1 Replacement of 11 kV post / disc insulator. No. Yes 1
2 Attending fault on 11 kV post / disc insulator. No. Yes 1
3 Replacement of 11 kV Lightning arrestors No. Yes 1
4 Replacement of 11 kV fuses indoor / outdoor type. No. Yes 1
5Replacement of Jumpers of all aluminium conductor
incl. proper binding etcNo. Yes 1
6Attending fault on Jumpers of all aluminium conductor
incl. proper binding etcNo. Yes 1
7Replacement of ACSR Ferret(HT) conductor and guard
wire. span Yes 1
8Repair / Jointing of broken ACSR Ferret(HT) conductor
and guard wire. span Yes 1
9 Replacement of guard cross wire on HT line. No. Yes 1
10 Repair or rectification of guard cross wire on HT line No. Yes 1
11Replacement of 11 KV gang operated switch/11kV load
break switch.set Yes 1
12
Complete maintenance and adjustment of 11 KV gang
operated switch/11kV load break switch panel and jumper
insulators & all accessories, repair,rectification or
replacement of an part of above, cleaning of all these
insulators and contacts.
set Yes 1
13 Removal of sag of conductors of HT line. span NA 1
14 Tightening of terminal connections and clamps etc. No. NA 1
15 Dismantling of HT over head lines. span NA 1
16Checking, cleaning and tightening of overhead line
insulators including rectification and binding of the
conductor with the insulator.
No. NA 1
17Digging out of HT (11/ 3.3 kV) cable of all sizes from ground
and re-filling the earth.Mtr NA 20
18Removal of HT (11/ 3.3 kV)cables from Trench/Trays/ pipes
structure etc.Mtr NA 47
19Digging and removal of old damaged cable in ground &
laying of new cable.Mtr Yes 22
20Removal /Re-laying of HT cable (11/ 3.3 kV) from / in ground
as desired by the Engr. in charge. Mtr NA 20
21Removal / Re-laying of HT cable (11/ 3.3 kV) from / in trench/
trays/ pipe structure etc.Mtr NA 20
22aStraight through / end jointing with heat shrinkable kit. 11KV
(UE) / 3.3 KV (UE) grade. No. Yes 2
22bStraight through / end jointing with epoxy kit. 11KV (UE) /
3.3 KV (UE) grade. No. Yes 1
23 Laying of HT cable (11 kV) as per specifications. Mtr NA
a Alongwith wall, in trench or on trays. NA 20
b Underground with supply of brick lining. NA 20
* Mat'l to
be
supplied
by NFL
SOR
Item No. DESCRIPTION OF ITEMS UnitEstimated
Qty.Rate (In Fig.)
24 Painting of poles (HT) .(Paint in contractor's scope) No. NO 86
25Digging out/removal of poles from concrete foundation
alongwith stay set wherever applicable.No. NA 200
26 Erection of pole (supply NFL's scope) No. NA 200
27 Erection of stay sets as per specifications. No. NO 1
28 Rectification of stay sets as per specifications. No. NO 1
29 Erection/replacement of cross arms on the pole. No. NO 1
30 Rectification ofcross arms on the pole. No. NO 1
31 Replacement of 132 kV LA, CT or PT. No. Yes 2
32 Replacement of 132 KV jumpers. No. Yes 2
33Cleaning/ checking of one stack of insulator of MOCB, CT,
PT, LA, Transformer bushing, isolator in 132 kV switch yard.No. NO 1288
34
Cleaning of radiator tubes of HT motors in plant.
Contractor's technician shall strictly follow all safety
precautions as per instructions of NFL's supervisor. All
materials like round brushes etc in the scope of the
contractor.
No. Man day 143
35 Replacement of 132 kV insulator stack. No. Yes 1
36Attending fault / tightening / checking of 132 kV LA, CT,PT,
jumpers or insulator stack.No. Yes 75
37Cleaning/ checking for any abnormality of one stack of string
/ suspension / strain type insulators on 132 kV towers. No. NA 1034
38Attending fault in 5A/15A socket, switch, plug top etc point
incl. tightening of connections, replacement of socket or No. yes 25819
39 Attending fault in 10/20 A plug socket, metal clad socket. No. NO 747
40 Replacement of 10/20 A plug socket, metal clad socket. No. yes 404
41Fuses (re-wirable) of all rating incl. tightening of connections
wherever reqd. incl. removal of burnt /damaged fuses
cleaning etc
No. NO 2220
42Replacement of Kit kat, HRC fuse base & carrier incl.
tightening of connections.No. yes 739
43Attending fault in Kit kat, HRC fuse base & carrier incl.
tightening of connections and replacement of rewireable
fuses.
No. NO 811
44Repalement of M.C.B.(Miniature circuit Breaker) all rating
incl. removal of burnt and replacement with new incl.
connections, tightening wherever reqd.
a MCB single pole of any rating. No. yes 446
b MCB, 3/4 pole any rating No. yes 213
45Replacement of DB/ SPN/ TPN/ TPDB of all rating including
replacement of components and tigtening of connections.No. yes 96
46Attending fault in DB/ SPN/ TPN/ TPDB of all rating
including tigtening of connections.No. yes 4228
47
Attending fault in fan point wiring incl. tightening of
connections, replacement of any or all the components like
switch, regulator selector switch or resistance for speed
variation etc.wherever reqd
No. yes 9643
48Attending fault in light point incl. replacement of any or all
the components like holder, bracket, switch, shade or their
rectification etc. wherever reqd.
No. yes 30615
49Rectification of fault of bell/buzzer incl. replacement or
repair of replacement of any or all the components likeBell,
Buzzer, switch, wire lead tightening etc. wherever required.
No. yes 2639
50
Rectification of fault in Heater/Hot plate incl. repair or
replacement of any or all the components like element, plug
top, wirelead and tightening of connections, taping etc. as
per requirement.
No. yes 1541
51
Replacement of wire mesh of size 480 x 400 mm inexisting
M.S.frame provided in the hole of kitchen exhaust fan. Wire
mesh should be of 140G with wire dia of 0.71 Sq.mm. The
M.S.frame is to be fixed back after grouting 75x6mm size
M.S. bolt. Wire mesh, nuts and bolts to be supplied by the
contractor.
No. NO 207
52Cleaning of wire mesh of Exhaust fan provided in the
kitchen / plants and public building. No. NA 1342
53Attending fault in lighting, power or telephone circuits as
required including replacement of telephone sets, rossets
and rectification in field junction boxes.
No. NA 9290
54Cleaning of light fixtures of all types, lamp shades/ Hylem
sheets of any size, incl.removal & refixing of cover/louvres
etc.
No. NA 3969
55
Rectification of fault in Heat Convector/ Geyser incl.
replacement of element (supply in NFL's scope),
thermostat, wireleads, bushes, washers, gaskets etc (supply
in contractor's scope) repair or replacement exculding
rewinding of motor for heat convector and excluding
plumbing work in case of Geyser.
No. yes 298
56 Replacement in public buildings/ offices of :-
a Lamps of all sizes No. yes 1937
b Tubes rods 20/40/65 Watts No. yes 2751
57
Renovation of ceiling/wall mounted tube light fitting,
replacement of tube rods,starter chokes, Holders,
condensor, incl.tightening of connections, etc. wherever
necessary,in public building / plant offices.
No. yes 5142
58Replacement of board and Bakelite/ Hylem/ Sunmica sheet
of switch board.No. NO
a Board Sizes upto 5"x8". 236
b Board Sizes above 5"x8". 94
59Rectification of fault of switch board and Bakelite/ Hylem/
Sunmica sheet.No. NO
a Board Sizes upto 5"x8". 4279
b Board Sizes above 5"x8". 1292
60Replacement of Bakelite/ Sunbmica/ Hylem Sheet
incl.cutting and fixing etc.No. NO 127
61Replacement of Round Block / ceiling rose.(supply in party"s
scope)No. NO 74
62Attending fault in Round Block / ceiling rose.(supply in
party"s scope)No. NO 580
63Removal /re-fixing and to and fro safe transportation to
factory complex and back of Energy Meter including taping
of all wires.
No. NA 232
64
Removal, to and fro transportation (factory to township or
within township), refixing , cleaning and trial run of ceiling fan/
kitchen fan/ Air circulators/ Exhaust fans or any other single
phase induction motor.
No. NO 110
65Removal, refixing, painting and to and fro transportation of
ceiling fan (paint in contractr's scope) as per specs. No. NA 69
66Overhauling of ceiling fans incl.greasing and replacement of
bearing, capacitor, removal, refixing, cleaning & giving its
satisfactory trial run.
No. yes 370
67Attending fault in ceiling fan, checking and Replacement of
split pins, rubber bush, etc as per requirement and cleaning
of ceiling fans.
No. NO 580
68
cleaning and checking for abnormality of ceiling fans incl
removal, complete dismantling, checking of all parts for their
integrity incl bush / bearing, assembly, refixing and taking
trial run.
No. NA 1187
69
Painting of numbers & letters on ceiling fans/ pannels/
DBs/ Poles/light fittings etc. as required. Paint brush &
stencil etc.to be supplied by contractor. Paint will be
approved by Engineer -in-Charge.
a Size :up tp 50 mm letter/number No. NA 2910
b Size up to 200 mm letter/number No. NA 1
70a Replacement of L.T. Line insulators. No. yes 1
70bReplacement of Jumpers of all aluminium conductor
including proper binding etc.No. yes 58
71aAttending fault in L.T. Line insulators, cleaning and binding
etc..No. NA 356
71bAttending faul in Jumpers of all aluminium conductor
including proper binding etc.No. NA 238
72aReplacement of all Aluminium conductor COCKROACH
(19/4.22mm).span yes 7
72b do WASP (7/4.39mm), ANT (7/3.10) and earth wire. span yes 1
73aJointing /repair of broken all Aluminium conductor
COCKROACH (19/4.22mm).span NA 5
73b do WASP (7/4.39mm), ANT (7/3.10) and earth wire. span NA 1
74 Dismantling of LT O/H Lines. Span NA 2
75 Replacement of cage guard on LT Lines. No. yes 2
76 Repair, rectification of cage guard on LT Lines. No. yes 181
77Digging out/removal of pole including stay wire, cross arms,
insulators etc from concrete foundations.No. NA 6
78Erection of Stay Sets as per specifications and tightning of
connections. sets yes 3
79Rectification of Stay Sets as per specifications and tightning
of connections. sets yes 2
80aErection of poles (Supply NFL's scope) as per
specifications. incl. Foundation, digging, and concreting etc.
(Contractor's scope).
No. NA 7
80bRepair of Poles includig necessary welding, civil jobs
digging,muffing etc and supply of material.No. NA 120
81 Erection/replacement of cross arms etc on the poles. No. yes 1
82
Painting of poles with Redoxide primer one coat & two coat
of Al. paint incl numbering of poles with stencil and paint.
Paint must confirm to Indian Standard specifications. Paint
and other materials to be supplied by the contractor.
No. NA 329
83
Replacement / installation of pole mounting junction boxes
on service lines /street light poles or tele Junction box with
frame, incl. removal of old box if any, connections of all
incoming & outgoing cables/replacement of damaged burnt
kit-kat or neutral link. Complete rectification, wrapping of
plastic polyethylene sheet covers in order to protect from
ingress of rain water as required by Engr.-in-charge. Petty
materials to be provided by the contractor.
No. yes 80
84
Attending fault in pole mounting junction boxes on service
lines /street light poles incl. connections of all incoming &
outgoing cables/replacement of damaged burnt kit-kat or
neutral link. Complete rectification, wrapping of plastic
polyethylene sheet covers in order to protect from ingress
of rain water as required by Engr.-in-charge. Petty
materials to be provided by the contractor.
No. yes 1058
85Cable connection or disconnction of armoured cable.
Reglanding (same gland), if required, is in the scope of the
contractor.
a cable sizes: up to 120 sq mm No. NO 1794
b Cable sizes: above 120 sq mm to 400 sq mm. No. NO 128
86
Glanding of cables including removal of old gland and
termination. Supply of double compression gland and lugs of
reputed make as approved by engr-in-charge will be in the
scope of the contractor.
No. NO
a cable sizes below 120 sq mm(3/4 core) No. 122
b cable sizes from 120 sq mm(3/4 core) up to 400 sq mm No. 68
87 Removal of sag of all conductors of LT line all sizes . span NA 2
88 Tightening of clamps. No. NA 1
89
Straight through/end cable jointing with heat shrinkable kits
suitable for 1.1KVgrade LT Cables of Raychem/M-
Seal/Denson/3-M make. Jointer shall be trained and hold
valid certifcate . Supply of joint as well as all other materials
in the scope of the contractor.
No. NO
a cable size upto 95 mm2 (3/4 core) No. 3
b cable size above 95 mm2 below 240 mm2 (3/4 core) No. 3
c cable size above 240 mm2 (3/4 core) No. 1
d Tele cable 101 pair No. 1
e Tele cable 51 pair No. 1
f Tele cable 21 pair No. 1
90
Straight through/end cable jointing with Epoxy jointing kits
Suitable for 1.1 Kv grade LT Cables of reputed make as
approved by engr-in-charge. Supply of joint as well as all
other materials in the scope of the contractor.
No. NO
a cable size upto 95 mm2 (3/4 core) No. 20
b cable size upto 240 mm2 (3/4 core) No. 5
c cable size above 240 mm2 (3/4 core) No. 1
91Replacement of PVC wire(NFL's scope) in wooden batton/
conduit/ PVC pipe/ PVC casing capping(contractor's scope)
including connections.
Mtr NA 4801
92aTemporary supply connections and dismantling of 24 volt
hand lamp & extension board as desired by the Engr. in
charge
No. yes 2209
92bTemporary provision of Flood Light / halogen fitting &
extension boardNo. yes 2114
92c Temporary laying of Flexible cables of any size Mtr. yes 31403
92d Laying of unarmoured telephone cables of 1/2/6 pair. Mtr. yes 7511
93aDigging out of LT cable of all sizes and re-filling the earth.
Cable (to be rolled on to drum) and bricks lining to be
transported as desired by Engr.-in-charge
Mtr NA 20
93bDigging out of LT cable and of all sizes and re-laying of the
same cable, underground with supply of brick lining as per
specifications.
Mtr. yes 527
94Laying of LT /HT cable (Cable to be supplied by NFL. All
other materials like clamping materials, bricks, sand,
cement etc. in contractor's scope.)
Mtr.
a1
Alongwith wall, pole or in trench including proper
clamping etc. (In case of laying in trench, removal and
replacement of slabs before and after the job is to be done
by the contractor.) Cable size up to 95mm2
Mtr. NA 5000
a2
Alongwith wall, pole or in trench including proper
clamping etc. (In case of laying in trench, removal and
replacement of slabs before and after the job is to be done
by the contractor.) Cable size above 95 to 240mm2
Mtr. NA 5500
a3
Alongwith wall, pole or in trench including proper
clamping etc. (In case of laying in trench, removal and
replacement of slabs before and after the job is to be done
by the contractor.) Cable size above 240 to 400mm2
Mtr NA 500
b1Underground with supply of brick lining Cable size up to
95mm2Mtr NA 2000
b2Underground with supply of brick lining Cable size above
95 to 240mm2Mtr NA 1000
b3Underground with supply of brick lining Cable size above
240 to 400mm2Mtr yes 250
c
Digging and removal of old damaged cable and laying of
new cable, incl. additional supply of sand and bricks as
desired by Engr.-in-Charge. Old Cable to be rolled on to
drum and transported as desired by the Engr-in-charge
Mtr NA 80
d1Laying under ground in RCC/PCC covered area (6-8 Inch
thick) including making good and restoring to original cable
size up to 95mm2
Mtr NA 20
d2Laying under ground in RCC/PCC covered area (6-8 Inch
thick) including making good and restoring to original cable
size above 95 to 240mm2
Mtr NA 15
d3Laying under ground in RCC/PCC covered area (6-8 Inch
thick) including making good and restoring to original cable
size above 240 to 400mm2
Mtr NA 5
e1
Laying of cable by chipping in wall/ PCC floor upto a depth
of 3 inches. Laying and fastening of cable by catcher etc.
Providing cement, making good and restoring to oiginal incl
supply of all meterials.cable size up to 95mm2
Mtr NA 72
e2
Laying of cable by chipping in wall/ PCC floor upto a depth
of 3 inches. Laying and fastening of cable by catcher etc.
Providing cement, making good and restoring to oiginal incl
supply of all meterials.cable size above 95 to 240mm2
Mtr NA 40
e3
Laying of cable by chipping in wall/ PCC floor upto a depth
of 3 inches. Laying and fastening of cable by catcher etc.
Providing cement, making good and restoring to oiginal incl
supply of all meterials.cable size above 240 to 400mm2
Mtr yes 24
fRemoval & replacement of Trailing Cables of EOT
cranes/Paddle feeders drives etc. as per scope.Mtr yes 126
g
Laying of UTP cable on wall, pole, columns, structure etc in
PVC pipe (3/4" dia) incl proper clampimg etc. Cable will be
supplied by NFL; All other materials like PVC pipe, clamps,
saddles etc in contractor's scope.
Mtr yes 400
95
Removal of cable from Trench / Trays / pipe
structures.(Removal & replacement of slabs etc. before &
after the job is to be done by the contractor. Cable to be
rolled on to drum and transported as desired by the Engr-in-
charge.
Mtr yes 9236
96Dressing and clamping of LT cable on Trays/walls up to 10
cables per tray. Supply of materials like clamps, nylon thread
and civil & welding jobs will be in the scope of the contractor.
Mtr. NA 3233
97aRemoval and replacing of cable trench covers up to trench of
width 1 mtr. No. NO 1061
97bRemoval and replacing of cable trench covers up to trench of
width above 1 mtr. No. NO 750
98Complete checking and cleaning of switches on LT
panels incl. Bus-ductNo. NO 8
99
Replacement of Star-Delta starter upto any kW Motor.
Removal of old one and burnt parts, if any, disconnection/
connection of cables, earth connections, insulation taping,
proper contacts tightening etc. as required and
approved by Engineer-in-Charge. Any civil or welding job
reqd shall be in the scope of the contractor.
No. NO 2
100
Rectification of fault of Star-Delta starter including
tightening of connections and replacement of any or all
components like contactors/relays/ timers etc upto any kW
Motor. Removal of burnt parts, if any, insulation taping,
proper contacts tightening etc. as required and
approved by Engineer-in-Charge.
No. NO 28
101
Replacement of DOL starter / photocell upto any kW motor.
Removal of old one and burnt parts, if any, disconnection/
connection of cables, earth connections, insulation taping,
proper contacts tightening etc.as required and approved by
Engineer-in-Charge. Any civil of welding job reqd shall be in
the scope of the contractor.
No. 14
102
Rectification of fault of DOL starter/photocell including
tightening of connections and replacement of any or all
components like contactors/relays/ timers etc upto any kW
Motor. Removal of burnt parts, if any, insulation taping,
proper contacts tightening etc. as required and
approved by Engineer-in-Charge.
No. NO 202
103To and fro safe transportation of 50/15 KW motor of
Sewerage pump house from site to factory and back.
Dismantling and re-fixing of motor.
No. NO 2
104aSupply and erection of earth pit as per IS:3043 - 1966,
including supply of GI pipe 40 mm dia, 2.5 mtr. long,
charcoal, salt etc. to make a complete earthing system.
No. NO 10
104bSupply and erection of earth pit as per drawings in detail
specs and other specs as per IS:3043 - 1966, including
supply of GI pipe 100 mm dia, 3.8 mtr. long, charcoal, salt
No. NO 5
104c
Supply and erection of earth pit in RCC/PCC covered area (6-
8 Inch thick) including making good and restoring to original
as per drawings in detail specs and other specs as per
IS:3043 - 1966, including supply of GI pipe 100 mm dia,
3.8 mtr. long, charcoal, salt etc. to make a complete
earthing system.
No. NO 20
104dModification of existing small sized earthing pits as per
IS:3043-1966 ID 600mm , depth 400mm, and width 125mmNo. No 1
105 Testing and Maintenance of earth pit as per detail scope No. 1029
106
Painting of junction boxes/DB/ Tel.boxes etc.(Paint must
be ISI Marked as appd.by Engr. -in-Charge and to be
supplied by the contractor.( 1 coat of primer & 2 coat of
paint will be done).
Sqmr NO 1
107 Painting of motors with epoxy paint. NO
a size 0 - 22 kW No. NO 1
b size 23 - 160 kW No. NO 1
c size 161 kW and above No. 1
108a
Laying, fixing & termination of 6/8 SWG G.I. wire / Al. strip
(NFL's scope)of any size in existing RCC walls/tray or any
other structures, etc. incl. Supply of hardware like clamps,
bolts etc.and related civil & welding jobs (Contractor's scope)
Mtr NO 20
108b do underground Mtr NO 20
109Wiring for light point with 1.5 sq.mm.PVC insulated Cu
conductor cable.NO
a Short point No. NO 300
b Medium point No. 134
c Long point No. NO 219
d Extra long point No. NO 100
110Wiring for fan point with 1.5 sq.mm PVC insulated, Cu
conductor cable.
a Short point No. NO 27
b Medium point No. NO 77
c Long point No. NO 70
d Extra long point No. 1
111Wiring for call bell point with 1.5 sq.mm. PVC insulated, Cu
conductor cable.(Buzzers in contractor"s scope)NO
a Medium point No. NO 40
b Long point No. NO 21
112Wiring for 3 pin 5 Amps. plug point with 1.5 sq.mm PVC
insulated, Cu conductor cable.
a Short point No. NO 152
b Medium point No. NO 27
c Long point No. 117
113Wiring for 3/5 pin,15 Amp. power plug with 4 /2.5 sq.mm
PVC insulated, Cu conductor cable.NO
a Short point No. NO 30
b Medium point No. NO 36
c Long point No. NO 122
114Wiring for main/ sub-main with PVC insulated, Cu conductor
cable.NO
a With 2x2.5 sq mm cable. Mtr NA 1664
b With 2x4 sq mm cable. Mtr NA 538
115 Renovation of O/H, street light fixtures / aviation lights NA
a 2x20 / 2x40 /2x65 /4x20 /4x40 Watt tube light fixtures No. NA 5920
b 200 W bulk head fittings No. yes 1313
c200 Watt Well glass fittings, all wattage of HPMV/HPSV
lamps fittings.No. NO 998
d Aviation light on the prilling tower/boiler chimney /flare stack. No. 42
116Shfting of ladders from plant to plant, within plant or within
t/shipNo. 757
117 Holding of ladders of size up to 30'. Hrs 490
118Erection and dismantling of scaffolding. Size: 30 sq ft area
and upto 30 ft height. Including to and fro transportation from
site to store.
No. 1
119
Replacement of Tower light fitting. Connection/
disconnection of cables, tightening of connections, etc. as
required. Any civil jobs or welding jobs reqd shall be in the
scope of the contractor.
No. 1
120Rectification of fault in Tower light fitting, tightening of
connections, replacement of all or any of the components
like lamp, choke, capacitor, ignitor etc. as required
No. yes 163
121
Maintenance of flame proof light fitting which includes
opening the light fixtures, replacement /cleaning of glass
covers if necessary, replacement of switches, re-laying of
cables, replacement of junction boxes, replacement of
cable gland lamp holder, choke and terminal block wherever
required up to 30 ft height in plant area.
No. 350
122
Rectification in of O/H, street Light fixture, aviation light
including replacement of rod/lamp, starter, lamp holder,
supporting structure wherever reqd. in plant/township, as
desired by Engr. in charge. (welding jobs will be in the scope
of the contractor)
No.
a 2x40/2x65 Watt tube light fixture No. 1783
b 200 Watt Wall glass fittings No. 902
c 500/1000 W Flood Light Fitting No. yes 871
d Of all wattage of Mercury/Sodium vapour lamps fittings. No. NO 3222
e Aviation light on the prilling tower/boiler chimney /flare stack. No. NO 40
123Installation of cable trays as reqd. by Engr-in-Charge
including welding/ cutting /civil works.Mtr Yes
a Cable tray upto 300 mm Mtr NO 240
b Cable tray from 301 to 700 mm Mtr 123
c do but from 701 to 1500 mm Mtr 20
dReplacement of cable tray of size upto 1000mm incl.
handling of cable on it. Mtr NO 20
124Installation of push button station. Welding of supprt
structure and civil jobs will be in the scope of the contractor.No. yes 1
125Maint. of light junction box single or 3 phase, grouting on
wall, welding of structure etc if reqd.No. 845
126Erection of panels. Size limited to 2.4 mtr(ht), 1.2 mtr (depth)
and 1000Kg (Wt). Shfting from stores to site, civil jobs and
cutting/ welding jobs in the scope of contractor.
No. 1
127Fabrication and erection of steel structures . Cutting / welding
and all other related jobs in the scope of the contractor
including provision of welding/ cuting sets.
MT 1
128Casting and machining of machine parts like motor end
cover, foot, fan etc. as per sample.Kg
a Cast Iron Kg 100
b Cast Aluminium Kg NO 1
129Erection, testing, commissioning and earthing of light fixture
of any size(supply NFL's scope) on existing pole incl. supply
of GI pipe and bracket(Contractor's scope)
No. NA 1
130
Erection, testing, commissioning and earthing of following
type of Lighting fixtures incl.control gear, regulator etc. (petty
materials as reqd. will be supplied by the contractor) Related
welding and civil jobs will be in the scope of the contractor.
No.
a F/L 2x40 W or 100 Watt bulk head light fitting. No. 125
b Well glass fitting upto 200W of any type No. 31
c Light fittings of any type upto 2x400 Watt No. 119
d Ceiling fan/Ex. fan of any size. No. 1
e Flameproof light fitting 125W. No. 1
fSupply and installation of protective guard (wire mesh) for
light fittings up to 400W of any type.No. 1
131Transportation of materials from plant to plant, within plant,
plant to workshop, stores to plant/workshop, workshop to
t/ship or within t/ship.
No. NA
a Below 20 Kg No. 1767
b Above 20 Kg up to 50 Kg No. 1562
c Above 50 Kg but below 100 Kg No. 1022
d LT motors upto 3.7 KW No. 524
e do above 3.7 KW to 15 KW No. NO 311
f Shifting of 200 Ltrs. oil drums No. yes 93
g Shifting of Grease gun bucket No. NA 838
132Pulling of cable over the cable tray in trench or pipe to bring
out margin at the end for its re-termination.No. yes
aPulling up to length of 50 mtr for cable sizes upto 3/3.5x70
sq.mm.No. NA 182
b --do-- but 150 mtr size -do- No. NA 85
cPulling upto length of 50 mtr of cable size upto 3/3.5x95 to
3/3.5x185 sq mm. No. NA 52
d -do- but 150 mtr size -do- NO 69
133
Cleaning of s/stn blower filter in 3.3KV, 11KV, 415V and
PCC rooms including removal of filters, steam washing and
refixing at site. Steam at suitable place will be provided by
NFL.
Manday NO 228
134
Cleaning of battery bank. Topping up with distilled water and
application of petroleum jelly on battery terminals and taking
readings of cell volatge and sp gravity and recording the
same.
Manday NO 349
135 Cleaning of Capacitor banksas per site requirement . Manday NO 251
136Cleaning of panels in substationsas per site
requirementManday NA 1484
137 Cleaning of transformers in s/stns as per site requirement. Manday NO 629
138Cleaning of cable tray of all sizes with water spray and
wire brush etc as per site requirement. Manday 877
139Cleaning of cable trench from including cleaning of cables
with water spray and removing mud from trench and
dewatering of trench etc as per site requirement.
Manday 461
140Cleaning of LT motors of all sizes in plant as per plant
requirement.Manday 946
141Cleaning of duct of pressurisation blower in Sub station as
per site requirement.Manday NA 205
142Cleaning of HT motors of all sizes in plantas per plant
requirement. Manday yes 426
143Cleaning, rinsing shifting of transformer oil drums, pipe
connections with oil filter machine, sampling etc as per site
requirement.
Manday yes 6
144Cutting and cleaning of burnt winding of motors in elect
workshop.Manday NA 278
144 aCleaning of smoke detectors ,pill boxes and panels of Fire
Alarm systemManday 150
145Transportation of sophisticated electronic / electrical testing
equipments from lab to plant and vice-versa. Manday
a Upto 50 Kg. Manday 224
b From 51 Kg to 100 Kg Manday 146
c Above 100 Kg. Manday 63
146Connection or disconnection of welding sets / jet cleaner or
other temporary equipments in plant.Manday 63
147Lubrication of HT/LT motors including all related job like
shifting of tools and tackles.Manday 144
148Making of motor coil sets in electrical workshop as per
instructions of engr-in-charge.Manday 143
149Assistance in execution of intermittent electrical jobs during
short shutdowns / onforeseen breakdowns / Annual turn
around etc.
a1 Unskilled labourer (Normal working time- 8 hrs per day) No. No 1344
a2 Unskilled labourer (oevr time after 8hrs normal duty) Hr No 3584
b1 Welder (Normal working time- 8 hrs per day) No. No 1
b2 Welder (oevr time after 8hrs normal duty) Hr No 1
c1 Rigger (Normal working time- 8 hrs per day) No. No 1
c2 Rigger (oevr time after 8hrs normal duty) Hr 1
d1 Skilled Electrician (Normal working time- 8 hrs per day) No. 276
d2 Skilled Electrician (oevr time after 8hrs normal duty) Hr 739
e Skilled supervisor No. 1
150a
Earthwork in excavation not exceeding 1.5 Mtr in width or 10
sq mts on plan including dressing of sides and ramming of
bottom lift upto 1.5 Mtr including getting out the excavated
soil and disposal of surplus soil as directed.
Cu Mtr 1
150b
Filling available excavated earth in trenches, plinth, sides of
foundation etc in layers not exceeding 20 cm in depth.
Consolidating each deposited layer upto 50 Mtr and lift upto
1.5 Mtr.
Cu Mtr 1
150c
Cutting Bituminous portion of Road and making good the
same including supply of extra quantities of materials
I.e.aggregate, Moorum screening, red bajri etc and labour
rquired.
Cu Mtr 1
150dDemolishing cement concrete incl disposal of material within
50 Mtr lead.Cu Mtr 1
150eProviding and laying in position cement concrete of specified
grade incl the cost of centring & shuttering - All work upto
plinth level.
Cu Mtr 1
152 a 2 Suitable for 3 core cable (PILCA) size 95 to 185 mm2 1
152 b1 Suitable for 3 core cable (XLPE) size 240 to 300 mm2 No. 1
152 b2 Suitable for 3 core cable (PILCA) size 240 to 300 mm2 No. 1
152c Siutable for cable (XLPE) size 1 X 400 mm2 No. 1
153
Supply of End jointing Suitable for 11Kv (UE) system with
heat shrinkable kits of Raychem make for XLPE/PILCA
cable. Jointer shall be trained and hold valid certificate
from Raychem. Supply of joint as well as all other materials
in the scope of the contractor
No.
153 a1 Suitable for 3 core cable (XLPE) size 95 to 185 mm2 No. 1
153 a2 Suitable for 3 core cable (PILCA) size 95 to 185 mm2 1
153 b1 Suitable for 3 core cable (XLPE)size 240 to 400 mm2 No. 1
153 b2 Suitable for 3 core cable (PILCA) size 240 to 400 mm2 1
153c Suitable for cable size 1 X 400 mm2 No. 1
154
Supply of Straight through jointing Suitable for 3.3Kv (UE)
system with heat shrinkable kits of Raychem make for
XLPE/PVC cable. Jointer shall be trained and hold valid
certificate from Raychem. Supply of joint as well as all other
materials in the scope of the contractor
No.
154a Suitable for 3 core cable size 95 to 150 mm2 No. 1
154b Suitable for 3 core cable size 185 to 400 mm2 No. 1
155
Supply of End jointing Suitable for 3.3Kv (UE) system with
heat shrinkable kits of Raychem make for XLPE/PVC cable.
Jointer shall be trained and hold valid certificate from
Raychem. Supply of joint as well as all other materials in the
No.
155a Suitable for 3 core cable size from 120 to 240mm2 No. 1
155b Suitable for 3 core cable size from 300 to 400mm2 No. 1
156a
Dressing of already laid LT cable upto size of 11 pair in
PVC pipes/ Cassing -capping.( All material Like PVC
pipe,Cassing-capping ,Saddle, surews, plastic gitti etc.
in the scope of contractor.
Mtr. 0 500
156b
Dressing of already laid Telephone cable upto size of
16mm square in PVC pipes/ Cassing -capping.( All
material Like PVC pipe,Cassing-capping ,Saddle,
surews, plastic gitti etc. in the scope of contractor
Mtr. 0 500
157Replacement of LT Motors of following rating as per
details as in scope of workNo.
157a Motors rating up to 1.1Kw No. 0 5
157b Motors rating above 1.1kw up to 3.7 Kw No. 0 10
157c Motors rating above 3.7kw up to 11 Kw No. 0 5
157d Motors rating above 11kw up to 37 Kw No. 0 5
157e Motors rating above 37kw up to 75 Kw No. 0 5
157f Motors rating above 75kw up to 125 Kw No. 0 5
157g Motors rating above 125kw up to 160 Kw No. 0 5
158Re-aalingment of LT Motors of following rating as per
details as in scope of workNo.
158a Motors rating up to 1.1Kw No. 0 5
158b Motors rating above 1.1kw up to 3.7 Kw No. 0 10
158c Motors rating above 3.7kw up to 11 Kw No. 0 5
158d Motors rating above 11kw up to 37 Kw No. 0 5
158e Motors rating above 37kw up to 75 Kw No. 0 5
158f Motors rating above 75kw up to 125 Kw No. 0 5
158g Motors rating above 125kw up to 160 Kw No. 0 5
159 Trimming / Pruning of tree branches Span 0 150
Grand Total
Overall Discount in %
Note - 1. Parties are required to quote item wise workable rates, however evaluation of bid shall be done on
2.Tendrer may quote overall percentage of discount which shall be applicable on all the Items.
SOR
AmountRate
(InWords.)
Grand Total
Overall Discount in %
Note - 1. Parties are required to quote item wise workable rates, however evaluation of bid shall be done on
2.Tendrer may quote overall percentage of discount which shall be applicable on all the Items.