Spring Hill High School – Phase 1 – Weekly Progress Report ...
1
Construction Manager: JE Dunn Architect: DLR Group Owner: Spring Hill School District Spring Hill High School – Phase 1 – Weekly Progress Report – September 15, 2017 Concrete Benches are Complete – Bldg F Fire Ceilings are Ready to be Installed 2 nd Floor – Bldg 4 – Ceilings Nearly Complete Phase 2 – Footings Being Installed Project Status This Week: Concrete Benches Completed Ceilings – 2 nd floor – Ready to be Painted Overhead MEP is nearly complete on 1 st floor Next Week: Ceilings – 2 nd Floor – Complete Fire Ceilings Complete Continue Phase 2 Footings Personnel on site: 40 JE Dunn Superintendent: 1 Accidents: 0 Lost time accidents: 0 Accident Free for: 153 Weather Days: 0 Learn. Create. Adapt. Succeed.
Transcript of Spring Hill High School – Phase 1 – Weekly Progress Report ...
Construction Manager: JE Dunn Architect: DLR Group Owner: Spring Hill School District
Spring Hill High School – Phase 1 – Weekly Progress Report – September 15, 2017
Concrete Benches are Complete – Bldg F Fire Ceilings are Ready to be Installed
2nd Floor – Bldg 4 – Ceilings Nearly Complete Phase 2 – Footings Being Installed
Project Status This Week:
Concrete Benches Completed
Ceilings – 2nd floor – Ready to be
Painted
Overhead MEP is nearly complete on 1st
floor
Next Week:
Ceilings – 2nd Floor – Complete
Fire Ceilings Complete
Continue Phase 2 Footings
Personnel on site: 40
JE Dunn Superintendent: 1
Accidents: 0
Lost time accidents: 0
Accident Free for: 153
Weather Days: 0