Staircase fdesign

21
Reference Calculation Design of Staircases: There were two staircases in the building to design. Design o staircase is detailed here. Choice of layout: Floor to floor height = 4600mm No. of rises = 24 Height of rise ® = 4600 24 = 192mm <175mm and accep for public build Going (G) = 300mm 2R+G = 2*200 +300 = 700mm (Appro. 600mm ) Hence Not OK. Nosing is not going to provide hence, tread and going are equ Stair span and Waist Thickness for Typical flights: Staircase was supported between two landings and landings wer designed to span perpendicular to the span of flights. BS8110 Cl.3.10.1.3 Effective span = = 6.9+0.5(1.7+0) = 7.75m Cl.3.10.2.2 Length of stairs (%) = (6.9/7.75)*100% = 89.00% >60% Hence span/depth enhancement is possible. I.S.E. manua Assume span/depth ratio of 31 for continous oneway spanning s Table3 Span/depth = 31*1.15 = 35.65 Effective depth = 7750/35.65 = 217mm Assume cover 25mm (mild exposure conditions and 2hr fire resi and using 12mm bars, choose h=275mm and d=275-25-8 = 242mm Hence waist thickness was selected as 275mm. Project: Dahampaya Feature Design DESIGN UNIT Designed Typical paln of the staircase is attached here with in figure la+ 0.5(lb,1 +lb,2) D

description

sample design

Transcript of Staircase fdesign

Page 1: Staircase fdesign

Reference Calculation Output

Design of Staircases:

There were two staircases in the building to design. Design of main staircase is detailed here.

Choice of layout:

Floor to floor height = 4600mmNo. of rises = 24Height of rise ® = 4600

24= 192mm <175mm and acceptable

for public buildings. Rise=200mmGoing (G) = 300mm Going=250mm

2R+G = 2*200 +300= 700mm

(Appro. 600mm )Hence Not OK.

Nosing is not going to provide hence, tread and going are equal.

Stair span and Waist Thickness for Typical flights:

Staircase was supported between two landings and landings were designed to span perpendicular to the span of flights.

BS8110Cl.3.10.1.3 Effective span =

= 6.9+0.5(1.7+0)= 7.75m

Cl.3.10.2.2 Length of stairs (%) = (6.9/7.75)*100% = 89.00% >60%

Hence span/depth enhancement is possible.

I.S.E. manual Assume span/depth ratio of 31 for continous oneway spanning staircase. Table3

Span/depth = 31*1.15= 35.65

Effective depth = 7750/35.65= 217mm

Assume cover 25mm (mild exposure conditions and 2hr fire resistance)and using 12mm bars, choose h=275mm and Waist thickness

d=275-25-8 = 242mm =Hence waist thickness was selected as 275mm.

Project: Dahampaya Feature Design of staircase

DESIGN UNIT Designed Date

Typical paln of the staircase is attached here with in figure 9-1.

la+ 0.5(lb,1 +lb,2)

DEC

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

Page 2: Staircase fdesign

Reference Calculation Output

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

EPC DIVISION Checked Date

CENTRAL ENGINEERING CONSULTANCY BUREAU (CECB) Job Code D-676 Page

Loading:

Consider 1m wide strip

Factor for slope === 1.2

Waist = (0.275).(24).(1.2).1= 7.92kN/m

Steps+Guard wall = (0.5).(0.2).(0.30).(24)= 4.02kN/m

Top finishes = (0.5).1= 0.5kN/m

Soffit plaster = (0.25).1.(1.2)= 0.3kN/m

Total dead load = 8.9kN/m

Imposed load = Design load

Design load = (1.4).(8.94)+(1.6).(4)= 18.9kN/m

For landing area:

Self weight of slab = (0.275).24 = 6.6kN/mSoffit plaster = (0.25).1.0 = 0.25kN/mTop finishes = (0.5).1.0 = 0.5kN/m

Total dead load = 7.35kN/m

Imposed load =Landing load

Design load = (1.4).(7.35)+(1.6).(4)

= 16.7kN/m

DEC

(R2+G2)0.5/G(2002+3002)0.5 /300

4.0kN/m2

4.0kN/m2

NF 13.277

High Flood Level

lood Level

Existing water LevelBed Rock Level

P2 P3Pw

1 8 0 0 0 ( a p p r o x . )4 0 0 0 ( a p p r o x . ) 4 0 0 0 ( a p p r o x . )1 8 0 0 0 / 3 = 6 0 0 0 ( a p p r o x . )

P2

P1

P3

PwP3 P2

6 0 0 f6 0 0 f 6 0 0 f

400x800

400x800

W2

W1

CTba400x800

279 KNm 340 KNm

River bed Level

800

Lateral load on the beam due to water presure

NF 13.277

High Flood Level

lood Level

Existing water LevelBed Rock Level

P2 P3Pw

1 8 0 0 0 ( a p p r o x . )4 0 0 0 ( a p p r o x . ) 4 0 0 0 ( a p p r o x . )1 8 0 0 0 / 3 = 6 0 0 0 ( a p p r o x . )

P2

P1

P3

PwP3 P2

6 0 0 f6 0 0 f 6 0 0 f

400x800

400x800

W2

W1

CTba400x800

279 KNm 340 KNm

River bed Level

800

Lateral load on the beam due to water presure

NF 13.277

High Flood Level

lood Level

Existing water LevelBed Rock Level

P2 P3Pw

1 8 0 0 0 ( a p p r o x . )4 0 0 0 ( a p p r o x . ) 4 0 0 0 ( a p p r o x . )1 8 0 0 0 / 3 = 6 0 0 0 ( a p p r o x . )

P2

P1

P3

PwP3 P2

6 0 0 f6 0 0 f 6 0 0 f

400x800

400x800

W2

W1

CTba400x800

279 KNm 340 KNm

River bed Level

800

Lateral load on the beam due to water presure

NF 13.277

High Flood Level

lood Level

Existing water LevelBed Rock Level

P2 P3Pw

1 8 0 0 0 ( a p p r o x . )4 0 0 0 ( a p p r o x . ) 4 0 0 0 ( a p p r o x . )1 8 0 0 0 / 3 = 6 0 0 0 ( a p p r o x . )

P2

P1

P3

PwP3 P2

6 0 0 f6 0 0 f 6 0 0 f

400x800

400x800

W2

W1

CTba400x800

279 KNm 340 KNm

River bed Level

800

Lateral load on the beam due to water presure

NF 13.277

High Flood Level

lood Level

Existing water LevelBed Rock Level

P2 P3Pw

1 8 0 0 0 ( a p p r o x . )4 0 0 0 ( a p p r o x . ) 4 0 0 0 ( a p p r o x . )1 8 0 0 0 / 3 = 6 0 0 0 ( a p p r o x . )

P2

P1

P3

PwP3 P2

6 0 0 f6 0 0 f 6 0 0 f

400x800

400x800

W2

W1

CTba400x800

279 KNm 340 KNm

River bed Level

800

Lateral load on the beam due to water presure

NF 13.277

High Flood Level

lood Level

Existing water LevelBed Rock Level

P2 P3Pw

1 8 0 0 0 ( a p p r o x . )4 0 0 0 ( a p p r o x . ) 4 0 0 0 ( a p p r o x . )1 8 0 0 0 / 3 = 6 0 0 0 ( a p p r o x . )

P2

P1

P3

PwP3 P2

6 0 0 f6 0 0 f 6 0 0 f

400x800

400x800

W2

W1

CTba400x800

279 KNm 340 KNm

River bed Level

800

Lateral load on the beam due to water presure

NF 13.277

High Flood Level

lood Level

Existing water LevelBed Rock Level

P2 P3Pw

1 8 0 0 0 ( a p p r o x . )4 0 0 0 ( a p p r o x . ) 4 0 0 0 ( a p p r o x . )1 8 0 0 0 / 3 = 6 0 0 0 ( a p p r o x . )

P2

P1

P3

PwP3 P2

6 0 0 f6 0 0 f 6 0 0 f

400x800

400x800

W2

W1

CTba400x800

279 KNm 340 KNm

River bed Level

800

Lateral load on the beam due to water presure

NF 13.277

High Flood Level

lood Level

Existing water LevelBed Rock Level

P2 P3Pw

1 8 0 0 0 ( a p p r o x . )4 0 0 0 ( a p p r o x . ) 4 0 0 0 ( a p p r o x . )1 8 0 0 0 / 3 = 6 0 0 0 ( a p p r o x . )

P2

P1

P3

PwP3 P2

6 0 0 f6 0 0 f 6 0 0 f

400x800

400x800

W2

W1

CTba400x800

279 KNm 340 KNm

River bed Level

800

Lateral load on the beam due to water presure

NF 13.277

High Flood Level

lood Level

Existing water LevelBed Rock Level

P2 P3Pw

1 8 0 0 0 ( a p p r o x . )4 0 0 0 ( a p p r o x . ) 4 0 0 0 ( a p p r o x . )1 8 0 0 0 / 3 = 6 0 0 0 ( a p p r o x . )

P2

P1

P3

PwP3 P2

6 0 0 f6 0 0 f 6 0 0 f

400x800

400x800

W2

W1

CTba400x800

279 KNm 340 KNm

River bed Level

800

Lateral load on the beam due to water presure

NF 13.277

High Flood Level

lood Level

Existing water LevelBed Rock Level

P2 P3Pw

1 8 0 0 0 ( a p p r o x . )4 0 0 0 ( a p p r o x . ) 4 0 0 0 ( a p p r o x . )1 8 0 0 0 / 3 = 6 0 0 0 ( a p p r o x . )

P2

P1

P3

PwP3 P2

6 0 0 f6 0 0 f 6 0 0 f

400x800

400x800

W2

W1

CTba400x800

279 KNm 340 KNm

River bed Level

800

Lateral load on the beam due to water presure

NF 13.277

High Flood Level

lood Level

Existing water LevelBed Rock Level

P2 P3Pw

1 8 0 0 0 ( a p p r o x . )4 0 0 0 ( a p p r o x . ) 4 0 0 0 ( a p p r o x . )1 8 0 0 0 / 3 = 6 0 0 0 ( a p p r o x . )

P2

P1

P3

PwP3 P2

6 0 0 f6 0 0 f 6 0 0 f

400x800

400x800

W2

W1

CTba400x800

279 KNm 340 KNm

River bed Level

800

Lateral load on the beam due to water presure

NF 13.277

High Flood Level

lood Level

Existing water LevelBed Rock Level

P2 P3Pw

1 8 0 0 0 ( a p p r o x . )4 0 0 0 ( a p p r o x . ) 4 0 0 0 ( a p p r o x . )1 8 0 0 0 / 3 = 6 0 0 0 ( a p p r o x . )

P2

P1

P3

PwP3 P2

6 0 0 f6 0 0 f 6 0 0 f

400x800

400x800

W2

W1

CTba400x800

279 KNm 340 KNm

River bed Level

800

Lateral load on the beam due to water presure

NF 13.277

High Flood Level

lood Level

Existing water LevelBed Rock Level

P2 P3Pw

1 8 0 0 0 ( a p p r o x . )4 0 0 0 ( a p p r o x . ) 4 0 0 0 ( a p p r o x . )1 8 0 0 0 / 3 = 6 0 0 0 ( a p p r o x . )

P2

P1

P3

PwP3 P2

6 0 0 f6 0 0 f 6 0 0 f

400x800

400x800

W2

W1

CTba400x800

279 KNm 340 KNm

River bed Level

800

Lateral load on the beam due to water presure

NF 13.277

High Flood Level

lood Level

Existing water LevelBed Rock Level

P2 P3Pw

1 8 0 0 0 ( a p p r o x . )4 0 0 0 ( a p p r o x . ) 4 0 0 0 ( a p p r o x . )1 8 0 0 0 / 3 = 6 0 0 0 ( a p p r o x . )

P2

P1

P3

PwP3 P2

6 0 0 f6 0 0 f 6 0 0 f

400x800

400x800

W2

W1

CTba400x800

279 KNm 340 KNm

River bed Level

800

Lateral load on the beam due to water presure

NF 13.277

High Flood Level

lood Level

Existing water LevelBed Rock Level

P2 P3Pw

1 8 0 0 0 ( a p p r o x . )4 0 0 0 ( a p p r o x . ) 4 0 0 0 ( a p p r o x . )1 8 0 0 0 / 3 = 6 0 0 0 ( a p p r o x . )

P2

P1

P3

PwP3 P2

6 0 0 f6 0 0 f 6 0 0 f

400x800

400x800

W2

W1

CTba400x800

279 KNm 340 KNm

River bed Level

800

Lateral load on the beam due to water presure

NF 13.277

High Flood Level

lood Level

Existing water LevelBed Rock Level

P2 P3Pw

1 8 0 0 0 ( a p p r o x . )4 0 0 0 ( a p p r o x . ) 4 0 0 0 ( a p p r o x . )1 8 0 0 0 / 3 = 6 0 0 0 ( a p p r o x . )

P2

P1

P3

PwP3 P2

6 0 0 f6 0 0 f 6 0 0 f

400x800

400x800

W2

W1

CTba400x800

279 KNm 340 KNm

River bed Level

800

Lateral load on the beam due to water presure

NF 13.277

High Flood Level

lood Level

Existing water LevelBed Rock Level

P2 P3Pw

1 8 0 0 0 ( a p p r o x . )4 0 0 0 ( a p p r o x . ) 4 0 0 0 ( a p p r o x . )1 8 0 0 0 / 3 = 6 0 0 0 ( a p p r o x . )

P2

P1

P3

PwP3 P2

6 0 0 f6 0 0 f 6 0 0 f

400x800

400x800

W2

W1

CTba400x800

279 KNm 340 KNm

River bed Level

800

Lateral load on the beam due to water presure

NF 13.277

High Flood Level

lood Level

Existing water LevelBed Rock Level

P2 P3Pw

1 8 0 0 0 ( a p p r o x . )4 0 0 0 ( a p p r o x . ) 4 0 0 0 ( a p p r o x . )1 8 0 0 0 / 3 = 6 0 0 0 ( a p p r o x . )

P2

P1

P3

PwP3 P2

6 0 0 f6 0 0 f 6 0 0 f

400x800

400x800

W2

W1

CTba400x800

279 KNm 340 KNm

River bed Level

800

Lateral load on the beam due to water presure

NF 13.277

High Flood Level

lood Level

Existing water LevelBed Rock Level

P2 P3Pw

1 8 0 0 0 ( a p p r o x . )4 0 0 0 ( a p p r o x . ) 4 0 0 0 ( a p p r o x . )1 8 0 0 0 / 3 = 6 0 0 0 ( a p p r o x . )

P2

P1

P3

PwP3 P2

6 0 0 f6 0 0 f 6 0 0 f

400x800

400x800

W2

W1

CTba400x800

279 KNm 340 KNm

River bed Level

800

Lateral load on the beam due to water presure

NF 13.277

High Flood Level

lood Level

Existing water LevelBed Rock Level

P2 P3Pw

1 8 0 0 0 ( a p p r o x . )4 0 0 0 ( a p p r o x . ) 4 0 0 0 ( a p p r o x . )1 8 0 0 0 / 3 = 6 0 0 0 ( a p p r o x . )

P2

P1

P3

PwP3 P2

6 0 0 f6 0 0 f 6 0 0 f

400x800

400x800

W2

W1

CTba400x800

279 KNm 340 KNm

River bed Level

800

Lateral load on the beam due to water presure

NF 13.277

High Flood Level

lood Level

Existing water LevelBed Rock Level

P2 P3Pw

1 8 0 0 0 ( a p p r o x . )4 0 0 0 ( a p p r o x . ) 4 0 0 0 ( a p p r o x . )1 8 0 0 0 / 3 = 6 0 0 0 ( a p p r o x . )

P2

P1

P3

PwP3 P2

6 0 0 f6 0 0 f 6 0 0 f

400x800

400x800

W2

W1

CTba400x800

279 KNm 340 KNm

River bed Level

800

Lateral load on the beam due to water presure

NF 13.277

High Flood Level

lood Level

Existing water LevelBed Rock Level

P2 P3Pw

1 8 0 0 0 ( a p p r o x . )4 0 0 0 ( a p p r o x . ) 4 0 0 0 ( a p p r o x . )1 8 0 0 0 / 3 = 6 0 0 0 ( a p p r o x . )

P2

P1

P3

PwP3 P2

6 0 0 f6 0 0 f 6 0 0 f

400x800

400x800

W2

W1

CTba400x800

279 KNm 340 KNm

River bed Level

800

Lateral load on the beam due to water presure

NF 13.277

High Flood Level

lood Level

Existing water LevelBed Rock Level

P2 P3Pw

1 8 0 0 0 ( a p p r o x . )4 0 0 0 ( a p p r o x . ) 4 0 0 0 ( a p p r o x . )1 8 0 0 0 / 3 = 6 0 0 0 ( a p p r o x . )

P2

P1

P3

PwP3 P2

6 0 0 f6 0 0 f 6 0 0 f

400x800

400x800

W2

W1

CTba400x800

279 KNm 340 KNm

River bed Level

800

Lateral load on the beam due to water presure

NF 13.277

High Flood Level

lood Level

Existing water LevelBed Rock Level

P2 P3Pw

1 8 0 0 0 ( a p p r o x . )4 0 0 0 ( a p p r o x . ) 4 0 0 0 ( a p p r o x . )1 8 0 0 0 / 3 = 6 0 0 0 ( a p p r o x . )

P2

P1

P3

PwP3 P2

6 0 0 f6 0 0 f 6 0 0 f

400x800

400x800

W2

W1

CTba400x800

279 KNm 340 KNm

River bed Level

800

Lateral load on the beam due to water presure

NF 13.277

High Flood Level

lood Level

Existing water LevelBed Rock Level

P2 P3Pw

1 8 0 0 0 ( a p p r o x . )4 0 0 0 ( a p p r o x . ) 4 0 0 0 ( a p p r o x . )1 8 0 0 0 / 3 = 6 0 0 0 ( a p p r o x . )

P2

P1

P3

PwP3 P2

6 0 0 f6 0 0 f 6 0 0 f

400x800

400x800

W2

W1

CTba400x800

279 KNm 340 KNm

River bed Level

800

Lateral load on the beam due to water presure

NF 13.277

High Flood Level

lood Level

Existing water LevelBed Rock Level

P2 P3Pw

1 8 0 0 0 ( a p p r o x . )4 0 0 0 ( a p p r o x . ) 4 0 0 0 ( a p p r o x . )1 8 0 0 0 / 3 = 6 0 0 0 ( a p p r o x . )

P2

P1

P3

PwP3 P2

6 0 0 f6 0 0 f 6 0 0 f

400x800

400x800

W2

W1

CTba400x800

279 KNm 340 KNm

River bed Level

800

Lateral load on the beam due to water presure

NF 13.277

High Flood Level

lood Level

Existing water LevelBed Rock Level

P2 P3Pw

1 8 0 0 0 ( a p p r o x . )4 0 0 0 ( a p p r o x . ) 4 0 0 0 ( a p p r o x . )1 8 0 0 0 / 3 = 6 0 0 0 ( a p p r o x . )

P2

P1

P3

PwP3 P2

6 0 0 f6 0 0 f 6 0 0 f

400x800

400x800

W2

W1

CTba400x800

279 KNm 340 KNm

River bed Level

800

Lateral load on the beam due to water presure

NF 13.277

High Flood Level

lood Level

Existing water LevelBed Rock Level

P2 P3Pw

1 8 0 0 0 ( a p p r o x . )4 0 0 0 ( a p p r o x . ) 4 0 0 0 ( a p p r o x . )1 8 0 0 0 / 3 = 6 0 0 0 ( a p p r o x . )

P2

P1

P3

PwP3 P2

6 0 0 f6 0 0 f 6 0 0 f

400x800

400x800

W2

W1

CTba400x800

279 KNm 340 KNm

River bed Level

800

Lateral load on the beam due to water presure

NF 13.277

High Flood Level

lood Level

Existing water LevelBed Rock Level

P2 P3Pw

1 8 0 0 0 ( a p p r o x . )4 0 0 0 ( a p p r o x . ) 4 0 0 0 ( a p p r o x . )1 8 0 0 0 / 3 = 6 0 0 0 ( a p p r o x . )

P2

P1

P3

PwP3 P2

6 0 0 f6 0 0 f 6 0 0 f

400x800

400x800

W2

W1

CTba400x800

279 KNm 340 KNm

River bed Level

800

Lateral load on the beam due to water presure

NF 13.277

High Flood Level

lood Level

Existing water LevelBed Rock Level

P2 P3Pw

1 8 0 0 0 ( a p p r o x . )4 0 0 0 ( a p p r o x . ) 4 0 0 0 ( a p p r o x . )1 8 0 0 0 / 3 = 6 0 0 0 ( a p p r o x . )

P2

P1

P3

PwP3 P2

6 0 0 f6 0 0 f 6 0 0 f

400x800

400x800

W2

W1

CTba400x800

279 KNm 340 KNm

River bed Level

800

Lateral load on the beam due to water presure

NF 13.277

High Flood Level

lood Level

Existing water LevelBed Rock Level

P2 P3Pw

1 8 0 0 0 ( a p p r o x . )4 0 0 0 ( a p p r o x . ) 4 0 0 0 ( a p p r o x . )1 8 0 0 0 / 3 = 6 0 0 0 ( a p p r o x . )

P2

P1

P3

PwP3 P2

6 0 0 f6 0 0 f 6 0 0 f

400x800

400x800

W2

W1

CTba400x800

279 KNm 340 KNm

River bed Level

800

Lateral load on the beam due to water presure

NF 13.277

High Flood Level

lood Level

Existing water LevelBed Rock Level

P2 P3Pw

1 8 0 0 0 ( a p p r o x . )4 0 0 0 ( a p p r o x . ) 4 0 0 0 ( a p p r o x . )1 8 0 0 0 / 3 = 6 0 0 0 ( a p p r o x . )

P2

P1

P3

PwP3 P2

6 0 0 f6 0 0 f 6 0 0 f

400x800

400x800

W2

W1

CTba400x800

279 KNm 340 KNm

River bed Level

800

Lateral load on the beam due to water presure

NF 13.277

High Flood Level

lood Level

Existing water LevelBed Rock Level

P2 P3Pw

1 8 0 0 0 ( a p p r o x . )4 0 0 0 ( a p p r o x . ) 4 0 0 0 ( a p p r o x . )1 8 0 0 0 / 3 = 6 0 0 0 ( a p p r o x . )

P2

P1

P3

PwP3 P2

6 0 0 f6 0 0 f 6 0 0 f

400x800

400x800

W2

W1

CTba400x800

279 KNm 340 KNm

River bed Level

800

Lateral load on the beam due to water presure

NF 13.277

High Flood Level

lood Level

Existing water LevelBed Rock Level

P2 P3Pw

1 8 0 0 0 ( a p p r o x . )4 0 0 0 ( a p p r o x . ) 4 0 0 0 ( a p p r o x . )1 8 0 0 0 / 3 = 6 0 0 0 ( a p p r o x . )

P2

P1

P3

PwP3 P2

6 0 0 f6 0 0 f 6 0 0 f

400x800

400x800

W2

W1

CTba400x800

279 KNm 340 KNm

River bed Level

800

Lateral load on the beam due to water presure

NF 13.277

High Flood Level

lood Level

Existing water LevelBed Rock Level

P2 P3Pw

1 8 0 0 0 ( a p p r o x . )4 0 0 0 ( a p p r o x . ) 4 0 0 0 ( a p p r o x . )1 8 0 0 0 / 3 = 6 0 0 0 ( a p p r o x . )

P2

P1

P3

PwP3 P2

6 0 0 f6 0 0 f 6 0 0 f

400x800

400x800

W2

W1

CTba400x800

279 KNm 340 KNm

River bed Level

800

Lateral load on the beam due to water presure

NF 13.277

High Flood Level

lood Level

Existing water LevelBed Rock Level

P2 P3Pw

1 8 0 0 0 ( a p p r o x . )4 0 0 0 ( a p p r o x . ) 4 0 0 0 ( a p p r o x . )1 8 0 0 0 / 3 = 6 0 0 0 ( a p p r o x . )

P2

P1

P3

PwP3 P2

6 0 0 f6 0 0 f 6 0 0 f

400x800

400x800

W2

W1

CTba400x800

279 KNm 340 KNm

River bed Level

800

Lateral load on the beam due to water presure

NF 13.277

High Flood Level

lood Level

Existing water LevelBed Rock Level

P2 P3Pw

1 8 0 0 0 ( a p p r o x . )4 0 0 0 ( a p p r o x . ) 4 0 0 0 ( a p p r o x . )1 8 0 0 0 / 3 = 6 0 0 0 ( a p p r o x . )

P2

P1

P3

PwP3 P2

6 0 0 f6 0 0 f 6 0 0 f

400x800

400x800

W2

W1

CTba400x800

279 KNm 340 KNm

River bed Level

800

Lateral load on the beam due to water presure

NF 13.277

High Flood Level

lood Level

Existing water LevelBed Rock Level

P2 P3Pw

1 8 0 0 0 ( a p p r o x . )4 0 0 0 ( a p p r o x . ) 4 0 0 0 ( a p p r o x . )1 8 0 0 0 / 3 = 6 0 0 0 ( a p p r o x . )

P2

P1

P3

PwP3 P2

6 0 0 f6 0 0 f 6 0 0 f

400x800

400x800

W2

W1

CTba400x800

279 KNm 340 KNm

River bed Level

800

Lateral load on the beam due to water presure

NF 13.277

High Flood Level

lood Level

Existing water LevelBed Rock Level

P2 P3Pw

1 8 0 0 0 ( a p p r o x . )4 0 0 0 ( a p p r o x . ) 4 0 0 0 ( a p p r o x . )1 8 0 0 0 / 3 = 6 0 0 0 ( a p p r o x . )

P2

P1

P3

PwP3 P2

6 0 0 f6 0 0 f 6 0 0 f

400x800

400x800

W2

W1

CTba400x800

279 KNm 340 KNm

River bed Level

800

Lateral load on the beam due to water presure

NF 13.277

High Flood Level

lood Level

Existing water LevelBed Rock Level

P2 P3Pw

1 8 0 0 0 ( a p p r o x . )4 0 0 0 ( a p p r o x . ) 4 0 0 0 ( a p p r o x . )1 8 0 0 0 / 3 = 6 0 0 0 ( a p p r o x . )

P2

P1

P3

PwP3 P2

6 0 0 f6 0 0 f 6 0 0 f

400x800

400x800

W2

W1

CTba400x800

279 KNm 340 KNm

River bed Level

800

Lateral load on the beam due to water presure

NF 13.277

High Flood Level

lood Level

Existing water LevelBed Rock Level

P2 P3Pw

1 8 0 0 0 ( a p p r o x . )4 0 0 0 ( a p p r o x . ) 4 0 0 0 ( a p p r o x . )1 8 0 0 0 / 3 = 6 0 0 0 ( a p p r o x . )

P2

P1

P3

PwP3 P2

6 0 0 f6 0 0 f 6 0 0 f

400x800

400x800

W2

W1

CTba400x800

279 KNm 340 KNm

River bed Level

800

Lateral load on the beam due to water presure

NF 13.277

High Flood Level

lood Level

Existing water LevelBed Rock Level

P2 P3Pw

1 8 0 0 0 ( a p p r o x . )4 0 0 0 ( a p p r o x . ) 4 0 0 0 ( a p p r o x . )1 8 0 0 0 / 3 = 6 0 0 0 ( a p p r o x . )

P2

P1

P3

PwP3 P2

6 0 0 f6 0 0 f 6 0 0 f

400x800

400x800

W2

W1

CTba400x800

279 KNm 340 KNm

River bed Level

800

Lateral load on the beam due to water presure

NF 13.277

High Flood Level

lood Level

Existing water LevelBed Rock Level

P2 P3Pw

1 8 0 0 0 ( a p p r o x . )4 0 0 0 ( a p p r o x . ) 4 0 0 0 ( a p p r o x . )1 8 0 0 0 / 3 = 6 0 0 0 ( a p p r o x . )

P2

P1

P3

PwP3 P2

6 0 0 f6 0 0 f 6 0 0 f

400x800

400x800

W2

W1

CTba400x800

279 KNm 340 KNm

River bed Level

800

Lateral load on the beam due to water presure

NF 13.277

High Flood Level

lood Level

Existing water LevelBed Rock Level

P2 P3Pw

1 8 0 0 0 ( a p p r o x . )4 0 0 0 ( a p p r o x . ) 4 0 0 0 ( a p p r o x . )1 8 0 0 0 / 3 = 6 0 0 0 ( a p p r o x . )

P2

P1

P3

PwP3 P2

6 0 0 f6 0 0 f 6 0 0 f

400x800

400x800

W2

W1

CTba400x800

279 KNm 340 KNm

River bed Level

800

Lateral load on the beam due to water presure

NF 13.277

High Flood Level

lood Level

Existing water LevelBed Rock Level

P2 P3Pw

1 8 0 0 0 ( a p p r o x . )4 0 0 0 ( a p p r o x . ) 4 0 0 0 ( a p p r o x . )1 8 0 0 0 / 3 = 6 0 0 0 ( a p p r o x . )

P2

P1

P3

PwP3 P2

6 0 0 f6 0 0 f 6 0 0 f

400x800

400x800

W2

W1

CTba400x800

279 KNm 340 KNm

River bed Level

800

Lateral load on the beam due to water presure

NF 13.277

High Flood Level

lood Level

Existing water LevelBed Rock Level

P2 P3Pw

1 8 0 0 0 ( a p p r o x . )4 0 0 0 ( a p p r o x . ) 4 0 0 0 ( a p p r o x . )1 8 0 0 0 / 3 = 6 0 0 0 ( a p p r o x . )

P2

P1

P3

PwP3 P2

6 0 0 f6 0 0 f 6 0 0 f

400x800

400x800

W2

W1

CTba400x800

279 KNm 340 KNm

River bed Level

800

Lateral load on the beam due to water presure

NF 13.277

High Flood Level

lood Level

Existing water LevelBed Rock Level

P2 P3Pw

1 8 0 0 0 ( a p p r o x . )4 0 0 0 ( a p p r o x . ) 4 0 0 0 ( a p p r o x . )1 8 0 0 0 / 3 = 6 0 0 0 ( a p p r o x . )

P2

P1

P3

PwP3 P2

6 0 0 f6 0 0 f 6 0 0 f

400x800

400x800

W2

W1

CTba400x800

279 KNm 340 KNm

River bed Level

800

Lateral load on the beam due to water presure

NF 13.277

High Flood Level

lood Level

Existing water LevelBed Rock Level

P2 P3Pw

1 8 0 0 0 ( a p p r o x . )4 0 0 0 ( a p p r o x . ) 4 0 0 0 ( a p p r o x . )1 8 0 0 0 / 3 = 6 0 0 0 ( a p p r o x . )

P2

P1

P3

PwP3 P2

6 0 0 f6 0 0 f 6 0 0 f

400x800

400x800

W2

W1

CTba400x800

279 KNm 340 KNm

River bed Level

800

Lateral load on the beam due to water presure

NF 13.277

High Flood Level

lood Level

Existing water LevelBed Rock Level

P2 P3Pw

1 8 0 0 0 ( a p p r o x . )4 0 0 0 ( a p p r o x . ) 4 0 0 0 ( a p p r o x . )1 8 0 0 0 / 3 = 6 0 0 0 ( a p p r o x . )

P2

P1

P3

PwP3 P2

6 0 0 f6 0 0 f 6 0 0 f

400x800

400x800

W2

W1

CTba400x800

279 KNm 340 KNm

River bed Level

800

Lateral load on the beam due to water presure

NF 13.277

High Flood Level

lood Level

Existing water LevelBed Rock Level

P2 P3Pw

1 8 0 0 0 ( a p p r o x . )4 0 0 0 ( a p p r o x . ) 4 0 0 0 ( a p p r o x . )1 8 0 0 0 / 3 = 6 0 0 0 ( a p p r o x . )

P2

P1

P3

PwP3 P2

6 0 0 f6 0 0 f 6 0 0 f

400x800

400x800

W2

W1

CTba400x800

279 KNm 340 KNm

River bed Level

800

Lateral load on the beam due to water presure

NF 13.277

High Flood Level

lood Level

Existing water LevelBed Rock Level

P2 P3Pw

1 8 0 0 0 ( a p p r o x . )4 0 0 0 ( a p p r o x . ) 4 0 0 0 ( a p p r o x . )1 8 0 0 0 / 3 = 6 0 0 0 ( a p p r o x . )

P2

P1

P3

PwP3 P2

6 0 0 f6 0 0 f 6 0 0 f

400x800

400x800

W2

W1

CTba400x800

279 KNm 340 KNm

River bed Level

800

Lateral load on the beam due to water presure

NF 13.277

High Flood Level

lood Level

Existing water LevelBed Rock Level

P2 P3Pw

1 8 0 0 0 ( a p p r o x . )4 0 0 0 ( a p p r o x . ) 4 0 0 0 ( a p p r o x . )1 8 0 0 0 / 3 = 6 0 0 0 ( a p p r o x . )

P2

P1

P3

PwP3 P2

6 0 0 f6 0 0 f 6 0 0 f

400x800

400x800

W2

W1

CTba400x800

279 KNm 340 KNm

River bed Level

800

Lateral load on the beam due to water presure

NF 13.277

High Flood Level

lood Level

Existing water LevelBed Rock Level

P2 P3Pw

1 8 0 0 0 ( a p p r o x . )4 0 0 0 ( a p p r o x . ) 4 0 0 0 ( a p p r o x . )1 8 0 0 0 / 3 = 6 0 0 0 ( a p p r o x . )

P2

P1

P3

PwP3 P2

6 0 0 f6 0 0 f 6 0 0 f

400x800

400x800

W2

W1

CTba400x800

279 KNm 340 KNm

River bed Level

800

Lateral load on the beam due to water presure

NF 13.277

High Flood Level

lood Level

Existing water LevelBed Rock Level

P2 P3Pw

1 8 0 0 0 ( a p p r o x . )4 0 0 0 ( a p p r o x . ) 4 0 0 0 ( a p p r o x . )1 8 0 0 0 / 3 = 6 0 0 0 ( a p p r o x . )

P2

P1

P3

PwP3 P2

6 0 0 f6 0 0 f 6 0 0 f

400x800

400x800

W2

W1

CTba400x800

279 KNm 340 KNm

River bed Level

800

Lateral load on the beam due to water presure

NF 13.277

High Flood Level

lood Level

Existing water LevelBed Rock Level

P2 P3Pw

1 8 0 0 0 ( a p p r o x . )4 0 0 0 ( a p p r o x . ) 4 0 0 0 ( a p p r o x . )1 8 0 0 0 / 3 = 6 0 0 0 ( a p p r o x . )

P2

P1

P3

PwP3 P2

6 0 0 f6 0 0 f 6 0 0 f

400x800

400x800

W2

W1

CTba400x800

279 KNm 340 KNm

River bed Level

800

Lateral load on the beam due to water presure

NF 13.277

High Flood Level

lood Level

Existing water LevelBed Rock Level

P2 P3Pw

1 8 0 0 0 ( a p p r o x . )4 0 0 0 ( a p p r o x . ) 4 0 0 0 ( a p p r o x . )1 8 0 0 0 / 3 = 6 0 0 0 ( a p p r o x . )

P2

P1

P3

PwP3 P2

6 0 0 f6 0 0 f 6 0 0 f

400x800

400x800

W2

W1

CTba400x800

279 KNm 340 KNm

River bed Level

800

Lateral load on the beam due to water presure

Page 3: Staircase fdesign

Reference Calculation Output

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

Project: Dahampaya Feature Design of staircase

DESIGN UNIT Designed Date

EPC DIVISION Checked Date

CENTRAL ENGINEERING CONSULTANCY BUREAU (CECB) Job Code D-676 Page

Design for bending

Specimen calculation for second flight:

The staircase can be idealised as follows:

W1 = 18.9kN/mW2 = 16.7kN/m

((21.31*0.85*(4.6+0.425))+(23.5*4.6*3.2))/(4.6+0.85)= 80

4.05= 80.17kN

21.31*0.85+23.5*(4.6+0.85)-80.17= 66

= 66.02kN

0.65 <x< 3.15

Mx = -

d(Mx) = - 8.125x- 14.1x+9.165d(x)

0 = 27.4-22.22x+9.165x = 2.1m

Mmax = (27.4*2.1)-(12.5*.65*1.775)-(14.1*1.05)= 28.3kNm

M =141.90

DEC

RA

RB

RA.x (12.5*.65*(x-0.325))- (14.1*(x-0.65)2/2)

RA

(18.9 *(6.9+0.85)2)/8

850mm 6900mm 0mm

x

A B

W1W2

W1

c/l of landing

Page 4: Staircase fdesign

Reference Calculation Output

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

Project: Dahampaya Feature Design of staircase

DESIGN UNIT Designed Date

EPC DIVISION Checked Date

Job Code D-676 Page

BS 8110 k = M =

Cl. 3.4.4.4

b = 1000 mm

d = 275-25-10= 240mm

=

k = = 0.098 < 0.156 (k')

Hence staircase could be designed as singly reinforced.

z = d (0.5 +

= d (0.5 +

= 0.87d < 0.95d

z = 0.87d= 0.87x 240mm= 208.8mm

As = M

=0.87x460x208.8

Main steel

= =(provide T20 @

150mm)

Check for deflection:

= = 1.515

Table 3.11fs = 5*460*977

(8*1206)

=

DEC

141.90x10 6

bd2.fcu bd2.fcu

fcu 25 N/mm2

141.90x10 6

(1000) (240)2 *25

(0.25- k/0.9)1/2)

(0.25- 0.122/0.9)1/2)

0.87fy.z

141.3x10 6

1698mm2

Provide T16@ 150 spacing (1206mm2)

M/bd2 87.25*10 6

(1000*2402)

233N/mm2

Page 5: Staircase fdesign

Reference Calculation Output

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

Ft = 0.55+(477-233)/120(1.51+0.9)= 1.393706777

Project: Dahampaya Feature Design of staircase

DESIGN UNIT Designed Date

EPC DIVISION Checked Date

CENTRAL ENGINEERING CONSULTANCY BUREAU (CECB) Job Code D-676 Page

Actual span < Allowable spandepth depth

Allowable span = Basic span x F1 x F2depth depth

Basic span = 26depth

Allowable span = 26 x1.39depth = 36.14

Actual span = 5450 = 22.7083333333333

depth 240

Actual span > Allowable spandepth depth

Hence deflection check is not satisfied, and have to increase the tensionsteel.

fs = 5*460*661(8*904)

=

Ft = 0.55+(477-210)/120(0.9+2)= 1.32 Steel for def.:

Allowable span = 26 x1.32 Provide T12 @depth = 34.3 > 34 125mm

Hence deflection check is ok for T12 @ 125mm spacing.

Check for shear

Vmax = 27.4 kN

v = Vbd

= 27.4(1000x119)

=

DEC

Assume T12 @ 125mm spacing (904mm2)

210N/mm2

(As=904mm2)

0.23N/mm2

Page 6: Staircase fdesign

Reference Calculation Output

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

BS 8110 100As/bd = 100(904)/(1000*119)= 0.76

Table 3.9vc = > v , hence O.K.

Project: Dahampaya Feature Design of staircase

DESIGN UNIT Designed Date

EPC DIVISION Checked Date

CENTRAL ENGINEERING CONSULTANCY BUREAU (CECB) Job Code D-676 Page

Distribution steel

No bending moment occurs at transverse direction.

100As/Ac = 0.13

As = (0.13x1000x150)=

Check for maximum bar spacing

Clear spacing between bars > 3d or 750mm

3d = 3*119 = 357mm >250mm

Hence maximum spacing between bars is satisfied.

Check for minimum area of r/f:

100As = 0.13bh

As = 0.13*1000*150100

= <

Stair span and Waist Thickness for first flight:

First flight was supported between raft foundation and landing slab

BS8110Cl.3.10.1.3 Effective span =

= 2.5+0.5(1.563)= 3.28m

Cl.3.10.2.2 Length of stairs (%) = (2.5/3.28)*100% = 76.00% >60%

0.77N/mm2

DEC

195 mm2

Provide T10@ 250mm spacing (As=314mm2)

195mm2/m 904mm2/m

la+ 0.5(lb,1 +lb,2)

Page 7: Staircase fdesign

Reference Calculation Output

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

Hence span/depth enhancement is possible.

I.S.E. manual Assume span/depth ratio of 27 for simply supported oneway spanning Table3 staircase.

Span/depth = 27*1.15= 31

Project: Dahampaya Feature Design of staircase

DESIGN UNIT Designed Date

EPC DIVISION Checked Date

CENTRAL ENGINEERING CONSULTANCY BUREAU (CECB) Job Code D-676 Page

DEC

Page 8: Staircase fdesign

Reference Calculation Output

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

800

Project Feature

DESIGN UNIT Designed Date

EPC DIVISION Checked Date

CENTRAL ENGINEERING CONSULTANCY BUREAU (CECB) Job Code Page

DEC

Page 9: Staircase fdesign

Output

191.66666667

Rise=200mmGoing=250mm

7.75

0.8903225806

217.39130435

Waist thickness 242

275mm

Design of staircase

Date

Page 10: Staircase fdesign

OutputDate

Page 01 of 13

7.92

0.72

0.3

8.94

Design load18.92

7.35

Landing load16.69

High Flood Level

lood Level

Existing water LevelBed Rock Level

4 0 0 0 ( a p p r o x . )1 8 0 0 0 / 3 = 6 0 0 0 ( a p p r o x . )6 0 0 fHigh Flood Level

lood Level

Existing water LevelPoint of virtual fixity

CT =1.5x9.81x{42/(2x9.81)}=12.00 KN/m

River bed Level

400Lateral load on the beam due to water presure

High Flood Level

lood Level

Existing water LevelBed Rock Level

4 0 0 0 ( a p p r o x . )1 8 0 0 0 / 3 = 6 0 0 0 ( a p p r o x . )6 0 0 fHigh Flood Level

lood Level

Existing water LevelPoint of virtual fixity

CT =1.5x9.81x{42/(2x9.81)}=12.00 KN/m

River bed Level

400Lateral load on the beam due to water presure

High Flood Level

lood Level

Existing water LevelBed Rock Level

4 0 0 0 ( a p p r o x . )1 8 0 0 0 / 3 = 6 0 0 0 ( a p p r o x . )6 0 0 fHigh Flood Level

lood Level

Existing water LevelPoint of virtual fixity

CT =1.5x9.81x{42/(2x9.81)}=12.00 KN/m

River bed Level

400Lateral load on the beam due to water presure

High Flood Level

lood Level

Existing water LevelBed Rock Level

4 0 0 0 ( a p p r o x . )1 8 0 0 0 / 3 = 6 0 0 0 ( a p p r o x . )6 0 0 fHigh Flood Level

lood Level

Existing water LevelPoint of virtual fixity

CT =1.5x9.81x{42/(2x9.81)}=12.00 KN/m

River bed Level

400Lateral load on the beam due to water presure

High Flood Level

lood Level

Existing water LevelBed Rock Level

4 0 0 0 ( a p p r o x . )1 8 0 0 0 / 3 = 6 0 0 0 ( a p p r o x . )6 0 0 fHigh Flood Level

lood Level

Existing water LevelPoint of virtual fixity

CT =1.5x9.81x{42/(2x9.81)}=12.00 KN/m

River bed Level

400Lateral load on the beam due to water presure

High Flood Level

lood Level

Existing water LevelBed Rock Level

4 0 0 0 ( a p p r o x . )1 8 0 0 0 / 3 = 6 0 0 0 ( a p p r o x . )6 0 0 fHigh Flood Level

lood Level

Existing water LevelPoint of virtual fixity

CT =1.5x9.81x{42/(2x9.81)}=12.00 KN/m

River bed Level

400Lateral load on the beam due to water presure

High Flood Level

lood Level

Existing water LevelBed Rock Level

4 0 0 0 ( a p p r o x . )1 8 0 0 0 / 3 = 6 0 0 0 ( a p p r o x . )6 0 0 fHigh Flood Level

lood Level

Existing water LevelPoint of virtual fixity

CT =1.5x9.81x{42/(2x9.81)}=12.00 KN/m

River bed Level

400Lateral load on the beam due to water presure

High Flood Level

lood Level

Existing water LevelBed Rock Level

4 0 0 0 ( a p p r o x . )1 8 0 0 0 / 3 = 6 0 0 0 ( a p p r o x . )6 0 0 fHigh Flood Level

lood Level

Existing water LevelPoint of virtual fixity

CT =1.5x9.81x{42/(2x9.81)}=12.00 KN/m

River bed Level

400Lateral load on the beam due to water presure

High Flood Level

lood Level

Existing water LevelBed Rock Level

4 0 0 0 ( a p p r o x . )1 8 0 0 0 / 3 = 6 0 0 0 ( a p p r o x . )6 0 0 fHigh Flood Level

lood Level

Existing water LevelPoint of virtual fixity

CT =1.5x9.81x{42/(2x9.81)}=12.00 KN/m

River bed Level

400Lateral load on the beam due to water presure

High Flood Level

lood Level

Existing water LevelBed Rock Level

4 0 0 0 ( a p p r o x . )1 8 0 0 0 / 3 = 6 0 0 0 ( a p p r o x . )6 0 0 fHigh Flood Level

lood Level

Existing water LevelPoint of virtual fixity

CT =1.5x9.81x{42/(2x9.81)}=12.00 KN/m

River bed Level

400Lateral load on the beam due to water presure

High Flood Level

lood Level

Existing water LevelBed Rock Level

4 0 0 0 ( a p p r o x . )1 8 0 0 0 / 3 = 6 0 0 0 ( a p p r o x . )6 0 0 fHigh Flood Level

lood Level

Existing water LevelPoint of virtual fixity

CT =1.5x9.81x{42/(2x9.81)}=12.00 KN/m

River bed Level

400Lateral load on the beam due to water presure

High Flood Level

lood Level

Existing water LevelBed Rock Level

4 0 0 0 ( a p p r o x . )1 8 0 0 0 / 3 = 6 0 0 0 ( a p p r o x . )6 0 0 fHigh Flood Level

lood Level

Existing water LevelPoint of virtual fixity

CT =1.5x9.81x{42/(2x9.81)}=12.00 KN/m

River bed Level

400Lateral load on the beam due to water presure

High Flood Level

lood Level

Existing water LevelBed Rock Level

4 0 0 0 ( a p p r o x . )1 8 0 0 0 / 3 = 6 0 0 0 ( a p p r o x . )6 0 0 fHigh Flood Level

lood Level

Existing water LevelPoint of virtual fixity

CT =1.5x9.81x{42/(2x9.81)}=12.00 KN/m

River bed Level

400Lateral load on the beam due to water presure

High Flood Level

lood Level

Existing water LevelBed Rock Level

4 0 0 0 ( a p p r o x . )1 8 0 0 0 / 3 = 6 0 0 0 ( a p p r o x . )6 0 0 fHigh Flood Level

lood Level

Existing water LevelPoint of virtual fixity

CT =1.5x9.81x{42/(2x9.81)}=12.00 KN/m

River bed Level

400Lateral load on the beam due to water presure

High Flood Level

lood Level

Existing water LevelBed Rock Level

4 0 0 0 ( a p p r o x . )1 8 0 0 0 / 3 = 6 0 0 0 ( a p p r o x . )6 0 0 fHigh Flood Level

lood Level

Existing water LevelPoint of virtual fixity

CT =1.5x9.81x{42/(2x9.81)}=12.00 KN/m

River bed Level

400Lateral load on the beam due to water presure

High Flood Level

lood Level

Existing water LevelBed Rock Level

4 0 0 0 ( a p p r o x . )1 8 0 0 0 / 3 = 6 0 0 0 ( a p p r o x . )6 0 0 fHigh Flood Level

lood Level

Existing water LevelPoint of virtual fixity

CT =1.5x9.81x{42/(2x9.81)}=12.00 KN/m

River bed Level

400Lateral load on the beam due to water presure

High Flood Level

lood Level

Existing water LevelBed Rock Level

4 0 0 0 ( a p p r o x . )1 8 0 0 0 / 3 = 6 0 0 0 ( a p p r o x . )6 0 0 fHigh Flood Level

lood Level

Existing water LevelPoint of virtual fixity

CT =1.5x9.81x{42/(2x9.81)}=12.00 KN/m

River bed Level

400Lateral load on the beam due to water presure

High Flood Level

lood Level

Existing water LevelBed Rock Level

4 0 0 0 ( a p p r o x . )1 8 0 0 0 / 3 = 6 0 0 0 ( a p p r o x . )6 0 0 fHigh Flood Level

lood Level

Existing water LevelPoint of virtual fixity

CT =1.5x9.81x{42/(2x9.81)}=12.00 KN/m

River bed Level

400Lateral load on the beam due to water presure

High Flood Level

lood Level

Existing water LevelBed Rock Level

4 0 0 0 ( a p p r o x . )1 8 0 0 0 / 3 = 6 0 0 0 ( a p p r o x . )6 0 0 fHigh Flood Level

lood Level

Existing water LevelPoint of virtual fixity

CT =1.5x9.81x{42/(2x9.81)}=12.00 KN/m

River bed Level

400Lateral load on the beam due to water presure

High Flood Level

lood Level

Existing water LevelBed Rock Level

4 0 0 0 ( a p p r o x . )1 8 0 0 0 / 3 = 6 0 0 0 ( a p p r o x . )6 0 0 fHigh Flood Level

lood Level

Existing water LevelPoint of virtual fixity

CT =1.5x9.81x{42/(2x9.81)}=12.00 KN/m

River bed Level

400Lateral load on the beam due to water presure

High Flood Level

lood Level

Existing water LevelBed Rock Level

4 0 0 0 ( a p p r o x . )1 8 0 0 0 / 3 = 6 0 0 0 ( a p p r o x . )6 0 0 fHigh Flood Level

lood Level

Existing water LevelPoint of virtual fixity

CT =1.5x9.81x{42/(2x9.81)}=12.00 KN/m

River bed Level

400Lateral load on the beam due to water presure

High Flood Level

lood Level

Existing water LevelBed Rock Level

4 0 0 0 ( a p p r o x . )1 8 0 0 0 / 3 = 6 0 0 0 ( a p p r o x . )6 0 0 fHigh Flood Level

lood Level

Existing water LevelPoint of virtual fixity

CT =1.5x9.81x{42/(2x9.81)}=12.00 KN/m

River bed Level

400Lateral load on the beam due to water presure

High Flood Level

lood Level

Existing water LevelBed Rock Level

4 0 0 0 ( a p p r o x . )1 8 0 0 0 / 3 = 6 0 0 0 ( a p p r o x . )6 0 0 fHigh Flood Level

lood Level

Existing water LevelPoint of virtual fixity

CT =1.5x9.81x{42/(2x9.81)}=12.00 KN/m

River bed Level

400Lateral load on the beam due to water presure

High Flood Level

lood Level

Existing water LevelBed Rock Level

4 0 0 0 ( a p p r o x . )1 8 0 0 0 / 3 = 6 0 0 0 ( a p p r o x . )6 0 0 fHigh Flood Level

lood Level

Existing water LevelPoint of virtual fixity

CT =1.5x9.81x{42/(2x9.81)}=12.00 KN/m

River bed Level

400Lateral load on the beam due to water presure

High Flood Level

lood Level

Existing water LevelBed Rock Level

4 0 0 0 ( a p p r o x . )1 8 0 0 0 / 3 = 6 0 0 0 ( a p p r o x . )6 0 0 fHigh Flood Level

lood Level

Existing water LevelPoint of virtual fixity

CT =1.5x9.81x{42/(2x9.81)}=12.00 KN/m

River bed Level

400Lateral load on the beam due to water presure

High Flood Level

lood Level

Existing water LevelBed Rock Level

4 0 0 0 ( a p p r o x . )1 8 0 0 0 / 3 = 6 0 0 0 ( a p p r o x . )6 0 0 fHigh Flood Level

lood Level

Existing water LevelPoint of virtual fixity

CT =1.5x9.81x{42/(2x9.81)}=12.00 KN/m

River bed Level

400Lateral load on the beam due to water presure

High Flood Level

lood Level

Existing water LevelBed Rock Level

4 0 0 0 ( a p p r o x . )1 8 0 0 0 / 3 = 6 0 0 0 ( a p p r o x . )6 0 0 fHigh Flood Level

lood Level

Existing water LevelPoint of virtual fixity

CT =1.5x9.81x{42/(2x9.81)}=12.00 KN/m

River bed Level

400Lateral load on the beam due to water presure

High Flood Level

lood Level

Existing water LevelBed Rock Level

4 0 0 0 ( a p p r o x . )1 8 0 0 0 / 3 = 6 0 0 0 ( a p p r o x . )6 0 0 fHigh Flood Level

lood Level

Existing water LevelPoint of virtual fixity

CT =1.5x9.81x{42/(2x9.81)}=12.00 KN/m

River bed Level

400Lateral load on the beam due to water presure

High Flood Level

lood Level

Existing water LevelBed Rock Level

4 0 0 0 ( a p p r o x . )1 8 0 0 0 / 3 = 6 0 0 0 ( a p p r o x . )6 0 0 fHigh Flood Level

lood Level

Existing water LevelPoint of virtual fixity

CT =1.5x9.81x{42/(2x9.81)}=12.00 KN/m

River bed Level

400Lateral load on the beam due to water presure

High Flood Level

lood Level

Existing water LevelBed Rock Level

4 0 0 0 ( a p p r o x . )1 8 0 0 0 / 3 = 6 0 0 0 ( a p p r o x . )6 0 0 fHigh Flood Level

lood Level

Existing water LevelPoint of virtual fixity

CT =1.5x9.81x{42/(2x9.81)}=12.00 KN/m

River bed Level

400Lateral load on the beam due to water presure

High Flood Level

lood Level

Existing water LevelBed Rock Level

4 0 0 0 ( a p p r o x . )1 8 0 0 0 / 3 = 6 0 0 0 ( a p p r o x . )6 0 0 fHigh Flood Level

lood Level

Existing water LevelPoint of virtual fixity

CT =1.5x9.81x{42/(2x9.81)}=12.00 KN/m

River bed Level

400Lateral load on the beam due to water presure

High Flood Level

lood Level

Existing water LevelBed Rock Level

4 0 0 0 ( a p p r o x . )1 8 0 0 0 / 3 = 6 0 0 0 ( a p p r o x . )6 0 0 fHigh Flood Level

lood Level

Existing water LevelPoint of virtual fixity

CT =1.5x9.81x{42/(2x9.81)}=12.00 KN/m

River bed Level

400Lateral load on the beam due to water presure

High Flood Level

lood Level

Existing water LevelBed Rock Level

4 0 0 0 ( a p p r o x . )1 8 0 0 0 / 3 = 6 0 0 0 ( a p p r o x . )6 0 0 fHigh Flood Level

lood Level

Existing water LevelPoint of virtual fixity

CT =1.5x9.81x{42/(2x9.81)}=12.00 KN/m

River bed Level

400Lateral load on the beam due to water presure

High Flood Level

lood Level

Existing water LevelBed Rock Level

4 0 0 0 ( a p p r o x . )1 8 0 0 0 / 3 = 6 0 0 0 ( a p p r o x . )6 0 0 fHigh Flood Level

lood Level

Existing water LevelPoint of virtual fixity

CT =1.5x9.81x{42/(2x9.81)}=12.00 KN/m

River bed Level

400Lateral load on the beam due to water presure

High Flood Level

lood Level

Existing water LevelBed Rock Level

4 0 0 0 ( a p p r o x . )1 8 0 0 0 / 3 = 6 0 0 0 ( a p p r o x . )6 0 0 fHigh Flood Level

lood Level

Existing water LevelPoint of virtual fixity

CT =1.5x9.81x{42/(2x9.81)}=12.00 KN/m

River bed Level

400Lateral load on the beam due to water presure

High Flood Level

lood Level

Existing water LevelBed Rock Level

4 0 0 0 ( a p p r o x . )1 8 0 0 0 / 3 = 6 0 0 0 ( a p p r o x . )6 0 0 fHigh Flood Level

lood Level

Existing water LevelPoint of virtual fixity

CT =1.5x9.81x{42/(2x9.81)}=12.00 KN/m

River bed Level

400Lateral load on the beam due to water presure

High Flood Level

lood Level

Existing water LevelBed Rock Level

4 0 0 0 ( a p p r o x . )1 8 0 0 0 / 3 = 6 0 0 0 ( a p p r o x . )6 0 0 fHigh Flood Level

lood Level

Existing water LevelPoint of virtual fixity

CT =1.5x9.81x{42/(2x9.81)}=12.00 KN/m

River bed Level

400Lateral load on the beam due to water presure

High Flood Level

lood Level

Existing water LevelBed Rock Level

4 0 0 0 ( a p p r o x . )1 8 0 0 0 / 3 = 6 0 0 0 ( a p p r o x . )6 0 0 fHigh Flood Level

lood Level

Existing water LevelPoint of virtual fixity

CT =1.5x9.81x{42/(2x9.81)}=12.00 KN/m

River bed Level

400Lateral load on the beam due to water presure

High Flood Level

lood Level

Existing water LevelBed Rock Level

4 0 0 0 ( a p p r o x . )1 8 0 0 0 / 3 = 6 0 0 0 ( a p p r o x . )6 0 0 fHigh Flood Level

lood Level

Existing water LevelPoint of virtual fixity

CT =1.5x9.81x{42/(2x9.81)}=12.00 KN/m

River bed Level

400Lateral load on the beam due to water presure

High Flood Level

lood Level

Existing water LevelBed Rock Level

4 0 0 0 ( a p p r o x . )1 8 0 0 0 / 3 = 6 0 0 0 ( a p p r o x . )6 0 0 fHigh Flood Level

lood Level

Existing water LevelPoint of virtual fixity

CT =1.5x9.81x{42/(2x9.81)}=12.00 KN/m

River bed Level

400Lateral load on the beam due to water presure

High Flood Level

lood Level

Existing water LevelBed Rock Level

4 0 0 0 ( a p p r o x . )1 8 0 0 0 / 3 = 6 0 0 0 ( a p p r o x . )6 0 0 fHigh Flood Level

lood Level

Existing water LevelPoint of virtual fixity

CT =1.5x9.81x{42/(2x9.81)}=12.00 KN/m

River bed Level

400Lateral load on the beam due to water presure

High Flood Level

lood Level

Existing water LevelBed Rock Level

4 0 0 0 ( a p p r o x . )1 8 0 0 0 / 3 = 6 0 0 0 ( a p p r o x . )6 0 0 fHigh Flood Level

lood Level

Existing water LevelPoint of virtual fixity

CT =1.5x9.81x{42/(2x9.81)}=12.00 KN/m

River bed Level

400Lateral load on the beam due to water presure

High Flood Level

lood Level

Existing water LevelBed Rock Level

4 0 0 0 ( a p p r o x . )1 8 0 0 0 / 3 = 6 0 0 0 ( a p p r o x . )6 0 0 fHigh Flood Level

lood Level

Existing water LevelPoint of virtual fixity

CT =1.5x9.81x{42/(2x9.81)}=12.00 KN/m

River bed Level

400Lateral load on the beam due to water presure

High Flood Level

lood Level

Existing water LevelBed Rock Level

4 0 0 0 ( a p p r o x . )1 8 0 0 0 / 3 = 6 0 0 0 ( a p p r o x . )6 0 0 fHigh Flood Level

lood Level

Existing water LevelPoint of virtual fixity

CT =1.5x9.81x{42/(2x9.81)}=12.00 KN/m

River bed Level

400Lateral load on the beam due to water presure

High Flood Level

lood Level

Existing water LevelBed Rock Level

4 0 0 0 ( a p p r o x . )1 8 0 0 0 / 3 = 6 0 0 0 ( a p p r o x . )6 0 0 fHigh Flood Level

lood Level

Existing water LevelPoint of virtual fixity

CT =1.5x9.81x{42/(2x9.81)}=12.00 KN/m

River bed Level

400Lateral load on the beam due to water presure

High Flood Level

lood Level

Existing water LevelBed Rock Level

4 0 0 0 ( a p p r o x . )1 8 0 0 0 / 3 = 6 0 0 0 ( a p p r o x . )6 0 0 fHigh Flood Level

lood Level

Existing water LevelPoint of virtual fixity

CT =1.5x9.81x{42/(2x9.81)}=12.00 KN/m

River bed Level

400Lateral load on the beam due to water presure

High Flood Level

lood Level

Existing water LevelBed Rock Level

4 0 0 0 ( a p p r o x . )1 8 0 0 0 / 3 = 6 0 0 0 ( a p p r o x . )6 0 0 fHigh Flood Level

lood Level

Existing water LevelPoint of virtual fixity

CT =1.5x9.81x{42/(2x9.81)}=12.00 KN/m

River bed Level

400Lateral load on the beam due to water presure

High Flood Level

lood Level

Existing water LevelBed Rock Level

4 0 0 0 ( a p p r o x . )1 8 0 0 0 / 3 = 6 0 0 0 ( a p p r o x . )6 0 0 fHigh Flood Level

lood Level

Existing water LevelPoint of virtual fixity

CT =1.5x9.81x{42/(2x9.81)}=12.00 KN/m

River bed Level

400Lateral load on the beam due to water presure

High Flood Level

lood Level

Existing water LevelBed Rock Level

4 0 0 0 ( a p p r o x . )1 8 0 0 0 / 3 = 6 0 0 0 ( a p p r o x . )6 0 0 fHigh Flood Level

lood Level

Existing water LevelPoint of virtual fixity

CT =1.5x9.81x{42/(2x9.81)}=12.00 KN/m

River bed Level

400Lateral load on the beam due to water presure

High Flood Level

lood Level

Existing water LevelBed Rock Level

4 0 0 0 ( a p p r o x . )1 8 0 0 0 / 3 = 6 0 0 0 ( a p p r o x . )6 0 0 fHigh Flood Level

lood Level

Existing water LevelPoint of virtual fixity

CT =1.5x9.81x{42/(2x9.81)}=12.00 KN/m

River bed Level

400Lateral load on the beam due to water presure

High Flood Level

lood Level

Existing water LevelBed Rock Level

4 0 0 0 ( a p p r o x . )1 8 0 0 0 / 3 = 6 0 0 0 ( a p p r o x . )6 0 0 fHigh Flood Level

lood Level

Existing water LevelPoint of virtual fixity

CT =1.5x9.81x{42/(2x9.81)}=12.00 KN/m

River bed Level

400Lateral load on the beam due to water presure

High Flood Level

lood Level

Existing water LevelBed Rock Level

4 0 0 0 ( a p p r o x . )1 8 0 0 0 / 3 = 6 0 0 0 ( a p p r o x . )6 0 0 fHigh Flood Level

lood Level

Existing water LevelPoint of virtual fixity

CT =1.5x9.81x{42/(2x9.81)}=12.00 KN/m

River bed Level

400Lateral load on the beam due to water presure

High Flood Level

lood Level

Existing water LevelBed Rock Level

4 0 0 0 ( a p p r o x . )1 8 0 0 0 / 3 = 6 0 0 0 ( a p p r o x . )6 0 0 fHigh Flood Level

lood Level

Existing water LevelPoint of virtual fixity

CT =1.5x9.81x{42/(2x9.81)}=12.00 KN/m

River bed Level

400Lateral load on the beam due to water presure

High Flood Level

lood Level

Existing water LevelBed Rock Level

4 0 0 0 ( a p p r o x . )1 8 0 0 0 / 3 = 6 0 0 0 ( a p p r o x . )6 0 0 fHigh Flood Level

lood Level

Existing water LevelPoint of virtual fixity

CT =1.5x9.81x{42/(2x9.81)}=12.00 KN/m

River bed Level

400Lateral load on the beam due to water presure

High Flood Level

lood Level

Existing water LevelBed Rock Level

4 0 0 0 ( a p p r o x . )1 8 0 0 0 / 3 = 6 0 0 0 ( a p p r o x . )6 0 0 fHigh Flood Level

lood Level

Existing water LevelPoint of virtual fixity

CT =1.5x9.81x{42/(2x9.81)}=12.00 KN/m

River bed Level

400Lateral load on the beam due to water presure

High Flood Level

lood Level

Existing water LevelBed Rock Level

4 0 0 0 ( a p p r o x . )1 8 0 0 0 / 3 = 6 0 0 0 ( a p p r o x . )6 0 0 fHigh Flood Level

lood Level

Existing water LevelPoint of virtual fixity

CT =1.5x9.81x{42/(2x9.81)}=12.00 KN/m

River bed Level

400Lateral load on the beam due to water presure

Page 11: Staircase fdesign

OutputDesign of staircase

Date

Date

Page 02 of 13

W1 W2 W1

Page 12: Staircase fdesign

Output

Design of staircase

Date

Date

Page 03 of 13

0.0985416666666667

0.875647588986155

208.8

1698.14518028342

Main steel

(provide T20 @

150mm)

232.908374792703

1206mm2

Page 13: Staircase fdesign

Output

Design of staircase

Date

Date

Page 04 of 13

Steel for def.:

Provide T12 @125mm(As=904mm2)

Page 14: Staircase fdesign

Output

Design of staircase

Date

Date

Page 05 of 13

Page 15: Staircase fdesign

Output

Design of staircase

Date

Date

Page 06 of 13

Page 16: Staircase fdesign

Output

Date

Date

Page of

Page 17: Staircase fdesign

W1

Page 18: Staircase fdesign

Reference Calculation Outputs

Project Feature DESIGN UNIT Designed Date EPC DIVISION Checked Date CENTRAL ENGINEERING CONSULTANCY BUREAU (CECB) Job Code Page of

DEC

NF 13.277

High Flood Level

lood Level

Existing water LevelBed Rock Level

P2 P3Pw

1 8 0 0 0 ( a p p r o x . )4 0 0 0 ( a p p r o x . ) 4 0 0 0 ( a p p r o x . )1 8 0 0 0 / 3 = 6 0 0 0 ( a p p r o x . )

P2

P1

P3

PwP3 P2

6 0 0 f6 0 0 f 6 0 0 f

400x800

400x800

High Flood Level

lood Level

Existing water Level

Point of virtual fixity

W2

W1

CTba400x800

=1.5x9.81x{42/(2x9.81)}=12.00 KN/m

279 KNm 340 KNm

River bed Level

400

800

Lateral load on the beam due to water presure

NF 13.277

High Flood Level

lood Level

Existing water LevelBed Rock Level

P2 P3Pw

1 8 0 0 0 ( a p p r o x . )4 0 0 0 ( a p p r o x . ) 4 0 0 0 ( a p p r o x . )1 8 0 0 0 / 3 = 6 0 0 0 ( a p p r o x . )

P2

P1

P3

PwP3 P2

6 0 0 f6 0 0 f 6 0 0 f

400x800

400x800

High Flood Level

lood Level

Existing water Level

Point of virtual fixity

W2

W1

CTba400x800

=1.5x9.81x{42/(2x9.81)}=12.00 KN/m

279 KNm 340 KNm

River bed Level

400

800

Lateral load on the beam due to water presure

NF 13.277

High Flood Level

lood Level

Existing water LevelBed Rock Level

P2 P3Pw

1 8 0 0 0 ( a p p r o x . )4 0 0 0 ( a p p r o x . ) 4 0 0 0 ( a p p r o x . )1 8 0 0 0 / 3 = 6 0 0 0 ( a p p r o x . )

P2

P1

P3

PwP3 P2

6 0 0 f6 0 0 f 6 0 0 f

400x800

400x800

High Flood Level

lood Level

Existing water Level

Point of virtual fixity

W2

W1

CTba400x800

=1.5x9.81x{42/(2x9.81)}=12.00 KN/m

279 KNm 340 KNm

River bed Level

400

800

Lateral load on the beam due to water presure

NF 13.277

High Flood Level

lood Level

Existing water LevelBed Rock Level

P2 P3Pw

1 8 0 0 0 ( a p p r o x . )4 0 0 0 ( a p p r o x . ) 4 0 0 0 ( a p p r o x . )1 8 0 0 0 / 3 = 6 0 0 0 ( a p p r o x . )

P2

P1

P3

PwP3 P2

6 0 0 f6 0 0 f 6 0 0 f

400x800

400x800

High Flood Level

lood Level

Existing water Level

Point of virtual fixity

W2

W1

CTba400x800

=1.5x9.81x{42/(2x9.81)}=12.00 KN/m

279 KNm 340 KNm

River bed Level

400

800

Lateral load on the beam due to water presure

NF 13.277

High Flood Level

lood Level

Existing water LevelBed Rock Level

P2 P3Pw

1 8 0 0 0 ( a p p r o x . )4 0 0 0 ( a p p r o x . ) 4 0 0 0 ( a p p r o x . )1 8 0 0 0 / 3 = 6 0 0 0 ( a p p r o x . )

P2

P1

P3

PwP3 P2

6 0 0 f6 0 0 f 6 0 0 f

400x800

400x800

High Flood Level

lood Level

Existing water Level

Point of virtual fixity

W2

W1

CTba400x800

=1.5x9.81x{42/(2x9.81)}=12.00 KN/m

279 KNm 340 KNm

River bed Level

400

800

Lateral load on the beam due to water presure

NF 13.277

High Flood Level

lood Level

Existing water LevelBed Rock Level

P2 P3Pw

1 8 0 0 0 ( a p p r o x . )4 0 0 0 ( a p p r o x . ) 4 0 0 0 ( a p p r o x . )1 8 0 0 0 / 3 = 6 0 0 0 ( a p p r o x . )

P2

P1

P3

PwP3 P2

6 0 0 f6 0 0 f 6 0 0 f

400x800

400x800

High Flood Level

lood Level

Existing water Level

Point of virtual fixity

W2

W1

CTba400x800

=1.5x9.81x{42/(2x9.81)}=12.00 KN/m

279 KNm 340 KNm

River bed Level

400

800

Lateral load on the beam due to water presure

NF 13.277

High Flood Level

lood Level

Existing water LevelBed Rock Level

P2 P3Pw

1 8 0 0 0 ( a p p r o x . )4 0 0 0 ( a p p r o x . ) 4 0 0 0 ( a p p r o x . )1 8 0 0 0 / 3 = 6 0 0 0 ( a p p r o x . )

P2

P1

P3

PwP3 P2

6 0 0 f6 0 0 f 6 0 0 f

400x800

400x800

High Flood Level

lood Level

Existing water Level

Point of virtual fixity

W2

W1

CTba400x800

=1.5x9.81x{42/(2x9.81)}=12.00 KN/m

279 KNm 340 KNm

River bed Level

400

800

Lateral load on the beam due to water presure

NF 13.277

High Flood Level

lood Level

Existing water LevelBed Rock Level

P2 P3Pw

1 8 0 0 0 ( a p p r o x . )4 0 0 0 ( a p p r o x . ) 4 0 0 0 ( a p p r o x . )1 8 0 0 0 / 3 = 6 0 0 0 ( a p p r o x . )

P2

P1

P3

PwP3 P2

6 0 0 f6 0 0 f 6 0 0 f

400x800

400x800

High Flood Level

lood Level

Existing water Level

Point of virtual fixity

W2

W1

CTba400x800

=1.5x9.81x{42/(2x9.81)}=12.00 KN/m

279 KNm 340 KNm

River bed Level

400

800

Lateral load on the beam due to water presure

NF 13.277

High Flood Level

lood Level

Existing water LevelBed Rock Level

P2 P3Pw

1 8 0 0 0 ( a p p r o x . )4 0 0 0 ( a p p r o x . ) 4 0 0 0 ( a p p r o x . )1 8 0 0 0 / 3 = 6 0 0 0 ( a p p r o x . )

P2

P1

P3

PwP3 P2

6 0 0 f6 0 0 f 6 0 0 f

400x800

400x800

High Flood Level

lood Level

Existing water Level

Point of virtual fixity

W2

W1

CTba400x800

=1.5x9.81x{42/(2x9.81)}=12.00 KN/m

279 KNm 340 KNm

River bed Level

400

800

Lateral load on the beam due to water presure

NF 13.277

High Flood Level

lood Level

Existing water LevelBed Rock Level

P2 P3Pw

1 8 0 0 0 ( a p p r o x . )4 0 0 0 ( a p p r o x . ) 4 0 0 0 ( a p p r o x . )1 8 0 0 0 / 3 = 6 0 0 0 ( a p p r o x . )

P2

P1

P3

PwP3 P2

6 0 0 f6 0 0 f 6 0 0 f

400x800

400x800

High Flood Level

lood Level

Existing water Level

Point of virtual fixity

W2

W1

CTba400x800

=1.5x9.81x{42/(2x9.81)}=12.00 KN/m

279 KNm 340 KNm

River bed Level

400

800

Lateral load on the beam due to water presure

NF 13.277

High Flood Level

lood Level

Existing water LevelBed Rock Level

P2 P3Pw

1 8 0 0 0 ( a p p r o x . )4 0 0 0 ( a p p r o x . ) 4 0 0 0 ( a p p r o x . )1 8 0 0 0 / 3 = 6 0 0 0 ( a p p r o x . )

P2

P1

P3

PwP3 P2

6 0 0 f6 0 0 f 6 0 0 f

400x800

400x800

High Flood Level

lood Level

Existing water Level

Point of virtual fixity

W2

W1

CTba400x800

=1.5x9.81x{42/(2x9.81)}=12.00 KN/m

279 KNm 340 KNm

River bed Level

400

800

Lateral load on the beam due to water presure

NF 13.277

High Flood Level

lood Level

Existing water LevelBed Rock Level

P2 P3Pw

1 8 0 0 0 ( a p p r o x . )4 0 0 0 ( a p p r o x . ) 4 0 0 0 ( a p p r o x . )1 8 0 0 0 / 3 = 6 0 0 0 ( a p p r o x . )

P2

P1

P3

PwP3 P2

6 0 0 f6 0 0 f 6 0 0 f

400x800

400x800

High Flood Level

lood Level

Existing water Level

Point of virtual fixity

W2

W1

CTba400x800

=1.5x9.81x{42/(2x9.81)}=12.00 KN/m

279 KNm 340 KNm

River bed Level

400

800

Lateral load on the beam due to water presure

NF 13.277

High Flood Level

lood Level

Existing water LevelBed Rock Level

P2 P3Pw

1 8 0 0 0 ( a p p r o x . )4 0 0 0 ( a p p r o x . ) 4 0 0 0 ( a p p r o x . )1 8 0 0 0 / 3 = 6 0 0 0 ( a p p r o x . )

P2

P1

P3

PwP3 P2

6 0 0 f6 0 0 f 6 0 0 f

400x800

400x800

High Flood Level

lood Level

Existing water Level

Point of virtual fixity

W2

W1

CTba400x800

=1.5x9.81x{42/(2x9.81)}=12.00 KN/m

279 KNm 340 KNm

River bed Level

400

800

Lateral load on the beam due to water presure

NF 13.277

High Flood Level

lood Level

Existing water LevelBed Rock Level

P2 P3Pw

1 8 0 0 0 ( a p p r o x . )4 0 0 0 ( a p p r o x . ) 4 0 0 0 ( a p p r o x . )1 8 0 0 0 / 3 = 6 0 0 0 ( a p p r o x . )

P2

P1

P3

PwP3 P2

6 0 0 f6 0 0 f 6 0 0 f

400x800

400x800

High Flood Level

lood Level

Existing water Level

Point of virtual fixity

W2

W1

CTba400x800

=1.5x9.81x{42/(2x9.81)}=12.00 KN/m

279 KNm 340 KNm

River bed Level

400

800

Lateral load on the beam due to water presure

NF 13.277

High Flood Level

lood Level

Existing water LevelBed Rock Level

P2 P3Pw

1 8 0 0 0 ( a p p r o x . )4 0 0 0 ( a p p r o x . ) 4 0 0 0 ( a p p r o x . )1 8 0 0 0 / 3 = 6 0 0 0 ( a p p r o x . )

P2

P1

P3

PwP3 P2

6 0 0 f6 0 0 f 6 0 0 f

400x800

400x800

High Flood Level

lood Level

Existing water Level

Point of virtual fixity

W2

W1

CTba400x800

=1.5x9.81x{42/(2x9.81)}=12.00 KN/m

279 KNm 340 KNm

River bed Level

400

800

Lateral load on the beam due to water presure

NF 13.277

High Flood Level

lood Level

Existing water LevelBed Rock Level

P2 P3Pw

1 8 0 0 0 ( a p p r o x . )4 0 0 0 ( a p p r o x . ) 4 0 0 0 ( a p p r o x . )1 8 0 0 0 / 3 = 6 0 0 0 ( a p p r o x . )

P2

P1

P3

PwP3 P2

6 0 0 f6 0 0 f 6 0 0 f

400x800

400x800

High Flood Level

lood Level

Existing water Level

Point of virtual fixity

W2

W1

CTba400x800

=1.5x9.81x{42/(2x9.81)}=12.00 KN/m

279 KNm 340 KNm

River bed Level

400

800

Lateral load on the beam due to water presure

NF 13.277

High Flood Level

lood Level

Existing water LevelBed Rock Level

P2 P3Pw

1 8 0 0 0 ( a p p r o x . )4 0 0 0 ( a p p r o x . ) 4 0 0 0 ( a p p r o x . )1 8 0 0 0 / 3 = 6 0 0 0 ( a p p r o x . )

P2

P1

P3

PwP3 P2

6 0 0 f6 0 0 f 6 0 0 f

400x800

400x800

High Flood Level

lood Level

Existing water Level

Point of virtual fixity

W2

W1

CTba400x800

=1.5x9.81x{42/(2x9.81)}=12.00 KN/m

279 KNm 340 KNm

River bed Level

400

800

Lateral load on the beam due to water presure

NF 13.277

High Flood Level

lood Level

Existing water LevelBed Rock Level

P2 P3Pw

1 8 0 0 0 ( a p p r o x . )4 0 0 0 ( a p p r o x . ) 4 0 0 0 ( a p p r o x . )1 8 0 0 0 / 3 = 6 0 0 0 ( a p p r o x . )

P2

P1

P3

PwP3 P2

6 0 0 f6 0 0 f 6 0 0 f

400x800

400x800

High Flood Level

lood Level

Existing water Level

Point of virtual fixity

W2

W1

CTba400x800

=1.5x9.81x{42/(2x9.81)}=12.00 KN/m

279 KNm 340 KNm

River bed Level

400

800

Lateral load on the beam due to water presure

NF 13.277

High Flood Level

lood Level

Existing water LevelBed Rock Level

P2 P3Pw

1 8 0 0 0 ( a p p r o x . )4 0 0 0 ( a p p r o x . ) 4 0 0 0 ( a p p r o x . )1 8 0 0 0 / 3 = 6 0 0 0 ( a p p r o x . )

P2

P1

P3

PwP3 P2

6 0 0 f6 0 0 f 6 0 0 f

400x800

400x800

High Flood Level

lood Level

Existing water Level

Point of virtual fixity

W2

W1

CTba400x800

=1.5x9.81x{42/(2x9.81)}=12.00 KN/m

279 KNm 340 KNm

River bed Level

400

800

Lateral load on the beam due to water presure

NF 13.277

High Flood Level

lood Level

Existing water LevelBed Rock Level

P2 P3Pw

1 8 0 0 0 ( a p p r o x . )4 0 0 0 ( a p p r o x . ) 4 0 0 0 ( a p p r o x . )1 8 0 0 0 / 3 = 6 0 0 0 ( a p p r o x . )

P2

P1

P3

PwP3 P2

6 0 0 f6 0 0 f 6 0 0 f

400x800

400x800

High Flood Level

lood Level

Existing water Level

Point of virtual fixity

W2

W1

CTba400x800

=1.5x9.81x{42/(2x9.81)}=12.00 KN/m

279 KNm 340 KNm

River bed Level

400

800

Lateral load on the beam due to water presure

NF 13.277

High Flood Level

lood Level

Existing water LevelBed Rock Level

P2 P3Pw

1 8 0 0 0 ( a p p r o x . )4 0 0 0 ( a p p r o x . ) 4 0 0 0 ( a p p r o x . )1 8 0 0 0 / 3 = 6 0 0 0 ( a p p r o x . )

P2

P1

P3

PwP3 P2

6 0 0 f6 0 0 f 6 0 0 f

400x800

400x800

High Flood Level

lood Level

Existing water Level

Point of virtual fixity

W2

W1

CTba400x800

=1.5x9.81x{42/(2x9.81)}=12.00 KN/m

279 KNm 340 KNm

River bed Level

400

800

Lateral load on the beam due to water presure

NF 13.277

High Flood Level

lood Level

Existing water LevelBed Rock Level

P2 P3Pw

1 8 0 0 0 ( a p p r o x . )4 0 0 0 ( a p p r o x . ) 4 0 0 0 ( a p p r o x . )1 8 0 0 0 / 3 = 6 0 0 0 ( a p p r o x . )

P2

P1

P3

PwP3 P2

6 0 0 f6 0 0 f 6 0 0 f

400x800

400x800

High Flood Level

lood Level

Existing water Level

Point of virtual fixity

W2

W1

CTba400x800

=1.5x9.81x{42/(2x9.81)}=12.00 KN/m

279 KNm 340 KNm

River bed Level

400

800

Lateral load on the beam due to water presure

NF 13.277

High Flood Level

lood Level

Existing water LevelBed Rock Level

P2 P3Pw

1 8 0 0 0 ( a p p r o x . )4 0 0 0 ( a p p r o x . ) 4 0 0 0 ( a p p r o x . )1 8 0 0 0 / 3 = 6 0 0 0 ( a p p r o x . )

P2

P1

P3

PwP3 P2

6 0 0 f6 0 0 f 6 0 0 f

400x800

400x800

High Flood Level

lood Level

Existing water Level

Point of virtual fixity

W2

W1

CTba400x800

=1.5x9.81x{42/(2x9.81)}=12.00 KN/m

279 KNm 340 KNm

River bed Level

400

800

Lateral load on the beam due to water presure

NF 13.277

High Flood Level

lood Level

Existing water LevelBed Rock Level

P2 P3Pw

1 8 0 0 0 ( a p p r o x . )4 0 0 0 ( a p p r o x . ) 4 0 0 0 ( a p p r o x . )1 8 0 0 0 / 3 = 6 0 0 0 ( a p p r o x . )

P2

P1

P3

PwP3 P2

6 0 0 f6 0 0 f 6 0 0 f

400x800

400x800

High Flood Level

lood Level

Existing water Level

Point of virtual fixity

W2

W1

CTba400x800

=1.5x9.81x{42/(2x9.81)}=12.00 KN/m

279 KNm 340 KNm

River bed Level

400

800

Lateral load on the beam due to water presure

NF 13.277

High Flood Level

lood Level

Existing water LevelBed Rock Level

P2 P3Pw

1 8 0 0 0 ( a p p r o x . )4 0 0 0 ( a p p r o x . ) 4 0 0 0 ( a p p r o x . )1 8 0 0 0 / 3 = 6 0 0 0 ( a p p r o x . )

P2

P1

P3

PwP3 P2

6 0 0 f6 0 0 f 6 0 0 f

400x800

400x800

High Flood Level

lood Level

Existing water Level

Point of virtual fixity

W2

W1

CTba400x800

=1.5x9.81x{42/(2x9.81)}=12.00 KN/m

279 KNm 340 KNm

River bed Level

400

800

Lateral load on the beam due to water presure

NF 13.277

High Flood Level

lood Level

Existing water LevelBed Rock Level

P2 P3Pw

1 8 0 0 0 ( a p p r o x . )4 0 0 0 ( a p p r o x . ) 4 0 0 0 ( a p p r o x . )1 8 0 0 0 / 3 = 6 0 0 0 ( a p p r o x . )

P2

P1

P3

PwP3 P2

6 0 0 f6 0 0 f 6 0 0 f

400x800

400x800

High Flood Level

lood Level

Existing water Level

Point of virtual fixity

W2

W1

CTba400x800

=1.5x9.81x{42/(2x9.81)}=12.00 KN/m

279 KNm 340 KNm

River bed Level

400

800

Lateral load on the beam due to water presure

NF 13.277

High Flood Level

lood Level

Existing water LevelBed Rock Level

P2 P3Pw

1 8 0 0 0 ( a p p r o x . )4 0 0 0 ( a p p r o x . ) 4 0 0 0 ( a p p r o x . )1 8 0 0 0 / 3 = 6 0 0 0 ( a p p r o x . )

P2

P1

P3

PwP3 P2

6 0 0 f6 0 0 f 6 0 0 f

400x800

400x800

High Flood Level

lood Level

Existing water Level

Point of virtual fixity

W2

W1

CTba400x800

=1.5x9.81x{42/(2x9.81)}=12.00 KN/m

279 KNm 340 KNm

River bed Level

400

800

Lateral load on the beam due to water presure

NF 13.277

High Flood Level

lood Level

Existing water LevelBed Rock Level

P2 P3Pw

1 8 0 0 0 ( a p p r o x . )4 0 0 0 ( a p p r o x . ) 4 0 0 0 ( a p p r o x . )1 8 0 0 0 / 3 = 6 0 0 0 ( a p p r o x . )

P2

P1

P3

PwP3 P2

6 0 0 f6 0 0 f 6 0 0 f

400x800

400x800

High Flood Level

lood Level

Existing water Level

Point of virtual fixity

W2

W1

CTba400x800

=1.5x9.81x{42/(2x9.81)}=12.00 KN/m

279 KNm 340 KNm

River bed Level

400

800

Lateral load on the beam due to water presure

NF 13.277

High Flood Level

lood Level

Existing water LevelBed Rock Level

P2 P3Pw

1 8 0 0 0 ( a p p r o x . )4 0 0 0 ( a p p r o x . ) 4 0 0 0 ( a p p r o x . )1 8 0 0 0 / 3 = 6 0 0 0 ( a p p r o x . )

P2

P1

P3

PwP3 P2

6 0 0 f6 0 0 f 6 0 0 f

400x800

400x800

High Flood Level

lood Level

Existing water Level

Point of virtual fixity

W2

W1

CTba400x800

=1.5x9.81x{42/(2x9.81)}=12.00 KN/m

279 KNm 340 KNm

River bed Level

400

800

Lateral load on the beam due to water presure

NF 13.277

High Flood Level

lood Level

Existing water LevelBed Rock Level

P2 P3Pw

1 8 0 0 0 ( a p p r o x . )4 0 0 0 ( a p p r o x . ) 4 0 0 0 ( a p p r o x . )1 8 0 0 0 / 3 = 6 0 0 0 ( a p p r o x . )

P2

P1

P3

PwP3 P2

6 0 0 f6 0 0 f 6 0 0 f

400x800

400x800

High Flood Level

lood Level

Existing water Level

Point of virtual fixity

W2

W1

CTba400x800

=1.5x9.81x{42/(2x9.81)}=12.00 KN/m

279 KNm 340 KNm

River bed Level

400

800

Lateral load on the beam due to water presure

NF 13.277

High Flood Level

lood Level

Existing water LevelBed Rock Level

P2 P3Pw

1 8 0 0 0 ( a p p r o x . )4 0 0 0 ( a p p r o x . ) 4 0 0 0 ( a p p r o x . )1 8 0 0 0 / 3 = 6 0 0 0 ( a p p r o x . )

P2

P1

P3

PwP3 P2

6 0 0 f6 0 0 f 6 0 0 f

400x800

400x800

High Flood Level

lood Level

Existing water Level

Point of virtual fixity

W2

W1

CTba400x800

=1.5x9.81x{42/(2x9.81)}=12.00 KN/m

279 KNm 340 KNm

River bed Level

400

800

Lateral load on the beam due to water presure

NF 13.277

High Flood Level

lood Level

Existing water LevelBed Rock Level

P2 P3Pw

1 8 0 0 0 ( a p p r o x . )4 0 0 0 ( a p p r o x . ) 4 0 0 0 ( a p p r o x . )1 8 0 0 0 / 3 = 6 0 0 0 ( a p p r o x . )

P2

P1

P3

PwP3 P2

6 0 0 f6 0 0 f 6 0 0 f

400x800

400x800

High Flood Level

lood Level

Existing water Level

Point of virtual fixity

W2

W1

CTba400x800

=1.5x9.81x{42/(2x9.81)}=12.00 KN/m

279 KNm 340 KNm

River bed Level

400

800

Lateral load on the beam due to water presure

NF 13.277

High Flood Level

lood Level

Existing water LevelBed Rock Level

P2 P3Pw

1 8 0 0 0 ( a p p r o x . )4 0 0 0 ( a p p r o x . ) 4 0 0 0 ( a p p r o x . )1 8 0 0 0 / 3 = 6 0 0 0 ( a p p r o x . )

P2

P1

P3

PwP3 P2

6 0 0 f6 0 0 f 6 0 0 f

400x800

400x800

High Flood Level

lood Level

Existing water Level

Point of virtual fixity

W2

W1

CTba400x800

=1.5x9.81x{42/(2x9.81)}=12.00 KN/m

279 KNm 340 KNm

River bed Level

400

800

Lateral load on the beam due to water presure

NF 13.277

High Flood Level

lood Level

Existing water LevelBed Rock Level

P2 P3Pw

1 8 0 0 0 ( a p p r o x . )4 0 0 0 ( a p p r o x . ) 4 0 0 0 ( a p p r o x . )1 8 0 0 0 / 3 = 6 0 0 0 ( a p p r o x . )

P2

P1

P3

PwP3 P2

6 0 0 f6 0 0 f 6 0 0 f

400x800

400x800

High Flood Level

lood Level

Existing water Level

Point of virtual fixity

W2

W1

CTba400x800

=1.5x9.81x{42/(2x9.81)}=12.00 KN/m

279 KNm 340 KNm

River bed Level

400

800

Lateral load on the beam due to water presure

NF 13.277

High Flood Level

lood Level

Existing water LevelBed Rock Level

P2 P3Pw

1 8 0 0 0 ( a p p r o x . )4 0 0 0 ( a p p r o x . ) 4 0 0 0 ( a p p r o x . )1 8 0 0 0 / 3 = 6 0 0 0 ( a p p r o x . )

P2

P1

P3

PwP3 P2

6 0 0 f6 0 0 f 6 0 0 f

400x800

400x800

High Flood Level

lood Level

Existing water Level

Point of virtual fixity

W2

W1

CTba400x800

=1.5x9.81x{42/(2x9.81)}=12.00 KN/m

279 KNm 340 KNm

River bed Level

400

800

Lateral load on the beam due to water presure

NF 13.277

High Flood Level

lood Level

Existing water LevelBed Rock Level

P2 P3Pw

1 8 0 0 0 ( a p p r o x . )4 0 0 0 ( a p p r o x . ) 4 0 0 0 ( a p p r o x . )1 8 0 0 0 / 3 = 6 0 0 0 ( a p p r o x . )

P2

P1

P3

PwP3 P2

6 0 0 f6 0 0 f 6 0 0 f

400x800

400x800

High Flood Level

lood Level

Existing water Level

Point of virtual fixity

W2

W1

CTba400x800

=1.5x9.81x{42/(2x9.81)}=12.00 KN/m

279 KNm 340 KNm

River bed Level

400

800

Lateral load on the beam due to water presure

NF 13.277

High Flood Level

lood Level

Existing water LevelBed Rock Level

P2 P3Pw

1 8 0 0 0 ( a p p r o x . )4 0 0 0 ( a p p r o x . ) 4 0 0 0 ( a p p r o x . )1 8 0 0 0 / 3 = 6 0 0 0 ( a p p r o x . )

P2

P1

P3

PwP3 P2

6 0 0 f6 0 0 f 6 0 0 f

400x800

400x800

High Flood Level

lood Level

Existing water Level

Point of virtual fixity

W2

W1

CTba400x800

=1.5x9.81x{42/(2x9.81)}=12.00 KN/m

279 KNm 340 KNm

River bed Level

400

800

Lateral load on the beam due to water presure

NF 13.277

High Flood Level

lood Level

Existing water LevelBed Rock Level

P2 P3Pw

1 8 0 0 0 ( a p p r o x . )4 0 0 0 ( a p p r o x . ) 4 0 0 0 ( a p p r o x . )1 8 0 0 0 / 3 = 6 0 0 0 ( a p p r o x . )

P2

P1

P3

PwP3 P2

6 0 0 f6 0 0 f 6 0 0 f

400x800

400x800

High Flood Level

lood Level

Existing water Level

Point of virtual fixity

W2

W1

CTba400x800

=1.5x9.81x{42/(2x9.81)}=12.00 KN/m

279 KNm 340 KNm

River bed Level

400

800

Lateral load on the beam due to water presure

NF 13.277

High Flood Level

lood Level

Existing water LevelBed Rock Level

P2 P3Pw

1 8 0 0 0 ( a p p r o x . )4 0 0 0 ( a p p r o x . ) 4 0 0 0 ( a p p r o x . )1 8 0 0 0 / 3 = 6 0 0 0 ( a p p r o x . )

P2

P1

P3

PwP3 P2

6 0 0 f6 0 0 f 6 0 0 f

400x800

400x800

High Flood Level

lood Level

Existing water Level

Point of virtual fixity

W2

W1

CTba400x800

=1.5x9.81x{42/(2x9.81)}=12.00 KN/m

279 KNm 340 KNm

River bed Level

400

800

Lateral load on the beam due to water presure

NF 13.277

High Flood Level

lood Level

Existing water LevelBed Rock Level

P2 P3Pw

1 8 0 0 0 ( a p p r o x . )4 0 0 0 ( a p p r o x . ) 4 0 0 0 ( a p p r o x . )1 8 0 0 0 / 3 = 6 0 0 0 ( a p p r o x . )

P2

P1

P3

PwP3 P2

6 0 0 f6 0 0 f 6 0 0 f

400x800

400x800

High Flood Level

lood Level

Existing water Level

Point of virtual fixity

W2

W1

CTba400x800

=1.5x9.81x{42/(2x9.81)}=12.00 KN/m

279 KNm 340 KNm

River bed Level

400

800

Lateral load on the beam due to water presure

NF 13.277

High Flood Level

lood Level

Existing water LevelBed Rock Level

P2 P3Pw

1 8 0 0 0 ( a p p r o x . )4 0 0 0 ( a p p r o x . ) 4 0 0 0 ( a p p r o x . )1 8 0 0 0 / 3 = 6 0 0 0 ( a p p r o x . )

P2

P1

P3

PwP3 P2

6 0 0 f6 0 0 f 6 0 0 f

400x800

400x800

High Flood Level

lood Level

Existing water Level

Point of virtual fixity

W2

W1

CTba400x800

=1.5x9.81x{42/(2x9.81)}=12.00 KN/m

279 KNm 340 KNm

River bed Level

400

800

Lateral load on the beam due to water presure

NF 13.277

High Flood Level

lood Level

Existing water LevelBed Rock Level

P2 P3Pw

1 8 0 0 0 ( a p p r o x . )4 0 0 0 ( a p p r o x . ) 4 0 0 0 ( a p p r o x . )1 8 0 0 0 / 3 = 6 0 0 0 ( a p p r o x . )

P2

P1

P3

PwP3 P2

6 0 0 f6 0 0 f 6 0 0 f

400x800

400x800

High Flood Level

lood Level

Existing water Level

Point of virtual fixity

W2

W1

CTba400x800

=1.5x9.81x{42/(2x9.81)}=12.00 KN/m

279 KNm 340 KNm

River bed Level

400

800

Lateral load on the beam due to water presure

NF 13.277

High Flood Level

lood Level

Existing water LevelBed Rock Level

P2 P3Pw

1 8 0 0 0 ( a p p r o x . )4 0 0 0 ( a p p r o x . ) 4 0 0 0 ( a p p r o x . )1 8 0 0 0 / 3 = 6 0 0 0 ( a p p r o x . )

P2

P1

P3

PwP3 P2

6 0 0 f6 0 0 f 6 0 0 f

400x800

400x800

High Flood Level

lood Level

Existing water Level

Point of virtual fixity

W2

W1

CTba400x800

=1.5x9.81x{42/(2x9.81)}=12.00 KN/m

279 KNm 340 KNm

River bed Level

400

800

Lateral load on the beam due to water presure

NF 13.277

High Flood Level

lood Level

Existing water LevelBed Rock Level

P2 P3Pw

1 8 0 0 0 ( a p p r o x . )4 0 0 0 ( a p p r o x . ) 4 0 0 0 ( a p p r o x . )1 8 0 0 0 / 3 = 6 0 0 0 ( a p p r o x . )

P2

P1

P3

PwP3 P2

6 0 0 f6 0 0 f 6 0 0 f

400x800

400x800

High Flood Level

lood Level

Existing water Level

Point of virtual fixity

W2

W1

CTba400x800

=1.5x9.81x{42/(2x9.81)}=12.00 KN/m

279 KNm 340 KNm

River bed Level

400

800

Lateral load on the beam due to water presure

NF 13.277

High Flood Level

lood Level

Existing water LevelBed Rock Level

P2 P3Pw

1 8 0 0 0 ( a p p r o x . )4 0 0 0 ( a p p r o x . ) 4 0 0 0 ( a p p r o x . )1 8 0 0 0 / 3 = 6 0 0 0 ( a p p r o x . )

P2

P1

P3

PwP3 P2

6 0 0 f6 0 0 f 6 0 0 f

400x800

400x800

High Flood Level

lood Level

Existing water Level

Point of virtual fixity

W2

W1

CTba400x800

=1.5x9.81x{42/(2x9.81)}=12.00 KN/m

279 KNm 340 KNm

River bed Level

400

800

Lateral load on the beam due to water presure

NF 13.277

High Flood Level

lood Level

Existing water LevelBed Rock Level

P2 P3Pw

1 8 0 0 0 ( a p p r o x . )4 0 0 0 ( a p p r o x . ) 4 0 0 0 ( a p p r o x . )1 8 0 0 0 / 3 = 6 0 0 0 ( a p p r o x . )

P2

P1

P3

PwP3 P2

6 0 0 f6 0 0 f 6 0 0 f

400x800

400x800

High Flood Level

lood Level

Existing water Level

Point of virtual fixity

W2

W1

CTba400x800

=1.5x9.81x{42/(2x9.81)}=12.00 KN/m

279 KNm 340 KNm

River bed Level

400

800

Lateral load on the beam due to water presure

NF 13.277

High Flood Level

lood Level

Existing water LevelBed Rock Level

P2 P3Pw

1 8 0 0 0 ( a p p r o x . )4 0 0 0 ( a p p r o x . ) 4 0 0 0 ( a p p r o x . )1 8 0 0 0 / 3 = 6 0 0 0 ( a p p r o x . )

P2

P1

P3

PwP3 P2

6 0 0 f6 0 0 f 6 0 0 f

400x800

400x800

High Flood Level

lood Level

Existing water Level

Point of virtual fixity

W2

W1

CTba400x800

=1.5x9.81x{42/(2x9.81)}=12.00 KN/m

279 KNm 340 KNm

River bed Level

400

800

Lateral load on the beam due to water presure

NF 13.277

High Flood Level

lood Level

Existing water LevelBed Rock Level

P2 P3Pw

1 8 0 0 0 ( a p p r o x . )4 0 0 0 ( a p p r o x . ) 4 0 0 0 ( a p p r o x . )1 8 0 0 0 / 3 = 6 0 0 0 ( a p p r o x . )

P2

P1

P3

PwP3 P2

6 0 0 f6 0 0 f 6 0 0 f

400x800

400x800

High Flood Level

lood Level

Existing water Level

Point of virtual fixity

W2

W1

CTba400x800

=1.5x9.81x{42/(2x9.81)}=12.00 KN/m

279 KNm 340 KNm

River bed Level

400

800

Lateral load on the beam due to water presure

NF 13.277

High Flood Level

lood Level

Existing water LevelBed Rock Level

P2 P3Pw

1 8 0 0 0 ( a p p r o x . )4 0 0 0 ( a p p r o x . ) 4 0 0 0 ( a p p r o x . )1 8 0 0 0 / 3 = 6 0 0 0 ( a p p r o x . )

P2

P1

P3

PwP3 P2

6 0 0 f6 0 0 f 6 0 0 f

400x800

400x800

High Flood Level

lood Level

Existing water Level

Point of virtual fixity

W2

W1

CTba400x800

=1.5x9.81x{42/(2x9.81)}=12.00 KN/m

279 KNm 340 KNm

River bed Level

400

800

Lateral load on the beam due to water presure

NF 13.277

High Flood Level

lood Level

Existing water LevelBed Rock Level

P2 P3Pw

1 8 0 0 0 ( a p p r o x . )4 0 0 0 ( a p p r o x . ) 4 0 0 0 ( a p p r o x . )1 8 0 0 0 / 3 = 6 0 0 0 ( a p p r o x . )

P2

P1

P3

PwP3 P2

6 0 0 f6 0 0 f 6 0 0 f

400x800

400x800

High Flood Level

lood Level

Existing water Level

Point of virtual fixity

W2

W1

CTba400x800

=1.5x9.81x{42/(2x9.81)}=12.00 KN/m

279 KNm 340 KNm

River bed Level

400

800

Lateral load on the beam due to water presure

NF 13.277

High Flood Level

lood Level

Existing water LevelBed Rock Level

P2 P3Pw

1 8 0 0 0 ( a p p r o x . )4 0 0 0 ( a p p r o x . ) 4 0 0 0 ( a p p r o x . )1 8 0 0 0 / 3 = 6 0 0 0 ( a p p r o x . )

P2

P1

P3

PwP3 P2

6 0 0 f6 0 0 f 6 0 0 f

400x800

400x800

High Flood Level

lood Level

Existing water Level

Point of virtual fixity

W2

W1

CTba400x800

=1.5x9.81x{42/(2x9.81)}=12.00 KN/m

279 KNm 340 KNm

River bed Level

400

800

Lateral load on the beam due to water presure

NF 13.277

High Flood Level

lood Level

Existing water LevelBed Rock Level

P2 P3Pw

1 8 0 0 0 ( a p p r o x . )4 0 0 0 ( a p p r o x . ) 4 0 0 0 ( a p p r o x . )1 8 0 0 0 / 3 = 6 0 0 0 ( a p p r o x . )

P2

P1

P3

PwP3 P2

6 0 0 f6 0 0 f 6 0 0 f

400x800

400x800

High Flood Level

lood Level

Existing water Level

Point of virtual fixity

W2

W1

CTba400x800

=1.5x9.81x{42/(2x9.81)}=12.00 KN/m

279 KNm 340 KNm

River bed Level

400

800

Lateral load on the beam due to water presure

NF 13.277

High Flood Level

lood Level

Existing water LevelBed Rock Level

P2 P3Pw

1 8 0 0 0 ( a p p r o x . )4 0 0 0 ( a p p r o x . ) 4 0 0 0 ( a p p r o x . )1 8 0 0 0 / 3 = 6 0 0 0 ( a p p r o x . )

P2

P1

P3

PwP3 P2

6 0 0 f6 0 0 f 6 0 0 f

400x800

400x800

High Flood Level

lood Level

Existing water Level

Point of virtual fixity

W2

W1

CTba400x800

=1.5x9.81x{42/(2x9.81)}=12.00 KN/m

279 KNm 340 KNm

River bed Level

400

800

Lateral load on the beam due to water presure

NF 13.277

High Flood Level

lood Level

Existing water LevelBed Rock Level

P2 P3Pw

1 8 0 0 0 ( a p p r o x . )4 0 0 0 ( a p p r o x . ) 4 0 0 0 ( a p p r o x . )1 8 0 0 0 / 3 = 6 0 0 0 ( a p p r o x . )

P2

P1

P3

PwP3 P2

6 0 0 f6 0 0 f 6 0 0 f

400x800

400x800

High Flood Level

lood Level

Existing water Level

Point of virtual fixity

W2

W1

CTba400x800

=1.5x9.81x{42/(2x9.81)}=12.00 KN/m

279 KNm 340 KNm

River bed Level

400

800

Lateral load on the beam due to water presure

NF 13.277

High Flood Level

lood Level

Existing water LevelBed Rock Level

P2 P3Pw

1 8 0 0 0 ( a p p r o x . )4 0 0 0 ( a p p r o x . ) 4 0 0 0 ( a p p r o x . )1 8 0 0 0 / 3 = 6 0 0 0 ( a p p r o x . )

P2

P1

P3

PwP3 P2

6 0 0 f6 0 0 f 6 0 0 f

400x800

400x800

High Flood Level

lood Level

Existing water Level

Point of virtual fixity

W2

W1

CTba400x800

=1.5x9.81x{42/(2x9.81)}=12.00 KN/m

279 KNm 340 KNm

River bed Level

400

800

Lateral load on the beam due to water presure

NF 13.277

High Flood Level

lood Level

Existing water LevelBed Rock Level

P2 P3Pw

1 8 0 0 0 ( a p p r o x . )4 0 0 0 ( a p p r o x . ) 4 0 0 0 ( a p p r o x . )1 8 0 0 0 / 3 = 6 0 0 0 ( a p p r o x . )

P2

P1

P3

PwP3 P2

6 0 0 f6 0 0 f 6 0 0 f

400x800

400x800

High Flood Level

lood Level

Existing water Level

Point of virtual fixity

W2

W1

CTba400x800

=1.5x9.81x{42/(2x9.81)}=12.00 KN/m

279 KNm 340 KNm

River bed Level

400

800

Lateral load on the beam due to water presure