Stability Chirag

download Stability Chirag

of 72

Transcript of Stability Chirag

  • 8/11/2019 Stability Chirag

    1/72

    Chirag Wellbore Stability

    Study - Part 1,

    Azerbaijan

    S/UTG/105/00

    Sophie Louise Dowson

    UTG Drilling Sunbury

    Upstream Technology Group, Sunbury

    August 2000 GQS50101

  • 8/11/2019 Stability Chirag

    2/72

    UNCLASSIFIED

    The information contained in this document is the property of BP Exploration. Due

    acknowledgement should be made if it is desired to refer to this information in publications or

    discussions with third parties.

  • 8/11/2019 Stability Chirag

    3/72

    UTG Indexing Sheet

    TEAM REPORT NO. JOB NO.

    U T G D R G U T G / 1 0 5 / 0 0 8 7 1 0 5 2 0

    AUTHOR(S) TELEPHONE LOCATION DATE

    Sophie Louise Dowson 01932 764541 200 / G27 August 2000

    MAIN TITLE

    Chirag Wellbore Stability Study - Part 1, Azerbaijan

    CLIENT PRINCIPAL RECIPIENT COMMISSIONED BY

    Chirag Drilling Team Tom Scoular Tom Scoular

    SECURITY CLASSIFICATION UNCLASSIFIED CONFIDENTIAL SECRET

    KEYWORDS

    Chirag, Wellbore Stability

    ACKNOWLEDGEMENT

    RECORD PAGE

    FOR EXTERNAL CLIENT LISTING DISTRIBUTION

    OVERLEAF

    ABSTRACT

    The main objective of this report was to review existing well data for the Chirag Field to assess further wellbore stability

    work requirements for future development drilling. Particular emphasis was given to well A-15 due to spud in August

    2000.

    Within well A-15, the most troublesome sections identified with regard to instability were the 12.25 pilot and side-track

    hole sections. Mud weight recommendations for minimising instability in each hole section are as follows:

    26 hole section : static mud weight of 8.6 ppg to 8.7 ppg

    17.5 hole section : static mud weight of 12.1 ppg. Dynamic losses experienced in previous wells highlights the need

    to maintain a reasonable ECD margin that does not exceed the fracture gradient. Since previous development wells

    have experienced chemical instability it is important that drilling mud inhibition is optimised.

    12.25 pilot hole and side-track sections : static mud weight of 12.4 ppg. As with the 17.5 hole, occurrences of

    chemical instability in previous development wells highlights the importance of optimising drilling mud inhibition.

    8.5 hole section : static mud weight of between 11.2 ppg to 11.4 ppg

    The most problematic formations within the 12.25 pilot hole section appear to be the Sabunchi and Balakhany. Previous

    occurrences of instability may have potentially been attributed to overpressured zones within the Sabunchi and inaddition to intact failure, slippage along pre-existing weakness planes within base Sabunchi / Balakhany. Minimum mud

    weight requirements for the 8.5 hole are those required to minimise instability within the shale interbeds. Since the 8.5

    hole will be terminated in the Pereriv instability concerns relating to the NKG need not be considered.

    Conclusions relating to existing data and analysis needs, for future development drilling, highlight the need for additional

    data acquisition above the Sabunchi. Future wellbore stability work identified includes a larger generic ERD study and a

    more specific study for the forthcoming A-16 well.

    PREPARED BY:

    Sophie L. Dowson

    .....................................................

    APPROVED BY:

    Sophie L. Dowson

    AUTHORISED FOR ISSUE BY:

    Sophie L. Dowson

    ..........................................................

    ISSUE DATE: August 2000

  • 8/11/2019 Stability Chirag

    4/72

    DISTRIBUTION LIST

    NO. OF COPIES NAME LOCATION

    1-2 BDM Library Sunbury (122/105)3 UTG Drilling Team Files Sunbury (200/G27)4 Tim Bailey UTG Sunbury (200/G27)5 Sophie Dowson UTG Sunbury (200/G27)

    6 - 7 Tom Scoular Chirag Asset8 Nigel Last UTG Sunbury (200/G27)

  • 8/11/2019 Stability Chirag

    5/72

    CONTENTS

    Page No

    1. Study Scope 1

    2. Principal Conclusions and Recommendations 2

    3. Data Review Summary 4

    3.1 Review of Chi rag Development Wells 4

    3.1.1 26 Hole Section and 20 Casing 4

    3.1.2 17.5 Hole Section and 13.375 Casing 5

    3.1.3 12.25 Hole Section and 9.625 Casing 7

    3.1.4 8.5 Hole Section and 7.0 L iner 9

    3.2 Review of Exploration Well GCA-1 10

    3.2.1 36 Hole Section and 30 Conductor 10

    3.2.2 26 Hole Section and 20 Casing 10

    3.2.3 17.5 Hole Section and 13.375 Casing 10

    3.2.4 12.25 Hole Section and 9.625 Casing 10

    3.2.5 8.5 Hole Section and 7.0 L iner 11

    3.3 Previous Report Summary 11

    4. A15 Stabil i ty Assessment and Mud Weight Requirements 13

    4.1 Planned Tr ajectory and Subsur face Condi tions 13

    4.2 Compressive Failure Analysis of I ntact Formation 15

    4.3 Fail ur e Along Pre-existing Weakness Planes 20

    4.4 Tensile Fail ure and Risk of Losses 25

    4.5 Mud Weight Recommendations for A-15 26

    5 Data Acquisiti on Requir ements for A15 and Future Well s 30

    6. Additional Well bore Stabil ity Work to Support Future ERD Dr il li ng 31

    7. References 32

  • 8/11/2019 Stability Chirag

    6/72

    APPENDIX A: F ield I nformation and Offset Well Review 33

    APPENDI X B: Review of Previous Studies for Chir ag 42

    B1 Exxon Well bore Stabili ty Report 42B2 BP Review of In-Situ Stresses & Rock Mechanical Properties for Fracturing 47

    B3 Notes by Tetsuro Tochi kawa 48

    B4 Notes by Dr Nobuo Mori ta 48

    B5 Characterisation of Shale Samples fr om Well A-13 49

    APPENDIX C: Defini tion of Subsur face Conditions perti nent to A-15 51

    C1 I ntact Rock Formation Properties 51

    C2 Pre-existing Weakness Planes / Faul ts 56

    C3 Prognosed Pore and Fracture Pressures 57

    C4 Stress Regime and Direction 59

    C5 Principal Stress Magnitudes 60

    C5.1 Vertical Stress 60

    C5.2 Maximum and M in imum Hori zontal Stresses 63

  • 8/11/2019 Stability Chirag

    7/72

    S/UTG/105/00 Study Scope

    August 2000 Page 1

    1. Study Scope

    This report has been compiled as the final deliverable for work requested by Tom Scoular of the ChiragAsset, Azerbaijan Business Unit, in March 2000. The main aim of the study was to review existing well

    data for the Chirag Field to assess further wellbore stability work requirements for future development

    drilling. Particular emphasis was given to well A-15 due to spud in August 2000. Based on the initial

    workscope, study objectives were as follows:

    Review available data and reports pertinent to wellbore instability

    Based on review findings advise whether further wellbore stability analyses required for the Chirag

    ERD well programme

    Identify additional data required for future analyses and better definition of subsurface conditions

    Advise what data, if any, should be obtained from well A-15, due to spud in August 2000

    Conduct a stability analyses for well A-15 and recommend mud weight requirements to minimisehole instability

  • 8/11/2019 Stability Chirag

    8/72

    S/UTG/105/00 Principal Conclusions and Recommendations

    August 2000 Page 2

    2. Pri ncipal Conclusions and Recommendations

    Based on findings from this study conclusions and recommendations may be split into those specific tothe forthcoming A-15 well and data / analysis needs for future development drilling.

    Recommendations for minimising instability within the A-15 well are as follows:

    Within the 26 hole section a static mud weight of 8.6 ppg is recommended to minimise the risk of

    instability. If tight spots are encountered density may be raised to 8.7 ppg.

    Within the 17.5 hole section a static mud weight of 12.1 ppg is recommended to minimise the risk

    of instability. Dynamic losses experienced in previous wells highlights the need to maintain a

    reasonable ECD margin that does not exceed the fracture gradient. Since previous development

    wells have experienced chemical instability it is important that drilling mud inhibition is optimised.

    Within the 12.25 pilot hole and side-track sections a static mud weight of 12.4 ppg is recommended

    to minimise the risk of instability. As with the 17.5 hole, occurrences of chemical instability in

    previous development wells highlights the importance of optimising drilling mud inhibition.

    The most problematic formations within the 12.25 pilot hole section appear to be the Sabunchi and

    Balakhany. Previous occurrences of instability may have potentially been attributed to

    overpressured zones within the Sabunchi and in addition to intact failure, slippage along pre-existing

    weakness planes within base Sabunchi / Balakhany.

    Within the 8.5 hole section a static mud weight of between 11.2 to 11.4 ppg is recommended to

    minimise the risk of instability. Uncertainty in mud weight results from uncertainty in stress regimewithin the Pereriv which may be reverse as opposed to extensional. In addition to shear failure of the

    intact formation, bedding plane slip may be a further risk of instability within the 8.5 hole although

    not considered as severe a risk compared with the Balakhany. Although the majority of the Pereriv

    is sandstone and potentially able to be drilled with a nominal overbalance, mud weights

    recommended are those required to minimise the risk of instability within shale inter-beds.

    A further risk of instability within the 8.5 hole section is a buckling mode of failure in the roof of

    the borehole which may occur if the well is drilled within 10oof bedding. Instability may also be

    compounded where the well crosses the prognosed thrust fault when slippage along pre-existing

    weakness planes may be a further risk. Without knowing the dip and dip direction of the fault at the

    point where it crosses the well path, however, analyses cannot be conducted to provide a qualitativeassessment of instability risk. Since the 8.5 hole will be terminated in the Pereriv instability

    concerns relating to the NKG need not be considered.

    Due to the increased risk of instability within the 12.25 and 8.5 hole sections as evidenced by

    occurrences of large caving volumes in previously drilled development wells, it is recommended that

    cavings morphology be continuously monitored at the rig site. Such procedures will enable the

    correct failure mode to be identified thus allowing the most suitable remedial action to be taken.

    Comparing minimum mud weight recommendations with fracture gradient values induced fractures

    are not considered to be a risk but will be dependant on the ECD margin. The main risk of losses for

    A-15 will be those that may be associated with pre-existing fractures and faults. From results of

  • 8/11/2019 Stability Chirag

    9/72

    S/UTG/105/00 Principal Conclusions and Recommendations

    August 2000 Page 3

    work conducted by Tetsuro and notes made by Jake Hossack of BP, risk of losses along the A-15

    trajectory are considered to be of medium severity.

    Conclusions relating to existing data and analysis needs for future development drilling are as follows:

    Within previous exploration, appraisal and development wells data is limited above the Sabunchi

    for characterisation of overburden properties

    For definition of the overburden gradient and rock properties, density, sonic and gamma ray logs

    should be extended to mud line.

    Current uncertainty exists in the stress regime and magnitudes of the two horizontal stresses.

    Within reservoir formations the vertical stress may no longer be the largest component if the stress

    regime is reverse as opposed to extensional

    To better constrain stress magnitudes more information on the type and degree of hole failure isrequired. Continual monitoring of cavings at the rig site will help to differentiate between failure

    modes. Image log data would then further help to define the degree and extent of failed zones. If

    image logs cannot be run four to six arm oriented callipers should be used instead.

    For definition of the minimum principal stress magnitude leak off tests should be extended in future

    wells to give closure pressure values. Ideally a reopening cycle should also be conducted to define

    the tensile strength of the formation.

    For stress direction, breakout studies conducted to date take no consideration of wellbore

    inclination and azimuth. For this reason, stress direction is currently based on observations of hole

    failure within the vertical exploration well GCA-1.

    ECD values should be closely monitored in future wells to assess actual downhole values

    associated with losses and gains. As wells become longer reach and higher angle there may be a

    need to differentiate between losses and gains associated with wellbore breathing and zones drilled

    underbalance.

    For future development drilling additional stability analyses will be required. Given the complexity

    of the structure, however, additional data is needed to better define subsurface conditions. A stress

    cube approach is suggested to better define the problem.

    Future wellbore stability needs identified for the Chirag Asset include a larger generic ERD study

    and a more specific study for the forthcoming A-16 well.

  • 8/11/2019 Stability Chirag

    10/72

    S/UTG/105/00 Data Review Summary

    August 2000 Page 4

    3. Data Review Summary

    In order to assess the need for further wellbore stability analyses in support of future developmentdrilling options, all pertinent data has been reviewed. A main part of this review included the need to

    ascertain subsurface conditions from drilling experience gained to date. Studying drilling reports for all

    wells on the Chirag Structure, summary charts have been compiled for each formation. Also collated as

    part of the study is information that was contained in previous reports and memos addressing

    geomechanical issues.

    3.1 Review of Chi rag Development Wells

    End of well reports for all fourteen development wells, A-1 to A-14, were used to provide summary

    information for all formations drilled. Resulting spreadsheets are presented in Appendix A with asummary of pertinent information provided below for each hole section. In addition to well reports

    notes were also made from conversations held with Asset staff about drilling experiences to date.

    Information believed to be of relevance is included in the hole section summaries also. All depths

    referred to in the text are measured and relative to the rotary table elevation.

    3.1.1 26 Hole Section and 20 Casing

    The 26 top hole sections of all development wells were drilled through Recent Sediments and for all,

    but well A-3, TDd in the Apsheron Formation. Within well A-3, the section was extended further and

    TDd in the Akchagyl Formation. In wells A-1, A-2, A-3, A-4, A-5 and A-6, a 17.5 pilot hole was

    drilled prior to the section being enlarged with a 26 hole opener. In all other wells the pilot hole drilledwas 12.25 in diameter.

    Hole inclinations within this section are near vertical. In the Recent Sediments, inclinations varied from

    0o to 12o and in the Apsheron inclination ranges were between 1.25o and 13o. Within the Akchagil

    Formation, well A-3 inclination was about 3.5o.

    Drilling mud used was always seawater with viscous sweeps. Densities ranged from 8.4 to 8.7 ppg,

    although the higher weights were typically spud weights that the hole was displaced with after having

    drilled the section.

    Overall, hole conditions in this section were good whilst drilling. Only a few problems were reported in

    terms of losses and very occasional tight spots. For the majority of cases, good returns were obtained

    whilst running casing and cementing. In a few instances, however, losses were reported with the

    majority of cases being associated with pumping the tail slurry. Lead cement densities were typically

    11.9 ppg, although in well A-1 lead density was a lower value of 11.1 ppg. Tail cement densities were

    typically 15.8 ppg.

    Regards drilling, losses occurred in well A-3 whilst pumping a 9.5 ppg sweep with the assumed lost

    zone in the Recent Sediments around 350m +/- 20m. At 364m, the A-3 hole was washed and reamed to

    393m and within the Apsheron Formation the hole was tight at 560m and 460m during a wiper trip.

    Within well A-13 while opening up the Pilot hole, the BHA was unable to get past an obstruction in the

    Recent Sediments at 390m : returns were lost whilst circulating and working the string. Using a new

    assembly, well A-13 was washed and reamed from 390m to 478m. Within well A-14, the hole opener

  • 8/11/2019 Stability Chirag

    11/72

  • 8/11/2019 Stability Chirag

    12/72

    S/UTG/105/00 Data Review Summary

    August 2000 Page 6

    conversations with Asset staff it is noted that wells drilled across the Chirag Structure appeared to be

    more susceptible to losses (e.g. A-4). Mention was also made that in high angle hole sections some

    stuck pipe incidents appear to be associated with sliding towards the base of the 17.5 section. Casing

    running operations were generally good with only occasional losses reported. During cementing, losses

    were reported for certain wells during both pumping and displacement. Within earlier wells (A-1, A-2)lead cement densities were 12.5 ppg but within all other wells this was increased to 13.5 ppg. Tail

    cement densities were the same for all wells, 15.8 ppg.

    Regards drilling, a 9.6 ppg brine flow was noted in well A-1 between the 20 and 13 3/8 annulus

    which took 14 days to stop. It is believed that the flow was emanating from just above the Surakhany

    within the Akchagyl. Within well A-2, pit level fluctuations and an increase in Cl2indicted a further

    possible brine flow. For well A-3, drilling records note dynamic losses of about 20 bbls an hour. A

    further brine flow was also noted in well A-3 within the 20 and 13 3/8 annulus. It is remarked that

    over-pressured salt water formations were not isolated with the most likely cause being loss of

    hydrostatic head as the slurry set up together with the existence of a channel behind the casing. Within

    well A-4, gumbo problems lead to pack off at 922m during a wiper trip. Losses were also noted in theAkchagyl at 737m. Below 1108m, losses were dynamic with gains reported when static. Tight spots

    were also noted in other wells such as A-5 at 800m and A-6, both of which noted high percentages of

    fine cuttings. Within well A-7, a wiper trip to TD resulted in the hole packing off with losses noted

    also. After having pulled out of the hole and ran back in with a new bottom hole assembly it was

    necessary to wash and ream from 788m in the Akchagyl. An inadvertent side-track at 1043m was noted

    so the well had to be re-drilled. Within well A-8, wiper trips were conducted every 300m to improve

    hole conditions resulting from gumbo related problems. Large cuttings volumes were reported after

    trips but cuttings integrity was supposedly good. Within wells A-9, A10, A12, A13 and A14, the use of

    a much more inhibitive Quadrill mud system dramatically improved hole conditions. Within well A-9,

    overpull was much reduced and hole conditions appeared good with no losses. Within well A-10 the

    inhibitive mud system is noted as improving stability and providing good cuttings integrity. A-12 and

    A-14 were also drilled supposedly trouble free but A-13 was noted as having occasional gumbo and

    losses. Within well A-11, the section was supposedly less challenging so a KCl / PHPA system was

    used with addition of Staplex 500. Although better than some of the earlier wells drilled without

    addition of Staplex, gumbo problems were still noted with flowline blockage and tight hole on wiper

    trips.

    Regards casing running, the only occasional losses reported were 15bbls within well A-6.

    Regards casing cementing, losses were reported in certain wells. Within well A-1, losses were noted

    during circulation prior to cementing, during mixing / pumping and displacement. Within well A-3,

    losses were recorded during displacement and within A-5 returns began to diminish towards the end of

    pumping. Within well A-7, good returns were reported whilst mixing / pumping but none duringdisplacement. Within A-8, partial to total losses were taken during displacement of the tail slurry.

    Within well A-14, partial returns were noted after pumping 398 bbls displacement with lost returns

    after 488 bbls. A total of 307 bbls were lost during the cement job.

  • 8/11/2019 Stability Chirag

    13/72

    S/UTG/105/00 Data Review Summary

    August 2000 Page 7

    3.1.3 12.25 Hole Section and 9.625 Casing

    The 12.25 hole sections of all wells were drilled through the remainder of the Surakhany, the Sabunchi

    and then either TDd in the Balakhany, the Pereriv or the NKG. 12.25 sections of wells A-1, A-2, A-

    7, A-9 and A-14 TDd in the Balakhany and wells A-3, A-8, A-11, A-13 which were TDd in thePereriv all had 8.5 hole sections drilled to well TD within the Pereriv. In certain cases, however, wells

    were all drilled in 12.25 to final well TD within either the Pereriv, as for wells A-4 and A-12, or the

    NKG, as for wells A-5, A-6 and A-10.

    Hole inclinations ranged from 0.5oto 70

    owithin the Surakhany, from 12.7

    oto 71

    owithin the Sabunchi,

    from 13oto 76

    oin the Balakhany and from 27

    oto 85

    oin the Pereriv / NKG.

    For most of the wells a Saraline Synthetic Based Mud was used. Exceptions were well A-1, A-2, A-3,

    A-13 and A-14. Well A-1 original hole and side-track were drilled with a KCl Polymer mud. Wells A-2

    and A-3 were both reportedly drilled with a Quadrill system. In the case of wells A-13 and A-14, a

    combination fluid was used said to consist of Ultidrill LAO, Novatec LAO and Saraline SBM. For A-

    1, drilled with the KCl Polymer, mud weights were initially around 11.9 ppg but had to be raised to

    12.8 ppg due to reactive clays. For wells A-2 and A-3, mud weights ranged from 12.7 ppg to 12.9 ppg.

    For more recent wells drilled with the a Saraline SBM, mud weight were lower and typically ranged

    from 12.0 ppg to 12.6 ppg. Within well A-5 an increase to 12.9 ppg is noted at 2400m depth. Wells A-

    13 and A-14 which used a combination fluid were drilled with densities of between 12.1 ppg to 12.4

    ppg.

    The 12.25 hole was typically the most troublesome section to drill. From conversations with Asset

    staff the over-pressured Sabunchi zone is typically associated with washouts and tight hole that

    requires back-reaming. The Balakhany is also noted as troublesome with several instances of instability

    that is not immediate but appears to have a time dependant element resulting in a large volume of

    cavings. Within the initial A-1 well, drilling with too low a mud weight and a mud system which wasnot perhaps inhibitive enough lead to several instability problems. Mud weight had to be increased

    accordingly. Within subsequent wells hole conditions appeared to improve with the use of more

    inhibitive mud systems and increased mud weights. Hole inclinations within the 12.25 section are

    typically greater for more recently drilled wells. Within wells A-2 to A-8 hole drilling conditions were

    relatively good with only a few overpulls and tight spots recorded. Within well A-7, the hole did require

    several wiper trips to clean up prior to logging but this may possibly be attributed to the fact that the

    mud pumps were continually breaking. Within subsequent higher angle wells, however, instability

    worsened with several incidences of tight holes and pack offs. Drilling reports note an abundance of

    large blocky cavings from base Sabunchi and Balakhany in wells A-9, A-11, A-12, A-13 and A-14.

    Within well A-10, hole instability was also noted but appeared to be associated with instability within

    the NKG rather than any Formations above. Studying hole inclinations for those wells that reportedhole problems and the abundance of large blocky cavings it is interesting to note that these are typically

    all high angle within the Balakhany. Typically inclinations range from 65oto 76o, with the exception of

    well A-13 which wad only at 57o through the Balakhany. Given the sudden change in instability for

    wells above a certain angle compared with those below, and the evidence of large chunky cavings, it

    may be the case that instability is attributed to failure along pre-existing weakness planes than classical

    breakout of the intact formation. Regards casing running, losses were reported in certain but typically

    ran to TD without any major problems. During cementing, losses were reported for certain wells during

    both pumping and displacement. Lead cement densities were typically 14.5 ppg and tail cement

    densities typically 15.8 ppg.

  • 8/11/2019 Stability Chirag

    14/72

    S/UTG/105/00 Data Review Summary

    August 2000 Page 8

    Within well A-1, the section was drilled to the top of the Pereriv but the pipe became stuck on the trip

    out. A high percentage of cuttings were reported between 2355m and 1989m. During the wiper trip,

    reamed from 1421m in the Surakhany to 2581m in the Balakhany. During the trip out excessive

    overpulls were noted and whilst back-reaming to 2750m, the string became stuck. The hole was side-

    tracked. The new hole was drilled to 2077m in the Sabunchi and then mud weight needed to beincreased to 12.8 ppg. Whilst running an LCM spotting assembly into the hole no mud returns were

    achieved so density was reduced to 12.6 ppg. Wells A-2 and A-3 were drilled relatively trouble free

    with reportedly good hole conditions. Well A-3, however, did have evidence of overpull on tripping and

    was tight on wiper trips mainly in the sandstones. Well A-4, the first to be drilled with a synthetic based

    mud reportedly had no wellbore stability problems. Calliper traces show and essentially in-gauge hole

    with an average diameter of ~13. Well A-5, which was reportedly close to a fault had good hole

    conditions throughout its section with only minor overpulls on wiper trips. Within well A-6, there was

    never a need to stop and circulate the hole clean. Within A-7, the mud pumps broke down frequently

    with several wiper trips and back-reaming required to prepare the hole for logging. Within well A-8, the

    section drilled fine although tight spots were noted within the Sabunchi during a wiper trip to the shoe.

    While attempting to run tools could not get past 2341m the first time and 2394m the second time, bothwithin the Sabunchi. The third attempt was successful.

    Within well A-9, occasional tight spots were noted with the presence of cuttings beds forcing tripping

    to stop at 2559m, 2900m and 3279m in the Sabunchi and Surakhany. A high percentage of cuttings

    and large cavings were reported. Within well A-10, overpull pulling out and drag running in required

    the section to be washed and reamed from 3729m to 3787m. Whilst circulating, abundant fines and

    cavings from the NKG were recorded. Pulling out of the hole, overpull was noted to be greater than

    normal in the Pereriv and Balakhany. Losses were also reported. One metre of fill in the base of the

    hole is believed to have been associated with cuttings beds created by the NKG having been severely

    washed out. Within well A-11, the section was fine to 3512m. Performing a wiper trip to 3018m

    indicated good hole conditions but when building from 3512m to 3612m in the Balakhany, the drill

    string became stuck . Many large blocky cavings were noted with the hole packing off. It is noted that

    that from +/-2600m the amount increased with the cavings being identified as most probably being

    from the Upper Balakhany. Within well A-12, a steady amount of 3 to 4 cm cavings are noted whilst

    drilling / sliding through the Balakhany also. Several tight spots were noted in both the Balakhany and

    the Pereriv. Whilst back-reaming through the Upper Balakhany and Sabunchi to prevent getting stuck,

    a steady increase in cavings was reported, described as blocky chunks. When tripping back into the

    bottom, the hole was tight in the Sabunchi and Balakhany V / VI. It was noted that between 2505m and

    3680m, hole condition was good with all problems related to the Upper Balakhany section above

    2505m. Logs reportedly show bad hole enlargements of up to 20 in the Sabunchi and Upper

    Balakhany. Within well A-13, tight spots are again noted in the Balakhany IX, VII and V, being worst

    towards the top. Abundant blocky cavings are also noted but no major downhole losses reported.

    Within well A-14, after having drilled / slid to 2850m, a moderate amount of cuttings were reportedbetween 2850m and 2450m whilst circulating bottoms up. These occurrences then became heavy above

    2450m in the Sabunchi. Ninety percent of the large blocky cavings came from the base of the Sabunchi.

    Losses were also reported whilst drilling between 2850m and 4155m at specific depths of 2810m and

    3998m in the Balakhany. Returns were lost at 2622m, 2480m, 2452m, 2219m and 2200m all in the

    Sabunchi. Further large blocky cavings from the Balakhany and Sabunchi and further losses were

    reported as the well was progressed and back-reaming continued.

    Regards casing running, within the side-track of well A-1 it had to be washed from 2544m to 2591m

    within the Balakhany. Within well A-4 no losses were supposedly reported whilst running but some

    were noted when circulating after the liner hanger was landed. Within well A-5, losses were reported

    whilst running and circulating with zero returns through the Sabunchi during running. Losses whilst

  • 8/11/2019 Stability Chirag

    15/72

    S/UTG/105/00 Data Review Summary

    August 2000 Page 9

    running were also reported in well A-6. Within wells A-7 and A-8, negligible fluid loss was reported

    and runs were made with negligible resistance. Casing within well A-9 was run with no losses. Within

    well A-10, losses were recorded whilst running casing and at 3747m it became stuck as the hole packed

    off. Finally the casing was circulated and washed down. Within well A-12 and A-14, losses were

    reported whilst running.

    Regards casing cementing, losses were reported in well A-4, A-5, A-6, A-10, A-11, A-12, A-14. Whilst

    circulating prior to cementing losses were recorded in well A-8.

    3.1.4 8.5 Hole Section and 7.0 L iner

    Within wells A-4, A-5, A-6, A-10 and A-12 wells were TDd in 12.25 hole with no 8.5 section.

    Other wells which did have an 8.5 hole section may be split into (i) those that were drilled through

    both the remainder of the Balakhany and the Pereriv / NKG and (ii) those that were solely drilled within

    the Pereriv Formation. Wells A-1, A-2, A-7, A-9 and A-14 fall into the former category and wells A-3,

    A-8, A-11, A-13 into the latter. Well A-7 was the only case where the 8.5 hole was TDd in the NKG.

    Within the Balakhany hole inclinations ranged from 10o to 78

    oand in the Pereriv / NKG ranged from

    10oto 88

    o.

    A range of mud types were used to drill the 8.5 hole sections. Quadrill was the most popular choice,

    used for wells A-2, A-3, A-8 and A-13 with mud weights ranging from 10.3 ppg to 11.1 ppg. Saraline

    SBM was used for wells A-9 and A-11 with mud weight ranges of 10.2 ppg to 10.9 ppg. Within well

    A-7 an Oil Based Mud was used with a much higher density of 12.1 ppg to 12.4 ppg. Ultidrill with a

    density of 10.7 ppg to 10.8 ppg was used to drill A-14. Within well A-1, an 11.6 ppg KCl Polymer

    mud was used.

    In general, within 8.5 hole sections, the majority of hole instability indicators were within the

    Balakhany Formation. Little instability was observed within the Pereriv other than when the hole was

    extended into the underlying NKG Formation. In a few instances, the 7 liner passed tight spots but

    was always worked past. No major losses were noted whilst running or cementing the liner. A 15.8 ppg

    cement slurry was used.

    Within well A-1, no problems were noted. Within well A-2, the logging tool temporarily stood up at

    3100m in the Pereriv. Within well A-3 it is noted that the use of Quadrill mud prevented washout of

    shale layers within the Pereriv. Within well A-7, hole conditions were noted as excellent although

    wireline became stuck because hole inclination was too great. The 7 liner had to be washed to 4200m

    at which point the hole packed off several times and could not be cleaned effectively. It was notpossible to rotate the liner at any time and not possible to pass 4581m. The liner was subsequently set

    at 4575m. Within well A-8 no problems were reported drilling or tripping but logging tools reportedly

    became stuck requiring extra trips. Within well A-9, signs of packing off were noted back-reaming the

    last stand. Within well A-11 no problems were reported but within well A-13 the calliper log reportedly

    shows large washouts at 4200m, the depth at which logs could not pass. A washed out zone between

    4095m and 4100m was noted also.

    The worst instability within this section was experienced within well A-14. After having drilled the 8.5

    hole to a TD of 4970m, the hole packed off and the pipe became stuck at 4387m in the Balakhany

    whilst back-reaming to the shoe. After having worked the pipe and started circulating, a steady stream

    of sand and small cuttings were noted at the surface. Back-reaming to the shoe again was better than

    the previous attempt and whilst tripping back to bottom the problem are was reamed. Tripping back out

  • 8/11/2019 Stability Chirag

    16/72

    S/UTG/105/00 Data Review Summary

    August 2000 Page 10

    again several tight spots were noted in the Balakhany but when tripping back into the hole conditions

    were much improved. Reportedly the calliper showed several washouts followed by sections of gauge

    hole. A decision was made to side-track. Within the side-tracked hole section tight spots in the

    Balakhany required back-reaming. The top drive was reportedly stalling with the hole packing off. The

    pipe was noted as becoming stuck several times and could not be jarred free. Whilst running the 7liner, several tight spots are noted with it becoming tagged up at 5185m.

    3.2 Review of Exploration Well GCA-1

    In addition to the fourteen development wells the exploration well GCA-1 was also reviewed as part of

    this study. Summary details for each formation are included on the appended spreadsheets with

    pertinent information for each hole section detailed below. The well was vertical. All depths referred to

    in the text are measured and relative to the rotary table elevation.

    3.2.1 36 Hole Section and 30 Conductor

    A 12.25 pilot hole was drilled with seawater to 505m to cut through shallow faults where gas could

    have been encountered. Unstable conditions and tight pulls were experienced, particularly between

    360m and 380m. From the seabed to 310m within Recent Sediments the hole was opened up to 36 and

    then a 30 conductor was run.

    3.2.2 26 Hole Section and 20 Casing

    The remainder of the 12.25 pilot hole was opened up to 26 through the remainder of Recent

    Sediments and presumably through the Apsheron Formation and into the Akchagyl (no formation topsavailable for near surface sediments). The 20 surface casing had to be worked through a tight interval

    from 360m to 380m. Casing was finally landed and the shoe cemented at 498m.

    3.2.3 17.5 Hole Section and 13.375 Casing

    The 17.5 hole section was drilled through the remainder of the Akchagyl and TDd within the

    Surakhany. A PHPA / KCl mud was used with an initial density of 9.5 ppg. At 655m, the well was

    observed to be flowing so mud weight was raised to 11.3 ppg and the flow killed. Density was then

    raised again with drilling resuming with a mud weight of 11.6 ppg. A further influx was finally

    controlled with a density of 12.0 ppg then severe swabbing and tight hole led to a further increase in

    mud weight of 12.3 ppg at the casing depth of 1215m. When the 13.375 casing was run there wasevidence of channelling.

    3.2.4 12.25 Hole Section and 9.625 Casing

    The 12.25 hole section was drilled through the remainder of the Surakhany, the Sabunchi and TDd in

    the Balakhany. A PHPA / KCl mud was used initially with a density of 12.0 ppg but gradually raised

    to 12.4 ppg from 1400m to 1500m to overcome swabbing and tight hole conditions. Mud weight was

    further raised to penetrating the Balakhany due to increased gas returns in the mud. 9.625 casing was

    run and cemented at 2558m.

  • 8/11/2019 Stability Chirag

    17/72

    S/UTG/105/00 Data Review Summary

    August 2000 Page 11

    3.2.5 8.5 Hole Section and 7.0 L iner

    The 8.5 hole section was drilled through the remainder of the Balakhany, the Pereriv and TDd in the

    NKG. The section was drilled with a KCl Polymer mud with a density of 11.0 ppg. From 2662m to

    2715m the hole was cored and then drilling continued from 2715m to 2769m. Mud weight wassubsequently raised to 11.4 ppg due to increase in connection gas, the well not being static and the hole

    reportedly tight on connections. A further 102m were then cored from 2769m but when pulling at

    2788m severe weather required hanging off the string. With the bit at 2683m for 11.5 hours the string

    became stuck and took 15 hours to free. Drilled continued from 2871m to 2958m and when close to TD

    mud weight was increased to 11.8 ppg due to instability. The 7" Liner was run without problem.

    3.3 Previous Report Summary

    Reviewing previous reports and memos made available by the Asset, the main report relating to

    wellbore stability is that written by Exxon in 19981. The main objective of the study was to assess

    wellbore stability for the forthcoming A-2 well and for several future development well trajectories.

    Offset wells were limited to exploration wells GCA-1, GCA-2 and the first development well A-1.

    Within the report uncertainty was noted in horizontal stresses and according to report findings stresses

    below 2000m appeared more consistent with compressive tectonic forces. Analyses conducted were

    soley based on intact formation failure with no consideration of slippage on pre-existing weakness

    planes. Mud weights quoted by Exxon to minimise instability are based on different breakout criterion

    to those used by BP so direct comparison of results is made more difficult. Comparing Exxons

    predictions for well A-2 with actual mud weights used and observations of hole instability the following

    are noted:

    Within the 17.5 section of well A-2 Exxon report that the well should be stable if drilled with about

    8% KCl and mud weights in the range 11.5 - 12.0 ppg. Actual mud used was KCl / PHPA but %salt is not known. Density was increased to 12.0 ppg at 640m with no major wellbore stability

    problems reported.

    Within the 12.25 section of well A-2 Exxon report that the well should be stable if drilled with an 8

    - 12% KCl mud with a densities in the range 12.0 to 13.0 ppg. Actual mud used was a 12.8 ppg

    Quadrill system. No major wellbore stability problems were reported.

    The above comparison indicates that Exxon predictions for well A-2 were reasonable. That said,

    however, mud range limits quoted by Exxon were considered large. If using mud weights towards the

    lower end of the range stability may not have been ensured. Limitations that Exxon point to in their

    study are (i) uncertainty in stress regime so extensional assumed, (ii) assume no anisotropy inhorizontal stresses so no distinction between different well azimuths and (iii) strength profiles derived

    from surface area data from GCA-1 which may not be representative of other locations.

    In addition to the Exxon Report, other studies were also reviewed. These include (i) a review of in-situ

    stresses and rock mechanical properties for stimulation design by Chris Dyke of BP2, (ii) notes by

    Tetsuro Tochikawa3,4 and Dr Nobuo Morita5, and (iii) a Schlumberger Dowell shale characterisation

    report6. In the case of the first two, information of relevance relates to data on in-situ stresses and rock

    properties. Drilling data (i.e. LOTs) and analyses results imply higher than may be expected horizontal

    stresses. For rock properties, results of rock strength and deformation parameters for GCA-1 sandstone

    core tested in the laboratory have been presented.

  • 8/11/2019 Stability Chirag

    18/72

    S/UTG/105/00 Data Review Summary

    August 2000 Page 12

    Within the Dowell Schlumberger report results of characterisation tests on shale cutttings from well A-

    13 were presented and discussed in the context of washouts in the 12.25 hole section. Since using

    Synthetic Based Mud, certain sections of 12.25 holes are reportedly enlarged. Characterisation tests

    involved determination of moisture content, cation exchange capacity, water activity , X-ray diffraction

    analysis and cuttings dispersion tests. Throughout the report hole enlargements are described aswashouts as opposed to breakout with the worst areas associated with the very top and very bottom of

    the Sabunchi Formation. Calliper data presented from well A-12 is one arm only so it is unclear what

    shape hole enlargements really are. This is important as washouts would certainly imply chemical

    instability as opposed to mechanical. After reviewing results of all tests, the report discussion notes that

    none of the shale physico- chemical characteristics are directly correlated with the cuttings recovery

    data. For this reason, the author concludes that instability is thought to be due to mechanical effects

    rather than chemical. In order for this to be investigated further, better knowledge is required on the

    shape of hole enlargements since as stated earlier, washouts would be indicative of chemical effects.

  • 8/11/2019 Stability Chirag

    19/72

    S/UTG/105/00 A-15 Stability Assessment and Mud Weight Requirements

    August 2000 Page 13

    4. A15 Stabi l i ty Assessment and Mud Weight Requi rements

    Having reviewed all offset well data and previous reports / memos, a further scope of this study was toprovide mud weight recommendations for minimising instability in the forthcoming A-15 injector well.

    4.1 Planned Trajectory and Subsur face Conditions

    The well, to be drilled from the Chirag platform, is due to spud at the beginning of August. The

    planned trajectory is presented in Figure 1, below, detailing prognosed formation tops and casing

    setting depths.

    F igure 1:Planned Trajectory for A-15 with Formation Tops and Casing Points

  • 8/11/2019 Stability Chirag

    20/72

    S/UTG/105/00 A-15 Stability Assessment and Mud Weight Requirements

    August 2000 Page 14

    The top hole 26 section will be drilled through Recent Sediments and mid-way into the Apsheron

    Formation with the 20 casing shoe set at a measured depth of 476m (475m TVDbrt). The following

    17.5 hole will then be drilled through the remainder of the Apsheron, the Akchagyl and into the

    Surakhany with the 13.375 casing shoe set at a measured depth of 1394m (1275m TVDbrt). A 12.25

    geologic pilot hole will then be drilled through the remainder of the Surakhany, the Sabunchi, theBalakhany and into the Pereriv crossing a thrust fault and TDd at a measured depth of 4700m (3315m

    TVDbrt). This hole will then be plugged back and side-tracked. A second 12.25 hole will then be

    drilled from a measured depth of 3650m (2669m TVDbrt) through the lower part of the Balakhany and

    TDd at top Pereriv. After running 9.625 casing, an 8.5 hole section will be drilled and TDd within

    the Pereriv reservoir at a measured depth of 4750m (3373m).

    Well inclinations and formations within each hole section are presented in Table 1 below:

    Hole Section (TVDbrt in metres) Formations and Hole Inclinations (TVDbrt in metres)

    26 (Mud Line to 475) Recent (Mud Line to 407): Inclination 0 to 7.5

    Apsheron (407 to 475): Inclination 7.5 to 1017.5 (475 to 1275) Apsheron (475 to 552): Inclination 10 to 12

    Ackhagyl (552 to 732): Inclination 12 to 21

    Surakhany (732 to 1275): Inclination 21 to 46

    12.25 Pilot Hole (1275 to 3316) Surakhany (1275 to 1642): Inclination 46 to 52

    Sabunchi (1642 to 1922): Inclination 52

    Balakhany (1922 to 2884): Inclination 52

    Pereriv (2884 to 3316): Inclination 52

    12.25 Side-track Hole (2669 to 2884)

    Note: above 2669m, the 12.25 hole will

    remain open

    Balakhany (2669 to 2884): Inclination 52 to 50

    Note: above 2669m, formations open as detailed for pilot

    hole

    8.5 Side-track Hole (2884 to 3373) Pereriv (2884 to 3373): Inclination 50

    Table 1 :Formations and Hole Inclinations for Each Section

    In order to provide mud weight recommendations for minimising hole instability, subsurface conditions

    along the A-15 well trajectory require definition. This is discussed within Appendix C where

    information on rock properties and in-situ stresses considered for A-15 design are detailed. Within

    formations above the Balakhany, an extensional regime is assumed with the vertical stress being greater

    than the two horizontal components. Within the Balakhany and Pereriv Formations, however,

    uncertainty exists in both the stress regime and actual horizontal magnitudes with the possibility of the

    vertical component being the least principal stress. For this reason, the following range of stress

    scenarios are considered for design below base Sabunchi:

    Stress Scenario 1 : Extensional with horizontal stresses from prognosed fracture gradient

    Vertical stress = overburden gradient as presented in Figure C6

    Minimum horizontal stress = fracture gradient as presented in Figure C4

    Maximum horizontal stress = value mid way between vertical stress and minimum stress value

    This stress scenario is as that to be used in overburden formations above the Balakhany

  • 8/11/2019 Stability Chirag

    21/72

  • 8/11/2019 Stability Chirag

    22/72

    S/UTG/105/00 A-15 Stability Assessment and Mud Weight Requirements

    August 2000 Page 16

    17.5 Hole Design

    Analysis 2 : CASE A with breakout width of 69othrough base Apsheron and Akchagyl Formations

    Analysis 3 : CASE B with breakout width of 44o

    through top Surakhany

    12.25 Pilot Hole Design

    Analysis 4 : CASE B with breakout width of 38othrough mid / bottom Surakhany and Sabunchi

    Analysis 5 : CASE C (Stress Scenario 1) with breakout width of 38othrough Balakhany and Pereriv

    Analysis 6 : CASE C (Stress Scenario 2) with breakout width of 38othrough Balakhany and Pereriv

    Analysis 7 : CASE C (Stress Scenario 3) with breakout width of 38othrough Balakhany and Pereriv

    12.25 Side-track Hole Design

    Results of Analysis 4 to 7 for formations drilled in the pilot hole that will remain open above side-

    tracked section

    Analysis 8 : CASE C (Stress Scenario 1) with breakout width of 38othrough base Balakhany

    Analysis 9 : CASE C (Stress Scenario 2) with breakout width of 38othrough base Balakhany

    Analysis 10 : CASE C (Stress Scenario 3) with breakout width of 38othrough base Balakhany

    8.5 Side-track Hole Design

    Analysis 11 : CASE C (Stress Scenario 1) with breakout width of 40othrough Pereriv

    Analysis 12 : CASE C (Stress Scenario 2) with breakout width of 40othrough Pereriv

    Analysis 13 : CASE C (Stress Scenario 3) with breakout width of 40othrough Pereriv

    Analyses were conducted using the stability software Stress and Failure in Inclined Boreholes (SFIB).

    The Well TRaJectory (WTRJ) module was used to provide minimum mud weight requirements along

    the specific A-15 well trajectory. Results of analyses 1, 3, 4 and 11 which dictate minimum mud weight

    requirements for each section are presented in Figures 2 to 5. The top and bottom diagrams on the far

    left of the output file define profiles for in-situ stresses and rock properties, respectively. Within thecentre, profile and plan views of the well trajectory are shown colour coded with minimum mud weights

    required to minimise the risk of compressive failure. Within the far right of the output files, the five

    columns of data show depth (MD and TVD brt), breakout to be expected using a specific mud weight,

    pore pressure, minimum mud weight required to limit breakouts to within tolerable limit set and the

    minimum principal stress made equal to the prognosed fracture gradient for A-15. For the condition

    where degree of breakout is shown for a specific mud weight, a default value of 1.49 SG (12.4 ppg) is

    set for all analyses.

    Results presented only provide summary details and not a complete listing of mud weight requirements

    for all data points considered. For this reason, the maximum mud weight in the section may be greater

    than that shown in Figures 2 to 5.

  • 8/11/2019 Stability Chirag

    23/72

    S/UTG/105/00 A-15 Stability Assessment and Mud Weight Requirements

    August 2000 Page 17

    F igure 2:WTRJ Analysis 1

    F igure 3:WTRJ Analysis 3

  • 8/11/2019 Stability Chirag

    24/72

    S/UTG/105/00 A-15 Stability Assessment and Mud Weight Requirements

    August 2000 Page 18

    F igure 4:WTRJ Analysis 4

    F igure 5:WTRJ Analysis 11

    Studying complete listings of results from each analyses, minimum mud weight requirements computed

    for each hole section were noted and are follows:

  • 8/11/2019 Stability Chirag

    25/72

    S/UTG/105/00 A-15 Stability Assessment and Mud Weight Requirements

    August 2000 Page 19

    26 Hole : 1.05 SG (8.7 ppg) at a depth of 407m TVDbrt at the top of the Apsheron Formation

    17.5 Hole : 1.45 SG (12.1 ppg) at a depth of 1237m TVDbrt in the Surakhany Formation

    12.25 Pilot Hole and Side-track : 1.47 SG (12.3 ppg) at a depth of 1647m TVDbrt in the SabunchiFormation

    8.5 Side-track Hole: 1.33 SG (11.1 ppg) for Stress Scenario 1 to 1.35 SG (11.3 ppg) for Stress

    Scenario 3 at a depth of between 2897m to 2952m TVDbrt in the Pereriv Formation

    Mud weights calculated are based on the Modified Lade Failure Criterion. This was used as it is

    considered a more realistic criterion in softer sediments compared with other more conservative criteria

    such as Mohr Coulomb. Comparing Modified Lade results with those that would be obtained using

    Mohr Coulomb, discrepancies between the two criterion appear to be worst within the 26and side-

    track sections of the well. Table 2 below, compares highest mud weight values computed using

    Modified Lade with equivalent densities assuming Mohr Coulomb.

    Hole Section Depth

    (metres TVDbrt)

    Maximum Mud Weight for Section (SG / ppg)

    Modified Lade Mohr Coulomb

    26 407 1.05 / 8.75 1.12 / 9.33

    17.5 1237 1.45 / 12.08 1.47 / 12.25

    12.25 Pilot and Side-

    track

    1647 1.47 / 12.25 1.53 / 12.75

    8.5 Side-track -

    Stress 1

    2897 1.33 / 11.08 1.46 / 12.17

    8.5 Side-track -

    Stress 3

    2952 1.35 / 11.25 1.49 / 12.4

    Table 2: Comparison of Modified Lade with Mohr Coulomb

    Analyses conducted are linear elastic with no accounting for poro-elastic effects over time where

    overbalance may reduce as mud pressure and formation fluid pressure equalise at the wellbore wall

    when in communication. The analyses also take no consideration of chemical effects which may worsen

    stability if mud chemistry is incompatible with the shale formations being drilled. For this reason, mud

    weights computed are based on the use of an oil based mud or similar.

    When drilling sandstone sequences, a nominal overbalance is typically required to prevent instability.

    The belief is that when drilled the sand grains dilate thereby redistributing induced stresses creating a

    plastic zone around the wellbore. Since, however, the stability code SFIB assumes brittle failure,stability in sandstone sequences is difficult to model with mud weights calculated often an over-

    prediction of what is actually required. For this reason, mud weights quoted are as those required to

    minimise instability of shale sequences. Since all hole sections pass through shale formations mud

    weights computed are considered applicable for all sections.

  • 8/11/2019 Stability Chirag

    26/72

    S/UTG/105/00 A-15 Stability Assessment and Mud Weight Requirements

    August 2000 Page 20

    4.3 Fail ur e Along Pre-existing Weakness Planes

    For analyses 1 to 13, mud weights are based on failure of the intact rock matrix. Within certain

    formations, however, instability may be worsened by failure along pre-existing weakness planes. Such

    planes may be either bedding features, fractures or faults. Having been provided ranges in bedding dip /dip direction for the Balakhany and Pereriv, additional analyses were conducted to assess what impact

    consideration of anisotropy would make on mud weights required to minimise instability risk. The two

    main concerns being (i) unfavourable attack angle between wellbore and bedding features, and (ii)

    intersection of the well with a thrust fault within the Pereriv.

    When considering instability associated with pre-existing weakness planes, failure may be either due to

    (i) slippage or (ii) buckling. The former will occur if the well is drilled at an unfavourable azimuth with

    respect to both stress orientation and weakness plane dip / dip direction. The second mode of failure

    will pose a risk if the well is drilled almost parallel to the feature such that buckling occurs in the roof

    of the borehole. This type of failure is typically associated with highly deviated wells drilled through

    near horizontal bedding and referred to as bedding parallel failure. An example of bedding parallelfailure observed within a shale sample tested in a laboratory is presented in Figure 6 below.

    F igure 6: Bedding parallel failure of a wellbore demonstrated in a laboratory

    experiment with a Jurassic shale sample. Montage of SEM photographs7

    For the A-15 trajectory, dip and dip direction for bedding in the Balakhany and Pereriv, provided by the

    Asset, are as below. Regards the thrust fault to be crossed within the Pereriv, uncertainty currently

    exists in its dip and dip direction at the point of intersection.

  • 8/11/2019 Stability Chirag

    27/72

    S/UTG/105/00 A-15 Stability Assessment and Mud Weight Requirements

    August 2000 Page 21

    Top Balakhany - dip around horizontal

    Top Balakhany IX -dip angle ~ 5oto 045 (approximate to +/- 8o)

    Top Balakhany X - dip angle ~ 15oto 045 (approximate to +/- 8o)

    Top Pereriv - dip angle ~ 24oto 045 ( +/- 3

    o)

    Top Pereriv - dip angle ~ 33oto 045 ( +/- 3o)

    To assess the likelihood for bedding plane slippage within the shale inter-beds of the Balakhany and

    Pereriv, anisotropic analyses were conducted for each of the cases noted above. Analyses of this kind,

    however, may only be conducted using the Mohr Coulomb criterion. If A-15 mud weights are to based

    on Modified Lade criterion results, anisotropic analyses only serves to provide a qualitative assessment

    of bedding plane slippage.

    Using the Get FaiLuRe (GFLR) module of SFIB, mud weights required to minimise instability for

    tolerable breakout widths were computed for (i) intact failure only and (ii) intact failure incorporating

    risk of slippage. If slippage is a risk, the failure zone for a given mud weight will be greater when

    considering slippage than intact failure alone. This being the case, mud weights will need to be higherthan that required to prevent failure of the intact formation if the tolerable breakout width is to be

    maintained. Using next the Borehole Stress and Failure Orientation (BSFO) module, breakout widths

    were computed for mud weights required to minimise intact failure alone and weights required to

    minimise both intact failure and slippage. The lower mud weights correspond to those required to

    maintain tolerable breakout width based on intact failure only. The higher mud weights are those

    required to maintain tolerable breakout width based on both intact rock failure and slippage. Breakout

    widths due solely to intact failure are denoted wBO and those corresponding to failure from both intact

    shear and slippage are denoted wBO.

    Within the Balakhany, the pilot hole section will be drilled at an inclination of 52oand within the side-

    track inclination will be slightly lower at 50o. Tolerable breakout within the Balakhany is set at 38

    o

    based on the highest inclination of 52o. Within the Pereriv a tolerable breakout of 40ois set based on an

    inclination of 50oplanned for the 8.5 hole section. Analyses conducted within the Balakhany are based

    on the pilot hole trajectory and for the Pereriv are based on the side-track trajectory.

  • 8/11/2019 Stability Chirag

    28/72

    S/UTG/105/00 A-15 Stability Assessment and Mud Weight Requirements

    August 2000 Page 22

    Formation

    (Depth in m

    TVDbrt)

    Bedding

    Dip / Dip

    Dirn.

    Min. Mud

    Weights with

    No AnisotropyMC (ML)

    SG / ppg

    Min. Mud

    Weights with

    AnisotropyMC

    SG / ppg

    Breakout for

    No Anisotropy

    Mud WeightwBO wBO

    Breakout for

    Anisotropy

    Mud WeightwBO wBO

    Top

    Balakhany

    (1922)

    1o/ 045

    o 1.491 (1.385) /

    12.43 (11.54)

    1.493 / 12.44 38 46 32 38

    Top

    Balakhany IX

    (2452)

    5o/ 045

    o 1.403 (1.270) /

    11.69 (10.58)

    1.411 / 11.76 38 68 15 38

    Top

    Balakhany X

    (2702)

    15o/ 045

    o 1.428 (1.295) /

    11.90 (10.79)

    1.440 / 12.00 38 84 0 38

    Top Pereriv

    (2884)

    24o/ 045o 1.325 (1.175) /

    11.04 (9.79)

    1.334 / 11.12 40 73 12 40

    Base Pereriv

    (3290)

    33o/ 045

    o 1.428 (1.290) /

    11.90 (10.75)

    1.436 / 11.97 40 56 25 40

    Note

    MC: Mohr Coulomb Criterion, ML : Modified Lade Criterion

    No Anisotropy: Density reqd. for intact formation failure only (tolerable wBO of 38oor 40

    o)

    With Anisotropy: Density reqd. for intact formation failure & slippage (tolerable wBO of 38oor 40

    o)

    wBO : breakout width for intact failure alone, wBO : breakout width for intact failure & slippage

    Table 3:Results of Anisotropic Analyses to Assess Risk of Bedding Plane Slippage

    Within Figures 7 and 8 below, BSFO output files for analyses at Top Balakhany X are presented.

    Figure 7 shows the result of the analysis which does not consider slippage effects. Here a mud weight

    of 1.43 SG (10.79 ppg) gives a tolerable breakout of 38o. Figure 8 shows that when slippage is

    considered the same mud weight will result in a much larger failed borehole circumference.

  • 8/11/2019 Stability Chirag

    29/72

    S/UTG/105/00 A-15 Stability Assessment and Mud Weight Requirements

    August 2000 Page 23

    F igure 7:BSFO Output File for Top Balakhany X - Failure without Anisotropy Considered

    F igure 8:BSFO Output File for Top Balakhany X - Failure with Anisotropy Considered

    To conduct analyses, an assumption had to be made about the strength of the weakness planes. This is

    difficult as no data exists to define such parameters. For results presented above, it was assumed that

    an equivalent unconfined compressive strength incorporating the weakness planes would be 1/3rdthat of

    the intact unconfined compressive strength value. Taking the friction angles along the bedding planes to

    be equal to intact friction values, cohesion for each bedding plane was computed from the equation

    below:

    Cohesion (MPa) = (UCS*(1-sin)) / (2*cos)

  • 8/11/2019 Stability Chirag

    30/72

  • 8/11/2019 Stability Chirag

    31/72

    S/UTG/105/00 A-15 Stability Assessment and Mud Weight Requirements

    August 2000 Page 25

    Considering the risk of bedding parallel failure due to buckling, the only way to minimise risk is to

    avoid drilling certain trajectories. In the case of A-15 attack angles between bedding and wellbore

    provided by the asset and based on apparent dips are as follows:

    37 degrees at top Balakhany32 degrees at top Balakhany IX

    22 degrees at top Balakhany X

    13 degrees at top Reservoir

    4 degrees at base Reservoir

    Studies by Okland and Cook7show that wells drilled within 10 degrees of the bedding parallel direction

    are at risk of this type of instability. Considering attack angles noted for A-15, bedding parallel failure

    is considered a potential threat in the reservoir section. To reduce the risk it is recommended that the

    well trajectory is altered to make attack angle between bedding and wellbore more favourable.

    4.4 Tensile Fail ur e and Risk of Losses

    In addition to minimising the risk of tight hole and stuck pipe by ensuring a high enough mud weight to

    prevent compressive failure of the formation, the risk of losses should also be assessed. Two potential

    causes of losses are drilling induced fractures and pre-existing fractures and faults. The former will

    result from tensile failure of the formation due to drilling with too high a mud weight. In the case of the

    latter, partial losses may result if natural fractures / faults are intersected and total losses occur if

    fractures / faults are propagated away from the wellbore wall. To be conservative, the fracture gradient

    for well A-15 is based on propagation values equivalent to the minimum principal stress. Assuming that

    fracture initiation is greater than fracture propagation, fractures will be neither initiated or propagated

    if mud weight is maintained below the value of the minimum principal stress. Comparing the highest

    static mud weight required to minimise stability in each hole section with the lowest value of minimumstress, typically at the shoe but not always, losses due to induced fractures are not considered to be a

    risk but will be dependant on the ECD margin. If ECDs do not exceed the minimum principal stress

    new fractures will not be initiated and pre-existing fractures will not be propagated away from the

    wellbore. The only exception to this would be in cases where the initiation gradient is less than the

    propagation value as is sometimes the case in high angle wells within an extensional regime or for

    HPHT wells. For stress scenario 2 within the Balakhany and Pereriv it should be noted that the

    minimum stress, still taken to be horizontal, is higher that used in Scenario 1. If such conditions do

    exist the corresponding fracture gradient line should be increased by the same amount. In the case of

    stress scenario 3, the vertical stress is made equal to the minimum principal value. Taking the fracture

    gradient to be equal to the propagation value the upper limit to the drilling window should be made

    equal to the vertical principal stress.

    Considering that all static mud weights, incorporating ECD margin, should be below the upper bound

    to the drilling window the only risk of losses should be along pre-existing faults and fractures. Whether

    or not these are partial or total losses will be dependant on (i) the degree of connectivity of the feature

    away from the wellbore wall and (ii) the nature of the fracture / fault directly dependant on its stress

    history - sealed with the major principal stress perpendicular or open with the minor principal stress

    perpendicular. Whilst reviewing previous reports / memos, results of a study conducted by Tetsuro4

    were noted. Within this note, occurrence of losses within previous development wells were related to

    well azimuth relative to the Chirag structure. All losses reported occurred whilst running the 9 5/8

    casing and in terms of depth relate to Top Sabunchi. The database was compiled from development

    wells A4 to A12. Corresponding ECD values quoted were derived using the Wellplan program. Results

  • 8/11/2019 Stability Chirag

    32/72

    S/UTG/105/00 A-15 Stability Assessment and Mud Weight Requirements

    August 2000 Page 26

    of the losses study implied that their occurrence was sensitive to well azimuth (e.g. A9 experienced no

    losses with 13.9 ppg ECD, while A4 experienced major losses with a 13.0 ppg ECD). Tetsuros

    explanation for observations noted is related to the azimuth of the well with respect to the maximum

    horizontal stress. Believing the maximum direction of compression to be perpendicular to the Chirag

    Structure Anticline Trend of NW-.SE, a maximum horizontal stress direction of 60ois assumed. Wellssuch as A4 and A5, drilled parallel to the maximum horizontal stress, are likely to be more at risk of

    instability than those drilled perpendicular to this direction. Tetsuro derived the following directionality

    - loss relationship:

    Most stable wells : up-dip and / cross dip wells with min horizontal stress dirn (330 o)

    Medium severity wells : down-dip wells with min horizontal stress direction (150o)

    Most unstable : wells with max. horiz. stress (60 / 240)

    Dip direction refers to the structural dip of the structure with up dip defined as 330o and down-dip

    referred to as 150o. This is not the same as smaller scale formation dips which will also have an effect

    on overall stability.

    Relating results of Tetsuros work with the A-15 azimuth of between approximately 10oto 40o, the risk

    of losses into natural fractures / faults is considered to be medium severity. The well direction falls

    between the worst and most favourable drilling direction in with respect to the in-situ stress orientation.

    Comparing well azimuth with structural dip, well azimuth lies mid way between up dip and cross dip

    directions.

    In addition to work by Tetsuro, the risk of losses within A-15 has been discussed in a note by Jake

    Hossack8. Jake states that with the maximum regional stress direction running perpendicular to the

    strike of the main thrust fault (i.e. ~ 60o), faults that strike perpendicular to the strike should be

    considered as high risk in terms of mud losses compared with thrust parallel faults.

    4.5 Mud Weight Recommendations for A-15

    Based on results presented in preceding sections and findings of the offset well review, the following

    static mud weights are recommended for minimising instability in well A-15:

    26 Hole : 8.6 ppg with contingency to weight up to 8.7 ppg if tight spots encountered

    17.5 Hole: 12.1 ppg

    12.25 Pilot Hole and Side-track : 12.4 ppg

    8.5 Side-track Hole: 11.2 to 11.4 ppg

    Within the 26 hole, offset data indicate that previous development wells were drilled with mud weights

    of between 8.4 ppg to 8.7 ppg. Results of stability analyses imply a minimum mud weight requirement

    of 8.7 ppg driven by subsurface conditions at the top of the Apsheron Formation. Since analyses may

    be slightly conservative within the very top hole soft sediments and considering previous drilling

    experience, a minimum mud weight of 8.6 ppg is thought the optimum mud weight for drilling this

    section.

    Within the 17.5 hole, offset data indicate that previous development wells were typically drilled with

    mud weights of between 11.9 ppg to 12.1 ppg with some tight spots noted but also occasional dynamic

  • 8/11/2019 Stability Chirag

    33/72

    S/UTG/105/00 A-15 Stability Assessment and Mud Weight Requirements

    August 2000 Page 27

    losses whilst circulating and during wiper trips. Results of stability analyses imply a minimum mud

    weight requirement of 12.1 ppg driven by subsurface conditions at 1237m TVDbrt in the Surakhany

    Formation. This weight is considered optimum for drilling this section. Since previous development

    wells report occurrences of dynamic losses within the 17.5 hole section careful attention must be given

    to minimising ECDs. As early development wells experienced several problems related to chemicalinstability it is important that mud type chosen provides optimum inhibition to minimise the occurrence

    of washouts.

    Within the 12.25 hole, offset data indicate that early development wells were typically drilled with

    mud weights as high as 12.9 ppg using a Quadrill mud system. Within later wells drilled with a

    synthetic based mud, densities were lower and ranged from 12.0 ppg to 12.6 ppg. The last two wells,

    A-13 and A-14, drilled with a combination fluid had density ranges of between 12.1 ppg and 12.4 ppg.

    Within offset wells A-2 to A-8 hole conditions were reportedly good with only a few overpulls and tight

    spots recorded. Within more recent wells drilled at higher inclinations instability appeared to worsen

    with an abundance of blocky cavings noted from the Sabunchi and Balakhany Formations. The report

    by Dowell Schlumberger notes hole enlargements within the Sabunchi Formation for wells drilled withsynthetic muds concluding that instability is most likely to be the result of mechanical failure as

    opposed to chemical effects.

    Results of stability analyses imply that both 12.25 pilot hole and side-track sections of A-15 should be

    drilled with a 12.3 ppg mud weight to minimise instability. This value is driven by the over-pressured

    Sabunchi Formation based on intact formation failure and assuming a completely inhibitive mud

    system. Considering hole problems in more recent wells resulting in large caving volumes, failure along

    pre-existing weakness planes may be an additional mode of failure to explain such instability in wells

    drilled at high angle through base Sabunchi / Balakhany. Considering ranges in bedding dip within the

    Balakhany, analyses incorporating anisotropic effects imply that failure along weakness planes could

    be a potential risk for the A-15 trajectory. To minimise the risk of bedding plane slip mud weights may

    need to be increased by a further 0.012 SG (0.1 ppg) within zones most at risk. Given that cavings

    within previous wells are reportedly from both the Sabunchi and the Balakhany it may be prudent to

    assume that this type of formation failure is feasible within both formations. Considering that the

    Sabunchi is described as a calcareous claystone with occasional inter-beds of sandstone and the

    Balakhany is described as blocky, failure along pre-existing weakness planes does not seem an

    unreasonable explanation. Also, within the Sabunchi, thin sand layers may be even more over-pressured

    than assumed. For this reason, increasing mud weight by an additional 0.1 ppg is seen to further reduce

    the risk of instability within these zones. For the 12.25 hole sections of A-15 a minimum mud weight

    of 12.4 ppg is thought the optimum mud weight for drilling this section. Since earlier development wells

    experienced occasional problems related to chemical instability it is important that mud type chosen

    provides optimum inhibition within this section.

    Within the 8.5 hole, offset data indicate that previous development wells were drilled with quite a wide

    range of mud weights of between 10.2 ppg to 12.4 ppg. From stability analyses conducted results imply

    that a mud weight between 11.1 ppg and 11.3 ppg should be used to minimise instability resulting from

    intact formation failure. The range of values quoted result from the variation in stress magnitudes

    considered. Given that the Pereriv may be susceptible to bedding plane slippage, mud weights should be

    further increased by 0.1 ppg. Optimum mud weight range for drilling this section is 11.2 to 11.4 ppg.

    A further risk of instability within this hole section is a buckling mode of failure in the roof of the

    borehole when the well is drilled within 10oof bedding. Instability may also be compounded where the

    well crosses the prognosed thrust fault. Without knowing the dip and dip direction of the fault at the

    point where it crosses the well path, however, analyses cannot be conducted to provide a qualitative

    assessment of instability risk. Although the majority of the Pereriv is sandstone and potentially able to

  • 8/11/2019 Stability Chirag

    34/72

    S/UTG/105/00 A-15 Stability Assessment and Mud Weight Requirements

    August 2000 Page 28

    be drilled with a nominal overbalance, mud weights recommended are those required to minimise the

    risk of instability within shale inter-beds.

    Given the risk of slippage along pre-existing weakness planes it is recommended that cavings be

    continually monitored at the rig site whilst drilling 12.25 and 8.5 hole sections. This will allow themost likely mode of failure to be identified such that the appropriate remedial action can be taken. If for

    example, instability is related to failure along pre-existing weakness planes, raising mud weight once

    instability has started will almost inevitably worsen hole conditions as the mud will act to lubricate and

    reduce the strength of planes still further. Crack blocking agents in the drilling fluid can retard the

    failure by restricting mud invasion. It is important to respond rapidly to sudden changes in cavings rate

    whereas a small constant volume of cavings are worth monitoring but may not require immediate

    remedial action. Photographs showing examples of typical cavings are presented in Figure 10 and

    Table 4 presents key characteristics and suggested remedial actions associated with different caving

    types. Differences between cavings delineated along fracture planes and those delineated along bedding

    features were presented earlier in section 4.3.

    F igure 10:Examples of Typical Cavings (Courtesy of Schlumberger)

  • 8/11/2019 Stability Chirag

    35/72

    S/UTG/105/00 A-15 Stability Assessment and Mud Weight Requirements

    August 2000 Page 29

    Caving Type Angular Platy / Tabular Splintery

    Failure

    Mechanism

    Shear failure resulting in

    multifaceted fragments

    Failure along pre-

    existing weakness planes

    Tensile failure believed

    to result from a poro-

    elastic response todrilling too fast through

    low permeability shale

    Key

    Characteristics

    Facets are newly

    created fracture

    surfaces

    Facets may be

    curviplaner

    Facets are non parallel

    Failure - two regions

    of wellbore separated

    by 180 degrees

    Majority of caving

    surfaces represent pre-

    existing planes of

    weakness

    One or more parallel

    surfaces are common

    Surfaces tend to be

    relatively smooth and

    planar Failure initiates on

    high side of wellbore

    when well is nearly

    parallel to a weakness

    plane

    Elongated platy rock

    fragments

    Typical lithology - low

    permeability shale

    Caving surfaces show

    plume structure

    indicative of tensile

    failure

    Entire circumferenceof wellbore may be

    damaged

    Remedial

    Action

    If mud weight close to

    pore pressure: raise

    mud weight

    If mud weight close to

    fracture pressure

    maintain mudweight

    decrease fluid loss

    manage hole

    cleaning

    Maintain mud weight

    Minimise fluid loss

    coefficient of drilling

    mud

    Use crack blocking

    additives Avoid back reaming

    Manage hole cleaning

    Avoid excessive rpm

    and drillstring

    vibrations

    Employ gentle drilling

    practices

    Raise mud weight

    Reduce ROP

    Table 4:Key Characteristics and Suggested Remedial Actions associated with Different Caving Type

    (Courtesy of Schlumberger)

    Comparing minimum mud weight recommendations with fracture gradient values induced fractures are

    not considered to be a risk but will be dependant on the ECD margin. The main risk of losses for A-15

    will be those that may be associated with pre-existing fractures and faults. From results of work

    conducted by Tetsuro and notes made by Jake Hossack of BP, risk of losses along the A-15 trajectory

    are considered to be of medium severity.

  • 8/11/2019 Stability Chirag

    36/72

  • 8/11/2019 Stability Chirag

    37/72

    S/UTG/105/00 Proposed Work Scope for Main ERD Study

    August 2000 Page 31

    6. Additional Wellbore Stabil ity Work to Support Future ERD Dr il li ng

    Following on from recommendations reported as part of this study, additional wellbore stability workwill be required to support future ERD drilling operations on Chirag. Given current knowledge of

    subsurface conditions across the structure, the following tasks are suggested to increase confidence in

    future wellbore stability predictions.

    Better definition of the pore pressure regime across the structure - pressure cube should be

    constructed using predictions from seismic, calibrated with offset well data

    Better definition of stress regimes and principal stress magnitudes. Numerical modelling should be

    employed to define total stress ranges. Linking this with improved pore pressure predictions an

    effective stress cube may be generated

    Improve rock strength predictions based on learnings from other Caspian Sea Fields and current

    advancements in populating stress cubes with rock property data derived from seismic.

    Incorporate faults into stress cube so as to optimise drilling trajectories by avoiding unfavourable

    attack angles. Information on losses into faults within previous development wells will help to

    differentiate between critical and non critically stressed faults

    Better definition of stress direction. Review all available breakout data. Possibility of performing a

    multi-well analysis using breakouts within a range of differently oriented well trajectories. Evidence

    of compressional failures and / or induced fracturing will also help to better constrain stress

    magnitudes.

    Optimise drilling practices in parallel with future wellbore stability work. Often hole problems are

    not solely the result of mechanical instability. Poor hole cleaning and general operational practices

    are often causes relating to pack offs and stuck pipe.

    Future wellbore stability needs identified for the Chirag Asset include a larger generic ERD study and a

    more specific study for the forthcoming A-16 well.

  • 8/11/2019 Stability Chirag

    38/72

    S/UTG/105/00 References

    August 2000 Page 32

    7. References

    1. D.E. Nierode; Chirag Wellbore Stability Study, Exxon Production Research Report, January 1998.RA

    2. Chris Dyke; Review of In-Situ Stresses and Rock Mechanical Properties for Hydraulic Fracturing /

    Frac Packing, Chirag, Azerbaijan, BP Draft Report, October 1997. RA

    3. Tetsuro Tochikawa; Sand Control Strategy, Memorandum, April 1999. RA

    4. Tetsuro Tochikawa; SBM Losses During 9 5/8 Casing Running and Cementing, File Note. RA

    5. Professor Nobuo Morita; Draft Stability Summary Notes - Various, Rock Mechanics and

    Production Research Section, Resources and Environmental Engineering, Waseda University. RA

    6. Davison and A. Burn; Characterisation of Shale Samples from Well A-13, Chirag Platform,

    Azerbaijan, Europe -Cis and Africa Technology Application Centre, July 2000. RA

    7. kland and J.M. Cook; Bedding Related Borehole Instability in High Angle Wells, SPE/ ISRM

    47285, Volume 1, Eurock Conference Proceedings, 1998. R

    8. Jake Hossack of BP, Notes on Faulting within the Overburden and Reservoir. RA

    9. Personal Communication: Dowson / Alberty. A

    10. Akhmedov; LOT and FIT Study, Azerbaijan Asset Document, 2000. A

    11. Horsrund; Estimating Mechanical Properties of Shale from Empirical Correlations, IKU Petroleum

    Research. Unsolicited SPE Paper (56017), January 1999. A

    12. Marie Scoular; Breakout Study Results. A

    Key

    RA - Within Main Report and Appendix

    R - Within Main Report Only

    A - Within Appendix Only

  • 8/11/2019 Stability Chirag

    39/72

    S/UTG/105/00 APPENDIX A: Field Information and Offset Well Review

    August 2000 Page 33

    APPENDI X A: F ield I nformation and Offset Well Review

    The Gunashli-Chirag-Azeri (GCA) field complex is located approximately 5km southeast of theApsheron Penninsula. The complex lies in water depths ranging from 85m to 300m. Hydrocarbons in

    the GCA complex are trapped within an elongated, north-west to south-east trending, south-east

    plunging anticlinal feature which extends nearly 50 km in length. The main oil producing intervals in

    the field are the Balakhany X and the Pereriv intervals of the Pliocene Productive series. Above the

    Balakhany Formation in the Sabunchi Formation, a number of sandstone reservoirs contain gas /

    condensate primarily on the crest of the structure. Figure A1 below presents a plan of the GCA

    structure with all exploration / appraisal well locations.

    .

    0 5km

    502800

    442

    0800

    512800 522800 532800 542800

    44

    30800

    444

    0800

    44

    50800

    502800 512800 522800 532800 542800

    442

    0800

    44

    30800

    444

    0800

    44

    50800

    Developed

    Gunashli

    PSAboundary

    Deepwater

    Gunashli

    Chirag

    Far East

    Azeri

    GCA-1

    GCA-4/4z

    GCA-5/5z

    GCA-2

    Prop.

    GCA-6/6z

    F igure A1:The GCA Structure Showing Exploration /Appraisal Well Locations

    The Chirag Field was discovered in 1984 by the drilling and testing of the exploration / appraisal well

    GCA-1. To date fourteen development wells, A-1 to A-14, have since been drilled to access reserves

    across the field. Well locations, together with the proposed A-15 trajectory, are presented in Figure A2

    below.

  • 8/11/2019 Stability Chirag

    40/72

    S/UTG/105/00 APPENDIX A: Field Information and Offset Well Review

    August 2000 Page 34

    F igure A2:Chirag Development and GCA-1 Well Locations

    As part of this study, all fourteen development wells and well GCA-1 were reviewed. For each

    formation a spreadsheet was compiled to pull together summary information from all wells. Details

    recorded include hole size, well inclination, well azimuth, mud type, mud weight, leak off test data and

    general notes detailing incidences of stuck pipe and losses associated with drilling and casing

    operations. All spreadsheets are presented on the following pages for Recent Sediments, Apsheron,

    Akchagyl, Surakhany, Sabunchi, Balakhany and Pereriv / NKG.

  • 8/11/2019 Stability Chirag

    41/72

    Recent

    T

    Well Hole Section

    Top Depth (MD

    brt) Blue :

    Casing, Red :

    Formation,

    Green : KOP

    End Depth (MD

    brt) Blue : Casing,

    Red : Formation,

    Green : KOP Incl. Azi.

    Mud Type

    for Entire

    Hole

    Section

    Mud Weight for

    Entire Hole

    Section

    LOT / FIT for

    Formation NOTES FOR ENTIRE HOLE SECTION (Chirag RTE = 36.6m ACSL, Water Depth = 121m)

    A1-OH 17.5" Pilot 157.6 416 0 to 1 185 Spud 8.7 Satisfactory drilling26" Opener 20" successfully run & cemented in place with returns (11.5 ppg lead & 15.8 ppg tail)

    A1-T1 - - - - - - - -

    A2 17.5" Pilot 157.6 409 0 to 5.4

    209 to

    230 to

    90

    Sea water

    and viscous

    pills Sea water

    Section drilled to TD of 480m. 20" casing cemented with 11.9 ppg lead & 15.8 ppg tail, full

    returns.26" Opener

    A3 17.5" Pilot 157.6 415 0 to 3.1

    206 to

    318

    viscous

    seawater

    and drilled 8.5 to 9.6 ppg

    Hole at 605m, total losses while pumping a sweep (9.5 ppg mw). Regained circ. after pulling

    BHA into 28" shoe. LCM pills to cure losses. At 364m the bit took weight, washed and reamed

    364m to 393m. No returns to TD. Assumed lost zone around 350m +/-20m

    Spotted LCM pills tripping from 420m to surface - no returns pumping. Hole opened to 26"

    - returns at top of cond. (8.6 - 8.7 ppg). Wiper trip - tight @560m & 460m. Hole displ. to

    9.6 ppg - returns lost at ~ 360m. 20" casing to 595m, cmt - no returns

    26" Opener

    seawater &

    viscous

    sweeps

    A4 17.5" Pilot 157.6 416

    0 to 4.8

    to 1.92

    191 to

    232 to

    133 to

    202

    seawater /

    PAC 8.5 ppg

    Drilled section IN 17.5" TO TD of 482m with good returns reported throughout. Opened up to

    26" again with good hole conditions. Prior to pulling out to run casing hole displaced with 8.5

    ppg spud mud. WOW and additional trip - good hole conds.

    20" casing run to 475.5m with good returns during running and circulating. 11.9 ppg lead

    and 15.8 ppg tail - good returns whilst cementing26" Opener

    A5 17.5" Pilot 157.6 417

    0 to

    2.22

    174 to

    to 187

    to 48

    seawater /

    PAC 8.4 to 8 .7 pp g

    Drill to section TD of 485m and open to 26". No losses - drilling / opening. Displace to 8.7 ppg

    spud mud prior to final trip out of hole. 20" run to 478m - no losses running / circulating. Cmt

    11.9 / 15.8 (lead / tail).

    Full to partial returns when pumping cmt slurry, after 473 bbls pumped returns were

    completely lost shortly after clear brine 160 ppm observed flowing out of well A3, btwn 28"

    & 20". Assumed A3 loss zone had allowed comm. with A5.26" Opener

    A6 17.5" Pilot 157.6 417 0 to 5

    174 to

    103 to

    203

    seawater /

    PAC 8.4 ppg

    Well drilled to TD of 479m: good returns reported. Hole opened to 26" - good hole conditions.

    Displace to a 8.5 ppg spud mud prior to running casing to TD of 472m: good returns running /

    circulating. 11.9 ppg lead & 15.8 ppg tail.

    Casing - good returns until 450 bbls lead pumped - lost total returns: started getting trickle

    returns of seawater after pumping 900bbls. Returns increased to 5 / 10 % after 1200 bbls

    lead pumped. No indication of hydraulic communication btwn. A6 & A326" Opener

    A7 12.25" Pilot 157.6 410 0 to 5

    188 to

    36

    seawater

    wi th sw eep s 8 .4 pp g

    Well drilled to 484m and opened to 26". Hole displaced to 8.7 ppg spud mud. 20" casing run to

    274m - worked and washed to 413m, then pulled. Hole cleaned out and deepened to 491m

    and again displaced to 8.7 ppg spud mud. 20" ran to 488m - no losses.

    11