Objective:Develop remaining non-critical components to allow complete authoring

Target Outcome:To enable a complete authoring experience

224/224Points fully deliveredIntegrated ‘reflection’ technologyChanges Added M25 – Timeline Removed M10 Events

Sprint Tracking

Artifacts included:G5: Browse TagsG8: SignpostsM5: CommentsM8: Document EmbedM11: Events-DetailsM12: Events-ListsM15: Featured LinkM16: Link ListM18: Image GalleryM23: Social ShareM25: TimelineNFR: Image Rendition WorkflowNFR: Etc Mapping NFR: Create AEM Tag StoreNFR: Deployment to Test EnvironmentNFR: Groups for componentsNFR: Dispatcher RulesDefine Content ModelAdd Departments to phonebookDispatcher integration for header/footerSearch

Extras included in sprint:CWS-129: Invalidate cache for downloadsCWS-149: Add options to hide fields on contact informationCWS-152: Rework featured article component to use models/reflectionCWS-156: Checklist CTA – no way to link to assetsCWS-170: Page name and title are identicalCWS-173: Checklist with no URL shouldn’t have “learn more”CWS-188: Allow link-list in main body CWS-222: Create jenkins job for content backupCWS–245: Meta tag for content type attribute

Achievements

Delivered target + more outcomeExtras in development CWS-129 CWS-149 CWS-152 CWS-156 CWS-170 CWS-173 CWS-188 CWS-222 CWS-245

Deployment to Test Environment

Demonstration – Home page

Study page

Education facilities page

Getting started page

What to expect page

What’s coming next?Objective:Go-live preparation. Support testing and remediation ready for go-live, whilst developing a comprehensive go-live plan

Target Outcome:To have a stable and functional platform deployed in production

Q & A