Agenda for 133rd OCC Meeting to be held on 13.07.2017 at SRPC Bengaluru Page 1
Southern Regional Power Committee Bengaluru
Agenda for the 133rd Meeting of Operation Coordination Committee
to be held at SRPC Bangalore on 13th July 2017
1 Confirmation of the Minutes of the 132nd Meeting of OCC of SRPC held on 9th June 2017 at
SRPC, Bengaluru.
2 Monthly Outage Plan/ Annual Outage Plan
2.1 ISGS/CGS: Generating Units
a) Shut Down Proposals for July/August 2017
b) Shut Down carried out during June 2017 along with reason for deviation, if any.
2.1.1 Reschedule of TSTPS Unit-4 Overhauling 2.1.1.1 TSTPS Unit-4 planned shutdown from 01.06.17 to 15.07.17 (45 days) for overhauling &
boiler modification was approved in 131st OCC meeting. NTPC vide letter dated 30.05.2017 referring a delay in mobilization of Tower Crane required for Boiler Modification work requested for Unit-4 shutdown re-scheduling for 19.6.17 for 45 days (till 02.08.17) which was approved by 132nd OCC Forum. The Unit was not taken out on 19.06.2017.
2.1.1.2 Further NTPC vide letter dated 30.06.2017(Annexure-2A) informed that TSTPS Unit-4 shutdown for overhauling and boiler-modification is getting delayed in completion of erection of tower crane. NTPC requested that rescheduling of TSTPS Unit -4 shutdown from 10.07.2017 for 45 days may kindly be considered favourably and approved.
2.1.2 Reschedule of Neyveli TS II Unit II Overhauling 2.1.2.1 In the 132nd OCC Meeting held on 09.06.2017 TPS II Unit 2 shutdown was approved for
25 days from 26.06.2017 for Annual Overall works. NLC vide letter dated 01.07.2017(Annexure-2B) had informed that as there was slight delay in firming up the maintenance contract, the planned shutdown could not be commenced on the approved date. The unit now is planned to been taken out of bars for planned works from night shift of 01.08.2017. All efforts will be taken to complete the maintenance works at the earliest and bring back the unit into service.
2.1.3 NTPL Unit II Shutdown from 01.08.2017 to 06.08.2017
NTPL vide letter dated 29.06.2017 (Annexure-2C) had requested for approval of shutdown of Unit II from 01.08.2017 to 06.08.2017 for Boiler Licence Renewal. It was informed that the validity of Boiled License is up to 02.08.2017.
2.2 ISTS/State Sector Transmission Lines and Elements
2.2.1 All utilities are to submit the S/D proposals for the subsequent month by 3rd of the
current month. Shutdown requests for the same month needed to be avoided. An outage
coordination group had been created ([email protected]) for
review of the previous OCC approved shut downs (construction/critical).
2.2.2 PGCIL – SR2 agenda for the 133rd OCC meeting(Annexure-2D)
Agenda for 133rd OCC Meeting to be held on 13.07.2017 at SRPC Bengaluru Page 2
The following outages are requested for inclusion for approval in the 133rd OCC meeting
to be held at Bengaluru on 11.7.2017. These shutdowns have been forwarded in the
standard format also.
1. Shutdown of Thiruvalam GIS Station (765 kV Side only):
As per IEC-62271-203, the impulse test of voltage 140 kV has to be injected for 765 kV GIS
main circuit for checking the insulation strength of GIS system. For this test, complete GIS
outage (2 nos. 1500 MVA ICTs and 2 nos. 765 kV lines) is stipulated for night time only
(18:00 Hrs to 06.:00 Hrs) for 10 days from 16.07.2017 to 25.07.2017. The shutdown may
kindly be approved under Deemed Available as it is done for system improvement.
2. Shutdown of Trichy ICT-1&2:
Trichy ICT-2 shutdown is required as per details given below for replacing of old 245 kV CB
with new CB under approved Additional Capitalization works. The shutdown already
approved in 131st OCC but TNEB didn‟t concur on the day (04.06.17) due to VIP visit to
Trichy city.
Sl.No. Name of Element S/D Period Remarks
ii Trichy ICT-2 24.07.2017.
27.07.2017.
ICT-2 will be in service through the 230 kV
Bus coupler of M/s.TANTRANSCO from to
26.07.2017.
3. Shutdown of Somanhalli ICT-3:
Shutdown is required on 19.08.17 for warranty testing before completion of one year of
service. It is requested to accord for the shutdown as it is for warranty tests.
4. Shutdown of 400 kV Kolar-Hosur-I, 400kV Kolar-Hoody -II & Palakkad-Tricur-1&2:
Shutdown of 400 kV Kolar-Hosur-I, Kolar-Hoody -II & Palakkad-Tricur-1&2 required on
08.08.17, 10.08.17, 27.07.17 & 28.07.17 respectively for relay configuration and testing of
revised over voltage settings as per the SRPC guidelines. The shutdown may kindly be
accorded deemed as it is for system requirement and online testing on these lines is not
advisable as they are connected to critical substations like Kolar & Palakkad.
2.2.3 Non-availing the OCC approved shut downs
SRLDC to furnish the approved vs availed percentage of shut down approved for June 2017. States/Utilities to furnish the reasons for non availing the shutdown.
2.2.4 All the utilities to furnish the details/deviations with respect to their Annual Outage plan
schedule VS maintenance carried out on a monthly basis as this information is required
for the Annual Outage Plan Deviation Report being submitted to CERC.
3 LGBR for upcoming five months
3.1 The following details to be furnished for discussion:
Agenda for 133rd OCC Meeting to be held on 13.07.2017 at SRPC Bengaluru Page 3
Schedule of Hydro, Thermal Generation, RES, Purchases, Anticipated Consumption etc.
Shortfall/Surplus, if any and how the same is proposed to be met.
Arrangements to meet the Demand and Energy surplus/deficit.
Status review of Development of State of the Art load forecasting tools as per clause
5.4.2 of IEGC.
Load Generation Balance in real time.
(Item No.3 of enclosed SRLDC letter dated 28.06.2017).
3.2 LGBR for upcoming five months & TTC/ATC computations
3.2.1 All states were requested to furnish PSSE base case for November 2017.
The following details are to be updated:
State 5 months LGB
Converged PSSE Base case
ATC/TTC Computation furnished to SRLDC
ATC/TTC Computation posted on SLDC website
Nodal Officer details
AP Being Furnished
TS
KAR
TN
KER
(Item No. 3 of enclosed SRLDC letter dated 28.06.2017).
4 Review of Power Supply Position /Inflows
Constituents/ Generators to furnish the reasons for deviation:
a) Actual with respect to anticipated (MW & MU) for availability and requirement.
b) Generation variation category wise with respect to MoP targets/LGBR figures.
c) Inflows (MU) to major reservoirs: Actual w.r.t. 10 year moving average and w.r.t.
same month last year.
d) Reasons for demand -supply gap and its variation
5 MAJOR ISSUES
5.1 Presentation by States on Operational Issues
5.1.1 It had been decided in the 126th OCC Meeting that all States/Generators/Powergrid may
kindly submit the presentation in prescribed template and specific issues needed to be
highlighted separately which would be deliberated. The statistics furnished in the
presentation were valuable and used in preparing the minutes.
5.1.2 In the 131st OCC Meeting SRPC had requested that States may kindly furnish the status of
SCADA visibility of newly commissioned Wind/Solar Generators to SLDC/SRLDC along with
LVRT Status.
Agenda for 133rd OCC Meeting to be held on 13.07.2017 at SRPC Bengaluru Page 4
5.1.3 SRLDC had requested that states may kindly upload their presentation by 5th of every month
so that SRLDC can compare with their information/data which will help in better
discussion/analysis of the issues.
5.2 High Voltage in Telangana Control Area
5.2.1 SRLDC vide letter dated 19.05.2017 had highlighted high voltage in the various pockets of
SR grid and SLDCs of SR were requested to take up the matter with the State
Generators/IPPs and with the STU/Intra State Entities so as to ensure reliable operation of
the power system.
5.2.2 SRLDC vide letter dated 22.06.2017(Annexure-5A) had observed the following with respect
to Telangana.
At present, with the onset of monsoon, the high voltage scenario has further become
intense in Telangana Control area.
Most of 400 KV stations, namely Nizamabad, Mamidapalli, Malkaram, Bhoopalapally,
Gajwel, Singareni, Suryapet, Srisailam, Shankarapally, Dindi and Mahaboobnagar
are predominantly high voltage areas. This is causing tripping of 400 kV lines on
Overvoltage and forcing the lines to be kept open on high voltage for long duration
as a regular phenomenon. The seriousness of the problem can be seen from
Annexure I which gives the list of lines tripped / kept open due to high voltage since
01.6.2017.
The list of buses operating for a longer duration of time at voltage > 420 kV since
01.6.2017 is given below:
Sl.No. Station % of time above 420 kV
1 400 kV Suryapet 63
2 400 kV Bhoopalapally 57
3 400 kV Dindi 50
4 400 kV Shankarpally 31
5 400 kV Singareni 26
In a recent event on 08.06.2017 @05:00 Hrs, the Srisailam 400 kV bus 2 went dead
due to tripping of lines on high voltage.
The list of reactors to be commissioned in Telangana system is given below:
Sl.No. Station % of time above 420 kV
1 Mamidapalli, 125 MVAR 36th SC Meeting – Yet to be commissioned 3 Shankarapally 125 MVAR
4 Mahaboobnagar 125 MVAR
5 Malkaram 125 MVAR
5.2.3 SRLDC vide letter dated 22.06.2017(Annexure-5B) had observed the following with respect
to Andhra Pradesh
At present, with the onset of monsoon, the high voltage scenario has further become
intense in AP Control area.
Most of 400 KV stations, namely Satenapally, K.V.Kota Jammalamadugu,
Urvakonda, Kurnool, Ghani, Gooty stations and 765 kV stations namely NPS &
Kurnool, 765 stations are predominantly high voltage areas. This is causing tripping
of 400 kV lines on Overvoltage and forcing the lines to be kept open on high voltage
for long duration as a regular phenomenon. The seriousness of the problem can be
Agenda for 133rd OCC Meeting to be held on 13.07.2017 at SRPC Bengaluru Page 5
seen from Annexure I which gives the list of lines tripped / kept open due to high
voltage since 01.6.2017.
The list of buses operating for a longer duration of time at voltage > 420 kV since
01.6.2017 is given below:
Sl.No. Station % of time above 420 kV
1 400 kV Jammalamadugu 80
2 400 kV Urvakonda 75
3 400 kV Kurnool 59
4 400 kV Ghani 52
5 400 kVGooty 30
5.2.4 In a recent event on 19.06.2017, the Urvakonda 400 kV bus went dead due to tripping of
lines on high voltage causing bottling up of wind generation for nearly two days.
5.2.5 The list of reactors to be commissioned in AP system is given below:
Sl.No. Station % of time above 420 kV
1 Vemagiri 125 MVAR 36th /39th SC Meeting – Yet to be commissioned
2 Kurnool 125 MVAR
3 Kalpakka 125 MVAR
4 VTPS Stage IV 125 MVAR
5 Chitoor 125 MVAR
6 VTPS 125 MVAR
5.2.6 It is therefore requested that the matter may please be taken up with the State Utilities /
IPPs/State Generators for ensuring the compliance of the Grid Code and accelerating the
commissioning of the above reactors.
5.2.7 All the measures such as MVAR absorption by the Conventional and RE generators,
commissioning of reactors and staggering of over voltage trip settings in all the transmission
lines as advised by SRPC may be taken up in earnest.
5.3 High Voltage in Kaiga Bus
5.3.1 SRLDC vide letter dated 15.06.2017(Annexure-5C) had brought out the following regarding
high voltage issues at Kaiga.
The pocket comprising of Kaiga, Narendra and Guttur is predominantly high voltage area in Karnataka. The issue of high MVAR injection by Kaiga Unit 3 & Unit 4 and the installation of reactors (2x125 MVAR) are under discussion since October 2016 in special meetings, OCC monthly meetings and in TCC/SRPC meetings.
During the Meetings, Kaiga have intimated that due to stator winding issue in Unit 3, absorption of MVAR is not possible. It was agreed that Unit 3 would operate without injecting MVAR, however other units would absorb as per capability.
Despite this, Kaiga U3 and U4 continue to inject MVAR, even at high voltages as given below:
1) MVAR injection by Unit 3 is in the range of 60-70 MVAR 2) MVAR injection by Unit 4 is in the range of 10-15 MVAR
The onus of ensuring that the generating units respond to the bus voltage by absorbing/generating MVAR as per the capability curve lies with the generator.
SRLDC, as a System operator, has the only option to open the lines to contain the
high voltage in this situation which will deplete the network and cause evacuation constraints of Kaiga generation. It is unfortunate that Kaiga Station insists on passing
Agenda for 133rd OCC Meeting to be held on 13.07.2017 at SRPC Bengaluru Page 6
the responsibility to the grid rather than ensuring compliance to the grid code and good utility practices.
At present, with the onset of monsoon, SR grid is experiencing high voltage throughout the grid. In this scenario, there is a need for proactive action by Kaiga Generating Station. Measures such as resolving MVAR absorption of Kaiga units with the OEM and commissioning of 2x125 MVAR reactors at Kaiga may be completed on emergency basis.
5.4 Request for enhancement in schedule to enable measuring of SPM, SOX & NOX
values by consultant.
5.4.1 NLC TPS II vide letter dated 01.07.2017(Annexure-5D) informed that in order to retrofit the
units of TPS-II for adherence to MoEF norms, M/s.MECON have been appointed as
Consultant by NLC. The consultant is now in the process of assessing the status of the units
by testing. The consultant requires that the unit under testing be operated at full load to
collect samples for examination. The tests in Stage-II (4x210MW) units have commenced on
30.6.2017 and will be completed in eight days and will be followed by Stage-I (3x210MW)
Units which will be completed in six days. It is not possible to proceed testing, since most of
the period the schedule is at Technical Minimum level. To enable us to offer one unit for
testing in full load at a time, it is requested that the schedule now at technical minimum may
please be raised further by an additional schedule of 80 MW between 08.00 hrs to 24.00 hrs
from 03.7.2017 to 08.7.2017 in TPS-II, Stage-II. As the process of testing and retrofitting on
the advice of the consultant is statutory. It is requested that NLCs request may be given due
cognizance and considered favourably. Beneficiaries are requested to given their consent for
enhancement of schedule during testing period. The exact duration of testing in TPS-II,
Stage-1 Units will be communicated to SRLDC after finalizing the schedule.
5.5 The methodology for certification of State Transmission lines (50% criteria)
5.5.1 As per the deliberations in the 31st SRPC meeting the methodology for certification (50%
criteria) had been discussed and approved by SRPC. In this regard, studies were carried out
by SRPC Secretariat along with SRLDC. Based on these studies the list of intra state lines
(non ISTS lines carrying interstate power) that have been certified as per the procedure
given under Clause 2.1.3 of Annexure – 1 CERC Regulations 2015 had been listed out.
Enclosing the list of lines to be certified, SRPC vide letter dated 19.06.2017 (Annexure-5E)
had communicated to AP, Karnataka and Tamil Nadu for their further necessary action
please.
5.6 Request for deemed available for 230 kV Tirunelveli-Edamon 1 & 2 shutdown
5.6.1 Powergrid, SR II vide letter dated 08.06.2017(Annexure-5F) had submitted the following:
The insulator replacement with CLR in 230 kV Tirunelveli-Edamon 1 & 2 has been
taken up from 03.09.2017 as per 131st OCC approved outage schedule.
The outage has been approved during the period 03-07 June 2017. However, the
shutdown has been extended upto 09.6.2017 with the approval of SRPC as the
unforeseen rains caused delay in the works. Total 736 insulators are being replaced
in critical areas.
5.6.2 It is requested by Powergrid to kindly accord deemed available for the subject outage as this
is a system improvement work.
Agenda for 133rd OCC Meeting to be held on 13.07.2017 at SRPC Bengaluru Page 7
5.7 Frequent Failures of transmission line tower of voltage level 220 kV and above in the
grid(for information of the forum)
5.7.1 POSOCO, NLDC vide letter dated 15.06.2017 (Annexure-5G) had furnished the following:
The reliability of transmission lines is of utmost importance for safe and secure
operation of the power system. The healthiness of substation equipment and
transmission towers play an important role in ensuring the reliability of the
transmission line.
It has been observed that frequent incidents of tower collapse are being reported as
a reason of transmission line outage. A list of transmission line outages on account of
transmission line tower collapse is enclosed at Annexure.
It is evident that the transmission tower collapse is not localized and is widespread in
nature. Such outages of transmission lines during stormy weather on account of
tower collapse causes a severe depletion of network and create emergency
conditions in the grid.
With the trippings in a localized corridor, the inter-regional power transfer margins are
hit and to control the situation, ATC/TTC revision and power market curtailments
have to be done at RLDCs/NLDC level.
Early restoration of lines are equally important which gains importance from
Regulation 5(b) of CERC (Standards of performance of inter-state transmission
licenses) Regulations, 2012. In the regulation, it is mentioned that restoration time for
tower after collapse by Emergency Restoration System (ERs) of transmission line
shall not exceed the 12 days. Also Central Electricity Authority (Grid Standards)
Regulations, 2010 where section 22 deals with Emergency Restoration System
states „Each transmission licensee shall have an arrangement for restoration of
transmission lines of 400 kV and above and strategic 220 kV lines through the use of
Emergency Restoration System in order to minimize the outage time of the
transmission lines in case of tower failures‟.
In this regard, it can be observed that some lines remain under prolonged outage for
weeks/months together. The Hon‟ble Central Electricity Regulatory Commission
(CERC) had taken suo-moto cognizance of such trippings in the past and had given
certain directions vide order dated 14.06.2016 in petition No.9/SM/2014 and
108/SM/2015. This is for kind information please.
5.7.2 It was observed that there are no lines of SR in the list of lines which remained under
prolonged outage for weeks/months together.
5.8 Surrender of power by the beneficiary states and sale of the same in the market:
5.8.1 NLC vide letter dated 22.05.2017 had raised the Technical problems in implementing IEGC
fifth Amendment and issues/Impact of URS sale on the Company as a result of
implementation of Technical Minimum and requested the following:
The beneficiaries shall firm up their requirement closer to actual demand while
furnishing the surrender quantity to the RLDC prior to the day of operation
It was suggested that the beneficiaries may be advised to provide at least 90% of
URS power for sale and keep 10% with them for operational flexibility at their ends.
Agenda for 133rd OCC Meeting to be held on 13.07.2017 at SRPC Bengaluru Page 8
Surrender by each beneficiary should not be below the proportionate Technical
Minimum Schedule as per their entitlement so that the Generator does not suffer
because of full surrender of their share by the beneficiaries.
URS power shall be treated Independent of the Technical Minimum Schedule.
5.8.2 SRPC vide letter dated 26.05.2017 had taken up the issue with all the States and had
requested that requirement as close to actual demand may kindly be firmed up while
furnishing the surrender quantity to SRLDC, prior to the day of operation. Maximum
possible power may be proved as URS power for sale, while keeping some power for
operational flexibility.
5.8.3 It was noted that NLC vide letter dated 18.05.2017 had requested Hon‟ble CERC for
upward revision of Technical Minimum on account of the difficulties encountered during
implementation of Technical Minimum at 55 %.
5.8.4 After deliberations in the Meeting all the states opined that existing practice may be
continued for the time being.
5.8.5 TANTRANSCO vide letter dated 31.05.2017 had submitted that demand forecasting is
being done at an accuracy of 2-3% both on day ahead and intraday basis and variability of
wind generation could not be forecasted as accurate as the demand forecast. The request
of NLCIL for offering 50% of surrendered quantum for Trade is not feasible on day ahead
during high penetration of wind generation which could not be forecasted accurately.
However, based on the Load generation balance surrender of URS power for sale will be
given on day ahead basis.
5.8.6 SRPC had requested TANTRANSCO to take up the issue of forecast error with NIWE.
Feedback on forecast needed to be passed on to NIWE. TN was requested to bring out a
daily report on error forecast and furnish to SRLDC/SRPC/NIWE/IWMPA for improvement.
5.8.7 KSEBL had informed that last year NLC had approached KSEBL for submission of NOC to
sell URS power which was given by KSEBL. This year NLC had not approached them.
SRPC had suggested NLC to approach KSEBL and other states for prior permission to sell
the URS power.
5.8.8 Subsequently TANTRANSCO vide letter dated 21.06.2017 had informed that during the
period from 01.06.17 to 12.06.17, even though TANGEDCO has offered 72 MU for trade,
only 25% has been traded which was not beneficial to both TANGEDCO and NLC. Hence,
it was kindly requested that necessary arrangements may please be made at NLC end to
increase the quantum of trade for the beneficial of both TANGEDCO and NLC.
5.8.9 It is noted that NTPC had filed a Petition in regard to difficulties encountered in
implementation of the Mechanism for degradation of Heat Rate, Auxiliary Power
Consumption and Secondary Fuel Consumption due to Part Load Operation and Multiple
Start/Stop of the units. (Annexure-5H).
5.9 Optimum harnessing of RE in Southern Region
5.9.1 CEA vide letter dated 30.03.2017 had brought to notice the Minutes of the Meeting held on
10.02.2017 in Ministry of Power for discussing matters related to optimum harnessing of
Renewable Energy Integration in SR without endangering Grid Security. It can be noted that
a number of actionable points had been finalized in the Meeting and time line for compliance
of the same also had been specified. Enclosing the Minutes of the Meeting, SRPC vide letter
dated 02.05.2017 had requested all the concerned that the matter may kindly be arranged to
be reviewed and urgent action be arranged wherever necessitated.
Agenda for 133rd OCC Meeting to be held on 13.07.2017 at SRPC Bengaluru Page 9
5.9.2 Subsequently a Special TCC Meeting was convened on 20.05.2017 at SRPC Bangalore to
discuss on the status of action taken w.r.t the Minutes of MoP Meeting. The minutes of the
Meeting are at SRPC website.
5.9.3 SRLDC had informed that in compliance to the minutes of MoP Meeting SRLDC had
conducted a Capacity Building Workshop on STOA procedures on 19.05.2017.
5.10 Constitution of “Sub-Group under Technical Committee for Implementation of Frame
work on Renewable at the state level”
5.10.1 CERC vide their communication dated 02.05.2017 informed the following:
Technical Committee under the Chairmanship of Member, CERC, Shri A.S.Bakshi
was formed at the direction of Forum of Regulators (FOR) in November, 2015. This
Committee comprises of Technical Members of State Commission of renewable rich
States, viz. Tamil Nadu, Gujarat, Rajasthan, Maharashtra, Andhra Pradesh, Karnataka
and Madhya Pradesh. The objectives of the Committee include facilitating
implementation of Regulations for Forecasting, Scheduling and Deviation Settlement
at the State level, implementation of ABT framework and Ancillary Services in member
States, among others.
The Committee in its eleventh meeting held in Chennai on 28.03.2017 felt that with
increasing penetration of Renewable Energy (RE) in the backdrop of GoI‟s 175 GW
RE target, increasing inter-state transmission of power and commitment of 24x7
Power to All, regional cooperation for optimum utilization of generation resources has
become critical.
Further, it was decided that Sub-Groups be constituted in the Northern Region,
Western Region and Southern Region (the three RE rich regions) headed by the
Member Secretaries of the respective Regional Power Committees (RPCs) to
examine this issue.
Accordingly, Sub-Groups have been constituted by the competent authority
comprising the following:
1. Member Secretary, RPC, as Chairman of the Sub-Group
2. One representative from concerned SERCs of the Region
3. One representative from concerned SLDCs of the Region
(b)&(c) as above to be nominated by the concerned SERC
4. One representative from RLDC (concerned RLDC) to be nominated by NLDC.
5. One representative from NLDC/POSOCO
6. One representative from FOR Secretariat (optional/observer)
The Sub-Group may co-opt any external expert as it deems fit.
This Sub-Group shall inter-alia examine the feasibility and modality of cooperation
among states in the respective region for ensuring optimum utilization of generation
resources with least cost options for balancing across the region.
The Sub-Groups are to submit their findings before the Technical Committee at the
earliest.
Agenda for 133rd OCC Meeting to be held on 13.07.2017 at SRPC Bengaluru Page 10
5.10.2 Further SRPC vide letter dated 24.05.2017 had informed that it is proposed to co-opt expert
from TSTRANSCO AND KESBL to this sub-group.
5.10.3 The Meeting was convened on 07.06.2017 at SRPC Bangalore and the Minutes of the
Meeting are available at SRPC website
5.11 Terms and Reference for the proposed study on Renewable Integration
5.11.1 It was noted that in the 31st SRPC Meeting held on 25th February 2017
TANGEDCO/TANTRANSCO had agreed to take up the matter of funding this study by RE
Developers with them. SRPC vide letter dated 03.05.2017 had requested TANTRANSCO
that the matter regarding possible funding of the consultancy may kindly be arranged to be
taken up with RE Developer Associations.
5.11.2 In the 131st OCC Meeting, it was noted that TANTRANSCO/TANGEDCO may call for a
meeting with RE Developer Association shortly.
5.11.3 Subsequently TANTRANSCO vide letter dated 08.06.2017 had informed that adverting to
SRPC letter the matter regarding possible funding of the consultancy was taken up with RE
Developer Association on 30.05.2017 and after deliberations, the following were suggested
by the RE developers:
i) The objective of the study on RE integration is highly elaborative which gives
solution on long term that is up to year 2030. Hence, the study should be based on
short term (immediate), Medium term (for year 2022) and long term (for year 2030).
ii) As per the preliminary assessment of SRPC, the cost could be around Rs.3.50
crores. In this regard, the amount may be segregated separately for short term
(immediate), Medium term (2022) and long term (for year 2030) so that the cost may
come down.
iii) Also, the study may be carried out in separate heads as Technical, Commercial and
Training & Administration. Hence, instead of a single consultant we may engage
more than one consultant for different heads of study.
iv) It is requested to conduct meetings with all the other RE rich states in SR/India with
their RE developers association (including solar) so as to share the financial
commitment equally.
v) It was agreed in-principle by IWPA during the meeting to share the cost, if the cost
is cut down from 3.5 Crore (preferably in lakhs) after taking the above suggested
measures.
5.12 Compliance of CEA Regulations for Grid connectivity of Renewable Energy Sources
5.12.1 CEA vide letter dated 12.04.2017 had informed that in compliance to the Clauses 6(3) and
6(4)(b) of Central Electricity Authority (Technical Standards for Connectivity to Grid)
Regulations 2007 and Central Electricity Authority (Technical Standards for Connectivity of
the Distributed Generation Resources) Regulations 2013 notified on 30th September 2013 it
is obligatory for all the grid connected renewable generators to provide necessary facilities
for data-communication and data-storage and other parameters as may be stipulated. The
said CEA Regulations also places onus on the generating plants including renewable to
Agenda for 133rd OCC Meeting to be held on 13.07.2017 at SRPC Bengaluru Page 11
coordinate with appropriate licenses on issues including but not limited to protection safety
and metering.
5.12.2 With the above perspective as emerging from the CEA Regulations in force, the SLDCs are
requested to take up the matter with all the renewable generators to ensure transfer of
data to the appropriate Load Despatch Centre, so that the real time generation data is
available with them for centralized monitoring. It was also requested that to indicate the
present status in this regard and the action plan with definite time frame to ensure real time
data telemetry from all the grid connected Renewable Generators/Plants to the SLDCs.
5.12.3 CEA had requested SRPC to take up the issue with the concerned SLDC/utility operating the
SLDC and desired that this may be kept as an agenda item for OCC Meetings for periodical
review of the status of real time data telemetry from all the Grid Connected Renewable
Generators/Plants to the SLDCs.
5.12.4 Subsequently CEA vide letter dated 08.05.2017 had enclosed MoP letter dated 06.04.2017.
MoP letter had conveyed the main decisions:
CEA to ensure that necessary rules and regulations regarding generation data
communication including RE generators are in place and being implemented in true
spirit along with the suitable monitoring mechanism/penal mechanism for non-
compliance.
The National level Registry to be maintained by Central Electricity Authority (CEA),
where generation capacity data of all kind of Generators (Conventional, Non-
conventional, Non-captive, Captive ISGS or In SGS) will be available. The State
level Registry shall be maintained at the respective SLDCs also generation capacity
data of all kind of Generators (Conventional, Non-conventional, Non-captive, Captive)
in the respective States will be available. The State level data should further be
communicated to CEA and NLDC for maintaining record at National level on real time
basis.
CEA observed that the data communication system for Discom embedded
Renewable Energy generators (Solar, Wind, Roof-Top Solar etc) is not available in a
number of cases, because of which real time generation data is not available. The
availability of data communication system is very vital considering Grid security
aspects.
Further, to have availability of data of installed Capacity (including RE capacity) in
the country, it is desirable that a data Registry-at State as well as National level be
put in place for compilation of generation data of all kind of Generators
(Conventional, Non-conventional, Non-captive, Captive ISGS or In SGS).
In view of the above, it was requested that in order to work out a necessary framework,
inputs be collected from the relevant stakeholders. It was requested to send to CEA the
relevant inputs including the suggestive framework of rules, appropriate mechanism,
penal provisions for non-compliance and a fool proof mechanism of implementation of
the framework.
Agenda for 133rd OCC Meeting to be held on 13.07.2017 at SRPC Bengaluru Page 12
5.12.5 SRPC vide letter dated 23.05.2017 had submitted to RES Division, CEA that during
deliberations in the subcommittee Meetings, it was noted that data availability for roof top
solar at the SLDCs would be difficult with available infrastructure at the DISCOM level as it
was disbursed and low installed capacity roof top solar installations. It was requested that it
may be kindly clarified whether data/communication availability of all Roof Top solar would
be required at the SLDCs.
5.12.6 SRPC had informed that this matter had been deliberated in the Special TCC Meeting held
on 20.05.2017. The minutes of the Meeting are available at SRPC website. States were
requested to take immediate action as per the Meeting Minutes.
5.13 Ramp down/up during sudden solar increase/decrease during morning/evening
5.13.1 In the 129th OCC Meeting SRLDC had expressed concern regarding the ramp down/up
during sudden increase/decrease during morning/evening hours. SRPC/SRLDC had
cautioned that Solar Capacity would be coming up very intensively in coming six months and
SR should be ready with contingency plan for managing the LGB during the solar ramp
up/ramp down period.
5.13.2 Subsequently a Meeting of Sub- Group of Southern Region formed under the Technical
Committee constituted by CEA for study of optimal location of the various types of balancing
energy sources/energy storage devises to facilitate grid integration of Renewable Energy
Sources and associate issues was conducted on 24.03.2017 with participation from CEA.
The minutes of the Meeting issued on 20.04.2017
5.13.3 All the states are requested to take action in this regard.
(Item No.4(e) of enclosed SRLDC letter dated 28.06.2017). 5.14 Implementation of CERC (Communication System for Inter-State Transmission of
Electricity) Regulations, 2017
5.14.1 CERC had notified the Central Electricity Regulatory Commission (Communication System
for Inter State Transmission of Electricity), Regulations, 2017 dated 15th may 2015. These
Regulations shall come into force w.e.f 01.07.2017. A number of actionable points are there
for the entities/stakeholders.
(Item No.4(f) of enclosed SRLDC letter dated 28.06.2017). 5.15 Confirmation for the indicated plan for FGD/Phasing Out Plan for implementation of
new Environmental Norms for Thermal Plants issued by MOEF & CC
5.15.1 It may be noted that a meeting on Preparation of Phasing Plan for implementation of new
Environmental Norms for Thermal Plants, issued by MOEF&CC in line with CEA‟s letter
No.CEA/Th./TPE&CC/ENV/55/2015/1473 Dated 22.12.2016 was held on 12.01.2017 at
SRPC, Bengaluru (Minutes available at SRPC website). After ascertaining the firmed up
Phasing Plan for FGD installation was communicated to CEA (the details available at SRPC
website). Subsequently, CEA has firmed up the FGD phasing plan and uploaded on its
website. Subsequently, a meeting to firm up phasing out plan for thermal unit which do not
Agenda for 133rd OCC Meeting to be held on 13.07.2017 at SRPC Bengaluru Page 13
have space for FGD was held on 25.03.2017 (Minutes of phasing out plan available at SRPC
website).
5.15.2 CEA has desired confirmation for the indicated plans. The final Plan for FGD implementation
with respect to SR Units with confirmation/comments had been communicated to CEA.
5.15.3 Phasing Out Plan are not received from most of the generators.
5.15.4 It is requested that all the concerned to kindly furnish the information at the earliest which
would be forwarded to CEA.
5.15.5 Chairperson, SRPC vide letter dated 24.05.2017 had put forward to Secretary-Power, MoP
that during discussions in the 31st SRPC meeting held on 25.2.2017, regarding
implementation of revised environmental norms, it was suggested that some funding either
from PSDF or any other fund could be kindly sought from the GoI to meet the stipulated
revised environmental norms. It was requested that the kind attention of MoP may be
bestowed on this issue of funding either from PSDF or any other fund to meet the stipulated
revised environmental norms.
5.16 State-wise allocation of 540 MW power from RGPPL to Railways
5.16.1 CEA vide letter No. 5/AI/CSA/GM/2017 dated 22.03.2017 had enclosed MoP Order No.
4/22/2011-Th-Vol-III) dated 17.03.2017 in which 540 MW power from Ratnagiri Gas and
Power Private Limited (RGPPL) has been allocated to Indian Railways. Allocation to SR
States (out of 540 MW) would be as under:
State Nodal Railway Maximum load in MW after availability of corridor between NEW Grid and SR*
Telangana SCR 50*
Tamil Nadu SR 100*
date of effectiveness subject to availability of transmission corridor as per
assessment of CTU.
5.16.2 Subsequently the following were noted:
SRPC vide letter dated 19.04.2017 had requested CTU that the likely time frame in
which the transmission corridor would be available for transmission of power to
Railways may kindly be arranged to be conveyed to SRPC at an early date.
CTU vide letter dated 20.04.2017 had informed that ATC to SR from new Grid has
already been allocated to LTA/MTOA applicants for transfer of power to constituent
states of Southern Region including Telangana and Tamil Nadu. Transfer of 150 MW
can be affected upon commissioning of upcoming Nizamabad-Maheswaram 765 kV D/C
line, which is likely to be commissioned by October 2017.
TSTRANSCO had convened a Meeting with Railways, SRLDC & SRPC on 28.04.2017.
TANTRANSCO vide letter dated 18.04.2017 had informed that the issue of
consideration of Open Access by Southern Railway as Deemed Licensee is sub-judice.
At this stage since the Petition on the above matter is pending with the Hon‟ble APTEL,
New Delhi and pending in principle approval from TANGEDCO, permitting Open Access
to Southern Railways as Deemed Distribution Licensee for availing allocated power
from RGPPL is not feasible.
Agenda for 133rd OCC Meeting to be held on 13.07.2017 at SRPC Bengaluru Page 14
Southern Railways representative had informed that PPA with RGPPL had been signed
on 25.04.2017 and requested TN for operationalization of the allocation. They have
applied for connectivity to CTU/STU(for 100 MW).
Subsequently CEA vide letter dated 22.05.2017had endorsed MoP letter dated
18.05.2017 in which 35 MW of power is allocated to KPTCL (SWR). Allocation to
Karnataka does not link the effectiveness subject to the availability of transmission
corridor as per assessment of CTU as for Telangana and Tamil Nadu.
SRPC vide letter dated 23.05.2017 had submitted to GM Division CEA that the above
may kindly be examined for clarity. CEA vide letter dated13.06.2017 had communicated
the allocation to Karnataka with slight modification in the conditions.
CTU, Planning vide letter dated 08.06.2017 had informed that Available Transfer
Capability (ATC) to Southern Region from NEW Grid has already been allocated to LTA
applicants for transfer of power to constituent states of Southern Region. Nevertheless,
transfer of above 35 MW can be effected upon commissioning of upcoming Nizamabad
– Maheswaram 765 kV D/C line, which is likely to be completed by Oct‟17.
5.16.3 TANTRANSCO/KPTCL to convene a Meeting in line with TSTRANSCO to firm up the
action plan.
5.17 Scheduling of Simhadri Stage I Station
5.17.1 Simhadri Stage-I scheduling had been started by SRLDC from 01.05.2017 onwards.
5.17.2 In the 132nd Meeting, SRLDC had pointed out that Main/Check meters at Simhadri Stage - I
end of Inter connector is not installed.
5.18 TTC/ATC reduction to SR
5.18.1 NLDC vide Revision No.6 dated 05.04.2017 had reduced TTC from WR-SR by 400 MW
(4750 MW to 4350 MW) with reason „revised considering high load in Maharashtra and rest
of Western Region‟. The limiting constraint for WR-SR and ER-SR has been mentioned as
(n-1) contingency of 765/400 kV, 1500 MVA single ICT at Nizamabad will lead to 874 MW
loading on 400 kV Vemagiri (PG) – Nunna (S/C). The assumptions in the base case show
19,346 MW of peak load, 14655 MW of off-peak load, 15,124 MW peak generations and
11,320 MW of off peak generation in respect of Maharashtra.
5.18.2 SRPC vide letter dated 06.04.2017 had brought some of the issues to the notice of NLDC.
NLDC had replied vide letter dated 11.04.2017 in this regard. SRPC vide letter dated
21.04.2017 had further sought some clarifications from NLDC.
5.19 Staggering of Loads/Overdrawal during peak hours
5.19.1 In the 130th OCC Meeting SRLDC had informed that from March 2017 onwards the SR
demand pattern was experiencing sudden and abrupt load change over in the evening peak
hours. SRPC and SRLDC had suggested that SLDCs may conduct a Meeting with
DISCOMs and discuss and arrive at an effective load staggering pattern which would
smoothen the changeover. Reports/minutes/staggering details may be submitted to
SRPC/SRLDC. In the 131st OCC it was noted that SRLDC vide letters dated
26.04.2017/24.05.2014 had again taken up this issue with all the States.
Agenda for 133rd OCC Meeting to be held on 13.07.2017 at SRPC Bengaluru Page 15
5.19.2 SRLDC/SRPC suggested that staggering may be done in a manner to avoid sudden change
in demand. Steep variation is observed in KPTCL demand during load change over. KPTCL
was requested to convene a Meeting with DISCOMs and finalize the action points to
limit the huge demand change during load change over within 15 days.
(Item No.4(d) of enclosed SRLDC letter dated 28.06.2017).
5.20 Monitoring of scheme funded from PSDF
5.20.1 NPC vide letter dated had furnished the Agenda from NPC for the 132nd OCC Meeting
(Annexure-5I). The details of the grant sanctioned from PSDF for the schemes in
Southern Region were furnished. It was requested that the status of implementation of the
above schemes physical as well as financial progress may please be reviewed and the
entities may be asked to kindly expedite implementation of the schemes. It was recalled
that the entities may furnish the information in the specified format by first week of every
month on regular basis to Member Convener, PSDF Project Monitoring Group (AGM,
NLDC, POSOCO) with a copy to NPC Division.
5.20.2 In the Meeting, it was noted that in May 2017 many new schemes have been received
sanction of grant from PSDF i.e. AP(1), KSEB(2), Tamil Nadu(1) and Telangana(2),
PGCIL(1-for STATCOM). NPC had requested through SRPC to kindly arrange to start the
works as mentioned in the agreement and to avail the sanctioned grant in installments in
the stipulated time. It was observed that progress of works of already sanctioned schemes
is not satisfactory except KSEBL, TS and KPCL. NPC informed that next Meeting of NPC
may be called shortly. Exact details of percentage of works completed needed to be filled
in the Remark Column which is furnished as Annexure (Refer Annexure-5I). A summary
on the percentage of works completed may kindly be furnished to NPC.
5.20.3 APTRANSCO, KPTCL, TANTRANSCO & PGCIL and SRPC needed to submit the summary
at the earliest.
5.20.4 Subsequently NLDC had convened a Meeting at NRLDC, New Delhi on 20.06.2017 at All
India Level to discuss on the progress of works of schemes and assess the actual Status.
Minutes/Report of the Meeting is awaited.
5.21 Enhancement in TTC of Southern Region
5.21.1 NLDC vide their letter dated 14.03.2017 had informed that it is difficult to consider the
extended mode (500 MW) of Talcher-Kolar HVDC for the purpose of TTC/ATC.
5.21.2 Subsequently TSTRANSCO vide letter dated 23.03.2017 had taken up the issue with
Secretary Power, MoP and had requested to consider the extended mode (500 MW) of
Talcher-Kolar HVDC for the purpose of TTC/ATC. It was requested that necessary
instructions may kindly be arranged to be issued to POSOCO to implement the extended
mode of 500 MW for 10 hrs a day on Talcher-Kolar HVDC link urgently.
Agenda for 133rd OCC Meeting to be held on 13.07.2017 at SRPC Bengaluru Page 16
5.21.3 Further, Chairperson SRPC vide letter dated 18.05.2017 had taken up the issue with
Secretary(Power), MoP .
5.22 Right of Way issue of 400 kV Nelamangala-Hoody Line/ commissioning of 400 kV Yelahanka substation/220 kV evacuation system of KPTCL at Yelahanka substation
5.22.1 SR II Powergrid had informed that the compensation issues were being settled for LILO of
Nelamangala - Hoody at Yelahanka. Regarding Madhugiri – Yelahanka in three districts,
Bengaluru Urban, Bengaluru Rural and Tumkur ROW issues are being faced. The
connectivity at Yelahanka will not be useful until the 220 kV side cables are made through
by KPTCL.
5.22.2 SR II, PGCIL had informed that the issue is being followed up with State Administration for
removal of ROW issues.
5.22.3 KPTCL had informed that cable for Yelahanka connectivity is awarded in December 2016
and scheduled to be commissioned in December 2017. They would be furnishing the
updates in detail shortly.
5.23 Daily Load Forecasting by SLDCs/RLDCS/NLDC
5.23.1 The mean absolute error (forecast Vs actual demand) for the month of June 2017 as
furnished by SRLDC.
(Item No.5 (b) of enclosed SRLDC letter dated 28.06.2017).
5.23.2 In the 126th OCC Meeting, SRLDC had informed that a Pilot Project for RE forecasting had
been started. Pilot Project for load forecasting was yet to commence. RE Connect has been
entrusted the work. They wanted past three years‟ data in specific format. The block wise
difference in forecast and actual and the reason for the inter block difference were also
needed. SRLDC had started the work. Weather input would be incorporated by RE Connect.
5.24 Web Portal on Weather information for Power Sector
5.24.1 CEO, POSOCO vide letter dated 07.06.2017 had informed that an MOU was signed
between POSOCO & IMD on 18.05.2015 to have an effective weather information
interface, exclusively for Power system operation. In pursuance to this MOU, dedicated
web portals for all the 5 regions have been developed jointly by IMD & POSOCO.
These web portals contain lot of information related to weather forecast, real time & past
data related to various locations in all the regions. The weather locations presently
available with IMD in all the regions have been mapped with the electrical locations /
stations. With a better understanding of this data, various utilities in the concerned
region can equip themselves with better preparedness and improved operational
Agenda for 133rd OCC Meeting to be held on 13.07.2017 at SRPC Bengaluru Page 17
planning, thereby enhancing the reliability of power system operation. Details of the
information available on the web portals is given at Annexure-I.
5.24.2 During the interaction with Director General, IMD, in this regard on 05.06.2017, it has
been agreed that representatives from IMD shall explain the interpretation of weather
data available on the web portal to derive the information and knowledge for decision
making in the day to day operation of Power System, through a series of interactive
sessions in all the regions. As OCC meetings are held on monthly basis in all the
regions and representatives from all the SLDCs, constituents & utilities attend the same
these interactions would be highly beneficial.
5.24.3 In view of the above, it was requested that the first session may be kept in the agenda of
the forthcoming OCC meeting in your region.
5.24.4 SRLDC vide letter dated 23.06.2017 had requested Indian Meteorological Department to
kindly give a session on 13.07.2017 in the OCC at SRPC, Bengaluru. It was also
requested to confirm the proposal so that all the operators from Load Despatch Centre of
Southern Region shall be informed accordingly.
5.25 Frequent tripping of Vallur-NCTPS lines
5.25.1 In the Meeting, it was noted that the replacement of insulators had been completed in the
NCTPS –Vallur lines and the replacement on other connected line has been taken up
and will be completed by December 2017(Vallur-Almathi lines).
5.25.2 SRPC had suggested that NTECL & NCTPS may go for RTV coating in their switchyard
as had been done by other entities
5.26 Scheduling of NTPC Ramagundam Solar Power Plant(10 MW)
NTPC had informed that written communication in this regard to MoP would be shared
with SRLDC/SRPC.
5.27 Scheduling of Solar at Kamuthi Solar Park
5.27.1 SRPC vide letter dated 07.02.2017 had taken up the issue with CE, CEA, Legal and had
requested to examine the issue and advise SRPC on whether the project needs to be
scheduled by SRLDC or by SLDC.
5.27.2 CEA, Legal vide letter dated 30.03.2017 had concluded that as per advice sought by the
SRPC the scheduling of the Solar Power Project can be scheduled under the
provisions of IEGC (Regulation 6.4.2(b) by SRLDC.
5.27.3 SRLDC vide letter dated 10.04.2017 had informed that SRLDC can schedule power
from M/s AGEL and its subsidiaries. However, in order to avoid any difficulties at a later
date it was suggested that M/s AGEL may seek Hon‟ble CERC‟s directions resolving the
Agenda for 133rd OCC Meeting to be held on 13.07.2017 at SRPC Bengaluru Page 18
difficulties mentioned in SRLDC‟s letter before SRLDC can begin scheduling of the
generating station under IEGC Regulation 6.4.2(b).
5.27.4 A Meeting to discuss further course of action on scheduling etc was proposed to be held
on 05.04.2017 which was further postponed to 19th April 2017 as per TANTRANSCO
request. Further TANTRANSCO had requested to convene the Meeting after May 2017
which was accepted
5.28 Upcoming Wind/Solar Projects
5.28.1 In the 130th OCC Meeting SRPC/SRLDC had enquired the States regarding the
proposed addition of Wind/Solar projects in their respective system. The following were
noted:
NTPC was requested to come back on status update of NP Kunta Stage II. In
Andhra Pradesh and Karnataka also Wind/Solar parks are expected to be come in
near future like at Ananthapur and Pavagada.
It was noted that procedure for RE Frameworks had been notified and is available
at NLDC website. It was requested to all the concerned to take up with generators
and whatever information as mentioned in the Notified Procedure are to be
collected/ensured from RE generators.
SRPC had informed that the progress of works of RE Generators and evacuation
system are available in TCC/SRPC Minutes. All the concerned were requested to
update the same and revert back at the earliest incorporating appropriate changes.
It was felt by the forum that a separate RE Meeting may be convened with States
and Major Generators (may be generators with 500 MW and above Installed
Capacity) quarterly to have focused discussion on the progress.
5.28.2 In the 131st OCC Meeting, States/RE Developers were requested to ensure that
infrastructure to implement RE Framework either at ISTS/ISTS level needs to in place
from inception stage itself.
5.28.3 No updates have been received from any of the states/entities. The list of evacuation
schemes for upcoming schemes was prepared with huge effort and no update /response
has been received.
5.29 Power Flow Analysis under high RE scenario
5.29.1 SRLDC vide E-Mail dated 08.06.2017 had informed that a project has been undertaken
jointly by POSOCO, USAID and NREL for power flow analysis under high RE scenario.
This study would look into the reliability and security issues with high RE penetration.
5.29.2 As a part of Phase-I of this work, studies are proposed to be conducted for 2018 grid
scenario. For this purpose States are kindly requested to share the details of existing
wind & Solar generator details and Wind and Solar expected to be commissioned by July
2018 with the details of planned transmission system. It was also requested to kindly fill
in the details sought as per the attached format. The sample wind station diagram is also
attached for reference.
Agenda for 133rd OCC Meeting to be held on 13.07.2017 at SRPC Bengaluru Page 19
5.30 Patrolling / Maintenance of critical lines and substations
5.30.1 In last couple of years insulator tracking has been observed in the Transmission lines
and Substations located in the coastal and polluted areas. The format for furnishing the
details of schedule / Patrolling and Maintenance carried out of the critical Transmission
lines and Substations had been circulated.
5.30.2 SRPC observed that every month some scheduled activity may be there and it is
responsibility of SLDCs to ensure that it was being carried out. SRPC/SRLDC needs to
be informed accordingly.
5.31 PSS Tuning of generators
5.31.1 4th Meeting to review the status of PSS tuning of the generators was convened on 13th
January 2017 and minutes of the Meeting are available at SRPC website. All the
generators to follow the action plan finalized in the 4th PSS meeting. PSS study group
had analyzed the SRT reports furnished and recommendations had been finalized. The
Step Response Test Reports in the specified formats to be submitted in soft form to
SRLDC ([email protected])/SRPC / CTU ([email protected]) / SRPC
(seoprnsrpc- [email protected]; [email protected]).
5.31.2 List of Units for which SRT had been analyzed in the 3rd and 4th Meetings and to be
analyzed for 5th meeting of PSS. Necessary action to be taken as per
Recommendations:
SRT of following units had been analyzed in the 3rd
and 4th Meetings and to be analyzed for 5
th
meeting of PSS and necessary action to be taken as per Recommendations:
Entity Generating Stations/Units
APGENCO Rayalaseema TPS U1 to U5; VTPS U1 to U4 & U7; SDSPP U1&U2; Srisailam RB HEP U1 to U7; Lower Sileru HEP U1
AP IPP HNPCL U1 & U2(reports to be analysed)
TSGENCO Nagarjunasagar HEP U1( U1 report to be analyzed),U2 to U8; Srisailam LB HEP U1 to U6( reports to be analyzed); Kakatiya TPS U1 & U2( U2 report to be analyzed); Kothagudem TPS U10 & U11
KPCL Raichur TPS U1,2,3,5,6,7& 8; BTPS U1 to U3; Varahi UGPH HEP U1,2 & 4; Nagjheri HEP U1,2,4 & 5; Sharavathy HEP U3,5,7,9 & 10; Sharavathy HEP U1,2,4& 6(Reports to be analysed); Nagjheri HEP U3(report to be analyzed)
KAR IPPs UPCL U1 & U2; JSWEL U1(report to be analyzed),U2 & U3
KSEBL
TANGEDCO MTPS St-I U1 to U4; NCTPS St-I U1 to U3(reports to be analyzed); Tuticorin TPS U2 to U5; NCTPS St-II U1(report to be analyzed)
TN IPPs
CGS NTPC- Ramagundam U7; NTPC-Simhadri U1 to U4; NTPC-Talcher STPS St-II U3 to U6; NTECL-Vallur TPS U1 to U3; NLC-Neyveli TPS II U4 to U7; NLC-Neyveli TPS II U1 to U3(reports to be analysed); NPCIL-KKNPP U1;NLC-Neyveli TPS II Exp. U1 & U2(reports to be analysed); (NLC & TN JV)NTPL U1(report to be analysed);
ISTS TPCIL U1; Coastal Energen U2; IL & FS U1 & U2
Agenda for 133rd OCC Meeting to be held on 13.07.2017 at SRPC Bengaluru Page 20
For the following Units, PSS is to be tuned and SRT to be carried out / information not available:
Entity Generating Stations/Units
APGENCO VTPS U5 & U6; Lower Sileru HEP U2 to U4
AP IPPs
TSGENCO Kothagudem TPS U7 & U8; Singareni Collieries U1 & U2
KPCL Raichur TPS U4; Yeramarus TPP; Varahi UGPH HEP U3; Nagjheri HEP U6(SRT report not submitted); Sharavathy HEP U8
KAR IPPs JSWEL U4
KSEBL Idukki HEP U1 to U6
TANGEDCO NCTPS St-II U2; Tuticorin TPS U1; Mettur St-II TPS U1; Kadamparai HEP U1 to U4
TN IPPs STCMS
CGS NTPC-Ramagundam U1 to U6; NTPC-Kudgi; Neyveli TPS I U7 to U9; NLC-Neyveli TPS I Exp. U1 & U2 (SRT report not submitted); NPCIL- KGS U1 to U4; NPCIL-MAPS U1 & U2; NPCIL-KKNPP U2
ISTS connected IPPs
SEL U1 to U4; MEL U1 & U2; TPCIL U2; Coastal Energen U1; Lanco Stage II & III; SGPL-Nellore
5.31.3 States/Generators are requested to kindly look into the table and discrepancies if any,
may be communicated to SRPC.
5.32 Implementation of URTDSM (PMU) project in Southern Region
5.32.1 A follow up Meeting to discuss the URTDSM (PMU) issues was convened on 07.02.2017
at SRTS II PGCIL, Yelehanka, Benguluru (MOM available on SRPC website).
5.32.2 URTDSM - Status update in respect of the Meeting held on 07.02.2017/subsequent OCC Meetings are as below:
1
Updated details of Nodal Officers:
WhatsApp group in name of Southern Region WAMS has been created on 03.11.2016.This Group will look into dispatch, installation and commissioning issues under URTDSM Project. The above group would be functional during the maintenance phase also.
2
Status of URTDSM Project(SR Portion)
PMUs to be installed in SR as per URTDSM Project Package–II had further increased from 240 to 264 and again to 270 on account of commissioning of certain new stations and additional feeders. (As per LOA-212)
Status
Total Envisaged
Survey completed
S/S PMU
SS PMU Installed
Pending in Hyderabad,
connected IPPs
Agenda for 133rd OCC Meeting to be held on 13.07.2017 at SRPC Bengaluru Page 21
SR I 12 Khammam and Vemagiri.
20
97
SR II
41 144 Completed 31 106
Remaining 52 PMUs as per revised BOQ (out of 270) would be supplied once rate negotiation with M/s GE is completed. Currently a Committee is formed by LD&C PGCIL for rate finalization as extra PMUs are exceeding the overall quantity variation of SR & WR limit of 15 % as per original LOA.
Forum requested Project Coordinator/PGCIL to freeze the total number of PMUs for SR at the earliest in the interest of faster execution of project as in the previous meeting the number of PMUs had been revised to 240 from 212(as per LOA). Additional requirement could be covered in Phase II.
Forum expressed concern that project was getting delayed and requested PGCIL / GE to share monthly project execution plan up to Sep 2017 and monthly progress ( installation and integration to Control Centre) status by end of every month.
3 Contractual amendment
Negotiation is under progress with GE T&D. Amendment is expected to be released in April 2017(last meeting agreed for January 2017) and system expected to be commissioned by Sep 2017.
4 Requirement of Auxiliary Power Supply System (APS) as per revised BOQ (excluding input ACDB and one battery bank of the proposed two battery banks).
APTRANSCO, TSTRANSCO and TANTRANSCO, confirmed the requirement of Auxiliary Power Supply System. TANTRANSCO submitted their requirement. Site survey is under progress.
APTRANSCO confirmed the requirement. TSTRANSCO will be confirming the same within two days.
SR-II informed that once all constituents finalized the APS System requirement the revised BOQ of APS would be furnished by LD&C, PGCIL.
It was noted that KSEBL and KPTCL had already confirmed in the previous review meetings that they do not require APS System.
APS System was expected to be delivered during the month of May 2017. All constituents were requested to make site ready for APS System installation to avoid further delay.
5 Capacity of Battery & charger
KSEBL suggested to have clear SAT procedure with current limiting and constant voltage charging as stipulated by OEM of VRLA battery set. SR II informed that in SAT Procedure OEM requirements are fully considered.
6 Responsibilities under Entities
SR-II confirmed that Dismantling of panels, any civil works etc required to prepare site for installing APS System was not under the scope of the Project and thus was in the scope of respective constituents.
Supply, erection& commissioning of UPS, ACDB Input &Output panels, Battery Bank and associated cabling works for establishing APS system was under the scope of the Project.
Air Conditioning System was required and constituents were to make necessary arrangements.
7 Redundancy for PMUs PGCIL confirmed that all PMUs are provided with redundant communication path and schematic diagram of
Agenda for 133rd OCC Meeting to be held on 13.07.2017 at SRPC Bengaluru Page 22
communication flow had been shared with the constituents.
8 SAT procedure Draft SAT procedure had been circulated among all constituents. SAT in SR earlier planned for January 2017 was postponed to April 2017. It was informed that FAT completed for three numbers SLDCs. SAT for SRLDC will be completed by
9 SR Region Training
Training had been firmed up by M/s GE and one batch training is over.
10 Availability of necessary communication ports for connection of servers under URTDSM
All constituents to make available necessary communication ports for connection of servers under URTDSM project by 20.02.2017 as decided in the last meeting. 130th OCC: TANTRANSCO, KSEBL and KPTCL to ensure availability of communication ports at PDS.
11 Training on Application part
PGCIL (LD & C) had stated that requirement of Training on Application part would be communicated to the Management
12 Update the Drawings Constituents‟ requested PGCIL to update the Drawings with changes done in the CT/PT/Status wiring for the PMU system and submit as built drawing.
13 Completion of the commissioning activity at each site
M/s Alstom and PGCIL representatives were requested by constituents to certify the completion of the commissioning activity at each site.
14 Mandatory spares PGCIL had agreed to furnish the details about the mandatory spares supplied at each site. 131st OCC: BoQ of the mandatory spares under finalisation.
In the 132nd OCC Meeting SR I had informed that 107 PMUs are supplied, 97
commissioned and 85 integrated.
SR II had informed that 106 PMUs at 31 S/s had been installed and commissioned in
which 101 nos had been integrated. Final Amendment had been issued on
19.05.2017.
SRLDC/SRPC recalled that in the Special Meeting held on 07.02.2017 it was agreed
by PGCIL that the Status Update would be furnished on monthly basis which was
not received yet. PGCIL stated that the Project was likely to be completed by
September 2017. It was also agreed that the Monthly Progress Report will be
furnished on each item and issues if, any, faced for implementation also will be
highlighted.
5.33 Discontinuation of payment of Hot Line by SRLDC w.e.f 01.07.2017 and providing of Hot line by respective entities
5.33.1 In the earlier Meeting, SRLDC had recalled that in 128th OCC Meeting SRLDC had
informed that existing BSNL hot line speech circuit between SRLDC Control Room and
Control Rooms of other entities would be discontinued by 30th June 2017. SRLDC
requested all the states to initiate and apply for new hotline speech circuit from state
end in line with IEGC clause 4.6.2”
5.33.2 The following were noted in the Meeting.
Agenda for 133rd OCC Meeting to be held on 13.07.2017 at SRPC Bengaluru Page 23
Kalpakka, Kaiga I & II, Hyderabad(TS), TN and Kalamassery communication will
be stopped w.e.f 01.07.2017. There is very short time left and requested all the
concerned to take immediate action in this regard and clarified that it is
responsibility of the states/generators(User) to establish the voice
communication to SRLDC.
KSEBL had informed that they have written a letter to SRLDC/ Powergrid in this
regard with a query that whether orange exchange can be used for hot line voice
communication. KSEBL have also approached BSNL for the same. SRLDC
suggested that Orange exchange communication can be kept as an additional
channel and it was advisable to establish the facility through BSNL which was
agreed by KSEBL.
TANTRANSCO had informed that after disconnecting the existing connection
only new connection can be established for which it was clarified that multiple
connections may be possible.
TSTRANSCO informed that they have established the new hotline
communication. Existing one can be withdrawn.
5.33.3 Subsequently KSEBL vide letter dated 21.06.2017 had communicated the following to
PGCIL/SRLDC:
As discussed with PGCIL, the Alcatel hotline exchange (Orange Exchange) at
SLDC and SRLDC are capable of being configured for hotline communication.
All the configuration at Kalamassery end will be coordinated between SRLDC
and PGCIL before discontinuing the existing hotline facility through BSNL. The
matter may kindly be treated as Urgent.
5.34 Video Conferencing facility at SLDCs
AP PUDU
APSLDC informed that they were in touch with M/s Alstom to make VC facility operational at APSLDC, Vijayawada. Expected by end of July 2017.
Puducherry would take up VC requirement in the next financial year 2017-18.
5.35 Status of important elements
I. ICT at Madurai It was noted that the provision of one No. of 500 MVA additional ICT at
Checkanoorani 400/230 kV S/s in PGCIL end 400 kV side was commissioned on 29.12.2017. LV side 230 kV Bay work is under progress and would be completed on 30.09.2017.
In the 132nd OCC Meeting, TANTRANSCO had informed that tender was opened on 16.05.2017
Agenda for 133rd OCC Meeting to be held on 13.07.2017 at SRPC Bengaluru Page 24
II. Status of ICTs at Trichy
The provision of one No.500 MVA additional ICT at 400 kV Alundur is under progress. At Alundur 230 kV substation Bay shifting works civil works (Plinth, Structure works) are under progress and yet to be commissioned by July 2017.
I In the 132nd OCC Meeting, it was noted that HV side of ICT is commissioned on 08.05.2017 at 16:30 hours and LV side would be commissioned before July 2017.
III. Completion of Karaikudi bay – PGCIL and TN SLDC to update In the 132nd OCC Meeting PGCIL had informed that the works will be completed by November 2017.
5.36 Advance intimation regarding first time synchronization of transmission elements with all necessary
The approved procedure needs to be followed.
5.37 Assessment of lift irrigation loads and necessary planning for using as demand response
5.37.1 In the 130th OCC Meeting SRLDC/SRPC had enquired the states regarding the lift
irrigation schemes existing in their system which can be utilized for Load Generation
Management/RE issues/load change over. Running these loads at different times can
very much help in load generation management. States were requested to kindly study
this in depth and can interact with Government Bodies/irrigation department to utilize
these schemes for effectively flexing the loads.
5.38 Scheduling of new LTA from MARWA Thermal Power Plant (1000 MW). 5.38.1 TSTRANSCO vide letter dated 03.05.2017(Annexure-5J) regarding operationalization of
new LTA for scheduling of power from Marwa Thermal Plant to Telangana had
communicated to SRLDC that, Chattisgarh Discom (supplier) is yet to communicate their
consent on the modifications to be taken up in the PPA as directed by Hon‟ble TSERC,
which is mandatory for enforcing the PPA. As such, it is requested to defer (the
operationalization) the new LTA TILL the Revised Scheduled Delivery Date & Effective
date in terms of the Article 6.1.3 of the PPA, to facilitate the completion of regulatory
compliance.
5.38.2 Subsequently TSTRANSCO vide letter dated 04.05.2017(Annexure-5K) had informed
the following.
CSPDCL has communicated its readiness to commence supply of power to Telangana under the Provisions of the PPA dated 22.09.2015 and sought to take appropriate action for scheduling of power w.e.f.01.04.2017.
Meanwhile, Hon‟ble TSERC has passed an interim order dated 31.03.2017 in Petition O.P.No.93/2015, wherein the TSERC has directed to take up modifications/amendments to certain clauses in the aforesaid PPA and as directed by TSERC, TSSPDCL (Lead Procurer on behalf of TSDISCOMS) has requested CSPDCL vide letter dated 25.04.2017 to give consent for amending the PPA Clauses. The consent of CSPDCL is awaited.
Whereas the PGCIL / POSOCO has addressed the Chief Engineer / TSSLDC, Hyderabad for operationalization of new LTA to Telangana from the same MARWA Thermal Power Plant under LTA No.L_17_04 w.e.f.04.05.2017.
Agenda for 133rd OCC Meeting to be held on 13.07.2017 at SRPC Bengaluru Page 25
Upon considering the above, pending receipt of consent from CSPDCL for modification to the PPA as directed by TSERC, it is requested to schedule the power from Marwa Thermal Power Station to Telangana as per the requisition given by Telangana SLDC.
5.38.3 TSTRANSCO vide letter dated 03.07.2017(Annexure-5L) had pointed out the
mismatch in the regional boundaries of LTA from Marwa to Telangana.
As per SRPC-REA for LTA from Marwa to Telangana (TSPCC) with Application No.L_17_04 for the month of May 2017.
1) The energy at SR Boundary is 369275372.5
2) The energy at Ex-Bus is 376802500
As per WRPC-REA for LTA from Marwa to Telangana (TSPCC) with Application No.L_17_04 for the month of May 2017.
1) The energy at WR Boundary is 369275319.250
2) The energy at Ex-Bus is 376802500
It is observed that the energy at Ex-bus is matching but there is a mismatch in the figures at the regional boundaries. It is requested to SRLDC to kindly look into the matter and arrange to rectify the anomaly.
5.39 Procedure to be adopted for finalizing the technical minimum STPP (2x600MW) TSTRANSCO vide E-Mail (Annexure-5M) has informed that STPP had communicated their station technical minimum as 840 MW for each unit. A copy of the startup curves furnished by STPP also enclosed. It was noted that KTPP-II has declared technical minimum as 400 MW at Ex-Bus for its 600 MW unit. TSTRANSCO requested SRLDC to advice the procedure to be adopted for finalizing the technical minimum of STPP Generator.
6 GRID FREQUENCY
6.1 High Frequency
a) High frequency at Load Change Over.
b) Status review of implementation of staggered load change over within the constituents
as per the decision of 23rd SRPC meeting, moderating own generation, surrendering of
ISGS power in advance and other actions by Regional Entities to avert high frequency
excursion.
c) Pump Mode Operation of Nagarjunasagar/Srisailam LB/Kadamparai HEP units.
TANTRANSCO had informed that Kadamparai units were being put under
pump mode operation for 3-4 hours daily.
It was noted that a Special Meeting had been convened at SLDC, TSTRANSCO in
which the recommendation finalized w.r.t Nagarjunasagar pump mode operation are
given below:
Agenda for 133rd OCC Meeting to be held on 13.07.2017 at SRPC Bengaluru Page 26
TSGENCO to address all issues for filling up the Tail Pond Reservoir ie legal
issues, elevating the lift irrigation schemes etc. TSGENCO to test the pump
mode operation through their OEM M/s Hitachi.
It was felt that the issue of the discharges (quantum/time duration) /
mechanism for enabling pump mode operation/utilization of the water pumped
back could be referred to CEA /MoP for further guidance and suitable
directions. This would help in utilization of Nagarjunasagar units in pump
mode in optimal manner especially with the higher renewable integration.
The following were the recommendation finalized w.r.t Srisailam pump mode operation
It was felt that the issue of weir could be taken up with CEA /MoP for further
advice/guidance/funding. Though it could take 2-3 years for completion but in
perspective plan with high targets of renewables, this would be useful in pump
mode operation at Srisailam and balancing of RE.
It was felt that issue regarding discharges (quantum/time duration) /
mechanism for enabling pump mode operation/utilization of the water pumped
back could be referred to CEA /MoP for further guidance and suitable
directions. This would help in utilization of Srisailam units in pump mode in
optimal manner especially with the higher renewable integration.
6.2 Low Frequency
a) Summary statement of different violation messages issued by SRLDC to each constituent as per new IEGC Amendment.
b) In the 124th OCC Meeting it was suggested that SRLDC may identify incidents of UD/OD for Analysis by States. SRLDC to furnish the incidence for analysis, if any.
c) In the earlier OCC Meetings SRLDC had suggested that ADMS settings may be changed to 49.9 Hz. and contingency plan w.r.t Tamil Nadu needs to be reviewed considering generation loss at pooling station level. TANTRANSCO was suggested to revert back.
(Item No. 5 (a) of enclosed SRLDC letter dated 28.06.2017) 6.2.1 Messages for violation of Deviation Limits 6.2.1.1 SRPC analysis of UD/OD for the period from 16.05.2016 to 15.06.2017 is at Annexure-6A
7 VOLTAGE PROFILE
7.1 Low voltage
a) It was observed that voltages at all nodes are above 380 kV during June 2017.
b) Details of Capacitors installed during June 2017. Details of the healthy/faulty
capacitors to be furnished.
c) KPTCL to furnish the updated status of the following:
Issues with BESCOM
Commissioning of 30 MVAR Capacitor banks at Somanahalli.
Any other action taken to improve the voltage profile in and around Bangalore.
UV Relay
Agenda for 133rd OCC Meeting to be held on 13.07.2017 at SRPC Bengaluru Page 27
State Location identified for implementation
Status of implementation /Remarks
KPTCL Somanahalli
Nelamangala
Hoody
1st Stage of 100 MW implemented at Somanahalli, Nelamangala and Hoody. The list of feeders given by BESCOM has been configured to trip whenever logic satisfies the condition specified. For Second Stage a letter had been communicated to BESCOM to identify the new set of feeders as the existing list of feeders configured will not suffice the required relief.
In 132nd OCC Meeting KPTCL had informed that feeder details from BESCOM are awaited
for implementation of second stage. It was suggested that if BESCOM was not able to
identify the feeders, feeders at higher level may be identified to trip through SCADA.
KPTCL had been asked to share the communication may be to BESCOM in this
regard.
(Item No. 6 (b) of enclosed SRLDC letter dated 28.06.2017).
7.1.1 Installation of Shunt Capacitors
7.1.1.1 The information regarding installation/healthy capacitors in the required format needed to be
regularly furnished every month. SRLDC requested that installation & ensuring healthiness
of capacitor banks at distribution level should be ensured by all the constituents.
7.1.1.2 PSS/E Base Case model has been received from the states of SR for low voltage scenario.
Complete converged network of SR had also been modeled by SRLDC/SRPC and
submitted to CPRI on 23rd March 2017 for capacitor requirement assessment. SRPC vide
letter dated 27.03.2017 had again requested constituents to make necessary arrangements
to contribute towards Consultant Fee charges for assessment study to CPRI.
7.1.1.3 SRPC vide letter dated 03.05.2017 had communicated to CPRI that SRPC is now pleased to
place a work order on CPRI for carrying out the assessment studies for Southern region
(except Karnataka). The total cost would be Rs.17.35 lakhs, excluding taxes, for the
Regional level study of Capacitor requirement for SRPC excluding Karnataka from the
scope of study. 4 states will be there as part of study namely Andhra Pradesh, Kerala and
Tamil Nadu and Telangana.
The terms of payment are as follows: 50% of the total consultancy charges after the preliminary data collection.
30% of the total consultancy charges on completion of base case load flow.
10% of the total consultancy charges after the submission of draft report.
Agenda for 133rd OCC Meeting to be held on 13.07.2017 at SRPC Bengaluru Page 28
10% of the total consultancy charges after the submission of final report.
SRPC will release the payment within two weeks of raising the invoices as per
the completion of tasks.
In this regard, Shri Anil Thomas, EE will be the Nodal Officer on behalf of SRPC. It was requested to CPRI that the study be taken up expeditiously.
7.2 High Voltage
7.2.1 High voltage at Vijayawada, VTPS, Uravakonda. Jammalmagadu. Ghani, Narnoor,
Hyderabad, Nagarjuna Sagar, Gooty, Kurnool, Malkaram, Srisailam, Sattenapalli, Warangal,
Gazwel, Bhoopalapalli, Suryapet, Mamidippalli, Vemagiri, Chittoor, Narendra, Almatty,
Pugalur Mahaboobnagar, Pugalur and 765 kV stations namely NPS, Thiruvalam and Kurnool
stations.
(Item No. 7 (a) of enclosed SRLDC letter dated 28.06.2017).
7.2.2 Status review of GT Tap positions
7.2.2.1 GT tap Positions - GT taps yet to change as per recommendation:
Station
Unit Present Tap And Corresponding Voltage(In kV)
Recommended Tap And Corresponding Voltage(In kV)
Remarks
ISTS connected Generators:
Kaiga I 1 & 2 6 & 229.125 7 & 223.25 MVAR interchange as per Special Meeting to be ensured. Kaiga II 3 & 4 3 & 409.5 4 & 399
APGENCO/APSLDC
IPPs of AP It is recommended that all IPPS under APSLDC could be advised to change their Tap position corresponding to voltage level of 400 kV / 220 kV.
KPCL/KAR SLDC
Sharavathi 9 & 10 2 & 231 4 & 220 KPCL informed that at Sharavathi new GTs (Thoshiba Make) were procured for Units 9 & 10 which were expected within one years. Tap change would be carried out after receiving the ICTs.
UPCL 1 & 2 4 & 409.5 5 & 400 Observed rotor teeth temperature issues. 2 x 125 MVAR reactors agreed in 39th SCPSPSR. It was suggested that their MVAR absorption should be around 50-60 MVAR in case they are not able to change
Agenda for 133rd OCC Meeting to be held on 13.07.2017 at SRPC Bengaluru Page 29
Tap.
TANGEDCO/TN SLDC
Tuticorin TPS 1,2,3,4 5
8 & 243 230 All the GTs in TTPS are kept in Tap No. 10.
MTPS St.III 1 6 & 409.5 7 & 399 Provision of Bus Reactor is being carried out by GCC/TANTRANSCO, Salem. After the provision of Bus Reactor the GT Tap will be increased to 7(399 kV) from Tap-6. Reactor bay works were completed at present and allotment of reactor is awaited.
7.2.2.2 GT taps of all new units getting synchronized to grid should be kept at the nominal grid
voltage level of 400 kV or 220/230 kV. SRLDC would ensure the requirement for ISTS
connected generators while SLDCs should ensure it for their embedded generators.
7.2.2.3 A Special Meeting was convened on 04.04.2017 to discuss on the MVAR
absorption/injection. The minutes of the Meeting are available at SRPC Website.
7.2.2.4 Summary / Recommendations of the Special Meeting:
For some generators, it was noted that there was injection / absorption at the same
voltage levels though tap position and Vref were reportedly unchanged. All the
generators were requested to kindly analyse the response and take steps to
improve the performance.
It was noted that there were still some margins available as per Capability Curve
and generators could consider improving the MVAR interchange.
It was noted that few units were not keeping the Vref at nominal and were changing it
manually to control / restrict the MVAR interchange. This was to be discontinued
immediately.
SLDCs would discuss MVAR issues for embedded generators along with
RGMO/FGMO issues.
SRLDC would take up the status point availability to SRLDC of the GT taps for ISG
stations wherever not extended.
MVAR testing would be taken up for a few stations shortly and schedule would be
communicated by SRLDC.
7.2.2.5 The issues regarding KGS Unit III and IV & NTPL
(Item No. 4(a) of enclosed SRLDC letter dated 28.06.2017).
7.2.2.6 MVAR Interchange/MVAR capability testing
Agenda for 133rd OCC Meeting to be held on 13.07.2017 at SRPC Bengaluru Page 30
Nodal Officers may kindly ensure that the data reaches SRLDC/SRPC in time (by
fourth of every month) so that SRLDC can correlate it with SCADA data and analysis
could be done facilitating actions for further improvement.
Recommendations finalized in the Special Meetings were required to be implemented.
All the SLDCs to kindly monitor VAR absorption/injection of generating units in their respective control areas in real-time.
Hon‟ble CERC Order dated 23.12.2009 merited attention in this regard. It had been
stated in the Order that all agencies needed to provide required reactive
compensation thus avoiding the need for exchange of reactive power to/from ISTS
and maintain ISTS voltage within specific range.
7.2.2.7 Status review of Bus/Line Reactors, Line Reactors and STATCOM
7.2.2.7.1 Status of implementation of Bus / Line Reactors approved in the Standing Committee /
SRPC pending for commissioning by the SR constituents is furnished below:
Entity Bus Name Status REMARKS
KPTCL Hoody Reactor erected on platform.
Civil works for associated elements has been taken up
Nelamangala Reactor erected on platform
June 2017
Entity Bus Name Capacity in MVAR
Approved in
Type
Remarks
PGCIL Yelahanka 2x63 Bus
Deferred as per 40th SCPSSR. When Madhugiri line will come it will be expedited.
Cuddapah 50 to 125 39th SC Yet to be awarded
APTRANSCO
Vemagiri 125 36th SC
Bus Kalpakka and Kurnool is expected by October 2017 Vemagiri and Chittoor is expected by December 2017.
Kurnool 125 Bus
Kalpakka 125 Bus
Chittoor 125 39th SC
Vijayawada 125 39th SC
It was noted that a separate reactor at Vijayawada in scope of AP had been identified. The exact location could be firmed up by APTRANSCO.
APTRANSCO/ APGENCO
VTPS Stage IV
125 39th SC
APGENCO informed that reactor enquiry was being taken up. It was noted that this reactor was different from the APTRANSCO reactor. APGENCO had been informed in this regard by
Agenda for 133rd OCC Meeting to be held on 13.07.2017 at SRPC Bengaluru Page 31
APTRANSCO
KPTCL
Davangere 125 39th SC KPTCL informed that they had taken up with CEA for reviewing. During studies no reactors had been considered at that area and arrived at 125 MVAR requirement. Now two reactors had come at Guttur and Talaguppa.
Talguppa 125 39th SC
TANTRANSCO
Almathy 125 39th SC Tender under progress
Kayathar 125 39th SC Tender under progress
TANTRANSCO/ TANGEDCO
Mettur 125 39th SC Diverted from Palavadi. Structural works are over
TSTRANSCO
Mamidipalli 125
36th SC
Bus Gazwel: Commissioned on 31.03.2017 For all other reactors Civil Works are in progress. Expected to be commissioned in September 2017.
Gajwel 125 Bus
Sankarapalli 125 Bus
Mehboob Nagar
125 Bus
Malkaram 125
Bus
TSTRANSCO: Sanction of funding from PSDF is received for 5 Nos of 125 MVAR reactors from MoP on 05.09.2016. Works for all five reactors awarded in September 2016 and works are in progress.
TSTRANSCO/ TSGENCO
Srisailam LB 125
39th SC
Erection of GIS Bus reactor is not suggestible due to financial implications and space constraint in 400 kV GIS of SLBHES. Hence, the erection of Bus reactors will be examined at other end. TSGENCO was requested to take up the issue with Standing Committee.
NPCIL Kaiga 2 x 125
Bus
KGS informed that both the reactors are expected to be commissioned by December 2019. Financial approval had been received. They were in the process of floating the tender.
UPCL Udupi 2 x 125
39th SC
KPTCL had informed that the line is planned to be LILOed at Drinking water substation between UPCL and Hassan. Subsequently the studies would be put up to
Agenda for 133rd OCC Meeting to be held on 13.07.2017 at SRPC Bengaluru Page 32
Standing Committee. UPCL will submit the issues to KPTCL and KPTCL will discuss with PCKL to sort out issues. UPCL had submitted all the information as required.
7.2.2.7.2 In the special meeting with NPCIL/BHAVINI held on 25.11.2016, the following were
deliberated with respect to KKNPP Stage II reactors:
NPCIL had informed that they had taken up the issue with CTU (through email)
and the reply was awaited.
SRPC&SRLDC had stated that the limitation of no absorption by Stage-2 units
needs to be taken up formally with CTU and the details to be communicated to
SRPC/SRLDC.
7.2.2.8 NGR bypass of Reactors
7.2.2.8.1 In the 133nd OCC Meeting SR I had informed that commissioning of NGR bypass
breaker/isolator for all reactors in SRTS I had been completed except the following
400 kV Nellore-Thiruvalam line I & II ,Thiruvalam-Kurnool I & II, Kozhikode-Mysore I & II line reactors : October 2017
(Item No. 4(a) of enclosed SRLDC letter dated 28.06.2017).
7.2.2.9 Reactive Power Planning
7.2.2.9.1 Status update on capacitor installation is given below:
Utility Reactive Power Planning Voltage level
Remarks
APTRANSCO
Kadapa: 288 MVAR
Vijayawada: 136.8 MVAR
Visakhapatanam:146.2 MVAR
On 33 kV side
14.4 MVAR commissioned
0 MVAR commissioned
0 MVAR commissioned
APSPDCL 802 MVAR
30 MVAR commissioned
APEPDCL 276 MVAR
0 MVAR commissioned.
KPTCL Bengaluru Tr. Zone:708.8 MVAR
12.1 kV LOA issued.
Bagalkot Tr. Zone :258.1 MVAR
12.1 kV Material supplied. Erection completed/under progress.
Hassan Tr. Zone 150.8 MVAR
Material supplied. Erection completed/under progress. Due to space constraints 2x2.9 MVAR Capacitor Bank at Belur, diverted from Belur to Javgal 110kV Substation
Mysore Tr. Zone :60.9 MVAR
1x2.9 MVAR at Davanur S/s commissioned on 26.10.2016
Agenda for 133rd OCC Meeting to be held on 13.07.2017 at SRPC Bengaluru Page 33
and 2x2.9 MVAR at Kikkeri commissioned on 26.10.2016
Gulbarga Tr. Zone :98.60 MVAR
No update
Tumkur Tr. Zone :281.3 MVAR
12.1 kV 40.6 MVAR commissioned. 34.8 MVAR cable laying, termination and testing and commissioning works completed. EI approval a waited. At Haluvagalu due to space problem, 2 nos of capacitor banks are diverted to JG Halli &Hariyabbe MUSS.
KSEBL
360 MVAR
66 kV Have done reactive compensation study 360 MVAR is planned. Works will be taken up after approval.
11kV
TANGEDCO 34 x 2.4 MVAR 11 kV
16 x 2.4 MVAR 22 kV 14 numbers 22 kV capacitor banks commissioned and balance works are under progress.
35 x 2.4 MVAR 11 kV Tender to be floated.
51 x 2.4 MVAR 22 kV Tender to be floated
13 x 24 MAVR 110 kV Tender under negotiation.
82 sets of 11 kV, 2.4 MVAR Capacitor Banks in Coimbatore Region
11 kV Tender to be floated.
822 MVAR capacitors at Distribution level had been commissioned out of 931 MVAR capacitors planned.
Balance 109 MVAR will be commissioned before 31.03.2017. However, for further enhancement of Reactive Power, Capacitor bank provisions have to be arranged by Planning/Transmission wings.
7.2.2.9.2 SRPC/SRLDC requested all the states to come up with the updated information like till
date commissioned, plan for new commissioning, quantum in working condition, action
taken to rectify/replace faulty capacitors, etc.
8 Network Protection/Security issues
8.1 U/F & df/dt Relays Schemes
8.1.1 Implementation of SRPC recommended quantum
Agenda for 133rd OCC Meeting to be held on 13.07.2017 at SRPC Bengaluru Page 34
It was noted that all the States had implemented and df/dt schemes fully. All the
Constituents were requested to furnish the details of the feeders implemented in AUFR &
df/dt schemes along with the status of SCADA mapping as per the specified Formats.
In accordance with clause 9 (2) of CEA (Grid Standards) Regulations, 2010, all
constituents shall submit a detailed report of operation of AUFR at different frequencies to
SRLDC and SRPC on daily basis. It was noted that only KSEBL and PED were submitting
the daily report regarding operation of relays.
8.2 SCADA mapping of feeders of AUFR & df/dt schemes
8.2.1 As per CERC vide Order dated 27.11.2015 on Petition No. 60/MP/2014, SRPC vide letter
dated 29.01.2016 had submitted the status report duly certified by SRLDC and SRPC
w.r.t implementation of SCADA mapping of all the constituents to Hon‟ble CERC. SCADA
mapping confirmation report of KSEBL had also been submitted to Hon‟ble CERC.
(Item No.8 (a) of enclosed SRLDC letter dated 26.05. 2017).
The status as updated in 132nd OCC Meeting is as follows:
State SCADA mapped
%
Status
AP 56 APSLDC informed that out of 25 RTUs, 8 had been
commissioned, 17 would be commissioned by June
2017 and they were likely to achieve around 70 %
mapping. For balance 30%, a composite proposal
has been put up for PSDF funding.
TS 79 TSSLDC informed that 6 RTUs had been provided
for Solar Generators and for 17 RTUs, procurement
was being taken up and it could take 4-5 months.
There were 18 RTUs for Interstate feeders and
some would provide UFR and df/dt relief quantum
also. With this they were likely to achieve 100%
mapping.
TN 92 Additional RTUs needed to be procured for 100%
SCADA mapping. 100 % data visibility will be
ensured by June 2017. Transducers to be procured
and expected by June 2017.
SRPC/SRLDC requested that a monthly report on the action taken to reach 100 %
availability may be furnished to SRPC/SRLDC.
8.2.2 APTRANSCO and TANTRANSCO were requested to initiate the action to achieve the 100
% SCADA visibility.
8.2.3 In the 132nd OCC Meeting, it was noted that in the feeder list furnished by APTRANSCO it
was mentioned that some of the feeders are grid connected and not radial.
Agenda for 133rd OCC Meeting to be held on 13.07.2017 at SRPC Bengaluru Page 35
8.2.4 After deliberations, it was decided that a group of officers from SRLDC & SRPC can visit
SLDCs and examine the exact status of feeders (whether radial or grid connected, what
type of tripping provisions are enabled including breaker position). As per identified
feeders list visibility at SLDC and SRLDC may also be checked.
8.2.5 Subsequently validation was carried out w.r.t. KPTCL system on 30.06.2017.
Observations at Annexure-8A
8.3 Special Protection Systems
8.3.1 It was informed by SRLDC that Mock Tests for Major Inter Regional links & KKNPP Units
had been carried out and reports had been issued.
8.3.2 All the concerned states/PGCIL was requested to take the action to rectify the issues as
mentioned in the Reports which are already forwarded to all. A compliance report needs to
be furnished by all regarding the action taken.
8.3.3 SRPC had observed that the requirement of SPS may be required to be reviewed. There is
no ATC/TTC linked with it.
8.4 System Protection using Optimization Technique (SPOT)- SRLDC proposal
SRLDC had informed that that they are following up the issue with M/s ABB. SRPC had
stated that our requirement should be firmed up first and M/s ABB could be approached
later, rather than to what ABB has to offer. SRLDC had informed that a group of
communication experts from SRPC, SRLDC, KPTCL etc may be entrusted the work of
assessing the requirement and be involved in the future course of action.
8.5 SPS operations
The SPS Operations during the month of June 2017 if any to be furnished by SRLDC.
8.6 Automatic Demand Side Management Scheme (Petition No. 250/MP/2012) & GSES
(Petition No. 265/MP/2012)
8.6.1 It was noted that the issue of changing the frequency setting to 49.9 Hz was discussed in the
29th TCC/30th SRPC Meetings held on 26th /27th August 2016 and it was agreed to retain the
settings at 49.8 Hz till the next TCC/SRPC meetings.
8.6.2 SRLDC had pointed out that similar to existing ADMS logic (O/D), backing down of
generation during the sustained U/Ds during high grid frequency may be required.
8.6.3 SRLDC had pointed out that ADMS was set at much lower point at 49.80 Hz which needs to
be enhanced to, 49.90 Hz.
OCC forum had felt that it could be reviewed in the next TCC/SRPC Meeting
8.7 Grouping of loads (IEGC clause 5.4.2 (e))
8.7.1 As per IEGC, to maintain the frequency within stipulated band and also to ensure network
security, the interruptible loads were to be arranged in four groups of loads, This was for the
Agenda for 133rd OCC Meeting to be held on 13.07.2017 at SRPC Bengaluru Page 36
purpose of scheduled power cuts/load shedding, loads for unscheduled load shedding,
loads to be shed through UF relays, df/dt relays and loads to be shed under any SPS
scheme. These loads are to be grouped in such a manner that there is no overlapping
between different groups of loads.
8.7.2 The issue was to be noted for compliance by the concerned utilities. SRLDC requested all
the states to kindly furnish the updated details in this regard.
8.7.3 Tripping Details/Reports
In various forums SRLDC had raised concern that it was not getting tripping
information/data within 24 hrs as per IEGC/CEA regulations and sometimes the
information from both the ends was not being received. Also at times, tripping details only
were being received without DR& EL details. SRLDC was unable to analyze events on
account of non-receipt of details of tripping in a timely manner. SRLDC had stated that all
tripping details should be uploaded on the SRLDC web portal. Para 29 of Hon‟ble CERC
Order dated 20.02.2014 in respect of Petition No.146/MP/2013 was brought to attention of
the OCC. Non furnishing of timely tripping details would be treated as non-compliance.
Procedure for timely furnishing information was needed to be streamlined by the utilities. It
was noted that tripping information details were to be uploaded within the stipulated time
frames.
8.7.4 Declaration of availability and healthiness of various protection / defense mechanism
8.7.4.1 SRLDC had stated that the healthiness certification was not being received in timely
manner from all the constituents.
8.7.4.2 Healthiness certificates and other reports were being sought as per directives of higher
bodies. Validated certificates needed to be communicated in a timely manner.
9 LVRT Implementation
9.1 Hon‟ble CERC has passed Order in respect of Petition No. 420/MP/2014 on 05.01.2016. The
Order directs a number of actionable points by various utilities for compliance of LVRT, CEA
& CERC Regulations etc. Three Special Meeting were conducted at SRPC Bangalore on
05.02.2016, 18.04.2016 & 05.07.2016 (Meeting minutes are available at SRPC website).
This issue was further discussed in the Special TCC Meeting held on 02.08.2016.
9.2 The following had been noted in the earlier OCC Meetings:
The following had been noted in the earlier OCC Meetings: SRLDC had pointed out that PMU at Pooling station was required to assess LVRT
performance.
TANTRANSCO had informed that P&C SCADA scheme was nearly complete and
would in place by December 2016. TANTRANSCO had informed that 40 % mapping
will be completed by June end.
Agenda for 133rd OCC Meeting to be held on 13.07.2017 at SRPC Bengaluru Page 37
TANGEDCO scheme at WTG level would be in place before next wind season (May
2017).
SRLDC had stated that the basic information which they have sought from new
generators had not received from any of the generator. SRLDC vide letter dated
20.01.2017 had requested all SLDCs to furnish the company wise installed capacity
and LVRT/HVRT characteristic at Renewable energy pooling stations.
SRLDC had requested that SLDCs may kindly prepare a geographic picture of the
Wind/Solar generators and extend it to SRLDC through ICCP. Later it can be
integrated to Regional Picture. In the REMC project extension of data s was to be
carried out by states and action now would make it easier subsequently.
9.3 All the constituents were requested to ensure provision and enabling of LVRT feature in all
the upcoming wind/solar generators before declaring COD. SLDCs were requested to
approve connectivity to new generators only on confirmation of availability of LVRT feature
and other CEA/CERC requirements. Monthly report of compliance needs to be furnished for
new wind/solar generators added to the grid.
9.4 Formulation of plan for procurement and Placement of Emergency Restoration
System (ERS) in the country
9.4.1 As per ERS requirement outlined in MoP letter dated 05.12.2014 status update on ERS is
given below:
Transmission Utility
Requirement as per MoP
Existing Status/Remarks
APTRANSCO 3 2 ERS III-submitted for approval of PSDF funding.
TSTRANSCO 1 TSTRANSCO informed that earlier tender had been cancelled and it was being retendered. Subsequently, it would be taken up for PDDF funding.
KPTCL 2 2
KSEBL 1 Tenders to be floated. Being followed up.
TANTRANSCO 2 Retendering.
PED NIL NIL
PGCIL 4 (2 Nos. Additional)
2 (SR I & SR II was having 1 no. Each)
SR II: one 400 KV ERS arrived and kept at Sriperumbudur. SR-I received and kept at Vizag. 765 KV ERS (one each for SR-I and SR-II) tendering under progress.
Agenda for 133rd OCC Meeting to be held on 13.07.2017 at SRPC Bengaluru Page 38
9.5 SCADA & COMMUNICATION ISSUES
9.5.1 A Special Meeting was held on 07.02.2017 to deliberate on pending
SCADA/Communication issues. Minutes of the Meeting is uploaded on SRPC website. The
status of pending Items as deliberated in the Special Meeting/subsequent OCC Meeting is
as follows:
S.No Issue Action Plan
1 Meeting with M/s ALSTOM
regarding AMC issues,
punch points
Alstom completed the pending works except some of the
on-site training modules, for which schedule was given
Alstom to complete by September 2017. Recovery
proposal towards short supply of software module under
the contract of constituents is initiated and the same is
under approval. Training being carried out throughout
the month of May 2017 and training is expected to
complete by the middle of June 2017.
2 ICCP link between RTAMC and SRLDC
Link is established and database tables have been exchanged. ICCP association is in progress by SRLDC and NTAMC/Manesar. Will be completed by next week. Data to be exchanged have been finalized.
3 Data discrepancies in ISGS/IPP/PGCIL/STUs
Data discrepancy is being updated and shared fortnightly. In the first SCADA O & M Meeting conducted on 4th April 2017, participants confirmed to submit their action plan against non reporting/pending data items by 12th April 2017. SR II informed that most of the points have been attended except some OLTC points. Action plan to attend the balance points (excluding the unwired) by May 2017 is sent to SRLDC SCADA department.
4 Providing additional RTU at NTPC Talcher
RTU procurement is under progress.
5 Protection coupler replacement for Kayamkulam Transmission system
Letter from KSEBL received. Approval for the depository amount to be paid to KSEBL is under process.
6 OPGW stringing on balance portion of KPTCL lines
Except Hassan-Santhigrama(7.4 kM) and mono-pole structure portion of Hoody-Nelamangala(5.3 kM), OPGW stringing is completed on all the lines of KPTCL. Work expected to be resumed in 3rd week of May 2017 and expected to be completed by end of May 2017.
7 Migration of SCADA periphery in line with SEM
Both AP & TS: Migrated to SEM based philosophy from 11:00 hours of 09.05.2017. TN migrated on 08.06.2017. KPTCL and Puducherry are pending.
8 SCADA Data failure Protocol
RTU not reporting/data failure would be communicated to the concerned entity/user with a copy to PGCIL. User would take lead role in getting the issue resolved. User/SRLDC would ensure necessary verification at their ends as explained in the training. Parallely, PGCIL would look into communication issues. User/SRLDC would appraise PGCIL about the verification at their end for PGCIL to sort out the communication issues.
Official email ID for SCADA issues to be created for each entity/User involved for easier communication
Agenda for 133rd OCC Meeting to be held on 13.07.2017 at SRPC Bengaluru Page 39
and proper delivery of information. All correspondences regarding any SCADA issue to be made through this mail ID only. Details to be communicated to SRLDC/SRPC within a weeks‟ time.
9 Integration of new elements in SRLDC/SLDC SCADA
SR I /SRII noted and shall be complied.
10 Issues with Orange Exchange
It was noted in the Meeting that a Meeting was held on 16.03.2017 at SR II Bangalore and the issues are being addressed. Most of the issues have been addressed
9.6 220kV station network and 220 kV station real time data from SR constituents may also be
emphasized and integrated. Although the above is discussed in SCADA Meeting it can be a
part of OCC Meeting also.
(Item No. 14(d) of enclosed SRLDC letter dated 28.06.2017).
9.7 KSEB issue of withdrawal of SCADA Service Engineers by Ms.GE.
In the 132nd OCC Meeting SR II, PGCIL had requested KSEBL to take up the issue at
Management level also and apprise him of the seriousness of the issue.
9.8 PGCIL SR II E-mail dated 16.06.2017(Annexure-9A) informed that award is placed on
M/s.Vallant Communications Ltd., for supply & installation of DTPC (60 no.) as approved by
SRPC. As you may be aware that the original proposal was approved for augmentation of
Raichur-Sholapur SPS and the protection signals have been planned to be sent directly from
Raichur to the identified load centres. Accordingly, half of the total DTPCs were planned to
be located at Raichur 765. However, there were many changes subsequently and the
requirements got changed. PGCIL requested that the final list of locations, where the above
new DTPCs are to be installed may kindly be furnished so as to dispatch to the sites
accordingly.
9.9 Status of Voice Communication between Regional entities and SRLDC
(Item No. 14(c) of enclosed SRLDC letter dated 28.06.2017).
9.9.1 SRLDC had invited attention of the forum that CERC had brought out Order on Suo moto
Petition 007/SM/2014 dated 29.01.2016 regarding SCADA. It was directed by Hon‟ble
CERC that NLDC and respective RLDC are directed to update the status of telemetry
every month at their website and persistent non availability of data from the generating
stations/substations be taken up in RPC meeting for appropriate direction and action.
Also NLDC is directed to submit user wise latest telemetry by 31.08.2016. SRLDC
informed that they have started posting this information from February 2016 on their
website
9.10 Compiled Telemetry status – Utility wise- as directed by Hon’ble Commission
Hon‟ble Commission vide order dated 19.12.2013 on Suo-moto petition No.
56/SM/2013 had directed all the utilities to provide the required telemetry within six
months of this order.
Agenda for 133rd OCC Meeting to be held on 13.07.2017 at SRPC Bengaluru Page 40
It was requested that MAPS, KGS & KKNPP may please furnish the compliance
status of pending SCADA inputs the earliest. Details in this regard were available on
SRLDC web site.
For KKNPP only 2 points are pending w.r.t GT tap position. Re -tendering was going
on and it will take 5 more months to complete the works.
10 PHYSICAL AND CYBER SECURITY/CRISIS MANAGEMENT PLAN/BLACK START
PROCEDURE
11 Physical and Cyber Security
Status update on Crisis Management Plan(C&DMP) of Power Sector is to be furnished every
quarter. Information regarding Cyber Security was to be furnished to Chief Engineer, DPD,
CEA, Sewa Bhavan, and New Delhi-110066. Report on Physical Security, other Mock Drills
for CMP, Mock Drill for Black Start Restoration was to be furnished Chief Engineer, DMLF,
CEA, Sewa Bhavan, and New Delhi-110066. A copy of the reports was to be sent to SRPC
Secretariat ([email protected] and [email protected]). Information required by CEA
(vide letter dated 26.11.2013) regarding Security of power installations was to be furnished
to CEA.
12 Black Start Procedure
In earlier OCC Meetings, SRPC/SRLDC had expressed concern that black start mock
test procedure is not being followed properly, mock exercise by point to point method is
not carried out by all and schedules are also not being furnished. All the concerned
entities were requested to furnish the details of BSRP Mock test completed during 1st
half i.e Jan 2017 to June 2017 and schedule for second half ie July 2017 to December
2017 to be submitted at the earliest.
In case of postponement or non-conducting of mock drill exercise then it must be intimated
to SRLDC along with the reason.
Status needs to be furnished in the following format :
State BSRP reports for Jan 2017 to June 2017
BSRP schedule for July 2017 – Dec 2017
Point to point mock exercise report being furnished
Updated list of Nodal Officer
Workshop Schedule
12.1 Planning of Black Start Mock drill of Nuclear Power Plants
Mock drill at KKNPP, KGS and MAPS. Kaiga and KKNPP to submit Mock Exercise
Procedure.
Agenda for 133rd OCC Meeting to be held on 13.07.2017 at SRPC Bengaluru Page 41
Development of mock exercise procedure for Individual Stations/Systems.
Point to point mock exercise for black start by all constituents.
Conducting mock exercise from RTPS to Jurala, Nagheri to BTPS and Kaiga NPP.
12.2 Conducting mock exercise from RTPS to Jurala, Nagheri to BTPS
In the 132nd OCC Meeting KPTCL had confirmed that during July 3rd week mock tests
may be planned. SRLDC, KPTCL and KPTCL may meet on a suitable day and
prepare detailed procedure
(Item No. 9(a),(b),(d) & (f) of enclosed SRLDC letter dated 28.06.2017).
12.3 Priority for Railways/Metros in the matter of Restoration of Supply
The following were noted earlier:
KPTCL: to expedite on the actionable points of KPTCL/BMRCL which were finalized in
the Special Meeting.
KSEBL: Vide letter dated 06.06.2016 had furnished the Operating Procedure for
extending supply of power to Kochi Metro.
TANTRANSCO/Southern Railway: The follow up of actionable points finalized in the
special meeting in respect of Chennai Metro may be expedited.
TSTRANSCO: was requested to take proactive action in respect of Hyderabad Metro.
13 RGMO
13.1 RGMO response had been deliberated in various Special/OCC/TCC/SRPC meetings.
Inadequate response was an area of serious concern and there was no noticeable
improvement.
13.2 In earlier OCC Meetings, the following had been noted:
SLDCs were requested to analyze the RGMO instances posted by SRLDC for the
generators in their control area and take up action as per 84/MP/2015.
Inadequate Response to be taken up with SERC (Petition No.302/MP/2013).
Action on recommendations finalized in the Special Meetings needed to be taken
by generators/states. All generators were kindly requested to take all steps to
ensure intended RGMO/FGMO response.
As per the order in RGMO Petition No. 302/MP/2013, the units (including state
embedded) shall not be scheduled beyond their ex-bus generation corresponding
to 100% of their installed capacity.
13.3 A Special Meeting had been convened on 04.04.2017 to discuss on RGMO/FGMO issues.
The minutes of the Meeting are available at SRPC website in which Summary /
Recommendations are listed out. It was noted that different logics were implemented by
different generators for RGMO compliance. A sub group meeting to have a better
understanding of different logics was held on 12.04.2017.
Agenda for 133rd OCC Meeting to be held on 13.07.2017 at SRPC Bengaluru Page 42
13.4 SRLDC vide letter dated 12.06.2017 had communicated regarding implementation of
RGMO as per IEGC 5th Amendment. The salient points of deliberations in the RGMO
subcommittee meeting held at SRPC Bangalore on 12.04.2017 were also included in the
letter. SRPC vide letter dated 15.06.2017 enclosing SRLDCs letter had communicated to
all concerned in this regard and had requested that comments, if any, may kindly be
intimated to SRPC/SRLDC on or before 26.06.2017.
13.5 NTPC vide E-mail dated 04.07.2017 (Annexure-13A) had informed that NTPC
Ramagundam has implemented the RGMO logic as per IEGC 5th Amendment regulation.
Accordingly, there will not be reduction in generation in case of improvement in grid
frequency to a level below 50.00 Hz. For any fall in grid frequency, generation from unit will
increase as per generator droop up to a maximum of 5% of the generation subject to
ceiling limit of 105% of the MCR of the unit having regard to machine capability.
13.6 NTECL vide E-mail dated (Annexure-13B) had informed that NTECL has implemented the
RGMO logic as per IEGC 5th Amendment regulation in their all units .
13.7 Chief (Engg), CERC vide letter dated 05.06.2017 had informed the following regarding
RGMO/FGMO compliance by generators in the Region:
Central Electricity Regulatory Commission (IEGC) Regulation, 2010 at 5.2(i)
provides that generators should provide RGMO/FGMO response. Further, vide 5th
Amendment to IEGC dated 12.4.2017, it has been provided at Regulation 5.2(h)
that RLDCs/SLDCs shall not schedule the generating station or unit(s) thereof
beyond ex-bus generation corresponding to 100% of the Installed capacity of the
generating station or unit(s) thereof and that the generation station shall not resort
to Valve Wide Open operation of units so that primary response is ensured.
RPC Secretariats and respective RLDCs are requested to obtain the status of
availability of RGMO/FGMO response from the generators (ISGS as well as intra-
state generators) in its region. The status of actual response being provided by
generators under the primary response may also be provided.
13.8 SRPC vide E-Mail dated 07.06.2017 had taken up the issue with all the generators/SLDCs. It
was informed that SRPC/SRLDC have finalized a format which has been circulated in
[email protected], [email protected] and uploaded at SRPC
website. It was requested that the details may be filled up at their end and furnish to
SRPC/SRLDC for vetting and further submission to CERC.
13.9 In the 132nd OCC Meeting after deliberations it was decided to revise the format and
accordingly the Revised Format along with the analysis for the incidents on 26.04.2017,
09.05.2017,18.05.2017, 20.05.2017 & 23.05.2017 had been circulated to all the
concerned.
13.10 It was requested that the reports may be kindly looked into and the constituents may revert
back with any comments/observations by 24.06.2017, so that the observations submitted
to SRPC/SRLDC will be vetted and further submitted to CERC
13.11 SRLDC vide letters dated 04.07.2017(Annexure-13C) had taken up the issue of no
response/poor response/partial response with TPCIL and IL & FS based on the analysis
made for the incidents on 26.04.2017 & 20/23.05.2017.
The following were highlighted:
Agenda for 133rd OCC Meeting to be held on 13.07.2017 at SRPC Bengaluru Page 43
As per the clause 5.2(f) (a) of IEGC and subsequent amendments thereafter, all
Coal/lignite based thermal generating units of 200 MW and above shall provide
governor response per the regulations specified in the clause which is
reproduced below
“There should not be any reduction in generation in case of improvement
in grid frequency to a level below 50.00 Hz. For any fall in grid frequency,
generation from the
unit should increase as per generator droop up to a maximum of 5% of the
generation subject to ceiling limit of 105% of the MCR of the unit having regard
to machine capability”
The following was noted w.r.t TPCIL Units:
All the three incidents posted by SRLDC requires more than 5%
change in generation hence expected response is taken as 5%
generation. But TPCIL generators provided only maximum 10% of
expected response. Generating units of such a large capacity (660
MW) not providing primary response in case of exigencies is a serious
threat to grid security. Hence it is requested to review the RGMO logic
implemented in the units and fine tune the logic for providing the
adequate primary response as mandated in IEGC.
The following was noted w.r.t IL & FS Units:
All the three incidents posted by SRLDC requires more than 5%
change in generation hence expected response is taken as 5%
generation. But ILFS generators provided only maximum 25% of
expected response for frequency dip incidents & 43-50% for frequency
rise incidents. It can be observed from analysis that unit‟s rgmo
performance is not satisfactory for frequency fall incidents. Generating
units of such a large capacity (600 MW) not providing adequate
primary response in case of exigencies is a serious threat to grid
security. Hence it is requested to review the RGMO logic implemented
in the units and fine tune the logic for providing the adequate primary
response at all times as mandated in IEGC.
13.12 In a similar line SRLDC vide letters dated 05.07.2017(Annexure-13D) had taken up the
issue with CEPL and Krishnapatanam Generating Stations..
13.13 RGMO implementation/ Extension of RGMO status point to SLDC
State/Entity RGMO Status extension to
SLDC/SRLDC
Comment
TS Thermal updated. Hydro TSTRANSCO is
Agenda for 133rd OCC Meeting to be held on 13.07.2017 at SRPC Bengaluru Page 44
Manually updated at the TSSLDC requested to take up the
issue with GENCO and
solve the issue
KAR RTPS-4, Supa and LDPH RTPS Unit IV: will be
made available during R
& M works. LDPH:
Carried out the works.
Complete wiring is over.
Extended upto SLDC.
Supa: yet to be carried
out.
KER Sholayar Sholayar: one unit
extended. Rest will be
extended during R & M.
It was noted that (if technically not feasible) breaker contacts could be alternatively extended for FGMO with MI as status point. For RGMO status point was to be extended.
RGMO could be kept ON always, even though the unit is out.
All SLDCs were suggested to ensure various provisions of IEGC/CERC/CEA regulations including RGMO before confirming COD for the embedded generators.
To maintain the continuity of the issues, it was agreed that Nodal Officer should invariably attend the meetings.
The list of Nodal Officers was updated in the Meeting.
13.14 KSEBL vide letter dated 17.06.2017(Annexure-13E) had furnished the details status of
FGMO/RGMO in their Units.
14 TRANSMISSION NETWORK ISSUES AND SYSTEM OPERATION ISSUES
14.1 Loadability of ICTs and revisit of the associated protection settings to prevent cascaded
tripping of ICTs / high loading of transmission lines
14.2 Insufficient action in controlling the loading of ICTs leads to N-1 criteria violation in
compliance of Regulation 3.1 f(8) of CEA(Grid Standards) Regulations 2010 and Regulation
3.5 a(i) of CERC Indian Electricity Grid Code Regulations 2010.
14.3 High loading on 400 kV Vemagiri PG- Vijayawada & Vemagiri PG-Gazuwaka lines and
status of system strengthening beyond Vemagiri PG Station.
14.4 SRLDC had requested all the constituents that whenever real time messages were issued
to control over ICT loadings, constituents should be committed to take necessary steps/load
shedding to curtail the overloading. SRLDC requested for urgent action to alleviate the
loading of 400/220 kV ICTs. A long term solution of augmentation/load reconfiguration
needed to be considered / implemented in view of grid security. Action Plan of constituents
to restrict the loading to permissible limit may kindly be furnished to SRLDC and immediate
action needs to be initiated.
(Item No. 8(c&d) of enclosed SRLDC letter dated 26.05.2017).
Agenda for 133rd OCC Meeting to be held on 13.07.2017 at SRPC Bengaluru Page 45
15 Prolonged Outages
15.1 Status review of prolonged outage of grid elements in SR & Realistic Action plan for revival
of the prolonged outage was awaited from some of the constituents. Monthly reports are
required to be submitted to CERC.
15.2 Prolonged Outage of U3, NTPC, Ramagundam for May 2017
NTPC vide letter dated 21.06.2017 had informed that NTPC Ramagundam Units-3 was
taken out in Overhauling for the period of 30 days (1st April 2017 to 30th April 2017). After
overhauling unit was synchronized to grid on 1st May 2017 at 05:12 Hrs. Further, due to
heavy leakage of steam from parting plane of HPT casing, it was decided to open the turbine
for detailed inspection. After completion of the job Unit was synchronized at 23:39 Hrs. of
21st May 2017.
16 Upper Sileru - Balimela line had been idle charged from 8th January 2015 from Upper Sileru
end. Revival of the line.
17 Upcoming Generating Stations
Station Unit Installed Capacity
MW
Scheduled date of synchronizing / commissioning
Remarks
NTPC
Kudgi TPS Stage-I
I,II, III
3 x 800= 2400
Unit-I Synchronized and achieved full load on 25.12.2016. CoD by May 17/June 2017. Unit-II Synchronization by Feb‟17. CoD by Aug‟17 Unit–III Synchronization by May 17. CoD by Nov‟17
On a query, NTPC confirmed that full DC would be ensured and there were no constraints.
Telangana STPP Phase I
2 x 800 U-I CoD May 2020 U-2 CoD Nov 2020
Pudimadaka AP 4 x 1000 52 Months from Zero Date
85% share to AP. Zero date yet to be finalized. AP requested NTPC to firm up the zero date at the earliest. AP informed evacuation system would be developed by PGCIL
30th TCC: NTPC informed that the domestic coal was yet to be tied up. APTRANSCO informed that they would apply for LTA with CTU after the coal linkage is firmed up.
NLC
Agenda for 133rd OCC Meeting to be held on 13.07.2017 at SRPC Bengaluru Page 46
New Thermal Power Project
I 500 April 2018 CTU had informed that for evacuation LILO of Neyveli - Puducherry and 400 kV D/C to Araliyur lines are planned. NLC had applied for LTA of 340 MW which could be managed with the LILO of Neyveli – Puducherry. Balance 600 MW would be catered by 230 kV system of TANTRANSCO. Araliyur S/S was being developed by TANTRASCO and was expected by June 2018
II 500 April 2018
NPCIL
BHAVINI
Kalpakkam (PFBR)
I 500 Synchronization by March 2017 COD by Sep 2017
UMPP
Krishnapatnam 3960 (6 x 660)
APEPDCL and PCKL had taken steps with their legal counsel to expedite the hearing before Honorable High Court of Delhi
Cheyyur 4000 New bids would be called
17.1 It was noted that NTPC Kudgi vide CERC Order dated 30.05.2017 had received permission to interchange of infirm power into Grid for commissioning tests including Full Load Test of Unit I upto 27.11.2017 or actual date of COD whichever is earlier. NTPC had informed that since the power input arrangement for running design make up water pump is essential for sustainable operation of Unit and establishing the same shall take more time infirm power from Unit I of the project needs to be injected to the Grid beyond 27.05.2017.
NEW PROJECTS OF STATE SECTOR & IPP
Updated status of new projects of State sector is furnished below:
Sl No
Name of project Located in
Capacity in MW
Commissioning Schedule /Remarks
1 Rayalaseema TPS ST-IV
AP 1 x 600 Synchronization by June 2017 COD by Dec 2017
2 Dr. NTTPS, Vijayawada
AP 1 x 800 2017-18
3 Krishnapatnam Stage II (U3)
AP 1 x 800
4 Polaki AP 4000 (5 x 800 MW)
5 Edlapur KAR 1 x 800
6 North Chennai Stage III TN 1 x 800 2019-20
7 North Chennai Stage IV
TN 2 x 800 Beyond 2019-20
8 Ennore TPS Exp TN 1 x 660 2018
9 Ennore replacement TN 1 x 660 2018
Agenda for 133rd OCC Meeting to be held on 13.07.2017 at SRPC Bengaluru Page 47
10 Udangudi Stage I TN 2 x 660 2019-20
11 Uppur TPP (TBCB) TN 2 x 800 2019-20
12 Singareni Telangana 2 x 600 Unit I: CoD from 25.09.2016 Unit II: CoD from 02.12.2016
13 Manuguru PPP Telangana 4 x 270 U1 : 20.03.2017 U2: 20.05.2017 U3: 20.09.2017 U4:20.09.2017
14 Kakatiya TPP Stage III Telangana 1 x 800 2017-18
15 Kothagudem TPS Phase VII
Telangana 1 x 800
16 Damaracherla (Yadadri)
Telangana 2 x 600 + 4 x 800
2018-19
Updated status of new projects of IPPs is furnished below:
Sl No.
Name of project Located in
Capacity in MW
Commissioning Schedule /Remarks
1 Meenakshi PH-II AP 2 x 350 2017-18 Untied: 640 MW
2 East Coast Energy Thermal
AP 2 x 660
2017-18 AP : 300 MW
3 Thermal Powertech (TPCIL) Unit-III
AP 1 x 660
2017-18
5 Godhna TPP, Janjir – Champa Dist, Chhattisgarh
For KAR 2 x 800 2017-18
SRPC had stated that declaration of COD letter from SLDC was required to be submitted to
CEA, Fuel Management Division for coal linkage etc.
SRLDC pointed out those new ISTS connected units should come out with detailed
metering scheme for various units commissioning schedule at least one year prior to
synchronization. The scheme needed to be discussed and finalized in the Meeting of
Commercial Sub Committee.
17.1 Schedule of trial run and COD of Kudgi TPS Unit I
17.2 ATS for Yeramarus, BTPS Unit III and Hinduja.
(Item No. 13 of enclosed SRLDC letter dated 28.06.2017).
18 LGBR & OUTAGE PLANNING
18.1 Status Review on development of load forecasting tools by SLDCs as per IEGC
Clause 5.4.2
The issue was noted for compliance by the states/SLDCs.
18.2 The following was noted from the Order dated 19.12.2013 on Petition No.
249/250/251/MP/2012
Agenda for 133rd OCC Meeting to be held on 13.07.2017 at SRPC Bengaluru Page 48
“We direct all STUs/SLDCs of the Northern Region, Southern Region and Eastern Region to
forecast their demand and make adequate arrangements to avoid dependence on
Unscheduled Interchange for meeting their demand or for injecting short term surplus power,
irrespective of the frequency”
There was need for further involvement of DISCOMs for their 96 block load forecast and by
state generators of their 96 block generation forecast. SLDCs needed to play more proactive
role in this regard.
18.3 Outage deviation report for the period April 2017 –June 2017 in respect of Generating
Units/Transmission Elements of Southern Region
Outage deviation report for the period April 2017- June 2017 in respect of Generating
Units/Transmission Elements of Southern Region need to be submitted by all the
constituents which is to be communicated to Hon‟ble CERC.
19 Constituents/Generators are also requested to furnish the following Data/Information:
a. Minimum/Maximum Demand Ratio of Constituent States: Information and measures adopted may please be shared.
b. Forced/Planned outages of thermal units.
c. Status of Srisailam/Kadamparai/Nagrjunasagar: Pump mode operation.
d. Installed Capacity in MW as on 30.06.2017. Additions to Installed Capacity in
June 2017.
e. Submission of details of new elements to be provided on monthly basis in the
agreed format by all the Regional Entities.
(Item No. 12 of enclosed SRLDC letter dated 28.06.2017).
f. Load Shedding in MW & MU carried out during June 2017 on daily/hourly basis.
g. Capacity in MW of Wind Mills/Renewable (Category wise) added in June 2017 by
State Sector and Private Sector - to be furnished separately.
h. PLF & PAF of Thermal & Nuclear Power Stations/ISTS connected MPPs.
i. Details of Energy Exchanges by the states (including embedded IPPs/CPPs)
through Power Exchanges.
j. Constituents may apprise the OCC of surplus power available, if any.
k. Progress of works of generating units to be commissioned in 2017-18 and also
coming up in future.
l. Details of Power Cuts on Industries, Load Shedding and Power supply to
Agriculture Sector may please be furnished in the Proforma prescribed by CEA
vide their letter No. 1/AI/COR/GM-2004/3405 dated 23.11.2004.
Agenda for 133rd OCC Meeting to be held on 13.07.2017 at SRPC Bengaluru Page 49
m. Coal Stock Position to be submitted on monthly basis by Generators
(States/ISGS).
n. Uploading of hourly Load Shedding details (both scheduled and unscheduled)
effected in previous day by all the constituents in SR.
o. Loss of generation due to coal shortage/technical problem needs to be furnished
for onward transmission to NLDC by 1000 hrs on daily basis.
p. Collection of data regarding Power Supply to Rural Areas
In the Meeting held at MoP on 09.04.2014 it had been decided to collect the data
invariably from DISCOMs. It is requested that the data in this regard in the
required format may please be arranged to be communicated to SRPC
Secretariat at the following E-mail addresses: msssrpc-
[email protected]/[email protected]
Data to be communicated by first week of the month for previous month.
q. Reporting the Status of implementation of the recommendations of the Enquiry Committee
Status as on last day of the month to be forwarded by 3rd day of the following
month, and that as on 15th of the month to be forwarded by 17th of the month All
the constituents were requested to furnish timely status updates
r. Energy Generation data Management from Renewable Energy Sources Monthly generation data in respect of Renewable Energy Sources was to be submitted to CEA with a copy to SRPC.
s. Reference from MNRE regarding compilation of data for meeting renewable energy Targets of 175 GW by 2020 MNRE/ MoP /CEA vide letters dated 02.03.2016, 22.03.2016 and 29.03.2016
respectively had communicated regarding compilation of data for meeting
renewable energy targets of 175 GW by 2020. The concerned State
Utilities/Generating companies are requested to furnish the data suggested by
MNRE. SLDCs are also requested to coordinate and furnish the data for the
generators in their control area.
It was noted that only APTRANSCO, TSTRANSCO, KSEBL and JSWEL had
furnished the information in this regard.
All the other utilities to furnish the information in this regard.
20 Any other point with the permission of the Chair.
21 Date and Venue of the next Meeting.