St. Louis Council of Construction Consumers - Best Practices Submission for the Journalism School
-
Upload
wesleyvillhard -
Category
Documents
-
view
308 -
download
1
description
Transcript of St. Louis Council of Construction Consumers - Best Practices Submission for the Journalism School
SLCCC - Best Practices 2008Donald W. Reynolds Journalism Institute - Missouri School of Journalism
S L C C C B E S T P R A C T I C E S A W A R D S 2 0 0 8
DONALD W. REYNOLDS JOURNALISM INSTITUTEUnivers i ty o f M issour i - Co lumbia
St . Lou is Counc i l Construct ion ConsumersAward Submiss ionOctober 24 , 2008
SLCCC - Best Practices 2008Donald W. Reynolds Journalism Institute - Missouri School of Journalism
ExECUTIVE SUMMARY
The new $19.0M Donald W. Reynolds School of Journalism at the University of Missouri – Columbia involved three interconnected buildings including interior renovation of Walter Williams Hall, a 1930’s era building, the complete renovation of the original 1890’s era Sociology Building and the construction of a new, modern “Link” building. The Sociology building included a new poured in-place concrete frame “building within a building”.
It was found that the 120 year-old Sociology building had crumbling masonry walls and foundations. Many constructability issues were created due to the condition of the Sociology building including interior and exterior temporary bracing and structural reinforcing of the 120 year-old building shell. The temporary bracing also created many conflicts with new construction work. Other challenges included custom construction of new roof steel and “drifting” steel frames thru the existing wooden roof structure.
Unique features of the “building within a building” concept included horizontal wind braces from the old building shell to the new concrete frame and interior glass walls around the perimeter of the new structure. Other project features included matching the original stained glass windows, a structural glass walkway and a new TV studio.
Despite the severe unforeseen conditions jeopardizing the project’s survival, the Sircal/Kozeny-Wagner team presented creative and responsible solutions to very challenging engineering conditions that resulted in salvaging the project, not to mention one of the
landmark historical centerpiece buildings to the University of Missouri Columbia Campus.
SLCCC - Best Practices 2008Donald W. Reynolds Journalism Institute - Missouri School of Journalism
INTRODUCTION
Sircal/Kozeny-Wagner a Joint Venture was selected, by competitive bidding, as the General Contractor for the new $19.0M Donald W. Reynolds School of Journalism at the University of Missouri – Columbia. (Photo 1.) The project involved three interconnected buildings including interior renovation of Walter Williams Hall, (Photo 2.) a 1930’s era building, the complete renovation of the original 1890’s era Sociology Building (Photo 3.) and the construction of a new, modern “Link” building. The Sociology building included a new poured in-place concrete frame “building within a building”. More details about the “building within a building” concept will be provided below.
BEST PRACTICES
This Best Practices submission will focus mainly on the constructability practices and methods used for the renovation of the 1890’s Sociology Building. (Photo 3.) However, many other Best Practices were utilized including materials management, team building, quality management, change management and zero accident techniques. Through the course of the project the construction team field verified every critical dimension and devised ingenious methods to overcome hidden conditions, design challenges and problematic existing conditions.
FOUNDATIONSInitially the project team set out to investigate the depth and thickness of the existing fieldstone foundation (Photo 4.) of the 120 year-old Sociology Building. Hand excavations were made at various locations and it was found that the foundation varied in depth up to 4’ around the perimeter of the building. This required custom fabrication of all drilled pier reinforcing cages (Photo 5.) and ‘haunch” beam steel. (Photo 6.) The drilled piers and haunch beams were required to stabilize and reinforce the building foundation before additional work could proceed. After installation of the drilled piers, the haunch beams were hand excavated (Photo 7.) and custom formed for each location. (Photo 9.) The initial investigation and attention to existing conditions allowed the drilled pier and haunch beam construction (Photo 8.) to proceed smoothly eliminating costly change orders and potential delays.
ROOF STEELDuring investigation of the foundations, the project team also acknowledged the importance of existing dimensions for the fabrication of new roof support steel. (Photo 10.) The project superintendent, project engineer and steel shop drawing detailer spent many days investigating the existing roof structure and existing conditions while taking accurate dimensions for fabrication of the new roof support steel. It was ultimately determined that each new steel support must be custom fabricated due to the 120 year-old existing conditions.
SLCCC - Best Practices 2008Donald W. Reynolds Journalism Institute - Missouri School of Journalism
It was also determined that even accurate existing dimensions and custom fabrication would not insure proper fit of some steel members. Miscellaneous angles and structural tee (WT) joist hanger sections (Photo 11.) were shipped loose and field welded in place as existing conditions dictated.
STEEL ERECTIONThe bid documents indicated that the existing roof was to remain in place and did not address access for installation of new steel. The project team and the erection contractor developed a plan to cut “slot” openings (Photo 12.) through the existing roof to “drift” the new steel into place. (Photo 13.)
Intense preplanning for fabrication and erection of the new roof steel kept erection on schedule and costly change orders due to a minimum. (Photos 14, 15, 16,17, 18.)
ExISTING MASONRY WALLSIn preparation to set the new roof steel, existing masonry bearing walls were uncovered and inspected by the project team. It was found that many of the existing bricks were crumbling and too weak to support the roof loads. It was also found that the original field-mixed mortar had deteriorated and had virtually no strength. Bricks could be removed by hand from existing structural walls. (Photo 19.) The 1890’s building structural integrity was unstable and put at risk the project’s ultimate success. Due to the historical importance of the 1890’s structure, Sircal/Kozeny-Wagner was challenged to develop solution to save the structure. Through creative and responsible engineering solutions, the building was saved and project vision was realized.
CUSTOM BUILDING BRACESThe project team engineered custom bracing to support the crumbling masonry building. Custom bracing included 4x4 buck frames (Photo 20.) to hold windows square, interior bracing to support walls and hold building corners square (Photos 21, 22, 23, 24,25.) and extensive exterior bracing (Photo 26.) to carry wind and potential seismic loads while an engineered “fix” was developed to save this historic 120 year-old building. (This temporary bracing would remain in place for more than a year creating many more complications, while the “fix” was completed and new structural elements were able to carry wind and seismic loads.)
MASONRY REINFORCINGA new project team member was added, Masonry Solutions International to engineer the “fix” for the crumbling 120 year-old walls. The on-site project team facilitated the new design by removing areas of existing brick for engineering investigations and performing in-place strength tests of the existing walls and foundations (Photo 26a.).
Plans and specifications (Photos 27, 28, 29, 30.) were developed that required new horizontal and “stitched” reinforcing for the existing exterior walls. “Stitched” reinforcing was added to the walls by drilling holes at 30-degree angles, (Photo 31.) in two directions, through the
SLCCC - Best Practices 2008Donald W. Reynolds Journalism Institute - Missouri School of Journalism
existing three and four wythe thick brick walls. The project team also experimented with drills, drill bits, drill supports and drill braces (Photo 32.) to determine the most efficient methods to drill more than 50,000 reinforcing holes through the crumbling brick walls and foundations. (Photo 33.) As the holes were drilled and reinforcing bars installed, (Photos 34, 35.) a structural grout slurry mix (Photos 36, 36a.) was pumped into all wall cavities, through the stone foundations and at all new reinforcing locations.
BASEMENT LEVEL CONSTRUCTIONAfter the building was structurally reinforced and certified by the engineer, the teamundercut the existing basement slab by approximately 8’ as part of the new “building within a building” concept. (Photos 37, 38, 39, 40, 41.) A new poured in place 3-story concrete frame would be constructed inside the old 2-story 1890’s building shell. Extreme care was taken throughout construction to protect the temporary bracing (Photo 42, 43.) and to not disturb the existing field stone foundations.
CONFLICTS WITH TEMPORARY BRACING
The temporary bracing was to remain in place (Photos 44,45,46.) until the new concrete slabs and columns could carry the exterior wind loads and potential seismic loads. The existing foundation bearing elevation would now be approximately 4’ above the new basement floor slab. (Photos 47, 48.) Low headroom drill rigs (Photos 49, 50, 51.) were utilized to complete the interior drilled piers while maintaining the temporary building braces in place.
The project team also devised a plan to maintain the exterior temporary bracing while the new “Link” building floor slabs were constructed. (Photos 52, 53, 54.) With the help of the structural engineer, exterior braces were located so that they would pass through the new elevated slabs (Photos 55, 56.) in locations that would not compromise the integrity of the new structure.
After completion of the new concrete “Link” structure the braces were removed and several small deck pours were made to fill in the temporary openings in the new pan slabs. This constructability technique allowed new construction to continue despite the interference of the exterior temporary bracing supporting the Sociology building.
SEPARATION OF NEW & OLD STRUCTURAL LOADSSeveral other aspects of the “building within a building” concept required close attention to constructability. The floor slab elevations of the new three-story structure did not line up with the floor slab locations of the old two-story building. (Photo 57.) The new three-story structure was held approximately 2’ away from the old exterior walls. (Photo 58.) New floor slab loads would be carried by the new concrete structure. Floor slab loads were not to be imposed on the existing exterior Sociology walls even after installation of the structural reinforcing designed by Masonry Solutions.
SLCCC - Best Practices 2008Donald W. Reynolds Journalism Institute - Missouri School of Journalism
PERIMETER GLASS WALLSThe differing floor slab elevations required close attention to layout and dimensions for wind bracing of the exterior walls and many other building components. The existing exterior windows also did not line up with the new floor slab elevations. Glass walls were installed as architectural “fall protection” due to the 2’ gap around the new floor slabs and the potential hazard of existing window locations. (Photos 59, 60.) The perimeter glass walls also allowed natural sunlight to fill the new classrooms and offices through the old exterior windows.
HISTORIC WINDOW REPLACEMENTClose attention to constructability was also required to match the historic 1890 window profiles (Photo 61.) and original stained glass window patterns. (Photo 62.) Multiple field meetings were held along with many iterations of shop drawings for modern aluminum window profiles to “match” the historic, hand-made window profiles. The team also searched for and found the original stained glass manufacturing company to replace several stained glass windows. (Photo 62.) The University and the Historical Society were very pleased with all the new replacement windows, since the window profile and stained glass” match” were nearly perfect.
DIFFERING FLOOR SLAB ELEVATIONSAnother constructability concern was the (10) different floor slab elevations in (3) separate buildings, Walter Williams Hall, the Sociology building and the new “Link” building, that comprise the new Journalism School. The three separate buildings connect to the adjacent buildings thru various ramps and stairs. (Photos 63, 64, 65.) One of these ramps included an opaque glass walkway (Photo 66.) with clear glass sidewalls below a glass skylight, creating a dramatic architectural feature connecting the new “Link” building to the Sociology building. (Photo 67.)
STRUCTURAL GLASS WALKWAYThe project scheduled required the structural glass walkway to be constructed first, with framing and finishes completed later in the project. Protective measures and great care were taken while installing metal stud framing, MEP rough-ins, painting, ceilings and decorative wood panels above this walkway. Scores of workmen crossed this walkway every day, over many months, during the construction of the J-School project. Only one damaged glass panel was replaced due to extreme care and protection during the construction process.
“TYPICAL” CONSTRUCTABILITY ISSUESThe Journalism School entailed many other “typical” constructability issues including, limited access for deliveries, limited lay down area, tower crane placement, utility trenches below walkways (Photo 68.) and maintaining student access and sidewalks on the busy Mizzou campus. (Photo 69.) To further challenge the project team, the Journalism School was also constructed during the wettest period on record, winter/spring 2008.
SLCCC - Best Practices 2008Donald W. Reynolds Journalism Institute - Missouri School of Journalism
CLOSING
Despite the severe unforeseen conditions jeopardizing the project’s survival, the Sircal/Kozeny-Wagner team presented creative and responsible solutions to very challenging engineering conditions that resulted in salvaging the project, not to mention one of the landmark historical centerpiece buildings to the University of Missouri Columbia Campus. Best Practices recommends that the constructor become involved early in the planning process to recognize and solved constructability and many other issues prior to start of construction. Although, this was not the case here.
We believe that this project demonstrates that a professional construction team adds tremendous value no matter what stage they become involved in a complex addition/renovation project. The new Donald W. Reynolds School of Journalism was successfully completed and ready for the first day of class in August 2008. The Journalism School includes a new library (Photos 70, 71.), computer labs (Photo 72.), a café (Photo 73.), an auditorium with raised seating (Photo 74.), a TV studio (Photos 75, 76.), along with new facility offices and many new classrooms. (Photos 77. & 78. show the exterior of the completed “Link” and Sociology buildings).
SLCCC - Best Practices 2008Donald W. Reynolds Journalism Institute - Missouri School of Journalism
Photo 6
Photo 4
Photo 2
Photo 5
Photo 3
Photo 1
SLCCC - Best Practices 2008Donald W. Reynolds Journalism Institute - Missouri School of Journalism
Photo 12
Photo 10
Photo 8
Photo 11
Photo 9
Photo 7
Field Welded WT
Loose Angles
SLCCC - Best Practices 2008Donald W. Reynolds Journalism Institute - Missouri School of Journalism
Photo 18
Photo 16
Photo 14
Photo 17
Photo 15
Photo 13
SLCCC - Best Practices 2008Donald W. Reynolds Journalism Institute - Missouri School of Journalism
Photo 24
Photo 22
Photo 20
Photo 23
Photo 21
Photo 19
SLCCC - Best Practices 2008Donald W. Reynolds Journalism Institute - Missouri School of Journalism
Photo 28
Photo 26
Photo 29
Photo 27
Photo 25
Photo 26A
SLCCC - Best Practices 2008Donald W. Reynolds Journalism Institute - Missouri School of Journalism
Photo 34
Photo 32 Photo 33
Photo 31
Photo 35
Photo 30
SLCCC - Best Practices 2008Donald W. Reynolds Journalism Institute - Missouri School of Journalism
Photo 40
Photo 38
Photo 39
Photo 37
Photo 36 APhoto 36
SLCCC - Best Practices 2008Donald W. Reynolds Journalism Institute - Missouri School of Journalism
Photo 46
Photo 44
Photo 45
Photo 43
Photo 42Photo 41
SLCCC - Best Practices 2008Donald W. Reynolds Journalism Institute - Missouri School of Journalism
Photo 52
Photo 50
Photo 51
Photo 49
Photo 48Photo 47
SLCCC - Best Practices 2008Donald W. Reynolds Journalism Institute - Missouri School of Journalism
Photo 58
Photo 56
Photo 57
Photo 55
Photo 54Photo 53
SLCCC - Best Practices 2008Donald W. Reynolds Journalism Institute - Missouri School of Journalism
Photo 64
Photo 62
Photo 63
Photo 61
Photo 60Photo 59
SLCCC - Best Practices 2008Donald W. Reynolds Journalism Institute - Missouri School of Journalism
Photo 70
Photo 68
Photo 69
Photo 67
Photo 66Photo 65
SLCCC - Best Practices 2008Donald W. Reynolds Journalism Institute - Missouri School of Journalism
Photo 76
Photo 74
Photo 75
Photo 73
Photo 72Photo 71
SLCCC - Best Practices 2008Donald W. Reynolds Journalism Institute - Missouri School of Journalism
Photo 78Photo 77