Administrative Services Update January 5, 2009 Spring 2009 Convocation

Transcript of Spring 2009 Convocation - Windward Community College · PDF fileExpenditure Plan by Program...

Administrative Services Update

January 5, 2009

Spring 2009 Convocation

Topics

  Electricity Challenge –  Recent Consumption and Rates –  Consumption History –  Mandate and Goals –  Institutionally –  Individually

  Budget Update –  Current Fiscal Year –  BI 2009-2011

  R&M Projects

Administrative Services Update – Spring 2009

Oct-2008 Dec-2008 Difference %

Change

Monthly Expense $ 148,151. $ 101,183. $ (46,968.) -46%

KWH Consumption 513,100 404,900 (108,200) -27%

Cost/KWH $ 0.2887 $ 0.2499 $ (0.0388) -16%

Cost/Day $ 4,629.72 $ 3,613.68 $ (1,016.04) -28%

Electricity Consumption Comparison October & December

Administrative Services Update – Spring 2009

Electricity Consumption Last Fiscal Year

Month Amount KWH $/KWH # Days $/Day Jul-07 Actual $ 74,451 452,600 0.1645 29 2,567.28

Aug-07 Actual $ 83,589 486,100 0.172 31 2,696.42 Sep-07 Actual $ 89,361 498,300 0.1793 31 2,882.61 Oct-07 Actual $ 95,187 522,500 0.1822 32 2,974.59 Nov-07 Actual $ 88,120 453,400 0.1944 29 3,038.62 Dec-07 Actual $ 90,199 459,800 0.1962 30 3,006.63 Jan-08 Actual $ 89,456 444,900 0.2011 32 2,795.50 Feb-08 Actual $ 92,918 434,500 0.2139 30 3,097.27 Mar-08 Actual $ 94,563 423,200 0.2234 30 3,152.10 Apr-08 Actual $ 101,499 453,000 0.2241 32 3,171.84

May-08 Actual $ 109,123 477,900 0.2283 29 3,762.86 Jun-08 Actual $ 121,206 510,600 0.2374 29 4,179.52

FY 08 Total $ 1,129,672

Administrative Services Update – Spring 2009

Electricity Consumption This Fiscal Year

Month Amount KWH $/KWH # Days $/Day July-08 Actual $ 131,272 560,500 0.2342 32 4,102.25

August-08 Actual $ 133,111 496,700 0.268 29 4,590.03 September-08 Actual $ 143,114 496,100 0.2885 31 4,616.58

October-08 Actual $ 148,151 513,100 0.2887 32 4,629.72 November-08 Actual $ 128,702 469,600 0.2741 30 4,290.07 December-08 Actual $ 101,183 404,900 0.2499 28 3,613.68

January-09 Estimated $ 100,062 400,410 0.2499 31 3,227.82 February-09 Estimated $ 97,723 391,050 0.2499 28 3,490.12

March-09 Estimated $ 95,182 380,880 0.2499 31 3,070.38 April-09 Estimated $ 101,884 407,700 0.2499 30 3,396.14 May-09 Estimated $ 107,484 430,110 0.2499 31 3,467.24

June-09 Estimated $ 114,839 459,540 0.2499 30 3,827.97 FY09 Total $ 1,402,709

Administrative Services Update – Spring 2009

Electricity Consumption

Administrative Services Update – Spring 2009

Electricity Consumption

Administrative Services Update – Spring 2009

Electricity Consumption

Administrative Services Update – Spring 2009

Electricity Consumption

Administrative Services Update – Spring 2009

Electricity Conservation Goal

 Current Fiscal Year Challenge WCC’s Allocation for Electricity = $1,145,220 Projected Expenditures FY 2009 = $1,402,709 Projected Shortfall = ($257,489)

  Budget Reduction BI 2009-2011 WCC’s Allocation for Electricity = $1,145,220 WCC’s Electricity Reduction = ($112,522) FY 2009-10 Electricity Allocation = $1,032,698

Administrative Services Update – Spring 2009

How Do We Get There?

Continue to Conserve Energy!!!

Hope HECO’s rate continue to decline

Repairs and Maintenance Projects

Photo Voltaic Project - UHCC System

Library Building, LEED – Silver Certification

Institutional Initiatives

Individual Initiatives

Administrative Services Update – Spring 2009

How Do We Get There?

R & M Projects Things That We’ve Done

• Replaced old campus electrical switchgear • Replaced old AC systems in Kuhina, Imiloa, Laakea

What We Will Be Doing • Campus electrical rewiring and re-alignment • Install energy efficient light fixtures • Install motion sensors • Replace window AC units with central system

Administrative Services Update – Spring 2009

How Do We Get There?

R & M Projects Things That We Plan or Want to Do:

• Upgrade energy management system (EMS) • Integrate individual AC systems into a campus chill

water loop system for efficiency • Install separate electrical sub-meters in each building • Install central AC in older buildings • Change light fixtures to be more energy efficient • Replace old mechanical and electrical equipment to be

more energy efficient

Administrative Services Update – Spring 2009

How Do We Get There?

UH CC System Project

Plan to construct a photo voltaic (PV) system on LCC’s parking lot to generate and store solar energy. Revenues and/or savings to be shared among Oahu Community Colleges. PV system should generate more electricity than what LCC can consume.

Administrative Services Update – Spring 2009

How Do We Get There?

New Library Building (LEED Certification)

• Architects Hawaii Limited • LEED Goal – Silver Certification Rating • Leadership in Energy & Environmental Design (LEED) • U. S. Green Building Council

Alternative Transportation Water Efficiency Energy & Atmosphere Materials & Resources Indoor Environmental Quality Innovation & Design Process

Administrative Services Update – Spring 2009

How Do We Get There?

Other Means to Reach Our Goal –

Institutionally:

Set AC thermostat at higher temp 73-75 degrees Purchase dehumidifiers if necessary More efficient class scheduling, Limit use of certain buildings on weekends, evenings, semester breaks, and holidays Reduce lights in hallways, parking lot and walkways when feasible using timers or photo sensors Reduce AC hours of operations cognizant of mold and mildew growth

Administrative Services Update – Spring 2009

How Do We Get There?

Administrative Services Update – Spring 2009

How Do We Get There?

Individually:

Close doors when AC is on Reduce humidity Extends life of equipment Turn off lights when not in use office, restrooms, classrooms Turn off window AC units when not in use Turn off your computer, monitor, printer, and any electronic devices Turn refrigerator thermostat to normal settings Use natural lighting when possible

Administrative Services Update – Spring 2009

Administrative Services Update – Spring 2009

Administrative Services Update – Spring 2009

General Funds (82%) $10,685,980

Tuition & Fees (17%) $2,249,149

Return of Overhead ( 1%) $73,338

TOTAL (100%) $13,008,467

FY 2009 Budget

Total Available Resources (est.)

Administrative Services Update – Spring 2009

Personnel Cost (75%) $9,749,485

Other Current Exp (25%) $3,258,982

Total (100%) $13,008,467

FY 2009 Budget

Expenditure Plan by Cost Category

Administrative Services Update – Spring 2009

Instruction (29%) $3,792,229 Vocational and Cont Ed (16%) $2,083,406 Academic Support (10%) $1,325,179 Student Services (11%) $1,439,737 Institutional Support (34%) $4,367,916 TOTAL (100%) $13,008,467

FY 2009 Budget

Expenditure Plan by Program Areas

Biennium 2009-2011 Budget Request

Governor’s Mandate

No Additional G-Funds Requested

10% Budget Reductions Electricity $112,522 ETC Counselor: $56,917 Cost Transfer TFSF: $67,890 TOTAL $237,329

Administrative Services Update – Spring 2009

Biennium 2009-2011 Budget Request

Tuition and Fee Special Funds Estimated Additional Revenue

From Tuition Rate Increase And Enrollment Growth

FY 2010 = $183,079 FY 2011= $389,970

To Fund: Financial Aid (Student Scholarships)

General Fund Cost Transfers (Reduction) Unfunded PCRs (Campus Initiatives)

Administrative Services Update – Spring 2009

Biennium 2009-2011 Budget Request

Capital Improvement Project (CIP) Library Learning Commons

Furniture and Equipment $1.578 Million

Administrative Services Update – Spring 2009

Repairs and Maintenance (R&M)

Administrative Services Update – Spring 2009

• Hale Laakea, AC replacement • Hale Alakai 102/129 to classrooms • Electrical Re-wiring Project • Hale Manaopono Renovation • Hale Kuhina 112, Nursing Classroom • Hale Palanikila Repair Leaks and Roof • Hale Palanikila/Imiloa, Repair Termite Damages • TLC relocation to Hale Alakai 106 • Telephone System Upgrade • Repair Ceiling Tiles and Fixtures • Water Sub-metering

Projects in Planning or Construction:

Have a great spring semester!