Spm unit iii-risk-intro
-
Upload
kanchana-devi -
Category
Engineering
-
view
285 -
download
0
Transcript of Spm unit iii-risk-intro
SPM-UNIT IIIRISK MANAGEMENT
Prof. Kanchana Devi
Prof. Kanchana Devi
2
Introduction An uncertain event or condition that, if it
occurs, has a positive or negative effect on a project’s objectives.
PRINCE2: The Chance of exposure to the adverse
consequences of future events
PRINCE PRojects IN Controlled Environment
Prof. Kanchana Devi
3
The key elements of risk
It relates to future Cost underestimation, New Technology
difficult to work. It involves cause and effect
Cost Over-run, Use of untrained staff, Poor Specification
Prof. Kanchana Devi
4
Socio-technical Model of Risk
Kalle Lyytinen and his Colleagues proposed a diagrammatic representation
Actors
TechnologyStructure
Tasks
Prof. Kanchana Devi
5
Risk Framework Actors : refers to all the people involved
in the development of the application in the question
Risk: High staff turn-over Technology: encompasses both the
technology used to implement the application and that embedded in the delivered products
Risk: Appropriateness of the technologies and possible faults within them
Prof. Kanchana Devi
6
…… Structure: Describes the management
structures and systems including those affecting planning and control.
Risk: Some implementation might need user participation in some tasks(not allotted)
Tasks: relates to the work planned Risk: Complexity of work might lead to delay
Prof. Kanchana Devi
7
A framework for dealing with Risk
Planning for risk includes Risk Identification Risk Analysis and Prioritization Risk Planning Risk Monitoring
Prof. Kanchana Devi
8
Risk Identification There are two main approaches:
Checklists Brain-stroming
Prof. Kanchana Devi
9
Checklists Checklists are simply lists of the risks
that have been found to occur regularly in software development projects.
Risk Risk Reduction TechniquesPersonnel shortfalls Staffing with top talent, job
matching, team building, training and career development…
Unrealistic time and Cost Estimates
Multiple Estimation techniques, Design to cost, Incremental development…
Developing the wrong software functions
Improved software evaluation, Formal Specification Methods…
Developing the wrong user interface
Prototyping, Task Analysis, User Involvement.
Gold Plating Requirements Scrubbing, Prototyping, Cost-benefit analysis…
Prof. Kanchana Devi
10
Brainstorming Stakeholders are brought together,
preliminary and plans are drafted Identifying the solution using the
individual knowledge.
Prof. Kanchana Devi
11
Risk Assessment A common problem in risk identification
is that a list of risks is potentially endless.
Estimating the risk exposure for each risk using the formula:
Risk Exposure = (Potential Damage)* (Probability of Occurrence)
Prof. Kanchana Devi
12
Example: Problem A project depended on a data centre
vulnerable to fire. It might be estimated that if a fire occurred a new computer configuration could be established for $500,000. It might also be estimated that a computer is located there is a 1 in 1000 chance of a fire actually happening, that is a probability of 0.001.
Prof. Kanchana Devi
13
Solution: By using the formula:
Risk Exposure= $500,000*0.001= $500
Risk Exposure = (Potential Damage)* (Probability of Occurrence)
Prof. Kanchana Devi
14
Risk Exposure Assessment Ref Hazard Likelihoo
dImpac
tRisk
R1 Changes to Requirement Specification during coding
8 8 64
R2 Specification Task longer than expected
3 7 21
R3 Significant staff sickness affecting critical path activities
5 7 35
R4 Significant staff sickness affecting non-critical path activities
10 3 30
R5 Module coding takes longer than expected
4 5 20
R6 Module testing demonstrates errors or deficiencies in design
4 8 32
H
S
M
S
H
S
Prof. Kanchana Devi
15
Risk Probability and Associated range valuesProbability Level RangeHigh Greater than 50% Chance of happeningSignificant 30-50% Chance of happeningModerate 10-29% Chance of happeningLow Less than 10% Chance of happening
Impact on Cost and Associated range valuesProbability Level RangeHigh More than 30% above Budgeted ExpenditureSignificant 20 to 29% above Budgeted ExpenditureModerate 10 to 19% above Budgeted ExpenditureLow Within 10% of Budgeted Expenditure
Prof. Kanchana Devi
16
Impact MatrixR6 R1
R2,R3,R5
R4
High
Significant
Moderate
Low
Low Moderate Significant
High
Probability
Tolerance Line
Prof. Kanchana Devi
17
Risk Planning After identifying the risks and priorities Task is to deal with them
Risk Acceptance Risk Avoidance Risk Reduction & Mitigation Risk Transfer
Prof. Kanchana Devi
18
Risk Management Eg: Staff absence through illness. “Contingency Plan”
Prof. Kanchana Devi
19
Risk Reduction Actions The risk reduction action can be assessed by
calculating the “Risk Reduction Leverage”(RRL)
RE Risk Exposure If RRL = 1.00 indicates the reduction in the
exposure is greater than its cost
RRL= (RE before-RE after)/(Cost of risk reduction)
Prof. Kanchana Devi
20
Example: An unrealistic example, it might cost
$200,000 to replace a hardware configuration used to develop a software application. There is a 1% chance of fire. The risk exposure would be 1% of $200000, that is $2000. Installing fire alarms at a cost of $500 would reduce the chance of fire to 0.5%. The new risk exposure would be $1000, a reduction of $1000 on previous exposure. Calculate the RRL.
Prof. Kanchana Devi
21
Solution: RRL = (2000-1000)/500
= 2.0=>So the action taken is worthwhile.
Prof. Kanchana Devi
22
Risk RegisterRisk Record
Risk DescriptionImpact DescriptionRecommended Risk MitigationProbability/ Impact Values
Incident/Action History
Risk Id Risk Title
Owner Date Raised Status
Probability Impact
Cost Duration QualityPre-mitigation
Post-mitigation
Date Incident/Action Actor Outcome/Comment