SOUTH DAKOTA 2014-2017 TRANSPORTATION IMPROVEMENT PROGRAM (TENTATIVE)
Transcript of SOUTH DAKOTA 2014-2017 TRANSPORTATION IMPROVEMENT PROGRAM (TENTATIVE)
1
SOUTH DAKOTA 2014-2017
TRANSPORTATION IMPROVEMENT PROGRAM (TENTATIVE)
Projects in the Rapid City Region
JULY 24, 2013
2
PROJECTS CURRENTLY IN PROGRESS IN THE RAPID CITY REGION
3
Currently in Progress I-90 eastbound lanes - Exit 10 – Exit 17
In Spearfish
• $12.4 million • Heavy Constructors • New concrete pavement in the
eastbound lanes • Work at Exit 14 excluded • Exit 10 to 14 anticipated to be complete
by end of July • Exit 14 to 17 to begin after 2013
Sturgis Rally and completion in December 2013
4
Currently in Progress I-90 eastbound lanes – Exit 112 - Exit 121
East of Wall
• $15.8 million • Stanley Johnsen Concrete • New concrete pavement in the
eastbound lanes • Subgrade treatments and edge drains • Completion date November 2013
Currently in Progress SD44 in Rapid City
Jackson Blvd from Rapid Creek to Mt View Road
5
• $15.5 million • Heavy Constructors • New concrete pavement • Bike lanes • Signal and lighting upgrades • New water, sanitary sewer, and storm
sewer • Major work to be completed by end of
2013 • Completion date June 2014
Currently in Progress SD34 – Lazelle Street - Sturgis
6
• $1.0 million • Ainsworth Benning Construction • ADA and sidewalk modifications • Lighting and signal upgrades • City water line • Work completed in early July 2013
• $1.1 million • Hills Materials Company • Mill and overlay asphalt pavement • Work starting after 2013 Sturgis Rally • Completion date in October 2013
Currently in Progress US385 – Heartland Express
Oelrichs to Nebraska State Line
7
Final Project of Heartland Express in South Dakota • $25.2 million • Loiseau Construction • Construction of 2 additional lanes 13.5 miles
• Earthwork • Drainage Structures • Concrete and Asphalt Pavements
• October 2014 Completion Date • Summer 2014 anticipated completion
Currently in Progress US16 & US16A
Custer & Hill City ADA Upgrades
8
• $1.0 million • Stanley Johnsen Concrete • Installation of new concrete ramps for ADA
compliance • Traffic signal and pedestrian push buttons • Work in Hill City is anticipated to be
completed by mid-July 2013 • Work in Custer is anticipated to begin late
August 2013 • Completion date December 2013
9
9
2014 to 2017 State Proposed Major Projects
SDDOT Rapid City Region
Roughlock
Falls
Badlands
National Park
Center of Nation
Belle Fourche
Needles Highway
Harney Peak
10
2014 - Item #9; SD87 Appx 1.7 m NW of the SD89 Jct near Hood Tunnel
• Roadway Widening • Context Sensitive Barriers
$2.3 million
11
2014 - Item #14; I-90 Westbound Lanes in Spearfish From Exit 10 – Exit 17
• Remove & replace concrete • Grading • Bridge modifications • Lighting at Exit 12 • Work at Exit 14 excluded
$12.8 million
Spearfish
12
2014 - Item #15; US85 -Deadwood From US 385 to Cemetery St.
Reconstruction of existing 2 lane to 3 lane roadway: • Left turn lane at various locations • On-street parking at various
locations • Asphalt concrete surfacing • Curb & gutter • Storm sewer • Roadway lighting • Traffic Signals
$8.4 million
Deadwood
13
2014 - Item #16; US85 – Lead Main St. from South Main St. to Washington St.
Lead • Concrete pavement • Curb & Gutter • Sidewalk • Storm Sewer • City utilities • Roadway Lighting • Pavement repair on US14A
$4.8 million
14
2014 - Item #19; I-90 Eastbound Frontage Road I-90 service road west of interstate from Exit 40 - Exit 44
• Grading • Asphalt concrete surfacing • New bridge • New Culvert & I-90 Crossover (for future reconstruction of I-90)
$13.7 million
Exit 40 Tilford
Exit 44 Piedmont
15
2014 - Item #20; I-90 Westbound Frontage Rd. From Exit 44 - Exit 46 east of I-90
• Elimination of the existing Frontage Rd.
• Reconstruction of existing Meade County Roads
• Construction of new roadway • Grading • Asphalt concrete surfacing • New drainage culverts
$2.7 million
Exit 44 Piedmont
Exit 46 Piedmont
16
2014 - Item #21; SD34 Over Bear Butte Creek, Spring Creek, Four Mile Creek, &
Belle Fourche River
• Replace 4 structures • Grading • Curve realignment at two (2) of the structures • Asphalt concrete surfacing
$4.4 million
9 M
ile R
oad
2014- Item #25; SD44 From US385 to Chapel Lane in Rapid City
17
• Mill • Asphalt concrete resurfacing
$4.5 million
Rapid City
2014- Item #26; SD44 – Jackson Blvd Rapid City From Chapel Lane Rd to Rapid Creek
18
Rapid City
• Grading • Concrete surfacing • Bike lanes • Curb & Gutter • Sidewalk • Storm sewer • Traffic signals and lighting
$9.0 million
2014- Item #27; US16– Rapid City Mt. Rushmore Rd. from Tower Rd. to Flormann St.
19
1st Phase • Grading • Concrete surfacing • Curb & gutter • Sidewalk • Storm sewer • Traffic Signals and Lighting • Bridge work
$4.8 million
Rapid City
2014- Item #28; SD231 – Rapid City From Sheffer Street to Sturgis Road
20
• Grading • Concrete surfacing • Curb & gutter • Sidewalk • Storm sewer • Traffic Signals and Lighting
$10.6 million
Rapid City
2014- Item #29; I-190– Rapid City Intersection of US16 & I-190 & West Blvd
21
Intersection Improvement • Removal of islands • Traffic signal modifications • ADA modifications
$0.7 million
Rapid City
2014- Item #31; Sheridan Lake Rd - Rapid City From US385 to Alberta Rd
22
• Grading • Asphalt concrete Surfacing • Curb & Gutter $8.5 million
Rapid City
2015- Item #64; SD18P & SD471 Near Edgemont
23
• Replace bridges • North of Edgemont on SD18P • 1.3 miles south of Edgemont on SD471
• Approach grading and surfacing $4.2 million
Edgemont
2015- Item #66; US85 in Buffalo and south of Buffalo
24
• ADA upgrades, asphalt concrete resurfacing in Buffalo
• Mill & asphalt concrete resurfacing 12 miles south of Buffalo $4.1 million
Buffalo
2015- Item #67; I-90 - Exit 14 in Spearfish
25
EXIT 14
SPEARFISH
Reconstruct Interchange: • Reconfigure crossroad, ramps, and Colorado Blvd • Traffic Signals and Lighting $21.2 million
26
2015 - Item #75; I-190 – Exit 1 (Silver Street )- Rapid City From Omaha St. to north of Anamosa St.
Interchange Replacement • Grading • Asphalt and concrete
surfacing • New bridges at Silver Street • Storm sewer • Curb and gutter • Traffic signal $16.2 million
Rapid City
27
2015 - Item #76; SD240 From Wall south to Badlands National Park
• Shoulder widening • Mill & asphalt concrete resurfacing
$5.6 million
i90
i90
Wall
28
2015 - Item #77; US16 – Rapid City Mt Rushmore Rd. from Flormann St. to St James St.
2nd Phase • Grading • Concrete surfacing • Curb & Gutter • Sidewalk • Storm Sewer • Traffic Signals and Lighting
$5.2 million
Rapid City
29
2015 - Item #78; Anamosa St - Rapid City From Midway St. to Milwaukee St.
• Grading • Concrete surfacing • Curb & Gutter • Sidewalk • Storm Sewer • Intersection Improvement • Traffic Signals and Lighting $3.1 million
Rapid City
30
2015 - Item #79; East Blvd- Rapid City East Blvd & East North St. from St Joseph St. to Herman St.
• Grading • Concrete surfacing • Curb & Gutter • Sidewalk • Storm Sewer • Intersection Improvement • Traffic Signals and Lighting $5.9 million
Rapid City
2015- Item #82; South Rochford Rd. from Rochford southwest to Deerfield Rd.
31
Reconstruction of existing 2 lane roadway: • Grading • Drainage Structures • Asphalt Surfacing
$10.0 million
Rochford
Mystic
Hill City
32
2015 - Item #83; SD73 Bridges northwest of Faith over Flint Rock Creek and
Moreau River
• Replace 2 bridges • Approach Grading • Asphalt surfacing $3.1 million
Faith
33
2015 - Item #85; US18 & SD391 US18 from Pine Ridge east 17 miles then south on SD391
to Nebraska State Line
Pine Ridge
• Shoulder Widening • Mill & asphalt concrete
resurfacing • New box culverts
$20.2 million
34
2016 - Item #114; I-90 I-90 eastbound and westbound lanes between
Exits 40 & 44 and Exit 44 Interchange
• Reconstruct Interstate • Concrete Pavement • Reconstruct interchange at Exit 44 • New bridges at Elk Creek and Little
Elk Creek
$31.4 million
Exit 40 Tilford
Exit 44 Piedmont
35
2016 - Item #115; Main Street in Sturgis From Middle Street to Fourth Street
• Grading • Asphalt concrete Surfacing • Curb & Gutter • Sidewalk • Storm Sewer
$1.5 million
Sturgis
36
2016 - Item #121; US16 in Rapid City Mt Rushmore Rd. from St James St. to Omaha St.
3rd Phase Reconstruct roadway from St. James St. to Kansas City St. • Grading • Concrete surfacing • Curb & gutter • Sidewalk • Storm sewer • Traffic Signals and Lighting Minor surface repair from Kansas City St. to Omaha St.
$4.0 million
2016- Item #122; SD231 & SD44 in Rapid City West Chicago St. from Sheffer St. to Deadwood Ave.
and Omaha St. from Deadwood Ave. to 12th St.
37
• Grading • Concrete surfacing • Curb and gutter • Sidewalk • Storm sewer • Traffic Signals and Lighting • Structure repair
$11.8 million
Rapid City
2016- Item #127; SD73 & US12 SD73 from the Grand River to the Jct of US12 near
Lemmon; US12 from ND State Line to Lemmon
38
Rural areas on SD73 & US12 • Shoulder Widening • Replace box culvert
In Lemmon • Roadway Lighting
Intersection of US12 & SD73 • Roadway Lighting • Widening for turn lane
$8.0 million
Lemmon
39
2017 - Item #151; US18 Fm Jct with US385 to southeast city limits of Hot Springs
• Grading • Concrete surfacing • Curb & gutter • Sidewalk • Storm sewer • Traffic Signals and Lighting
$6.4 million
40
2017 - Item #155; I-90 east of Wall Westbound lanes from Exit 112 East to
Exit 131 (Cactus Flats)
Wall
• Mill • Asphalt Surfacing
$5.6 million
41
2017 - Item #158; SD34 – East of Sturgis From 0.2 east of SD79 East 8 miles
Safety Improvement • Shoulder widening • Inslope flattening • Asphalt surfacing
$4.7 million
42
2017 - Item #159; County Rd 14-16 in Box Elder From Exit 63 east to east of Ellsworth Rd
Reconstruction – convert divided section to a 3 lane section • Grading • Storm sewer • Asphalt concrete
$3.4 million
Box Elder
43
2017 - Item #160; US385 From North of Pactola Dam to 4 Miles North of SD44 Jct
Shoulder Widening $8.4 million
Pactola
Reservoir
44
2017 - Item #164; Sheridan Lake Rd. in Rapid City From Canyon Lake Dr. north to West Main St.
• Grading • Concrete pavement • Curb & Gutter • Sidewalk • Storm sewer • Traffic Signals and Lighting
$3.0 million
Rapid City