SP Departmental Substations

22
DEPARTMENTAL SUBSTATIONS Document STD.002.U04 Page 1/22 Rev. B LIST OF ELECTRICAL STANDARD SPECIFICATIONS 01 Codes for electrical equipment 02 Preparation of electrical documents 03 Incoming substations 04 Departmental substations 05 Medium voltage distribution boards 06 Power transformers 07 Power control centres, motor control centres 08 Large motors 09 Small motors 10 Starters 11 Variable speed drives 12 Erection, cabling, earthing connections, lightning protection 13 Production and distribution of auxiliary voltages 14 Electrical cabinets and marshalling cabinets 15 Instrumentation 16 Process Control System : equipment and configuration 17 Process Control System: application software and integration 18 Lighting and power outlets 19 Electrical devices for to mechanical equipment 20 Earthing grid 21 Process Control System : basic functional objects 22 Visible Cut-off Switches 23 Incoming transformers Key codes : Substation, Electrical room, Switchroom, Power, Technical floor, Pressurisation, Air-conditioning, Lighting, Fire detection, Earthing, Cabling. F E D C B 18/10/05 General revision S. DECANTER M. MAHAUX R. MEINHARDT A 28/05/03 Approval by CTEC R. STRAUB M. MAHAUX R. MEINHARDT 0 19/09/02 Document edition R. STRAUB M. MAHAUX Rev Date Scope of revision Issued Approved CTI Approved CTEC LAFARGE CENTRE TECHNIQUE INTER-UNITES L’Isle d’Abeau – Parc de Chesnes – B.P. 70 F-38291 ST QUENTIN-FALLAVIER Cedex Phone : + 33 474 82 16 16 / Fax + 33 474 94 30 07 LAFARGE CENTRE TECHNIQUE EUROPE CENTRALE Gumpendorfer Strasse 19-21, A-1060 WIEN, Postfach 264 Phone : + 43 1 811 42 0 / + 43 1 811 42 44 09 ASIA TECHNICAL CENTRE Level 3,Wisma Lafarge N°2 Jalan Kilang 46050 PETALING JAYA – SELANGOR DARUL EHSAN MY-MALAYSIA Phone : + 603 77874800 / Fax : + 603 77874890 Reproduction & usage strictly forbidden without Lafarge explicite agreement (Law March 11 th , 1957) ELECTRICAL STANDARD SPECIFICATION

description

PS Departmental Substations

Transcript of SP Departmental Substations

Page 1: SP Departmental Substations

DEPARTMENTAL SUBSTATIONS

Document STD.002.U04

Page 1/22

Rev. B

LIST OF ELECTRICAL STANDARD SPECIFICATIONS

01 Codes for electrical equipment 02 Preparation of electrical documents 03 Incoming substations 04 Departmental substations 05 Medium voltage distribution boards 06 Power transformers 07 Power control centres, motor control centres 08 Large motors 09 Small motors 10 Starters 11 Variable speed drives 12 Erection, cabling, earthing connections, lightning protection 13 Production and distribution of auxiliary voltages 14 Electrical cabinets and marshalling cabinets 15 Instrumentation 16 Process Control System : equipment and configuration 17 Process Control System: application software and integration 18 Lighting and power outlets 19 Electrical devices for to mechanical equipment 20 Earthing grid 21 Process Control System : basic functional objects 22 Visible Cut-off Switches 23 Incoming transformers

Key codes : Substation, Electrical room, Switchroom, Power, Tec hnical floor, Pressurisation, Air-conditioning, Lighting, Fire detection, Earthin g, Cabling.

F E D C

B

18/10/05

General revision

S. DECANTER

M. MAHAUX

R. MEINHARDT A 28/05/03 Approval by CTEC R. STRAUB M. MAHAUX R. MEINHARDT 0 19/09/02 Document edition R. STRAUB M. MAHAUX

Rev Date Scope of revision Issued Approved CTI Approved CTEC

LAFARGE CENTRE TECHNIQUE INTER-UNITES L’Isle d’Abeau – Parc de Chesnes – B.P. 70 F-38291 ST QUENTIN-FALLAVIER Cedex Phone : + 33 474 82 16 16 / Fax + 33 474 94 30 07

LAFARGE CENTRE TECHNIQUE EUROPE CENTRALE Gumpendorfer Strasse 19-21, A-1060 WIEN, Postfach 264 Phone : + 43 1 811 42 0 / + 43 1 811 42 44 09

ASIA TECHNICAL CENTRE Level 3,Wisma Lafarge N°2 Jalan Kilang 46050 PETALING JAYA – SELANGOR DARUL EHSAN MY-MALAYSIA Phone : + 603 77874800 / Fax : + 603 77874890

Reproduction & usage strictly forbidden without Laf arge explicite agreement (Law March 11 th, 1957)

ELECTRICAL STANDARD SPECIFICATION

Page 2: SP Departmental Substations

DEPARTMENTAL SUBSTATIONS

Document STD.002.U04

Page 2/22

Rev. B

Page 3: SP Departmental Substations

DEPARTMENTAL SUBSTATIONS

Document STD.002.U04

Page 3/22

Rev. B

CONTENT

1. GENERAL POINTS ..................................... .................................................................................4

1.1. APPLICABILITY.....................................................................................................................4 1.2. ASSOCIATED SPECIFICATIONS .........................................................................................4 1.3. APPLICABLE STANDARDS..................................................................................................4 1.4. LOCAL CONDITIONS............................................................................................................4 1.5. GLOSSARY...........................................................................................................................4

2. CIVIL WORKS........................................ ......................................................................................6

2.1. GENERAL DESIGN...............................................................................................................6 2.2. FINISHING ASPECTS AND PAINTING.................................................................................6 2.3. DOORS .................................................................................................................................7

2.3.1. Common requirements ...................................................................................................7 2.3.2. Electrical rooms, staff access door..................................................................................7 2.3.3. Electrical rooms, door for emergency exit and equipment bringing in..............................7 2.3.4. Transformer rooms, staff access and equipment bringing in doors .................................8

3. TECHNICAL FLOOR.................................... ................................................................................8

4. AIR-CONDITIONING AND PRESSURISATION ................ ...........................................................9

4.1. AIR-CONDITIONING .............................................................................................................9 4.2. PRESSURISATION .............................................................................................................10 4.3. POWER SUPPLY ................................................................................................................10

5. LIGHTING AND FIRE DETECTION........................ ....................................................................11

5.1. LIGHTING............................................................................................................................11 5.2. FIRE DETECTION...............................................................................................................11

6. GENERAL ELECTRICAL CONTRACTOR...................... ...........................................................12

6.1. CONTROL AND SAFETY DEVICES ...................................................................................12 6.2. EARTHING..........................................................................................................................12 6.3. CABLING.............................................................................................................................12 6.4. SAFETY EQUIPMENT.........................................................................................................12

7. DOCUMENTS.............................................................................................................................13

8. GUARANTEE.......................................... ...................................................................................13

9. DATA SHEET......................................... ....................................................................................13

10. TYPICAL DRAWINGS................................... .............................................................................15

Page 4: SP Departmental Substations

DEPARTMENTAL SUBSTATIONS

Document STD.002.U04

Page 4/22

Rev. B

B

B

B

B

B

1. GENERAL POINTS

1.1. APPLICABILITY

• This specification is applicable to any departmental substation, i.e. any electrical room feeding and controlling a plant department.

• It is also applicable to the incoming substation feeding the departmental substations with some additional requirements mentioned in specification STD.002.U03.

1.2. ASSOCIATED SPECIFICATIONS STD.002.U01: Codes for Electrical Equipment STD.002.U02: Preparation of Electrical Documents STD.002.U12: Erection, cabling, earthing connections, lightning protection STD.002.U13: Production and distribution of auxiliary voltages STD.002.U18 : Lighting and Power Outlets. STD.2.99.0.V98: Paintwork

1.3. APPLICABLE STANDARDS Unless otherwise mentioned in the Site Specification, IEC standards shall be implemented for manufacturing and installing equipment and systems, and in particular: IEC 60903: Personal Protective Equipment.

1.4. LOCAL CONDITIONS

• Local conditions are described in the site specification. Anyway, surrounding temperature considered in equipment dimensioning shall not be less than 40°C, with a daily average not less than 35°C, as required by IEC standards.

• The attention of the Supplier is drawn on the fact that a cement plant is a very dusty environment.

1.5. GLOSSARY ACC Auxiliary Control Centre. CCR Central Control Room. Department Functionally linked sub-process stage for a given process stage and a

given line (please refer to specification STD.002.U01, section 1.1). Examples are : Raw Mill 2, Kiln 1, Cement Mill C, …

DESD Emergency Shut-Down of a given department initiated by pressing an

emergency shut-down push button installed in this department or in the CCR. It initiates a quick shut-down of each sequence and trips the contactors and MV circuit breakers of all users of the department.

Page 5: SP Departmental Substations

DEPARTMENTAL SUBSTATIONS

Document STD.002.U04

Page 5/22

Rev. B

Electrical room Room of a substation where electrical switchgear and electrical

equipment are installed to be kept in clean and cool ambiance ; also called “ Switchroom”.

MCC Motor Control Centre. ( LV switchboard controlling motors and 3-phase

users ) MV Medium voltage (above 1000 V and not exceeding 36 kV) MVESD Medium voltage emergency shut-down (tripping the departmental MV

switchboard) PCC Power Control Centre. ( LV distribution switchboard feeding MCCs or

other 3-phase users ) Site Specification The Site Specification is a technical specification complementing the

Electrical Standard Specifications and describing, for a given site, its particulars such as :

• Local conditions (climate, altitude, earthquakes, …)

• Voltages and frequency of power and control circuits

• Local regulations

• Technical requirements specific to the site

• Approved deviations from the Electrical Standard Specifications if required.

Substation Place where electrical equipment are concentrated, installed in

electrical room(s)/switchroom(s) and transformer room(s). Switchroom Room of a substation where electrical switchgear and electrical

equipment are installed to be kept in clean and cool ambience ; also called “ Electrical Room “.

Transformer room Room of a substation where power transformers are installed. UPS Uninterruptible Power System. VSD Variable Speed Drive.

Page 6: SP Departmental Substations

DEPARTMENTAL SUBSTATIONS

Document STD.002.U04

Page 6/22

Rev. B

B

B

2. CIVIL WORKS

2.1. GENERAL DESIGN

• Generally speaking, departmental substations shall be designed in accordance with typical drawings included in section 10. When local conditions are suitable (not frequently flooded area), basic solution (drawing 2) will be preferred. If the site is subject to flooding alternative solution (drawing 3) will be chosen. Then the stairs shall be completed with adequate handrails.

• The electrical equipment shall be installed preferably along the walls, keeping 100 to 200 mm space for ventilation.

• For each modular switchboard (MV switchboard, MCC, marshalling boards, …), spare room shall be kept for future installation of at least one additional module.

• In particularly, civil works design:

� shall include reservations for the installation of a technical floor covering the whole Electrical Room (access airlock excluded). A free space of 3000 mm minimum shall be kept between this technical floor and the beams supporting the ceiling or the insulated ceiling.

� shall include cable trenches and reservations of any kind for cable routings (including embedded conduits and cable galleries).

� shall include supply and installation of transformers supporting rails and of frames for retaining leaking oil.

� shall include supplies and services listed in sections 2.2 and 2.3.

� shall include reservations for the installation, by others, of air-conditioning and pressurisation equipment detailed in section 4.

• Electrical rooms of different departments shall be segregated by fire resisting walls / floors and by 2 hours fire resisting doors.

• To avoid dust ingress electrical rooms shall not be equipped with windows nor with glass doors (that could be broken).

• Each oil-immersed transformer shall be segregated from other oil-immersed transformers by a fire-resisting wall, or better be installed in a separate room.

• Shall also be installed in the transformer room(s) equipment dissipating huge heat quantities (braking resistors, ...) or which are too large and not dust critical (fixed capacitor power factor correction banks, ...).

2.2. FINISHING ASPECTS AND PAINTING The Supplier shall:

• Install a thermal insulation under the ceiling of the whole substation if this ceiling is just under a roof. In the electrical room this insulation shall be covered with panels made of a sound-absorbing material.

Page 7: SP Departmental Substations

DEPARTMENTAL SUBSTATIONS

Document STD.002.U04

Page 7/22

Rev. B

Materials used shall be non flammable and shall be certified by the National Fire Protection Association ( NFPA ).

• Fill in any hole or space through which the dust could penetrate, in order to make the pressurisation system efficient.

• Paint all the substation internal walls with a semi-glossy paint of light shade.

• Paint the concrete slab of the transformers room and of the airlock with a glossy paint of similar shade specially designed for concrete surfaces.

2.3. DOORS

2.3.1. Common requirements

• Doors shall be made of steel painted according to specification STD.2.99.0.V.98 or of anodized aluminium. Their design and installation shall meet the principles developed in typical drawings of section 10.

• A common key (pass key) shall make people able to open any door of any substation on the site (Master Key system). Locks shall be of dust resisting type.

• Alternatively, mechanical locks can be replaced by electrical locks controlled by a common access badge. If this solution is chosen the Supplier shall also supply a workstation for controlling this access system and equipment necessary for making personal access badges.

2.3.2. Electrical rooms, staff access door

• Staff will access the electrical room (clean area) through an airlock in order to limit dust ingress. This airlock will be, if possible, oriented towards the main building for facilitating staff circulation.

• Both airlock doors will be of local standard size, but not less than 2.10 m high and 0.90 m broad. These doors shall open towards outside and shall be equipped with antipanic bars at inside. They shall be equipped with seals to prevent dust ingress and with automatic door closers.

• The outside door frame shall border the door on its 4 sides, including a bottom section that will keep between the ground and the door a free space of 30 mm minimum to avoid that small stones could block the door. This outside door shall be equipped with a lock.

• A mat or a grate shall be inserted into the airlock slab, in order to keep the electrical room clean.

2.3.3. Electrical rooms, door for emergency exit an d equipment bringing in

• Except in small electrical rooms, a second door shall be installed at the other end of this area to facilitate staff evacuation in case of hazard, and also for bringing in the equipment.

Page 8: SP Departmental Substations

DEPARTMENTAL SUBSTATIONS

Document STD.002.U04

Page 8/22

Rev. B

B

• This door shall be identical to the inside door of the airlock here above mentioned but, in order to bring in the equipment easily, it shall be surrounded with metallic panels fixed by bolts or by locks. The passage shall be 2.80 m high and 1.20 m broad when panels are removed.

• This door shall not be equipped at outdoors side with any handle or lock entry so that entering in this area will be by the airlock only (but at indoors side with a panic bar). This door being a single barrier to dust ingress (the airlock is a double barrier), it shall be really dust tight. As it will be used in case of urgency only, thin silicon seals can be used, easy to be broken in case of emergency.

• The door frame shall border the door on its 4 sides, including a bottom section that will keep between the ground and the door a free space of 30 mm minimum to avoid that a small stone could block the door.

Note : For small electrical rooms, staff entry and equipment bringing in will be by the same

access; this single access will be an airlock with both doors surrounded with metallic panels as explained here above.

2.3.4. Transformer rooms, staff access and equipmen t bringing in doors

• The transformer rooms shall be equipped with staff access doors identical to these ones described here above. These doors shall be surrounded with metallic panels removable to bring in equipment.

• Dimensions of these panels will depend upon equipment dimensions but when panels are removed the passage shall not be less than 2.80 m high and 1.20 m broad.

• These doors shall be equipped with louvres for circulation of cooling air. Note : In principle, access to medium voltage and low voltage bushings of each transformer is

interlocked with the position of the MV cubicle earthing isolator and with the position of the LV circuit breaker. If such interlock does not exist, the transformer room shall be equipped with a door locked when the MV earthing isolator is not closed or the LV circuit breaker not open.

3. TECHNICAL FLOOR

• A technical floor shall cover all the electrical room.

• It shall be designed for an even load of 1500 daN/sqm (15 kN/sqm) and a local load of 300 daN/sqm (3 kN/sqm) on a 25 mm by 25 mm area.

• It shall be made of modular panels (600 mm x 600 mm). Each panel shall be made of:

� a high density clipboard panel, at least 30 mm thick;

� a high pressure laminated surface;

� a PVC edge, or better aluminium, crimped around panel sides.

Page 9: SP Departmental Substations

DEPARTMENTAL SUBSTATIONS

Document STD.002.U04

Page 9/22

Rev. B

B

B

B

Panels shall be non flammable and shall be certified by the National Fire Protection Association (NFPA) or at least comply with ASTM standards.

• Panels shall be supported on a steel structure made of adjustable jacks and mobile supporting steel sections. Each steel item shall be protected from rust by hot dip galvanisation.

• Jacks shall be fixed to the base ground by bolts or glue. Their length shall be so that technical floor finish surface be at not less than 600 mm above supporting concrete slab. When necessary, additional steel sections shall be installed for reinforcing panels placed in cantilever, in order to keep resistance to here above mentioned loads. Technical floor installation is explained in section 10, drawing 5.

• A suction disc for lifting technical floor panels shall also be supplied in each electrical room as specified in section 6.4.

Note : For a revamping, if it is not possible to install a technical floor, the electrical room’s

ground shall be covered with a plastic material (tiles or bands) limiting dust emissions and reducing electrical shock hazards by insulating operators from the ground, or at least with insulating mats on front and back of each cabinet.

4. AIR-CONDITIONING AND PRESSURISATION

4.1. AIR-CONDITIONING

• Air-conditioning system for the electrical rooms shall be reliable and simple. Priority shall be given to reliability rather than to performance.

• In countries with a hot climate (when average day/night temperature exceeds 35°C during more than 7 days a year) double air-conditioners shall be used, one unit only being able to keep internal temperature under here after mentioned maximum temperature.

• Air-conditioning units will use water cooled condensers or be of the "split system" type with an air cooled condenser installed outdoors.

• Electrical equipment shall be protected IP55.

• Air-conditioning system shall be dimensioned to keep into the Electrical Room a temperature lower than or equal to 28°C . This requirement is for limiting the temperature inside the cabinets so that this average temperature over a period of 24 h does not exceed +35°C as required by standard IEC 60947-1. The air-conditioning power installed shall not be less than 100 W/m3 of room volume; it shall be sufficient to evacuate:

� the heat dissipated in the room,

� the heat flowing through the walls, ceiling, floor of the room,

� the heat of the air injected in the room by the pressurisation system.

Page 10: SP Departmental Substations

DEPARTMENTAL SUBSTATIONS

Document STD.002.U04

Page 10/22

Rev. B

B

• If batteries of lead-acid type are installed in the electrical room the ambient temperature of this room shall be limited to 20°C . Indeed, a temperature of 28°C would reduce consid erably its lifetime: raising the temperature from 20°C to 30°C divides by 2 the lifetime of a lead-acid battery. An alternative solution could be to install the battery in a separate room kept at 20°C maximum as it is common in incoming substations for feeding the HV switchgear control circuits.

• A heating system shall also be installed, if necessary, to keep the temperature above 15°C.

• Cool air shall be distributed from upside. Back air shall flow under the technical floor, passing through this floor by louvres to be installed at the opposite corner of the room to the air-conditioning unit. The Supplier will decide whether air distribution ducts should be installed for cool air.

• Please also refer to section 10, drawing 6.

4.2. PRESSURISATION

• Pressurisation of the electrical rooms is to avoid or limit dust ingress. This system shall be capable of keeping into the room a 20 mm water column (200 Pa) overpressure with a minimum air flow equal to 2 times the room volume each hour. This capability will be demonstrated by submitting to the Owner’s approval appropriate technical data (fan curve) about proposed equipment.

• Pressurisation equipment shall be mounted through the wall with an access for maintenance from the outside. It shall include:

� a static filter with an easy access for maintenance, generously dimensioned to avoid maintenance intervals shorter than three months. This filter shall stop any sedimentable dust particle (size above 10µm) and be of class EU4 (90 % weight efficiency). Self cleaning filters shall be proposed by the Supplier as an option;

� a low noise fan running at 1500 RPM at the maximum with a motor protected IP55;

� a fresh air inlet duct in the electrical room.

• The pressurisation system shall automatically be switched off in case of fire (please refer to section 5.2).

• Please also refer to section 10, drawing 7.

4.3. POWER SUPPLY Air-conditioning and pressurisation systems shall be fed from a single feeder from a lighting distribution board ; please refer to specification STD.002.U18 : “Lighting and Power Outlets”. The electrical cabinet protecting and controlling power supply to air conditioning and pressurisation equipment is included in this Supply.

Page 11: SP Departmental Substations

DEPARTMENTAL SUBSTATIONS

Document STD.002.U04

Page 11/22

Rev. B

B

5. LIGHTING AND FIRE DETECTION

5.1. LIGHTING

• Technical specification: substation lighting shall meet the clauses of specification STD.002.U18.

• Electrical Rooms shall be illuminated with fluorescent lamps (except for very high ceiling substations where it will be better to use high pressure sodium lamps). All these lighting fittings shall be controlled by a switch installed in the area access airlock. Emergency lighting blocks shall be installed inside this area above each access door and in the airlock. In large rooms, some additional emergency lighting blocks shall also be installed throughout the room to facilitate the exit.

• Transformer Rooms shall be illuminated with watertight fluorescent lamp fittings. These lighting fittings shall be controlled by switches installed close to each access door.

• Power outlets: at least two single-phase power outlets shall be installed in each electrical room and one in each transformer room.

5.2. FIRE DETECTION

• Automatic fire detectors: ionisation fire detectors shall be installed:

� in the electrical rooms above technical floor;

� in the electrical rooms under technical floor, protected by a wiremesh cover;

� in the transformer rooms above transformers.

The numbers of detectors shall be adapted to volumes to be monitored.

• Non automatic fire detectors: 1 push button protected by a breaking glass (IP65) shall be installed close to the access doors to the transformer rooms.

• Annunciators: 1 red lamp flashing lamp (IP 65) and 1 amovible signal, 100dB at 1m

• Monitoring: all the detectors of each substation shall be connected to a common monitoring panel installed in the Central Control Room. Each substation will be a separate monitoring area on this panel.

• Integration in an existing fire detection system: if the plant is already equipped with a general fire detection system the present supply shall be integrated into the existing system and fires annunciated on the existing general fire monitoring panel in the CCR.

• The fire detection system shall automatically switch off the pressurisation fan in case of fire (please refer to section 4.2).

• Test: each detector shall be tested regularly in accordance with standards applicable on the site. Equipment required for performing periodic tests is included into the Supply.

Page 12: SP Departmental Substations

DEPARTMENTAL SUBSTATIONS

Document STD.002.U04

Page 12/22

Rev. B

B

B

6. GENERAL ELECTRICAL CONTRACTOR

6.1. CONTROL AND SAFETY DEVICES In addition to Supplies and Services related to the process described in other specifications, the General Electrical Contactor shall supply and install:

• 3 MV emergency Shut-Down push buttons (MVESD). These push buttons, of large size red mushroom type, shall be installed:

� 2 inside the electrical room, close to each door (access door and emergency exit door),

� 1 outdoors, close to the access doors to transformer rooms.

Each of these push buttons shall trip the incomer of the MV switchboard installed in the electrical room, cause a Department Emergency Shut-Down (DESD) and be signalled in the CCR by an alarm message. The detail of these emergency shut-down circuits is given in specification STD.002.U13.

• A temperature switch initiating an alarm message in the Central Control Room informing the operator that the temperature in the electrical room is abnormally high.

• An alarm message in the Central Control Room informing the operator that the pressurisation fan is off (Warning alarm).

6.2. EARTHING As required by specification STD.002.U12, the General Electrical Supplier has to earth the metallic structure supporting the technical floor. This shall be performed by connecting each third supporting jack to an insulated 16 sqmm copper cable. This cable shall in turn be connected at both ends to the plant earthing grid or to the main earthing conductor in 2 different points.

6.3. CABLING

• Cables shall be installed in accordance with specification STD.002.U12 as well as with principles given in section 10 drawing 4.

• At the end of cabling any access into the departmental substation shall be filled in with fire resisting material as required by specification STD.002.U12.

Note : It is reminded that no cable should be installed directly on the ground. This is also valid

for cables running under the technical floor.

6.4. SAFETY EQUIPMENT

• The Supply shall include for each substation safety equipment required by applicable regulations. It shall include at least:

� Personal Protective Equipment:

- 2 boxes with insulating gloves

- 1 MV insulating stool / platform

Page 13: SP Departmental Substations

DEPARTMENTAL SUBSTATIONS

Document STD.002.U04

Page 13/22

Rev. B

- 1 voltage tester up to 22 kV

- 1 MV rescue insulated stick perch.

� warning signs (in local language),

� suction disc for lifting technical floor panels;

• The Supply shall also include the fire extinguishers as required by applicable regulations, except if these extinguishers are part of the civil work contract or of a general fire protection contract.

7. DOCUMENTS The Supplier shall supply following documents :

• Substation general lay-out

• Civil works guide drawing

• Cable routings lay-out

• Air conditioning and pressurisation systems:

� Air conditioning calculation note;

� Pressurisation system technical data;

� General lay-out;

� Electrical diagrams;

� Erection and maintenance leaflets.

� Lighting design documents

� Fire detection system design documents. These documents shall comply with the requirements of specification STD.002.U02, Preparation of Electrical Documents, except for leaflets and standard documents from the manufacturers.

8. GUARANTEE Guarantee on equipment supplied shall cover a minimum period of 24 months after Provisional Acceptance, with a maximum of 30 months after the equipment has been delivered at site.

9. DATA SHEET Values to be mentioned in boxes shaded and marked with sign are to be given by the Owner or by the main Contractor.

Page 14: SP Departmental Substations

DEPARTMENTAL SUBSTATIONS

Document STD.002.U04

Page 14/22

Rev. B

CUSTOMER: SUPPLIER : PROJECT: DATA SHEET PROJECT N°: AIR-CONDITIONING / PRESSURISATION OFFER: EQUIPMENT: DATE : Air-conditioning system 1 Equipment type 2 Manufacturer 3 Stand-by device Yes/No 4 Electrical power kW 5 Full load cooling capacity kW 6 Air flow Cum/h normal 7 Design with ducts, louvres, deflection grids Yes/No 8 Condensation type 9 Water flow (if water cooling) l/h 10 Humidity control system Yes/No 11 Dimensions mmxmmxmm 12 Weight kg 13 Heater power (if required) kW Pressurisation system 14 Filter type 15 Filter cleaning system type 16 Dust storage system 17 Filter weight efficiency % 18 Operpressure maintained to : mm H2O 19 Air flow Cum/h normal 20 Electrical power kW 21 Fan sound pressure DB(A) 22 Dimensions mmxmmxmm 23 Weight kg 24

Deviations from this specification

Note : The Supplier is requested to fill in a data sheet for each type of equipment proposed and to

return it with his proposal.

Page 15: SP Departmental Substations

DEPARTMENTAL SUBSTATIONS

Document STD.002.U04

Page 15/22

Rev. B

10. TYPICAL DRAWINGS All free space dimensions indicated in the following drawings are minimum requirements.

S U - E lec tr ica l room

T rans form er room

E C E C

U P

V S 1 V S 2

C P 2 C P 2

C P 1

T F 2

T F1

LT

e x tens ion M C

M CM C

D eta il 1 :

- S m oke detec tor

M ate ria l A ccess&

S a fe ty D oor

- see D e ta il 2

- see D e ta il 4

- see de ta il 3

T F 3

Pre

ssur

isat

ion

- see de ta il 2

Doc

umen

tatio

n

Tab

le

D MA M

A C

D H D H D H D H D H

M C

M C

M C

M C

M CM C M C

see D e ta il 1

S U -

C ab le trenches

Cab

le tr

ench

es

AU

1 1000

1200

033

00

1500

1 700

1500

1500

800m in .

800

min

. 8 00m in .

800m in .

A ccesso ries- Indoors L igh ting = 250 lux- T echn . F loo r (see D rw g.)- C ab les a lw ays to be la id on cab le trays (see D rw g .)- E m ergency S hu t-dow n Push-bu tton- A ir cond ition ing + P ressu risa tion

D R A W IN G 1

see D e ta il 1

H ot a ir exhaus t

extens ion

ex tension

see D e ta il 1

see D e ta il 5

A

A

A irlock

E m bedded P ipes

B B

see D e ta il 6

M V E m ergency S hut D ow npush bu tton (M VE S D )

500

min

.

Cab

le tr

ench

es

see D e ta il 1

Cab

le tr

ench

es

Typ ical Boards D im ens ions

L ighting D istr ib . B oardLTA ir-condition ing sys temA U -

2000kV A -T ransfo rm er

W eigh feede r boa rd

V S D - 1400kW

V S D - 400kW

M V -C apac itor

LV - C apac itor

M V S w itchboa rd

16kV A aux. T ransf.

1000kV A -Transfo rm er

C P 1

V S 1

E C

V S 2

C P 2

TF 1

TF3

TF 2

D H

U P

1550

800

5230

2100

800

U P S

520

2120

1850

750

600

D ev ice

M arsha lling B oa rd

C ode

A M /D M

M C

A C

M C C

A C C

1000

1200

1200

Length(m m )

- -

- -

340950

400

600

600

400

-

2800

-

870

342

1180

1000

1220

700

96

3700

2300

-

-

400

400

400

D epth(m m )

-

-

-

W e ightkg ) D eviceC ode

Leng th(m m )

W eigh tkg )

D ep th(m m )

FA F ire a la rm push bu tton

FA

Page 16: SP Departmental Substations

DEPARTMENTAL SUBSTATIONS

Document STD.002.U04

Page 16/22

Rev. B

Detail 2:Door Standard Dimensions:

900*2100

Screwed Plate extensions around doorto ensure easy material access

Detail 4:Door with Louvre forTransformer Room

Anti- Panic Barno key lock

2100

1200900

Detail 3:

2800

OutdoorsGround Level

DRAWING 1 (Continued)

Floor level

Page 17: SP Departmental Substations

DEPARTMENTAL SUBSTATIONS

Document STD.002.U04

Page 17/22

Rev. B

SECTION A-A

Side Walk

Door Mat

Airlock

DRAWING 1 (Continued)

Thermal Insulation

SECTION B-B

TF2TF3

CP1

See Detail 5

Detail 5 Detail 6

Rails Anchoringframe for retaining leaking oil

Seal

See Detail 6

Thermal Insulation

Page 18: SP Departmental Substations

DEPARTMENTAL SUBSTATIONS

Document STD.002.U04

Page 18/22

Rev. B

Alternative Solution(When there are risks of cable room's flooding)

DRAWING 3

MV Switch-Board

MCC

Side Walk

Basic Solution(General Case)

DRAWING 2

MV Switch-Board

MCC

To be filled in after cables'installation

To be filled in after cables'installation

3000

3000

100

100

1000

600

600

Thermal Insulation

Page 19: SP Departmental Substations

DEPARTMENTAL SUBSTATIONS

Document STD.002.U04

Page 19/22

Rev. B

SU - Electrical room

Transformer room

UP

CP2 CP2

CP1 TF2

TF1

LT

extension MC

MCMC

Detail 1:Cable crossing to be made within 2 levels

by means of cable bridge

TF3

AC DM

DH DH DH DH DH

MC

MC

MC

MC

MCMC MC

SU -

Cab

le tr

ench

AU

CE

ME

NT

PLA

NT

SID

E

Legend 3:Field bus cables to be installed in steel pipes

unless they have a metal armor

Detail 2:

MV - Cable tray

LV - Cable tray

Control Cable tray

DRAWING 4

AM

Embedded pipes

DC

CFire Alarm Detector

D

Cab

le tr

ench

Cab

le tr

ench

Cab

le tr

ench

VS2EC VS1EC

Fire Alarm Detector

Emergencylighting block

Emergencylighting block

Lighting fixtures

Lighting fixtures

Page 20: SP Departmental Substations

DEPARTMENTAL SUBSTATIONS

Document STD.002.U04

Page 20/22

Rev. B

Embedded pipes from " Electrical Room "to "Production Area " (field)

SECTION C-C

DRAWING 4 (Continued)

SECTION D-D

Sidewalk

Plant

SECTION E-E

Plant Electrical Room

Electrical Room

Sidewalk

Concrete

See Detail 7

Detail 7

Control

LV

MV

Pipes end to be filled in after cables installation

Cable ladder

Pipes end to be filled in after cables installation

600

1000

300

600

900

200 200 150

200

150

200

45°

Page 21: SP Departmental Substations

DEPARTMENTAL SUBSTATIONS

Document STD.002.U04

Page 21/22

Rev. B

DRAWING 5

600

600

Fire AlarmDetector

Fire AlarmDetector

600

600

16mm²

30mm Thickness Adjustable Jacks

Screwed or Stuck

Base concrete

Wire mesh protection

Page 22: SP Departmental Substations

DEPARTMENTAL SUBSTATIONS

Document STD.002.U04

Page 22/22

Rev. B

Pressurisation

DRAWING 7

Air Conditioning

DRAWING 6

Fresh Air

OutsideAir Dust

Filter

Cooled Air Flow

Air Condenserif no cooling water used

(Split system)

Thermal Insulation

Thermal Insulation