet showing the name, qualification and designation of each operator.

3.2.4 Coating Manufacturer For new construction and where required on maintenance work, the Contractor shall require the coating manufacturer to designate a Manufacturer’s Technical Representative (MTR) who is fully conversant with the coating materials and coating process techniques. The Principal shall approve the MTR. The MTR shall:

1) Be full time at fabrication yards

2) Be a NACE Level II certified Coating inspector in possession of a valid certification card to that effect.

3) Attend the pre-job meeting and other similar meetings.

4) Inspect and approve blasting and coating application tests.

5) Provide field guidance and personnel instruction during initial stages of blasting and coating application operations.

6) Submit written, auditable reports regarding compliance with procedures.

3.2.5 Coordination Meetings The Contractor shall schedule a pre-job meeting to review job requirements. Notification shall be submitted a minimum of two (2) weeks in advance of scheduled pre-job meeting. Mandatory Attendees shall be the Contractor Superintendent, Coating Supervisor, Quality control representative, Manufacturer’s technical representative, Principal representative and the Principal’s nominated coating specialist. Other attendees may be included with prior written agreement of Contractor. Principal shall be given two (2) days notice of initial job start and four (4) hours notice of schedule changes. No work shall be performed without Principal’s knowledge.

3.2.6 Compatibility of Fabrication and Construction Site Conditions The coating systems given in this standard have primarily been selected with due consideration to conditions during operation of the facilities. It is the Subcontractor’s responsibility to ensure that the selected coatings are suitable for the construction site environmental conditions during fabrication and construction. Should the subcontractor identify a discrepancy in the specification due to construction site environmental conditions, the Subcontractor shall propose alternative coatings for Principal approval during the bidding process. All Sub-contractor proposed changes and substitutions shall require Principal approval prior to any coating application taking place.

Page 15: Standard Protective Coatings

This document is protected by copyright. No part of this document may be reproduced, adapted, transmitted, or stored in any form by any process (electronic or otherwise) without the specific written consent of Woodside. All rights are reserved.

Controlled Ref No. W1000SM002 DRIMS No. 3205381 Revision : 1 Page 15

DRIMS Classification/No. Uncontrolled when printed, unless stamped in Red to the contrary.

3.2.7 Handling of Chemicals Material safety data sheets shall always be available for review during transport of materials, storage of materials, and prior to and during the application of the product. Manufacturer’s instructions for the safe handling of products shall be followed to minimise the risk of injury or creation of health hazards to all personnel. Handling of coatings, solvents and chemicals shall be carried out with due care and diligence. Personnel not directly concerned with coating operations will be protected against the affects products used during coating application. The correct use of personal protection equipment (PPE) shall be employed during surface preparation, coating preparation and application, and site clean up. Disposal of waste products, solvents and chemicals must be removed or treated in accordance with Woodside Energy Ltd environmental protection policy.

3.2.8 Pressure Equipment The safe operation of all pressure equipment shall be detailed in the contractors Safety Management System (SMS). It shall detail how and when inspection and maintenance of such equipment shall be carried out and the method of recording and logging the inspections. Other equipment and associated connections shall be regularly inspected and well maintained.

3.2.9 Earthing Proper grounding, both electrical and static shall be provided for tanks, airless spray equipment, hand power tools, power supplies and other electrical equipment.

3.2.10 Breathing Apparatus Appropriate air-fed masks should be used during blasting and coating operations. Other personnel in the vicinity shall wear suitable protective masks or respirators when necessary. Adequate ventilation must be provided in confined spaces and when using air-fed masks in these areas, attention should be paid to the possibility of explosive vapour build-up. As a minimum, dust, rust and vapours should be directed away from the operator by wind or extractor fan. Woodside safety and permit requirements for entry into confined spaces shall apply.

3.2.11 Access Scaffolding, platforms or lifts shall be used to reach otherwise inaccessible areas. This equipment must only be erected and operated by licensed or qualified personnel. The appropriate tagging system as stipulated by the relevant authorities shall be employed and clearly displayed. Scaffolding and staging shall be constructed so that operators are able to stand erect with body and arms free of obstruction and so that sufficient access is provided for coating process and quality control inspections. Care should be taken to maintain a clear and uncluttered work area to reduce the risk of falling or tripping or dislodging items from above deck work areas.

Page 16: Standard Protective Coatings

This document is protected by copyright. No part of this document may be reproduced, adapted, transmitted, or stored in any form by any process (electronic or otherwise) without the specific written consent of Woodside. All rights are reserved.

Controlled Ref No. W1000SM002 DRIMS No. 3205381 Revision : 1 Page 16

DRIMS Classification/No. Uncontrolled when printed, unless stamped in Red to the contrary.

Safety harnesses, standby personnel and any other appropriate safety precautions must be used when applicable. Rope access may be used where appropriate and with the proper procedures.

3.2.12 Work Permits The appropriate work permit systems shall be followed. This may involve the use of Job Hazard Analyses (JHAs).

3.2.13 Selection of Coatings and Application Methods Woodside has a global responsibility for the protection of the environment and will use products and application methods that are environmentally ‘friendly’, providing they meet the minimum engineering requirements for achieving corrosion protection. The specifier must understand the systems and their relation to original condition, surface preparation, profile and sequence of coats.

Page 17: Standard Protective Coatings

This document is protected by copyright. No part of this document may be reproduced, adapted, transmitted, or stored in any form by any process (electronic or otherwise) without the specific written consent of Woodside. All rights are reserved.

Controlled Ref No. W1000SM002 DRIMS No. 3205381 Revision : 1 Page 17

DRIMS Classification/No. Uncontrolled when printed, unless stamped in Red to the contrary.

4 SURFACE PREPARATION 4.1 GENERAL

All edges shall be ground to a minimum radius of 2 mm or otherwise agreed with the Principal and Flame cut areas should have been ground flush. Weld spatter shall have been ground flush. Cleaning of surfaces shall, as a general rule, be done by dry blast cleaning (hereafter referred to as blast cleaning) as outlined in AS 1627.4 to achieve a class 2 ½ (ISO 8501-1 Sa 2 ½). The surface profile and the anchor pattern shall be in accordance with the requirements of this Standard. Welds in immersion areas shall conform to NACE RP 0178-2003 Surface Condition C. Welds in non-immersion areas shall conform to NACE RP 0178-2003 Surface Condition D. Fabrication should be complete before surface preparation begins. However, surface preparation and application of the base layers of the specified coating system before assembly will be allowed. Prefabrication primers are allowed. However, after assembly these primers shall be removed by abrasive blast cleaning and the surface shall be blasted to the initial specified surface cleanliness unless otherwise agreed with the Principal. Alternative surface cleaning methods are only acceptable after written approval of the Principal. Alternative surface preparation such as power tool cleaning is not acceptable for areas difficult to access such as areas exposed to water, steelwork to be insulated or to be buried and internal surfaces of equipment and tanks. Stainless steel surfaces shall not be treated with carbon steel cleaning tools.

4.2 PRETREATMENT Salt contaminated surfaces (> 50 mg/m2 for atmospheric steel and > 25 mg/m2 for immersion zones) shall be washed down with a potable water jet wash ((e.g.7-28 MPa) to remove soluble surface contamination to below acceptable levels. Oil, grease, wax, dirt and other foreign matter shall be removed by cleaning and degreasing of metal surfaces in accordance with AS1627 Part 1 or approved equivalent international standard. All bolt holes shall be drilled and their edges ground to remove sharp edges and solvent cleaned prior to the commencement of blast cleaning. Solvent cleaning shall be carried out in accordance with AS1627 Part 1 (SSPC-SP1). All welded areas and appurtenances shall have welding flux removed from crevices prior to commencement of any surface preparation. Any weld undercut or other crevices not acceptable to the fabrication standard shall be reported and repaired. All weld spatter, temporary attachment points, surface defects etc shall be removed and ground flat.

Page 18: Standard Protective Coatings

This document is protected by copyright. No part of this document may be reproduced, adapted, transmitted, or stored in any form by any process (electronic or otherwise) without the specific written consent of Woodside. All rights are reserved.

Controlled Ref No. W1000SM002 DRIMS No. 3205381 Revision : 1 Page 18

DRIMS Classification/No. Uncontrolled when printed, unless stamped in Red to the contrary.

Labels, marker plates, valve stems, flange faces, glass, mechanical seals, rubber gaskets and other sensitive areas shall be covered to prevent damage during the coating process. Protective materials shall be removed after coating is completed. Dust shall be removed by blowing with clean, dry, oil free air or by vacuum cleaner. For maintenance, firmly adherent coating systems may be left on the substrate providing their edges are suitably 'feathered'.

4.3 ABRASIVE BLAST CLEANING Applies to all surfaces listed and where appropriate within each system identified in sections 8 & 9.

4.3.1 Grades of Surface Finish

The recognised surface finish grades are summarised in the table below.

Table 4.1 Surface finish grades

Surface finish grade ISO/AS 1627.4 SSPC NACE White metal Sa 3 SP-5 1

Near-white metal Sa 2.5 SP-10 2 Sweep blast cleaning Sa 1 SP-7 4 Solvent cleaning - SP-1 - Power tool cleaning St 3 SP-3 Power tool cleaning to bare metal

- SP11 -

Water jetting - SP-12 5 Wet abrasive blasting - TR2 6G198 “Sweep” blasting may be approved to slightly roughen (5 – 10 micron profile) previously coated surfaces that have exceeded re-coat times. All loosely adhered coatings remaining after sweep blasting must be entirely removed prior to any coating operation. If maintenance or re-work is to be carried out adjacent to a coated surface, the dressed areas shall be re-blasted to provide adequate paint key. The blast cleaning shall carry over onto the secure surrounding coating for not less than 25mm all around and the edges shall be chamfered by a method approved by Woodside, following a written submission by the Contractor. All blasting residue (spent abrasive, dust, rust and paint) shall be gathered and disposed of in an approved environmentally acceptable manner.

4.3.2 Dry Abrasive Blast Cleaning Blast cleaning of carbon steel surfaces shall comply with AS1627 Part 4, Class 2.5 (or ISO 8501-1 approved equivalent international standard) at the time of coating unless otherwise nominated.

Page 19: Standard Protective Coatings

This document is protected by copyright. No part of this document may be reproduced, adapted, transmitted, or stored in any form by any process (electronic or otherwise) without the specific written consent of Woodside. All rights are reserved.

Controlled Ref No. W1000SM002 DRIMS No. 3205381 Revision : 1 Page 19

DRIMS Classification/No. Uncontrolled when printed, unless stamped in Red to the contrary.

Blasting abrasive shall be dry, clean, free from contaminants and of a type and size adequate to give anchor pattern amplitude of 40 to 75 microns (or as specified). The abrasive conductivity as assessed by ISO 11127-6 shall be 25 mS/m maximum when used on carbon steel and 150 μS/m for stainless steel as per ISO 11127-7. For new construction work abrasive conductivity shall be verified daily and with each new batch of abrasives. For maintenance work the proposed frequency of the conductivity determination test shall be submitted in writing for Woodside Materials/Inspection Group’s approval.

4.3.3 Wet Abrasive Blast Cleaning Wet abrasive blasting may be permitted with prior approval from Woodside. Wet abrasive blasting shall be in accordance with AS1627 Part 4 Section 3.2. Water for wet abrasive blasting shall be fresh potable water. The cleaned surface should be washed off immediately after blast cleaning using fresh water. Only after written approval of the Principal, a suitable corrosion inhibitor such as mass fraction 0.3 % sodium nitrite with mass fraction 1.2 % ammonium phosphate may be used to prevent flash rusting. Chromate inhibitors shall not be used. However, the paint Manufacturer shall approve the use of an inhibitor or the removal of residues of the inhibitor before painting. The cleaned surface shall be dry at the time of painting. Particular care shall be taken to dry areas which are not self-draining, so that water collected is removed. Any existing protective coating shall be properly protected to prevent any possible damage.

4.4 ULTRA HIGH PRESSURE WATER CLEANING (MAINTENANCE ONLY) Where abrasive blast cleaning is deemed impractical or unsuitable by Woodside for maintenance/HSE purposes, and where the surface has been previously abrasive blast cleaned, ultra high pressure water cleaning may be substituted in consultation with Woodside. The ultra high pressure-cleaning unit shall be capable of a minimum operating pressure of 270 MPa and shall have a proven effective performance. Oil, grease, wax, dirt and other foreign matter shall be removed by cleaning and degreasing of metal surfaces in accordance with AS1627 Part 1 (or approved equivalent International standard) prior to ultra high pressure cleaning. Where black spots occur in pits or other surface defects, the surface shall be cleaned again at higher pressure to remove these defects caused by residual salts. Ultra high pressure water cleaning shall only be used where compatible coating systems are specified. The contractor shall provide evidence of a robust safety system for protection of operators and personnel in the vicinity of the unit. The minimum required standard of surface preparation is NACE No. 5 /SSPC-SP 12 WJ-2 with no more than a light flash rust for spot repair and WJ1 with a light flash rust for full strip and re-coat. An acceptable alternative is the International Paints Hydro blast standard with a HB 2 ½ L being the minimum acceptable standard.

Page 20: Standard Protective Coatings

This document is protected by copyright. No part of this document may be reproduced, adapted, transmitted, or stored in any form by any process (electronic or otherwise) without the specific written consent of Woodside. All rights are reserved.

Controlled Ref No. W1000SM002 DRIMS No. 3205381 Revision : 1 Page 20

DRIMS Classification/No. Uncontrolled when printed, unless stamped in Red to the contrary.

4.5 OTHER CLEANING METHODS FOR CARBON STEEL SURFACES Where applicable, steel surfaces may be mechanically cleaned using power tools such as flap or disk sanders, etc. Care needs to be taken as these items can lead to polishing of the surface. Hand power tooling shall be restricted to small areas only following approval from the Principal. For maintenance painting this shall be further restricted to non-pressure containing components only. Should power tooling be necessary, power tool cleaning should be performed according to AS1627, Part 2, (or approved equivalent international standard) with a surface finish to ISO 8501-1, Grade St 3 or equivalent. Prior approval shall be obtained from Woodside Materials/Inspection Groups before any of these methods of surface preparation are used. If these methods are approved, inorganic zinc silicate primer, where specified, shall be substituted with epoxy zinc rich primer or a primer more surface tolerant.

4.6 GALVANISED STEEL SURFACES All spikes and dross shall be removed and all edges shall be free from lumps and runs. All galvanised surfaces that are to be additionally coated shall be solvent cleaned in accordance with section 4.2 and brush/sweep abrasive blast. A suitable etch primer may be used as an alternative to brush abrasive blasting. If for any reason the galvanised products have been allowed to weather prior to application of the topcoat, the surface shall be pre-cleaned in accordance with the following requirements. High-pressure water jet wash (17 to 28 MPa or 2500 to 4000 psi) and dry using dry compressed air. Solvent clean all surfaces in accordance with Section 4.2. Galvanised surfaces that are showing signs of red rust shall be prepared in accordance with the appropriate system for carbon steel.

4.7 ALUMINIUM & STAINLESS STEEL SURFACES All aluminium and stainless steel surfaces that are to be coated shall be cleaned in accordance with Section 4.2. Stainless steel surfaces are to be additionally abraded or sweep blasted using non-metallic abrasive to provide an effective keying surface. Any coating to be applied directly only stainless steel shall contain no more than 50 ppmv of leachable chlorides.

4.8 CONCRETE SURFACES Concrete surfaces to be coated shall be prepared in accordance with NACE RP 0892 and the coating manufacturer’s recommendations to ensure a suitable surface for over coating. Concrete cure shall be confirmed by an acceptable method (e.g. AS1012 Method of Testing Concrete). All concrete defects (e.g. honeycombs and spalling), laitance, physical damage, chemical damage and contamination shall be repaired/rectified using a method approved by the principal. Guidance can be found in NACE No 6/SSPC-SP13.

Page 21: Standard Protective Coatings

This document is protected by copyright. No part of this document may be reproduced, adapted, transmitted, or stored in any form by any process (electronic or otherwise) without the specific written consent of Woodside. All rights are reserved.

Controlled Ref No. W1000SM002 DRIMS No. 3205381 Revision : 1 Page 21

DRIMS Classification/No. Uncontrolled when printed, unless stamped in Red to the contrary.

Surface preparation shall be in accordance with the most appropriate of the methods laid out in NACE No 6/SSPC-SP13. The proposed method shall be submitted to the Principal for acceptance, if accepted, a written acceptance will be issued to the Contractor. Acceptance criteria shall be as for severe service (significant exposure to traffic, chemicals and/or changes in temperature) as detailed in Table 1 NACE No.6/SSPC SP13 and reproduced below. Table 4.2: Acceptance Criteria for Concrete Surfaces after Surface Preparation

Property Test Method Severe Service Surface tensile strength NACE No.6 Para A1.6 2.1 MPa Surface profile Visual comparison Coarse (60) abrasive paper Surface cleanliness Visible dust No significant dust Residual contaminants Water drop 0o contact angle pH ASTM D4262 pH of rinse water * Moisture content ASTM D4263 No visible moisture Moisture content ASTM F 1869 15g/24hr/m2 max Moisture content ASTM F 2170 80% max

*The acceptance criteria for ASTM D4262 is as follows: The pH readings following the final rinse shall not be more than 1.0 lower or 2.0 higher than the pH of the rinse water (tested at the beginning and end of the final rinse) unless otherwise specified

Page 22: Standard Protective Coatings

This document is protected by copyright. No part of this document may be reproduced, adapted, transmitted, or stored in any form by any process (electronic or otherwise) without the specific written consent of Woodside. All rights are reserved.

Controlled Ref No. W1000SM002 DRIMS No. 3205381 Revision : 1 Page 22

DRIMS Classification/No. Uncontrolled when printed, unless stamped in Red to the contrary.

5 COATING APPLICATION 5.1 INTRODUCTION

The coating systems to be applied shall be as detailed in Section 8 & 9. It should be noted that both 'New Construction' and 'Maintenance' sections are included for most systems. Woodside approved coating materials are nominated in the coating system detail in Section 10. It is the project engineer’s responsibility in consultation with the TA to ensure that the coating systems selected from section 10 will meet the required operating conditions for the stated design life. The coating contractor in accordance with the Woodside deviations process may submit alternative products to those nominated in Section 10. This must receive package engineer (in consultation with Woodside TA or Woodside TA if maintenance work) approval prior to application and may include low temperature cure rapid recoat coatings where appropriate. Paints containing metallic zinc shall never be used on, oversprayed or dropped onto stainless steel pressure retaining components. Polysiloxane gloss topcoats may be a suitable alternative to the urethanes and acrylics that Woodside have extensive experience with for large static surfaces with little risk of impact damage. The use of Polysiloxane coatings may be submitted through the Woodside deviation process on a case by case basis where there is a suitable business case including extensive technical information to justify their use. The colour of the final coat shall be as nominated in Section 11 for offshore structures, vessels and equipment. Offshore pipework colour coding shall also be in accordance with Section 11. Onshore colour codes are presented in Section 12. Colours listed as “Practical Equivalents” to those in accordance with AS 2700 shall be acceptable. Pipe insulation cladding shall be left unpainted unless otherwise specified. Surfaces requiring temporary protection shall first be cleaned in accordance with Section 4.2 and then protected either by application of Shell Ensis Fluid SDC or equivalent for periods up to 6 months indoors, (1 month outdoors), or Shell Ensis Fluid HB or equivalent for periods up to 12 months indoors, (6 months outdoors).

5.2 APPLICATION - PROCEDURES CONSTRAINTS AND QUALITY CONTROL The paint manufacturer’s product data sheets and specifications for mixing, application and curing shall be considered an integral part of this standard. The Contractor shall be responsible for obtaining from the paint manufacturer or supplier the product and safety data sheets of each material. All coating systems shall be applied in accordance with this standard and the paint manufacturer's instructions and data sheets. Any conflicting requirements shall be brought to the attention of the Principal prior to the application of the coating. Coatings shall be free of dust, dry spray, oil, entrapped grit, grease and other contaminants before application of succeeding coats.

Page 23: Standard Protective Coatings

This document is protected by copyright. No part of this document may be reproduced, adapted, transmitted, or stored in any form by any process (electronic or otherwise) without the specific written consent of Woodside. All rights are reserved.

Controlled Ref No. W1000SM002 DRIMS No. 3205381 Revision : 1 Page 23

DRIMS Classification/No. Uncontrolled when printed, unless stamped in Red to the contrary.

Coating application shall begin as soon as surfaces are prepared, inspected, and before surface deterioration occurs. Zinc rich primers shall be applied over abrasive blast cleaned carbon and low alloy steel surfaces only. Paints containing metallic zinc shall never be used, over sprayed or dropped on stainless steel pressure retaining components. To ensure that only correctly blasted surfaces are coated, a minimum of 100 mm around the edges of prepared areas shall be left uncoated, unless adjoining a coated surface. When adjoining a coated surface, the connection to the existing paint film shall be made as described in this section. In case an object is delivered by the Principal to the Contractor in order to be painted, the Principal shall inform the Contractor about the layers of coating which have already been applied and the Contractor shall complete the required system in accordance with this standard. No coating shall be applied within 50 mm to areas that need to be welded later. Crevices or pits that cannot be adequately coated shall, after blasting operations and prior to application of the final coating, be sealed with an approved caulking compound. Excess caulking compound shall be removed. Caulking compound must be approved in writing by the manufacturer of the coating material being applied and by the Principal. For quality assurance and control refer to Section 6.

5.2.1 Ambient Conditions Coatings shall not be applied:

• When surface temperatures are less than 3º C above the dew-point temperature of ambient air.

• During exposure to inclement weather conditions (e.g., fog, mist or rain).

• When relative humidity exceeds 85%.

• When the ambient temperature is below 10° C for zinc/epoxy/urethane systems. Note: Low temperature coatings may be allowed. Contractor shall submit proposed coatings for low temperature application to Principal for written approval prior to use.

• When other detrimental conditions exist (e.g., high winds or airborne dust). High winds shall be defined as winds in excess of 25 kilometres per hour (13.5 knots).

• If the coating manufacturer’s recommendations for temperature and humidity limitations differ from the above, written approval to proceed must be submitted from manufacturer.

• Contractor shall ensure adequate ventilation and airflow in all recesses of enclosed areas to allow removal of solvents and proper cure.

Page 24: Standard Protective Coatings

This document is protected by copyright. No part of this document may be reproduced, adapted, transmitted, or stored in any form by any process (electronic or otherwise) without the specific written consent of Woodside. All rights are reserved.

Controlled Ref No. W1000SM002 DRIMS No. 3205381 Revision : 1 Page 24

DRIMS Classification/No. Uncontrolled when printed, unless stamped in Red to the contrary.

5.2.2 Mixing and Thinning The mixer and pot shall be thoroughly cleaned before mixing of new materials. All coating materials shall be mixed and thoroughly stirred in accordance with the instructions of the paint manufacturer. Sufficient agitation to maintain good mixing shall be applied until the product is used. If during mixing/stirring air is entrapped in the product, sufficient time should be allowed for air bubbles to escape before application. Only thinners as specified by the paint manufacturer shall be used. When the manufacturer’s specified pot life is reached or other indications of elapsed pot life such as thickening or film-build problems occur, the material shall be discarded. The paint manufacturer shall specify the type and amount of thinners that can be used and the contractor shall maintain an accurate record of the amount of thinner used.

5.2.3 Compatibility With Existing Coating Systems Before commencing any painting work, the compatibility with existing coating systems or layers shall be checked. The paint manufacturer shall be consulted. If there is any doubt about compatibility, the patch test in accordance with ASTM D 5064 shall be conducted to evaluate the interfacial adhesion. Coating layers should be over coated only with products made by the same manufacturer.

5.2.4 Over Coating Coatings shall be dried and cured in accordance with paint manufacturer’s recommendations, prior to over coating. Before over coating, over-runs, droppings and smears shall be removed and any coating damage or imperfection shall be repaired. Where the DFT does not meet the requirements of this Standard, corrective action shall be taken. When a zinc primer is specified in coating systems, these shall be over coated as soon as possible but only after sufficient cure if the primer is an inorganic zinc primer. The paint manufacturer’s maximum over coating times shall not be exceeded. Zinc salts that have formed during the intervening period shall be removed in accordance with the paint manufacturer's instructions prior to over coating.

5.2.5 Handling Very few of the coating systems in this standard will take rough handling or impact with a sharp object. The bulk of external corrosion on WEL assets is due to mechanical damage to coatings. After proper application of the coatings, components must be handled with due diligence.

Page 25: Standard Protective Coatings

This document is protected by copyright. No part of this document may be reproduced, adapted, transmitted, or stored in any form by any process (electronic or otherwise) without the specific written consent of Woodside. All rights are reserved.

Controlled Ref No. W1000SM002 DRIMS No. 3205381 Revision : 1 Page 25

DRIMS Classification/No. Uncontrolled when printed, unless stamped in Red to the contrary.

5.3 APPLICATION METHODS Airless or pneumatic spray applications are the preferred methods of application. If spray painting is to be carried out, the following shall be taken into account:

• Spray painting may cause interference with other works and so approval from Woodside shall be obtained.

• The correct spray tips, air pressures etc, as recommended by the equipment supplier, shall be used.

• Spray guns shall be held perpendicular to the surface and at a distance required to deposit a continuous wet layer of coating. Arcing of the gun shall not be permitted.

• Conventional spray guns shall be held 150 to 300 mm from the surface. Airless spray guns shall be held at a distance such that the fan width does not exceed 300 mm.

• Each spray pass shall overlap the preceding pass by 50%. Visible streaking at the overlap shall not be acceptable. Large areas being coated with high build materials (nominal dry film thickness above 100 microns) shall receive passes in two (2) perpendicular directions.

Each coat shall be applied uniformly and completely over the entire surface. All runs and sags shall be brushed out immediately or the paint shall be removed and the surface resprayed. Brush application may be used under the following circumstances:

• When spraying for any reason, such as complex geometry, material or environmental considerations cannot properly coat areas.

• For the initial stripe coat of paint to all corners, edges, crevices, holes, welds or irregular surfaces prior to spray application.

• For “touch up" or repairs to localised damaged paint or areas of incorrectly applied paint.

Brushes shall be of a style and quality that will permit the proper application of paint. Brush applications should be done in two passes that are at right angles to each other so that a smooth coat, as near uniform in thickness as possible, is obtained. There should be no deep or detrimental brush marks. Paint shall be worked into all crevices and corners. Runs and sags shall be brushed out. During the application of each coat, all areas such as corners, edges, welds, small brackets, bolts, nuts, and interstices shall receive additional paint to ensure that these areas have at least the minimum specified dry film thickness and to ensure continuity of coating. Stripe coating shall provide a continuous coating film and shall not exceed the maximum dry film thickness specified for that material and shall be touch dry before over coating.

Page 26: Standard Protective Coatings

This document is protected by copyright. No part of this document may be reproduced, adapted, transmitted, or stored in any form by any process (electronic or otherwise) without the specific written consent of Woodside. All rights are reserved.

Controlled Ref No. W1000SM002 DRIMS No. 3205381 Revision : 1 Page 26

DRIMS Classification/No. Uncontrolled when printed, unless stamped in Red to the contrary.

5.3.1 Repair/Reinstatement 5.3.1.1 Organic & Inorganic Coatings

Small areas of coatings, which require repair may be abraded to bare steel with sandpaper, hand file or rotating fibre discs. Coating materials may be applied to such repair areas using a brush. Coatings, not including inorganic zinc, which have to be over-coated and which have become contaminated with oil, grease, or other foreign material shall be cleaned with water soluble biodegradable cleaners and then water rinsed. Inorganic zinc primers lightly contaminated with oil, grease, or other foreign material shall have the contaminants removed using a biodegradable hot water detergent pressure wash. Heavily contaminated inorganic zinc silicate shall be removed and reinstated. Inorganic zinc surfaces must be thoroughly dry prior to over-coating, preferably by constant flow of dry ventilation over the surface for a minimum of four (4) hours after washing and before over-coating. The repair technique for coatings with dry film thickness below that specified shall depend upon the state of cure of the coating. Coatings that have exceeded the minimum recoat interval and have not exceeded the maximum recoat interval may be cleaned, as required, and over-coated with the same material. Coatings that have exceeded the maximum recoat interval shall be removed by blasting or at the discretion of the Principal quality control representative abrading the surface to provide an adequate key for overcoating. Principal will not accept additional costs for repair work. Inorganic zinc silicate (IZS) primer with dry film thickness (DFT) above that specified (as measured in accordance with AS 3894.3 Method B) shall be removed by blasting. For IZS coatings with DFT less than that specified but beyond the recoat interval may be overcoated with a compatible zinc rich epoxy to achieve the required DFT. The application of IZS coatings in humidities of < 50% shall require the use of either a water mist or wet hession covering the IZS coating within 1 hour of application but after the coating has dried sufficiently to be water insoluble to ensure full cure of the coating. Runs and sags shall be brushed out immediately or the coating shall be removed. When welding occurs after coating application, the coating shall be removed by spot-blasting 100 mm past the edge of the heat-affected coating. After welding, the surface shall be prepared in accordance with this standard and the paint shall be reinstated such that the finished coating complies with this standard. Coating defects or damage shall be reinstated such that the finished coating complies with this standard. All repair and reinstatement procedures shall be submitted to Woodside for approval, prior to commencement of the repair. The procedures shall take into consideration all surface preparation requirements to ensure that full substrate and inter-coat adhesion is achieved. Touch up of the zinc primer (inorganic zinc silicate or hot dipped galvanised) shall be with a zinc rich epoxy complying with AS3750 Part 9 Type 2.

Page 27: Standard Protective Coatings

This document is protected by copyright. No part of this document may be reproduced, adapted, transmitted, or stored in any form by any process (electronic or otherwise) without the specific written consent of Woodside. All rights are reserved.

Controlled Ref No. W1000SM002 DRIMS No. 3205381 Revision : 1 Page 27

DRIMS Classification/No. Uncontrolled when printed, unless stamped in Red to the contrary.

All care shall be taken during the lifting, tie down and transport of coated items, to minimise damage. Repair of coating damage, occurring as a result of transport by the Contractor, shall be the responsibility of the Contractor.

5.3.1.2 Thermally Sprayed Aluminium Surfaces Areas of insufficient thickness of thermally sprayed aluminium (TSA) shall be rectified by further application of TSA, and before the seal coating application. Areas of damage or defective coating including sites of adhesion testing and areas of coating which fail to meet the requirements for adhesion shall be repaired as follows:

• Seal coat shall be removed by blast cleaning

• Damaged or defective TSA coating shall be removed by abrasive blasting

• Repair area shall be prepared by blast cleaning to AS 1627.4 class 2.5/ 3

• Small points of damage or defective coating shall be prepared for recoating by vacuum-blasting or power disking, subject to acceptance by Principal, if necessary to avoid damaging surrounding sound coating

• A 75mm margin of sound coating shall be feathered to a fine edge by vacuum blasting.

• TSA coating shall be re-instated in accordance with this standard.

5.4 COATING OF FLANGE BOLTS AND NUTS The back face of carbon steel flanges shall be primed only prior to assembly. Following assembly, the remainder of the system can be applied to the joint including the bolting. Stainless steel bolting should be left unpainted. Carbon steel bolting that requires tensioning with Hydro-tight equipment (studs over 1 3/8”) should be blasted and wrapped in Denso tape for preservation. Destec Hub identification markings should be masked and that area be top coated with urethane for easy viewing. Galvanised structural bolts should be treated with the same system as the structure.

Page 28: Standard Protective Coatings

This document is protected by copyright. No part of this document may be reproduced, adapted, transmitted, or stored in any form by any process (electronic or otherwise) without the specific written consent of Woodside. All rights are reserved.

Controlled Ref No. W1000SM002 DRIMS No. 3205381 Revision : 1 Page 28

DRIMS Classification/No. Uncontrolled when printed, unless stamped in Red to the contrary.

6 INSPECTION AND TESTING 6.1 GENERAL

All inspection and testing detailed below are the minimum requirements. The result of routine testing shall be recorded and submitted as follows:

• Daily surface and ambient conditions as per AS 3894.10 or approved equivalent.

• Daily abrasive contamination check, surface cleanliness & surface salt checks

• Daily blast and paint inspection report as per AS 3894.13 or approved equivalent.

• Equipment reporting (AS3894.11) shall be as required (i.e. when equipment is changed or calibrated) or weekly whichever is the shortest time interval.

• Coating summary reporting (AS3894.12) shall be on completion of the nominated area following sign off by client.

The painting Contractor shall ensure that updated product technical data sheets are obtained from the Manufacturer before commencing any painting and that coating materials are within their shelf life. The Principal or its Representative shall have the right to inspect, check or review, at all times, any or all of the activities, equipment, inspection equipment, product used or to be used related to the work. All parts of the work shall be accessible for this purpose. Regular quality checks should be carried-out by a qualified and independent third party inspector. The Principal Representative assigned to the painting work shall be given at least four hours notice of any change in the schedule of the painting activities. Whenever any section is to be assembled that will prevent subsequent inspection of an area, the Principal Representative shall be notified in time, so that inspection and repair activities can be carried out before proceeding with the assembly.

6.1.1 Rejected Work and Equipment The Principal shall have the right to reject any work, tools, materials, testing equipment, personal protection, staging and scaffolding, where these do not conform to the requirements of the contract or this standard. Rejected surface preparation or coating application shall be properly marked and documented. Any rejected equipment, surface preparation and/or applied coating shall be replaced or corrected to a level in accordance with this standard.

6.1.2 Quality Plan A quality plan is applicable to major projects only or as required by the TA. Before commencing any work, a written project specific quality plan shall be submitted to the Principal for approval. This plan shall include:

a) A sequence for the various activities in relation to the total work to be done;

Page 29: Standard Protective Coatings

This document is protected by copyright. No part of this document may be reproduced, adapted, transmitted, or stored in any form by any process (electronic or otherwise) without the specific written consent of Woodside. All rights are reserved.

Controlled Ref No. W1000SM002 DRIMS No. 3205381 Revision : 1 Page 29

DRIMS Classification/No. Uncontrolled when printed, unless stamped in Red to the contrary.

b) Detailed scope of the work to be done including per item or area, the required surface preparation and coating system to be applied;

c) A listing of the paints and materials to be used including batch numbers;

d) Full details of the blast and paint equipment including where appropriate dehydration, temperature and any other environmental control measures shall be taken:

e) methods of access;

e) Details of the personnel involved in the work together with a clear definition of their responsibilities and lines of communication;

f) Detailed procedures for testing and inspection including the methods and equipment to be used and the frequency of their application and acceptance criteria;

g) Details to document the essential steps in achieving quality;

h) Dew point determination table;

i) Calibration methods of the inspection equipment. Following review and approval by the Principal, the project quality plan shall, during the work, be updated and revised, as and when required. All revisions shall be submitted to the Principal for written approval prior to being included in the quality plan.

6.1.3 Reporting The Contractor shall submit inspection reports not less than once per week giving details of weather conditions, air humidity, temperature, particulars of application, e.g. blast cleaning, wet and dry film thickness, anomalies and progress of work versus approved programme when required by the Principal. All parts and areas that have been inspected and accepted or rejected shall be clearly identified and documented.

6.1.4 Inspection Personnel and Equipment Inspection personnel shall be individually certified by an approved organization (NACE or equivalent) or as approved by the TA. The Contractor shall provide and use all inspection equipment necessary to ensure that the specified conditions and quality requirements are achieved. Equipment shall include, but not be restricted to equipment to measure/determine:

a) Relative humidity, accuracy minimum 2 %

b) Air-and substrate temperature, accuracy minimum 0.2 °C

c) Dew point, accuracy minimum 0.2 °C.

Testing and inspection shall be carried out in accordance with Table 3.1 and Table 6.1

Page 30: Standard Protective Coatings

This document is protected by copyright. No part of this document may be reproduced, adapted, transmitted, or stored in any form by any process (electronic or otherwise) without the specific written consent of Woodside. All rights are reserved.

Controlled Ref No. W1000SM002 DRIMS No. 3205381 Revision : 1 Page 30

DRIMS Classification/No. Uncontrolled when printed, unless stamped in Red to the contrary.

Table 6.1 Inspection and Testing Requirements

Test type Method Frequency Acceptance criteria

Consequence

Environmental Conditions

As per Section 6.2.3 & 6.3.1

Before start of each shift + Every 4 hours.

In accordance with specified requirements

No blasting or coating

Abrasives Carbon steel as per ISO 11127-6, Stainless steel as per ISO 11127-7

Daily and with every new batch

Carbon steel < 25 mS/m Stainless steel < 150 μS/m

Change of abrasive

Visual examination of Cleaned Surface

As per Section 6.2.2 100 % of all surfaces

No defects. In accordance with specified requirements.

a) Reblasting b) Recleaning and retesting until acceptable

Surface dust for TSA prepped surfaces

As per section 6.2.4 Spot checks on each prepped area prior to TSA application

Rating < 2 as per ISO 8502-3

Recleaning & retesting until acceptable

Surface Salt test

AS 3894.6 method A or equivalent (e.g. ISO 8502-9).

Spot checks Maximum corresponding to < 50 mg/m2 (atmospheric service) and 25 mg/m2 NaCl (immersion service).

Recleaning and retesting until acceptable

Roughness As per Section 6.2.1 3 readings per 10 m2

In accordance with specified requirements

Reblasting

Visual Examination of coating

As per Section 6.3.2 100 % of surface after each coat.

In accordance with specified requirements

Repair of defects

Wet Film Thickness

As per section 6.3.3 Frequently during course of painting

In accordance with Manufacturer specified requirements

Additional film build as appropriate.

Film thickness As per Section 6.3.4 As per AS 3894.3 Method B or SSPC SP2

Coating thickness within minima and maxima given in system

Additional coats or recoating as appropriate.

Adhesion As per Section 6.3.7 Test panels and Spot checks

As per Section 6.3.7

Coating to be rejected.

Primer Cure As per Section 6.3.5 Spot check for ZRE and IOZ primers

As per Section 6.3.5

Allow longer curing time. Check Relative Humidity.

Holiday Detection

As per Section 6.3.6 As defined in section 6.3.6

No holidays Repair and retesting.

Page 31: Standard Protective Coatings

This document is protected by copyright. No part of this document may be reproduced, adapted, transmitted, or stored in any form by any process (electronic or otherwise) without the specific written consent of Woodside. All rights are reserved.

Controlled Ref No. W1000SM002 DRIMS No. 3205381 Revision : 1 Page 31

DRIMS Classification/No. Uncontrolled when printed, unless stamped in Red to the contrary.

6.2 SURFACE PREPARATION INSPECTION 6.2.1 Surface Profile

The surface profile shall be assessed by profile comparator standards in accordance with AS 3894.5 Method B. This shall be confirmed by other techniques (such as a calibrated depth micrometer or replica tape. This assessment shall be carried out at random locations over the prepared surface to provide an accurate assessment of the surface profile. The number and locations of determinations shall be as described in Table 6.2. Surface profile results shall be included in the Contractor's Coating Inspection Report if applicable to the specifications.

6.2.2 Surface Cleanliness Surface cleanliness shall be determined just prior to coating application by comparison to ISO 8501 or approved equivalent visual standards. Adequate light (500 Lux) shall be present for colour discrimination. For surfaces to be coated with TSA, residual surface dust levels shall be checked using the procedure detailed in ISO 8502-3 (Pressure sensitive tape method) with an acceptance criteria of 2 or less as per Figure 1 of that standard. Surfaces that fail the acceptance criteria shall be further cleaned of dust using clean, oil free dry air or industrial vacuum cleaner. The tapes for the final cleanliness achieved shall be included in the daily reports.

6.2.3 Ambient Conditions Prior to commencement of any coating application, the component temperature, ambient temperature, dew point and relative humidity shall be measured and recorded on the Contractor's Coating Inspection Report. A psychrometer shall be used at the location to determine the relative humidity.

6.3 COATING APPLICATION INSPECTION & TESTING 6.3.1 Dew Point, Air Humidity and Substrate Temperature

No coating work shall be carried out when the temperature of the surfaces is less than 3°C above dew point or the relative humidity of the air is greater than 85 % and the air or substrate temperature is below 10°C. For maintenance painting offshore a maximum relative humidity of the air of 90% is acceptable. Dew point determination shall be done in accordance with ISO 8502-4. No coatings shall be applied to surfaces exceeding a substrate temperature of 50°C. Higher substrate temperatures shall only be accepted if paint manufacturers have confirmed in writing that this application shall not affect the quality of the coating work.

6.3.2 General Coating Appearance The completed coating shall be free from defects such as runs, sags, pinholes, voids, bubbles, orange peel, grit, dust inclusions or other deleterious anomalies and be of good visual appearance. The topcoat shall completely cover the colour of the underlying layers.

Page 32: Standard Protective Coatings

This document is protected by copyright. No part of this document may be reproduced, adapted, transmitted, or stored in any form by any process (electronic or otherwise) without the specific written consent of Woodside. All rights are reserved.

Controlled Ref No. W1000SM002 DRIMS No. 3205381 Revision : 1 Page 32

DRIMS Classification/No. Uncontrolled when printed, unless stamped in Red to the contrary.

6.3.3 Wet Film Thickness (WFT) Spot checks shall be carried out during the course of painting operation to ensure that film thickness is being maintained. These shall be performed according to the procedure described in AS 3894.3 Appendix C – WFT by comb gauge.

6.3.4 Dry Film Thickness (DFT) Coating dry film thickness (DFT) measurement method shall be in accordance with AS 3894.3 method B(Magnetic induction and Eddy current methods) or the equivalent SSPC PA2. For measurement of dry film thickness, the digital magnetic induction type gauges are preferred for magnetic substrates and the eddy current type gauges for non-magnetic substrates. The magnetic ‘banana’ type gauges shall not be used. DFT gauges shall be calibrated daily or when dropped or when subjected to extremes of heat and/or cold. The number of measurements shall be in accordance with Table 6.2 or SSPC SP2. Calibration shall be done in accordance with AS 3894.3 appendix D or SSPC SP2. For the acceptance of an inspected area the following criteria shall be fulfilled:

• The dry film thickness of the completed coating system shall be equal to or greater than the specified minimum end of the range of dry film thicknesses as detailed in section 8 & 9;

• The average of the dry film thickness of the individual coating layers shall be equal to or above the specified minimum dry film thickness in the range. No single spot measurement shall be less than 80% of the specified minimum thickness. For TSA a single minimum value of 180 microns shall be acceptable.

• The dry film thickness of the individual coating layers shall be maximum 1.2 x the maximum DFT shown in the range, except for areas such as corners where overlaps are difficult to avoid. For such areas a maximum of 1.5 x the maximum DFT shall be accepted.

Table 6.2 — Sampling plan

Area/length of inspection area

m² or m

Minimum number of spot measurements*

Up to 1 5 Above 1 to 3 10 Above 3 to 10 15 Above 10 to 30 20 Above 30 to 100 30 Above 100 For additional ranges (m2 or m), the

corresponding number of measurements shall be added.

NOTE: Areas above 1000 m² should be divided into smaller inspection areas

*Each spot measurement to comprise the average of at least 3 individual gauge readings within a 4 cm diameter circle.

Page 33: Standard Protective Coatings

This document is protected by copyright. No part of this document may be reproduced, adapted, transmitted, or stored in any form by any process (electronic or otherwise) without the specific written consent of Woodside. All rights are reserved.

Controlled Ref No. W1000SM002 DRIMS No. 3205381 Revision : 1 Page 33

DRIMS Classification/No. Uncontrolled when printed, unless stamped in Red to the contrary.

6.3.5 Primer Cure The cure of any epoxy zinc primer shall be determined as per AS3894.4 Method C solvent rub test with no loss of DFT or deposit of cloth. For inorganic zinc silicate primers ASTM 4752 rub test shall be used with a minimum resistance rating of 5 being required prior to over coating.

6.3.6 Detection of Pinholes Pinhole testing for electrically non-conductive coatings in accordance with AS 3894 parts 1 or 2 (as required) shall be required for internal coatings of tanks and vessels as well as external coatings of buried tanks, vessels and piping. Holiday testing should be done as follows: Location % Surface Area Immersed surfaces cathodically protected 10 + all welds Splash Zone 100 Immersed surfaces not cathodically protected 100

Defects found shall be marked, repaired and retested in accordance with this Standard. The Contractor shall provide the necessary equipment for calibrating the holiday detector. The voltage to be used for the high voltage-spark testing shall be agreed with the paint manufacturer; otherwise a voltage of 5 V per μm shall be used, with a maximum of 25 kV.

6.3.7 Adhesion The quality of adhesion between the coating system and the steel substrate, and of the adhesion between the coating layers, shall not be less than:

a) Pull-off test in accordance with ASTM D 4541 using a self-aligning adhesion tester: minimum pull-off force for coating systems with a DFT greater than 150 μm shall be :

5 MPa for zinc primed coating systems

7 MPa for non-zinc primed coatings systems

10 MPa for internal tank coatings and linings

TSA – as per Table 3.1

b) Cross-cut test in accordance with AS 3894.9 method B for coating systems with a total DFT of maximum 150 μm.

Adhesion testing shall be done on sufficiently cured systems only, i.e. for organic coating systems not less than 14 days after the application of the final layer. For new construction, adhesion testing shall be carried out on each component and at least once per 100 m² of coated surface. Spots damaged by the adhesion tests shall be repaired in accordance with this Standard. For maintenance coating adhesion testing shall be carried out for application of new systems offshore and on an as needs basis.

Page 34: Standard Protective Coatings

This document is protected by copyright. No part of this document may be reproduced, adapted, transmitted, or stored in any form by any process (electronic or otherwise) without the specific written consent of Woodside. All rights are reserved.

Controlled Ref No. W1000SM002 DRIMS No. 3205381 Revision : 1 Page 34

DRIMS Classification/No. Uncontrolled when printed, unless stamped in Red to the contrary.

6.3.8 Antiskid System for Helidecks The Principal shall specify the friction coefficient and test method of anti skid coating systems applied to helidecks.

6.3.9 Final Inspection As part of the Quality Assurance, a final inspection shall be conducted prior to the final acceptance of the paintwork. Part of this final inspection shall be a visual check of the appearance and over blast of the coating work, checks on DFT’s of the total applied coating system and work completed. The Contractor and the Principal shall both be represented and they shall sign an agreed acceptance form to be part of the warranty agreement. As part of the acceptance procedure, a report shall be prepared that shall at least include:

• General

Names of the Contractor and the responsible personnel.

Scope of work

Dates when work was carried out.

Good quality copies of the work and quality plan

Deviations from this Standard and the quality plan

• Inspection equipment

Type and calibration of instruments used.

Surface preparation

Condition of surface before preparation

Checks on the requirements as specified for cleaned surfaces (refer to 5.2)

• Coating application

Information on coating systems being applied (i.e. product names, batch numbers, DFT’s etc)

Checks on requirements as specified for coating application (refer to 5.3)

Check on dry film thicknesses of the total coating system applied.

• Inspection reports

A good quality copy of the inspection reports of the Contractor

Inspection reports from an independent third party.

6.4 COMMISSIONING / HANDOVER As part of the commissioning process to handover the facility to operations the project engineer shall be responsible for the preparation of the following reports and the inclusion of them in the deliverables for the project:

Page 35: Standard Protective Coatings

This document is protected by copyright. No part of this document may be reproduced, adapted, transmitted, or stored in any form by any process (electronic or otherwise) without the specific written consent of Woodside. All rights are reserved.

Controlled Ref No. W1000SM002 DRIMS No. 3205381 Revision : 1 Page 35

DRIMS Classification/No. Uncontrolled when printed, unless stamped in Red to the contrary.

• Coating selection design basis

• As installed coating structure inventory report

• Installed condition assessment report The coating selection design basis should include the design rationale for all coatings used offshore including supporting technical selection criteria covering the areas of design life, manning strategy, environment, materials of construction, maintenance philosophy, economics and any special conditions. The inventory report should include location, dimensions, and type of substrate, configuration, process, previous surface preparation, and coating plans, specifications, history and any other pertinent information. The installed condition report shall comprise a detailed visual assessment in line with the requirements of SSPC PA 5.

Page 36: Standard Protective Coatings

This document is protected by copyright. No part of this document may be reproduced, adapted, transmitted, or stored in any form by any process (electronic or otherwise) without the specific written consent of Woodside. All rights are reserved.

Controlled Ref No. W1000SM002 DRIMS No. 3205381 Revision : 1 Page 36

DRIMS Classification/No. Uncontrolled when printed, unless stamped in Red to the contrary.

7 CONTRACTOR RECORDS 7.1 RESPONSIBILITIES

The contractor is responsible for recording and logging the QA/QC reports for each module or equipment type. Production details for the execution of the work must be recorded in an efficient manner to enable productivity assessments and costs to be monitored.

7.2 SAFETY The work permits are issued by the facility but the safe work execution, from paint storage to work site clean up, is the sole responsibility of the painting contractor.

Page 37: Standard Protective Coatings

This document is protected by copyright. No part of this document may be reproduced, adapted, transmitted, or stored in any form by any process (electronic or otherwise) without the specific written consent of Woodside. All rights are reserved.

Controlled Ref No. W1000SM002 DRIMS No. 3205381 Revision : 1 Page 37

DRIMS Classification/No. Uncontrolled when printed, unless stamped in Red to the contrary.

8 COATING SYSTEMS FOR NEW CONSTRUCTION AND MODIFICATIONS

8.1 COATING SYSTEM DESIGNATION The coating system designation shall consist of a minimum 5 digits made up of the following

AA – XX - A Base Material System Number Application (New or Maintenance)

8.1.1 Base Material (first 2 digits) CS – carbon steel SS – stainless steel Al – aluminium Cu – copper

8.1.2 System Code (second 2 digits) 01, 02 etc

8.1.3 Application N – new construction or modification M – maintenance

8.2 EQUIVALENTS TABLE The following table provide the old systems as per W9000SM001 and the equivalent new systems to assist in familiarising with the new systems.

Old System New Standard systems Typical Applications Construction Maintenance SYSTEM 1 a, 1 b

Onshore and Offshore General Marine berths, offshore platform topsides and similar structures Process piping Trunkline onshore facilities Deck plate

CS-01N CS-01M

SYSTEM 2a, 2b

Offshore trafficable decks and walkways

CS-5N, CS-07N CS-06M, CS-07M

SYSTEM 3 Galvanised steel, piping, equipment, handrails Structural studbolts and fixings (carbon steel, galvanised, and cadmium plated Fire hydrants Cable tray

CS-18N, CS-16M

SYSTEM 4 Onshore and offshore galvanised deck gratings

Page 38: Standard Protective Coatings

This document is protected by copyright. No part of this document may be reproduced, adapted, transmitted, or stored in any form by any process (electronic or otherwise) without the specific written consent of Woodside. All rights are reserved.

Controlled Ref No. W1000SM002 DRIMS No. 3205381 Revision : 1 Page 38

DRIMS Classification/No. Uncontrolled when printed, unless stamped in Red to the contrary.

Old System New Standard systems Typical Applications Construction Maintenance SYSTEM 5 Wet process surfaces whilst in

service (condensation) Fuel gas piping

CS-01N CS-17M

SYSTEM 6 Insulated services (-35oC to 60oC) CS-02N CS-02M SYSTEM 7 Structural surface which include

friction grip mating (faying) surfaces Structures which include mating surfaces for bolted structural joints

CS-01N CS-01M

SYSTEM 8 Surfaces requiring hand or power tool preparation Equipment sensitive to abrasive blasting

CS-18M

SYSTEM 9 Onshore and offshore transportable equipment (skips, racks, pallets, etc) Containers Heavy tools Frequently used mobile equipment

CS-19M CS-19M

SYSTEM 10a Dry, 100oC to 400oC Insulated and non insulated equipment Electrical Switchgear & motors (carbon steel & cast iron)

CS-22N CS-23M

SYSTEM 10b Dry, 400oC to 600oC Insulated and non insulated equipment

CS-03N, CS-04N

CS-03M, CS-04M

SYSTEM 11a Wet, to 120°C constant or 150°C intermittent Insulated and non insulated equipment

CS-02N CS-02M

SYSTEM 11b Cyclic wet, 250oC to 400oC Insulated and non insulated equipment (DRIERS)

CS-04N CS-04M

SYSTEM 11c Cyclic wet, 400oC to 600oC Insulated and non insulated equipment

CS-03N CS-04M

SYSTEM 12 Jacket legs, conductors, piles, structural steel Pump columns Caissons Sheet steel piling

CS-16N CS-15M

SYSTEM 13 Subsea valves, templates, support frames, pipe spools Bar screens, pumps Sheet steel and jetty piling Submerged Structures

CS-17N CS-15M

Page 39: Standard Protective Coatings

This document is protected by copyright. No part of this document may be reproduced, adapted, transmitted, or stored in any form by any process (electronic or otherwise) without the specific written consent of Woodside. All rights are reserved.

Controlled Ref No. W1000SM002 DRIMS No. 3205381 Revision : 1 Page 39

DRIMS Classification/No. Uncontrolled when printed, unless stamped in Red to the contrary.

Old System New Standard systems Typical Applications Construction Maintenance SYSTEM 14 Process tank lining

Potable water tank lining, mud tanks, etc Pipe internal lining (CP insulating flanges) Storage tank bottoms and roof

CS-13N CS-13M

SYSTEM 15 Pipeline Coating CS-14N, CS-15N

CS-14M

SYSTEM 16a Less than 100oC Process equipment, ducting and piping

SS-01N SS-01M

SYSTEM 16b Cyclic wet below 100oC Protection beneath insulation on insulated process equipment and piping

SS-02N SS-02M

SYSTEM 16c Wet, to 120°C constant or 150°C intermittent Protection beneath insulation on insulated process equipment and piping

SS-02N SS-02M

SYSTEM 16d Cyclic wet over 150oC Protection beneath insulation on insulated process equipment and piping

SS-03N SS-03M, SS-04M

SYSTEM 17 Lining for drain pits and holding basins Lining for chemical loading bunds Waste water treatment tanks

CS-19N CS-20M

SYSTEM 18a Aesthetic and colour coding of plastics, rubber, fibre reinforced plastic, rigid non-metallic surfaces

CS-20N CS-21M

SYSTEM 18b Flexible fibre reinforced plastic, flexible non-metallic surfaces

CS-21N CS-22M

SYSTEM 19 Aluminium junction boxed, cabinets, guards

Al-01N Al-01M

SYSTEM 20 Copper and copper alloy castings, piping and equipment

Cu-01N Cu-01M

NEW FPSO decks and floor/light and normal duty

CS-06N CS-06M

NEW Hull of Floating production storage & offloading (FPSO) vessel

CS-08N, CS-09N

CS-08M, CS-09M

NEW FPSO ballast and void tanks CS-10N CS-10M NEW Passive fire protection CS-12N, CS-

13N CS-11M, CS-12M

Page 40: Standard Protective Coatings

This document is protected by copyright. No part of this document may be reproduced, adapted, transmitted, or stored in any form by any process (electronic or otherwise) without the specific written consent of Woodside. All rights are reserved.

Controlled Ref No. W1000SM002 DRIMS No. 3205381 Revision : 1 Page 40

DRIMS Classification/No. Uncontrolled when printed, unless stamped in Red to the contrary.

8.3 COATING SYSTEMS FOR NEW CONSTRUCTION AND MODIFICATIONS 8.3.1 Carbon and Low alloy Steels – External

SYSTEM CODE PREVIOUS EQUIVALENT

TYPICAL APPLICATION SURFACE PREP/

PROFILE

COAT PRODUCT DESCRIPTION DFT RANGE

(μm)

PRODUCT CODE

COMMENTS

CS-01N SYSTEM 1a, 1b, 5, 7(1),

Atmospheric zone & under insulation -20 up to + 100 oC

Class 2 1/2 1 2 3

Zinc rich primer Epoxy high build Gloss Acrylic Urethane

(Total DFT)

50-100 200 – 350 60 – 75 310 - 525

2p 2c 1t

Facility Design life < 20 years or where appropriate: Omit Coat 3 under insulation > 20 yrs use CS-04N as preferred coating system on critical items. Note (1)

CS-02N

New, replaces (6, 11a)

Atmospheric zone & under insulation -170 up to 200 oC

Class 2 1/2 1 2 3

Epoxy Phenolic Epoxy Phenolic Epoxy Phenolic

(Total DFT)

80 – 100 80 – 100 80 - 100 240 - 300

2h 2h 2h

Design life < 20 years or any cryogenic service > 20 yrs use CS-04N for temp -20 oC to + 200 oC

CS-03N 10b, 11c Atmospheric zone > 200 to 450 oC

Class 2 ½ 1 2

Inorganic zinc silicate Al pigmented silicone(mist coat) Al pigmented silicone

(Total DFT)

50 - 70 25 – 40 25 – 40 75 - 110

1p 3h 3h

Design life < 20 years or where appropriate > 20 yrs use CS-04N as preferred coating system on critical items. For T > 450 oC consult materials engineer

CS-04N New (replaces 10b, 11b)

Insulated/ un insulated >200 to 400 oC or immersion/splashzone service (see comments)

Class 3 75 – 125 μm profile

1 2 3 4

Thermal spray aluminium (TSA) Thermal spray aluminium (TSA) Heat resistant silicone Heat resistant silicone

(Total DFT)

100 – 150 100 – 150 20 – 30 20 – 30 240 - 360

1h 1h 3h 3h

Any design life. For applications requiring colour & where sealer product performance data is available to confirm equivalent life replace silicone with epoxy or vinyl ester sealer

CS-05N System 2a, 2b Platform decks and floor/light and normal duty

Class 2 ½ 1 2 3

Epoxy primer High build high solids epoxy Gloss Acrylic Urethane

(Total DFT)

30 - 50 300 - 500 60 – 75 390 - 625

7p 5c 1t

Notes (2), (3), (4), (5), (6) Gloss topcoat applied to walkways only

CS-06N New FPSO decks and floor/light and normal duty

Class 2 ½ 1 2 3

Aluminium loaded pure epoxy Aluminium loaded pure epoxy Gloss Acrylic Urethane

(Total DFT)

150 - 200 150 – 200 60 – 75 360 - 475

11c 11c 1t

Notes (4)

Gloss topcoat applied to walkways only

CS-07N System 2a, 2b Steel floors / heavy duty & Helidecks (non skid (1))

Class 2 ½ 75 – 125 μm profile

1 2 3

Epoxy primer Ultrahigh build epoxy Gloss Acrylic Urethane

(Total DFT)

30 - 50 600 – 800 60 – 75 690 - 925

7p 4c 1t

Notes (2), (3), (4), (5)

Gloss topcoat applied to walkways & helideck only

CS-08N New Hull of floating vessel (FPSO) Class 2 ½ 1 2 3 4

Aluminium loaded pure epoxy Aluminium loaded pure epoxy Silicone based anti-foul tie coat Silicone fouling release coating

Total (DFT)

150 - 250 150 - 250 100 – 125 150 – 175 550 - 800

11c 11c 3a 2a

Infrequent dockings (15 yrs +)

CS-09N New Hull of floating vessel (FPSO) Class 2 ½ 1 2 3 4-6

Tar free modified epoxy Tar free modified epoxy Modified epoxy tie coat Self polishing co-polymer antifoulant

(Total DFT)

125 - 150 125 – 150 100 - 125 75 – 100 475 - 525

13c 13c 5p 1a

Regular 5 yearly Dockings to refurbish antifouling

Notes: (1) For surfaces requiring friction grip, faying surfaces or mating surfaces for bolted structural joints apply rapid cure version of primer 2p. Do not topcoat mating faces (2) An aggregate of fused alumina (grade AFM3-1) shall be broadcast onto the freshly applied high build epoxy on decks and walkways to provide uniform full coverage of the surface at a nominal coverage rate of 2.5 kg/m2. The aggregate may be lightly rollered in if required. (3) Upon the coating reaching full cure, any loose aggregate particles shall be vacuumed off. (4) The edges of the escape routes shall be identified by painting a 100 mm wide strip using product code 1t colour AS2700 Y14 Golden Yellow and other markings as required

(5) For smaller areas, with untarnished Class 2 ½ blast, UHB can be applied direct (i.e. with no primer). (6) Check surface for amine bloom (greasy surface) on epoxy after cure – water wash with 130 -200 Bar fresh water or solvent wipe or if past recoat interval abrasive whip for key.

Page 41: Standard Protective Coatings

This document is protected by copyright. No part of this document may be reproduced, adapted, transmitted, or stored in any form by any process (electronic or otherwise) without the specific written consent of Woodside. All rights are reserved.

Controlled Ref No. W1000SM002 DRIMS No. 3205381 Revision : 1 Page 41

DRIMS Classification/No. Uncontrolled when printed, unless stamped in Red to the contrary.

Carbon and Low alloy Steels – External (cont.) SYSTEM CODE

PREVIOUS EQUIVALENT

TYPICAL APPLICATION SURFACE PREP/

PROFILE

COAT PRODUCT DESCRIPTION DFT RANGE

(μm)

PRODUCT CODE

COMMENTS

CS-10N New FPSO Seawater ballast and void tanks

Class 2 ½

1 2

Aluminium loaded pure epoxy Aluminium loaded pure epoxy (stripe coat) Aluminium loaded pure epoxy

Total (DFT)

175 – 200 50 – 100 175 – 200 350 - 400

11c 11c 11c

Infrequent dockings (15 yrs +) Operation up to 60 oC Stripe coat to be different colour to full coat

CS-11N New Passive fire Protection T < 80 oC Class 2 ½ 1 2 3 4

Epoxy primer PFP Epoxy PFP Epoxy Gloss Acrylic Urethane

(Total DFT)

30 - 50 TBA TBA 60 – 75 TBA

7p 12c 12c 1t

TBA - PFP thickness to be calculated by supplier to achieve fire type & duration specified

CS-12N New Passive fire Protection 80 oC > T < 150 oC

Class 2 1/2 1 2 3 4

Epoxy primer Epoxy Insulation PFP Epoxy Gloss Acrylic Urethane

(Total DFT)

30 - 50 TBA TBA 60 – 75 TBA

7p 15c 12c 1t

TBA – Insulation & PFP thickness to be calculated by supplier to achieve fire type & duration specified. For areas where surface temps can occur in range of 80oC to 150oC due to external sources of heat (e.g. flare, solar, etc), change the application order to apply PFP epoxy one step before the Epoxy insulation.

CS-13N System 14 Internal Lining - Tanks (Pot water, diesel, mud tanks etc

Class 3 1 High build solvent free epoxy High build solvent free epoxy

Total (DFT)

200 - 250 200 – 250 400 - 500

7c 7c

Can be applied wet on wet to achieve final DFT Spark test as per 5.3.6 Pot water tank linings to be certified suitable for such (e.g. NSF/ANSI 61)

CS-14N New Buried parts < 60 oC (+ cathodic protection)

Class 2 ½ 1 High build sintered MDPE to AS4321

Manf spec Joints as per system CS-15N

CS-15N System 15 Buried parts < 60 oC (+ cathodic protection)

Class 2 1/2 1 2 3

Bituminous Primer Self Adhesive Bituminous Rubber Self Adhesive Bituminous Rubber with PVC backing

8-10 m2/l 55% overlap 55% overlap

T1 T2 T3

Requires spark testing as per 5.3.6

CS-16N System 12 Splash zones for jackets & fixed installations

Class 3 1 Ultrahigh build epoxy Antifouling tie Coat 1 Antifouling 2

Total (DFT)

2500 – 3000 100 - 125 Note (2) 2500 - 3000

4c Design life < 20 years For design life > 20 years use CS-04N with Al silicone or epoxy sealer. Antifouling may be deleted if not required

CS-17N System 13 Immersed in water < 70 oC Class 2 ½ 1 High build, high solids epoxy suitable for immersion service

Total (DFT)

400 – 500 400 - 500

5c Design life < 20 years Add antifouling as per systems 08N, 09N as required for ROV interfaces etc3.

CS-18N System 3, 4 Galvanised steel < 100 oC (piping, handrails etc)

Class 2 ½ 1 2 3 4

HDG to AS 4680 600 g/m2 Sweep blast or Etch prime Self priming Epoxy Mastic Acrylic Urethane

Total (DFT)

85 – 200 10 – 20 100 – 150 60 - 75 170 - 245

None 6p 1c 1t

Design life < 10 yrs Design life > 10 yrs, use FRP grating

CS-19N System 17 Drain Pits and Chemical Splash Zones onshore

As per Section 4.8

1 2 3

Concrete Primer High Build high Solids Glass Filled Vinyl Ester Acid/Alkali resistant coating

Total (DFT)

50 – 75 750 – 1500 600 – 700 1400 - 2275

4p 8c 4t

CS-20N System 18a Aesthetic & Colour coding of non metallics

As per Note (1)

1 2

Water Borne Gloss Acrylic Water Borne Gloss Acrylic

Total (DFT)

50 - 75 50 – 75 100 - 150

2t 2t

1 Antifouling tie-coat to be selected depends on system type. For SPC copper based system use 5p. For silicone fouling release use 3a 2 Antifouling to be selected depends on type. For SPC copper based system use 3 coats system 1a of 75 – 100 microns DFT. For silicone fouling release use 1 coat of system 2a 150 – 175 microns DFT. 3 The use of an environmentally friendly fluorescent anti-fouling labelling system such as Aquasign™ is acceptable for sub-sea markings.

Page 42: Standard Protective Coatings

This document is protected by copyright. No part of this document may be reproduced, adapted, transmitted, or stored in any form by any process (electronic or otherwise) without the specific written consent of Woodside. All rights are reserved.

Controlled Ref No. W1000SM002 DRIMS No. 3205381 Revision : 1 Page 42

DRIMS Classification/No. Uncontrolled when printed, unless stamped in Red to the contrary.

Carbon and Low alloy Steels – External (cont.) SYSTEM CODE

PREVIOUS EQUIVALENT

TYPICAL APPLICATION SURFACE PREP/ PROFILE

COAT PRODUCT DESCRIPTION DFT RANGE (μm)

PRODUCT CODE

COMMENTS

CS-21N System 18b Aesthetic & Colour coding of flexible hoses and related non metallics

As per Note (1)

1 Flexible high build Acrylic Flexible high build Acrylic

Total (DFT)

100 – 150 100 – 150 200 - 300

3t 3t

Also sealant for insulation and cladding

CS-22N System 10a Insulated & non insulated equipment 100 – 400 oC; electrical switchgear & motors (CS & CI)

Class 2 1/2 1 Inorganic zinc silicate 75 - 90 1p Inside humidity controlled spaces only

NOTES: (1) Degrease area in accordance with AS 1627.1. Do not use solvents or chemicals that will affect the integrity of the substrate. Abrade lightly as required.

8.3.2 Stainless Steels – External Austenitic stainless steels (e.g. 316L) shall not normally be used in pressure containing service above 60 oC ( Duplex ss 100 oC) where it is exposed to the external atmosphere without a lifetime coating such as TSA. Requests to operate these materials above the nominated temperature limits in service need the written approval of the TA.

SYSTEM

CODE PREVIOUS

EQUIVALENT TYPICAL APPLICATION SURFACE

PREP/ PROFILE

COAT PRODUCT DESCRIPTION DFT RANGE

(μm)

PRODUCT CODE

COMMENTS

SS-01N System 16a Atmospheric zone -20 up to + 100 oC

Class 2 ½ 1 2

Epoxy primer Gloss Acrylic Urethane

(Total DFT)

30 - 50 80 – 160 110 – 210

7p 1t

Design life < 20 years or where appropriate > 20 yrs use SS-04N as preferred coating system on critical items

SS-02N System 16c, 16b

Atmospheric zone + 100 up to 200 oC and under insulation from -170 oC to 200 oC.

Class 2 ½ 1 2

Epoxy Phenolic Epoxy Phenolic

(Total DFT)

80 – 100 80 – 100 160 – 200

2h 2h

Design life < 20 years or cryogenic service > 20 yrs use SS-04N as preferred coating system on critical items

SS03N System 16d Atmospheric Zone > 200 to 450 oC

Class 2 ½ 1 2

Al pigmented silicone Al pigmented silicone

(Total DFT)

25 – 40 25 – 40 50 – 80

3h 3h

Design life < 20 years or where appropriate > 20 yrs use SS-04N as preferred coating system on critical items

SS-04N System 16d Insulated/ non insulated from >200 to 400 oC

Class 3 75 – 125 μm profile

1 2 3 4

Thermal spray aluminium (TSA) Thermal spray aluminium (TSA) Heat resistant silicone Heat resistant silicone

(Total DFT)

100 – 150 100 – 150 20 – 30 20 – 30 240 - 360

1h 1h 3h 3h

Any design life. For use at ambient conditions (T < 100 oC) replace Al silicone with approved epoxy sealer DSS T > 100 oC & any temp under insulation 316ss T > 60 oC & any temp under insulation

SS-05N New Buried parts < 60 oC (+ cathodic protection)

Class 2 ½ 1 High build sintered MDPE to AS 4321

Manf spec S1 Joints as per system SS-06N

SS-06N System 15 Buried parts < 60 oC (+ cathodic protection)

1 2 3

Bituminous Primer Self Adhesive Bituminous Rubber Self Adhesive Bituminous Rubber with PVC backing

8-10 m2/l 55% overlap 55% overlap

T1 T2 T3

Requires spark testing as per 5.3.6

8.3.3 Non-Ferrous Materials - External

SYSTEM CODE

PREVIOUS EQUIVALENT

TYPICAL APPLICATION SURFACE PREP/

PROFILE

COAT PRODUCT DESCRIPTION DFT RANGE

(μm)

PRODUCT CODE

COMMENTS

Al-01N System 19 Aluminium junction boxes, handrails etc

Sa 1 - 2 1 2

Epoxy primer Acrylic Urethane

(Total DFT)

30 – 50 60 – 75 90 - 125

7p 1t

Cu-01N System 20 Copper and Copper alloys Sa 1 - 2 1 2 3

Epoxy primer High build epoxy Acrylic Urethane

(Total DFT)

30 - 50 150 - 200 60 – 75 240 - 325

7p 2c 1t

Topcoat not required for immersion

Page 43: Standard Protective Coatings

This document is protected by copyright. No part of this document may be reproduced, adapted, transmitted, or stored in any form by any process (electronic or otherwise) without the specific written consent of Woodside. All rights are reserved.

Controlled Ref No. W1000SM002 DRIMS No. 3205381 Revision : 1 Page 43

DRIMS Classification/No. Uncontrolled when printed, unless stamped in Red to the contrary.

8.4 COATING SYSTEMS FOR MAINTENANCE 8.4.1 Carbon and Low alloy Steels – External

SYSTEM CODE

PREVIOUS EQUIVALENT

TYPICAL APPLICATION SURFACE PREP/

PROFILE

COAT PRODUCT DESCRIPTION DFT RANGE (μm)

PRODUCT CODE

COMMENTS

CS-01M SYSTEM 1A, 1B, 5, 7

Atmospheric zone & under insulation -20 up to + 100 oC

Class 2 ½ or NACE No. 5 WJ2L or IP HP 2.5L

1 2 3 4

Zinc rich primer Epoxy high build (stripe) Epoxy high build Gloss Acrylic Urethane

(Total DFT)

50-100 80 - 160 200 – 350 60 – 75 310 - 525

2p 2c 2c 1t

Design life < 20 years Omit urethane under insulation Stripe coat to be different colour to full coat of epoxy

CS-02M NEW (replaces 6, 11a)

Atmospheric zone & under insulation + 100 up to 200 oC

Class 2 ½ or NACE No. 5 WJ2L

1 2

Epoxy Phenolic Epoxy Phenolic

(Total DFT)

80 – 100 80 – 100 160 - 200

2h 2h

Design life < 20 years

CS-03M 10b Atmospheric zone & under insulation > 200 to 450 oC

Class 2 ½ or NACE No. 5 WJ2L or IP HP 2.5L

1 2 3

Inorganic zinc silicate Al pigmented silicone Al pigmented silicone

(Total DFT)

50 - 70 25 – 40 25 – 40 100 - 150

1p 3h 3h

Design life < 20 years Not cyclic service

CS-04M New (replaces 10b, 11b, 11c)

Under insulation >200 to 400 oC

Class 2 ½ with a 50 micron profile

1 2

Cold Spray Aluminium (CSA) Cold Spray Aluminium (CSA)

(Total DFT)

80 - 100 80 - 100 160 - 200

5h 5h

For damage down to substrate. Any design life. Can be used for services down to – 29 oC. Stripe coat all edges, welds, etc prior to first coat.

CS-05M System 2a, 2b Wet areas requiring a coating system that will cure with some moisture present

Class 2 ½ or NACE No. 5 WJ2L or IP HP 2.5L

1 2 3

Epoxy primer High build high solids epoxy Gloss Acrylic Urethane

(Total DFT)

30 - 50 300 - 500 60 – 75 390 - 625

7p 5c 1t

Notes (1), (2), (3), (4) if required Gloss topcoat applied to walkways only

CS-06M New FPSO & fixed installation decks Class 2 ½ or NACE No. 5 WJ2L or IP HP 2.5L

1 2 3

Al pigmented surface tolerant rapid cure pure epoxy primer UV resistant deck epoxy Gloss Acrylic Urethane

(Total DFT)

150 - 200 150 – 200 60 – 75 360 - 475

8p 9c 1t

Gloss topcoat applied to walkways only For non skid walkways use system CS-07M

CS-07M System 2a, 2b Steel floors / heavy duty & Helidecks (non skid (1))

Class 2 ½ 75 – 125 μm profile

1 2 3 4

Al pigmented surface tolerant rapid cure pure epoxy primer UV resistant deck epoxy UV resistant deck epoxy Gloss Acrylic Urethane

(Total DFT)

100 - 150 150 - 200 150 - 200 60 - 75 460 - 625

8p 9c 9c 1t

Notes (1), (2), (3) Gloss topcoat applied to walkways & helideck only

CS-08M New Hull of floating vessel, seawater ballast and void tanks (FPSO)

Class 2 ½ or NACE No. 5 WJ2L or IP HP 2.5L

1 High build, high solids epoxy suitable for immersion service

Total (DFT)

300 – 400 300 - 400

14c Dry dock repairs as per CS-08N, CS-09N or CS-10N depending on original system selected

CS-11M New Passive fire Protection T < 80 oC Class 2 ½ or NACE No. 5 WJ2L or IP HP 2.5L

1 2 3 4

Epoxy primer PFP Epoxy PFP Epoxy Gloss Acrylic Urethane

(Total DFT)

30 - 50 TBA TBA 60 – 75 TBA

7p 12c 12c 1t

TBA - PFP thickness to be calculated by supplier to achieve fire type & duration specified

CS-12M New Passive fire Protection 80 oC > T < 150 oC

Class 2 1/2 1 2 3 4

Epoxy primer Epoxy Insulation PFP Epoxy Gloss Acrylic Urethane

(Total DFT)

30 - 50 TBA TBA 60 – 75 TBA

7p 15c 12c 1t

TBA – Insulation & PFP thickness to be calculated by supplier to achieve fire type & duration specified. For areas where surface temps can occur in range of 80 oC to 150 oC due to external sources of heat (e.g. flare, solar, etc), change the application order to apply PFP epoxy one step before the Epoxy insulation.

CS-13M System 14 Internal Lining - Tanks (Pot water, diesel, mud tanks etc

Class 3 1 High build solvent free epoxy

Total (DFT)

400-500 400-500

7c 2 coats wet on wet acceptable Requires a spark test as per section 5.3.6

CS-14M System 15 Buried parts < 60 oC (+ cathodic protection)

1 2 3

Bituminous Primer Self Adhesive Bituminous Rubber Self Adhesive Bituminous Rubber with PVC backing

8-10 m2/l 55% overlap 55% overlap

T1 T2 T3

Requires spark testing as per section 5.3.6

Notes: (1) An aggregate of fused alumina (grade AFM3-1) shall be broadcast onto the freshly applied UV resistant epoxy (coat 2) on decks and walkways to provide uniform full coverage of the surface at a nominal coverage rate of 2.5 kg/m2. The aggregate may be lightly rollered in if required.

(2) Upon the coat 2 reaching full cure, any loose aggregate particles shall be vacuumed off followed by application of coat 3 UV resistant deck epoxy.

(3) The edges of the escape routes shall be identified by painting a 100 mm wide strip using product code 1t colour AS2700 Y14 Golden Yellow and other markings as required

(4) Check surface for amine bloom (greasy surface) on epoxy after cure – water wash with 130 -200 Bar fresh water or solvent wipe or if past recoat interval abrasive whip for key.

Page 44: Standard Protective Coatings

This document is protected by copyright. No part of this document may be reproduced, adapted, transmitted, or stored in any form by any process (electronic or otherwise) without the specific written consent of Woodside. All rights are reserved.

Controlled Ref No. W1000SM002 DRIMS No. 3205381 Revision : 1 Page 44

DRIMS Classification/No. Uncontrolled when printed, unless stamped in Red to the contrary.

Carbon and Low alloy Steels – External (cont.) SYSTEM

CODE PREVIOUS

EQUIVALENT TYPICAL APPLICATION SURFACE

PROFILE COAT PRODUCT DESCRIPTION DFT

RANGE (μm)

PRODUCT CODE

COMMENTS

CS-15M SYSTEM 13 Immersed in water < 70 oC incl spashzones

Class 2 ½ or NACE No. 5 WJ2L or IP HP 2.5L

1 High build, high solids epoxy suitable for immersion service

Total (DFT)

400 – 500 400 - 500

5c Design life < 20 years Add antifouling as per systems 08N, 09N as required

CS-16M System 3, 4 Galvanised steel < 100 oC (legacy items)

Class 1 1 2 3

Zinc rich epoxy Self priming Epoxy Mastic Gloss Acrylic Urethane

Total (DFT)

50 - 75 100 – 150 60 – 75 210 - 300

2p 1c 1t

Primer required where red rust or corrosion is evident on surface

CS-17M System 5 Wet process surfaces while in operation T < 75 oC

Class 2 ½ or NACE No. 5 WJ2L or IP HP 2.5L

1 2 3

Multi Purpose Petrolatum Primer Petrolatum Tape MP/HD Over wrap Tape (Yellow)

2-3m2/kg 55% overlap 55% overlap

P1 P2 P3

Remove as much condensation and solids debris as possible. Follow Manufacturer’s Instructions.

CS-18M System 8 Hand Power Tool Prep for short term protection

AS1627.1 St3

1 2

Self Priming Epoxy Mastic Gloss Acrylic Urethane

Total (DFT)

150 – 200 60 – 75 210 - 275

1c 1t

< 5 year life

CS-19M System 9 Onshore/Offshore Transportable equip

Class 2 ½ 1 2

Inorganic zinc silicate Acrylic Urethane (3)

Total (DFT)

75 – 90 60 – 75 135 - 165

1p 1t

Note (1)

CS-20M System 17 Drain Pits & Chemical Splash Zones

As per section 4.8

Maintenance only after consulting with Corrosion/Materials Engineer

CS-21M System 18a Aesthetic, UV protection & Colour coding of non metallics

As per Note (2)

1 Water Borne Gloss Acrylic Water Borne Gloss Acrylic

Total (DFT)

50 – 75 50 - 75 100 - 150

2t 2t

CS-22M System 18b Aesthetic & Colour coding of flexible hoses and related non metallics

As per Note (2)

1 Flexible high build Acrylic Flexible high build Acrylic

Total (DFT)

100 – 150 100 – 150 200 - 300

3t 3t

Also sealant for insulation and cladding

CS-23M System 10a Insulated & non insulated equipment 100 – 400 oC; electrical switchgear & motors (carbon steel & cast iron

Class 2 1/2 1 Inorganic zinc silicate 75 - 90 1p Inside humidity controlled spaces only

Notes: (1) Onshore Application Only

(2) Topcoat only where aesthetics or colour coding require it

(3) Skip or container end surfaces to be painted white for load markings

Page 45: Standard Protective Coatings

This document is protected by copyright. No part of this document may be reproduced, adapted, transmitted, or stored in any form by any process (electronic or otherwise) without the specific written consent of Woodside. All rights are reserved.

Controlled Ref No. W1000SM002 DRIMS No. 3205381 Revision : 1 Page 45

DRIMS Classification/No. Uncontrolled when printed, unless stamped in Red to the contrary.

8.4.2 Stainless Steels – External Austenitic stainless steels (e.g. 316L) shall not normally be used in pressure containing service above 60 oC (Duplex ss 100 oC) where it is exposed to the external atmosphere without a lifetime coating such as TSA. Requests to operate these materials above the nominated temperature limits in service need the written approval of the TA.

SYSTEM CODE

PREVIOUS EQUIVALENT

TYPICAL APPLICATION SURFACE PROFILE

COAT PRODUCT DESCRIPTION DFT RANGE

(μm)

PRODUCT CODE

COMMENTS

SS-01M System 16 Atmospheric zone -20 up to + 100 oC

Class 2 1/2 1 2

Epoxy primer Gloss Acrylic Urethane

(Total DFT)

30 - 50 60 - 75 90 - 125

7p 1t

Design life < 20 years

SS-02M System 16c, 16b

Atmospheric zone : + 100 up to 200 oC and insulated from -170 oC to 200 oC.

Class 2 1/2 1 2 3

Epoxy Phenolic Epoxy Phenolic Epoxy Phenolic

(Total DFT)

80 – 100 80 – 100 80 - 100 240 - 300

2h 2h 2h

Design life < 20 years or cryogenic service DSS T > 100 oC 316L SS T > 60 oC

SS03M System 16d Atmospheric Zone > 200 to 450 oC

Class 2 ½ 1 2

Al pigmented silicone Al pigmented silicone

(Total DFT)

25 – 40 25 – 40 50 - 80

3h 3h

Design life < 20 years

SS-04M New, System 16d

Insulated/ non insulated from +200 to 400 oC

Class 2 ½ with a 50 micron profile

1 2

Cold Spray Aluminium (CSA) Cold Spray Aluminium (CSA)

(Total DFT)

80 - 100 80 - 100 160 - 200

5h 5h

For damage down to substrate. Any design life. Can be used for services down to – 29 oC. Stripe coat all edges, welds, etc prior to first coat.

SS-05M System 15 Buried parts < 60 oC (+ cathodic protection)

Class 2 1/2 1 2 3

Bituminous Primer Self Adhesive Bituminous Rubber Self Adhesive Bituminous Rubber with PVC backing

8-10 m2/l 55% overlap 55% overlap

T1 T2 T3

Requires spark testing

8.4.3 Non-Ferrous Materials – External

SYSTEM CODE

PREVIOUS EQUIVALENT

TYPICAL APPLICATION SURFACE PROFILE

COAT PRODUCT DESCRIPTION DFT RANGE

(μm)

PRODUCT CODE

COMMENTS

Al-01M System 19 Aluminium junction boxes, handrails etc

Sa 1 - 2 1 2

Epoxy primer Acrylic Urethane

(Total DFT)

30 – 50 60 – 75 90 - 125

7p 1t

Cu-01M System 20 Copper and Copper alloys Sa 1 - 2 1 2 3

Epoxy primer High build epoxy Acrylic Urethane

(Total DFT)

30 - 50 150 - 200 60 – 75 210 - 325

7p 2c 1t

Topcoat not required for immersion

Page 46: Standard Protective Coatings

This document is protected by copyright. No part of this document may be reproduced, adapted, transmitted, or stored in any form by any process (electronic or otherwise) without the specific written consent of Woodside. All rights are reserved.

Controlled Ref No. W1000SM002 DRIMS No. 3205381 Revision : 1 Page 46

DRIMS Classification/No. Uncontrolled when printed, unless stamped in Red to the contrary.

9 PRODUCT CODE AND APPROVAL LIST AT DECEMBER 2006 It is the responsibility of the project engineer in consultation with the Woodside TA and the coating vendor to verify that the products selected below can meet the system service requirements as detailed in sections 8 & 9 of this document.

PRODUCT CODE PRODUCT DESCRIPTION INTERNATIONAL SIGMA AMERON JOTUN

OTHER (APPROVAL REQUIRED)

PRIMERS 1p Inorganic Zinc Silicate Primer Interzinc 22 / 86 Sigmazinc 158 Ameron D9 Resist 86 AU 2p Zinc Rich Epoxy Primer Interzinc 52 / 315 Sigmazinc 102/

109HS Amercoat 68HS/471

Barrier

4p Concrete Primer Interline 949 Sigmacover 256 Ameron Permaclad VE EPL Primer

Chemclear

5p Modified Epoxy Tie Coat Intergard 263 Sigmacover 525 Amerlock 2K Jotamastic 87 6p Etch Primer - Zinc Interprime 741 Sigma Etch MultiEtch 531A Jota-etch AU 7p Non – inhibiting epoxy primer

for UHPWB or Abrasive blasting

Intergard 269 Sigmacover 256 Amercoat 182ZPK Penguard Special

8p Marine epoxy primer for UHPWJ

Interbond 373 Sigmacover 280 Amerlock 2K Jotamastic 87

CORROSION COAT 1c Self Priming Epoxy Mastic Interseal 670HS Sigmacover 630 Amerlock 400 Jotamastic 87 2c High Build Epoxy Intergard 475 /

Intercure 420 Sigmacover 410 Amerlock 2K /

Amercoat 472 Jotacote 605

4c Ultra High Build Epoxy Interzone 485 Sigmashield 1090

Amercoat CC703/2

Jotacote UHB

5c High Build High Solids Surface Tolerant Epoxy

Interzone 954 Sigmacover TCP coating

Amercoat CC 89 Jotazone

7c High Build Solvent Free Epoxy Interline 975 SF Sigmaguard CSF 650

Amercoat CC 703/3

Jotacote 410

8c High Build High Solids Glass Filled Vinyl Ester

Interline 955 Corrocoat Polyglass VEF

Permaclad VE504 EPL GF

Chemflake II

9c UV resistant Deck Epoxy Interbond 501 Sigmacover 456 Amerlock 2K 11c Aluminium loaded pure epoxy

(min 9% Al by Wt) EN300 Sigmaprime 200

12c Epoxy Intumescent Fireproofing Coating

Chartek 7 Firebarr 2000 Leigh’s Firetex M90

13c Tar free modified epoxy Intergard 403 Sigmaguard 440 14c High Build, High Solids Al

loaded Surface Tolerant Epoxy for Marine Applications

Interbond 808 Sigmacover 630 Alum

15c Epoxy Insulation Intertherm 7050 TOP COAT

1t Gloss 2 Pack Acrylic Polyurethane

Interfine 990 Sigmadur 750 Amercoat 450K/ Amershield

Hardtop AS

2t Water Borne Gloss Acrylic Intercryl 853 Sigma Vikote 56 PPG Gloss Trade Acrylic

Jotun Acrylic Gloss

3t Flexible High Build Acrylic Intercryl 988 Sigmaguard 790 Amercoat 228 4t Acid/Alkali Resistant Coating Interline 955 Permaclad VE504

EPL Chemflake II

5t

Acid/ Alkali Resistant Coating Interline 955 Corrocoat Polyglass VEF

Permaclad VE504 EPL

Tankguard Storage

Page 47: Standard Protective Coatings

This document is protected by copyright. No part of this document may be reproduced, adapted, transmitted, or stored in any form by any process (electronic or otherwise) without the specific written consent of Woodside. All rights are reserved.

Controlled Ref No. W1000SM002 DRIMS No. 3205381 Revision : 1 Page 47

DRIMS Classification/No. Uncontrolled when printed, unless stamped in Red to the contrary.

PRODUCT CODE AND APPROVAL LIST AT DECEMBER 2006 (cont.)

PRODUCT CODE PRODUCT DESCRIPTION INTERNATIONAL SIGMA AMERON JOTUN

OTHER (APPROVAL REQUIRED)

HEAT RESISTANT COATINGS 1h Thermally Sprayed Aluminium

(TSA) 99.5 Al wire complying to UNS A91350 or AWS W-Al-1350

2h Epoxy Phenolic Intertherm 228 Sigma Phenguard

Amercoat 91 Epoxy HR

3h Silicone Based heat Resistant Coating

Intertherm 50 Sigmatherm 540 Solvalitt

4h Inorganic Butyl Titanate Coating (legacy systems only)

Intertherm 510 N/A N/A Jotacote T300

5h Aluminium loaded inorganic coating suitable for thermal cyclic service to 400 oC

Intertherm 751 CSA

ANTI-FOULING 1a Self Polishing Copolymer Anti-

Fouling Intersmooth Ecoloflex 360

Sigma Alphagen 650

Seaquantum Ultra

2a Silicone fouling release coating Intersleek 425

Sigmaglide 890 ABC Release 671 Sea-Lion

3a Silicone fouling release tie coat Intersleek 386 Sigmaglide 790 ABC Release 670 Sea-Lion Tie Coat PETROLATUM

P1 Petrolatum Primer Denso, Petro Coating

P2 Petrolatum Tape Denso, Petro Coating

P3 MP/HD Tape Overwrap Denso, Petro Coating

TAPE WRAP T1 Bituminous Primer Denso, Petro

Coating T2 Self Adhesive Bituminous

Rubber Denso, Petro

Coating T3 Self Adhesive Bituminous

Rubber with PVC Backing Denso, Petro

Coating PIPELINE COATING

S1 Sintered Medium Density Polyethylene* to AS 4321

E.g. Tycowater Sintapipe or equivalent

Note* Product selection will be dependant on application/ service requirements.

Page 48: Standard Protective Coatings

This document is protected by copyright. No part of this document may be reproduced, adapted, transmitted, or stored in any form by any process (electronic or otherwise) without the specific written consent of Woodside. All rights are reserved.

Controlled Ref No. W1000SM002 DRIMS No. 3205381 Revision : 1 Page 48

DRIMS Classification/No. Uncontrolled when printed, unless stamped in Red to the contrary.

10 OFFSHORE COLOUR CODE 10.1 OFFSHORE – TYPICAL STRUCTURES

These colour codes are specified for new projects and strongly recommended for existing facilities. Should the existing equipment be different to those colours below, and there are economic, aesthetic and safety reasons for remaining with them, a variation is not required.

COLOUR STANDARDS – GENERAL PURPOSE

TYPICAL STRUCTURES COLOUR DESCRIPTION

AS 2700 S – 1996 NOMENCLATURE

PRACTICAL EQUIVALENT

Steelwork all Topsides structural Steelwork unless otherwise specified

Orange X24 Rockmelon BS 5252 06E51

All Substructural steelwork Grey N45 Koala Grey BS 5252 10A07 Tanks and coated exterior wall cladding

Off White Y35 Off White BS 5252 10B15

Accommodation, storerooms and other interior living and workroom areas

Per Architectural Schedule

Firewalls (If painted) Off White Y35 Off White BS 5252 10B15 Painted Floor Decks/Walkways

Grey N22 Cloud Grey BS 5252 10A03

Access/Escape Routes Black with Yellow Stripes

N61 Black Y14 Golden Yellow

BS 5252 00E53 BS 5252 08E51

Overhead Obstructions Yellow with Black Stripes

Y14 Golden Yellow N61 Black

BS 5252 08E51 BS 5252 00E53

Monorails/Hoists Yellow Y14 Golden Yellow BS 5252 08E51 Handrails Yellow Y14 Golden Yellow BS 5252 08E51 Ladder Cages Colour of Structure Clean-Up Burner Orange X24 Rockmelon BS 5252 06E51 Piperacks Off White Y35 Off White BS 5252 10B15 Lifeboat Davits White N14 White BS 5252 00E55 Gratings Brown X54 Brown BS 5252 06C39 Pipe Supports Off White Y35 Off White BS 5252 10B15

Page 49: Standard Protective Coatings

This document is protected by copyright. No part of this document may be reproduced, adapted, transmitted, or stored in any form by any process (electronic or otherwise) without the specific written consent of Woodside. All rights are reserved.

Controlled Ref No. W1000SM002 DRIMS No. 3205381 Revision : 1 Page 49

DRIMS Classification/No. Uncontrolled when printed, unless stamped in Red to the contrary.

10.2 OFFSHORE – HVAC DUCTING COLOUR STANDARDS – GENERAL PURPOSE

HVAC DUCTING COLOUR DESCRIPTION

AS 2700 S – 1996 NOMENCLATURE

PRACTICAL EQUIVALENT

Conditioned Air

Red with Blue Bands

R13 Signal Red T11 Tropical Blue

BS 381C 537 BS 5252 18E53

Fresh Air Green G37 Beanstalk BS 5252 14E51 Extract/Recirculated Air Grey N22 Cloud Grey BS 5252 10A03 Exhaust Air Brown with

Off White Bands X54 Brown

Y35 Off White BS 5252 06C39 BS 5252 10B15

10.3 OFFSHORE – MISCELLANEOUS ITEMS COLOUR STANDARDS – GENERAL PURPOSE

MISCELLANEOUS COLOUR DESCRIPTION

AS 2700 S – 1996 NOMENCLATURE

PRACTICAL EQUIVALENT

Platform Pedestal Cranes Refer Crane Specification A1840SM530 Orange

X24 Rockmelon BS 5252 06E51

Lifeboats Orange X24 Rockmelon BS 5252 06E51 Lagging Aluminium or

stainless steel jacket unpainted. Colour of service banded only.

Cladding (If coated) Off White Y35 Off White BS 5252 10B15 Flare Tip Handling System Yellow Y14 Golden Yellow BS 5252 08E51 Riser Turret Mooring Yellow Y14 Golden Yellow BS 5252 08E51

Page 50: Standard Protective Coatings

This document is protected by copyright. No part of this document may be reproduced, adapted, transmitted, or stored in any form by any process (electronic or otherwise) without the specific written consent of Woodside. All rights are reserved.

Controlled Ref No. W1000SM002 DRIMS No. 3205381 Revision : 1 Page 50

DRIMS Classification/No. Uncontrolled when printed, unless stamped in Red to the contrary.

10.4 OFFSHORE – BULK PRODUCT LOADING HOSE ENDS & MANIFOLD COLOUR STANDARDS – GENERAL PURPOSE

Bulk Loading Hose Ends & manifold

COLOUR DESCRIPTION

AS 2700 S – 1996 NOMENCLATURE

PRACTICAL EQUIVALENT

Dry cement Yellow Y14 Golden Yellow BS 5252 08E51 Dry Barytes or Bentonite Orange X15 Orange BS 381C 557 Potable Water Blue T11 Tropical Blue BS 5252 18E53 Diesel / Fuel Brown X54 Brown BS 5252 06C39 Base Oil White N 14 white BS 5252 00E55 Drill Water Green G37 Beanstalk BS 5252 14E51 Oil Based Mud Black N 61 Black BS 5252 00E53 Brine Red R 13 Signal Red BS 381C 537 Glycol Purple P14 Blueberry BS 5252 22D45 Scale inhibitor No colour

10.5 OFFSHORE – PIPING COLOUR STANDARDS – GENERAL PURPOSE

PIPING P & ID

SERVICE CODE

COLOUR DESCRIPTION

AS 2700 S – 1996 NOMENCLATURE

PRACTICAL EQUIVALENT

Produced Gas PM/PG Yellow Y14 Golden Yellow BS 5252 08E51 Fuel Gas GF Yellow with

White Bands Y14 Golden Yellow

N14 White BS 5252 08E51 BS 5252 00E55

HP Injection Gas PG downstream of Gas Lift

Compressor

Yellow with Black Bands

Y14 Golden Yellow N61 Black

BS 5252 08E51 BS 5252 00E53

Condensate, Recovered Oil

OR PL

Yellow with Brown Bands

Y14 Golden Yellow X54 Black

BS 5252 08E51 BS 5252 06C39

Riser (Below Production deck)

- Grey N45 Koala Grey BS 5252 10A07

Jet Fuel – Jet A1 - Brown X54 Brown BS 5252 06C39 Hydraulic Oil (except tubing which is SS)

OH HO

Brown with Blue Bands

X54 Brown T11 Tropical Blue

BS 5252 06C39 BS 5252 18E53

Diesel Fuel OD FL

Brown with Yellow Bands

X54 Brown Y14 Golden Yellow

BS 5252 06C39 BS 5252 08E51

Valves, Traps, etc - Off White Y35 Off White BS 5252 10B15 Lube Oil OL Brown with

Orange Bands X54 Brown

X24 Rockmelon BS 5252 06C39 BS 5252 06E51

Seal Oil OS Brown with Orange Bands

X54 Brown X24 Rockmelon

BS 5252 06C39 BS 5252 06E51

Page 51: Standard Protective Coatings

This document is protected by copyright. No part of this document may be reproduced, adapted, transmitted, or stored in any form by any process (electronic or otherwise) without the specific written consent of Woodside. All rights are reserved.

Controlled Ref No. W1000SM002 DRIMS No. 3205381 Revision : 1 Page 51

DRIMS Classification/No. Uncontrolled when printed, unless stamped in Red to the contrary.

COLOUR STANDARDS – GENERAL PURPOSE PIPING

P & ID SERVICE

CODE COLOUR

DESCRIPTION AS 2700 S – 1996 NOMENCLATURE

PRACTICAL EQUIVALENT

Methanol CM Violet P14 Blueberry BS 5252 22D45 Glycol CG Violet with

Orange Bands P14 Blueberry

X24 Rockmelon BS 5252 22D45 BS 5252 06E51

Hypochlorite CH Violet with Yellow Bands

P14 Blueberry Y14 Golden Yellow

BS 5252 22D45 BS 5252 08E51

Corrosion Inhibitor CC Violet with Green Bands

P14 Blueberry G37 Beanstalk

BS 5252 22D45 BS 5252 14E51

De-emulsifier CD Violet with Black Bands

P14 Blueberry N61 Black

BS 5252 22D45 BS 5252 00E53

Anti-foam CE Violet with Brown Bands

P14 Blueberry X54 Brown

BS 5252 22D45 BS 5252 06C39

Oxygen Scavenger CL Violet with Blue Bands

P14 Blueberry T11 Tropical Blue

BS 5252 22D45 BS 5252 18E53

Reticulated Degreaser

- Brown with Black Bands

X54 Brown N61 Black

BS 5252 06C39 BS 5252 00E53

Flare HP Flare VH/BH Orange X24 Rockmelon BS 5252 06E51 LP Flare VL/BL Orange with

Blue Bands X24 Rockmelon

T11 Tropical Blue BS 5252 06E51 BS 5252 18E53

Atmospheric Vent VA Orange with Silver Grey Bands

X24 Rockmelon N24 Silver Grey

BS 5252 06E51 TBA

Water Sea Water WS Green with

Black Bands G37 Beanstalk

N61 Black BS 5252 14E51 BS 5252 00E53

Service (Utility) WD Green with White Bands

G37 Beanstalk N14 White

BS 5252 14E51 BS 5252 00E55

Jetting Water - Green with Black Bands

G22 Serpentine N61 Black

BS 381C 275 BS 5252 00E53

Potable Water OW/WZ/WP Light Green G36 Kikuyu BS 5252 12E53 Potable Water – Softened

WX Light Green with Blue Bands

G36 Kikuyu T11 Tropical Blue

BS 5252 12E53 BS 5252 18E53

Potable Water – Hot

WY Light Green with Red Bands

G36 Kikuyu R13 Signal Red

BS 5252 12E53 BS 381C 537

Fresh Water /Supply Water

WZ Light Green with Green Bands

G36 Kikuyu G37 Beanstalk

BS 5252 12E53 BS 5252 14E51

Tempered Water WT/WC White N14 White BS 5252 00E55 Drill Water WD Dark Grey with

Blue Bands N53 Blue Grey

T11 Tropical Blue BS 381C 637

BS 5252 18E53 Chilled Water WH Green Bands G37 Beanstalk BS 5252 14E51

Page 52: Standard Protective Coatings

This document is protected by copyright. No part of this document may be reproduced, adapted, transmitted, or stored in any form by any process (electronic or otherwise) without the specific written consent of Woodside. All rights are reserved.

Controlled Ref No. W1000SM002 DRIMS No. 3205381 Revision : 1 Page 52

DRIMS Classification/No. Uncontrolled when printed, unless stamped in Red to the contrary.

COLOUR STANDARDS – GENERAL PURPOSE PIPING

P & ID SERVICE

CODE COLOUR

DESCRIPTION AS 2700 S – 1996 NOMENCLATURE

PRACTICAL EQUIVALENT

Chilled Water WV Light Green with Yellow Bands

G36 Kikuyu Y14 Golden Yellow

BS 5252 12E53 BS 5252 08E51

Brine Dark Grey with Green Bands

N53 Blue Grey G37 Beanstalk

BS 381C 637 BS 5252 14E51

Well Kill System Green with Red Bands

G37 Beanstalk R13 Signal Red

BS 5252 14E51 BS 381C 537

Fire Fighting Firewater, Fire Foam, Deluge

WF/FF/CF Red R13 Signal Red BS 381C 537

Halon HA Red with Green Bands

R13 Signal Red G37 Beanstalk

BS 381C 537 BS 5252 14E51

Carbon Dioxide CJ Red with Black Bands

R13 Signal Red N61 Black

BS 381C 537 BS 5252 00E53

Nitrogen Red with Blue Bands R13 Signal Red T11 Tropical Blue

BS 381C 537 BS 5252 18E53

Air Nitrogen Orange with

Green Bands X15 Orange

G31 Verdigris BS 381C 557 BS 381C 280

Plant (Utility) Air, Bulk Transport Air, Starting Air

AS Blue T11 Tropical Blue BS 5252 18E53

Instrument Air, Pneumatic Control Air

A1 Light Blue with White Bands

B41 Bluebell N14 White

BS 5252 20E51 BS 5252 00E55

Wet Air (Air from upstream of driers)

AS Blue with Red Bands

T11 Tropical Blue R13 Signal Red

BS 5252 18E53 BS 381C 537

Liquid Mud and Cement HP Mud – Kill & Choke

MH/KS Dark Grey with Brown Bands

N53 Blue Grey X54 Brown

BS 381C 637 BS 5252 06C39

HP Cement EH Dark Grey with Red Bands

N53 Blue Grey R13 Signal Red

BS 381C 637 BS 381C 537

LP Liquid Mud ML Dark Grey with Green Bands

N53 Blue Grey G37 Beanstalk

BS 381C 637 BS 5252 14E51

Low Toxic Oil OT Dark Grey with Green Bands

N53 BlueGrey G37 Beanstalk

BS 381C 637 BS 5252 14E51

Dry Storage and Transfer Cement EB Light Grey with

Violet Bands N22 Cloud Grey P14 Blueberry

BS 5252 10A03 BS 5252 22D45

Baryte MB Light Grey with Yellow Bands

N22 Cloud Grey Y14 Golden Yellow

BS 5252 10A03 BS 5252 08E51

Page 53: Standard Protective Coatings

This document is protected by copyright. No part of this document may be reproduced, adapted, transmitted, or stored in any form by any process (electronic or otherwise) without the specific written consent of Woodside. All rights are reserved.

Controlled Ref No. W1000SM002 DRIMS No. 3205381 Revision : 1 Page 53

DRIMS Classification/No. Uncontrolled when printed, unless stamped in Red to the contrary.

COLOUR STANDARDS – GENERAL PURPOSE PIPING

P & ID SERVICE

CODE COLOUR

DESCRIPTION AS 2700 S – 1996 NOMENCLATURE

PRACTICAL EQUIVALENT

Bentonite MB Light Grey with Orange Bands

N22 Cloud Grey X24 Rockmelon

BS 5252 10A03 BS 5252 06E51

Drains Hazardous (open drains)

DH Black with Yellow Bands

N61 Black Y14 Golden Yellow

BS 5252 00E53 BS 5252 08E51

Non-hazardous (open deck drains)

DN Black N61 Black BS 5252 00E53

Hazardous (closed drains)

DCI Black with Brown Bands

N61 Black X54 Brown

BS 5252 00E53 BS 5252 06C39

Domestic (Sanitary)

DS Black with Green Bands

N61 Black G37 Beanstalk

BS 5252 00E53 BS 5252 14E51

Produced Water (oily water)

W Black with Blue Bands

N61 Black T11 Tropical Blue

BS 5252 00E53 BS 5252 18E53

Soiled Waste - Black with Orange Bands

N61 Black X24 Rockmelon

BS 5252 00E53 BS 5252 06E51

Note 1: Where specified all piping and vessels, excluding uncoated stainless steel, should have an off-white (BS 5252 00A05, AS 2700 – Y35) continuous topcoat. The service shall be indicated by colour banding (must be colour stable) applied to the final painted surface. The colours for each service are indicated in the preceding table. Colour banding may be by painting or durable tape material. Direction of flow arrows shall also be applied to the final painted surface. For insulated lines, the identification and direction of flow arrows shall be applied to the outer surface of the insulation cladding. (N.B. Tape materials may not be suitable for harsh NW environment and may produce crevices).

Each colour band shall be approximately 150mm wide. Where two colour bands are required to indicate a service, a 400mm band of the first listed colour shall be applied with a secondary colour placed in the centre of the base colour band. Banding shall be applied at bulkheads, package and vessel termination points, pipe junctions and either side of each valve

Note 2: With prior approval from Woodside, small integrated packages (eg fire pumps/motors may be painted the colour of service).

10.6 OFFSHORE – EQUIPMENT

COLOUR STANDARDS – GENERAL PURPOSE EQUIPMENT

P & ID SERVICE

CODE COLOUR

DESCRIPTION AS 2700 S – 1996 NOMENCLATURE

PRACTICAL EQUIVALENT

Vessels Off White Y35 Off White BS 5252 10B15 Turbines, Pumps, Compressors

Light Green G36 Kikuyu BS 5252 12E53

Engines Light Grey N22 Cloud Grey BS 5252 10A03 Heat Exchangers Off White Y35 Off White BS 5252 10B15 Air Compressors Blue T11 Tropical Blue BS 5252 18E53 Minor Equipment Light Grey N22 Cloud Grey BS 5252 10A03 Wellhead & Yellow Y14 Golden Yellow BS 5252 08E51

Page 54: Standard Protective Coatings

This document is protected by copyright. No part of this document may be reproduced, adapted, transmitted, or stored in any form by any process (electronic or otherwise) without the specific written consent of Woodside. All rights are reserved.

Controlled Ref No. W1000SM002 DRIMS No. 3205381 Revision : 1 Page 54

DRIMS Classification/No. Uncontrolled when printed, unless stamped in Red to the contrary.

COLOUR STANDARDS – GENERAL PURPOSE EQUIPMENT

P & ID SERVICE

CODE COLOUR

DESCRIPTION AS 2700 S – 1996 NOMENCLATURE

PRACTICAL EQUIVALENT

Christmas Tree Fire Fighting Red R13 Signal Red BS 381C 537 Winches Grey N22 Cloud Grey BS 5252 10A03 Cement EB Light Grey N22 Cloud Grey BS 5252 10A03 Control Panels: Exterior Surfaces Beige Semi Gloss Y34 Cream BS 5252 10C31 Interior Surfaces White Gloss N14 White BS 5252 00E55 Plinths Black Semi Gloss N61 Black BS 5252 00E53 Electrical Equipment Exteriors: Switchgear, Lighting, Panels etc.

Electrical Green G41 Lawn Green BS 5252 14E53

Transformers, Motors, Alternators

Electrical Green G41 Lawn Green BS 5252 14E53

Stainless Steel Terminal Boxes

Natural Finish - -

Page 55: Standard Protective Coatings

This document is protected by copyright. No part of this document may be reproduced, adapted, transmitted, or stored in any form by any process (electronic or otherwise) without the specific written consent of Woodside. All rights are reserved.

Controlled Ref No. W1000SM002 DRIMS No. 3205381 Revision : 1 Page 55

DRIMS Classification/No. Uncontrolled when printed, unless stamped in Red to the contrary.

11 ONSHORE COLOUR CODES

COLOUR STANDARDS – GENERAL PURPOSE ITEM OF ONSHORE EQUIPMENT COLOUR

DESCRIPTION AS 2700 S - 1996 NOMENCLATURE

PRACTICAL EQUIVALENT

Vessels, columns, exchangers, tanks

Lightbox Grey N33 BS 5252 00A05

Pipe, pipe fittings, valves and other piping components (except fire water mains and foam systems)

Lightbox Grey N33 BS 5252 00A05

CP Pipework (Above ground) Rockmelon X24 BS 5252 06E51

Pipe banding * - Nitrogen - Instrument air - Plant air - Methanol - Process fresh cooling water - Potable water - Chilled water (HVAC)

Lead Grey Bluebell

Tropical Blue Blueberry Beanstalk

Kikuyu Beanstalk

N55 B41 T11 P14 G37 G36 G37

BS 5252 10A11 BS 5252 20E51 BS 5252 18E53 BS 5252 22D45 BS 5252 14E51 BS 5252 12E53 BS 5252 14E51

Fire water mains and foam system pipe, pipe fittings, valves and other piping components

Signal Red R13 BS 381C 537

Foam hydrant Bright Blue B23 BS 5252 20E56 Pumps, compressors, generators and turbines

Serpentine G22 BS 381C 275

Electric motors - High voltage - Medium/Low voltage

Navy Blue Serpentine

B13 G22

BS 381C 105 BS 381C 275

Ladders, stairways and walkways (where specified to be painted)

Wattle

Y12

BS 381C 355

Cranes Wattle Y12 BS 381C 355 Structural Steel - Not fireproofed - Concrete fireproofed - Non-cementitous fireproofed

Lightbox Grey

Charcoal Koala Grey

N33 B64 N45

BS 5252 00A05 BS 5252 18B29 BS 5252 10A07

Instrument console panels, cabinets and desks

Cloud Grey N22 BS 5252 10A03

Electrical panels Storm Grey N42 BS 381C 631

Note* Main pipework shall be painted in aluminium with colour banks 100mm in width applied to either side of valves, flanges and connections at wall penetrations and ground entry points.

Page 56: Standard Protective Coatings

This document is protected by copyright. No part of this document may be reproduced, adapted, transmitted, or stored in any form by any process (electronic or otherwise) without the specific written consent of Woodside. All rights are reserved.

Controlled Ref No. W1000SM002 DRIMS No. 3205381 Revision : 1 Page 56

DRIMS Classification/No. Uncontrolled when printed, unless stamped in Red to the contrary.

12 REFERENCES

The following reference documents are a part of this standard in addition to the requirements contained herein. Except where specifically modified by this Standard, the coatings and their application shall comply with the latest edition of the Standards and documents as listed below. Other recognized codes and standards meeting or exceeding the referenced documents may be substituted or added with the approval of the Principal. The Contractor is responsible for gaining access to, understanding, and complying with all the requirements contained in the reference documents listed below: AS1012 Method of Testing Concrete

AS1580 Methods of Test for Paints and Related Materials

AS1627 Metal Finishing - Preparation and Pre-treatment of Surfaces (Including surface characteristics of steel substrates)

AS 2312 Guide to the protection of structural steel against corrosion by the use of protective coatings

AS4680 Hot dipped galvanised coatings on ferrous articles

AS2700 Colour Standards for General Purposes

AS3750 Protective Coatings for Steel Structures

AS3894.1 Non-conductive coatings - Continuity testing - High voltage ("brush") method

AS3894.2 Non-conductive coatings - Continuity testing - Wet sponge method

AS3894.3 Determination of Dry Film Thickness

AS3894.4 Assessment of degree of cure

AS3894.5 Determination of surface profile

AS3894.6 Determination of residual contaminants

AS3894.9 Determination of adhesion

AS3894.10 Inspection Report –Daily surface and ambient conditions

AS3894.11 Equipment report

AS3894.12 Inspection report - Coating

AS3894.13 Inspection report - Daily

AS3894.14 Inspection report – Daily painting

AS 4321 Fusion bonded medium density polyethylene coating and lining for pipes and fittings

SSPC-SP COM Surface preparation Commentary

SSPC-SP1 Solvent Cleaning

SSPC-SP5 White Metal Cleaning

SSPC-SP7 Brush-off Blast Cleaning

Page 57: Standard Protective Coatings

This document is protected by copyright. No part of this document may be reproduced, adapted, transmitted, or stored in any form by any process (electronic or otherwise) without the specific written consent of Woodside. All rights are reserved.

Controlled Ref No. W1000SM002 DRIMS No. 3205381 Revision : 1 Page 57

DRIMS Classification/No. Uncontrolled when printed, unless stamped in Red to the contrary.

SSPC-SP10 Near-White Metal Cleaning

SSPC-SP11 Power Tool Cleaning to Bare Metal

SSPC-PA2 Measurement of Dry Coating Thickness with Magnetic Gauges

SSPC Paint 20 Paint Specification 20 Zinc rich primers

ASTM D4752 Measuring MEK Resistance of Ethyl Silicate (Inorganic) Zinc Rich Primers by Solvent Rub

ASTM D 1186 Standard Test Method for Non destructive Measurements of Dry film Thickness of Non magnetic Coatings applied to Ferrous Base

ASTM D 4417 Standard Test Method for Field Measurement of Surface Profile of Blast Cleaned Steel

ASTM D5064 Conducting a Patch Test to Assess Coating Compatibility

ASTM D4541 Pull Off Strength of Coatings Using Portable Adhesion Testers

ASTM D4228 Qualification of Coating Applicators for Application of Coatings to Steel Surfaces

AWS C2.2 Recommended Practice for Metallising with Aluminium and Zinc for Protection of Iron and Steel

AWS C2.16 Guide for Thermal Spray Operator Qualification

AWS C2.18-93R Guide for the Protection of Steel with Thermal Sprayed Coatings of Aluminium and Zinc and Their Alloys and Composites.

AWS C2.25 Specification of Thermal Spray Feedstock –Solid and Composite Wire and Ceramic Rod

NACE No. 5/ SSPC-SP12

Surface Preparation and Cleaning of Metals by Water jetting Prior to Recoating

NACE No.6/ SSPC-SP13

Surface Preparation of Concrete

NACE RP0892 Coatings and Linings over Concrete for Chemical Immersion and Containment Service

NACE RP0178 Fabrication Details, Surface Finish Requirements, and Proper Design Consideration for Tanks and Vessels to Be Lined for Immersion Service

BS4800 Specification for paint colours for building purposes

ISO 8501

Preparation of steel substrates before application of paint and related products

ISO 8502-3 Preparation of steel substrates before application of paints and related products -- Tests for the assessment of surface cleanliness -- Part 3: Assessment of dust on steel surfaces prepared for painting (Pressure-sensitive tape method)

ISO 8502-4 Preparation of steel substrates before application of paints and related products -- Tests for the assessment of surface cleanliness -- Part 4: Guidance on the estimation of the

Page 58: Standard Protective Coatings

This document is protected by copyright. No part of this document may be reproduced, adapted, transmitted, or stored in any form by any process (electronic or otherwise) without the specific written consent of Woodside. All rights are reserved.

Controlled Ref No. W1000SM002 DRIMS No. 3205381 Revision : 1 Page 58

DRIMS Classification/No. Uncontrolled when printed, unless stamped in Red to the contrary.

probability of condensation prior to paint application

ISO 11127-6 Determination of water soluble contaminants by conductivity measurements

ISO 11127-7 Determination of water soluble chlorides

ISO 12944-7 Execution and supervision of paint work

ISO 12944-8 Development and specification for new work and maintenance

SSPC PA 5 Guide to Maintenance Painting Programs

DIN EN1395 Acceptance Inspection of Thermal Spraying Equipment

International Paints Hydro blasting Standards 1998

Page 59: Standard Protective Coatings

This document is protected by copyright. No part of this document may be reproduced, adapted, transmitted, or stored in any form by any process (electronic or otherwise) without the specific written consent of Woodside. All rights are reserved.

Controlled Ref No. W1000SM002 DRIMS No. 3205381 Revision : 1 Page 59

DRIMS Classification/No. Uncontrolled when printed, unless stamped in Red to the contrary.

13 APPENDICES

APPENDIX

SUPERCEDED HISTORICAL STANDARDS 1

Page 60: Standard Protective Coatings

This document is protected by copyright. No part of this document may be reproduced, adapted, transmitted, or stored in any form by any process (electronic or otherwise) without the specific written consent of Woodside. All rights are reserved.

Controlled Ref No. W1000SM002 DRIMS No. 3205381 Revision : 1 Page 60

DRIMS Classification/No. Uncontrolled when printed, unless stamped in Red to the contrary.

APPENDIX 1 – SUPERCEDED HISTORICAL STANDARDS

SSS002 Standard Specification for Coating of Miscellaneous Structural Steelwork

SSM002 Standard Specification for Coating of Mechanical Equipment.

A9680SS001 Specification for Offshore Maintenance Painting

A1840SG501 Specification for Coating of Mechanical Equipment and Packages (Goodwyn A).

A1840SG532 Specification for Coating Onshore Construction (Goodwyn A).

A1840SS506 Specification for Jacket and MSF Coating (Goodwyn A).

N0000SL001 Technical Specification for Shop Applied Protective Coatings (LNG)

N0000SL002 Specification for Selection of Paint Systems (LNG)

L7000SL001 Technical Specification - Corrosion Protection for LNG and Condensate Load Out Jetty

E3110-ES-002.0001 Wanaea Cossack Revised Painting Specification (was E3110.EG.002.0001)

E3180-EL-001.0001 Marine Coating Manual.

E4000-EL-021.0001 Painting Data Sheets

E4000-EL-022.0001 Corrosion Protection Painting Specification.

E5040-EM-100 FPSO Process Facilities Contract Specification for Paint and Protective Coatings.

W9000SM001 Protective Coating Standard