Spectrometer Solenoid Fabrication Update

8
. Virostek - LBNL Spectrometer Solenoid Fabrication Update Vendor still expects to complete fabrication of first magnet before Christmas Unit #1 cold mass assembly is ready to install in vacuum vessel, cold mass supp’ts load tested Other Unit #1 progress: vacuum vessel, thermal shield and support stands fabrication complete Winding of 2 nd magnet including banding complete Installation of quench protection system and instrumentation in 2 nd magnet

description

Spectrometer Solenoid Fabrication Update. Vendor still expects to complete fabrication of first magnet before Christmas Unit #1 cold mass assembly is ready to install in vacuum vessel, cold mass supp’ts load tested - PowerPoint PPT Presentation

Transcript of Spectrometer Solenoid Fabrication Update

Page 1: Spectrometer Solenoid Fabrication Update

1S. Virostek - LBNL

Spectrometer Solenoid Fabrication Update

•Vendor still expects to complete fabrication of first magnet before Christmas•Unit #1 cold mass assembly is ready to install in vacuum vessel, cold mass supp’ts load tested•Other Unit #1 progress: vacuum vessel, thermal shield and support stands fabrication complete•Winding of 2nd magnet including banding complete•Installation of quench protection system and instrumentation in 2nd magnet is under way•Cryocooler testing conducted by Bert Wang and Mike Green is to be complete this week

Page 2: Spectrometer Solenoid Fabrication Update

2S. Virostek - LBNL

Magnet warm bores and inner thermal shields

Page 3: Spectrometer Solenoid Fabrication Update

3S. Virostek - LBNL

Outer thermal shield

Page 4: Spectrometer Solenoid Fabrication Update

4S. Virostek - LBNL

Vacuum vessel outer shell

Page 5: Spectrometer Solenoid Fabrication Update

5S. Virostek - LBNL

End walls and flanges

Page 6: Spectrometer Solenoid Fabrication Update

6S. Virostek - LBNL

Support structure assembly

Page 7: Spectrometer Solenoid Fabrication Update

7S. Virostek - LBNL

Cold mass support load testing

Page 8: Spectrometer Solenoid Fabrication Update

8S. Virostek - LBNL

Completed cold mass assembly