Spectrometer Solenoid Fabrication Update
description
Transcript of Spectrometer Solenoid Fabrication Update
1S. Virostek - LBNL
Spectrometer Solenoid Fabrication Update
•Vendor still expects to complete fabrication of first magnet before Christmas•Unit #1 cold mass assembly is ready to install in vacuum vessel, cold mass supp’ts load tested•Other Unit #1 progress: vacuum vessel, thermal shield and support stands fabrication complete•Winding of 2nd magnet including banding complete•Installation of quench protection system and instrumentation in 2nd magnet is under way•Cryocooler testing conducted by Bert Wang and Mike Green is to be complete this week
2S. Virostek - LBNL
Magnet warm bores and inner thermal shields
3S. Virostek - LBNL
Outer thermal shield
4S. Virostek - LBNL
Vacuum vessel outer shell
5S. Virostek - LBNL
End walls and flanges
6S. Virostek - LBNL
Support structure assembly
7S. Virostek - LBNL
Cold mass support load testing
8S. Virostek - LBNL
Completed cold mass assembly