Sower's Lecture Atlanta May 8, 2012 - Geosystem Gatechgeosystems.ce.gatech.edu/abstracts/Bengt_H_...

37
Wick Drains and Piling for Cai Mep Container Port, Vietnam Bengt H. Fellenius Sower's Lecture Atlanta May 8, 2012

Transcript of Sower's Lecture Atlanta May 8, 2012 - Geosystem Gatechgeosystems.ce.gatech.edu/abstracts/Bengt_H_...

1

Wick Drains and Piling

for Cai Mep Container

Port, Vietnam

Bengt H. Fellenius

Sower's Lecture

Atlanta

May 8, 2012

The Mekong

3

The General Area Saigon/HoChiMinhCity

4

Thi Vai Port

Cai Mep Port

5

Artist View

6

CFSCG

The site of the new container facility extends over an 800 m by 600 m area along the Thi Vai River

7

Locations of Buildings, Boreholes, and Settlement Points

0

200

400

600

800

1,000

1,200

0 100 200 300 400 500 600 700 800 900 1,000

EAST-WEST

NO

RT

H-S

OU

TH

TCM and CPTU

SS

BH

Piezometers

Extensometers

N

CFS

C-Gate

M-Shop

Substation

BH-14

8

Soil Profile

0

5

10

15

20

25

30

35

40

45

50

0 20 40 60 80 100

WATER CONTENT (%)

DE

PT

H (m

)

0

5

10

15

20

25

30

35

40

45

50

0.0 1.0 2.0

CONE STRESS, qt (MPa)

DE

PT

H (m

)

0

5

10

15

20

25

30

35

40

45

50

0 20 40 60 80 100

GRAIN SIZE DISTRIBUTION

DE

PT

H (m

)

CLAY SILT

SAND

wn BH-14

SILTCLAY

GRAVEL

wP wn wL

wn BH-14wn BH-76

CPTU-26

+ 3.5 m

GW & GL

CONE STRESS, qt (MPa)

9

CPTU Sounding Results

0

5

10

15

20

25

30

35

0 2 4

Cone Stress, qt (MPa)

DE

PT

H (m

)

0

5

10

15

20

25

30

35

0 20 40 60 80 100

Sleeve Friction, fs (KPa)

DE

PT

H (m

)

0

5

10

15

20

25

30

35

0 500 1,000 1,500

Pore Pressure (KPa)

DE

PT

H (m

)

0

5

10

15

20

25

30

35

0 1 2 3 4 5

Friction Ratio, fR (%)

DE

PT

H (m

)

10

Results from a large series of consolidation tests show the soil to be

very compressible, normally consolidated

1.00

1.20

1.40

1.60

1.80

2.00

2.20

2.40

10 100 1,000

Stress (KPa)

Vo

id R

ati

o (-

-)

m = 5

mr = 55

e0 = 1.92

Cc = 1.40

DEPTH: 9 m0

5

10

15

20

25

30

35

0 2 4 6 8 10

Modulus Number, m

DE

PT

H (m

)

From consolido-

meter Test

From CPTU

Sounding

Typical example of results

CR = 0.48

11

The highest water level expected at the site is Elev. +4.0 m, which level is about 0.5 m

above the ground surface. Therefore, the ground elevation will be raised by about 2.0 m

to Elev. +5.5 m in order to avoid flooding and to create a suitable foundation surface.

Risk for flooding in the area is real and the inundation can be severe,

as illustrated by the flooding of the Fall of 2011. The above shows an

areal photo of a Honda factory parking lot in Bangkok (October 2011).

12

Because of the thick very compressible clay and silt layer, the

2+ m thick fill placed to raise the land will cause significant

settlement, which would continue for a very long time. To

shorten that time, vertical drains (wick drains) were installed

to 37 m depth across the site (in some places into the sand,

in other places a bit of the clay was left between the drain tip

and the sand). Moreover, a temporary surcharge was added

raising the surface to Elev. +8 m through Elev. +10 m, i.e., an

additional 2.5 m to 4.5 m of fill height.

13

FIL

L H

EIG

HT

TIME

SE

TT

LE

ME

NT

Surcharge removed

when 80% – 90%

consolidation is

achieved

For case of surcharge

not removed

For case of surcharge

removed

For case of surcharge

not removed

Paving and

roadways

For case of surcharge

removed

80 % to 90 % of

total consolidation

settlement

ORIGINAL GROUND SURFACE

ORIGINAL GROUND SURFACE

Amount of fill placed

FILL

SETTLEMENTInitial compression and

consolidation settlement

Principle of the wick drain and surcharge

soil improvement scheme

14

The wick drain used for the project is a 100 mm wide

and 3 mm thick and consists of a corrugated, 0.15 mm

thick, plastic core wrapped with a synthetic filter.

15

Fill height and ground surface settlement until one month before

start of driving piles for the building foundations

16

Fill height and pore pressures measured June 24, 2009, through

September 17, 2010 (Days -527 and -77) at the CFS building

The tip elevations are

per original installed

depth. The settlement

of the piezometer tips

is not included.

17

0

5

10

15

20

25

30

35

40

0 50 100 150 200 250 300 350 400D

EP

TH

(m

)

June 24, and Sep 18, '09 just before adding surcharge (Days -504 and -447).

Sep 17, '09 last reading (Day -77).≈U0

+ 5.0 m

PORE PRESSURES JUNE 24, 2009 THROUGH SEP 17, 2010 (KPa)

Dec 1, '09 maximum reading (Day -365).

Distribution with depth of the pore pressures at the CFS building

FILL ELEVATION

18

0

500

1,000

1,500

2,000

2,500

3,000

3,500

4,000

-800 -700 -600 -500 -400 -300 -200 -100 0

DAYS

Se

ttle

me

nt

(mm

)

Container Freight Station, CFS

and Container Gate, CG

SS-32

SS-39

SS-30

SS-108

SS-29

SS-28SS-104

SS-38Surcharge

removal

Ground surface settlements 10-12-01

Start of pile

driving for

the CFS and

CG buildings 09-01-01

19

View on October 4, 2011, taken from the south-east end of CFS building

showing some of the about 1,680 piles driven for the CFS.

20

The building foundations were placed on precast, ordinary reinforced, concrete piles with a

square 400 mm cross section made up by 10-m segments spliced in the field by welding steel

end-plates together. For Buildings CFS and CG, the piles were driven to 28 m and 18 m depth,

respectively. The intended working loads were 347 KN for the CFS building and 265 KN for the

other buildings. One pile at each building was subjected to a static loading test. The test piles

were not instrumented, and the test schedule included unloading/reloading cycles and varying

load hold durations. Therefore, the test results have very limited use for the design.

Load-movement curves from static

loading tests at CFS and CG buildings

The static loading tests (CFS and CG) were carried

out in September 2010, nine months after pile driving

21

22

23

The below figure shows the settlements measured by the SS-plates at or near the buildings

until November 15, 2011. The zero date is December 1, 2010, the day of the start of the pile

driving for the CGS building. Driving was completed on January 24 at the CG building.

0

500

1,000

1,500

2,000

2,500

3,000

3,500

4,000

-800 -700 -600 -500 -400 -300 -200 -100 0 100 200 300 400 500

DAYSS

ett

lem

en

t (m

m)

Container Freight Station, CFS

and Container Gate, CG

SS-32

SS-39

SS-30

SS-108

SS-29

SS-28

SS-108

SS-104

SS-38

Surcharge

removal

Pile

driving

24

2,000

3,000

4,000

5,000

6,000

7,000

8,000

9,000

10,000

-800 -700 -600 -500 -400 -300 -200 -100 0 100 200 300 400 500 600

DAYS

EL

EV

AT

ION

(m

m)

ORIGINAL GROUND SURFACE

MEAN WATER LEVEL

MAXIMUM WATER LEVEL

ELEV. +5.5 m

SS-28

SS-29

PILE

DRIVING

AS-PLACED FILL HEIGHT

0

500

1,000

1,500

2,000

2,500

3,000

3,500

4,000

-800 -700 -600 -500 -400 -300 -200 -100 0 100 200 300 400 500 600

DAYSS

ett

lem

en

t (m

m)

Red heavy lines are

SS-28 and SS-29

All values are normalized to

the 2,900 mm average

settlement at Day 0

Start

placing fill

End placing

surcharge Removing

surcharge

Pile

driving

AT CFS and CG

400 mm

25

0

50

100

150

200

250

300

350

400

500 550 600 650 700 750 800 850 900

EAST-WEST

NO

RT

H-S

OU

TH

SS-29

SS-34

SS-234

SS-22

SS-28

SS-33SS-233

SS-230

SS-24

SS-30

SS-23

SS-108

SS-36

SS-37

SS-236

SS-235

SS-227

SS-102

SS-228

CFS

C-Gate

CONTAINER FREIGHT STATION, CFS

AND CONTAINER GATE

Ext-09

Pz-09

Pile head settlements and benchmark

settlements at the building locations

Container Freight Station (CFS) and Container Gate (CG)

0

500

1,000

1,500

2,000

2,500

3,000

3,500

4,000

-800 -700 -600 -500 -400 -300 -200 -100 0 100 200 300 400 500

DAYS

Se

ttle

me

nt

(mm

)

Container Freight Station, CFS

and Container Gate, CG

SS-32

SS-39

SS-30

SS-108

SS-29

SS-28

SS-108

SS-104

SS-38

Surcharge

removal

Pile

driving

0

500

1,000

1,500

2,000

2,500

3,000

3,500

4,000

-800 -700 -600 -500 -400 -300 -200 -100 0 100 200 300 400 500

DAYS

Se

ttle

me

nt

(mm

)

Container Freight Station, CFS

and Container Gate, CG

SS-32

SS-39

CFS Average of

Piles added to

SS29

SS-30

C-Gate Average of

Piles added to

SS108

SS-108

SS-29

SS-28

SS-108

SS-104

SS-38

Surcharge

removal

Pile

driving

26

Settlements measured for SS-plates and piles at the

CFS and CG buildings until November 15, 2011

2,500

2,600

2,700

2,800

2,900

3,000

-100 -50 0 50 100 150 200 250 300 350 400 450 500

DAYS

Se

ttle

me

nt

(mm

)

CFS Average values of pile head

settlement added to SS-29

CG Average values of pile head

settlement added to SS-108

SS-108

SS-29

27

0

5

10

15

20

25

30

35

40

0.0 0.5 1.0 1.5 2.0 2.5 3.0

SETTLEMENT (m)

DE

PT

H (m

)

July 17, 2009 — January 14, 2011

+ 5.0 m

Zero Reading of was taken on July 17, 2009. The

settlement plates located within the CFS footprint then

showed that 0.6 m settlement had already occurred

(since February 20, 2009). Total plate settlement on

January 14, 2011, was 3.08 m. The curves show

readings spaced about one month apart.

First Fill

Surface

June 29, 2010, after the

temporary surcharge

had been removed

Relative

settlement

between anchor

points during

last five months

of monitoring

R≈4 mm/m

R≈6 mm/m

R≈30 mm/m

R≈12 mm/m

Settlement distribution measured in an extensometer station (multi-anchor points) outside the CFS

building during 18 months: from July 17, 2009 (one to three months after start of placing fill) through

January 14, 2011, one month after piles were driven near the location of the extensometer station.

28

0

20

40

60

80

100

120

140

0 5 10 15 20 25 30 35 40

MONTHS

ST

RE

SS

(K

Pa

)

Stress from

as-placed fill

(approximated)

Removal of Surcharge

Stress reduction due to

settlement and buoyancy

Stress from fill adjusted for

settlement and buoyancy

Stress from fill elevation

From measured fill height and settlement to input to analysis

29

UniSettle4 input and results [[email protected]]

30

UniSettle4 input and results [[email protected]] Input alternatives

31

0

500

1,000

1,500

2,000

2,500

3,000

3,500

4,000

0 6 12 18 24 30 36 42MONTHS

SE

TT

LE

ME

NT

(m

m)

Measured

settlement

Settlement calculated with

the drains assumed not to

function below 20 m depth

Settlement calculated

with the drains

assumed functioning

along the full depth

Piles

driven

Surcharge

removed

Immediate

Compression

Secondary

Compression

Full fill height

reached

32

28 m

CFS

Pile

CLAY

SAND

DEPTH

SETTLEMENT

Settlement

of the CFS

Building for

28 m Pile

Neutral

Plane

28 m

CFS

Pile

40 m

CFS

Pile

CLAY

SAND

DEPTH

SETTLEMENT

Settlement

of the CFS

Building for

28 m Pile

Neutral

Plane

Neutral

Plane

33

View on October 4, 2011, taken from the south end of CFS building

showing some of the about 750 piles driven for the CFS building. In

the background, lengthened piles are being driven for the CG building.

39

Photos from the driving

of piles with extension

40

41

CONCLUSIONS

The most probable cause to the continued consolidation below about 20 m depth is that large soil

stresses have squashed the wick drains preventing the drains from functioning properly.

The consequence is that the overall area and the piles will continue to settle even if no new loads

are placed. But there will be new loads, so ...

The problem with the piled foundations can be (and was hopefully) resolved by lengthening the

piles to bring the neutral plane (the depth to the settlement equilibrium) into the non-settling sand

below the clay.

It is not realistic to install new and better drains or arrange, say, for vacuum treatment to get the

consolidation to occur quickly. The site will have to live with continuing to add fill to compensate

for excessive settlement, which will in turn add consolidation, and to suffer the maintenance

actions that regularly will be required for non-piled foundations.

The monitoring scheme was designed to confirm that the wick drain method worked. When the

measurements showed that the method did not work, the method became very much inadequate,

and it could not be of any assistance for selecting a solution to the problem. Every monitoring

programme should have redundancy and be designed to resolve issues should the design show to

be unsuccessful. How to resolve the question "what if we're wrong?" should always be kept in

mind and in the planning of a monitoring programme.

42

The Lotus — Vietnam's National Flower

Thank you for your attention