SPE DISTINGUISHED LECTURER SERIES SPE FOUNDATION · Recommendation. Critical Information only: ......

88
SPE DISTINGUISHED LECTURER SERIES is funded principally through a grant of the SPE FOUNDATION The Society gratefully acknowledges those companies that support the program by allowing their professionals to participate as Lecturers. And special thanks to The American Institute of Mining, Metallurgical, and Petroleum Engineers (AIME) for their contribution to the program.

Transcript of SPE DISTINGUISHED LECTURER SERIES SPE FOUNDATION · Recommendation. Critical Information only: ......

Page 1: SPE DISTINGUISHED LECTURER SERIES SPE FOUNDATION · Recommendation. Critical Information only: ... PDVSA, AGIP. Lessons learned • Projects that failed: – Underestimated psychological

SPE DISTINGUISHED LECTURER SERIESis funded principally

through a grant of the

SPE FOUNDATIONThe Society gratefully acknowledges

those companies that support the programby allowing their professionals

to participate as Lecturers.

And special thanks to The American Institute of Mining, Metallurgical,and Petroleum Engineers (AIME) for their contribution to the program.

Page 2: SPE DISTINGUISHED LECTURER SERIES SPE FOUNDATION · Recommendation. Critical Information only: ... PDVSA, AGIP. Lessons learned • Projects that failed: – Underestimated psychological
Page 3: SPE DISTINGUISHED LECTURER SERIES SPE FOUNDATION · Recommendation. Critical Information only: ... PDVSA, AGIP. Lessons learned • Projects that failed: – Underestimated psychological

SPE DISTINGUISHED LECTURER SERIESis funded principally

through a grant of the

SPE FOUNDATIONThe Society gratefully acknowledges

those companies that support the programby allowing their professionals

to participate as Lecturers.

And special thanks to The American Institute of Mining, Metallurgical,and Petroleum Engineers (AIME) for their contribution to the program.

Page 4: SPE DISTINGUISHED LECTURER SERIES SPE FOUNDATION · Recommendation. Critical Information only: ... PDVSA, AGIP. Lessons learned • Projects that failed: – Underestimated psychological

Distinguished Lecturer Series

Use of 21st Century Computer and

Communications Technologies

to Make Effective Drilling Decisions

Keith Womer

Page 5: SPE DISTINGUISHED LECTURER SERIES SPE FOUNDATION · Recommendation. Critical Information only: ... PDVSA, AGIP. Lessons learned • Projects that failed: – Underestimated psychological

The Good Old Days of Drilling

Page 6: SPE DISTINGUISHED LECTURER SERIES SPE FOUNDATION · Recommendation. Critical Information only: ... PDVSA, AGIP. Lessons learned • Projects that failed: – Underestimated psychological

The Good Old Days of Drilling

The rig Site

(Downtown L.A.)

Page 7: SPE DISTINGUISHED LECTURER SERIES SPE FOUNDATION · Recommendation. Critical Information only: ... PDVSA, AGIP. Lessons learned • Projects that failed: – Underestimated psychological

The Good Old Days of Drilling

Real time data

(the martin-decker)

Page 8: SPE DISTINGUISHED LECTURER SERIES SPE FOUNDATION · Recommendation. Critical Information only: ... PDVSA, AGIP. Lessons learned • Projects that failed: – Underestimated psychological

The Good Old Days of Drilling

MWD

(The totco)

Page 9: SPE DISTINGUISHED LECTURER SERIES SPE FOUNDATION · Recommendation. Critical Information only: ... PDVSA, AGIP. Lessons learned • Projects that failed: – Underestimated psychological

The Good Old Days of Drilling

The Data Logger

(The Geolograph)

Page 10: SPE DISTINGUISHED LECTURER SERIES SPE FOUNDATION · Recommendation. Critical Information only: ... PDVSA, AGIP. Lessons learned • Projects that failed: – Underestimated psychological

The Good Old Days of Drilling

Remote Comm

(as far as you could shout)

Page 11: SPE DISTINGUISHED LECTURER SERIES SPE FOUNDATION · Recommendation. Critical Information only: ... PDVSA, AGIP. Lessons learned • Projects that failed: – Underestimated psychological

What Happened?

Page 12: SPE DISTINGUISHED LECTURER SERIES SPE FOUNDATION · Recommendation. Critical Information only: ... PDVSA, AGIP. Lessons learned • Projects that failed: – Underestimated psychological

What Happened?

Close Not so Close

Page 13: SPE DISTINGUISHED LECTURER SERIES SPE FOUNDATION · Recommendation. Critical Information only: ... PDVSA, AGIP. Lessons learned • Projects that failed: – Underestimated psychological

What Happened?

Straightis good

Straightis Bad

Page 14: SPE DISTINGUISHED LECTURER SERIES SPE FOUNDATION · Recommendation. Critical Information only: ... PDVSA, AGIP. Lessons learned • Projects that failed: – Underestimated psychological

What Happened?

Funny Not Funny

Page 15: SPE DISTINGUISHED LECTURER SERIES SPE FOUNDATION · Recommendation. Critical Information only: ... PDVSA, AGIP. Lessons learned • Projects that failed: – Underestimated psychological

What Happened?

Exploitation Stewardship

Page 16: SPE DISTINGUISHED LECTURER SERIES SPE FOUNDATION · Recommendation. Critical Information only: ... PDVSA, AGIP. Lessons learned • Projects that failed: – Underestimated psychological

Result:

Complexity

Isolation

Stress

Error

Page 17: SPE DISTINGUISHED LECTURER SERIES SPE FOUNDATION · Recommendation. Critical Information only: ... PDVSA, AGIP. Lessons learned • Projects that failed: – Underestimated psychological

Solutions?More PeopleTrainingEngineering AdvancesPsychologySocial ScienceErgonomicsEnvironmental Science

Computer TechnologiesCommunications Technologies

Page 18: SPE DISTINGUISHED LECTURER SERIES SPE FOUNDATION · Recommendation. Critical Information only: ... PDVSA, AGIP. Lessons learned • Projects that failed: – Underestimated psychological

Two Case Studies

1. Computersmanage the complexityof the drilling process

2. Telecommunicationbrings togetherpeople and informationin real time

Page 19: SPE DISTINGUISHED LECTURER SERIES SPE FOUNDATION · Recommendation. Critical Information only: ... PDVSA, AGIP. Lessons learned • Projects that failed: – Underestimated psychological

Computersmanage the complexityof the drilling process

Page 20: SPE DISTINGUISHED LECTURER SERIES SPE FOUNDATION · Recommendation. Critical Information only: ... PDVSA, AGIP. Lessons learned • Projects that failed: – Underestimated psychological

Good Old Days WERE Good (ergonomically speaking)

• Comfortable Working Position

• Good Vision of Process

• Simple Display of Critical Information

• Low complexityLow stress Best performance

Page 21: SPE DISTINGUISHED LECTURER SERIES SPE FOUNDATION · Recommendation. Critical Information only: ... PDVSA, AGIP. Lessons learned • Projects that failed: – Underestimated psychological

But now add:

SCR Controlsand Autodriller

Intercom

Pit/gas monitoring BOP ControlsService Company Info

Page 22: SPE DISTINGUISHED LECTURER SERIES SPE FOUNDATION · Recommendation. Critical Information only: ... PDVSA, AGIP. Lessons learned • Projects that failed: – Underestimated psychological

And You Get:

Page 23: SPE DISTINGUISHED LECTURER SERIES SPE FOUNDATION · Recommendation. Critical Information only: ... PDVSA, AGIP. Lessons learned • Projects that failed: – Underestimated psychological

THEN add controls and displays for:

Iron RoughneckAutomated

Drawworks

Top Drive

Pipe Racking System

Computer display of sensors and alarms

Page 24: SPE DISTINGUISHED LECTURER SERIES SPE FOUNDATION · Recommendation. Critical Information only: ... PDVSA, AGIP. Lessons learned • Projects that failed: – Underestimated psychological

And You Get: Ergonomic Nightmares

• Uncomfortable Working Position

• Poor Vision of Process

• Information Overload

• High complexityHigh stressDemotivationPotential for error

Page 25: SPE DISTINGUISHED LECTURER SERIES SPE FOUNDATION · Recommendation. Critical Information only: ... PDVSA, AGIP. Lessons learned • Projects that failed: – Underestimated psychological

Other Examples

Page 26: SPE DISTINGUISHED LECTURER SERIES SPE FOUNDATION · Recommendation. Critical Information only: ... PDVSA, AGIP. Lessons learned • Projects that failed: – Underestimated psychological

Managing Complexity

1. Create Comfortable but Engaging Work environment

2. Manage Presentation of Information and Controls

Page 27: SPE DISTINGUISHED LECTURER SERIES SPE FOUNDATION · Recommendation. Critical Information only: ... PDVSA, AGIP. Lessons learned • Projects that failed: – Underestimated psychological

Step 1: Create Comfortable, Engaging Work Environment

First generation (early/mid-90’s)

Page 28: SPE DISTINGUISHED LECTURER SERIES SPE FOUNDATION · Recommendation. Critical Information only: ... PDVSA, AGIP. Lessons learned • Projects that failed: – Underestimated psychological

Step 1: Create Comfortable, Engaging Work Environment

•Stand up - Sit down•Rotating pedestal•Adjustable arm rests•Workspace

•Front Entry•Rotating Chair mount•Clear view front and down

Displays use hi-brite color CRT’s or touch screen LCD’s

Second generation (mid/late-90’s)

Page 29: SPE DISTINGUISHED LECTURER SERIES SPE FOUNDATION · Recommendation. Critical Information only: ... PDVSA, AGIP. Lessons learned • Projects that failed: – Underestimated psychological

Ergonomically Designed Workstation

Up to “Hi-brite”Touch Screen Terminals with optional CCTV Support

Adjustable arm rests with gel packs and fingertip joysticks

Footrest

Page 30: SPE DISTINGUISHED LECTURER SERIES SPE FOUNDATION · Recommendation. Critical Information only: ... PDVSA, AGIP. Lessons learned • Projects that failed: – Underestimated psychological

Ergonomically Designed Workstation

Rotating Pedestal

Sliding Chair for Stand-up/Sit-down workstation operation

Ergonomic Chair with Options

Space for discrete controls

Page 31: SPE DISTINGUISHED LECTURER SERIES SPE FOUNDATION · Recommendation. Critical Information only: ... PDVSA, AGIP. Lessons learned • Projects that failed: – Underestimated psychological

Step 2: Manage Presentation of Information and Controls

First generation:

Data hardwired to console

Driller sees:All the data

All the controlsAll the time

Page 32: SPE DISTINGUISHED LECTURER SERIES SPE FOUNDATION · Recommendation. Critical Information only: ... PDVSA, AGIP. Lessons learned • Projects that failed: – Underestimated psychological

Block Diagram of Second Generation System

Second generation:

Data routed to console by software,

not hardwired

Driller sees:Software-controlled

presentation

Page 33: SPE DISTINGUISHED LECTURER SERIES SPE FOUNDATION · Recommendation. Critical Information only: ... PDVSA, AGIP. Lessons learned • Projects that failed: – Underestimated psychological

Second Generation Operator screens

FLOW IN/

ALARM PAGE 8595 22-MAR-94 11:49:32

MASTER HORN ON M/D TOTCO (C) 1994 ALARMS ACTIVE

FLOW IN 675FLOW OUT

TOTAL GAS

685

15

GPM

GPM

UNITS

675GPM

11:19

11:24

11:29

11:34

11:39

11:44

11:49

FEETDRILLING MARKS

DELTA FLOW INFLUX ALARM AT 11:41:26 8:06

FLOW OUT IS INCREASINGBUT FLOW IN IS STEADY

A KICK IS POSSIBLE IF THISTREND CONTINUES

GAIN/LOSS 2.7DELTA FLOW 8.4

BBLS

FLOW OUT

685GPM

1 ALARM ACK 2 RESET ALARM 3 PRINT 4 EXIT

650.0 700.0 orCustom Screens to

fit specific applications

Page 34: SPE DISTINGUISHED LECTURER SERIES SPE FOUNDATION · Recommendation. Critical Information only: ... PDVSA, AGIP. Lessons learned • Projects that failed: – Underestimated psychological

Process Based Screen (drilling)

Page 35: SPE DISTINGUISHED LECTURER SERIES SPE FOUNDATION · Recommendation. Critical Information only: ... PDVSA, AGIP. Lessons learned • Projects that failed: – Underestimated psychological

Process Based Screen (drilling)

Page 36: SPE DISTINGUISHED LECTURER SERIES SPE FOUNDATION · Recommendation. Critical Information only: ... PDVSA, AGIP. Lessons learned • Projects that failed: – Underestimated psychological

Process Based Screen (drilling)

Page 37: SPE DISTINGUISHED LECTURER SERIES SPE FOUNDATION · Recommendation. Critical Information only: ... PDVSA, AGIP. Lessons learned • Projects that failed: – Underestimated psychological

Process Based Screen (auto drilling)

Page 38: SPE DISTINGUISHED LECTURER SERIES SPE FOUNDATION · Recommendation. Critical Information only: ... PDVSA, AGIP. Lessons learned • Projects that failed: – Underestimated psychological

Process Based Screen (tripping)

Page 39: SPE DISTINGUISHED LECTURER SERIES SPE FOUNDATION · Recommendation. Critical Information only: ... PDVSA, AGIP. Lessons learned • Projects that failed: – Underestimated psychological

Process Based Screen (tripping)

Page 40: SPE DISTINGUISHED LECTURER SERIES SPE FOUNDATION · Recommendation. Critical Information only: ... PDVSA, AGIP. Lessons learned • Projects that failed: – Underestimated psychological

Critical Information only:Kick “Smart Alarm”

FLOW IN/

ALARM PAGE 8595 22-MAR-94 11:49:32

MASTER HORN ON M/D TOTCO (C) 1994 ALARMS ACTIVE

FLOW IN 675FLOW OUT

TOTAL GAS

685

15

GPM

GPM

UNITS

675GPM

11:19

11:24

11:29

11:34

11:39

11:44

11:49

FEETDRILLING MARKS

DELTA FLOW INFLUX ALARM AT 11:41:26 8:06

FLOW OUT IS INCREASINGBUT FLOW IN IS STEADY

A KICK IS POSSIBLE IF THISTREND CONTINUES

GAIN/LOSS 2.7DELTA FLOW 8.4

BBLS

FLOW OUT

685GPM

1 ALARM ACK 2 RESET ALARM 3 PRINT 4 EXIT

650.0 700.0Flow In/Out

monitored in background

Trend anomaly triggers alarm

Driller pushes button to see:

VerificationRecommendation

Page 41: SPE DISTINGUISHED LECTURER SERIES SPE FOUNDATION · Recommendation. Critical Information only: ... PDVSA, AGIP. Lessons learned • Projects that failed: – Underestimated psychological

Critical Information only: Washout “Smart Alarm”

Flow/pressure monitored in background

Trend anomaly triggers alarm

Driller pushes button to see:

VerificationRecommendation

ALARM PAGE 8595 22-MAR-94 11:49:32

MASTER HORN ON M/D TOTCO (C) 1994 ALARMS ACTIVE

PUMP PRESS 3390TOTAL SPM

FLOW IN

205

675

PSIG

SPM

GPM

FLOW IN PUMP PRESSFEETDRILLING MARKS

675 3390GPM PSIG

11:19

11:24

11:29

11:34

11:39

11:44

11:49

11:19

11:24

11:29

11:34

11:39

11:44

11:49

PRESSURE DROP ALARM AT 11:41:26 8:06

PUMP PRESSURE IS DROPPINGBUT FLOW IN IS STEADY

A WASHOUT IS POSSIBLE IF THIS TREND CONTINUES

1 ALARM ACK 2 RESET ALARM 3 PRINT 4 EXIT

WASHOUT 8.9

650.0 700.0 3350.0 3450.0

Page 42: SPE DISTINGUISHED LECTURER SERIES SPE FOUNDATION · Recommendation. Critical Information only: ... PDVSA, AGIP. Lessons learned • Projects that failed: – Underestimated psychological

Result: Improvement of Physical and Mental Work Environment

Page 43: SPE DISTINGUISHED LECTURER SERIES SPE FOUNDATION · Recommendation. Critical Information only: ... PDVSA, AGIP. Lessons learned • Projects that failed: – Underestimated psychological

Real Life Examples

Page 44: SPE DISTINGUISHED LECTURER SERIES SPE FOUNDATION · Recommendation. Critical Information only: ... PDVSA, AGIP. Lessons learned • Projects that failed: – Underestimated psychological

Real Life Examples

Page 45: SPE DISTINGUISHED LECTURER SERIES SPE FOUNDATION · Recommendation. Critical Information only: ... PDVSA, AGIP. Lessons learned • Projects that failed: – Underestimated psychological

Final thoughts on computers:

Potential Pitfalls

Page 46: SPE DISTINGUISHED LECTURER SERIES SPE FOUNDATION · Recommendation. Critical Information only: ... PDVSA, AGIP. Lessons learned • Projects that failed: – Underestimated psychological

Potential Pitfall #1Hardware and Software Reliability

Page 47: SPE DISTINGUISHED LECTURER SERIES SPE FOUNDATION · Recommendation. Critical Information only: ... PDVSA, AGIP. Lessons learned • Projects that failed: – Underestimated psychological

Potential Pitfall #2

Software Programmers are not:

– Drillers

– Psychologists

– Ergonomics majors

Page 48: SPE DISTINGUISHED LECTURER SERIES SPE FOUNDATION · Recommendation. Critical Information only: ... PDVSA, AGIP. Lessons learned • Projects that failed: – Underestimated psychological

Potential Pitfall #3Computers manage details.

Humans synthesize and adapt.

DON’T MIX THESE UP!

Page 49: SPE DISTINGUISHED LECTURER SERIES SPE FOUNDATION · Recommendation. Critical Information only: ... PDVSA, AGIP. Lessons learned • Projects that failed: – Underestimated psychological

Potential Pitfall #4Don’t underestimate time it takes to design

“simple, reliable systems”

Page 50: SPE DISTINGUISHED LECTURER SERIES SPE FOUNDATION · Recommendation. Critical Information only: ... PDVSA, AGIP. Lessons learned • Projects that failed: – Underestimated psychological

Computersmanage the complexityof the drilling process

Page 51: SPE DISTINGUISHED LECTURER SERIES SPE FOUNDATION · Recommendation. Critical Information only: ... PDVSA, AGIP. Lessons learned • Projects that failed: – Underestimated psychological

Telecommunicationbrings together

people and information in real time

Page 52: SPE DISTINGUISHED LECTURER SERIES SPE FOUNDATION · Recommendation. Critical Information only: ... PDVSA, AGIP. Lessons learned • Projects that failed: – Underestimated psychological

The Good Old Days of Drilling

Remote Comm

(as far as you could shout)

Page 53: SPE DISTINGUISHED LECTURER SERIES SPE FOUNDATION · Recommendation. Critical Information only: ... PDVSA, AGIP. Lessons learned • Projects that failed: – Underestimated psychological

What Happened?

Close Not so Close

Page 54: SPE DISTINGUISHED LECTURER SERIES SPE FOUNDATION · Recommendation. Critical Information only: ... PDVSA, AGIP. Lessons learned • Projects that failed: – Underestimated psychological

What Happened?

Straightis good

Straightis Bad

Page 55: SPE DISTINGUISHED LECTURER SERIES SPE FOUNDATION · Recommendation. Critical Information only: ... PDVSA, AGIP. Lessons learned • Projects that failed: – Underestimated psychological

Increased Complexity

0

200

400

600

800

1000

1200

90 91 92 93 94 95 96 97

Horizontal

Under-Balanced

Coil Tubing

Number of High-TechnologyWells being Drilled

Page 56: SPE DISTINGUISHED LECTURER SERIES SPE FOUNDATION · Recommendation. Critical Information only: ... PDVSA, AGIP. Lessons learned • Projects that failed: – Underestimated psychological

Increased Complexity requires:

• Specialized expertise

• Specialized software

• “Real Time” decisions

Page 57: SPE DISTINGUISHED LECTURER SERIES SPE FOUNDATION · Recommendation. Critical Information only: ... PDVSA, AGIP. Lessons learned • Projects that failed: – Underestimated psychological

“Specialized Expertise”Problem: Shrinking Talent Pool

0

200

400

600

800

1000

1200

1400

1600

1800

74 76 78 80 82 84 86 88 90 92 94 96 98

Employees(1000's)

0

5

10

15

20

25

20-24 25-29 30-34 35-39 40-44 45-49 50-54 55-59 60-64 65+

Age Range%

Employee Count of the 25 Largest Oil & Gas Companies

Average Age of SPE Member (2002)

Page 58: SPE DISTINGUISHED LECTURER SERIES SPE FOUNDATION · Recommendation. Critical Information only: ... PDVSA, AGIP. Lessons learned • Projects that failed: – Underestimated psychological

“Specialized Software”Problem: Too sophisticated for rig-site use

• Much Sophisticated software not local– Earth models

– Geosteering

– Drilling optimization

• Requires specialized training– Operate

– Interpret

– Consult with stakeholders

Page 59: SPE DISTINGUISHED LECTURER SERIES SPE FOUNDATION · Recommendation. Critical Information only: ... PDVSA, AGIP. Lessons learned • Projects that failed: – Underestimated psychological

“Real Time Decisions”Problem: Remote Locations

• Travel to rig-site increasingly impractical– Hours (land)

– Days (offshore)

– Not possible (political/safety)

• Offsite-onsite issues– Miscommunication

– Lack of shared knowledge

– Mistrust

Page 60: SPE DISTINGUISHED LECTURER SERIES SPE FOUNDATION · Recommendation. Critical Information only: ... PDVSA, AGIP. Lessons learned • Projects that failed: – Underestimated psychological

Telecommunication can help

Bring together (electronically):

1. The “right” people

2. With the “right” information

3. At the “right” time

Page 61: SPE DISTINGUISHED LECTURER SERIES SPE FOUNDATION · Recommendation. Critical Information only: ... PDVSA, AGIP. Lessons learned • Projects that failed: – Underestimated psychological

Telecommunication can help

Centralized Operations Center

Subject Matter Expert

Subject Matter Experts

Rig C

Rig A

Rig B

Page 62: SPE DISTINGUISHED LECTURER SERIES SPE FOUNDATION · Recommendation. Critical Information only: ... PDVSA, AGIP. Lessons learned • Projects that failed: – Underestimated psychological

Earliest Example of Telecommunication in Drilling?

From 1972 “History of the Martin Decker Corporation”

Page 63: SPE DISTINGUISHED LECTURER SERIES SPE FOUNDATION · Recommendation. Critical Information only: ... PDVSA, AGIP. Lessons learned • Projects that failed: – Underestimated psychological

First Generation Systems(80’s-mid 90’s)• Amoco Critical Drilling Facility

• Tenneco Real Time Data Center

• Mobil Real Time Data Center(still in operation)

• Superior

• Pemex

• Later: Chevron, PDVSA, AGIP

Page 64: SPE DISTINGUISHED LECTURER SERIES SPE FOUNDATION · Recommendation. Critical Information only: ... PDVSA, AGIP. Lessons learned • Projects that failed: – Underestimated psychological

Lessons learned

• Projects that failed:– Underestimated psychological impact (“Big Brother”)– Used “bleeding edge” communications technologies– Were operationally effective, but doomed by time and cost

• Projects that succeeded:+ Kept control in hands of rig personnel + Used simple, conventional technologies+ Had simple, compelling benefits shared by all+ Emphasized consultancy over command-and-control

From SPE ATW on “Off Well Site Decision Making” (Austin, April 2002)

Page 65: SPE DISTINGUISHED LECTURER SERIES SPE FOUNDATION · Recommendation. Critical Information only: ... PDVSA, AGIP. Lessons learned • Projects that failed: – Underestimated psychological

Second Generation Systems

“Limited Duration Events”e.g. Remote Geosteering

(Service Companies)

Operations Centers(operators)

Integrated Services Centers(Service Companies)

Remote Rig Equipment Monitoring(Rig Equipment Suppliers)

Page 66: SPE DISTINGUISHED LECTURER SERIES SPE FOUNDATION · Recommendation. Critical Information only: ... PDVSA, AGIP. Lessons learned • Projects that failed: – Underestimated psychological

Example 1: Operations Centers Anadarko’s Operations Intelligence Center

• Based at Headquarters:The Woodlands (near Houston)

• Open since April 2002

• Collaborate around any activity (both on-line and off-line to rigs)

• Use in lower 48 and Alaska

• Soon to expand internationally

Page 67: SPE DISTINGUISHED LECTURER SERIES SPE FOUNDATION · Recommendation. Critical Information only: ... PDVSA, AGIP. Lessons learned • Projects that failed: – Underestimated psychological

Anadarko’s Operations Intelligence Center

Display Wall with DLP Projection

Observation/Training Gallery

Data Pilot StationsDisplays for weather/news

Conference Area seating 12

Page 68: SPE DISTINGUISHED LECTURER SERIES SPE FOUNDATION · Recommendation. Critical Information only: ... PDVSA, AGIP. Lessons learned • Projects that failed: – Underestimated psychological

Anadarko’s Operations Intelligence CenterWith Real Time Data Feed• Critical drilling operations• Cementing operations• Casing Point Selection• Well testing/MDT logging• Emergency response incidents• Completions and stimulation treatments

• Logging operations• Pressure transient analysis• Non-critical drilling surveillance

OIC Activity SummaryApril through February 2003

21

33

78

94

0

10

20

30

40

50

60

70

80

90

100

Real-time Training Planning Sessions Post Analysis

No.

of E

vent

s

With No Real Time Data Feed• Training• Development planning• Post appraisals of engineering activities• Learning curve analysis• Acquisition and divestiture evaluations Satellite Low cost

Field Frac Kit

Page 69: SPE DISTINGUISHED LECTURER SERIES SPE FOUNDATION · Recommendation. Critical Information only: ... PDVSA, AGIP. Lessons learned • Projects that failed: – Underestimated psychological

Anadarko’s Operations Intelligence Center:Critical Problem Solving

• E-mail alert hits drilling engineer’s computer or Blackberry• Rig needs decision critical information within next hour• Team gathers in OIC and using all available data, software and

communications capabilities• Problem reviewed, data analyzed and decision made in minutes• Decision relayed to field

Page 70: SPE DISTINGUISHED LECTURER SERIES SPE FOUNDATION · Recommendation. Critical Information only: ... PDVSA, AGIP. Lessons learned • Projects that failed: – Underestimated psychological

Example 2:Integrated Services Centers

• Based in Stavanger, Norway

• Commercialized in 2001-2002

with BP and Norsk Hydro

• New center opened April 2002

– capacity 15 rigs

– 24 hours operation with real time data

• Second center opened in Houston

Information Courtesy of Baker Hughes, Inc. BEACON Service

Page 71: SPE DISTINGUISHED LECTURER SERIES SPE FOUNDATION · Recommendation. Critical Information only: ... PDVSA, AGIP. Lessons learned • Projects that failed: – Underestimated psychological

Integrated Services Centers

Online:MWD

Data EngineerDirectional Driller

RIG

Increased TEAM IQ

Support Specialists:Directonal DrillingDrilling Dynamics

Pressure ManagementFormation and Log Evaluation

Reservoir NavigationSoftware SupportProduct Expertise

Rig:X-trained Dir. Driller

Mud logger

Operator personnelDrilling Contractor

Page 72: SPE DISTINGUISHED LECTURER SERIES SPE FOUNDATION · Recommendation. Critical Information only: ... PDVSA, AGIP. Lessons learned • Projects that failed: – Underestimated psychological

Integrated Services Centers: Support Software Applications

Update of geological and reservoir models

QC log “real time”

Geo steering

Drilling Optimization

0

1

23

4

5

6

78

9

10

Today Team2000

FluidsSLSMWD/DrillingTotalTeam 2000

Improved personnel utilization

Real Time Data Transfer

Page 73: SPE DISTINGUISHED LECTURER SERIES SPE FOUNDATION · Recommendation. Critical Information only: ... PDVSA, AGIP. Lessons learned • Projects that failed: – Underestimated psychological

Example 3: “Limited Duration” Events(Remote Geosteering)

• Real time wellbore placement

• Specialist runs operation from operator’s visualization room

• Monitor/analyze/control operation of geosteering tool

• Correlate LWD to modeled logs

• Wellplan adjusted dynamically

• Remote re-orientation possible

• Used on all North Sea, Middle East, South America and North America jobs since 2003

Information Courtesy of Halliburton StratSteer® 3D Service

Page 74: SPE DISTINGUISHED LECTURER SERIES SPE FOUNDATION · Recommendation. Critical Information only: ... PDVSA, AGIP. Lessons learned • Projects that failed: – Underestimated psychological

Remote Geosteering

INSITE

OFFIC

ESER

VER

OfficeNetwork

Rig Site Location

ClientOffice

RigsiteNetwork

Page 75: SPE DISTINGUISHED LECTURER SERIES SPE FOUNDATION · Recommendation. Critical Information only: ... PDVSA, AGIP. Lessons learned • Projects that failed: – Underestimated psychological

Remote Geosteering: Results

• Optimal wellbore positioning decisions

• Involves entire asset team

• Access to global experts

• Avoid NPT associated with waiting on orders

Page 76: SPE DISTINGUISHED LECTURER SERIES SPE FOUNDATION · Recommendation. Critical Information only: ... PDVSA, AGIP. Lessons learned • Projects that failed: – Underestimated psychological

Example 4:Remote Rig Equipment Monitoring

Service Center in Houston, TX USASince January, 2002Four major offshore contractors, 14 rigsOne major land contractor, 19 rigsEquipment monitored:

Control and Information SystemsTop DrivesPipe Handling EquipmentDrawworks

“Smart People” offsiteare connected on-line to“Smart Equipment” onsite

Information Courtesy of Varco e-Drill Service

Page 77: SPE DISTINGUISHED LECTURER SERIES SPE FOUNDATION · Recommendation. Critical Information only: ... PDVSA, AGIP. Lessons learned • Projects that failed: – Underestimated psychological

Remote Rig Equipment Monitoring

Goals:

1. Reduce Down Time (re-active)

2. Improve Performance (pro-active)Insure Proper Operation Insure Optimum UsageInsure Proper Maintenance and Tuning

Top Drive

Pipe Racking System

Page 78: SPE DISTINGUISHED LECTURER SERIES SPE FOUNDATION · Recommendation. Critical Information only: ... PDVSA, AGIP. Lessons learned • Projects that failed: – Underestimated psychological

Rig Equipment Problem ResolutionRig Site Data

Logging Computer

Voice

Network

The Internet

Service CenterSubject

Matter Expert

Control and Information Systems / Top Drives / Pipe Handling

Equipment / Drawworks

Page 79: SPE DISTINGUISHED LECTURER SERIES SPE FOUNDATION · Recommendation. Critical Information only: ... PDVSA, AGIP. Lessons learned • Projects that failed: – Underestimated psychological

Final thoughts on Telecommunication:

Potential Pitfalls

Page 80: SPE DISTINGUISHED LECTURER SERIES SPE FOUNDATION · Recommendation. Critical Information only: ... PDVSA, AGIP. Lessons learned • Projects that failed: – Underestimated psychological

Potential Pitfall #1

Big Brother

Page 81: SPE DISTINGUISHED LECTURER SERIES SPE FOUNDATION · Recommendation. Critical Information only: ... PDVSA, AGIP. Lessons learned • Projects that failed: – Underestimated psychological

Potential Pitfall #2

Lack of Process and Policy

HSE Recommends:

• Process: Enhance, not restructure

• Policy: Develop formal decision policies that describe proper use of the technology

From SPE ATW on “Off Well Site Decision Making” (Austin, April 2002)Views from the Health and Safety Executive (UK), Norwegian Petroleum Directorate (NPD) and

Minerals Management Service (MMS)

Page 82: SPE DISTINGUISHED LECTURER SERIES SPE FOUNDATION · Recommendation. Critical Information only: ... PDVSA, AGIP. Lessons learned • Projects that failed: – Underestimated psychological

Potential Pitfall #3Making a “Bad” Situation Worse

• Operator-Contractor-Service relationship today:– conflicting goals

– “bad” communication

• “Computer mediated” decision inadequacies– Less psychologically satisfying– Less efficient– Decision Quality degrades over time

From SPE ATW on “Off Well Site Decision Making” (Austin, April 2002)From Presentation by Dr. Charles Samuelson, Industrial/Organization Psychology, Texas A&M

Page 83: SPE DISTINGUISHED LECTURER SERIES SPE FOUNDATION · Recommendation. Critical Information only: ... PDVSA, AGIP. Lessons learned • Projects that failed: – Underestimated psychological

Potential Pitfall #4Data Security

• In an IT sense, we have it– Virtual Private Networking (VPN) technology– Point-to-point data security

• In an operational sense, we don’t have it– Multiple creators and consumers of data– Who owns what data?– Who has the need-to-know?

• May be an irresolvable problem

Page 84: SPE DISTINGUISHED LECTURER SERIES SPE FOUNDATION · Recommendation. Critical Information only: ... PDVSA, AGIP. Lessons learned • Projects that failed: – Underestimated psychological

Potential Pitfall #5

“Everybody Wants to Get into The Act”

• Multiple centers– Operators– Service Companies– Equipment Suppliers

• “Über-center” inefficient

• Must learn to “play together”

Page 85: SPE DISTINGUISHED LECTURER SERIES SPE FOUNDATION · Recommendation. Critical Information only: ... PDVSA, AGIP. Lessons learned • Projects that failed: – Underestimated psychological

Further Study:Analogs from Outside our Industry

• International Space Station “Human Interactions in Space”– Remote, dangerous environment– Multi-cultural– More info at: http://www.kanas1.net

• Space Shuttle: Mission control and shuttle crew interaction– Command Structure– Roles and responsibilities– Use of situation simulations

Page 86: SPE DISTINGUISHED LECTURER SERIES SPE FOUNDATION · Recommendation. Critical Information only: ... PDVSA, AGIP. Lessons learned • Projects that failed: – Underestimated psychological

Lessons Learned

• Technology readily available

• Focus on people and process

• Enhance, not change, decision structure

• Can be effective, but troubles ahead

Page 87: SPE DISTINGUISHED LECTURER SERIES SPE FOUNDATION · Recommendation. Critical Information only: ... PDVSA, AGIP. Lessons learned • Projects that failed: – Underestimated psychological

Telecommunicationbrings together

people and information in real time

Page 88: SPE DISTINGUISHED LECTURER SERIES SPE FOUNDATION · Recommendation. Critical Information only: ... PDVSA, AGIP. Lessons learned • Projects that failed: – Underestimated psychological

Questions?