SPR 2009_Pontianak

download SPR 2009_Pontianak

of 3

Transcript of SPR 2009_Pontianak

  • 8/14/2019 SPR 2009_Pontianak

    1/3

    2009 STANDARD PROGRESS REPORTFORUNFPA 7TH CP

    INDONESIADISTRICTSAND PROVINCES

    DISTRICT: KOTAPONTIANAK

    PROVINCE: WESTKALIMANTAN

    DISTRICT/PROVINCE MANAGERNAME: IRMAPUTRIANDYANA

    DATEOFSUBMITTINGTHISREPORT: 20 JANUARY 2010

    PURPOSE

    1. To report on the progress achieved in 2009 as per the approved Country Programme Action Plan and

    Annual Work Plan.

    2. To accompany the Annual Work Plan Monitoring Tool as a narrative and provide an assessment of

    progress made in achieving CP outputs, challenges faced and obstacles met.

    Section 1: Outcome and Output indictors reporting

    Please fill in the excel file to inform us about the progress that was made in 2009. If you dont have the

    information just write down Information not available. If for 2009 in your district you didnt work on this

    area just right down Not Applicable. (D Annex 2 for districts and provinces overview 2009.xls)

    Section 2. Summary of 2009 Programme (max 2.5 page and KEEP IT SIMPLE and TO THE POINT)

    Summarize the main constraining and facilitating factors affecting implementation and the achievement of

    results. Identify key lessons learned in addressing constraints and taking advantage of facilitating factors.

    Output P101

    A. Results of programme in 2009 (please refer to Progress Towards Target file and elaborate on

    achievements

    1. Funcioning of Forum Database for Population data in Pontianak under Mayor decree number

    354 year 2008. Every quartal they had a coordination meeting about population, RH and

    gender data. Identify indicator and data which was integrated in Pontianak Figure was one of

    function this working group from BAPPEDA, Dinas Kesehatan, Dinas Pendidikan, DinasSosial Kependudukan dan Catatan Sipil, PKBI, KPA, BPS and Police. Pontianak in figure

    incorporated disaggregated data on population, reproductive health, adolescent reproductive

    health, STIs including HIV/AIDS, gender

    2. Data of RH, FP, population and gender already integrated into DDA book of Pontianak City

    B. Constraints and obstacles faced in trying to achieving the annual targets

    1. Participants who attended Forum database meeting is not always the same person

    C. Lessons learned and recommendations1. Will revised SK forum database in 2010.

    Section 3: Monitoring

    Summarize what knowledge and insights you have gained from monitoring activities conducted in the course

    of the year and assess how this knowledge was used to improve project performance (keep it short and to the

    point). (Monev Q2.doc,Monev Q3.doc, Monev Q4.doc)

    1

    http://var/www/apps/conversion/tmp/scratch_5/D%20Annex%202%20for%20districts%20and%20provinces%20overview%202009.xlshttp://var/www/apps/conversion/tmp/scratch_5/Monev%20Q2.dochttp://var/www/apps/conversion/tmp/scratch_5/Monev%20Q2.dochttp://var/www/apps/conversion/tmp/scratch_5/Monev%20Q3.dochttp://var/www/apps/conversion/tmp/scratch_5/Monev%20Q4.dochttp://var/www/apps/conversion/tmp/scratch_5/D%20Annex%202%20for%20districts%20and%20provinces%20overview%202009.xlshttp://var/www/apps/conversion/tmp/scratch_5/Monev%20Q2.dochttp://var/www/apps/conversion/tmp/scratch_5/Monev%20Q3.dochttp://var/www/apps/conversion/tmp/scratch_5/Monev%20Q4.doc
  • 8/14/2019 SPR 2009_Pontianak

    2/3

    1. Data base in puskesmas recorded manually, so the process of collecting data takes so long time. It is

    important to enhance our puskesmas using computer technology so that recording and reporting is

    very efficient and accurate.

    2. Theres one office that I visited and I saw only one person who did all job, from planning the

    activities, prepare the activities, and made an activity reports from local budget until UNFPA budget.The reason was lack of skilled staff (can not operate the computer at all) and so many activities, it

    made reporting very late. While I was though, there are several human resource can be used, althoughperhaps not optimal, but very helpful in the process, so that the activities and reporting are not

    significantly delayed.

    Section 4: Trainings and workshops all components:

    1. How many people were trained for each output? (if not available just write down NA)

    Output

    Indicator Planned to be

    trained

    Actually trained

    Male Female Total

    P101

    Improved availability

    and increased

    capability to utilizedisagregatted data on

    population,

    reproductive health

    and adolescent

    reproductive health ,

    STIs and HIV/AIDS,

    gender, poverty and

    enhanced

    understanding ofplanners, policy

    makers and

    parliamentarians on

    their linkages with

    development.

    20 15 5 20

    proportion of

    identified planners and

    policy makers in each

    district and province

    trained utilizing

    available data for sub-

    national developmentplans (rencana

    Strategis Daerah &

    Rencana KerjaPemerintah Daerah)

    20 16 4 20

    2

  • 8/14/2019 SPR 2009_Pontianak

    3/3

    2. How many workshops/trainings/meetings were held in 2009

    Workshops TrainingsCoordination

    meetingsTotal

    R101 5 1 5 11

    R301 1 1 1 3

    R105 5 0 4 9

    R205 5 4 8 17

    P101 1 2 4 7

    G101 2 0 4 6

    Programme Management (such as

    quarterly coordination meeting with

    Bappeda and PPMs

    1 0 6 7

    SECTION 4. Financial implementation

    Output Budget Expenses

    Implementation

    Rate

    R101 79.950.000 74.000.000 92.56%

    R301 119.065.000 119.065.000 100%

    R105 100.175.000 100.175.000 100%

    R205 377.316.800 377.316.800 100%P101 92.990.000 92.990.000 100%

    G101 48.075.000 48.000.000 99.84%

    Total 817.571.800 811.546.800 99.26%

    Before submitting please check whether you have attached all the required attachments.