Spoil Management Sub Plan · Management Plan (CEMP) for the Hunter Expressway Alliance (HEA). The...
Transcript of Spoil Management Sub Plan · Management Plan (CEMP) for the Hunter Expressway Alliance (HEA). The...
Spoil Management Sub Plan Seahampton to Kurri Kurri Section
HEA-PL-GL-SMP-001-00-03
Rev Date Prepared by Reviewed by Approved by Remarks
1 Feb 2010 Tracey Doczy Howard Chemney Peter Chatburn
2 31 May 2010 Tracey Doczy Howard Chemney Peter Chatburn Updated to include
Agency, Council, RTA and
EMR review comments
3 14 July 2010 Erran
Woodward
Howard Chemney Peter Chatburn Updated to include
Department of Planning
comments
Hunter Expressway Alliance
SPOIL MANAGEMENT SUB PLAN
HEA-PL-GL-SMP-001-00-03 Page 2
DOCUMENT CONTROL
Document Type: Environmental Management Sub Plan Document No/Ref:
HEA-PL-GL-SMP-001-00-02
Title: Spoil Management Sub Plan
General
Description:
Provides management measures and mitigation strategies to be undertaken to mitigate the
potential impacts as they relate to pre-construction and construction phases of the project.
Document Path: S:\HEA\01 Environment\01_08 CEMP\Volume 2\Spoil\Final for Submission\HEA-PL-GL-
SMP-001-00-02.docx
Approval Name: Position: Signed / Approved: Date:
Document
Editor / Author
Tracey Doczy Environmental
Manager Construction
Review Howard Chemney Environment Manager
Design
Alliance Project
Director
Peter Chatburn Alliance Project
Director
Hunter Expressway Alliance
SPOIL MANAGEMENT SUB PLAN
HEA-PL-GL-SMP-001-00-03 Page 3
TABLE OF CONTENTS
1 INTRODUCTION ................................................................................................................................4
1.1 Purpose ...............................................................................................................................................4
1.2 Objectives ...........................................................................................................................................4
1.3 Conditions of Approval ........................................................................................................................4
2 LEGISLATIVE REQUIREMENTS AND GUIDELINES ......................................................................6
3 Spoil Management Overview ...........................................................................................................8
3.1 Spoil types ..........................................................................................................................................8
3.2 Spoil strategy ......................................................................................................................................9
3.3 Spoil generating activities ...................................................................................................................9
3.4 Volumes and sources of spoil .......................................................................................................... 10
3.5 Spoil classification ........................................................................................................................... 11
3.6 Locations of spoil disposal and off-site storage / re-use sites ......................................................... 12
3.7 Transportation of spoil ..................................................................................................................... 12
3.8 Storage of spoil ................................................................................................................................ 13
4 PERFORMANCE CRITERIA ........................................................................................................... 14
5 POTENTIAL IMPACTS ................................................................................................................... 15
6 MANAGEMENT MEASURES AND MITIGATION STRATEGIES .................................................. 16
7 MONITORING AND REPORTING .................................................................................................. 21
8 CORRECTIVE ACTION .................................................................................................................. 22
LIST OF TABLES
Table 1.1: Minister’s Condition of Approval requirements ...................................................................... 5
Table 2.1: Key legislation and guidelines ............................................................................................... 6
Table 3.1: Material quantities ............................................................................................................... 11
Table 3.2: Potential locations of spoil disposal / off-site storage / re-use areas .................................. 12
Table 5.1: Potential environmental impacts ......................................................................................... 15
Table 6.1: Management measures and mitigation strategies .............................................................. 16
Table 7.1: Monitoring and reporting requirements ............................................................................... 21
Hunter Expressway Alliance
SPOIL MANAGEMENT SUB PLAN
HEA-PL-GL-SMP-001-00-03 Page 4
1 INTRODUCTION
1.1 Purpose
This Spoil Management Sub Plan (SMP) forms part of the Construction Environmental Management Plan (CEMP) for the Hunter Expressway Alliance (HEA).
The purpose of the SMP is to:
• identify the environmental management issues associated with the sourcing, handling,
transportation, stockpiling, disposal and reuse of spoil material; and
• document and describe the systems and procedures developed to mitigate
environmental impacts.
This Sub Plan provides practical measures that will be put in place in order to minimise any detrimental impact on the surrounding environment resulting from spoil management during pre-construction, construction and post-construction phases of the project.
This Sub Plan is applicable to all HEA activities during the construction phase of the Project
While this Sub Plan provides overall guidance and direction for the management of spoil, Work Method Statements (WMS) and Environmental Construction Method Statements (ECMS) will be prepared to be used in site specific situations.
1.2 Objectives
The objectives of the Spoil Management Sub Plan are to:
• manage spoil generated during the Hunter Expressway Alliance Project in accordance
with preferred waste management hierarchy of avoidance, minimisation, reuse,
recycling and finally disposal;
• where possible ensure all clean and/or treated spoil shall be reused or recycled;
• Minimise off-site disposal of spoil;
• minimise the impact of erosion and sedimentation from construction activities
associated with the Project;
• ensure all sediment and erosion controls are implemented on site in accordance with
best practice environmental management as outlined in Managing Urban Stormwater -
Soils and Construction (Landcom 2004) including Volume 2D Main Roads Construction;
• provide an organised, integrated and systematic approach to effectively address spoil
management issues during the project; and
• provide staff with an increased level of understanding and awareness of spoil and fill
management issues.
1.3 Conditions of Approval
Relevant conditions applicable to spoil management required by the Conditions of Approval (CoA) are listed in Table 1.1 with a cross reference to where the condition is addressed in this Sub Plan or other project management documents. Condition 122 is the specific CoA to
Hunter Expressway Alliance
SPOIL MANAGEMENT SUB PLAN
HEA-PL-GL-SMP-001-00-03 Page 5
which this Sub Plan applies.
Table 1.1: Minister’s Condition of Approval requirements
CoA
No.
Minister’s Condition of Approval Sub Plan /
Document
Reference
122 The Proponent shall prepare a Spoil Management Sub Plan. The Sub Plan shall
identify how spoil would be handled, stockpiled, reused and disposed. The Sub
Plan shall be prepared:
i. in consultation with the EPA and the relevant Councils;
ii. prior to construction; and
iii. for all relevant sites.
This Sub Plan
123 All clean and/or treated spoil shall be reused or recycled where possible and
cost effective to do so. The Proponent shall ensure that spoil generated from
construction activities is maximised in preference to any import of fill.
This Sub Plan
129(e) (Ancillary facilities must) be separated from the nearest residences by at least
200 metres (or at least 250 metres for a temporary batching plant and stockpiling
sites).
This Sub Plan
Hunter Expressway Alliance
SPOIL MANAGEMENT SUB PLAN
HEA-PL-GL-SMP-001-00-03 Page 6
2 LEGISLATIVE REQUIREMENTS AND GUIDELINES
Key legislation relevant to spoil management is listed in Table 2.1.
Table 2.1: Key legislation and guidelines
Relevant key legislation
and guidelines Applicable to project
Protection of the
Environment Operations
Act, 1997 (POEO Act)
This Act provides for the control of polluting activities in NSW in order to prevent
pollution of the environment. Offences exist in relation to activities that cause
water, soil and air pollution. Soil, water and air pollution associated with
generation, handling and disposal of waste including spoil are controlled through
the CEMP and this Sub Plan.
The Act also requires notification to the DECCW or incidents likely to cause or
threaten material harm in accordance with Part 5.7 of the Act.
Protection of the
Environment Operations
(General) Regulation, 1998
Provides details on everyday implementation of the POEO Act to control pollution
of the environment including the following areas:
� identifies scheduled activities, premises, and licence
requirements, and situations where remedial notices
and orders can be issued;
� creates a framework for managing licence
requirements; and
� identifies appropriate regulatory authorities to
administer licences and pollution controls and issue
notices;
Applies to the management and disposal of waste, including spoil from the works.
Protection of the
Environment Operations
(Waste) Regulation, 2005
(and relevant gazetted
exemptions)
Provides for waste assessment and classification. It sets requirements for
handling, storage, transport and disposal of wastes including reporting
requirements.
Applies to disposal of spoil from the excavation works.
Exemptions are gazetted for certain waste types such as mulch. Exemptions will
need to be checked at the time of proposed disposal.
Waste Avoidance and
Resource Recovery Act,
2001
Promotes the waste management hierarchy (avoidance, resource recovery, and
disposal).
Applies to the management of spoil associated with excavation works on this
project.
Waste Classification
Guidelines 2008 (DECCW
publication)
Defines types of wastes, procedures for assessing waste, waste storage and
disposal requirements, record keeping and licence requirements.
Applies to the handling and disposal of spoil associated with excavation works on
this project.
Hunter Expressway Alliance
SPOIL MANAGEMENT SUB PLAN
HEA-PL-GL-SMP-001-00-03 Page 7
Contaminated Land
Management Act 1997
This Act regulates the discovery and management of contaminated land.
S60 of this Act requires that: notification be provided to DECCW if:
� Contamination exceeds guideline level on land
� Contamination enters or may enter neighbouring land and exceeds guideline level
� Contamination otherwise meets criteria in regulations
Hunter Expressway Alliance
SPOIL MANAGEMENT SUB PLAN
HEA-PL-GL-SMP-001-00-03 Page 8
3 SPOIL MANAGEMENT OVERVIEW
3.1 Spoil types
Spoil is defined as any earthen material that is surplus to requirements or unsuitable for re-use in fill and embankments (such as unsuitable rock and soil material) or material that is contaminated.
This plan has been prepared to facilitate the beneficial reuse of all material, ensuring that none is disposed off-site, except if unsuitable for reuse.
Fill is defined as earthen material excavated from one location along the corridor (for example, for a detention basin or cut excavations) and relocated elsewhere as compacted fill.
Cut and fill material will generally not be stockpiled, but will be removed from the excavation site and transported directly to the construction face for immediate reuse as compacted fill. Unsuitable excavated material will primarily be transported to identified locations within the road corridor for reuse or, if space is not available, will be stored temporarily off-site for re-use later.
Select material is defined as earthen material of comparatively higher quality, necessary for
engineered backfill and incorporation in upper earthworks layers as part of the overall
pavement design. Typically on the HEA project this will include high strength sandstone and
low/medium strength claystones, siltstones and sandstones.
Wherever possible, select material will be sourced on site, and stockpiled as necessary until
incorporated in the works. However, preliminary investigations suggest that a considerable
proportion of the select material required for the project will need to be sourced from off site.
Unsuitable (non-contaminated) material on the HEA project is generally composed of silty, sandy, gravely and organic clays; sandy silts; clayey, silty and gravely sands and carbonaceous rock.
This material will be reused on the project in the following ways:
• widen embankments where possible;
• land contouring;
• landscaping mounds;
• landscape treatments; and
• noise mounds (if required).
Topsoil will be stripped and recovered for reuse in landscaping and revegetation. On
average, the top 100mm of topsoil will be collected for future use.
Hunter Expressway Alliance
SPOIL MANAGEMENT SUB PLAN
HEA-PL-GL-SMP-001-00-03 Page 9
3.2 Spoil strategy
The following provides an overview of the HEA strategy for achieving the key spoil management objectives:
• Minimise the amount of spoil generated – this requirement will be achieved by
ensuring that the design minimises the volume of spoil generated from excavation (a
key driver for this is the need to minimise our construction footprint in order to reduce
clearing). It should be noted that the minimisation of spoil generation is a standard
process in developing designs and planning construction activities as there are
significant financial savings in minimising spoil generation and management. .
• Classify the spoil generated using recognised guidelines and its geotechnical
characteristics – The Waste Classification Guidelines (DECCW Apr 08) are the
primary guidelines for the classification of spoil and other waste materials in relation to
contamination. The geotechnical characteristics of spoil are also important to consider
as it will determine the potential engineering uses of spoil.
• Maximise the beneficial reuse of spoil on site based on its classification (both
contamination category and geotechnical characteristics) – Some of the spoil
generated is expected to be able to be reused on site and will be suitable as general fill
across the site. Some spoil may be unsuitable, however this maybe used for inclusion in
capped landscaping mounds or features. Some spoil material, mainly due to its
geotechnical characteristics will not be suitable for reuse.
• Maximise the beneficial reuse of spoil off site based on its classification (both
contamination category and geotechnical characteristics) – Whilst it is HEA’s
intention to try and re-use all material on-site some of the spoil generated may be able
to be reused off site on other projects. Further investigation into the needs of the
numerous nearby mine sites will continue in this regard. Some spoil material due to its
geotechnical characteristics will not be suitable for reuse.
• Dispose of spoil off site based on its contamination classification - spoil unable to
be reused on site or off site would be disposed of at a facility that has the appropriate
development approval and Environment Protection Licence to receive and store the
relevant waste classification of the spoil.
• Manage the excavation, storage, transport reuse and disposal of spoil to
minimise impacts and meet other environmental requirements – this includes
implementing mitigation measures to manage potential impacts on traffic and soil and
water, dust generation and contamination of spoil (e.g. onsite - dust control, erosion and
sedimentation controls, monitoring and validation for contamination and Potential Acid
Sulphate Soils, offsite – tracking and monitor spoil/fill movements and quality
(contamination), haulage routes, impacts on public safety and roads and public amenity,
noise impacts and required compliance requirements (i.e. approvals and
consents/licences).
Note: The detailed spoil and materials management strategy will be addressed in both the Earthworks Management Plan and the Materials Management Plan for the Project.
3.3 Spoil generating activities
Spoil generated by construction will primarily come from excavation works. The spoil is expected to vary in content with silty, sandy, gravely and organic clays; sandy silts; clayey, silty and gravely sands and carbonaceous rock.
Hunter Expressway Alliance
SPOIL MANAGEMENT SUB PLAN
HEA-PL-GL-SMP-001-00-03 Page 10
The activities associated with the generation and management of spoil and fill materials are:
• clearing of vegetation;
• selection of material;
• clearing of topsoil;
• excavation of earthen material;
• blasting of earthen material (if required);
• transport of earthen material;
• storage/stockpiling of spoil, topsoil and mulch; and
• reuse of spoil, topsoil and mulch.
There is a small possibility that acid sulfate soils may be encountered during construction work. Management and mitigation measures of potential acid sulfate soils are presented in the Acid Sulfate Soil Management Strategy (Refer to Appendix C of the Soil and Water Management Sub Plan).
3.4 Volumes and sources of spoil
Overall approximately 2,172,994 m³ of material will be won on-site from excavation works over the life of the Project. This will be made up of select material, un-suitable and topsoil.
Approximately 370,918 m³ of material will require importing to site to be used as select material for pavement design, drainage blanket material and as backfill for retaining walls. It should be noted that this figure does not include the aggregate required for the supply of concrete for the batching plant which, based on current estimates, will require 100,000 tonnes of aggregate and 60,000 tonnes of sand. The source location for this material is currently unknown but will likely be sourced from local quarries..
Given the volume of imported material required in excess of that won on-site, numerous local quarries will be engaged to supply the required material. At this stage it is not known which quarries will be used as negotiations are currently taking place.
Refer to Table 3.1 for details on material quantities and Table 3.2 for the location of potential spoil disposal and off-site storage / re-use sites.
As can be seen from Table 3.1, approximately 2,115,833 m³ of material will be used as fill for pavement and embankment construction. Approximately 293,079 m³ of spoil will be produced which may require off-site disposal or re-use.
Hunter Expressway Alliance
SPOIL MANAGEMENT SUB PLAN
HEA-PL-GL-SMP-001-00-03 Page 11
Table 3.1: Material quantities
LOCATION
TOTAL VOLUME OF MATERIAL REQUIRED TOTAL VOLUME OF
MATERIAL PLACED SURPLUS
Won on-site Import
Topsoil Select / Un-
Suitable
Select and
Verge
Drainage
Blanket
RSW
Backfill
Embankment
Construction
Select and
Verge Spoil
Units m3 m
3 m
3 m
3 m
3 m
3 m
3 m
3
F3 Interchange Included 114,502 8,337 4,358 11,326 115,128 8,337 44,760
Main C/Way 135,000 1,810,822 158,682 83,386 79,030 1,599,457 158,682 248,319
Stockrington
Rd
Included 6,640 1,087 0 0 2,658 1,087 0
Buchanan
Rest Area Included 1,761 5,961 0 0 110,100 5,961 0
Buchanan
Interchange
Included 100,071 9,958 6,150 0 65,560 9,958 0
Avery's Lane Included 186 924 0 0 33,000 924 0
Shearmans
Lane
Included 4,012 1,219 500 0 3,762 1,219 0
Totals 135,000 2,037,994 186,168 94,394 90,356 1,929,665 186,168 293,079
3.5 Spoil classification
The classification of spoil will be undertaken in accordance with the Waste Classification Guideline, 2008 including the implementation of a spoil sampling and analysis program during excavations. This will determine the type of spoil:
Virgin Excavated Natural Material (VENM): DECCW places no specific restrictions on reuse options of VENM
Clean fill (e.g. Inert): If deemed suitable (i.e. waste classification and poses no environmental or OH&S risk) can be used as fill on site. Topsoils are suitable for reuse in rehabilitation works
Potentially contaminated material: Requires management or disposal in accordance with EPA guidelines
Hunter Expressway Alliance
SPOIL MANAGEMENT SUB PLAN
HEA-PL-GL-SMP-001-00-03 Page 12
3.6 Locations of spoil disposal and off-site storage / re-use sites
Potential spoil disposal / off-site storage sites are detailed in Table 3.2.
Table 3.2: Potential locations of spoil disposal / off-site storage / re-use areas
Name Location/ chainage
Off-site storage / Re-Use
The Brick Pit1 Ch 5300
abandoned quarry off the alignment
Buchanan Rest Areas Ch 7600 and 7800
Daracon Quarry Operational quarry adjacent to site
RTA owned properties Various properties close to alignment
Temp Water Quality Basins Various chainages along alignment
Spoil disposal / landfill sites
Cessnock City Council Waste Management Centre2
Old Maitland Road, Cessnock
Awaba Waste Management Facility2
Lake Macquarie City Council 60 Wilton Road Awaba
1Negotiations are continuing with Coal & Allied re: the use of the Brick Pit as a disposal site with the
potential for using surplus spoil to rehabilitate the site. 2Both landfill sites are licensed to accept general solid waste (non-putrescible)
Prior to any permanent disposal of spoil at these locations (or others yet to be determined), a review of the CoA, associated approvals and environmental documentation shall be carried out by the HEA Environment Team and additional approvals sought when required.
3.7 Transportation of spoil
40T off-road dump trucks and on-road spoil trucks will be used to move spoil material between sites in the construction corridor. Wherever possible, material is to be moved internally along the construction corridor.
Where the construction programme necessitates movement of material prior to access along the construction corridor becoming available, material will be hauled on public roads by road trucks, in accordance with the project Traffic Management and OHS Management Plans.
Haulage by road trucks will be along the Project corridor wherever possible. In instances where haulage of cut material is required by road, exit from and entry to the project will be via specific Project access points, using designated haul routes as detailed in the project Traffic Management Plan.
Hunter Expressway Alliance
SPOIL MANAGEMENT SUB PLAN
HEA-PL-GL-SMP-001-00-03 Page 13
3.8 Storage of spoil
Material which can be re-used on-site but which cannot be directly re-placed will be stored in designated stockpile areas on-site. Where space is restricted material may require temporary storage off-site prior to re-use on-site. Temporary spoil storage locations are detailed in Table 3.2.
All spoil material requiring disposal will be classified according to the Waste Classification Guidelines 2008 (DECCW publication)
The Construction Environmental Manager and Project Engineer will identify storage areas prior to commencement of construction in each area primarily to ensure that disturbance to local residents is minimised, local amenity is maintained, and to protect receiving waters from potential runoff.
Temporary stockpile areas for the Project will be located as detailed in Table 6.1.
Erosion and Sediment Control Plans prepared for specific areas will contain details on the locations and control measures for stockpiling. The relevant ECMS will also provide general measures for the location and management of stockpiles.
Hunter Expressway Alliance
SPOIL MANAGEMENT SUB PLAN
HEA-PL-GL-SMP-001-00-03 Page 14
4 PERFORMANCE CRITERIA
The performance criteria for the Spoil Management Sub Plan are to ensure:
• All clean and/or treated spoil shall be reused or recycled to the greatest extent where
possible and cost effective to do so (CoA 123).
• Spoil generated from construction activities is maximised in preference to any import of
fill (CoA 123).
• Erosion of stockpiles is minimised and release of sediment into any waterway is
avoided;
• Any weed invasion of stockpiled materials is managed;
• Dust generated from stockpiles is minimised;
• Stockpiled material is reused wherever possible rather than disposed of offsite;
• Staff are aware of the requirements of relevant sections of documents to be adhered to
including: the CEMP, any associated Environmental Construction Method Statements
(ECMS), erosion and sediment control plans (ESCP) and all other statutory
requirements to be met whilst on site; and
• Effective communication is maintained with statutory authorities and all statutory
requirements are carried out to control impacts on the environment and prevent
pollution.
Hunter Expressway Alliance
SPOIL MANAGEMENT SUB PLAN
HEA-PL-GL-SMP-001-00-03 Page 15
5 POTENTIAL IMPACTS
Environmental aspects and impacts associated with spoil management have been identified by reviewing the information and studies related to the project. These are summarised in Table 5.1.
Table 5.1: Potential environmental impacts
Category Environmental aspect Environmental impact
Spoil disposal � Vegetation clearing/disturbance
� Removal, stockpiling and re-spreading of
road construction soils – general earthwork
activities
� Site establishment - site compounds, access
points and access routes
� Adjustments of existing public utilities.
� Operation of site compound
� Haulage of spoil
� Blasting
� Water pollution due to sediment runoff from
spoil excavation and excess spoil storage.
� Weed infestation from dispersion of seeds,
etc. during clearing and access upgrading
activities.
� Water and air pollution due to dust
generated from stockpiles.
� Flora and fauna damage due to sediment
runoff from spoil excavation.
� Water, soil and air pollution from
inappropriate storage, handling and disposal
of spoil.
� Mud-tracking during haulage operations.
� Noise & vibration impacts from blasting
Hunter Expressway Alliance
SPOIL MANAGEMENT SUB PLAN
HEA-PL-GL-SMP-001-00-03 Page 16
6 MANAGEMENT MEASURES AND MITIGATION STRATEGIES
Table 6.1: Management measures and mitigation strategies
Management measures and mitigation strategies Responsibility Source of
requirement
Pre-construction
� This Spoil Management Sub Plan has been/is being prepared in
consultation with relevant Government Departments, and relevant
Councils.
Environment
Manager
MCoA 122
� This Spoil Management Sub Plan is to be reviewed and certified by the
EMR, prior to seeking approval from DoP before construction
commences.
Environment
Manager MCoA 21
� Education of site personnel as to the requirements for spoil control
measures will be implemented and maintained on site. This shall be
undertaken via the project induction and toolbox talks and ECMS.
Environment
Manager/
Superintendent
� Detailed soil testing will be undertaken in areas where acid-sulfate soils
may occur. Acid Sulfate Soil Management Strategy (Appendix C of the
SWMSP) will be prepared for excavation in acid-sulfate soils.
Environment
Manager
Reps Report Vol
1 - 139
� Environmental Construction Method Statements providing detailed
information on work method for managing spoil associated with
excavation works shall be developed for critical construction activities.
Refer to Appendix H of Volume 1 of the CEMP.
Environment
Manager
Construction
Stockpile management
� Stockpiles must:
o generally be located within the road reserve or at sites specifically
identified for compound, stockpiling and/or batching plant location;
o be located on flat, grassed area where possible. Stockpiles are not
to be placed on native vegetation;
o be covered where practical to do so;
o be located more than 2 metres from existing native vegetation,
concentrated water flow, roads, gutters, drains and other restricted
areas including residential areas, places of public access and site
buildings;
o generally be located away from steep slopes (note: temp stockpiles
of vegetation may be required on steep slopes during clearing
operations);
Senior Project
Engineer/
Superintendent
Hunter Expressway Alliance
SPOIL MANAGEMENT SUB PLAN
HEA-PL-GL-SMP-001-00-03 Page 17
Management measures and mitigation strategies Responsibility Source of
requirement
o be located away from the drip line of trees;
o be located at least 100 metres from any creeks or water bodies
unless adequate erosion and sedimentation controls are installed;
o be located on sites above the 20 ARI flood level;
o be located on sites that do not cause exceedance of the maximum
native vegetation clearing limit specified for the project;
o be constructed as low, flat elongated mounds where possible;
o have sediment fences down-slope and earth banks upslope to
divert water and/or use sandbags to divert run-off from disturbed
areas;
o sediment and erosion controls to be used shall be in accordance
with the requirements of Managing Urban Stormwater - Soils and
Construction (including Volume 2D) published by Landcom (2004);
o be accessible for the purpose of dust suppression (e.g. application
of water sprays, covers, binding agents etc).
� Stockpile must be located no less than 250 meters from the nearest
residence CoA 129
� Any long-term stored topsoil stockpiles are to be protected from water
and wind erosion by stabilising with hydro-seed or by covering with a
geo-textile fabric until required.
Senior Project
Engineer/
Superintendent
Spoil Management
� Separate all spoil and segregate into:
o Virgin Excavated Natural Material (VENM);
o acid sulfate soils;
o construction materials;
o hazardous and non-hazardous wastes (i.e. contaminated/ non-
contaminated soil, etc.);
o waste states (liquids, solid); and
o waste types (flammables, corrosives, etc.)
o in accordance with Waste Classification Guidelines 2008 (DECCW
publication).
Senior Project
Engineer/
Superintendent
� Maximise the reuse of suitable select material generated from
construction, particularly material classified as Virgin Excavated Natural
Material (VENM), in preference to importing fill or disposal to landfill.
Construction
Manager/
Environment
Hunter Expressway Alliance
SPOIL MANAGEMENT SUB PLAN
HEA-PL-GL-SMP-001-00-03 Page 18
Management measures and mitigation strategies Responsibility Source of
requirement
� Maximise reuse of un-suitable spoil as backfill materials in preference to
disposal to landfill.
� All material excavated from the construction must be re-used or recycled
where suitable and if cost-effective to do so. Re-use of material
generated from construction is to be maximised in preference to any
import of fill.
� Unsuitable fill material is to be used for non-structural purposes
(including landscaping) on the project.
Manager
� Ensure all spoil/waste material removed from the site is assessed and
classified in accordance with the Waste Classification Guidelines 2008
(DECCW publication).
� Ensure that any spoil transported from the site is taken to a place that
can lawfully accept it.
� Use appropriately licensed (DECCW) waste transporters for the
transportation of spoil to off site locations.
Senior Project
Engineer/
Environment
Manager
� Ensure that weed infested topsoil, as identified by a qualified ecologist,
is not used in the rehabilitation works unless it is treated and sterilised in
an appropriate manner.
Superintendent MCoA 63
� Cover all trucks transporting spoil to off site locations and check tailgates
are secured before leaving the site. Superintendent
Erosion and sedimentation
� Ensure all erosion and sedimentation controls are in place prior to the
placement of spoil in stockpiles in accordance with the Soil and Water
Management Sub Plan.
� Erosion and sediment controls must include:
o diversion banks or drains on the up gradient sides to divert surface
water around the stockpiling area;
o sediment fencing, straw bales, silt traps and barriers for drains and
pits on the down gradient sides;
o turfing of embankments.
Construction
Manager/
Environment
Manager/
Superintendent
Refer to Soil
and Water
Management
Sub Plan.
Dust
� Ensure dust associated with spoil generation, handling and disposal or
reuse is managed in accordance with mitigation measures outlined in
the Air Quality Management Sub Plan. Project Manager
Refer to Air
Quality
Management
Sub Plan.
Hunter Expressway Alliance
SPOIL MANAGEMENT SUB PLAN
HEA-PL-GL-SMP-001-00-03 Page 19
Management measures and mitigation strategies Responsibility Source of
requirement
Waste
� Ensure waste associated with spoil generation, handling and disposal or
reuse is managed in accordance with mitigation measures outlined in
the Waste Management & Re-Use Sub Plan.
� Store any hazardous and liquid wastes in a covered, labelled and secure
compound with an impermeable floor and appropriate bund walls.
Project Manager
Refer to Waste
Management &
Re-Use Sub
Plan.
Traffic
� Designated haulage and light vehicles routes shall be upgraded (or
established if necessary), mapped and communicated to staff prior to
the commencement of construction actions.
� Ensure traffic associated with spoil generation, handling and disposal or
reuse is managed in accordance with mitigation measures outlined in
the Traffic Management Plan.
� Where significant volumes of fill material need to be transferred between
sections, this transfer will not coincide with peaks in delivery of
construction materials.
� If roads managed by the Local Council are used for haulage operations
both pre and post dilapidation surveys shall be undertaken.
Project Manager/
Senior Project
Engineer
Refer to Traffic
Management
Plan.
Noise
� Ensure noise and vibration associated with spoil generation, handling
and disposal or reuse is managed in accordance with mitigation
measures outlined in the Noise and Vibration Management Sub Plan.
� Consideration will be given to the use of unsuitable fill material as
temporary or permanent noise mounds.
Construction
Manager
Refer to Noise
and Vibration
Management
Sub Plan.
Acid Sulfate soils
� If potential acid sulfate soils are identified and avoidance is not possible,
soils will be managed and disposed in accordance with the Acid
Sulphate Soil Manual (Acid Sulphate Soil Management Advisory
Committee, 1998) and the Acid Sulfate Soil Management Strategy
(Appendix C of the SWMSP).
Construction
Manager/
Environment
Manager
Refer to Acid
Sulfate Soil
Management
Strategy
(Appendix C of
the SWMSP).
� Acid sulfate soils will be classified in reference to the Waste
Classification Guidelines, Part 4: Acid Sulphate Soils (DECCW 2008) Construction
Manager/
Environment
Manager
Hunter Expressway Alliance
SPOIL MANAGEMENT SUB PLAN
HEA-PL-GL-SMP-001-00-03 Page 20
Management measures and mitigation strategies Responsibility Source of
requirement
Contaminated materials
� If suspected contaminated materials are encountered during
construction, work will stop at the site until the material has been
assessed and removed, or stabilised, in accordance with the Waste
Classification Guidelines 2008 (DECCW publication).
� If contaminated materials are uncovered, notification to DECCW shall be
undertaken in accordance with s60 of the Contaminated land
Management Act.
Construction
Manager/
Environment
Manager
Post-construction
� All exposed areas are to be stabilised (that is, compacted, sealed or
vegetated) as soon as practicable following completion of works.
� All exposed areas are to be progressively rehabilitated if possible in
accordance with Flora and Fauna Management Sub Plan and
Landscape Management Plan.
Senior Project
Engineer
Refer to Flora
and Fauna
Management
Sub Plan and
Landscape
Management
Plan
� Erosion and sediment control devices are to be removed once work
areas have been rehabilitated. Superintendent
� All wastes are to be removed from the site during the construction phase
or at the completion of the project. Waste removed from site shall be
removed in a lawful manner.
Superintendent/
Environment
Manager
Hunter Expressway Alliance
SPOIL MANAGEMENT SUB PLAN
HEA-PL-GL-SMP-001-00-03 Page 21
7 MONITORING AND REPORTING
Table 7.1: Monitoring and reporting requirements
Monitoring and reporting requirements Responsibility Source of
requirement
Pre-construction
� Confirm appropriate environmental and planning approvals
exist for sites identified for spoil reuse, recycling, storage
and/or disposal.
Environment Manager/
Construction Manager
� Check soil sedimentation control structures are in place
before construction activities commence. Senior Project Engineer/
Superintendent
Construction
� Monitor for actual or potential acid sulfate soils on excavated
material from below a surface elevation of 5 m AHD. Senior Project Engineer /
Superintendent
� Undertake weekly inspections and maintenance of erosion
and sediment controls around stockpiles and immediately
following sever storm conditions such as high winds, heavy
and /or prolonged rain events.
Environment Manager
� Maintain spoil and waste management records, including:
o haulage dockets;
o daily output records;
o daily haulage log sheet per work site;
o inspection records;
o weighbridge (site based or off site facility) records; and
o completed Section 143 forms (POEO ACT 1997) for spoil
transported off-site.
Senior Project Engineer
Post-construction
� Ensure sediment and erosion controls are removed on
completion of the rehabilitation works. Environment Manager/
Superintendent
� Ensure all spoil is either re-used, recycled or disposed of in a
lawful manner after completion of works. Environment Manager/
Senior Project Engineer
Hunter Expressway Alliance
SPOIL MANAGEMENT SUB PLAN
HEA-PL-GL-SMP-001-00-03 Page 22
8 CORRECTIVE ACTION
Possible non-conformances with this Sub Plan include non-compliance with the management measures and mitigation strategies outlined in Section 5.
All incidents and non-conformances are to be reported and investigated and corrected in accordance with Sections 4.6 of the Construction Environmental Management Plan (HEA-PL-GL-ENV-001-0) to ensure effective spoil management practices at all times.
Specific corrective action items for the Spoil Management Sub Plan are outlined below:
• sediment controls not effectively maintained and reinstatement or remedial action
required; and
• release of sediment laden water occurs, an incident report is submitted and remedial
action required.
This management plan will be reviewed during the construction period based on results from monitoring, observations, non-conformance or complaints. The review will allow adjustments to occur to the plan if they are found to be beneficial, or if measures need adjusting. All project staff will be notified of changes made to this Sub Plan.