Spm ap-network model-

32
SPM-UNIT II ACTIVITY PLANNING Prof. Kanchana Devi

Transcript of Spm ap-network model-

Page 1: Spm ap-network model-

SPM-UNIT II

ACTIVITY PLANNING

Prof. Kanchana Devi

Page 2: Spm ap-network model-

Network Planning Models

Prof. Kanchana Devi

2

Scheduling techniques model the project’s activ ities and

their relationships as a “Network”.

In network time flows from left to right

These techniques were developed in 1950’s

There are two best techniques: CPM (Critical Path Method)

PERT (Program Evaluation Review Technique)

Both uses an “activity-on-arrow” approach

Activities are drawn as arrows joining circles, or nodes

Which show the start and completion time of the activities

Page 3: Spm ap-network model-

Precedence Network

Prof. Kanchana Devi

3

Recently used , Popular one

It uses “activity-on-node” networks

Where activities are represented as nodes

Links between the nodes are represented as

sequencing requirements.

Page 4: Spm ap-network model-

Formulating a Network Model

Prof. Kanchana Devi

4

First stage:

Representing the activities and their

relationships as graph.

In “Activity-on-node”

Representing the activities as nodes(boxes) and

the lines between nodes represent the

dependencies.

Page 5: Spm ap-network model-

Rules: Constructing Precedence

Network

Prof. Kanchana Devi

5

A project network should have only one start node

A project network should have only one end node

A node has a duration

Links normally have no duration

Precedents are the immediate preceding activities

Time moves from left to right

A network may not contain loops

A network should not contain dangles

Page 6: Spm ap-network model-

Fragment of precedence Network

Prof. Kanchana Devi

6

Install Program

Test

Data

Take-on

Code

Page 7: Spm ap-network model-

A loop represents an impossible

sequence

Prof. Kanchana Devi

7

Code

Program

Release

Program

Test

Program

Diagnose

Errors

Correct

Errors

Page 8: Spm ap-network model-

A Dangle

Prof. Kanchana Devi

8

Design

Program

Install

Program Test Program

Code

Program

Write User

Manual

Page 9: Spm ap-network model-

Resolving the Dangle

Prof. Kanchana Devi

9

Design

Program

Install

Program

Test

Program

Code

Program

Write

User

Manual

Sign-Off

Page 10: Spm ap-network model-

Representing Lagged Activities

Prof. Kanchana Devi

10

Undertake two activities in parallel as there

is a lag between two.

Activities are lagged because a stage in one

activity must be completed before the other

may proceed.

Show each stage as separate activity.

Page 11: Spm ap-network model-

Adding Time Dimension

Prof. Kanchana Devi

11

Each activity have an estimate of its duration.

Forward pass – Earliest dates at which

activities may commence and project be

completed.

Backward pass – Latest start dates for

activities and critical path.

Page 12: Spm ap-network model-

Project Specification

Prof. Kanchana Devi

12

Page 13: Spm ap-network model-

Project Activity Network

Prof. Kanchana Devi

13

Page 14: Spm ap-network model-

Project Activity Network

represented as CPM Network

Prof. Kanchana Devi

14

Page 15: Spm ap-network model-

Dummy activities 15

When two paths within a network have a

common event to occur.

It is incorrect to require both hardware

specification and data structure design

Page 16: Spm ap-network model-

Using Dummy Activities

Prof. Kanchana Devi

16

Page 17: Spm ap-network model-

…….

Prof. Kanchana Devi

17

Dummy activities shown as dotted lines have

a zero duration and use no resources.

Use of dummy activity where two activities

share the same start and end nodes makes it

easier to distinguish activity end points.

Page 18: Spm ap-network model-

Forward Pass

Prof. Kanchana Devi

18

Activity Duration

(Weeks)

Earliest Start

Date (Weeks)

Earliest Finish

Date(Weeks)

A 6 0 6

B 4 0 4

C 3 6 9

D 4 4 8

E 3 4 7

F 10 0 10

G 3 10 13

H 2 9 11

Page 19: Spm ap-network model-

CPM Network

Prof. Kanchana Devi

19

Page 20: Spm ap-network model-

A CPM Network after forward

pass

Prof. Kanchana Devi

20

Page 21: Spm ap-network model-

Activity table for forward pass

Prof. Kanchana Devi

21

Activity Duration

(weeks)

Earliest

Start

Date

Latest

Start

Date

Earliest

Finish

Date

Latest

Finish

Date

Total

Float

A 6 0 6

B 4 0 4

C 3 6 9

D 4 4 8

E 3 4 7

F 10 0 10

G 3 10 13

H 2 9 11

Page 22: Spm ap-network model-

Backward Pass

Prof. Kanchana Devi

22

Page 23: Spm ap-network model-

CPM Network after the backward

pass

Prof. Kanchana Devi

23

Page 24: Spm ap-network model-

Identifying the Critical Path

Prof. Kanchana Devi

24

Any delay on the critical path will delay the

project.

Difference between earliest and latest date

for an event is known as slack.

Event with slack of zero is critical as any

delay in achieving that event will delay the

completion date of the project.

Page 25: Spm ap-network model-

Critical Path

Prof. Kanchana Devi

25

Event

Number

Latest

Date

Earliest

Date

Slack

Page 26: Spm ap-network model-

Activity Float

Prof. Kanchana Devi

26

As events have slack, activities possess float.

Total float is the difference between earliest

start and latest start ( or difference between

earliest finish and latest finish)

Page 27: Spm ap-network model-

Activity Schedule showing total

float for each activity

Prof. Kanchana Devi

27

Page 28: Spm ap-network model-

Activity Schedule

Prof. Kanchana Devi

28

Actvity Name Time Actvity Name Time

1-2 A 4 5-6 G 4

1-3 B 1 5-7 H 8

2-4 C 1 6-8 I 1

3-4 D 1 7-8 J 2

3-5 E 6 8-10 K 5

4-9 F 5 9-10 L 7

Page 29: Spm ap-network model-

Activity Network Diagram

Prof. Kanchana Devi

29

1

2

3 5

4

7

6

8

10 9

Page 30: Spm ap-network model-

Solution

Prof. Kanchana Devi

30

Activity Activity

Name

Normal

Time

E.S E.F L.S L.F Total

Float

1-2 A 4 0 4 5 9 5

1-3 B 1 0 1 0 1 0

2-4 C 1 4 5 9 10 5

3-4 D 1 1 2 9 10 8

3-5 E 6 1 7 1 7 0

4-9 F 5 5 10 10 15 5

5-6 G 4 7 11 12 16 5

5-7 H 8 7 15 7 15 0

6-8 I 1 11 12 16 17 5

7-8 J 2 15 17 15 17 0

8-10 K 5 17 22 17 22 0

9-10 L 7 10 17 15 22 5

Page 31: Spm ap-network model-

Problem 1

Prof. Kanchana Devi

31

Draw activity network of the project.

Find total float of each activity.

Activity Time in Weeks

1-2 20

1-3 25

2-3 10

2-4 12

3-4 5

3-5 10

Page 32: Spm ap-network model-

Problem 2

Prof. Kanchana Devi

32

Find out the critical path and total float.

Activity Immediate

Predecessor

Time

A 3

B 8

C 5

D A 9

E C 2

F B,E 6

H B,E 12

G D 11