SRF Accelerator Test Facility at NML Jerry Leibfritz May 23, 2011.

35
SRF Accelerator Test Facility at NML Jerry Leibfritz May 23, 2011

Transcript of SRF Accelerator Test Facility at NML Jerry Leibfritz May 23, 2011.

Page 1: SRF Accelerator Test Facility at NML Jerry Leibfritz May 23, 2011.

SRF Accelerator Test Facility at NML

Jerry Leibfritz

May 23, 2011

Page 2: SRF Accelerator Test Facility at NML Jerry Leibfritz May 23, 2011.

May 23, 2011 AEM Meeting 2

Outline

• Quick Recap of NML Facility• Current Status

– Cryomodule testing– Expansion construction– Cryomodule Test Facility (CMTF) – Development of linac

• Future Plans• Schedule

Page 3: SRF Accelerator Test Facility at NML Jerry Leibfritz May 23, 2011.

3

NML Test Facility

May 23, 2011 AEM Meeting

Page 4: SRF Accelerator Test Facility at NML Jerry Leibfritz May 23, 2011.

4May 23, 2011 AEM Meeting 4

Phase-1 Layout of NML

Cryomodule-1 (CM1) (Type III+)

Capture Cavity 2 (CC2)

CC2 RF System5 MW RF System for CM1

Page 5: SRF Accelerator Test Facility at NML Jerry Leibfritz May 23, 2011.

5May 23, 2011 AEM Meeting

RF Gun & Capture Cavity II (CC2)

Page 6: SRF Accelerator Test Facility at NML Jerry Leibfritz May 23, 2011.

6

Cryomodule-1 (CM1)

May 23, 2011 AEM Meeting

Page 7: SRF Accelerator Test Facility at NML Jerry Leibfritz May 23, 2011.

7

CM1 Test Plan

• Virtually identical to DESY run plan for XFEL modules (courtesy of Dennis Kostin) and Fermilab experience at HTS and CC2

• TEST PROCEDURE: – 1. RF Cable Calibration done– 2. Technical Interlock / Sensor checkout done– 3. RF source / Waveguides / LLRF done– 4. Warm Input RF Coupler Conditioning done– 5. Cooldown to 2K done– 6. Cavity Spectra measurements done– 7. Cavity Tuners Test and Tuning done– 8. Coupler Qload measurement done– 9. Set Cavities On Resonance done– 10. Cold Input RF Coupler and Cavity Conditioning done– 11. Single Cavity RF Measurements in progress– 12. RF Measurement of 8 Cavity Cryomodule– 13. Cryo performance testing

May 23, 2011 AEM Meeting

Page 8: SRF Accelerator Test Facility at NML Jerry Leibfritz May 23, 2011.

8

CM1 – RF Distribution

May 23, 2011 AEM Meeting

Page 9: SRF Accelerator Test Facility at NML Jerry Leibfritz May 23, 2011.

9

Phase-1 Civil Construction

Existing NML Building

New Underground Tunnel Expansion

(Space for 6 Cryomodules (2 RF Units), AARD Test Beam Lines)

Funded by ARRA

May 23, 2011 AEM Meeting

Page 10: SRF Accelerator Test Facility at NML Jerry Leibfritz May 23, 2011.

10May 23, 2011 AEM Meeting

NML Expansion

Existing NML Building Alcove for Cryoplant Tie-in

CM6CM5

Rack Room/Laser Lab

Beam Dump

Test Beamlines/AARD Area

- Construction Complete 4/11

10 meter Ring

Page 11: SRF Accelerator Test Facility at NML Jerry Leibfritz May 23, 2011.

11

NML Expansion Construction

May 23, 2011 AEM Meeting

Finished Tunnel Electrical Service BuildingDigging Tunnel

Page 12: SRF Accelerator Test Facility at NML Jerry Leibfritz May 23, 2011.

12

Phase-2 Layout of NML

CryomoduleCapture Cavity 1 (CC1)

5MW RF System for Gun

CC1 & CC2 RF Systems

RF Gun

10MW RF System for Cryomodules

High Energy Beam Absorber

CC2

Test Beam Lines

May 23, 2011 AEM Meeting

Page 13: SRF Accelerator Test Facility at NML Jerry Leibfritz May 23, 2011.

Utility Upgrade

• New Transformers, Switchboards, Generator• New Chiller for LCW System

May 23, 2011 AEM Meeting 13

Page 14: SRF Accelerator Test Facility at NML Jerry Leibfritz May 23, 2011.

Beam Absorber/Dump

• Three High Power (75 kW) Beam Absorbers

May 23, 2011 AEM Meeting 14

Page 15: SRF Accelerator Test Facility at NML Jerry Leibfritz May 23, 2011.

Beam Absorber/Dump

• Recycled over 600 Tons of Class-1 Steel from Railhead (value of ~ $500k)

May 23, 2011 AEM Meeting 15

Page 16: SRF Accelerator Test Facility at NML Jerry Leibfritz May 23, 2011.

16

Phase-2 Civil Construction (CMTF)

New Cryoplant & CM Test Facility

(300 W Cryogenic Plant, Cryomodule Test Stands, RF Test Area, Vacuum Cleanroom)

Vacuum Cleanroom

Cryomodule Test StandsRF Systems

Compressor Building

Cryogenic Refrigerators

Funded by ARRA

May 23, 2011 AEM Meeting

Page 17: SRF Accelerator Test Facility at NML Jerry Leibfritz May 23, 2011.

17

CMTF Construction

May 23, 2011 AEM Meeting

Page 18: SRF Accelerator Test Facility at NML Jerry Leibfritz May 23, 2011.

New Cryogenic Plant

• Ordered 12/10 from Linde

with ARRA Funds– 24 month lead time

• Supplement system with

SLAC Refrigerator

• Recycle Tevatron Equip.– Compressors– Storage Tanks– Cryogenic Piping

May 23, 2011 AEM Meeting 18

Page 19: SRF Accelerator Test Facility at NML Jerry Leibfritz May 23, 2011.

19

Phase-3 of NML and CMTF

May 23, 2011 AEM Meeting

Page 20: SRF Accelerator Test Facility at NML Jerry Leibfritz May 23, 2011.

20

NML Complex

May 23, 2011 AEM Meeting

Page 21: SRF Accelerator Test Facility at NML Jerry Leibfritz May 23, 2011.

21

NML Complex

May 23, 2011 AEM Meeting

Page 22: SRF Accelerator Test Facility at NML Jerry Leibfritz May 23, 2011.

Summary and Future Plans

• Phase-1 of Project is complete!– CC2 and CM1 have been cooled to 2K and RF powered– Upcoming talk on CM1 Operations – Elvin Harms

• Phase-2 in progress– Installation of gun, injector, beam lines, absorber/dump– First Beam in 2012

• Phase-3– Full Accelerator Operations (beam through at least 3 CM’s)– Advanced Accelerator R&D (AARD) Program

May 23, 2011 AEM Meeting 22

Page 23: SRF Accelerator Test Facility at NML Jerry Leibfritz May 23, 2011.

AARD Program

May 23, 2011 AEM Meeting 23

Page 24: SRF Accelerator Test Facility at NML Jerry Leibfritz May 23, 2011.

AARD Program - 2

May 23, 2011 AEM Meeting 24

Page 25: SRF Accelerator Test Facility at NML Jerry Leibfritz May 23, 2011.

Results of FNAL/ANL AARD Meeting

• Selected Three “Phase-1” AARD Experiments for NML

– Double Emittance Exchange (D-EEX) beam line for pulse shaping experiments (at 250-350 MeV)

– Integrable Optics Test Accelerator (IOTA) to demonstrate new nonlinear optics solution (at 150-300 MeV)

– High Brightness Compact Diamond Radiator (NIU/Vanderbilt) test experiment (at 40 MeV)

May 23, 2011 AEM Meeting 25

Page 26: SRF Accelerator Test Facility at NML Jerry Leibfritz May 23, 2011.

26May 23, 2011 AEM Meeting

NML Schedule/Milestones

• Phase-1 Cryogenic System Operational (August 2007)

• Delivery of First Cryomodule to NML (August 2008)• Begin Construction of CMTF Building (August 2010)• Cold RF Testing of First Cryomodule (Dec. 2010)• Complete Construction of NML Expansion (April 2011)

• Install Injector & Test Beam Lines (2011-2012)• First Beam (2012)• New Cryoplant Installation/Operation (2013-2014)• Install 3 Cryomodule String (2013-2014)• RF Unit Test with Beam (S2) (2014)

Page 27: SRF Accelerator Test Facility at NML Jerry Leibfritz May 23, 2011.

27

NML M&S Budget

• SRF (18.2) – FY11 $1,100k• Beamline/Facility Equipment (ARRA) $9,800k

– FY10-FY11

• Expansion Construction (ARRA GPP) $4,900k– Essentially Complete

• CMTF Construction (ARRA GPP) $7,100k– Expected Completion – 9/11

• Cryoplant Purchase (ARRA MIE) $9,300k– Ordered 12/10, Delivery ~ 2013

• RF Equipment for HTS2 & CMTF (ARRA) $2,900k

• Total $35,100k

May 23, 2011 AEM Meeting

Page 28: SRF Accelerator Test Facility at NML Jerry Leibfritz May 23, 2011.

Thanks to…

May 23, 2011 AEM Meeting 28

The Entire NML Team!

Page 29: SRF Accelerator Test Facility at NML Jerry Leibfritz May 23, 2011.

Backup Slides

Additional Information

May 23, 2011 AEM Meeting 29

Page 30: SRF Accelerator Test Facility at NML Jerry Leibfritz May 23, 2011.

30AEM Meeting

NML Project Overview

• Overall Goals– Build an RF Unit Test Facility at the New Muon Lab (NML)

• ILC RF Unit = 3 cryomodules• 10-MW RF system• Beam with ILC parameters (3.2 nC/bunch @3 MHz, Up to 3000 bunches @ 5Hz,

300-μm rms bunch length)

– Build Test facilities for Project-X cryomodules

• Phase-1 (FY07 – FY10) (Completed Dec. 2010)– Prepare facility for testing first cryomodule (CM1) without beam

• Infrastructure, RF power, cryogenics (Tevatron satellite refrigerators #1 & #2)

• Install first cryomodule (CM1) and Capture Cavity-2 (CC2), cooldown, and begin RF testing

• New tunnel civil construction (capability for 2 RF units)

May 23, 2011

Page 31: SRF Accelerator Test Facility at NML Jerry Leibfritz May 23, 2011.

31AEM Meeting

NML Project Overview

• Phase-2 (FY11 – FY12)– Prepare for First Beam

• Civil construction for new cryoplant and test stands• Move parts from FNPL photo-injector to NML• Install new gun, injector, Test beamlines, and beam dump• Swap CM1 with second cryomodule (CM2) - (S1)• Commission gun – generate first beam• Accelerate beam through single cryomodule

• Phase-3 (FY12 – FY14)– Complete RF Unit

• Upgrade RF system to 10 MW• Install RF Unit (3 cryomodules)• Commission new Cryogenic Plant• Operate full RF Unit with beam - (S2)

May 23, 2011

Page 32: SRF Accelerator Test Facility at NML Jerry Leibfritz May 23, 2011.

NML Project-X Test Stands

• CMTF (FY14 – FY15)– Test Stands for Project X

• Install shielding, RF, cryo for PX test stands• 1300 MHz (pulsed) CM test stand (with India)• 650 MHz (CW) CM test stand (with India)• 325 MHz (CW) CM test stand (with India)

May 23, 2011 32AEM Meeting

Page 33: SRF Accelerator Test Facility at NML Jerry Leibfritz May 23, 2011.

33

Beam Parameters

May 23, 2011 AEM Meeting

Page 34: SRF Accelerator Test Facility at NML Jerry Leibfritz May 23, 2011.

AEM Meeting 34May 23, 2011

Cooldown of CM1

Cool down to 4.5 Kelvin(2+ days)

Cool down to 2 Kelvin(~2 hours)

Page 35: SRF Accelerator Test Facility at NML Jerry Leibfritz May 23, 2011.

May 23, 2011 AEM Meeting 35

Cavity #1 Performance

Fast Thermometry response during a possible quench

Gradient (22 MV/m)

HOM temperature

Cavity vacuum