A New Technique for Predicting Rock Fragmentation in Blasting
Special Blasting Technique
-
Upload
arief-pratama -
Category
Documents
-
view
107 -
download
4
description
Transcript of Special Blasting Technique
DRILL AND BLAST SECTION MINING SERVICES DEPARTMENT PT
KALTIM PRIMA COAL
Special Blasting TechniqueTrim and Pre Split Blasting
Reasons for Pit Wall Damage
Gas DrivenCrackExtension
Compressive and Tensile Failure
Shear Failure
Load Release
Block Heaving
No Free Face Prevents Burden Movement
Subdrill Damages Crests
Areas Concern in Wall Control Blasting
• Selection of best wall control blast method• Design blast based on geology and past
history to minimize wall damage• Development of blast pad area prior to
drilling to provide suitable blast area• Optimal implementation of chosen design
to minimize variation from design• Fragmentation and muck pile looseness
Wall Control Blasting Options
KPC has two main tools for controlling the strength and stability of interim and final pit walls:
• Trim Blasts• Pre split Blasts
Trim Blasts
The aim is to• Break rock mass to the pre-split or final wall
line
• Not to break through the line!
• Clearly, a good pre-split with a poor trim blast will not work
• A poor pre-split with a good trim blast also will not work!
• If pre-splitting is not appropriate, trim blasting may still provide a good final wall
There are some ‘Rules of Thumb’ to try in a new situation -
• Stand-off from pre-split should be about half the hole burden (i.e. 4m, KPC uses 3m)
• Last row spacing should be half the main spacing (OK)
• Burden between last (buffer) row and 2nd last row should be 3/4 the main burden (5.2m, KPC uses 6m or 6.6m)
Trim Blasts
Trim Blasts
Optimum burden relief for a detonating hole requires -
• Sufficient number of neighbouring holes to detonate
• Free face be close enough to the next hole to fire
• Enough time before this hole fires to create a free face it can use
These requirements can be investigated using JKSimBlast
Trim Blasts
Adequate burden relief is important in any production blast and absolutely critical in trim blasts.
• If any part of the blast is over-confined, material will not move properly
• This will over-confine the blastholes behind - it gets worse!
• In a small blast like a trim blast, this will not correct itself - damage will penetrate behind the pre-split or final wall line.
Trim Blasts
Issues to think about in dynamic burden relief 1. Drill Pad Preparation
Free faces – this means• shovel digs back to hard material• pad preparation dozing does not push loose material
over the free face
Accurate hole locations
2. Correct design implementation Accurate crest burdens Blastholes located to follow crest line Drilling accuracy
3. Correct tie-up
Pit AB Phase 2 Trim & Presplit Design, 20m Benches
Revised design using vertical presplit
Production Holes
Presplit Holes
40m
Trim Holes
Standoff 1m
10m
70o
17m 6.6m
6m
8m
6m
8m
3m
20m
20m
20m
Pit AB Phase 2 Trim & Presplit Design, 20m Benches
Revised design using vertical presplit
40m
Standoff 1m
10m
70o
17m 6.6m
6m
8m
20m
20m
20m
6m
8m
3m
6m
8m
3m
This will damage crest and cause early failures
Pit AB Phase 2 Trim & Presplit Design, 20m Benches
Revised design using vertical presplit
40m
Standoff 1m
10m
70o
17m 6.6m
6m
8m
15m
15m
15m
6m
8m
3m
6m
8m
3m
Pit AB Phase 2 Trim & Presplit Design, 20m Benches
6m 8m3m Upper Bench
Production rows:1. Max 4 rows2. Burden = 7 m3. Spacing = 8 m4. Depth = 11.5m5. Spacing direction must be parallel to presplit
row6. Blast area must have a free face – without
broken material in front – parallel to presplit row
Pit AB Phase 2 Trim & Presplit Design, 20m Benches
6m 8m3m Upper Bench
Trim row:1. Burden = 3.0m2. Spacing = 4.6m3. Depth = 11.5m4. Charge is as
shown in diagram
3.5m Stemming
2.0m Air Deck
4.0m Charge
2.0m Air Deck
Pit AB Phase 2 Trim & Presplit Design, 20m Benches
8mLower Bench
3.5m Stemming
1.75m Air Deck
2.75m Charge
1.0m Air Deck
First Trim row:1. Burden = 6.0m2. Spacing = 4.6m3. Depth = 9.0m4. Charge is as
shown in diagram
6m3m
Pit AB Phase 2 Trim & Presplit Design, 20m Benches
8mLower Bench
Second Trim row:
1. Burden = 3.0m2. Spacing = 4.6m3. Depth = 9.0m4. Charge is as
shown in diagram
6m3m
3.5m Stemming
1.75m Air Deck
2.75m Charge
1.0m Air Deck
Presplit Blast
• A line of closely spaced blast holes drilled at the limits line.
• Often smaller diameter than production blastholes.• Much lower charge density – laterally or vertically
decoupled.• Fired before the main blast; usually with no delay
between holes.
Why Pre-split?
• Increases wall stability.• Defines wall position, ensures consistent front row
burdens in strip mining.• Channels blast gases away from rock mass, reducing
back-break and damage.• Others (eg. limits dilution, aids equipment).
Proposed Mechanism – Tensile Failure from Compressive Shock
BlastholeBlasthole
Tensile Stress Zone
Compressive ShockCompressive Shock
Resultant Tensile Stress
How do we start?
The engineering variables (really variable)
• Hole diameter.• Hole spacing.• Total energy (explosive mass / product).• Energy distribution (charge positions,
decoupling).
What Else?
Rock mass variables (not so variable!)• Compressive strength.• Tensile strength.• Discontinuities (a.k.a. Joints).• Must not under-estimate joints!
A successful pre-split blast hole will…
• Generate sufficient pressure to cause tensile failure (the ‘split’)
• NOT generate too much pressure so that collateral crushing is avoided (ideally pressure is less than the compressive strength)
• Be close enough to its neighbour to form a continuous split
KPC Presplit Calculations
Explosive DynoSplitVOD (m/s) 4300
Density (g/cc) 1.1
Cartridge dia (mm) 32
Borehole dia (mm) 200
Borehole length (m) 20
Detonation pressure (GPa) 5.1
Explosion pressure (GPa) 2.5
Borehole pressure (MPa) 72
Presplit Charge One String DynoSplit 32mm diameter
Parameter ValueHole Spacing (m) 3Bench Height (m) 20
Explosive Specific Charge (kg/m) 0.88Uncharged Hole Length (m) 1
Doubled Over Length (m) 2No of Charge Strings per Hole 1
Pre-Split Powder Factor (kg/m2) 0.31
Alternative Presplit Charges
Airdeck & stem or leave open
Usually Airdeck & stem
Multiple small deck
charges
Multiple decoupled charges
Continuous low
density charge
Continuous
decoupled charge
Single small
charge