Stability Chirag
-
Upload
leidy-laura-alvarez-berrio -
Category
Documents
-
view
223 -
download
0
Transcript of Stability Chirag
-
8/11/2019 Stability Chirag
1/72
Chirag Wellbore Stability
Study - Part 1,
Azerbaijan
S/UTG/105/00
Sophie Louise Dowson
UTG Drilling Sunbury
Upstream Technology Group, Sunbury
August 2000 GQS50101
-
8/11/2019 Stability Chirag
2/72
UNCLASSIFIED
The information contained in this document is the property of BP Exploration. Due
acknowledgement should be made if it is desired to refer to this information in publications or
discussions with third parties.
-
8/11/2019 Stability Chirag
3/72
UTG Indexing Sheet
TEAM REPORT NO. JOB NO.
U T G D R G U T G / 1 0 5 / 0 0 8 7 1 0 5 2 0
AUTHOR(S) TELEPHONE LOCATION DATE
Sophie Louise Dowson 01932 764541 200 / G27 August 2000
MAIN TITLE
Chirag Wellbore Stability Study - Part 1, Azerbaijan
CLIENT PRINCIPAL RECIPIENT COMMISSIONED BY
Chirag Drilling Team Tom Scoular Tom Scoular
SECURITY CLASSIFICATION UNCLASSIFIED CONFIDENTIAL SECRET
KEYWORDS
Chirag, Wellbore Stability
ACKNOWLEDGEMENT
RECORD PAGE
FOR EXTERNAL CLIENT LISTING DISTRIBUTION
OVERLEAF
ABSTRACT
The main objective of this report was to review existing well data for the Chirag Field to assess further wellbore stability
work requirements for future development drilling. Particular emphasis was given to well A-15 due to spud in August
2000.
Within well A-15, the most troublesome sections identified with regard to instability were the 12.25 pilot and side-track
hole sections. Mud weight recommendations for minimising instability in each hole section are as follows:
26 hole section : static mud weight of 8.6 ppg to 8.7 ppg
17.5 hole section : static mud weight of 12.1 ppg. Dynamic losses experienced in previous wells highlights the need
to maintain a reasonable ECD margin that does not exceed the fracture gradient. Since previous development wells
have experienced chemical instability it is important that drilling mud inhibition is optimised.
12.25 pilot hole and side-track sections : static mud weight of 12.4 ppg. As with the 17.5 hole, occurrences of
chemical instability in previous development wells highlights the importance of optimising drilling mud inhibition.
8.5 hole section : static mud weight of between 11.2 ppg to 11.4 ppg
The most problematic formations within the 12.25 pilot hole section appear to be the Sabunchi and Balakhany. Previous
occurrences of instability may have potentially been attributed to overpressured zones within the Sabunchi and inaddition to intact failure, slippage along pre-existing weakness planes within base Sabunchi / Balakhany. Minimum mud
weight requirements for the 8.5 hole are those required to minimise instability within the shale interbeds. Since the 8.5
hole will be terminated in the Pereriv instability concerns relating to the NKG need not be considered.
Conclusions relating to existing data and analysis needs, for future development drilling, highlight the need for additional
data acquisition above the Sabunchi. Future wellbore stability work identified includes a larger generic ERD study and a
more specific study for the forthcoming A-16 well.
PREPARED BY:
Sophie L. Dowson
.....................................................
APPROVED BY:
Sophie L. Dowson
AUTHORISED FOR ISSUE BY:
Sophie L. Dowson
..........................................................
ISSUE DATE: August 2000
-
8/11/2019 Stability Chirag
4/72
DISTRIBUTION LIST
NO. OF COPIES NAME LOCATION
1-2 BDM Library Sunbury (122/105)3 UTG Drilling Team Files Sunbury (200/G27)4 Tim Bailey UTG Sunbury (200/G27)5 Sophie Dowson UTG Sunbury (200/G27)
6 - 7 Tom Scoular Chirag Asset8 Nigel Last UTG Sunbury (200/G27)
-
8/11/2019 Stability Chirag
5/72
CONTENTS
Page No
1. Study Scope 1
2. Principal Conclusions and Recommendations 2
3. Data Review Summary 4
3.1 Review of Chi rag Development Wells 4
3.1.1 26 Hole Section and 20 Casing 4
3.1.2 17.5 Hole Section and 13.375 Casing 5
3.1.3 12.25 Hole Section and 9.625 Casing 7
3.1.4 8.5 Hole Section and 7.0 L iner 9
3.2 Review of Exploration Well GCA-1 10
3.2.1 36 Hole Section and 30 Conductor 10
3.2.2 26 Hole Section and 20 Casing 10
3.2.3 17.5 Hole Section and 13.375 Casing 10
3.2.4 12.25 Hole Section and 9.625 Casing 10
3.2.5 8.5 Hole Section and 7.0 L iner 11
3.3 Previous Report Summary 11
4. A15 Stabil i ty Assessment and Mud Weight Requirements 13
4.1 Planned Tr ajectory and Subsur face Condi tions 13
4.2 Compressive Failure Analysis of I ntact Formation 15
4.3 Fail ur e Along Pre-existing Weakness Planes 20
4.4 Tensile Fail ure and Risk of Losses 25
4.5 Mud Weight Recommendations for A-15 26
5 Data Acquisiti on Requir ements for A15 and Future Well s 30
6. Additional Well bore Stabil ity Work to Support Future ERD Dr il li ng 31
7. References 32
-
8/11/2019 Stability Chirag
6/72
APPENDIX A: F ield I nformation and Offset Well Review 33
APPENDI X B: Review of Previous Studies for Chir ag 42
B1 Exxon Well bore Stabili ty Report 42B2 BP Review of In-Situ Stresses & Rock Mechanical Properties for Fracturing 47
B3 Notes by Tetsuro Tochi kawa 48
B4 Notes by Dr Nobuo Mori ta 48
B5 Characterisation of Shale Samples fr om Well A-13 49
APPENDIX C: Defini tion of Subsur face Conditions perti nent to A-15 51
C1 I ntact Rock Formation Properties 51
C2 Pre-existing Weakness Planes / Faul ts 56
C3 Prognosed Pore and Fracture Pressures 57
C4 Stress Regime and Direction 59
C5 Principal Stress Magnitudes 60
C5.1 Vertical Stress 60
C5.2 Maximum and M in imum Hori zontal Stresses 63
-
8/11/2019 Stability Chirag
7/72
S/UTG/105/00 Study Scope
August 2000 Page 1
1. Study Scope
This report has been compiled as the final deliverable for work requested by Tom Scoular of the ChiragAsset, Azerbaijan Business Unit, in March 2000. The main aim of the study was to review existing well
data for the Chirag Field to assess further wellbore stability work requirements for future development
drilling. Particular emphasis was given to well A-15 due to spud in August 2000. Based on the initial
workscope, study objectives were as follows:
Review available data and reports pertinent to wellbore instability
Based on review findings advise whether further wellbore stability analyses required for the Chirag
ERD well programme
Identify additional data required for future analyses and better definition of subsurface conditions
Advise what data, if any, should be obtained from well A-15, due to spud in August 2000
Conduct a stability analyses for well A-15 and recommend mud weight requirements to minimisehole instability
-
8/11/2019 Stability Chirag
8/72
S/UTG/105/00 Principal Conclusions and Recommendations
August 2000 Page 2
2. Pri ncipal Conclusions and Recommendations
Based on findings from this study conclusions and recommendations may be split into those specific tothe forthcoming A-15 well and data / analysis needs for future development drilling.
Recommendations for minimising instability within the A-15 well are as follows:
Within the 26 hole section a static mud weight of 8.6 ppg is recommended to minimise the risk of
instability. If tight spots are encountered density may be raised to 8.7 ppg.
Within the 17.5 hole section a static mud weight of 12.1 ppg is recommended to minimise the risk
of instability. Dynamic losses experienced in previous wells highlights the need to maintain a
reasonable ECD margin that does not exceed the fracture gradient. Since previous development
wells have experienced chemical instability it is important that drilling mud inhibition is optimised.
Within the 12.25 pilot hole and side-track sections a static mud weight of 12.4 ppg is recommended
to minimise the risk of instability. As with the 17.5 hole, occurrences of chemical instability in
previous development wells highlights the importance of optimising drilling mud inhibition.
The most problematic formations within the 12.25 pilot hole section appear to be the Sabunchi and
Balakhany. Previous occurrences of instability may have potentially been attributed to
overpressured zones within the Sabunchi and in addition to intact failure, slippage along pre-existing
weakness planes within base Sabunchi / Balakhany.
Within the 8.5 hole section a static mud weight of between 11.2 to 11.4 ppg is recommended to
minimise the risk of instability. Uncertainty in mud weight results from uncertainty in stress regimewithin the Pereriv which may be reverse as opposed to extensional. In addition to shear failure of the
intact formation, bedding plane slip may be a further risk of instability within the 8.5 hole although
not considered as severe a risk compared with the Balakhany. Although the majority of the Pereriv
is sandstone and potentially able to be drilled with a nominal overbalance, mud weights
recommended are those required to minimise the risk of instability within shale inter-beds.
A further risk of instability within the 8.5 hole section is a buckling mode of failure in the roof of
the borehole which may occur if the well is drilled within 10oof bedding. Instability may also be
compounded where the well crosses the prognosed thrust fault when slippage along pre-existing
weakness planes may be a further risk. Without knowing the dip and dip direction of the fault at the
point where it crosses the well path, however, analyses cannot be conducted to provide a qualitativeassessment of instability risk. Since the 8.5 hole will be terminated in the Pereriv instability
concerns relating to the NKG need not be considered.
Due to the increased risk of instability within the 12.25 and 8.5 hole sections as evidenced by
occurrences of large caving volumes in previously drilled development wells, it is recommended that
cavings morphology be continuously monitored at the rig site. Such procedures will enable the
correct failure mode to be identified thus allowing the most suitable remedial action to be taken.
Comparing minimum mud weight recommendations with fracture gradient values induced fractures
are not considered to be a risk but will be dependant on the ECD margin. The main risk of losses for
A-15 will be those that may be associated with pre-existing fractures and faults. From results of
-
8/11/2019 Stability Chirag
9/72
S/UTG/105/00 Principal Conclusions and Recommendations
August 2000 Page 3
work conducted by Tetsuro and notes made by Jake Hossack of BP, risk of losses along the A-15
trajectory are considered to be of medium severity.
Conclusions relating to existing data and analysis needs for future development drilling are as follows:
Within previous exploration, appraisal and development wells data is limited above the Sabunchi
for characterisation of overburden properties
For definition of the overburden gradient and rock properties, density, sonic and gamma ray logs
should be extended to mud line.
Current uncertainty exists in the stress regime and magnitudes of the two horizontal stresses.
Within reservoir formations the vertical stress may no longer be the largest component if the stress
regime is reverse as opposed to extensional
To better constrain stress magnitudes more information on the type and degree of hole failure isrequired. Continual monitoring of cavings at the rig site will help to differentiate between failure
modes. Image log data would then further help to define the degree and extent of failed zones. If
image logs cannot be run four to six arm oriented callipers should be used instead.
For definition of the minimum principal stress magnitude leak off tests should be extended in future
wells to give closure pressure values. Ideally a reopening cycle should also be conducted to define
the tensile strength of the formation.
For stress direction, breakout studies conducted to date take no consideration of wellbore
inclination and azimuth. For this reason, stress direction is currently based on observations of hole
failure within the vertical exploration well GCA-1.
ECD values should be closely monitored in future wells to assess actual downhole values
associated with losses and gains. As wells become longer reach and higher angle there may be a
need to differentiate between losses and gains associated with wellbore breathing and zones drilled
underbalance.
For future development drilling additional stability analyses will be required. Given the complexity
of the structure, however, additional data is needed to better define subsurface conditions. A stress
cube approach is suggested to better define the problem.
Future wellbore stability needs identified for the Chirag Asset include a larger generic ERD study
and a more specific study for the forthcoming A-16 well.
-
8/11/2019 Stability Chirag
10/72
S/UTG/105/00 Data Review Summary
August 2000 Page 4
3. Data Review Summary
In order to assess the need for further wellbore stability analyses in support of future developmentdrilling options, all pertinent data has been reviewed. A main part of this review included the need to
ascertain subsurface conditions from drilling experience gained to date. Studying drilling reports for all
wells on the Chirag Structure, summary charts have been compiled for each formation. Also collated as
part of the study is information that was contained in previous reports and memos addressing
geomechanical issues.
3.1 Review of Chi rag Development Wells
End of well reports for all fourteen development wells, A-1 to A-14, were used to provide summary
information for all formations drilled. Resulting spreadsheets are presented in Appendix A with asummary of pertinent information provided below for each hole section. In addition to well reports
notes were also made from conversations held with Asset staff about drilling experiences to date.
Information believed to be of relevance is included in the hole section summaries also. All depths
referred to in the text are measured and relative to the rotary table elevation.
3.1.1 26 Hole Section and 20 Casing
The 26 top hole sections of all development wells were drilled through Recent Sediments and for all,
but well A-3, TDd in the Apsheron Formation. Within well A-3, the section was extended further and
TDd in the Akchagyl Formation. In wells A-1, A-2, A-3, A-4, A-5 and A-6, a 17.5 pilot hole was
drilled prior to the section being enlarged with a 26 hole opener. In all other wells the pilot hole drilledwas 12.25 in diameter.
Hole inclinations within this section are near vertical. In the Recent Sediments, inclinations varied from
0o to 12o and in the Apsheron inclination ranges were between 1.25o and 13o. Within the Akchagil
Formation, well A-3 inclination was about 3.5o.
Drilling mud used was always seawater with viscous sweeps. Densities ranged from 8.4 to 8.7 ppg,
although the higher weights were typically spud weights that the hole was displaced with after having
drilled the section.
Overall, hole conditions in this section were good whilst drilling. Only a few problems were reported in
terms of losses and very occasional tight spots. For the majority of cases, good returns were obtained
whilst running casing and cementing. In a few instances, however, losses were reported with the
majority of cases being associated with pumping the tail slurry. Lead cement densities were typically
11.9 ppg, although in well A-1 lead density was a lower value of 11.1 ppg. Tail cement densities were
typically 15.8 ppg.
Regards drilling, losses occurred in well A-3 whilst pumping a 9.5 ppg sweep with the assumed lost
zone in the Recent Sediments around 350m +/- 20m. At 364m, the A-3 hole was washed and reamed to
393m and within the Apsheron Formation the hole was tight at 560m and 460m during a wiper trip.
Within well A-13 while opening up the Pilot hole, the BHA was unable to get past an obstruction in the
Recent Sediments at 390m : returns were lost whilst circulating and working the string. Using a new
assembly, well A-13 was washed and reamed from 390m to 478m. Within well A-14, the hole opener
-
8/11/2019 Stability Chirag
11/72
-
8/11/2019 Stability Chirag
12/72
S/UTG/105/00 Data Review Summary
August 2000 Page 6
conversations with Asset staff it is noted that wells drilled across the Chirag Structure appeared to be
more susceptible to losses (e.g. A-4). Mention was also made that in high angle hole sections some
stuck pipe incidents appear to be associated with sliding towards the base of the 17.5 section. Casing
running operations were generally good with only occasional losses reported. During cementing, losses
were reported for certain wells during both pumping and displacement. Within earlier wells (A-1, A-2)lead cement densities were 12.5 ppg but within all other wells this was increased to 13.5 ppg. Tail
cement densities were the same for all wells, 15.8 ppg.
Regards drilling, a 9.6 ppg brine flow was noted in well A-1 between the 20 and 13 3/8 annulus
which took 14 days to stop. It is believed that the flow was emanating from just above the Surakhany
within the Akchagyl. Within well A-2, pit level fluctuations and an increase in Cl2indicted a further
possible brine flow. For well A-3, drilling records note dynamic losses of about 20 bbls an hour. A
further brine flow was also noted in well A-3 within the 20 and 13 3/8 annulus. It is remarked that
over-pressured salt water formations were not isolated with the most likely cause being loss of
hydrostatic head as the slurry set up together with the existence of a channel behind the casing. Within
well A-4, gumbo problems lead to pack off at 922m during a wiper trip. Losses were also noted in theAkchagyl at 737m. Below 1108m, losses were dynamic with gains reported when static. Tight spots
were also noted in other wells such as A-5 at 800m and A-6, both of which noted high percentages of
fine cuttings. Within well A-7, a wiper trip to TD resulted in the hole packing off with losses noted
also. After having pulled out of the hole and ran back in with a new bottom hole assembly it was
necessary to wash and ream from 788m in the Akchagyl. An inadvertent side-track at 1043m was noted
so the well had to be re-drilled. Within well A-8, wiper trips were conducted every 300m to improve
hole conditions resulting from gumbo related problems. Large cuttings volumes were reported after
trips but cuttings integrity was supposedly good. Within wells A-9, A10, A12, A13 and A14, the use of
a much more inhibitive Quadrill mud system dramatically improved hole conditions. Within well A-9,
overpull was much reduced and hole conditions appeared good with no losses. Within well A-10 the
inhibitive mud system is noted as improving stability and providing good cuttings integrity. A-12 and
A-14 were also drilled supposedly trouble free but A-13 was noted as having occasional gumbo and
losses. Within well A-11, the section was supposedly less challenging so a KCl / PHPA system was
used with addition of Staplex 500. Although better than some of the earlier wells drilled without
addition of Staplex, gumbo problems were still noted with flowline blockage and tight hole on wiper
trips.
Regards casing running, the only occasional losses reported were 15bbls within well A-6.
Regards casing cementing, losses were reported in certain wells. Within well A-1, losses were noted
during circulation prior to cementing, during mixing / pumping and displacement. Within well A-3,
losses were recorded during displacement and within A-5 returns began to diminish towards the end of
pumping. Within well A-7, good returns were reported whilst mixing / pumping but none duringdisplacement. Within A-8, partial to total losses were taken during displacement of the tail slurry.
Within well A-14, partial returns were noted after pumping 398 bbls displacement with lost returns
after 488 bbls. A total of 307 bbls were lost during the cement job.
-
8/11/2019 Stability Chirag
13/72
S/UTG/105/00 Data Review Summary
August 2000 Page 7
3.1.3 12.25 Hole Section and 9.625 Casing
The 12.25 hole sections of all wells were drilled through the remainder of the Surakhany, the Sabunchi
and then either TDd in the Balakhany, the Pereriv or the NKG. 12.25 sections of wells A-1, A-2, A-
7, A-9 and A-14 TDd in the Balakhany and wells A-3, A-8, A-11, A-13 which were TDd in thePereriv all had 8.5 hole sections drilled to well TD within the Pereriv. In certain cases, however, wells
were all drilled in 12.25 to final well TD within either the Pereriv, as for wells A-4 and A-12, or the
NKG, as for wells A-5, A-6 and A-10.
Hole inclinations ranged from 0.5oto 70
owithin the Surakhany, from 12.7
oto 71
owithin the Sabunchi,
from 13oto 76
oin the Balakhany and from 27
oto 85
oin the Pereriv / NKG.
For most of the wells a Saraline Synthetic Based Mud was used. Exceptions were well A-1, A-2, A-3,
A-13 and A-14. Well A-1 original hole and side-track were drilled with a KCl Polymer mud. Wells A-2
and A-3 were both reportedly drilled with a Quadrill system. In the case of wells A-13 and A-14, a
combination fluid was used said to consist of Ultidrill LAO, Novatec LAO and Saraline SBM. For A-
1, drilled with the KCl Polymer, mud weights were initially around 11.9 ppg but had to be raised to
12.8 ppg due to reactive clays. For wells A-2 and A-3, mud weights ranged from 12.7 ppg to 12.9 ppg.
For more recent wells drilled with the a Saraline SBM, mud weight were lower and typically ranged
from 12.0 ppg to 12.6 ppg. Within well A-5 an increase to 12.9 ppg is noted at 2400m depth. Wells A-
13 and A-14 which used a combination fluid were drilled with densities of between 12.1 ppg to 12.4
ppg.
The 12.25 hole was typically the most troublesome section to drill. From conversations with Asset
staff the over-pressured Sabunchi zone is typically associated with washouts and tight hole that
requires back-reaming. The Balakhany is also noted as troublesome with several instances of instability
that is not immediate but appears to have a time dependant element resulting in a large volume of
cavings. Within the initial A-1 well, drilling with too low a mud weight and a mud system which wasnot perhaps inhibitive enough lead to several instability problems. Mud weight had to be increased
accordingly. Within subsequent wells hole conditions appeared to improve with the use of more
inhibitive mud systems and increased mud weights. Hole inclinations within the 12.25 section are
typically greater for more recently drilled wells. Within wells A-2 to A-8 hole drilling conditions were
relatively good with only a few overpulls and tight spots recorded. Within well A-7, the hole did require
several wiper trips to clean up prior to logging but this may possibly be attributed to the fact that the
mud pumps were continually breaking. Within subsequent higher angle wells, however, instability
worsened with several incidences of tight holes and pack offs. Drilling reports note an abundance of
large blocky cavings from base Sabunchi and Balakhany in wells A-9, A-11, A-12, A-13 and A-14.
Within well A-10, hole instability was also noted but appeared to be associated with instability within
the NKG rather than any Formations above. Studying hole inclinations for those wells that reportedhole problems and the abundance of large blocky cavings it is interesting to note that these are typically
all high angle within the Balakhany. Typically inclinations range from 65oto 76o, with the exception of
well A-13 which wad only at 57o through the Balakhany. Given the sudden change in instability for
wells above a certain angle compared with those below, and the evidence of large chunky cavings, it
may be the case that instability is attributed to failure along pre-existing weakness planes than classical
breakout of the intact formation. Regards casing running, losses were reported in certain but typically
ran to TD without any major problems. During cementing, losses were reported for certain wells during
both pumping and displacement. Lead cement densities were typically 14.5 ppg and tail cement
densities typically 15.8 ppg.
-
8/11/2019 Stability Chirag
14/72
S/UTG/105/00 Data Review Summary
August 2000 Page 8
Within well A-1, the section was drilled to the top of the Pereriv but the pipe became stuck on the trip
out. A high percentage of cuttings were reported between 2355m and 1989m. During the wiper trip,
reamed from 1421m in the Surakhany to 2581m in the Balakhany. During the trip out excessive
overpulls were noted and whilst back-reaming to 2750m, the string became stuck. The hole was side-
tracked. The new hole was drilled to 2077m in the Sabunchi and then mud weight needed to beincreased to 12.8 ppg. Whilst running an LCM spotting assembly into the hole no mud returns were
achieved so density was reduced to 12.6 ppg. Wells A-2 and A-3 were drilled relatively trouble free
with reportedly good hole conditions. Well A-3, however, did have evidence of overpull on tripping and
was tight on wiper trips mainly in the sandstones. Well A-4, the first to be drilled with a synthetic based
mud reportedly had no wellbore stability problems. Calliper traces show and essentially in-gauge hole
with an average diameter of ~13. Well A-5, which was reportedly close to a fault had good hole
conditions throughout its section with only minor overpulls on wiper trips. Within well A-6, there was
never a need to stop and circulate the hole clean. Within A-7, the mud pumps broke down frequently
with several wiper trips and back-reaming required to prepare the hole for logging. Within well A-8, the
section drilled fine although tight spots were noted within the Sabunchi during a wiper trip to the shoe.
While attempting to run tools could not get past 2341m the first time and 2394m the second time, bothwithin the Sabunchi. The third attempt was successful.
Within well A-9, occasional tight spots were noted with the presence of cuttings beds forcing tripping
to stop at 2559m, 2900m and 3279m in the Sabunchi and Surakhany. A high percentage of cuttings
and large cavings were reported. Within well A-10, overpull pulling out and drag running in required
the section to be washed and reamed from 3729m to 3787m. Whilst circulating, abundant fines and
cavings from the NKG were recorded. Pulling out of the hole, overpull was noted to be greater than
normal in the Pereriv and Balakhany. Losses were also reported. One metre of fill in the base of the
hole is believed to have been associated with cuttings beds created by the NKG having been severely
washed out. Within well A-11, the section was fine to 3512m. Performing a wiper trip to 3018m
indicated good hole conditions but when building from 3512m to 3612m in the Balakhany, the drill
string became stuck . Many large blocky cavings were noted with the hole packing off. It is noted that
that from +/-2600m the amount increased with the cavings being identified as most probably being
from the Upper Balakhany. Within well A-12, a steady amount of 3 to 4 cm cavings are noted whilst
drilling / sliding through the Balakhany also. Several tight spots were noted in both the Balakhany and
the Pereriv. Whilst back-reaming through the Upper Balakhany and Sabunchi to prevent getting stuck,
a steady increase in cavings was reported, described as blocky chunks. When tripping back into the
bottom, the hole was tight in the Sabunchi and Balakhany V / VI. It was noted that between 2505m and
3680m, hole condition was good with all problems related to the Upper Balakhany section above
2505m. Logs reportedly show bad hole enlargements of up to 20 in the Sabunchi and Upper
Balakhany. Within well A-13, tight spots are again noted in the Balakhany IX, VII and V, being worst
towards the top. Abundant blocky cavings are also noted but no major downhole losses reported.
Within well A-14, after having drilled / slid to 2850m, a moderate amount of cuttings were reportedbetween 2850m and 2450m whilst circulating bottoms up. These occurrences then became heavy above
2450m in the Sabunchi. Ninety percent of the large blocky cavings came from the base of the Sabunchi.
Losses were also reported whilst drilling between 2850m and 4155m at specific depths of 2810m and
3998m in the Balakhany. Returns were lost at 2622m, 2480m, 2452m, 2219m and 2200m all in the
Sabunchi. Further large blocky cavings from the Balakhany and Sabunchi and further losses were
reported as the well was progressed and back-reaming continued.
Regards casing running, within the side-track of well A-1 it had to be washed from 2544m to 2591m
within the Balakhany. Within well A-4 no losses were supposedly reported whilst running but some
were noted when circulating after the liner hanger was landed. Within well A-5, losses were reported
whilst running and circulating with zero returns through the Sabunchi during running. Losses whilst
-
8/11/2019 Stability Chirag
15/72
S/UTG/105/00 Data Review Summary
August 2000 Page 9
running were also reported in well A-6. Within wells A-7 and A-8, negligible fluid loss was reported
and runs were made with negligible resistance. Casing within well A-9 was run with no losses. Within
well A-10, losses were recorded whilst running casing and at 3747m it became stuck as the hole packed
off. Finally the casing was circulated and washed down. Within well A-12 and A-14, losses were
reported whilst running.
Regards casing cementing, losses were reported in well A-4, A-5, A-6, A-10, A-11, A-12, A-14. Whilst
circulating prior to cementing losses were recorded in well A-8.
3.1.4 8.5 Hole Section and 7.0 L iner
Within wells A-4, A-5, A-6, A-10 and A-12 wells were TDd in 12.25 hole with no 8.5 section.
Other wells which did have an 8.5 hole section may be split into (i) those that were drilled through
both the remainder of the Balakhany and the Pereriv / NKG and (ii) those that were solely drilled within
the Pereriv Formation. Wells A-1, A-2, A-7, A-9 and A-14 fall into the former category and wells A-3,
A-8, A-11, A-13 into the latter. Well A-7 was the only case where the 8.5 hole was TDd in the NKG.
Within the Balakhany hole inclinations ranged from 10o to 78
oand in the Pereriv / NKG ranged from
10oto 88
o.
A range of mud types were used to drill the 8.5 hole sections. Quadrill was the most popular choice,
used for wells A-2, A-3, A-8 and A-13 with mud weights ranging from 10.3 ppg to 11.1 ppg. Saraline
SBM was used for wells A-9 and A-11 with mud weight ranges of 10.2 ppg to 10.9 ppg. Within well
A-7 an Oil Based Mud was used with a much higher density of 12.1 ppg to 12.4 ppg. Ultidrill with a
density of 10.7 ppg to 10.8 ppg was used to drill A-14. Within well A-1, an 11.6 ppg KCl Polymer
mud was used.
In general, within 8.5 hole sections, the majority of hole instability indicators were within the
Balakhany Formation. Little instability was observed within the Pereriv other than when the hole was
extended into the underlying NKG Formation. In a few instances, the 7 liner passed tight spots but
was always worked past. No major losses were noted whilst running or cementing the liner. A 15.8 ppg
cement slurry was used.
Within well A-1, no problems were noted. Within well A-2, the logging tool temporarily stood up at
3100m in the Pereriv. Within well A-3 it is noted that the use of Quadrill mud prevented washout of
shale layers within the Pereriv. Within well A-7, hole conditions were noted as excellent although
wireline became stuck because hole inclination was too great. The 7 liner had to be washed to 4200m
at which point the hole packed off several times and could not be cleaned effectively. It was notpossible to rotate the liner at any time and not possible to pass 4581m. The liner was subsequently set
at 4575m. Within well A-8 no problems were reported drilling or tripping but logging tools reportedly
became stuck requiring extra trips. Within well A-9, signs of packing off were noted back-reaming the
last stand. Within well A-11 no problems were reported but within well A-13 the calliper log reportedly
shows large washouts at 4200m, the depth at which logs could not pass. A washed out zone between
4095m and 4100m was noted also.
The worst instability within this section was experienced within well A-14. After having drilled the 8.5
hole to a TD of 4970m, the hole packed off and the pipe became stuck at 4387m in the Balakhany
whilst back-reaming to the shoe. After having worked the pipe and started circulating, a steady stream
of sand and small cuttings were noted at the surface. Back-reaming to the shoe again was better than
the previous attempt and whilst tripping back to bottom the problem are was reamed. Tripping back out
-
8/11/2019 Stability Chirag
16/72
S/UTG/105/00 Data Review Summary
August 2000 Page 10
again several tight spots were noted in the Balakhany but when tripping back into the hole conditions
were much improved. Reportedly the calliper showed several washouts followed by sections of gauge
hole. A decision was made to side-track. Within the side-tracked hole section tight spots in the
Balakhany required back-reaming. The top drive was reportedly stalling with the hole packing off. The
pipe was noted as becoming stuck several times and could not be jarred free. Whilst running the 7liner, several tight spots are noted with it becoming tagged up at 5185m.
3.2 Review of Exploration Well GCA-1
In addition to the fourteen development wells the exploration well GCA-1 was also reviewed as part of
this study. Summary details for each formation are included on the appended spreadsheets with
pertinent information for each hole section detailed below. The well was vertical. All depths referred to
in the text are measured and relative to the rotary table elevation.
3.2.1 36 Hole Section and 30 Conductor
A 12.25 pilot hole was drilled with seawater to 505m to cut through shallow faults where gas could
have been encountered. Unstable conditions and tight pulls were experienced, particularly between
360m and 380m. From the seabed to 310m within Recent Sediments the hole was opened up to 36 and
then a 30 conductor was run.
3.2.2 26 Hole Section and 20 Casing
The remainder of the 12.25 pilot hole was opened up to 26 through the remainder of Recent
Sediments and presumably through the Apsheron Formation and into the Akchagyl (no formation topsavailable for near surface sediments). The 20 surface casing had to be worked through a tight interval
from 360m to 380m. Casing was finally landed and the shoe cemented at 498m.
3.2.3 17.5 Hole Section and 13.375 Casing
The 17.5 hole section was drilled through the remainder of the Akchagyl and TDd within the
Surakhany. A PHPA / KCl mud was used with an initial density of 9.5 ppg. At 655m, the well was
observed to be flowing so mud weight was raised to 11.3 ppg and the flow killed. Density was then
raised again with drilling resuming with a mud weight of 11.6 ppg. A further influx was finally
controlled with a density of 12.0 ppg then severe swabbing and tight hole led to a further increase in
mud weight of 12.3 ppg at the casing depth of 1215m. When the 13.375 casing was run there wasevidence of channelling.
3.2.4 12.25 Hole Section and 9.625 Casing
The 12.25 hole section was drilled through the remainder of the Surakhany, the Sabunchi and TDd in
the Balakhany. A PHPA / KCl mud was used initially with a density of 12.0 ppg but gradually raised
to 12.4 ppg from 1400m to 1500m to overcome swabbing and tight hole conditions. Mud weight was
further raised to penetrating the Balakhany due to increased gas returns in the mud. 9.625 casing was
run and cemented at 2558m.
-
8/11/2019 Stability Chirag
17/72
S/UTG/105/00 Data Review Summary
August 2000 Page 11
3.2.5 8.5 Hole Section and 7.0 L iner
The 8.5 hole section was drilled through the remainder of the Balakhany, the Pereriv and TDd in the
NKG. The section was drilled with a KCl Polymer mud with a density of 11.0 ppg. From 2662m to
2715m the hole was cored and then drilling continued from 2715m to 2769m. Mud weight wassubsequently raised to 11.4 ppg due to increase in connection gas, the well not being static and the hole
reportedly tight on connections. A further 102m were then cored from 2769m but when pulling at
2788m severe weather required hanging off the string. With the bit at 2683m for 11.5 hours the string
became stuck and took 15 hours to free. Drilled continued from 2871m to 2958m and when close to TD
mud weight was increased to 11.8 ppg due to instability. The 7" Liner was run without problem.
3.3 Previous Report Summary
Reviewing previous reports and memos made available by the Asset, the main report relating to
wellbore stability is that written by Exxon in 19981. The main objective of the study was to assess
wellbore stability for the forthcoming A-2 well and for several future development well trajectories.
Offset wells were limited to exploration wells GCA-1, GCA-2 and the first development well A-1.
Within the report uncertainty was noted in horizontal stresses and according to report findings stresses
below 2000m appeared more consistent with compressive tectonic forces. Analyses conducted were
soley based on intact formation failure with no consideration of slippage on pre-existing weakness
planes. Mud weights quoted by Exxon to minimise instability are based on different breakout criterion
to those used by BP so direct comparison of results is made more difficult. Comparing Exxons
predictions for well A-2 with actual mud weights used and observations of hole instability the following
are noted:
Within the 17.5 section of well A-2 Exxon report that the well should be stable if drilled with about
8% KCl and mud weights in the range 11.5 - 12.0 ppg. Actual mud used was KCl / PHPA but %salt is not known. Density was increased to 12.0 ppg at 640m with no major wellbore stability
problems reported.
Within the 12.25 section of well A-2 Exxon report that the well should be stable if drilled with an 8
- 12% KCl mud with a densities in the range 12.0 to 13.0 ppg. Actual mud used was a 12.8 ppg
Quadrill system. No major wellbore stability problems were reported.
The above comparison indicates that Exxon predictions for well A-2 were reasonable. That said,
however, mud range limits quoted by Exxon were considered large. If using mud weights towards the
lower end of the range stability may not have been ensured. Limitations that Exxon point to in their
study are (i) uncertainty in stress regime so extensional assumed, (ii) assume no anisotropy inhorizontal stresses so no distinction between different well azimuths and (iii) strength profiles derived
from surface area data from GCA-1 which may not be representative of other locations.
In addition to the Exxon Report, other studies were also reviewed. These include (i) a review of in-situ
stresses and rock mechanical properties for stimulation design by Chris Dyke of BP2, (ii) notes by
Tetsuro Tochikawa3,4 and Dr Nobuo Morita5, and (iii) a Schlumberger Dowell shale characterisation
report6. In the case of the first two, information of relevance relates to data on in-situ stresses and rock
properties. Drilling data (i.e. LOTs) and analyses results imply higher than may be expected horizontal
stresses. For rock properties, results of rock strength and deformation parameters for GCA-1 sandstone
core tested in the laboratory have been presented.
-
8/11/2019 Stability Chirag
18/72
S/UTG/105/00 Data Review Summary
August 2000 Page 12
Within the Dowell Schlumberger report results of characterisation tests on shale cutttings from well A-
13 were presented and discussed in the context of washouts in the 12.25 hole section. Since using
Synthetic Based Mud, certain sections of 12.25 holes are reportedly enlarged. Characterisation tests
involved determination of moisture content, cation exchange capacity, water activity , X-ray diffraction
analysis and cuttings dispersion tests. Throughout the report hole enlargements are described aswashouts as opposed to breakout with the worst areas associated with the very top and very bottom of
the Sabunchi Formation. Calliper data presented from well A-12 is one arm only so it is unclear what
shape hole enlargements really are. This is important as washouts would certainly imply chemical
instability as opposed to mechanical. After reviewing results of all tests, the report discussion notes that
none of the shale physico- chemical characteristics are directly correlated with the cuttings recovery
data. For this reason, the author concludes that instability is thought to be due to mechanical effects
rather than chemical. In order for this to be investigated further, better knowledge is required on the
shape of hole enlargements since as stated earlier, washouts would be indicative of chemical effects.
-
8/11/2019 Stability Chirag
19/72
S/UTG/105/00 A-15 Stability Assessment and Mud Weight Requirements
August 2000 Page 13
4. A15 Stabi l i ty Assessment and Mud Weight Requi rements
Having reviewed all offset well data and previous reports / memos, a further scope of this study was toprovide mud weight recommendations for minimising instability in the forthcoming A-15 injector well.
4.1 Planned Trajectory and Subsur face Conditions
The well, to be drilled from the Chirag platform, is due to spud at the beginning of August. The
planned trajectory is presented in Figure 1, below, detailing prognosed formation tops and casing
setting depths.
F igure 1:Planned Trajectory for A-15 with Formation Tops and Casing Points
-
8/11/2019 Stability Chirag
20/72
S/UTG/105/00 A-15 Stability Assessment and Mud Weight Requirements
August 2000 Page 14
The top hole 26 section will be drilled through Recent Sediments and mid-way into the Apsheron
Formation with the 20 casing shoe set at a measured depth of 476m (475m TVDbrt). The following
17.5 hole will then be drilled through the remainder of the Apsheron, the Akchagyl and into the
Surakhany with the 13.375 casing shoe set at a measured depth of 1394m (1275m TVDbrt). A 12.25
geologic pilot hole will then be drilled through the remainder of the Surakhany, the Sabunchi, theBalakhany and into the Pereriv crossing a thrust fault and TDd at a measured depth of 4700m (3315m
TVDbrt). This hole will then be plugged back and side-tracked. A second 12.25 hole will then be
drilled from a measured depth of 3650m (2669m TVDbrt) through the lower part of the Balakhany and
TDd at top Pereriv. After running 9.625 casing, an 8.5 hole section will be drilled and TDd within
the Pereriv reservoir at a measured depth of 4750m (3373m).
Well inclinations and formations within each hole section are presented in Table 1 below:
Hole Section (TVDbrt in metres) Formations and Hole Inclinations (TVDbrt in metres)
26 (Mud Line to 475) Recent (Mud Line to 407): Inclination 0 to 7.5
Apsheron (407 to 475): Inclination 7.5 to 1017.5 (475 to 1275) Apsheron (475 to 552): Inclination 10 to 12
Ackhagyl (552 to 732): Inclination 12 to 21
Surakhany (732 to 1275): Inclination 21 to 46
12.25 Pilot Hole (1275 to 3316) Surakhany (1275 to 1642): Inclination 46 to 52
Sabunchi (1642 to 1922): Inclination 52
Balakhany (1922 to 2884): Inclination 52
Pereriv (2884 to 3316): Inclination 52
12.25 Side-track Hole (2669 to 2884)
Note: above 2669m, the 12.25 hole will
remain open
Balakhany (2669 to 2884): Inclination 52 to 50
Note: above 2669m, formations open as detailed for pilot
hole
8.5 Side-track Hole (2884 to 3373) Pereriv (2884 to 3373): Inclination 50
Table 1 :Formations and Hole Inclinations for Each Section
In order to provide mud weight recommendations for minimising hole instability, subsurface conditions
along the A-15 well trajectory require definition. This is discussed within Appendix C where
information on rock properties and in-situ stresses considered for A-15 design are detailed. Within
formations above the Balakhany, an extensional regime is assumed with the vertical stress being greater
than the two horizontal components. Within the Balakhany and Pereriv Formations, however,
uncertainty exists in both the stress regime and actual horizontal magnitudes with the possibility of the
vertical component being the least principal stress. For this reason, the following range of stress
scenarios are considered for design below base Sabunchi:
Stress Scenario 1 : Extensional with horizontal stresses from prognosed fracture gradient
Vertical stress = overburden gradient as presented in Figure C6
Minimum horizontal stress = fracture gradient as presented in Figure C4
Maximum horizontal stress = value mid way between vertical stress and minimum stress value
This stress scenario is as that to be used in overburden formations above the Balakhany
-
8/11/2019 Stability Chirag
21/72
-
8/11/2019 Stability Chirag
22/72
S/UTG/105/00 A-15 Stability Assessment and Mud Weight Requirements
August 2000 Page 16
17.5 Hole Design
Analysis 2 : CASE A with breakout width of 69othrough base Apsheron and Akchagyl Formations
Analysis 3 : CASE B with breakout width of 44o
through top Surakhany
12.25 Pilot Hole Design
Analysis 4 : CASE B with breakout width of 38othrough mid / bottom Surakhany and Sabunchi
Analysis 5 : CASE C (Stress Scenario 1) with breakout width of 38othrough Balakhany and Pereriv
Analysis 6 : CASE C (Stress Scenario 2) with breakout width of 38othrough Balakhany and Pereriv
Analysis 7 : CASE C (Stress Scenario 3) with breakout width of 38othrough Balakhany and Pereriv
12.25 Side-track Hole Design
Results of Analysis 4 to 7 for formations drilled in the pilot hole that will remain open above side-
tracked section
Analysis 8 : CASE C (Stress Scenario 1) with breakout width of 38othrough base Balakhany
Analysis 9 : CASE C (Stress Scenario 2) with breakout width of 38othrough base Balakhany
Analysis 10 : CASE C (Stress Scenario 3) with breakout width of 38othrough base Balakhany
8.5 Side-track Hole Design
Analysis 11 : CASE C (Stress Scenario 1) with breakout width of 40othrough Pereriv
Analysis 12 : CASE C (Stress Scenario 2) with breakout width of 40othrough Pereriv
Analysis 13 : CASE C (Stress Scenario 3) with breakout width of 40othrough Pereriv
Analyses were conducted using the stability software Stress and Failure in Inclined Boreholes (SFIB).
The Well TRaJectory (WTRJ) module was used to provide minimum mud weight requirements along
the specific A-15 well trajectory. Results of analyses 1, 3, 4 and 11 which dictate minimum mud weight
requirements for each section are presented in Figures 2 to 5. The top and bottom diagrams on the far
left of the output file define profiles for in-situ stresses and rock properties, respectively. Within thecentre, profile and plan views of the well trajectory are shown colour coded with minimum mud weights
required to minimise the risk of compressive failure. Within the far right of the output files, the five
columns of data show depth (MD and TVD brt), breakout to be expected using a specific mud weight,
pore pressure, minimum mud weight required to limit breakouts to within tolerable limit set and the
minimum principal stress made equal to the prognosed fracture gradient for A-15. For the condition
where degree of breakout is shown for a specific mud weight, a default value of 1.49 SG (12.4 ppg) is
set for all analyses.
Results presented only provide summary details and not a complete listing of mud weight requirements
for all data points considered. For this reason, the maximum mud weight in the section may be greater
than that shown in Figures 2 to 5.
-
8/11/2019 Stability Chirag
23/72
S/UTG/105/00 A-15 Stability Assessment and Mud Weight Requirements
August 2000 Page 17
F igure 2:WTRJ Analysis 1
F igure 3:WTRJ Analysis 3
-
8/11/2019 Stability Chirag
24/72
S/UTG/105/00 A-15 Stability Assessment and Mud Weight Requirements
August 2000 Page 18
F igure 4:WTRJ Analysis 4
F igure 5:WTRJ Analysis 11
Studying complete listings of results from each analyses, minimum mud weight requirements computed
for each hole section were noted and are follows:
-
8/11/2019 Stability Chirag
25/72
S/UTG/105/00 A-15 Stability Assessment and Mud Weight Requirements
August 2000 Page 19
26 Hole : 1.05 SG (8.7 ppg) at a depth of 407m TVDbrt at the top of the Apsheron Formation
17.5 Hole : 1.45 SG (12.1 ppg) at a depth of 1237m TVDbrt in the Surakhany Formation
12.25 Pilot Hole and Side-track : 1.47 SG (12.3 ppg) at a depth of 1647m TVDbrt in the SabunchiFormation
8.5 Side-track Hole: 1.33 SG (11.1 ppg) for Stress Scenario 1 to 1.35 SG (11.3 ppg) for Stress
Scenario 3 at a depth of between 2897m to 2952m TVDbrt in the Pereriv Formation
Mud weights calculated are based on the Modified Lade Failure Criterion. This was used as it is
considered a more realistic criterion in softer sediments compared with other more conservative criteria
such as Mohr Coulomb. Comparing Modified Lade results with those that would be obtained using
Mohr Coulomb, discrepancies between the two criterion appear to be worst within the 26and side-
track sections of the well. Table 2 below, compares highest mud weight values computed using
Modified Lade with equivalent densities assuming Mohr Coulomb.
Hole Section Depth
(metres TVDbrt)
Maximum Mud Weight for Section (SG / ppg)
Modified Lade Mohr Coulomb
26 407 1.05 / 8.75 1.12 / 9.33
17.5 1237 1.45 / 12.08 1.47 / 12.25
12.25 Pilot and Side-
track
1647 1.47 / 12.25 1.53 / 12.75
8.5 Side-track -
Stress 1
2897 1.33 / 11.08 1.46 / 12.17
8.5 Side-track -
Stress 3
2952 1.35 / 11.25 1.49 / 12.4
Table 2: Comparison of Modified Lade with Mohr Coulomb
Analyses conducted are linear elastic with no accounting for poro-elastic effects over time where
overbalance may reduce as mud pressure and formation fluid pressure equalise at the wellbore wall
when in communication. The analyses also take no consideration of chemical effects which may worsen
stability if mud chemistry is incompatible with the shale formations being drilled. For this reason, mud
weights computed are based on the use of an oil based mud or similar.
When drilling sandstone sequences, a nominal overbalance is typically required to prevent instability.
The belief is that when drilled the sand grains dilate thereby redistributing induced stresses creating a
plastic zone around the wellbore. Since, however, the stability code SFIB assumes brittle failure,stability in sandstone sequences is difficult to model with mud weights calculated often an over-
prediction of what is actually required. For this reason, mud weights quoted are as those required to
minimise instability of shale sequences. Since all hole sections pass through shale formations mud
weights computed are considered applicable for all sections.
-
8/11/2019 Stability Chirag
26/72
S/UTG/105/00 A-15 Stability Assessment and Mud Weight Requirements
August 2000 Page 20
4.3 Fail ur e Along Pre-existing Weakness Planes
For analyses 1 to 13, mud weights are based on failure of the intact rock matrix. Within certain
formations, however, instability may be worsened by failure along pre-existing weakness planes. Such
planes may be either bedding features, fractures or faults. Having been provided ranges in bedding dip /dip direction for the Balakhany and Pereriv, additional analyses were conducted to assess what impact
consideration of anisotropy would make on mud weights required to minimise instability risk. The two
main concerns being (i) unfavourable attack angle between wellbore and bedding features, and (ii)
intersection of the well with a thrust fault within the Pereriv.
When considering instability associated with pre-existing weakness planes, failure may be either due to
(i) slippage or (ii) buckling. The former will occur if the well is drilled at an unfavourable azimuth with
respect to both stress orientation and weakness plane dip / dip direction. The second mode of failure
will pose a risk if the well is drilled almost parallel to the feature such that buckling occurs in the roof
of the borehole. This type of failure is typically associated with highly deviated wells drilled through
near horizontal bedding and referred to as bedding parallel failure. An example of bedding parallelfailure observed within a shale sample tested in a laboratory is presented in Figure 6 below.
F igure 6: Bedding parallel failure of a wellbore demonstrated in a laboratory
experiment with a Jurassic shale sample. Montage of SEM photographs7
For the A-15 trajectory, dip and dip direction for bedding in the Balakhany and Pereriv, provided by the
Asset, are as below. Regards the thrust fault to be crossed within the Pereriv, uncertainty currently
exists in its dip and dip direction at the point of intersection.
-
8/11/2019 Stability Chirag
27/72
S/UTG/105/00 A-15 Stability Assessment and Mud Weight Requirements
August 2000 Page 21
Top Balakhany - dip around horizontal
Top Balakhany IX -dip angle ~ 5oto 045 (approximate to +/- 8o)
Top Balakhany X - dip angle ~ 15oto 045 (approximate to +/- 8o)
Top Pereriv - dip angle ~ 24oto 045 ( +/- 3
o)
Top Pereriv - dip angle ~ 33oto 045 ( +/- 3o)
To assess the likelihood for bedding plane slippage within the shale inter-beds of the Balakhany and
Pereriv, anisotropic analyses were conducted for each of the cases noted above. Analyses of this kind,
however, may only be conducted using the Mohr Coulomb criterion. If A-15 mud weights are to based
on Modified Lade criterion results, anisotropic analyses only serves to provide a qualitative assessment
of bedding plane slippage.
Using the Get FaiLuRe (GFLR) module of SFIB, mud weights required to minimise instability for
tolerable breakout widths were computed for (i) intact failure only and (ii) intact failure incorporating
risk of slippage. If slippage is a risk, the failure zone for a given mud weight will be greater when
considering slippage than intact failure alone. This being the case, mud weights will need to be higherthan that required to prevent failure of the intact formation if the tolerable breakout width is to be
maintained. Using next the Borehole Stress and Failure Orientation (BSFO) module, breakout widths
were computed for mud weights required to minimise intact failure alone and weights required to
minimise both intact failure and slippage. The lower mud weights correspond to those required to
maintain tolerable breakout width based on intact failure only. The higher mud weights are those
required to maintain tolerable breakout width based on both intact rock failure and slippage. Breakout
widths due solely to intact failure are denoted wBO and those corresponding to failure from both intact
shear and slippage are denoted wBO.
Within the Balakhany, the pilot hole section will be drilled at an inclination of 52oand within the side-
track inclination will be slightly lower at 50o. Tolerable breakout within the Balakhany is set at 38
o
based on the highest inclination of 52o. Within the Pereriv a tolerable breakout of 40ois set based on an
inclination of 50oplanned for the 8.5 hole section. Analyses conducted within the Balakhany are based
on the pilot hole trajectory and for the Pereriv are based on the side-track trajectory.
-
8/11/2019 Stability Chirag
28/72
S/UTG/105/00 A-15 Stability Assessment and Mud Weight Requirements
August 2000 Page 22
Formation
(Depth in m
TVDbrt)
Bedding
Dip / Dip
Dirn.
Min. Mud
Weights with
No AnisotropyMC (ML)
SG / ppg
Min. Mud
Weights with
AnisotropyMC
SG / ppg
Breakout for
No Anisotropy
Mud WeightwBO wBO
Breakout for
Anisotropy
Mud WeightwBO wBO
Top
Balakhany
(1922)
1o/ 045
o 1.491 (1.385) /
12.43 (11.54)
1.493 / 12.44 38 46 32 38
Top
Balakhany IX
(2452)
5o/ 045
o 1.403 (1.270) /
11.69 (10.58)
1.411 / 11.76 38 68 15 38
Top
Balakhany X
(2702)
15o/ 045
o 1.428 (1.295) /
11.90 (10.79)
1.440 / 12.00 38 84 0 38
Top Pereriv
(2884)
24o/ 045o 1.325 (1.175) /
11.04 (9.79)
1.334 / 11.12 40 73 12 40
Base Pereriv
(3290)
33o/ 045
o 1.428 (1.290) /
11.90 (10.75)
1.436 / 11.97 40 56 25 40
Note
MC: Mohr Coulomb Criterion, ML : Modified Lade Criterion
No Anisotropy: Density reqd. for intact formation failure only (tolerable wBO of 38oor 40
o)
With Anisotropy: Density reqd. for intact formation failure & slippage (tolerable wBO of 38oor 40
o)
wBO : breakout width for intact failure alone, wBO : breakout width for intact failure & slippage
Table 3:Results of Anisotropic Analyses to Assess Risk of Bedding Plane Slippage
Within Figures 7 and 8 below, BSFO output files for analyses at Top Balakhany X are presented.
Figure 7 shows the result of the analysis which does not consider slippage effects. Here a mud weight
of 1.43 SG (10.79 ppg) gives a tolerable breakout of 38o. Figure 8 shows that when slippage is
considered the same mud weight will result in a much larger failed borehole circumference.
-
8/11/2019 Stability Chirag
29/72
S/UTG/105/00 A-15 Stability Assessment and Mud Weight Requirements
August 2000 Page 23
F igure 7:BSFO Output File for Top Balakhany X - Failure without Anisotropy Considered
F igure 8:BSFO Output File for Top Balakhany X - Failure with Anisotropy Considered
To conduct analyses, an assumption had to be made about the strength of the weakness planes. This is
difficult as no data exists to define such parameters. For results presented above, it was assumed that
an equivalent unconfined compressive strength incorporating the weakness planes would be 1/3rdthat of
the intact unconfined compressive strength value. Taking the friction angles along the bedding planes to
be equal to intact friction values, cohesion for each bedding plane was computed from the equation
below:
Cohesion (MPa) = (UCS*(1-sin)) / (2*cos)
-
8/11/2019 Stability Chirag
30/72
-
8/11/2019 Stability Chirag
31/72
S/UTG/105/00 A-15 Stability Assessment and Mud Weight Requirements
August 2000 Page 25
Considering the risk of bedding parallel failure due to buckling, the only way to minimise risk is to
avoid drilling certain trajectories. In the case of A-15 attack angles between bedding and wellbore
provided by the asset and based on apparent dips are as follows:
37 degrees at top Balakhany32 degrees at top Balakhany IX
22 degrees at top Balakhany X
13 degrees at top Reservoir
4 degrees at base Reservoir
Studies by Okland and Cook7show that wells drilled within 10 degrees of the bedding parallel direction
are at risk of this type of instability. Considering attack angles noted for A-15, bedding parallel failure
is considered a potential threat in the reservoir section. To reduce the risk it is recommended that the
well trajectory is altered to make attack angle between bedding and wellbore more favourable.
4.4 Tensile Fail ur e and Risk of Losses
In addition to minimising the risk of tight hole and stuck pipe by ensuring a high enough mud weight to
prevent compressive failure of the formation, the risk of losses should also be assessed. Two potential
causes of losses are drilling induced fractures and pre-existing fractures and faults. The former will
result from tensile failure of the formation due to drilling with too high a mud weight. In the case of the
latter, partial losses may result if natural fractures / faults are intersected and total losses occur if
fractures / faults are propagated away from the wellbore wall. To be conservative, the fracture gradient
for well A-15 is based on propagation values equivalent to the minimum principal stress. Assuming that
fracture initiation is greater than fracture propagation, fractures will be neither initiated or propagated
if mud weight is maintained below the value of the minimum principal stress. Comparing the highest
static mud weight required to minimise stability in each hole section with the lowest value of minimumstress, typically at the shoe but not always, losses due to induced fractures are not considered to be a
risk but will be dependant on the ECD margin. If ECDs do not exceed the minimum principal stress
new fractures will not be initiated and pre-existing fractures will not be propagated away from the
wellbore. The only exception to this would be in cases where the initiation gradient is less than the
propagation value as is sometimes the case in high angle wells within an extensional regime or for
HPHT wells. For stress scenario 2 within the Balakhany and Pereriv it should be noted that the
minimum stress, still taken to be horizontal, is higher that used in Scenario 1. If such conditions do
exist the corresponding fracture gradient line should be increased by the same amount. In the case of
stress scenario 3, the vertical stress is made equal to the minimum principal value. Taking the fracture
gradient to be equal to the propagation value the upper limit to the drilling window should be made
equal to the vertical principal stress.
Considering that all static mud weights, incorporating ECD margin, should be below the upper bound
to the drilling window the only risk of losses should be along pre-existing faults and fractures. Whether
or not these are partial or total losses will be dependant on (i) the degree of connectivity of the feature
away from the wellbore wall and (ii) the nature of the fracture / fault directly dependant on its stress
history - sealed with the major principal stress perpendicular or open with the minor principal stress
perpendicular. Whilst reviewing previous reports / memos, results of a study conducted by Tetsuro4
were noted. Within this note, occurrence of losses within previous development wells were related to
well azimuth relative to the Chirag structure. All losses reported occurred whilst running the 9 5/8
casing and in terms of depth relate to Top Sabunchi. The database was compiled from development
wells A4 to A12. Corresponding ECD values quoted were derived using the Wellplan program. Results
-
8/11/2019 Stability Chirag
32/72
S/UTG/105/00 A-15 Stability Assessment and Mud Weight Requirements
August 2000 Page 26
of the losses study implied that their occurrence was sensitive to well azimuth (e.g. A9 experienced no
losses with 13.9 ppg ECD, while A4 experienced major losses with a 13.0 ppg ECD). Tetsuros
explanation for observations noted is related to the azimuth of the well with respect to the maximum
horizontal stress. Believing the maximum direction of compression to be perpendicular to the Chirag
Structure Anticline Trend of NW-.SE, a maximum horizontal stress direction of 60ois assumed. Wellssuch as A4 and A5, drilled parallel to the maximum horizontal stress, are likely to be more at risk of
instability than those drilled perpendicular to this direction. Tetsuro derived the following directionality
- loss relationship:
Most stable wells : up-dip and / cross dip wells with min horizontal stress dirn (330 o)
Medium severity wells : down-dip wells with min horizontal stress direction (150o)
Most unstable : wells with max. horiz. stress (60 / 240)
Dip direction refers to the structural dip of the structure with up dip defined as 330o and down-dip
referred to as 150o. This is not the same as smaller scale formation dips which will also have an effect
on overall stability.
Relating results of Tetsuros work with the A-15 azimuth of between approximately 10oto 40o, the risk
of losses into natural fractures / faults is considered to be medium severity. The well direction falls
between the worst and most favourable drilling direction in with respect to the in-situ stress orientation.
Comparing well azimuth with structural dip, well azimuth lies mid way between up dip and cross dip
directions.
In addition to work by Tetsuro, the risk of losses within A-15 has been discussed in a note by Jake
Hossack8. Jake states that with the maximum regional stress direction running perpendicular to the
strike of the main thrust fault (i.e. ~ 60o), faults that strike perpendicular to the strike should be
considered as high risk in terms of mud losses compared with thrust parallel faults.
4.5 Mud Weight Recommendations for A-15
Based on results presented in preceding sections and findings of the offset well review, the following
static mud weights are recommended for minimising instability in well A-15:
26 Hole : 8.6 ppg with contingency to weight up to 8.7 ppg if tight spots encountered
17.5 Hole: 12.1 ppg
12.25 Pilot Hole and Side-track : 12.4 ppg
8.5 Side-track Hole: 11.2 to 11.4 ppg
Within the 26 hole, offset data indicate that previous development wells were drilled with mud weights
of between 8.4 ppg to 8.7 ppg. Results of stability analyses imply a minimum mud weight requirement
of 8.7 ppg driven by subsurface conditions at the top of the Apsheron Formation. Since analyses may
be slightly conservative within the very top hole soft sediments and considering previous drilling
experience, a minimum mud weight of 8.6 ppg is thought the optimum mud weight for drilling this
section.
Within the 17.5 hole, offset data indicate that previous development wells were typically drilled with
mud weights of between 11.9 ppg to 12.1 ppg with some tight spots noted but also occasional dynamic
-
8/11/2019 Stability Chirag
33/72
S/UTG/105/00 A-15 Stability Assessment and Mud Weight Requirements
August 2000 Page 27
losses whilst circulating and during wiper trips. Results of stability analyses imply a minimum mud
weight requirement of 12.1 ppg driven by subsurface conditions at 1237m TVDbrt in the Surakhany
Formation. This weight is considered optimum for drilling this section. Since previous development
wells report occurrences of dynamic losses within the 17.5 hole section careful attention must be given
to minimising ECDs. As early development wells experienced several problems related to chemicalinstability it is important that mud type chosen provides optimum inhibition to minimise the occurrence
of washouts.
Within the 12.25 hole, offset data indicate that early development wells were typically drilled with
mud weights as high as 12.9 ppg using a Quadrill mud system. Within later wells drilled with a
synthetic based mud, densities were lower and ranged from 12.0 ppg to 12.6 ppg. The last two wells,
A-13 and A-14, drilled with a combination fluid had density ranges of between 12.1 ppg and 12.4 ppg.
Within offset wells A-2 to A-8 hole conditions were reportedly good with only a few overpulls and tight
spots recorded. Within more recent wells drilled at higher inclinations instability appeared to worsen
with an abundance of blocky cavings noted from the Sabunchi and Balakhany Formations. The report
by Dowell Schlumberger notes hole enlargements within the Sabunchi Formation for wells drilled withsynthetic muds concluding that instability is most likely to be the result of mechanical failure as
opposed to chemical effects.
Results of stability analyses imply that both 12.25 pilot hole and side-track sections of A-15 should be
drilled with a 12.3 ppg mud weight to minimise instability. This value is driven by the over-pressured
Sabunchi Formation based on intact formation failure and assuming a completely inhibitive mud
system. Considering hole problems in more recent wells resulting in large caving volumes, failure along
pre-existing weakness planes may be an additional mode of failure to explain such instability in wells
drilled at high angle through base Sabunchi / Balakhany. Considering ranges in bedding dip within the
Balakhany, analyses incorporating anisotropic effects imply that failure along weakness planes could
be a potential risk for the A-15 trajectory. To minimise the risk of bedding plane slip mud weights may
need to be increased by a further 0.012 SG (0.1 ppg) within zones most at risk. Given that cavings
within previous wells are reportedly from both the Sabunchi and the Balakhany it may be prudent to
assume that this type of formation failure is feasible within both formations. Considering that the
Sabunchi is described as a calcareous claystone with occasional inter-beds of sandstone and the
Balakhany is described as blocky, failure along pre-existing weakness planes does not seem an
unreasonable explanation. Also, within the Sabunchi, thin sand layers may be even more over-pressured
than assumed. For this reason, increasing mud weight by an additional 0.1 ppg is seen to further reduce
the risk of instability within these zones. For the 12.25 hole sections of A-15 a minimum mud weight
of 12.4 ppg is thought the optimum mud weight for drilling this section. Since earlier development wells
experienced occasional problems related to chemical instability it is important that mud type chosen
provides optimum inhibition within this section.
Within the 8.5 hole, offset data indicate that previous development wells were drilled with quite a wide
range of mud weights of between 10.2 ppg to 12.4 ppg. From stability analyses conducted results imply
that a mud weight between 11.1 ppg and 11.3 ppg should be used to minimise instability resulting from
intact formation failure. The range of values quoted result from the variation in stress magnitudes
considered. Given that the Pereriv may be susceptible to bedding plane slippage, mud weights should be
further increased by 0.1 ppg. Optimum mud weight range for drilling this section is 11.2 to 11.4 ppg.
A further risk of instability within this hole section is a buckling mode of failure in the roof of the
borehole when the well is drilled within 10oof bedding. Instability may also be compounded where the
well crosses the prognosed thrust fault. Without knowing the dip and dip direction of the fault at the
point where it crosses the well path, however, analyses cannot be conducted to provide a qualitative
assessment of instability risk. Although the majority of the Pereriv is sandstone and potentially able to
-
8/11/2019 Stability Chirag
34/72
S/UTG/105/00 A-15 Stability Assessment and Mud Weight Requirements
August 2000 Page 28
be drilled with a nominal overbalance, mud weights recommended are those required to minimise the
risk of instability within shale inter-beds.
Given the risk of slippage along pre-existing weakness planes it is recommended that cavings be
continually monitored at the rig site whilst drilling 12.25 and 8.5 hole sections. This will allow themost likely mode of failure to be identified such that the appropriate remedial action can be taken. If for
example, instability is related to failure along pre-existing weakness planes, raising mud weight once
instability has started will almost inevitably worsen hole conditions as the mud will act to lubricate and
reduce the strength of planes still further. Crack blocking agents in the drilling fluid can retard the
failure by restricting mud invasion. It is important to respond rapidly to sudden changes in cavings rate
whereas a small constant volume of cavings are worth monitoring but may not require immediate
remedial action. Photographs showing examples of typical cavings are presented in Figure 10 and
Table 4 presents key characteristics and suggested remedial actions associated with different caving
types. Differences between cavings delineated along fracture planes and those delineated along bedding
features were presented earlier in section 4.3.
F igure 10:Examples of Typical Cavings (Courtesy of Schlumberger)
-
8/11/2019 Stability Chirag
35/72
S/UTG/105/00 A-15 Stability Assessment and Mud Weight Requirements
August 2000 Page 29
Caving Type Angular Platy / Tabular Splintery
Failure
Mechanism
Shear failure resulting in
multifaceted fragments
Failure along pre-
existing weakness planes
Tensile failure believed
to result from a poro-
elastic response todrilling too fast through
low permeability shale
Key
Characteristics
Facets are newly
created fracture
surfaces
Facets may be
curviplaner
Facets are non parallel
Failure - two regions
of wellbore separated
by 180 degrees
Majority of caving
surfaces represent pre-
existing planes of
weakness
One or more parallel
surfaces are common
Surfaces tend to be
relatively smooth and
planar Failure initiates on
high side of wellbore
when well is nearly
parallel to a weakness
plane
Elongated platy rock
fragments
Typical lithology - low
permeability shale
Caving surfaces show
plume structure
indicative of tensile
failure
Entire circumferenceof wellbore may be
damaged
Remedial
Action
If mud weight close to
pore pressure: raise
mud weight
If mud weight close to
fracture pressure
maintain mudweight
decrease fluid loss
manage hole
cleaning
Maintain mud weight
Minimise fluid loss
coefficient of drilling
mud
Use crack blocking
additives Avoid back reaming
Manage hole cleaning
Avoid excessive rpm
and drillstring
vibrations
Employ gentle drilling
practices
Raise mud weight
Reduce ROP
Table 4:Key Characteristics and Suggested Remedial Actions associated with Different Caving Type
(Courtesy of Schlumberger)
Comparing minimum mud weight recommendations with fracture gradient values induced fractures are
not considered to be a risk but will be dependant on the ECD margin. The main risk of losses for A-15
will be those that may be associated with pre-existing fractures and faults. From results of work
conducted by Tetsuro and notes made by Jake Hossack of BP, risk of losses along the A-15 trajectory
are considered to be of medium severity.
-
8/11/2019 Stability Chirag
36/72
-
8/11/2019 Stability Chirag
37/72
S/UTG/105/00 Proposed Work Scope for Main ERD Study
August 2000 Page 31
6. Additional Wellbore Stabil ity Work to Support Future ERD Dr il li ng
Following on from recommendations reported as part of this study, additional wellbore stability workwill be required to support future ERD drilling operations on Chirag. Given current knowledge of
subsurface conditions across the structure, the following tasks are suggested to increase confidence in
future wellbore stability predictions.
Better definition of the pore pressure regime across the structure - pressure cube should be
constructed using predictions from seismic, calibrated with offset well data
Better definition of stress regimes and principal stress magnitudes. Numerical modelling should be
employed to define total stress ranges. Linking this with improved pore pressure predictions an
effective stress cube may be generated
Improve rock strength predictions based on learnings from other Caspian Sea Fields and current
advancements in populating stress cubes with rock property data derived from seismic.
Incorporate faults into stress cube so as to optimise drilling trajectories by avoiding unfavourable
attack angles. Information on losses into faults within previous development wells will help to
differentiate between critical and non critically stressed faults
Better definition of stress direction. Review all available breakout data. Possibility of performing a
multi-well analysis using breakouts within a range of differently oriented well trajectories. Evidence
of compressional failures and / or induced fracturing will also help to better constrain stress
magnitudes.
Optimise drilling practices in parallel with future wellbore stability work. Often hole problems are
not solely the result of mechanical instability. Poor hole cleaning and general operational practices
are often causes relating to pack offs and stuck pipe.
Future wellbore stability needs identified for the Chirag Asset include a larger generic ERD study and a
more specific study for the forthcoming A-16 well.
-
8/11/2019 Stability Chirag
38/72
S/UTG/105/00 References
August 2000 Page 32
7. References
1. D.E. Nierode; Chirag Wellbore Stability Study, Exxon Production Research Report, January 1998.RA
2. Chris Dyke; Review of In-Situ Stresses and Rock Mechanical Properties for Hydraulic Fracturing /
Frac Packing, Chirag, Azerbaijan, BP Draft Report, October 1997. RA
3. Tetsuro Tochikawa; Sand Control Strategy, Memorandum, April 1999. RA
4. Tetsuro Tochikawa; SBM Losses During 9 5/8 Casing Running and Cementing, File Note. RA
5. Professor Nobuo Morita; Draft Stability Summary Notes - Various, Rock Mechanics and
Production Research Section, Resources and Environmental Engineering, Waseda University. RA
6. Davison and A. Burn; Characterisation of Shale Samples from Well A-13, Chirag Platform,
Azerbaijan, Europe -Cis and Africa Technology Application Centre, July 2000. RA
7. kland and J.M. Cook; Bedding Related Borehole Instability in High Angle Wells, SPE/ ISRM
47285, Volume 1, Eurock Conference Proceedings, 1998. R
8. Jake Hossack of BP, Notes on Faulting within the Overburden and Reservoir. RA
9. Personal Communication: Dowson / Alberty. A
10. Akhmedov; LOT and FIT Study, Azerbaijan Asset Document, 2000. A
11. Horsrund; Estimating Mechanical Properties of Shale from Empirical Correlations, IKU Petroleum
Research. Unsolicited SPE Paper (56017), January 1999. A
12. Marie Scoular; Breakout Study Results. A
Key
RA - Within Main Report and Appendix
R - Within Main Report Only
A - Within Appendix Only
-
8/11/2019 Stability Chirag
39/72
S/UTG/105/00 APPENDIX A: Field Information and Offset Well Review
August 2000 Page 33
APPENDI X A: F ield I nformation and Offset Well Review
The Gunashli-Chirag-Azeri (GCA) field complex is located approximately 5km southeast of theApsheron Penninsula. The complex lies in water depths ranging from 85m to 300m. Hydrocarbons in
the GCA complex are trapped within an elongated, north-west to south-east trending, south-east
plunging anticlinal feature which extends nearly 50 km in length. The main oil producing intervals in
the field are the Balakhany X and the Pereriv intervals of the Pliocene Productive series. Above the
Balakhany Formation in the Sabunchi Formation, a number of sandstone reservoirs contain gas /
condensate primarily on the crest of the structure. Figure A1 below presents a plan of the GCA
structure with all exploration / appraisal well locations.
.
0 5km
502800
442
0800
512800 522800 532800 542800
44
30800
444
0800
44
50800
502800 512800 522800 532800 542800
442
0800
44
30800
444
0800
44
50800
Developed
Gunashli
PSAboundary
Deepwater
Gunashli
Chirag
Far East
Azeri
GCA-1
GCA-4/4z
GCA-5/5z
GCA-2
Prop.
GCA-6/6z
F igure A1:The GCA Structure Showing Exploration /Appraisal Well Locations
The Chirag Field was discovered in 1984 by the drilling and testing of the exploration / appraisal well
GCA-1. To date fourteen development wells, A-1 to A-14, have since been drilled to access reserves
across the field. Well locations, together with the proposed A-15 trajectory, are presented in Figure A2
below.
-
8/11/2019 Stability Chirag
40/72
S/UTG/105/00 APPENDIX A: Field Information and Offset Well Review
August 2000 Page 34
F igure A2:Chirag Development and GCA-1 Well Locations
As part of this study, all fourteen development wells and well GCA-1 were reviewed. For each
formation a spreadsheet was compiled to pull together summary information from all wells. Details
recorded include hole size, well inclination, well azimuth, mud type, mud weight, leak off test data and
general notes detailing incidences of stuck pipe and losses associated with drilling and casing
operations. All spreadsheets are presented on the following pages for Recent Sediments, Apsheron,
Akchagyl, Surakhany, Sabunchi, Balakhany and Pereriv / NKG.
-
8/11/2019 Stability Chirag
41/72
Recent
T
Well Hole Section
Top Depth (MD
brt) Blue :
Casing, Red :
Formation,
Green : KOP
End Depth (MD
brt) Blue : Casing,
Red : Formation,
Green : KOP Incl. Azi.
Mud Type
for Entire
Hole
Section
Mud Weight for
Entire Hole
Section
LOT / FIT for
Formation NOTES FOR ENTIRE HOLE SECTION (Chirag RTE = 36.6m ACSL, Water Depth = 121m)
A1-OH 17.5" Pilot 157.6 416 0 to 1 185 Spud 8.7 Satisfactory drilling26" Opener 20" successfully run & cemented in place with returns (11.5 ppg lead & 15.8 ppg tail)
A1-T1 - - - - - - - -
A2 17.5" Pilot 157.6 409 0 to 5.4
209 to
230 to
90
Sea water
and viscous
pills Sea water
Section drilled to TD of 480m. 20" casing cemented with 11.9 ppg lead & 15.8 ppg tail, full
returns.26" Opener
A3 17.5" Pilot 157.6 415 0 to 3.1
206 to
318
viscous
seawater
and drilled 8.5 to 9.6 ppg
Hole at 605m, total losses while pumping a sweep (9.5 ppg mw). Regained circ. after pulling
BHA into 28" shoe. LCM pills to cure losses. At 364m the bit took weight, washed and reamed
364m to 393m. No returns to TD. Assumed lost zone around 350m +/-20m
Spotted LCM pills tripping from 420m to surface - no returns pumping. Hole opened to 26"
- returns at top of cond. (8.6 - 8.7 ppg). Wiper trip - tight @560m & 460m. Hole displ. to
9.6 ppg - returns lost at ~ 360m. 20" casing to 595m, cmt - no returns
26" Opener
seawater &
viscous
sweeps
A4 17.5" Pilot 157.6 416
0 to 4.8
to 1.92
191 to
232 to
133 to
202
seawater /
PAC 8.5 ppg
Drilled section IN 17.5" TO TD of 482m with good returns reported throughout. Opened up to
26" again with good hole conditions. Prior to pulling out to run casing hole displaced with 8.5
ppg spud mud. WOW and additional trip - good hole conds.
20" casing run to 475.5m with good returns during running and circulating. 11.9 ppg lead
and 15.8 ppg tail - good returns whilst cementing26" Opener
A5 17.5" Pilot 157.6 417
0 to
2.22
174 to
to 187
to 48
seawater /
PAC 8.4 to 8 .7 pp g
Drill to section TD of 485m and open to 26". No losses - drilling / opening. Displace to 8.7 ppg
spud mud prior to final trip out of hole. 20" run to 478m - no losses running / circulating. Cmt
11.9 / 15.8 (lead / tail).
Full to partial returns when pumping cmt slurry, after 473 bbls pumped returns were
completely lost shortly after clear brine 160 ppm observed flowing out of well A3, btwn 28"
& 20". Assumed A3 loss zone had allowed comm. with A5.26" Opener
A6 17.5" Pilot 157.6 417 0 to 5
174 to
103 to
203
seawater /
PAC 8.4 ppg
Well drilled to TD of 479m: good returns reported. Hole opened to 26" - good hole conditions.
Displace to a 8.5 ppg spud mud prior to running casing to TD of 472m: good returns running /
circulating. 11.9 ppg lead & 15.8 ppg tail.
Casing - good returns until 450 bbls lead pumped - lost total returns: started getting trickle
returns of seawater after pumping 900bbls. Returns increased to 5 / 10 % after 1200 bbls
lead pumped. No indication of hydraulic communication btwn. A6 & A326" Opener
A7 12.25" Pilot 157.6 410 0 to 5
188 to
36
seawater
wi th sw eep s 8 .4 pp g
Well drilled to 484m and opened to 26". Hole displaced to 8.7 ppg spud mud. 20" casing run to
274m - worked and washed to 413m, then pulled. Hole cleaned out and deepened to 491m
and again displaced to 8.7 ppg spud mud. 20" ran to 488m - no losses.
11