SPR 2009_NTB Province

download SPR 2009_NTB Province

of 6

Transcript of SPR 2009_NTB Province

  • 8/14/2019 SPR 2009_NTB Province

    1/6

    2009 STANDARD PROGRESS REPORTFORUNFPA 7TH CP

    INDONESIADISTRICTSAND PROVINCES

    DISTRICT: -----

    PROVINCE: WEST NUSA TENGGARA

    DISTRICT/PROVINCE MANAGERNAME: DUDDIN A HUSEIN

    DATEOFSUBMITTINGTHISREPORT: 28 JANUARY 2010

    PURPOSE

    1. To report on the progress achieved in 2009 as per the approved Country Programme Action Plan and

    Annual Work Plan.

    2. To accompany the Annual Workplan Monitoring Tool as a narrative and provide an assessment of

    progress made in achieving CP outputs, challenges faced and obstacles met.

    Section 1: Outcome and Output indictors reporting

    Please fill in the excel file to inform us about the progress that was made in 2009. If you dont have the

    information just write down Information not available. If for 2009 in your district you didnt work on this

    area just right down Not Applicable.

    Section 2. Summary of 2009 Programme (max 2.5 page and KEEP IT SIMPLE and TO THE POINT)

    Summarize the main constraining and facilitating factors affecting implementation and the achievement of

    results. Identify key lessons learned in addressing constraints and taking advantage of facilitating factors.

    Output R101

    A. Results of programme in 2009 (please refer to Progress Towards Target file and elaborate on

    achievements (so dont summarize all activities just mention how the progress has been achieved)

    1. Endorsed Strategic Planning (Renstrada) and Local Action Plan (Rencana Aksi Daerah/RAD)

    on Prevention of HIV-AIDS.

    2. Endorsed Renstrada and RAD on Reproductive Health and ARH.

    3. Endoresed Guidelines on integration 0f ARH into Local Curricula

    B. Constraints and obstacles faced in trying to achieving the annual targets (you can mention here big

    issues such as lack of time, lack of commitment from politicians and policy makers unclear targets,

    not enough IEC material available, better trainers needed, need for more technical support, etc)

    Lack of reference in developing Guideleine on ARH. However, the constrain can be countered by

    using Draft on National ARH Guidelines and other literature related to RH.

    C. Lessons learned and recommendations

    Any National guidelines related to UNFPA Mandates (RH, gender and others issues) shouled be

    developed before province and districts asked to adopt or develop the guidelines.

    Output R105

    A. Results of programme in 2009 (please refer to Progress Towards Target file and elaborate on

    achievements (so dont summarize all activities just mention how the progress has been achieved)

    1. Socialized/informed Local Regulation (Perda) on Prevention of HIV-AIDS to new elected

    provincial parliamentarians (Anggota baru DPRD Provinsi).

    1

  • 8/14/2019 SPR 2009_NTB Province

    2/6

    2. Socialized/informed Local Regulation (Perda) on Trafficking to new elected provincial

    parliamentarians

    3. Dveloped and endorsed Local Regulation (Perda) on Protection of Women and Choldren

    (Perda No 2 th 2009)

    4. Informed RH, and gender issues to Community and Religious Leaders.

    B. Constraints, obstacles and opportunities (such as supportive environment from legislatures) faced intrying to achieving the annual targets (you can mention here big issues such as lack of time, unclear

    targets, not enough IEC material available, better trainers needed, need for more technical support,

    etc)

    Most of new elected parliamentarians have not understood and awared about RH and gender

    issues. This condition leads to difficulties in order to inform RH and gender issues. Therefore, in

    the begining, it alsobecome an obstacle in developing any regulation related to RH and gender

    issues.

    C. Lessons learned and recommendations.

    It need more advocacies to the new pariamentarians on RH and gender issues as well as other

    issues related to UNFPA Mandates.

    Output R301

    A. Results of programme in 2009 (please refer to Progress Towards Target file and elaborate on

    achievements (so dont summarize all activities just mention how the progress has been achieved)

    Increased awareness of community on RH and gender issues. This is shown by many questions

    related to RH and gender issues during the radio talk show and airing Radio Drama Series and

    PSA regarding with RH and Gender issues which were conducted by BKKBN.

    B. Constraints and obstacles faced in trying to achieving the annual targets (you can mention here big

    issues such as lack of time, lack of commitment from politicians and policy makers unclear targets,

    not enough IEC material available, better trainers needed, need for more technical support, etc)

    1. There are two government agencies those are related to activities under outputs R301, i.e

    BPPKB and BKKBN. This condition sometiemes makes a difficulty to define weather an

    activity is under responsibility of BPPKB or BKKBN.

    2. Change of staff at BKKBN lead to delaying implementation of activities under output R301.

    This condition occured because staff who is usually responsible for oraginzing UNFPAs

    activities at BKKBN was changed. The new staff was not familier to organize the UNFPAs

    activities.

    C. Lessons learned and recommendations

    1. It needs a special discussion between BPPKB and BKKBN to define which activity is under

    responsibility of BKKBN and which activity is under responsibility BPPKB.2. It is difficult to measure number of audiences who have been listening PSA or any airing

    programme related to RH and gender issues and to find out the impact of this IEC programme

    exactly. It needs a rapid survey to solve this problem.

    Output R205

    A. Results of programme in 2009 (please refer to Progress Towards Target file and elaborate on

    achievements (so dont summarize all activities just mention how the progress has been achieved)

    2

  • 8/14/2019 SPR 2009_NTB Province

    3/6

    1. Improved IERH Services at Puskesmas and CEONC at district hospital.

    2. Improve capacity of District and Puskesmas VCT laboratorium staff.

    3. Improved knowledge of Puskesmas staff on Gender Issues

    4. Improved skill of Puskesmas Staff on how to use DMT.

    B. Constraints and obstacles faced in trying to achieving the annual targets (you can mention here big

    issues such as lack of time, lack of commitment from politicians and policy makers unclear targets,not enough IEC material available, better trainers needed, need for more technical support, etc)

    Staff of Dinkes who is responsible to organized UNFPA Programme was changed. As the new staff

    has not known anything about UNFPA programme, there were some activities under output R205,

    which were organized by Dinkes, were delayed.

    C. Lessons learned and recommendations.

    Facing such problem above, PPCU ask implementing partner to send the new staf to be trained

    at PPCU office on how to organize UNFPA activities.

    Output P101

    A. Results of programme in 2009 (please refer to Progress Towards Target file and elaborate onachievements (so dont summarize all activities just mention how the progress has been achieved)

    1. Developed and distributed NTB in Figures (books and CD Rom) that involeve disaggregated

    data on population, RH and gender.

    2. Functioned Data Base Forum.

    3. Trained SKPDs Planners on utilization of disaggregated data on population, RH and gender in

    kdeveloping Local Development Planning (Rencana Pembangunan Daerah).

    B. Constraints and obstacles faced in trying to achieving the annual targets (you can mention here big

    issues such as lack of time, lack of commitment from politicians and policy makers unclear targets,

    not enough IEC material available, better trainers needed, need for more technical support, etc)

    Some government offices (SKPD) submitted data to BPS lately, therefore NTB in figure (DDA)

    could not be published earlier.

    C. Lessons learned and recommendations.

    Data Base Forum should more active to ask SKPD to submit sectoral data in order to develope

    NTB in figure.

    Output G101

    A. Results of programme in 2009 (please refer to Progress Towards Target file and elaborate on Results

    of programme in 2008 (please refer to Progress Towards Target file and elaborate on achievements(so dont summarize all activities just mention how the progress has been achieved)

    1. Strengthened Network for GBV prevention & management services for province & districts,

    including Reporting and Recording System.

    2. Increased knowledge and awareness of SKPDs planners on Gender Responsive Budgetting.

    3

  • 8/14/2019 SPR 2009_NTB Province

    4/6

    B. Constraints and obstacles faced in trying to achieving the annual targets (you can mention here big

    issues such as lack of time, lack of commitment from politicians and policy makers unclear targets,

    not enough IEC material available, better trainers needed, need for more technical support, etc)

    As a new government agency, Badan Pemeberdayaan Perempuan dan KB (BPPKB) has not had

    clear organization strucure and function. Therefore, there is no definitive staff who is responsible

    for organiziing UNFPA activities under outputs G101.

    C. Lessons learned and recommendations.

    BPPKB should define a special staff to organize any UNFPA activity under outputs G101.

    4

  • 8/14/2019 SPR 2009_NTB Province

    5/6

    Section 3: Monitoring

    Summarize what knowledge and insights you have gained from monitoring activities conducted in the course

    of the year and assess how this knowledge was used to improve project performance (keep it short and to thepoint).

    Section 4: Trainings and workshops all components:

    1. How many people were trained for each output? (if not available just write down NA)

    Output

    Indicator Planned to be

    trained

    Actually trained

    Male Female Total

    R101

    R301

    R105

    R205

    P101

    G101

    2. How many workshops/trainings/meetings were held in 2009

    Workshops

    Trainings

    Coordination

    meetings

    Total

    R101

    R301

    R105

    R205

    P101

    G101

    Programme Management (such as

    quarterly coordination meeting with

    Bappeda and PPMs

    5

  • 8/14/2019 SPR 2009_NTB Province

    6/6

    SECTION 4. Financial implementation

    Output Budget Expenses

    Implementation

    Rate

    R101

    R301

    R105

    R205

    P101

    G101

    Total

    Before submitting please check whether you have attached all the required attachments.

    6