SPP.org 1. Final Report: Reliability and Economic Assessments Stakeholder Meeting December 1, 2008...

32
SPP.org 1

Transcript of SPP.org 1. Final Report: Reliability and Economic Assessments Stakeholder Meeting December 1, 2008...

Page 1: SPP.org 1. Final Report: Reliability and Economic Assessments Stakeholder Meeting December 1, 2008 Austin, TX.

SPP.org 1

Page 2: SPP.org 1. Final Report: Reliability and Economic Assessments Stakeholder Meeting December 1, 2008 Austin, TX.

Final Report:

Reliability and Economic

AssessmentsStakeholder Meeting

December 1, 2008

Austin, TX

Page 3: SPP.org 1. Final Report: Reliability and Economic Assessments Stakeholder Meeting December 1, 2008 Austin, TX.

SPP.org 3

Activities Completed Since Last Meeting

• Reliability Assessment

Finalize results for SPP QPR option

Tie back Study for ERCOT QPR option

Stability Analysis for SPP QPR option

• Economic Assessment

Economic projects identified

Cost/Benefit Analysis for Status Quo and Integrated case

Page 4: SPP.org 1. Final Report: Reliability and Economic Assessments Stakeholder Meeting December 1, 2008 Austin, TX.

SPP.org 4

Transmission Upgrades: Reliability Upgrades and Economic Upgrades

Page 5: SPP.org 1. Final Report: Reliability and Economic Assessments Stakeholder Meeting December 1, 2008 Austin, TX.

SPP.org 5

Reliability Study Cases

• Contingency analysis (N-1) for SPP-ETI system

More stringent reliability criteria in Western Region (N-1, G-1)

Monitored 69 kV and above

• Several potential thermal and voltage violations found

• SPP examined a set of reliability upgrades to mitigate these violations

Substation work at Orange County

Reconductor eight 138 kV lines in ETI area

Reconductor five 69 kV lines in ETI area

• High level planning estimate of projects required to meet SPP Criteria is $105 M

COTTONWOOD IN EASTERN INTERCONNECTION

Projects to meet SPP Criteria

New Orange County Substation work ($50 M)

138 kV and 69 kV Upgrades ($55 M)

Planned Known Projects

ETI Proposed Projects for 2012

Local Reliability projects for Western Region

Transmission Reliability projects from the 2007 approved STEP Plan

ETI Transmission Construction Plan

Page 6: SPP.org 1. Final Report: Reliability and Economic Assessments Stakeholder Meeting December 1, 2008 Austin, TX.

SPP.org 6

Tie Back Study

• Objective of this study to evaluate reliability of SPP system under ERCOT QPR option

• Most of the tie-lines across LA-TX removed and loop backed

• DC ties at two locations considered

Hartburg (830 MW and 250 MW)

Quarry, Near Crockett (150 MW and 50 MW)

Page 7: SPP.org 1. Final Report: Reliability and Economic Assessments Stakeholder Meeting December 1, 2008 Austin, TX.

SPP.org 7

Potential ETI-ERCOT Disconnection Points

Quarry

Newton Bulk

Leach

Hartburg

Sabine

To Big Three, Hollywood, Toomey

Orange

Bon WierDETAIL 1

DETAIL 2

Page 8: SPP.org 1. Final Report: Reliability and Economic Assessments Stakeholder Meeting December 1, 2008 Austin, TX.

SPP.org 8

DETAIL 1

Page 9: SPP.org 1. Final Report: Reliability and Economic Assessments Stakeholder Meeting December 1, 2008 Austin, TX.

SPP.org 9

DETAIL 2

Page 10: SPP.org 1. Final Report: Reliability and Economic Assessments Stakeholder Meeting December 1, 2008 Austin, TX.

SPP.org 10

ETEC System Disconnection Points

X

Pineland- Bronson

Page 11: SPP.org 1. Final Report: Reliability and Economic Assessments Stakeholder Meeting December 1, 2008 Austin, TX.

SPP.org 11

Tie Back Study : Study Results

• SPP Area were examined based on N-1 contingency analysis using SPP Criteria

• Four Key Transmission Projects were identified by SPP staff to meet the SPP reliability criteria for ERCOT QPR option

Upgrade Broken Bow – Bethel 138kV line

Upgrade Fisher Transformer (138/115kV)

Upgrade Toledo Bend – Hemphill 138kV Line

Acadiana Projects

Page 12: SPP.org 1. Final Report: Reliability and Economic Assessments Stakeholder Meeting December 1, 2008 Austin, TX.

SPP.org 12

Estimated Cost for SPP Members under ERCOT QPR option

Direction is from ETI to SPP

Hartburg DC Tie

(830 MW) (250 MW)

Quarry DC Tie

150 MW $25 Million $31 Million

50 MW $25 Million $61 Million

Page 13: SPP.org 1. Final Report: Reliability and Economic Assessments Stakeholder Meeting December 1, 2008 Austin, TX.

SPP.org 13

Stability Assessment

• Objective of this study is to evaluate stability of ETI under SPP QPR and ERCOT QPR options

• A consultant (Powertech) is performing this study

• Transient and Voltage Stability analyses being performed using Entergy and SPP Stability Criteria

• ETI system will be tested under various fault scenarios and transfers into ETI using projects identified for SPP QPR option

Page 14: SPP.org 1. Final Report: Reliability and Economic Assessments Stakeholder Meeting December 1, 2008 Austin, TX.

SPP.org 14

Stability Assessment : Cont.

• Stability study models are prepared jointly by SPP and ETI staff and sent to Powertech

• Simulated critical N-1, G-1, and N-G-1 contingencies in ETI first-tier areas (both electrical and geographical areas in SPP and rest of Entergy)

• Preliminary results indicated no significant issues in ETI system

Results indicate that RMR Requirements can be reduced

• The final results are expected in first quarter of 2009

Page 15: SPP.org 1. Final Report: Reliability and Economic Assessments Stakeholder Meeting December 1, 2008 Austin, TX.

SPP.org 15

Economic Upgrades

• Two Projects included as Economic Upgrades

Mt. Olive to Hartsburg series capacitor ($10 M)

Increased rating to 1,450 MW thus reducing significant constrained hours

Weber-Richard 500 kV line ($229 M)

Helped reduced congestion in Cottonwood area and RMR need in Sabine area along with other reliability upgrades

Page 16: SPP.org 1. Final Report: Reliability and Economic Assessments Stakeholder Meeting December 1, 2008 Austin, TX.

SPP.org 16

Cost allocation of ETI Reliability projects

• Reliability projects are required solely to integrate ETI into SPP

• SPP policy is to allocate these costs to the local zone

Similar to current discussion with Nebraska entities

Consistent with treatment with Pre Base Plan funding

• ETI Benefits compared to full cost of Reliability Projects ($105 M)

Page 17: SPP.org 1. Final Report: Reliability and Economic Assessments Stakeholder Meeting December 1, 2008 Austin, TX.

SPP.org 17

Cost allocation of ETI Economic Projects

• ETI Benefits compared to full cost of Economic Projects ($239 M)

• Economic Upgrades may be fully or partially funded by SPP pursuant to their Tariff provisions (i.e. Balanced Portfolio)

Page 18: SPP.org 1. Final Report: Reliability and Economic Assessments Stakeholder Meeting December 1, 2008 Austin, TX.

SPP.org 18

Economic Assessment

Page 19: SPP.org 1. Final Report: Reliability and Economic Assessments Stakeholder Meeting December 1, 2008 Austin, TX.

SPP.org 19

Key Market Assumptions – Status Quo Model

• SPP Market Assumptions

SPP modeled as Day 2 Market planned by SPP Cost Benefit Task Force

System wide unit commitment

System wide treatment of spinning reserve requirements

Security Constrained Unit Commitment and Economic Dispatch

SPP operates as a Single Balancing Authority

• Entergy (including ETI) Operating Assumptions

System wide unit commitment

Security Constrained Economic Dispatch

Reserve Requirements set and met on Entergy System wide basis

ETI RMR Requirement consistent with historical operation to address local voltage constraints

ETI and Entergy generation output consistent with historical operations

• Hurdle rates between SPP / other Regions and Entergy / other Regions

Dispatch hurdle 7 $/MWh (Entergy/SPP hurdle rate $14/MWh)

Commitment hurdle 25 $/MWh

Consistent with SPP Future Market Design Study assumptions

Page 20: SPP.org 1. Final Report: Reliability and Economic Assessments Stakeholder Meeting December 1, 2008 Austin, TX.

SPP.org 20

Key Market Assumptions – ETI/SPP Integrated Model

• SPP Market Assumptions same as Status Quo model

• ETI is a Member of SPP

• ETI RMR Requirements are reduced due to Reliability and Economic Transmission upgrades

Consistent with preliminary stability analysis results

Thermal constraints continue to be identified via Security Constrained Economic Dispatch (transmission system now includes all Reliability Projects and Economic Projects)

• Hurdle rates same as Status Quo except no hurdle rate between SPP and ETI

Page 21: SPP.org 1. Final Report: Reliability and Economic Assessments Stakeholder Meeting December 1, 2008 Austin, TX.

SPP.org 21

Benefit Metric – ETI Adjusted Production Cost

• Same Benefit metric being used by the SPP Cost Benefit Task Force in the Future Market Design Study

• Adjusted Production Cost for ETI

Generation Total Variable Cost

+ Purchase Cost at ETI Load-Hub Rate

– Sales Revenue at ETI Generation-Hub Rate

Page 22: SPP.org 1. Final Report: Reliability and Economic Assessments Stakeholder Meeting December 1, 2008 Austin, TX.

SPP.org 22

ETI Benefits

Page 23: SPP.org 1. Final Report: Reliability and Economic Assessments Stakeholder Meeting December 1, 2008 Austin, TX.

SPP.org 23

2012 Benefits to ETIETI Operational Benefits

Status Quo - Cottonwood

in Eastern Interconnect

Integrated SPP/ETI Case -

Cottonwood in Eatern

Interconnect

Status Quo - Cottonwood

in ERCOT

Integrated SPP/ETI Case - Cottonwood

in ERCOT

ETI Benefits - Cottonwood

in Eastern Interconnect

ETI Benefits - Cottonwood

in ERCOT2012 2,336.21 2,233.58 2,389.48 2,299.72 102.64 89.76

1 209.98 197.56 209.98 197.24 12.41 12.74 2 174.16 164.55 173.92 165.01 9.62 8.91 3 186.52 175.32 186.43 174.90 11.19 11.53 4 175.97 161.66 175.22 161.93 14.32 13.29 5 191.15 180.59 194.53 185.27 10.56 9.26 6 202.72 196.08 213.34 209.25 6.65 4.09 7 227.63 222.80 239.92 240.17 4.84 (0.24) 8 228.14 225.39 245.36 246.37 2.74 (1.01) 9 197.61 190.22 204.86 197.30 7.39 7.56

10 192.89 184.53 193.98 186.39 8.35 7.59 11 156.56 149.09 158.40 150.28 7.47 8.12 12 192.88 185.79 193.56 185.62 7.10 7.94

Adjusted Production Cost in MM$ - (APC) Operational Benefit MM$

Page 24: SPP.org 1. Final Report: Reliability and Economic Assessments Stakeholder Meeting December 1, 2008 Austin, TX.

SPP.org 24

Discussion of Findings - ETI

• Cottonwood in Eastern Interconnection (EIC) ETI Generation Cost reduced by $404 M, purchase costs increased

by $237 M and sales revenue was reduced by $64 M, resulting in an overall benefit of $103 M.

Based on an 18% carrying charge rate for Transmission Investment, this $103 M would support about $570 M in transmission investment

Proposed total cost of Reliability and Economic Upgrades is about $344 M

Benefit to Cost Ratio is 1.63 Includes $5 M in ROA implementation cost

• Cottonwood in ERCOT Benefits reduced due to loss of Cottonwood generation $90 M in benefits would support about $500 M in Transmission

Investment Benefit to Cost Ratio drops slightly to 1.43

Includes $5M in ROA implementation costs

Page 25: SPP.org 1. Final Report: Reliability and Economic Assessments Stakeholder Meeting December 1, 2008 Austin, TX.

SPP.org 25

ETI Benefits Sensitivity – NO RMR Requirements

Page 26: SPP.org 1. Final Report: Reliability and Economic Assessments Stakeholder Meeting December 1, 2008 Austin, TX.

SPP.org 26

2012 Benefits to ETI if RMR Requirement RemovedETI Operational Benefits

Adjusted Production Cost in MM$ - (APC)

Status Quo - Cottonwood

in EIC

Integrated SPP/ETI Case - Cottonwood

in Eastern Interconnect -

No RMR Requirements

ETI Benefits - Cottonwood

in Eastern Interconnect -

No RMR Requirements

2012 2,336.21 2,173.67 162.54 1 209.98 188.66 21.31 2 174.16 155.40 18.77 3 186.52 167.30 19.21 4 175.97 156.77 19.20 5 191.15 173.90 17.25 6 202.72 193.40 9.32 7 227.63 221.28 6.35 8 228.14 223.94 4.20 9 197.61 186.02 11.59

10 192.89 180.71 12.18 11 156.56 143.99 12.58 12 192.88 182.31 10.57

Page 27: SPP.org 1. Final Report: Reliability and Economic Assessments Stakeholder Meeting December 1, 2008 Austin, TX.

SPP.org 27

Discussion of Findings – No RMR Requirement

• Benefits increase to $163 M, creating an incremental benefit of about $60 M

• This $60 M in incremental benefits would support about $333 M in potential projects Based on 18% carrying charge rate on transmission investment

Potential for future Economic Upgrade

There is no guarantee that this level of investment would be sufficient to relieve the remaining RMR requirements

Page 28: SPP.org 1. Final Report: Reliability and Economic Assessments Stakeholder Meeting December 1, 2008 Austin, TX.

SPP.org 28

Questions?

Page 29: SPP.org 1. Final Report: Reliability and Economic Assessments Stakeholder Meeting December 1, 2008 Austin, TX.

SPP.org 29

Detail Slides

Page 30: SPP.org 1. Final Report: Reliability and Economic Assessments Stakeholder Meeting December 1, 2008 Austin, TX.

SPP.org 30

2012 ETI Benefits Breakdown

Gen MWH Gen $Gen Cost - $/MWh

Purch MWH Purch Cost $

Purch Cost - $/MWh Sale MWH Sale Rev $

Sales Revenue -

$/MWh Benefits2012 3,461,447 404,061,106 116.73 -2,934,040 -237,067,800 80.80 -527,407 -64,359,021 122.03 102,634,286

1 584,633 68,573,567 117.29 -550,173 -51,334,735 93.31 -34,461 -4,825,091 140.02 12,413,7412 257,711 32,610,295 126.54 -248,583 -21,680,935 87.22 -9,129 -1,314,599 144.01 9,614,7623 436,419 44,589,306 102.17 -421,145 -31,326,310 74.38 -15,274 -2,068,576 135.43 11,194,4204 355,362 40,168,595 113.04 -354,140 -25,718,392 72.62 -1,221 -134,980 110.54 14,315,2225 337,433 37,629,680 111.52 -274,419 -20,564,155 74.94 -63,015 -6,501,816 103.18 10,563,7096 196,660 23,652,936 120.27 -130,197 -9,580,478 73.58 -66,462 -7,426,933 111.75 6,645,5257 174,574 23,557,281 134.94 -72,653 -6,695,495 92.16 -101,921 -12,024,652 117.98 4,837,1348 177,645 22,831,198 128.52 -90,478 -8,845,269 97.76 -87,167 -11,242,531 128.98 2,743,3979 274,870 30,491,316 110.93 -218,170 -16,468,768 75.49 -56,700 -6,636,008 117.04 7,386,540

10 172,741 22,967,024 132.96 -137,230 -10,588,263 77.16 -35,511 -4,024,079 113.32 8,354,68211 248,017 28,714,237 115.78 -214,861 -16,805,985 78.22 -33,156 -4,438,471 133.87 7,469,78112 245,382 28,275,672 115.23 -221,991 -17,459,015 78.65 -23,391 -3,721,284 159.09 7,095,372

ETI Benefits Breakdown - Cottonwood in EIC - With Reliability and Economic Transmission Upgrades

Page 31: SPP.org 1. Final Report: Reliability and Economic Assessments Stakeholder Meeting December 1, 2008 Austin, TX.

SPP.org 31

2012 ETI Benefits Breakdown

Gen MWH Gen $Gen Cost - $/MWh

Purch MWH Purch Cost $

Purch Cost - $/MWh Sale MWH Sale Rev $

Sales Revenue -

$/MWh Benefits2012 3,439,498 395,276,876 114.92 -3,310,541 -287,728,528 86.91 -128,957 -17,789,618 137.95 89,758,730

1 607,197 70,743,812 116.51 -579,214 -54,230,757 93.63 -27,983 -3,773,853 134.86 12,739,2022 264,373 32,838,565 124.21 -255,791 -22,716,208 88.81 -8,582 -1,208,339 140.80 8,914,0183 438,799 44,215,170 100.76 -427,902 -31,300,125 73.15 -10,898 -1,387,820 127.35 11,527,2254 391,365 43,194,221 110.37 -390,585 -29,822,447 76.35 -780 -86,047 110.27 13,285,7275 326,408 37,418,768 114.64 -321,851 -27,630,574 85.85 -4,557 -528,412 115.95 9,259,7826 197,894 22,634,070 114.37 -193,077 -17,940,629 92.92 -4,817 -607,471 126.11 4,085,9707 178,337 21,799,524 122.24 -173,204 -21,396,621 123.53 -5,133 -646,314 125.91 -243,4118 128,006 15,119,437 118.12 -122,813 -15,445,157 125.76 -5,193 -688,640 132.60 -1,014,3609 258,789 29,128,529 112.56 -252,909 -20,872,665 82.53 -5,880 -700,678 119.17 7,555,186

10 188,860 23,936,631 126.74 -175,238 -14,418,146 82.28 -13,622 -1,928,846 141.60 7,589,63911 225,661 27,204,776 120.56 -201,751 -15,539,812 77.02 -23,910 -3,543,179 148.19 8,121,78512 233,809 27,043,372 115.66 -216,207 -16,415,386 75.92 -17,602 -2,690,018 152.82 7,937,967

ETI Benefits Breakdown - Cottonwood in ERCOT - With Reliability and Economic Transmission Upgrades

Page 32: SPP.org 1. Final Report: Reliability and Economic Assessments Stakeholder Meeting December 1, 2008 Austin, TX.

SPP.org 32

Mak NagleManager, Technical Studies & Modeling(501)[email protected]

Wayne [email protected]