1 August 11, 2014
SPLOST 2014 Quick Facts
Educa onal Impact of SPLOST in 2014
1—New school completed
22—Renova on projects
5—New ligh ng in 5 high school’s gyms completed
89—Entry access control systems installed
37—School playscapes will be replaced
4—In addi on, four new schools under construc on (2015
opening)
Economic Impact of SPLOST
Over $215‐Million commi ed to local firms
Over $86‐Million expended to date
Over 1,000 trade laborers employed this summer
Over 50,000 labor hours worked per summer week
Over 500,000 labor hours worked this summer
Over 850,000 labor hours to date
Zero Lost Time accidents since start in 2012
Over 300 local firms hold (sub)contracts or POs
2
August 11, 2014
New South Fulton Elementary School
Quick Facts:
Total site area +/‐ 17.65 Acres
Building size 126,612 S.F.
42 Regular and 14 special classrooms
Supports 850 FTE
Core facilities support 1,000 FTE
Project Team
Collins Cooper Carusi Architects
Evergreen Construction
This three story school offers the same programmatic and site amenities found in all other Fulton County
Schools prototypes. The school is organized with K‐5 classrooms stacked in an academic wing and the core
functions—Media Center, Music, Gymnasium, Cafetorium and Administration suite stacked at the end of
the building.
3
August 11, 2014
Hapeville Elementary School
This mul ple phased project includes major renova ons and building systems replacements to improve space comfort and reduce energy consump on. Significant interior renova ons and finishes improve aesthe cs in classrooms, corridors, and the media center. Exterior improvements include repaving the parking lot and improving drainage.
Phase 2 (2014)
Comprehensive renovation including
ceilings, lighting, flooring, and paint
HVAC, and select systems replaced
Project Team
Gardner Spencer Smith Tench & Jarbeau
Triad Construction Company, Inc.
Phase 1 (2013)
Parking lot resurfacing
Grading and drainage improvements
New PE flooring & windows
Structural reinforcing gym walls
Toilet rooms remodeled
4
August 11, 2014
Spalding Drive Elementary School
This multiple phased project includes modifications to the existing main entrance to enhance safety and
security and major renovations to the existing kitchen & serving area to relieve congestion. Building
systems replacements to improve space comfort and reduce energy consumption and significant interior
renovations to improve aesthetics.
Phase 2 (2014)
New flooring and finishes
Major HVAC equipment and systems
Complete lighting & ceilings
Project Team
Manley Spangler Smith Architects
Triad Construction Company, Inc.
Phase 1 (2013)
New asphalt parking and service area
Toilet room remodeling
PE flooring replaced
Regraded and grassed playfield
Drainage improvements
5
August 11, 2014
Tri‐Ci es High School
This mul ple phased project includes major renova ons to the exis ng kitchen & serving area to relieve conges on. Building systems replacements to improve space comfort and reduce energy consump on and significant interior renova ons to improve aesthe cs. Bulldog Way is reconstructed, and the building roof is replaced.
Phase 2 (2014)
Complete roofing scope
Complete flooring & finishes scope
Complete HVAC, lighting & ceilings
Project Team
BRPH Architects
Merit Construction
Phase 1 (2013)
New Kitchen & equipment
New Cafeteria & Serving Lines
New roof (partial)
New central plant
New flooring and finishes (partial)
HVAC, lighting & ceilings (partial)
6
August 11, 2014
Creekside High School
This multiple phased project includes modifications to the existing main entrance to enhance safety and
security. Major renovations to the existing kitchen & serving area to relieve congestion. Building systems
replacements to improve space comfort and reduce energy consumption and significant interior renovations
to improve aesthetics.
Phase 3 (2015)
Complete roofing scope
Complete flooring & finishes
Complete HVAC, lighting & ceilings
Project Team
CGLS Architects
Merit Construction
Phase 1 & 2 (2014)
Kitchen & equipment
Cafeteria finishes & serving lines
Roof (partial area)
New central plant
New flooring and finishes (partial)
Front entrance enhancements
HVAC, lighting & ceilings (partial area)
7
August 11, 2014
North Springs High School
This mul ple phased project includes modifica ons to the exis ng main entrance to enhance safety and security. Building systems replacements to improve space comfort and reduce energy consump on and significant interior renova ons to improve aesthe cs. Casework is replaced in classrooms, and the video produc on lab is remodeled.
Phase 3 (2015)
Complete roofing scope
Complete flooring & finishes
Complete HVAC, lighting & ceilings
Project Team
Cooper Carry Inc.
Hogan Construction Group
Phase 1 & 2 (2014)
Front entrance enhancements
Roofing (partial areas)
Flooring and finishes (partial areas)
HVAC, lighting & ceilings (partial areas)
White board and tack board replacement
8
August 11, 2014
Cha ahoochee High School
This mul ple phased project includes modifica ons to the exis ng main entrance to enhance safety and security. Major renova ons to the exis ng kitchen & serving area to relieve conges on. Building systems replacements to improve space comfort and reduce energy consump on and significant interior renova ons to improve aesthe cs.
Phase 3 (2015)
Complete roofing scope
Complete flooring & finishes
Complete HVAC, lighting & ceilings
Project Team
CGLS Architects
Evergreen Construction
Asphalt paving and bus canopy
Phase 1 & 2 (2014)
New Kitchen & equipment
New Cafeteria & Serving Lines
New central plant
New flooring and finishes (partial)
Front entrance enhancements
HVAC, lighting & ceilings (partial)
Fire alarm system
9
August 11, 2014
Roswell High School
This mul ple phased project includes modifica ons to the exis ng main entrance to enhance safety and security. Major renova ons to the exis ng kitchen & serving area to relieve conges on. Building systems replacements to improve space comfort and reduce energy consump on and significant interior renova ons to improve aesthe cs.
Phase 3 (2015)
Complete roofing scope
Complete flooring & finishes
Complete HVAC, lighting & ceilings
Project Team
CGLS Architects
Evergreen Construction
Asphalt paving and bus canopy
Phase 1 & 2 (2014)
Kitchen & equipment
Cafeteria & serving lines
Front entrance enhancements
Site improvements
New central plant
New flooring and finishes (partial areas)
HVAC, lighting & ceilings (partial areas)
10
August 11, 2014
Dolvin Elementary School
This two‐phased project has a light touch in the first year. First year improvements include limited pain ng and refinishing doors and casework, and re‐grading grassing the playfield. Second phase work includes HVAC, electrical and plumbing system work, and aesthe c improvements including pain ng, flooring, ceilings.
Phase 2 (2015)
Major electrical upgrades
Complete flooring & finishes
Complete HVAC, lighting & ceilings
Asphalt Paving
Canopy replacement
Phase 1 (2014)
Regrading and grassing playground
Minor interior finishes
Project Team
Manley Spangler Smith Architects
Swofford Construction
11
August 11, 2014
Woodland Elementary School
This first phase of a two‐phased project improves landscaping and drainage at the playfield, replaces the electrical service, and makes select interior improvements. The more significant second phase renovates the serving lines, and improves systems and aesthe cs throughout the school.
Phase 2 (2015)
Complete roofing
Complete flooring & finishes
Complete HVAC, lighting & ceilings
Project Team
Cooper Carry Inc.
Merit Construction
Windows
Phase 1 (2014)
Playground improvements
New Cafeteria & Serving Lines
New roof (partial)
New flooring and finishes (partial)
HVAC, lighting & ceilings (partial)
12
August 11, 2014
Brookview Elementary School
This single‐phase project replaces select HVAC equipment to improve indoor air quality. Life safety system improvements include a new fire alarm and emergency generator. Aesthe c improvements include pain ng, flooring, and ceiling le replacement. Drainage and grassing is improved at the play area.
Project Team
Forman Seeley Fountain Architecture
Swofford Construction
13
August 11, 2014
Barnwell Elementary School
This single phased project replaces building systems to improve space comfort and reduce energy consump on. To accommodate the systems replacements, significant interior renova ons including new ceilings and ligh ng will be replaced. Exterior improvements include underground and surface storm water deten on and parking lot repaving.
Project Team
Goode Van Slyke Architecture
Triad Construction Company, Inc.
14
August 11, 2014
Camp Creek Middle School
This single‐phase project includes a new serving line and select kitchen equipment. Carpe ng was replaced in the Media Center, and flooring, pain ng and ceiling les were replaced to improve aesthe cs. Exterior improvements include repaving and sidewalks.
Project Team
Collins Cooper Carusi Architects
Merit Construction
15
August 11, 2014
Haynes Bridge Middle School
This single‐phase project improves the kitchen and cafeteria serving lines and improves toilet rooms. HVAC, ligh ng and window replacements improve the building environment. Signage is replaced to improve wayfinding. Aesthe c improvements include marker and tack board replacement, pain ng, ceiling and flooring, casework and locker replacement.
Project Team
Collins Cooper Carusi Architects
Amacher Bros. Construction Co.
16
August 11, 2014
Holcomb Bridge Middle School
This single‐phase project includes a new serving line and select kitchen equipment. HVAC and roofing were replaced selec vely, and the bus canopy was expanded. Flooring, pain ng and ceiling les were replaced to improve aesthe cs. Exterior improvements include repaving, sidewalks and recondi oning the two storm water deten on ponds.
Project Team
Collins Cooper Carusi Architects
Merit Construction
17
August 11, 2014
Parklane Elementary School
This single phase project repaves the front entry and parking lot, regrades and grasses the playfield to
improve drainage, replaces canopies at the bus lot. Interior work includes thermal insulation in the gym to
improve aesthetics and energy consumption, toilet room remodeling, and replacement of aged finishes.
Project Team
The Brown Design Group
Southcore Construction Company, Inc.
18
August 11, 2014
Seaborn Lee Elementary School
This single‐phase project replaces select HVAC equipment and life safety systems including a new fire alarm and emergency generator. Aesthe c improvements include toilet room renova ons, terrazzo crack repairs, refinishing the stage, pain ng, flooring, and ceiling le replacement. Paving is replaced at the bus and parking lot.
Project Team
Forman Seeley Fountain Architecture
Swofford Construction
19
August 11, 2014
SL Lewis Elementary School
This single‐phase project improves several student, staff and accessible toilet rooms, replaces marker boards and tack boards, and improves aesthe cs by pain ng, replacing flooring and ceilings, recondi oning interior doors, replacing windows. Interior safety is improved by replacing branch circuit wiring and devices.
Project Team
Gardner Spencer Smith Tench & Jarbeau
Swofford Construction
20
August 11, 2014
Alphare a HS So ball Concessions
Project Team
Goode Van Slyke Architecture
Osprey Management
This single phased project constructs a separate storage building and concession stand adjacent to the
so ball field.
21
August 11, 2014
North Springs HS So ball Concessions
Project Team
Sy Richards Architect Inc.
SouthCore Construction
This single phased project constructs a separate concession stand adjacent to the
so ball field with miscellaneous field upgrades.
22
August 11, 2014
Northview HS Track Renova ons
Project Team
Breedlove Land Planning
Sports Turf Co./Sprinturf, LLC
This single phased project replaces the exis ng track surface replacement with new surfacing and football
field turf replacement.
23
August 11, 2014
Lake Windward Elementary School
This breakout package improves the play area and playscapes. A major renovation project is under design
and will be under construction by summer 2015.
Project Team
Breedlove Land Planning
PE Structures & Associates
24
August 11, 2014
Westlake High School
This wall was improperly constructed during the construction of Westlake High School in SPLOST III. The wall was
removed and is being replaced. Construction quality is monitored constantly by onsite geo‐technical engineers and
two web cameras.
Project Team
GSST&J/Breedlove Land Planning
Randolph & Company