  • MW Standard Operation Procedure for Axis SwapAMBER Project

    HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential

  • Version Prepared by Reviewed by Approved by Revision Record

    V1.0 Zhou Shengwei Chew Weng Soon Initial release

    Related international specifications or document consistency:

    Specifications or documents that are replaced or expire:

    Correlation of specifications and documents:

    MW Standard Operation Procedure for Axis Swap Project

    Revision Declaration

    Specifications or documents related to this document:

    This document is prepared and explained by the Site Business Dept of Global Technical Service Dept.

    Issue Date: 2011-09-05 Effective Date: 2011-09-05

    Page 2

    Huawei Confidential

    Copyright Huawei Technologies Co., Ltd. All rights reserved.

    Issue Date: 2011-09-05 Effective Date: 2011-09-05

    Page 2

  • The IDU of OptiX RTN is installed on the Huawei rack

    The distance of 2 sites between this link is 4.3km

    Protection:1+1 HSB

    Typical Installation Scenarios for OptiX RTN

    The DDF/DCDB/Rack/Mounting Pole are installed on site

    The height of tower is about 50m .

    The configuration of 2 sites between this link is same

    IDU DC Power

    Rack GND

    Antenna

    Pole

    ODU and Coupler

    Page 3

    DDF

    DCDBACDB

    Battary

    DC power cabinet

    IDU DC Power

    PGND

    IDU

    Ground barIF cable

    Page 3

  • 40 10

    Operator ADOperator AD Operator AD

    1.3.3

    Operator D Operator D

    1.5.2 1.6.2

    10:30 10:40 10:40 10:50

    Operator AD Operator AD

    10:00 10:10 10:10 10:30

    11:15 11:40

    11:35

    1.7

    Check Materials Assemble Antenna Install coupler Install ODU Install Rack Install DCDB Install IDU and DDF

    11:4510:50 11:15 11:15 11:35

    1.1.2 1.2.2 1.3.2 1.4

    MW Standard Operation Procedure for Axis Swap Project

    1.1.1 1.2.1 1.3.1 1.5.1

    Lift & install poleLift & install Antenna

    and Grond ODU

    1.6.1

    Preparation Assemble Pole Per-work on tower

    (AD)BC

    10:50 11:1510:00 10:10 10:10 10:25 10:25 10:50

    Operator (AD)BCOperatorBC Operator BCOperator BC Operator

    Start

    Page 4

    40 10

    1.16

    Operator BDOperator (A)BC Operator B

    Install Microwave

    at site B

    11:55 12:45 13:10 16:2012:55 13:10

    1.14

    When BE finish

    installation at site B

    then go to site A for

    aligning antenna

    Grounding and

    waterproof of IF

    cable

    1.11 1.121.9.2 1.13

    Power on

    equipment

    Single site

    configuration

    12:45 12:55

    1.15.1

    Check installation and

    take photograph

    17:50 18:00

    16:20 17:50

    1.8.1 1.9.1 1.14

    11:40 11:55 11:55 12:30

    Lift & Route IF

    cable

    Waterproof ODU&

    Bind IF cable

    Align Antenna at site

    A

    Operator A

    1.3.3Assemble IF

    terminal (outdoor)

    10:30 11:45

    A, B, C and D from the site implementation team will finish the new site within Eight hours.

    Don't consider the distance between two sites

    1.16

    Swap MW Link

    1:00 1:10

    Operator A

    Operator DOperator D Operator D

    Operator A AOperatorOperator AC

    12:20 12:3012:10 12:2011:45 12:10

    1.9.4

    Install power cable

    1.8.3Route IF

    cable(indoor)

    1.10

    Clear Sites

    Operator ABCDOperator BD Operator C Operator A

    Operator A

    Operator A

    11:45 12:10

    Install E1/LANcable

    and Patching

    1.8.2

    11:55 12:45 13:10 16:2012:55 13:10aligning antenna

    18:00

    1.15.2

    Perform test/ATP

    17:50

    12:45 12:55

    12:10

    1.141.9.3

    12:45

    Align Antenna at site

    B

    16:20 17:50

    Make cable labels

    Operator BDC17:50 18:00

    End

    Don't consider the distance between two sites

    AB are experienced on MW installation5

    Page 4

  • MW Standard Operation Procedure for Axis Swap Project

    Flathead screwdriver Cross screwdriver Diagonal pliers

    Adjustable wrench Punchdown tool Crimping pliers

    Paper knife Antistatic gloves Marking pen

    File Wire cutter Solid wrench

    ScissorsSafty helmet Camera Claw hammer Crimping

    Telescope Safety harnessPercussion drill Cleaner Torque wrench Socket wrench

    Compass Lifting hook Lifting ropeAllen wrench Ladder Multimeter

    Page 5

  • Type-N Connector Lightning ArresterCoaxial Cable External Power Cable Protection Ground Cable IF Jumper Cable

    Orderwire Phone Crossover Network CableHybrid coupler Naked crimping terminal IF Cable Label Power Cable Label

    ODU

    Installation Materials

    IDU subrack SL61EMS6 SL61SU2 SL61PXC SL61PH1A

    Page 6

    OT terminal AntennaSignal Cable Label Waterproof tape Cable tie Alarm cable

    LAN cable Panel NutsGrounding Clip PVC tape 16mm Grounding Cable Captive nuts

    Page 6

  • 23

    4

    5

    1

    2

    3

    Site Pack Documents:

    1. Work Permit

    2. AMBER 110614001-Q -F003-TSSR (Approved)

    3. AMBER 110614001-Q -F002-Site Design

    4. Equipment Delivery Note (DN)

    5. AMBER110614001-Q-F074-Site Damage Condition Report

    6. AMBER110614001-Q-F075-Site Diary

    7. AMBER110614001-H-F001-Toolbox Talk Report

    8. AMBER110614001-H-F008-Job Safety Analysis

    9. AMBER110614001-Q-F100-MS Site Handover Checklist

    10. AMBER110614001-Q-F101-ATP Microwave

    11. AMBER110614001-Q-F102-Swap Leader Checklist

    12. AMBER110614001-Q-F103-Site Quality Audit Checklist

    Site Pack Reference Documents:

    13. AMBER110614001-Q-P050-MOP for Swap BTS and MW

    14. AMBER110614002-Q-G011-Quick Installation Guide-RTN950 ODU

    15. AMBER110614002-Q-G009-Quick Installation Guide-RTN950 IDU

    16. AMBER110614001-Q-P007-SOP for Microwave Swap

    HSE Manager/Officer Documents:

    1. AMBER110614001-H-F002-Contractor HSE Management System Checklist

    Procedure - Site Pack Documents and Site Access

    1Implement and maintain effective risk management procedures and strategies to

    ensure all required safety procedures are adhered to.

    Site access/Login procedures should be followed on entering a facility.

    Refer Access Procedure Draft v1.

    The Site Pack must be available and all forms filled in on entering the site and

    updated on departure to reflect any work done on site.

    Upon arrival at site, promptly conduct a site inspection for any damage/vandalism. In

    the case of any damage or vandalism, please contact the NOC and local field

    operations (MS) team. Record it in the AMBER110614001-Q-F074-Site Condition

    Damage Report V1.0.

    Refer to AMBER110614001-Q-F103-Site Quality Audit Checklist for pending tasks.

    Note

    If site condition is different from the site survey report, contact Huawei interface for

    further action.

    Take Site condition photos to report any issues upon arrival at site. Refer to Procedure

    no. 4.

    Make sure that the building site access, work permit and application to work has been

    approved.

    MW Standard Operation Procedure for Axis Swap Project SN Task Description Operator Duration

    1.1.1 A Preparation BC 10 minutes

    1.1.1 PreparationHuawei Confidential

    Copyright Huawei Technologies Co., Ltd. All rights reserved. Page 7

    3

    4

    1 2 3

    4 5 6

    1 2

    3 4

    5 6

    Materials

    HSE Manager/Officer Documents:

    1. AMBER110614001-H-F002-Contractor HSE Management System Checklist

    2. AMBER110614001-H-F003-Contractor HSE Communication Log

    3. AMBER110614001-H-F004-Contractor HSE Program

    4. AMBER110614001-H-F005-Contractor HSE Inspection Checklist

    5. AMBER110614001-H-F006-Accident and Incident Report

    approved.

    Make sure all Site Pack documents and PPE is avaliable and practised.

    Tools

    Camera Marker pen

    Axis Work Permit Building Site Access Approval

    Site Keys

    Measuring tape

    Level Bar

    1.1.1 PreparationHuawei Confidential

    Copyright Huawei Technologies Co., Ltd. All rights reserved. Page 7

  • 23

    4

    1

    2

    3

    4

    1 2 3

    Additional Site Installation Materials:

    Indoor

    19" Rack wall support L-bracket 2 PCS

    Coach Screw sized (M12mm x 40-50mm) 4PCS

    Outdoor

    Anaconda 1 inch with metal protector 10m

    Black Cable Ties 6 Inch 2 Packs

    Black cable ties L300 x 4.8mm 2 Packs

    "Waterproof adhesive Rubber tape (Brand 3M, or Polymoth)" 6 PCS

    Isolation tape black (Brand 3M) 4 PCS

    ABPDB inlet (1 inch) 1 PCS

    Procedure - Additional Installation Materials

    1

    Install the outdoor site lightings. Carefully read all the installation manual of the

    equipment & make sure the installation of all the equipment according to the design

    specified in TSSR.

    Check the installation position of BTS Rack according to design floor plan. Verify

    location and measurements.

    Verify TSSR and site solution including site ID, site name, site configuration, power,

    transmission and RF Feeder & Antenna system, etc.

    Take pictures of the site.

    Note

    If site condition is different from the site survey report, contact Huawei interface for

    further action.

    Any thing not according to plan or design or any such issues that includes unplanned

    Live network interruption should be notified straight away to Huawei interface.

    Ensure that the site lightings are sufficient to conduct the work safely.

    Tools

    Camera Marker pen Measuring tape

    MW Standard Operation Procedure for Axis Swap Project SN Task Description Operator Duration

    1.1.1 B Preparation BC 10 minutes

    1.1.1 PreparationHuawei Confidential

    Copyright Huawei Technologies Co., Ltd. All rights reserved. Page 8

    1 2 3

    4 5 6

    1 2

    3 4

    5 6

    AMBER110614001-Q-P050-

    MOP for Swap BTS and MWTechnical Site Survey Report (TSSR)

    Camera Marker pen Measuring tape

    AMBER110614002-Q-G009-

    Quick Installation Guide-

    RTN950 IDU

    AMBER110614002-Q-G011-Quick Installation

    Guide-RTN950 ODU

    Level Bar

    Materials

    Coach Screw

    Wall mounted bracket

    1.1.1 PreparationHuawei Confidential

    Copyright Huawei Technologies Co., Ltd. All rights reserved. Page 8

  • 13

    4

    5

    6

    1

    2

    1 2 3

    MW Standard Operation Procedure for Axis Swap Project SN Task Description Operator Duration

    1.1.1 C Preparation BC 10 minutes

    Move unpacked equipment and packing materials and keep them indoors.

    Procedure

    Check the design documents ;

    2

    A. Antenna installation manual(In packed box) ;

    B. OptiX RTN radio transmisssion system-IDU&ODU quick installation guide ;

    Make the labels according to the templates provided by Huawei ;

    Check installation condition(place of antenna\cable\IDU, power,cable rack,earth

    bar,hole,indoor entironment ;

    Tools (see tools card in this guide) .

    Note

    Do not handle the uncoated metal surface of parts and components with sweat-

    soaked or dirty gloves.

    Tools

    Paper knife

    2-

    Design document

    2-1

    2-

    3 4

    4 5 6

    1 2

    3 4

    5 6

    Materials

    AMBER110614002-Q-G009-

    Quick Installation Guide-

    RTN950 IDU

    AMBER110614002-Q-G011-Quick Installation

    Guide-RTN950 ODU

    Label

    1.1.1 PreparationHuawei Confidential

    Copyright Huawei Technologies Co., Ltd. All rights reserved. Page 9

  • 12

    3

    4

    5

    1

    2

    3

    4

    MW Standard Operation Procedure for Axis Swap Project SN Task Description Operator Duration

    1.1.2A Check Materials AD 5 minutes

    Tools

    Procedure

    Check the total number of materials in the packing case according to the attached

    Site Packing list and Delivery Note (DN).

    Check whether the cases have the same number and types of items as are

    mentioned in the packing list.

    Sign off the proof of delivery and DN. Submit the copy of the DN with Site Pack to

    Huawei.Additional installation materials is sufficient and brought to site. Refer to attached

    photos.

    Keep the rectifier cabinet pallet base for the temporary installation of the cabinets.

    Note

    Ensure that the parts and components do not collide with objects like doors, walls, or

    trolleys during transportation, moving, or installation.

    Do not touch the uncoated metal surface of any of the equipment parts and

    components with sweat-soaked or dirty gloves.

    Unpacked equipments and packing materials should be kept indoors.

    If found any discrepencies inform Huawei Site Engineer.

    MR

    DDF

    IF board

    Tributary

    IDU

    Material for Indoor Installation

    1.1.2 Check MaterialsHuawei Confidential

    Copyright Huawei Technologies Co., Ltd. All rights reserved. Page 10

    1 2 3

    4 5 6

    1 2

    3 4

    5 6

    Tools

    Paper knife Flat-head screwdriver Hammer

    Camera

    Materials

    Delivery Note

    IF board

    Tributary

    IDU

    Power Ground IDU accessory

    packetE1

    1.1.2 Check MaterialsHuawei Confidential

    Copyright Huawei Technologies Co., Ltd. All rights reserved. Page 10

  • 12

    3

    4

    5

    1

    2

    3

    4

    MW Standard Operation Procedure for Axis Swap Project SN Task Description Operator

    Check whether the diameter and frequency band of the antenna, the frequency band

    of the ODU are consistent with the design document.

    Duration

    1.1.2B Check Materials AD 5 minutes

    Note

    Ensure that the parts and components do not collide with objects like doors, walls, or

    trolleys during transportation, moving, or installation.

    Procedure

    Check whether the goods, including the antenna, ODU, ODU accessory box, and IF

    cable, are consistent with the MR;

    Do not touch the uncoated metal surface of parts and components with sweat-soaked

    or dirty gloves.

    Move unpacked equipment and packing materials and keep them indoors.

    If found any discrepencies inform huawei engineer

    ODU accessory case

    IF cable

    ODU

    Antenna

    Check the frequency band of the ODU

    Goods for Outdoor Installation

    1.1.2 Check MaterialsHuawei Confidential

    Copyright Huawei Technologies Co., Ltd. All rights reserved. Page 11

    1 2 3

    3 5 6

    1 2

    3 4

    5 6

    Delivery Note

    Camera

    Materials

    Tools

    Paper knife Flat-head screwdriver Hammer

    Check the diameter and frequency band of the antenna

    1.1.2 Check MaterialsHuawei Confidential

    Copyright Huawei Technologies Co., Ltd. All rights reserved. Page 11

  • 12

    3

    4

    5

    1

    2

    3

    4

    1 2 3Wrench Solid wrench Adjustable wrench

    Tools

    Note

    Make sure that all bolts and nuts of the pole are tight and secure.

    Install the first U-bolts of T-bracket at one end of pole and fasten it ;

    Install the second U-bolts of T-bracket at the other both end of pole and fasten it.

    Duration

    1.2.1 Assemble Pole BC 15 minutesMW Standard Operation Procedure for Axis Swap Project

    SN Task Description Operator

    Procedure

    2-

    1- 1-

    1-

    2- 2-

    1.2.1 Assemble PoleHuawei Confidential

    Copyright Huawei Technologies Co., Ltd. All rights reserved. Page 12

    1 2 3

    4 5 6

    1 2

    3 4

    5 6

    Materials

    Microwave pole

    Wrench Solid wrench Adjustable wrench2- 2-

    1.2.1 Assemble PoleHuawei Confidential

    Copyright Huawei Technologies Co., Ltd. All rights reserved. Page 12

  • 12

    3

    4

    5

    1

    2

    3

    4

    1 2 3

    Procedure

    Insert the flathead screwdriver into the the hole of the tongue on the cover of the

    wooden case, and then straighten the tongue ;

    Remove the cover after all tongues on the cover are straightened;

    Take out the antenna and the accessories.

    MW Standard Operation Procedure for Axis Swap Project SN Task Description Operator Duration

    1.2.2AAssemble Antenna-

    unpacking the equipmentAD 5 minutes

    Note

    Tools

    Flathead screwdriver Adjustable wrench

    1-1-A

    1-C 2-

    3-A 3-

    1.2.2 Assemble AntennaHuawei Confidential

    Copyright Huawei Technologies Co., Ltd. All rights reserved. Page 13

    4 5 6

    1 2

    3 4

    5 6

    Materials

    Antenna

    3-A 3-

    1.2.2 Assemble AntennaHuawei Confidential

    Copyright Huawei Technologies Co., Ltd. All rights reserved. Page 13

  • 12

    3

    4

    5

    6

    7

    8

    9

    Install the retaining bolts and clamps of the antenna on the stand base.

    Procedure

    Determine where to install the antenna according to the azimuth and the design

    height of the antenna, then remove bolt A on the antenna, and loosen bolt B ;

    Loosen the bolt on the stand of the antenna;

    Adjust the elevation adjustment bolt on the stand to the middle position;

    Fasten the hanging bracket to bolt B. Pass bolt A through the stand and insert bolt A

    in the installation hole on the antenna. Then, tighten the two bolts ;

    Remove the bolts on the level adjustment screw, and then install the level adjustment

    screw on the stand;

    Note

    Engineers should select a proper installation manner for left installation or right

    Remove the nuts of the level adjustment screw, and then fix the stand base to the

    level adjustment screw;

    Apply anti-seize grease to the level adjustment screw and the retaining bolts of the

    antenna;

    Duration

    1.2.2B Assemble the Antenna AD 10 minutesMW Standard Operation Procedure for Axis Swap Project

    SN Task Description Operator

    Bolt ABolt B

    Bolt ABolt B

    1 2 3

    4- 4-B 5-

    6-5-C5-

    6-B

    7-A 7-B

    1.2.2 Assemble AntennaHuawei Confidential

    Copyright Huawei Technologies Co., Ltd. All rights reserved. Page 14

    1

    2

    1 2 3

    4 5 6

    1 2

    3 4

    Materials

    Antenna Hanging bracket

    Anti-seize grease

    Allen wrench Solid wrench

    Tools

    Engineers should select a proper installation manner for left installation or right

    installation based on antenna receiving direction, mounting pipe and relevant position

    of surrounding object.

    6-B

    7-A 7-B

    8- 8-8-B

    1.2.2 Assemble AntennaHuawei Confidential

    Copyright Huawei Technologies Co., Ltd. All rights reserved. Page 14

  • 12

    3

    4

    5

    6

    1

    2

    3

    4

    MW Standard Operation Procedure for Axis Swap Project SN Task Description Operator Duration

    1.2.2CModify the Antenna

    Polarization ModeAD 5 minutes

    Note

    Vaseline can't be lay on the surface or inner part of the feeder.

    Procedure

    The default polarization mode of the antenna is the vertical polarization. If the radio

    link is designed with the horizontal polarization, the polarization mode needs to be

    modified as follows.

    Loosen the four bolts that fix the feed boom ;

    Rotate the feed boom 90 degrees smoothly, and point the polarization indicator to the

    letter H . In this manner, the antenna is in the horizontal polarization mode;

    Tighten the four bolts that fix the feed boom.

    90909090 H Horizontal

    V Vertical

    1-

    1- 2

    3- 3-

    1.2.2 Assemble AntennaHuawei Confidential

    Copyright Huawei Technologies Co., Ltd. All rights reserved. Page 15

    4

    1 2 3

    4 5 6

    1 2

    3 4

    5 6

    Materials

    Antenna

    Tools

    Cross screwdriver Adjustable wrench

    90909090 H Horizontal

    4- 4-

    1.2.2 Assemble AntennaHuawei Confidential

    Copyright Huawei Technologies Co., Ltd. All rights reserved. Page 15

  • 12

    3

    4

    5

    1

    2

    Note

    Must carefully check the pretended antenna installation place on tower as

    suggested in TSSR.

    Tools

    Before you lift and install the antenna, determine the height and azimuth of

    the antenna according to the design document by compass;

    The operators should carry the following materials and tools on the tower: the

    pulley, lifting rope, anti-fall clamp, ground cable of the IF cable, PVC tape,

    waterproof tape, bundling tape, wrench, socket-head wrench, diagonal pliers,

    flathead screwdriver, and paper knife;

    Fix the pulley on tower above the antenna which will be mounted,thread

    hanging rope through the pulley to ground.

    MW Standard Operation Procedure for Axis Swap Project

    SN. Task Description Operator

    Procedure

    Duration

    1.3.1 Pre-work on tower BC 25 minutes

    3

    1-A

    21-

    1.3.1 Per-work on the towerHuawei Confidential

    Copyright Huawei Technologies Co., Ltd. All rights reserved. Page 16

    1 2 3

    4 5 6

    1 2

    3 4

    Tools

    Safety belt Tools bag

    Compass Hanging rope Pulley

    Materials

    Design document

    321-

    1.3.1 Per-work on the towerHuawei Confidential

    Copyright Huawei Technologies Co., Ltd. All rights reserved. Page 16

  • 12

    3

    4

    5

    6

    1

    2

    3

    Coupler polarization should be same as the design document.

    Tools

    Note

    MW Standard Operation Procedure for Axis Swap Project SN Task Description Operator

    Procedure

    Remove the dust protection cover, by default the polarization of the coupler is

    vertical, the arrow is pointing to "V";

    Check the polarization from document, the default polarization mode of the antenna

    is the vertical polarization then go to SN 1.3.2C . If the radio link is designed with the

    horizontal polarization, the polarization mode needs to be modified SN1.3.2B .

    Duration

    1.3.2A Install coupler D 2 minutes

    1- 1-

    2-

    1 2 3

    4 5 6

    1 2

    3 4

    5 6

    Material

    Coupler

    Adjustable wrench Cross screwdriver

    Tools

    2-

    1.3.2 Install coupler(1+1)Huawei Confidential

    Copyright Huawei Technologies Co., Ltd. All rights reserved. Page 17

  • 12

    3

    4

    5

    6

    1

    2

    3

    Note

    The waveguide direction of horizontal polarizer must be the same as the polarization part.

    Replace the vertical polarization converter with the horizontal polarizer and connect to

    the polarization part;

    Confirm the interface of the polarization part is the same as coupler, then insert the

    polarization part into the antenna interface of the coupler;

    Confirm the arrow on the polarization part points to "H",and fix the two screws on the

    polarization part by hex key wrench.

    5 minutes

    Procedure

    Loosen the screws by hex key wrench and remove the polarization part;

    Remove the vertical polarization converter from the polarization part;

    MW Standard Operation Procedure for Axis Swap Project SN Task Description Operator Duration

    1.3.2BModify the polarization of

    couplerD

    1- 1- 2-

    2- 3- 3-

    4- 4- 5

    1.3.2 Install coupler(1+1)Huawei Confidential

    Copyright Huawei Technologies Co., Ltd. All rights reserved. Page 18

    1 2 3

    4 5 6

    1 2

    3 4

    5 6

    Material

    Allen wrench

    Coupler

    Tools

    4- 4- 5

    H - HorizontalH - Horizontal

    1.3.2 Install coupler(1+1)Huawei Confidential

    Copyright Huawei Technologies Co., Ltd. All rights reserved. Page 18

  • 12

    3

    4

    5

    6

    7

    1

    2

    3

    4

    Storage polarization component well.

    Procedure

    Remove the two lifting rings of the antenna;

    Close the four latches cornerwise and tighten the four screws on the coupler;, fasten

    4 bolts with inner hexagonal tool;

    Note

    Coupler's polarization should be as the feeder's polarization.

    Vaseline can't be lay on the surface or inner part of the feeder.

    Install the removed lifting rings on the antenna .

    Remove the protective cap of the feed boom, and then apply an appropriate ainstallof

    vaseline to the gasket of the feed boom;

    Remove the protective cap of the feed boom of coupler;

    Apply anti-seize grease to the retaining bolts of the coupler;

    Confirm that the coupler is consistent with the antenna in the polarization mode;

    MW Standard Operation Procedure for Axis Swap Project SN Task Description Operator Duration

    1.3.2C Install coupler D 3 minutes

    1 2- 2-

    5 6- 6-

    2- 3 4

    1.3.2 Install coupler(1+1)Huawei Confidential

    Copyright Huawei Technologies Co., Ltd. All rights reserved. Page 19

    4

    1 2 3

    4 5 6

    1 2

    3 4

    5 6

    Coupler Antenna

    Vaseline

    Material

    Tools

    7 7

    1.3.2 Install coupler(1+1)Huawei Confidential

    Copyright Huawei Technologies Co., Ltd. All rights reserved. Page 19

  • 12

    3

    4

    5

    6

    7

    1

    2

    Note

    Reserve the shielding layer of 4 mm and cut off the redundant part ;

    Strip the insulating layer off, and obtain the inner conductor of 4.5 mm. Then, file the

    head of inner conductor to the arc shape;

    Fit the IF cable in the body of connector, and tighten the body and nut with the

    wrenches(S=16mm);

    Procedure

    Place the nut to the IF cable, and then strip the sheath off the IF cable ;

    Place the clamp to the end of the IF cable;

    Fold back the shielding layer to the clamp. Then, place the sleeve between the

    shielding layer and the insulating layer;

    Duration

    1.3.3AAssemble IF cable

    (Outdoor)A 15 minutes(Total)

    MW Standard Operation Procedure for Axis Swap Project

    SN Task Description Operator

    15.5mm

    Sheath Shieldinglayer

    Insulating layer

    Inner conductor Nut Clam

    pSleeve Body

    1- 1-B 1- 2

    3 4-A 4- 4-

    1.3.3 Assemble IF terminalHuawei Confidential

    Copyright Huawei Technologies Co., Ltd. All rights reserved. Page 20

    2

    3

    4

    1 2 3

    4 5 6

    1 2

    3 4

    5 6

    File Brush

    Materials

    Tools

    Paper knife Diagonal pliers Solid Wrench

    IF cable IF cable connector (N-JRG8-1 Connector)

    4mm

    4.5mm

    3 4-A 4- 4-

    5- 5-B 5- 5-

    5- 6-A 6- 6-

    1.3.3 Assemble IF terminalHuawei Confidential

    Copyright Huawei Technologies Co., Ltd. All rights reserved. Page 20

  • 12

    3

    4

    5

    6

    7

    1

    2

    3

    Notes

    If the buzz is generated, the IF cable is short-circuited. The IF cable connector should

    be made again.

    Procedure

    Set the multimeter to the continuity test mode.

    Connect one needle of the multimeter to the external conductor of the IF cable

    connector. Connect the other needle to the core of the IF cable connector.

    If no buzz is generated, the IF cable is normal.

    Duration

    1.3.3B Test the IF Cable Connector A 15 minutes(Total)MW Standard Operation Procedure for Axis Swap Project

    SN Task Description Operator

    1

    2

    ....

    1.3.3 Assemble IF terminalHuawei Confidential

    Copyright Huawei Technologies Co., Ltd. All rights reserved. Page 21

    4

    1 2 3

    3 4 6

    1 2

    3 4

    5 6

    Materials

    Tools

    Multimeter

    2

    1.3.3 Assemble IF terminalHuawei Confidential

    Copyright Huawei Technologies Co., Ltd. All rights reserved. Page 21

  • 12

    3

    4

    5

    6

    1

    2

    3

    4

    MW Standard Operation Procedure for Axis Swap Project SN Task Description Operator Duration

    1.3.3CAssemble IF terminal

    (outdoor)A 15 minutes(Total)

    Note

    Procedure

    Mark the IF cable by color tape to identify which connected to main ODU;

    Mark the IF cable with waterproof label(yellow) to identify which connected to main

    ODU ;

    Protect the IF terminal to avoid the damage during hanging .

    1 2-A 2-

    3- 3-B

    1.3.3 Assemble IF terminalHuawei Confidential

    Copyright Huawei Technologies Co., Ltd. All rights reserved. Page 22

    1 2 3

    4 5 6

    1 2

    3 4

    5 6

    Materials

    PVC tape Cable tie (black)

    Outdoor label

    Tools

    Cutter

    1.3.3 Assemble IF terminalHuawei Confidential

    Copyright Huawei Technologies Co., Ltd. All rights reserved. Page 22

  • 12

    3

    4

    5

    1

    2

    3

    1 2 3

    MW Standard Operation Procedure for Axis Swap Project SN Task Description Operator

    Procedure

    Main ODU should be mounted on THIS SIDE UP MAINside;

    Duration

    1.4A Install ODU D 5 minutes

    Remove the protective cap of the feed boom, and then apply an appropriate ainstallof

    vaseline to the gasket of the feed boom;

    installODU on coupler as polarization decided.Close the 4 latches cornerwise ;

    Install stand-by ODU on the other side of coupler with same method above .

    Note

    Main ODU should be mounted onTHIS SIDE UP MAINside.

    The IF interface on ODU must face to the opposite from hoisting ring.

    Tools

    1-A 1-B 1-C

    2 3-A 3-

    3-C 4-A 4-

    4 5 6

    1 2

    3 4

    Material

    ODU

    3-C 4-A 4-

    1.4 Install ODUHuawei Confidential

    Copyright Huawei Technologies Co., Ltd. All rights reserved. Page 23

  • 12

    3

    4

    5

    6

    1

    2

    3

    1 2 3

    MW Standard Operation Procedure for Axis Swap Project SN Task Description Operator Duration

    Note

    1.4B Install ODU D 5 minutes

    Procedure

    Remove the nut of the grounding bolt on the ODU;

    Place the ring terminal of the ODU ground cable around the grounding bolt ;

    Tighten the nut.

    Fasten the grounding kits tightly.

    Tools

    Wrench

    1- 1-B 1-C

    2- 2-B 2-C

    3- 3-B 3-C

    1.4 Install ODUHuawei Confidential

    Copyright Huawei Technologies Co., Ltd. All rights reserved. Page 24

    1 2 3

    4 5 6

    1 2

    3 4

    Wrench

    Material

    ODU Grounding kits

    1.4 Install ODUHuawei Confidential

    Copyright Huawei Technologies Co., Ltd. All rights reserved. Page 24

  • 13

    4

    5

    2

    3

    4

    installthe pole at right position on the tower as the azimuth, high of the design document.

    Confirm the pole verticality.

    Tools

    Clamp the upper and lower T-bracket to the tower,fasten the bolts on T-bracket;

    Confirm the pole verticality with adjustment of the lower T-bracket.

    Note

    Bind hanging rope on the upper T-bracket and bind towing rope on another T-bracket ;

    2

    BCD hang the pole up and A control the pole not touch tower with towing rope simultaneous;

    CD hold the pole at the position antenna will be mounted with calling:"up/down" to the people on

    ground ;

    Duration

    1.5.1 Lift & Install pole (AD)BC 25 minutes

    MW Standard Operation Procedure for Axis Swap

    Project

    SN Task Description Operator

    Procedure

    1 2

    3 4

    1.5.1 Lift & Install poleHuawei Confidential

    Copyright Huawei Technologies Co., Ltd. All rights reserved. Page 25

    1 2 3

    4 5 6

    1 2

    3 4

    5 6

    Material

    pole

    Hanging rope Towing rope Spanner

    Level Safety belt

    Tools

    1.5.1 Lift & Install poleHuawei Confidential

    Copyright Huawei Technologies Co., Ltd. All rights reserved. Page 25

  • 12

    3

    4

    5

    1

    2

    1 2 3

    3 4 6

    Duration

    1.5.2A Install 19"Rack AD 8 minutes

    Procedure

    MW Standard Operation Procedure for Axis Swap Project SN Task Description Operator

    Mark the location of the 19" Rack according to the equipment layout, identify the

    installation reference point and mark it for the 19" Rack installation;

    Use a percussion drill with bit 16 to drill holes at the anchor points,clear the dust

    inside and around the holes ;

    Tools

    Percussion drill Claw hammer Wrench

    Marking pen

    Hammer the expansion bolt until it tube completely enters the hole.

    Note

    Clear the dust inside and around the holes. If the inter-hole spacing is too wide or too

    narrow, locate and drill holes again;

    1 2

    3

    1.5.2 Install 19'RackHuawei Confidential

    Copyright Huawei Technologies Co., Ltd. All rights reserved. Page 26

    3 4 6

    1 2

    3 4

    Marking pen

    Materials

    Expansion nut

    1.5.2 Install 19'RackHuawei Confidential

    Copyright Huawei Technologies Co., Ltd. All rights reserved. Page 26

  • 12

    3

    4

    5

    1

    2

    1 2 3

    3 4 6

    MW Standard Operation Procedure for Axis Swap Project SN Task Description Operator Duration

    Place the rack on the hole that had been drilled , tighten the bolts to ensure that

    Rack and base is installed together;

    Wire bindings can be assembled to the front or the back of Rack frame according to

    wire outlet.

    Note

    When the wire is up-route, let the two wire bindings empty position on the top of Rack

    , when the wire is dowen-route, let the two wire bindings empty at the bottom of

    Rack.

    1.5.2B Install 19"Rack AD 6 minutes

    Procedure

    Install the base to the frame of rack, then tighten the four bolts;

    Tools

    Screwdriver Level bar

    1- 1-

    2- 2-

    3-A 3-

    Insulated plate

    1.5.2 Install 19'RackHuawei Confidential

    Copyright Huawei Technologies Co., Ltd. All rights reserved. Page 27

    3 4 6

    1 2

    3 4

    Materials

    19"Rack Insulated plate

    3-A 3-

    1.5.2 Install 19'RackHuawei Confidential

    Copyright Huawei Technologies Co., Ltd. All rights reserved. Page 27

  • 12

    3

    4

    5

    1

    2

    3

    4

    1 2 3

    MW Standard Operation Procedure for Axis Swap Project SN Task Description Operator Duration

    1.5.2C Install 19'Rack AD 6 minutes

    Procedure

    Assemble OT terminals to one end of the PGND cable , for details, see SN 1.5.2D.

    Tools

    Cross screwdriver Crimping plier

    Link the OT terminal to the grounding screw on the 19"rack ;

    Lay PGND cable from 19" rack to grounding bar along cable ladder ;

    Assemble OT terminal to the other end of PGND cable, then link it to the grounding

    bar .

    Note

    Keep the cross-section of the conductor level with the end face of the OT terminal

    1.5.2 Install 19'RackHuawei Confidential

    Copyright Huawei Technologies Co., Ltd. All rights reserved. Page 28

    1 2 3

    4 5 6

    1 2

    3 4

    5 6

    Cross screwdriver Crimping plier

    Materials

    OT terminal Power cable with yellow green 16mm2

    1.5.2 Install 19'RackHuawei Confidential

    Copyright Huawei Technologies Co., Ltd. All rights reserved. Page 28

  • 12

    3

    4

    5

    1

    2

    3

    4

    Tools

    Note

    When making the core end or ring terminal, you should level the exposed conductor

    with the endface of the terminal and press the endface to the conductor with the

    crimping pliers.

    Procedure

    Strip a certain length of the insulation layer off the ground cable ;

    Insert the exposed conductor into the core end terminal. Ensure that the conductor is

    level with the endface of the core end terminal;

    Press the endface to the conductor by using the crimping pliers.

    Duration

    1.5.2D Install 19'Rack AD 5 minutesMW Standard Operation Procedure for Axis Swap Project

    SN Task Description Operator

    6 MM

    1- 1-B 1-

    1- 2-A 2-

    3- 3-B

    1.5.2 Install 19'RackHuawei Confidential

    Copyright Huawei Technologies Co., Ltd. All rights reserved. Page 29

    1 2 3

    4 5 6

    1 2

    3 4

    5 6

    Materials

    OT terminal Power cable with yellow green

    Tools

    Crimping plier OT Terminal

    3- 3-B

    1.5.2 Install 19'RackHuawei Confidential

    Copyright Huawei Technologies Co., Ltd. All rights reserved. Page 29

  • 12

    3

    4

    5

    6

    7

    1

    2

    Procedure

    Before you lift and install the antenna, determine the pole and azimuth of the antenna

    according to the design document ;

    Bind the lifting rope and pulling rope to the lifting ring and stand of the antenna ;

    Two installation operators on the ground lift the antenna to the tower;

    Install the two clamps of the stand around the pole and fix the clamps on the stand.

    Then, fix the antenna according to the azimuth specified in the design document .For

    details, see working procedure 1.6.1C.

    Remove the rubber plugs of the two air holes on the bottom of the antenna;

    MW Standard Operation Procedure for Axis Swap Project

    SN Task Description Operator Duration

    1.6.1A Lift and Install the Antenna (AD)BC 25 minutes

    Note

    When fixing the antenna, you cannot remove the lifting rope from the antenna.

    Instead, you should keep the lifting rope bound on the tower tightly till the antenna is

    When lifting the antenna, you must use the pulling rope to prevent the antenna from

    hitting the tower. In this manner, the equipment can be protected from damage.

    Install the anti-fall clamp on the pole. For details , see working procedure 1.6.1B.

    Perform the grounding for the ODU. For details, see working procedure 1.6.1D.

    1 2 3

    4 5 6

    7-A 7-B

    1.6.1 Lift & Install Antenna Huawei Confidential

    Copyright Huawei Technologies Co., Ltd. All rights reserved. Page 30

    2

    1 2 3

    4 5 6

    1 2

    3 4

    Solid wrench

    Materials

    Antenna ODU

    Instead, you should keep the lifting rope bound on the tower tightly till the antenna is

    fixed to the pole. In this manner, the antenna can be protected from falling down.

    Tools

    Lifting hook Lifting rope Allen wrench

    Anti-fall clamp

    7-A 7-B

    1.6.1 Lift & Install Antenna Huawei Confidential

    Copyright Huawei Technologies Co., Ltd. All rights reserved. Page 30

  • 12

    3

    4

    5

    1

    2

    3

    4

    1 2 3

    5 minutes

    Procedure

    Loosen one bolt on the anti-fall clamp;

    Place the anti-fall clamp around the pole;

    Tighten the bolt to fix the anti-fall clamp to the pole.

    MW Standard Operation Procedure for Axis Swap Project SN Task Description Operator Duration

    1.6.1B Install the Anti-fall Clamp C

    Note

    Tools

    Allen wrench

    1- 1-

    1-

    3- 3-

    2-

    3-C

    2-

    1.6.1 Lift & Install Antenna Huawei Confidential

    Copyright Huawei Technologies Co., Ltd. All rights reserved. Page 31

    4 5 6

    1 2

    3 4

    5 6

    Materials

    Anti-fall clamp

    3- 3- 3-C

    1.6.1 Lift & Install Antenna Huawei Confidential

    Copyright Huawei Technologies Co., Ltd. All rights reserved. Page 31

  • 12

    3

    4

    Hanging Bracket Left Installation 5

    1

    2

    3

    4

    1 2 3

    MW Standard Operation Procedure for Axis Swap Project SN Task Description Operator Duration

    1.6.1C Fix the Hanging Bracket C 10 minutes

    Hanging Bracket Right Installation

    Note

    Fasten the antenna tightly.

    When installing the antenna, ensure that the hanging bracket is close to the anti-fall

    clamp .

    Procedure

    Install the down clamps of the hanging bracket around the pole, then tighten the nuts

    to fix the antenna to the pole;

    Install the up clamps of the hanging bracket around the pole, then tighten the nuts to

    fix the antenna to the pole.

    Tools

    Solid wrench

    1-

    2-b

    1-b

    2-C

    2-

    2-D

    1.6.1 Lift & Install Antenna Huawei Confidential

    Copyright Huawei Technologies Co., Ltd. All rights reserved. Page 32

    1 2 3

    4 5 6

    1 2

    3 4

    5 6

    Materials

    Solid wrench

    2-b 2-C 2-D

    1.6.1 Lift & Install Antenna Huawei Confidential

    Copyright Huawei Technologies Co., Ltd. All rights reserved. Page 32

  • 12

    3

    4

    5

    1

    2

    3

    4

    1 2 3

    Fix the fixing clip of the ground cable to the grounding point ;

    Bind the ground cable to the tower and cut off the redundant bundling tape .

    Note

    The position of grounding point should be lower than the antenna.

    MW Standard Operation Procedure for Axis Swap Project SN Task Description Operator

    Determine a proper grounding point on the tower. Then, remove anti-rustic paint or

    rust at the grounding point;

    Duration

    1.6.1DPerform the Grounding for

    the ODU C 5 minutes

    Procedure

    Tools

    Solid wrench Diagonal pliers

    1- 1- 2-

    2- 2- 3-

    3- 3-C 3-D

    1.6.1 Lift & Install Antenna Huawei Confidential

    Copyright Huawei Technologies Co., Ltd. All rights reserved. Page 33

    1 2 3

    4 5 6

    1 2

    3 4

    5 6

    Ground cable of the ODU Bundling tape

    Materials

    Solid wrench Diagonal pliers3- 3-C 3-D

    1.6.1 Lift & Install Antenna Huawei Confidential

    Copyright Huawei Technologies Co., Ltd. All rights reserved. Page 33

  • 12

    3

    4

    5

    6

    1

    2

    3

    MW Standard Operation Procedure for Axis Swap Project SN Task Description Operator Duration

    1.6.2A Install DCDB AD 8 minutes

    Note

    The power cable must be 16mm2.

    Tools

    Procedure

    According the design document, fix the four captive nuts to the installbar on the rack

    column;

    Install the DCDB in the correct position of 19" Rack, tighten the four screws on the

    panel to secure the DCDB on the rack ;

    Remove the four panel of DCDB,and remove the panel;

    Connect the -48 power cable(blue cable) to the first air breaker, and the grounding

    cable(black cable) to the place above the air breaker .

    4U

    1- 1-

    2- 2-

    1 2 3

    3 4 6

    1 2

    3 4

    5 6

    Materials

    DCDB Power cable

    Captive nuts

    Cross screwdriver Crimping plier OT terminal

    -48V cable

    Grounding

    3 4

    1.6.2 Install DCDBHuawei Confidential

    Copyright Huawei Technologies Co., Ltd. All rights reserved. Page 34

  • 12

    3

    4

    5

    6

    1

    2

    3

    MW Standard Operation Procedure for Axis Swap Project SN Task Description Operator Duration

    1.6.2B Install DCDB AD 6 minutes

    Note

    The power must connect to the 63A air breaker in the DC power cabinet.

    Tools

    Procedure

    Route the power cable (blue cable and black cable) to the DC power cabinet along

    cable ladder.

    Install power cable(from DCDB) in the proper air breaker at the DC power cabinet.

    Grounding cable of DCDB

    -48v cable of DCDB

    1.6.2 Install DCDBHuawei Confidential

    Copyright Huawei Technologies Co., Ltd. All rights reserved. Page 35

    1 2 3

    4 5 6

    1 2

    3 4

    5 6

    Tools

    Materials

    DCDB Power cable

    Cross screwdriver Crimping plier OT terminal

    -48v cable of DCDB

    1.6.2 Install DCDBHuawei Confidential

    Copyright Huawei Technologies Co., Ltd. All rights reserved. Page 35

  • 12

    3

    4

    5

    6

    1

    2

    3

    MW Standard Operation Procedure for Axis Swap Project SN Task Description Operator Duration

    1.6.2C Install DCDB AD 6 minutes

    Note

    Procedure

    Connect the grounding cable in the DCDB.

    Route the grounding cable from DCDB to indoor grounding bar along the cable

    ladder.

    Determine the length of the grounding cable based on the grounding position

    ,terminal the grounding cable with OT terminal. Then, properly fasten the grounding

    cable to the grounding bar.

    Grounding cable of

    1.6.2 Install DCDBHuawei Confidential

    Copyright Huawei Technologies Co., Ltd. All rights reserved. Page 36

    3

    1 2 3

    4 5 6

    1 2

    3 4

    5 6

    Tools

    Materials

    DCDB PGND cable

    Cross screwdriver Crimping plier OT terminal

    1.6.2 Install DCDBHuawei Confidential

    Copyright Huawei Technologies Co., Ltd. All rights reserved. Page 36

  • 12

    3

    4

    5

    6

    1

    2

    3

    4

    Hold the IDU with both hands and push the IDU into the rack. Then, tighten the four

    panel screws in a diagonal sequence. In this manner, the IDU is fixed to the rack;

    Note

    When installing the IDUon a Huawei open rack, you should fix two captive nuts with a

    space of four holes on the installbar.

    Assemble OT terminals to one end of the PGND cable,Link the OT terminal to the

    grounding screw on the 19"rack.

    MW Standard Operation Procedure for Axis Swap Project SN Task Description Operator

    Procedure

    Obtain the IDU and ground cable;

    Remove the two screws at the grounding point on the left of the IDU;

    Use the removed screws to fix the ground cable to the grounding point of the IDU;

    Duration

    1.7A Install the IDU AD 4 minutes

    Tighten the four front panel screws in a diagonal sequence.

    There must be a space of two holes above and below the IDU chasssis for heat

    disspation.

    Fix the four captive nuts to the installbar on the rack column, according to the deigned

    location of the IDU;

    2U

    1- 1-B 2

    3- 3-B 4

    1.7 Install IDU and DDFHuawei Confidential

    Copyright Huawei Technologies Co., Ltd. All rights reserved. Page 37

    4

    1 2 3

    4 5 6

    1 2

    3 4

    5 6

    Materials

    IDU 620 Ground cable

    Four M6 captive nuts Four M6 panel screws

    Cross screwdriver Flathead screwdriver

    Tools5- 5-A 6

    1.7 Install IDU and DDFHuawei Confidential

    Copyright Huawei Technologies Co., Ltd. All rights reserved. Page 37

  • 12

    3

    4

    5

    6

    1

    2

    3

    4

    Press the ejector levers inward forcibly;

    Tighten the two screws on the front panel ;

    Note

    When installing the tributary board and IF board, you should wear antistatic gloves.

    Install the IF board in the same manner .

    MW Standard Operation Procedure for Axis Swap Project SN Task Description Operator

    Procedure

    Take out the tributary board from the package;

    Press the ejector levers with both hands. Then, insert the board smoothly along the

    board track till the board cannot move forward;

    Push the board to ensure that the board is caught tightly;

    Duration

    1.7B Install IDU Boards AD 2 minutes

    1- 1-B 2

    3 4 5

    6- 6-B 6-

    1.7 Install IDU and DDFHuawei Confidential

    Copyright Huawei Technologies Co., Ltd. All rights reserved. Page 38

    1 2 3

    4 5 6

    1 2

    3 4

    5 6

    Boards on the RTN

    Materials

    Cross screwdriver Antistatic gloves

    6- 6-B 6-

    1.7 Install IDU and DDFHuawei Confidential

    Copyright Huawei Technologies Co., Ltd. All rights reserved. Page 38

  • 12

    3

    4

    5

    1

    2

    3

    4

    1 2 3

    Duration

    1.7C Install the DDF AD 4 minutes

    Procedure

    MW Standard Operation Procedure for Axis Swap Project SN Task Description Operator

    When installing the DDF on a Huawei open rack, you should fix two captive nuts with a

    space of one hole on the installbar.

    Tighten the four front panel screws in a diagonal sequence.

    Tools

    Flathead screwdriver Cross screwdriver

    Take out the DDF from the package ;

    Remove the captive nuts and panel screws on the DDF;

    Fix the four captive nuts to the installbar on the rack column, according to the deigned

    location of the DDF;

    Tighten the four panel screws. In this manner, the DDF is fixed to the rack .

    Note

    1111UUUU

    1 2-A 2-

    3 4-A 4-

    4-C

    1.7 Install IDU and DDFHuawei Confidential

    Copyright Huawei Technologies Co., Ltd. All rights reserved. Page 39

    1 2 3

    4 5 6

    1 2

    3 4

    5 6

    Flathead screwdriver Cross screwdriver

    Materials

    120-ohm DDF Four M6 captive nuts

    Four M6 panel screws

    4-C

    1.7 Install IDU and DDFHuawei Confidential

    Copyright Huawei Technologies Co., Ltd. All rights reserved. Page 39

  • 12

    3

    4

    5

    6

    1

    2

    3

    4

    1 2 3

    Tools

    Lifting rope Solid wrench

    Procedure

    Put the hanging rope along the cable ladder down to the ground;

    Diagonal pliers

    Note

    When binding the IF cable to the lifting rope, you can not bind the connector with the rope. Otherwise, the connect

    might be damaged in the lifting process.

    Bind the IF cable to the lifting rope on the ground, then pull up the lifting rope with the IF cable ;

    Reserve the IF cable of extra three to five meters at the ODU. Coil the extra cable into a circle of more than 0.6

    meter in diameter, and fix the cable to the tower ;

    Fix the IF cable to the cable ladder along the route of the IF cable. Pass the IF cable through the feeder window

    into the room;

    Make the coiled cable a waterproof curve in front of the feeder window, and fix the cable to the cable ladder .

    MW Standard Operation Procedure for Axis Swap Project SN Task Description Operator Duration

    1.8.1 Lift and Route IF Cable (A)BC 15 minutes

    0.6M

    1 2- 2-

    3- 3- 4

    5

    1.8.1 Lift & Route IF cableHuawei Confidential

    Copyright Huawei Technologies Co., Ltd. All rights reserved. Page 40

    4 5 6

    1 2

    3 4

    Materials

    IF cable Bundling tape

    1.8.1 Lift & Route IF cableHuawei Confidential

    Copyright Huawei Technologies Co., Ltd. All rights reserved. Page 40

  • 12

    3

    4

    5

    1

    2

    3

    4

    MW Standard Operation Procedure for Axis Swap Project SN Task Description Operator

    Note

    Tools

    Duration

    1.8.2ARoute and Install 120-Ohm

    E1 CablesA

    Cut the E1 cables to a proper length and mark the cables for the transmit and receive

    directions (such as Tx/Rx) ;

    Bond the E1 cables. For details on how to bond the 120-ohm E1 cables , see working

    procedure 1.8.2B.

    15 minutes

    Procedure

    Connect the E1 cables to the E1 interface on the tributary board. Then, tighten the

    screws to fix the cables ;

    Route the E1 cables from the equipment side to the DDF, and tighten it to the Rack by

    cable tie;

    1- 1 1-

    1- 2 3

    4- 4 4-

    1.8.2 Install E1 or FE cableHuawei Confidential

    Copyright Huawei Technologies Co., Ltd. All rights reserved. Page 41

    1 2 3

    4 5 6

    1 2

    3 4

    5 6

    Cross screwdriver Marking pen Punchdown tool

    Paper knife Diagonal pliers

    Materials

    120-ohm E1 cable PVC insulation tape

    Cable tie(white)

    4- 4 4-

    1.8.2 Install E1 or FE cableHuawei Confidential

    Copyright Huawei Technologies Co., Ltd. All rights reserved. Page 41

  • 12

    3

    4

    5

    1

    2

    3

    4

    MW Standard Operation Procedure for Axis Swap Project SN Task Description Operator Duration

    1.8.2B Bond 120-Ohm E1 Cables A 10 minutes

    Procedure

    Remove the DDF module of the DDF ;

    Pass the E1 cable through the hole on the backplane of the DDF ;

    Tools

    Strip the sheath, shielding layer, and protection layer off the E1 cable. Apply the PVC

    tape on the cable for protection;

    Pass the core wires of the E1 cable through the hole of the DDF module;

    Insert the core wires to the connection holes of the DDF module according to the wire

    sequence table of the E1 cable ). For details, see working procedure 1.8.2C.

    Note

    1 2 3-

    3- 3 3-D

    3- 4 5-

    1.8.2 Install E1 or FE cableHuawei Confidential

    Copyright Huawei Technologies Co., Ltd. All rights reserved. Page 42

    1 2 3

    4 5 6

    1 2

    3 4

    5 6

    Diagonal pliers Marking pen Punchdown tool

    Paper knife

    Materials

    120-ohm E1 cable PVC insulation tape

    Bundling tape

    5- 5 5-D

    1.8.2 Install E1 or FE cableHuawei Confidential

    Copyright Huawei Technologies Co., Ltd. All rights reserved. Page 42

  • 12

    3

    4

    5

    1

    2

    3

    4

    1 2 3Punchdown tool

    Tools

    Note

    Procedure

    Connect the E1 cables according to the MUX plan.

    Duration

    1.8.2C120-ohm E1 cable

    Connections

    MW Standard Operation Procedure for Axis Swap Project SN Task Description Operator

    Color of the core Relationship Color of the core Relationship

    1 White 25 White

    2 Blue 26 Orange

    3 White 27 White

    4 Green 28 Brown

    5 White 29 Red

    6 Grey 30 Blue

    7 Red 31 Red

    8 Orange 32 Green

    9 Red 33 Red

    10 Brown 34 Grey

    11 Black 35 Black

    12 Blue 36 Orange

    13 Black 37 Black

    14 Green 38 Brown

    15 Black 39 Yellow

    16 Grey 40 Blue

    17 White 41 White

    18 Blue 42 Orange

    19 White 43 White

    20 Green 44 Brown

    21 White 45 Red

    22 Grey 46 Blue

    23 Red 47 Red

    24 Orange 48 Green

    49 Red 73 Red

    50 Brown 74 Grey

    51 Black 75 Black

    52 Blue 76 Orange

    53 Black 77 Black

    54 Green 78 Brown

    55 Black 79 Yellow

    56 Grey 80 Blue

    Remarks Tape Color W W

    Pin Remarks Tape Color Pin

    Twisted pair

    Twisted pair

    Twisted pair

    Twisted pair

    Twisted pair

    Twisted pair

    Twisted pair

    Blue

    Orange

    T7

    T8

    T9

    T10

    T11

    T12

    T13

    T14

    T15 R15

    T0

    T1

    T2

    T3

    T4

    T5

    T6

    Twiste d pair

    R0

    R1

    R2

    R3

    R4

    Blue

    Orange

    R5

    R6

    R7

    R8

    Twisted pair

    R11

    R12

    Twiste d pair

    Twisted pair

    Twisted pair

    Twisted pair

    R13

    R14

    Twisted pair

    Twiste d pair

    Twiste d pair

    Twiste d pair

    Twiste d pair

    Twiste d pair

    Twiste d pair

    Twiste d pair

    Twiste d pair

    Twisted pair

    Twisted pair

    Twisted pair

    Twisted pair

    Twisted pair

    R9

    R10

    Twisted pair

    Twisted pair

    Twisted pair

    Twisted pair

    Twisted pair

    1.8.2 Install E1 or FE cableHuawei Confidential

    Copyright Huawei Technologies Co., Ltd. All rights reserved. Page 43

    4 5 6

    1 2

    3 4

    5 6

    Materials

    E1 cable DDF

    LAN cable

    Color of the core Relationship Color of the core Relationship

    1 White 25 White

    2 Blue 26 Orange

    3 White 27 White

    4 Green 28 Brown

    5 White 29 Red

    6 Grey 30 Blue

    7 Red 31 Red

    8 Orange 32 Green

    9 Red 33 Red

    10 Brown 34 Grey

    11 Black 35 Black

    12 Blue 36 Orange

    13 Black 37 Black

    14 Green 38 Brown

    15 Black 39 Yellow

    16 Grey 40 Blue

    17 White 41 White

    18 Blue 42 Orange

    19 White 43 White

    20 Green 44 Brown

    21 White 45 Red

    22 Grey 46 Blue

    23 Red 47 Red

    24 Orange 48 Green

    49 Red 73 Red

    50 Brown 74 Grey

    51 Black 75 Black

    52 Blue 76 Orange

    53 Black 77 Black

    54 Green 78 Brown

    55 Black 79 Yellow

    56 Grey 80 Blue

    Remarks Tape Color W W

    Pin Remarks Tape Color Pin

    Twisted pair

    Twisted pair

    Twisted pair

    Twisted pair

    Twisted pair

    Twisted pair

    Twisted pair

    Blue

    Orange

    T7

    T8

    T9

    T10

    T11

    T12

    T13

    T14

    T15 R15

    T0

    T1

    T2

    T3

    T4

    T5

    T6

    Twiste d pair

    R0

    R1

    R2

    R3

    R4

    Blue

    Orange

    R5

    R6

    R7

    R8

    Twisted pair

    R11

    R12

    Twiste d pair

    Twisted pair

    Twisted pair

    Twisted pair

    R13

    R14

    Twisted pair

    Twiste d pair

    Twiste d pair

    Twiste d pair

    Twiste d pair

    Twiste d pair

    Twiste d pair

    Twiste d pair

    Twiste d pair

    Twisted pair

    Twisted pair

    Twisted pair

    Twisted pair

    Twisted pair

    R9

    R10

    Twisted pair

    Twisted pair

    Twisted pair

    Twisted pair

    Twisted pair

    1.8.2 Install E1 or FE cableHuawei Confidential

    Copyright Huawei Technologies Co., Ltd. All rights reserved. Page 43

  • 12

    3

    4

    5

    6

    1

    2

    3

    MW Standard Operation Procedure for Axis Swap Project SN Task Description Operator Duration

    1.8.3A Route the IF Cable(indoor) D 15 minutes

    Note

    Tools

    Procedure

    Lay the IF cable from the feeder window to the position connected to IF jumper along

    the cable labber;

    Cut off the IF cable of an appropriate length to make the IF cable connector

    according to (Assemble IF terminal (oitdoor)), after make the IF terminal test it as

    follow 1.8.3B;

    1

    2

    1.8.3 Route the IF cableHuawei Confidential

    Copyright Huawei Technologies Co., Ltd. All rights reserved. Page 44

    1 2 3

    4 5 6

    1 2

    3 4

    File

    Paper knife Diagonal pliers Solid Wrench

    Materials

    IF cable IF cable connector (N-JRG8-1 Connector)

    Cable tie(White)

    1.8.3 Route the IF cableHuawei Confidential

    Copyright Huawei Technologies Co., Ltd. All rights reserved. Page 44

  • 12

    3

    4

    5

    6

    1

    2

    3

    4

    MW Standard Operation Procedure for Axis Swap Project SN Task Description Operator Duration

    1.8.3B Route the IF Cable(indoor) D 5minutes

    Procedure

    Set the multimeter to R/. Connect one needle of the multimeter to the external conductor of the IF cable connector. Connect the other needle to the core of the IF

    cable connector

    In the short circuit, the test value of resistance should be infinitude.

    In the open circuit , the test value of resistance should be very small.

    Note

    1

    2

    The test value of resistance should be infinitude.

    ODU Side IDU Side

    Open circuit.

    The test value of resistance should be very small.

    ODU Side IDU Side

    1.8.3 Route the IF cableHuawei Confidential

    Copyright Huawei Technologies Co., Ltd. All rights reserved. Page 45

    4

    1 2 3

    4 5 6

    1 2

    3 4

    5 6

    Tools

    Multimeter

    Materials

    resistance should be very small.

    Short circuit

    1.8.3 Route the IF cableHuawei Confidential

    Copyright Huawei Technologies Co., Ltd. All rights reserved. Page 45

  • 12

    3

    4

    5

    1

    2

    3

    4

    MW Standard Operation Procedure for Axis Swap Project SN Task Description Operator Duration

    1.8.3C Route the IF Cable(indoor) D 5 minutes

    Procedure

    Mark the IF cable with color tape at the two ends of IF cable to devide which

    connecting the IF cable from main ODU;

    Connect the IF cable to the IF interface on the IF board, and then fix the connector;

    Tools

    Route the IF jumper from the equipment side to a proper location on the cable ladder,

    Interconnect the IF jumper with the IF cable properly .

    Note

    In case of 1+1 HSB/SD,IF cable from slot 5/6 must be connected with IF cable of

    main ODU, IF cable from slot 7/8 must be connected with IF cable of stand-by ODU

    1- 1- 2-

    2- 2-C 2-D

    1.8.3 Route the IF cableHuawei Confidential

    Copyright Huawei Technologies Co., Ltd. All rights reserved. Page 46

    1 2 3

    4 5 6

    1 2

    3 4

    5 6

    Tools

    Wrench

    Materials

    IF jumper cable

    1.8.3 Route the IF cableHuawei Confidential

    Copyright Huawei Technologies Co., Ltd. All rights reserved. Page 46

  • 12

    3

    4

    5

    1

    Wrap the connector with one layer of PVC tape 35 cm below the connector and

    toward the direction of the ODU ;

    When wrapping the connector with the waterproof tape and PVC tape, you should

    stretch the tape to 3/4 of its original width. In addition, the upper layer should cover

    about 1/2 of the lower layer.

    Wrap the connector with three layers of waterproof tape 35 cm below the connector.

    The wrapping directions of the three layers are from down to up, from up to down,

    and from down to up respectively;

    Wrap the PVC tape on both ends tightly with cable tie. Then, cut off the redundant

    bundling tape.

    DurationSN Task Description

    MW Standard Operation Procedure for Axis Swap Project

    Note

    15 minutes

    Procedure

    Connect the connector of IF cable to the IF interface on the ODU. Then, tighten the

    connector gently with a wrench;

    1.9.1A

    Perform the Waterproof

    Treatment of the IF Cable

    Connector

    B

    Wrap the connector with three layers of PVC tape 35 cm below the connector. The

    wrapping directions of the three layers are from down to up, from up to down, and

    from down to up respectively ;

    Operator

    123

    123

    1

    1- 1- 2

    3- 3- 4

    1.9.1 Waterproof ODUHuawei Confidential

    Copyright Huawei Technologies Co., Ltd. All rights reserved. Page 47

    2

    3

    1 2 3

    4 5 6

    1 2

    3 4

    5 6

    Paper knife Diagonal pliers

    about 1/2 of the lower layer.

    The redundant of cable tie must be 5-10mm.

    Waterproof tape PVC tape

    Cable tie

    Materials

    Tools

    123

    123

    3- 3- 4

    5- 5-C5-

    1.9.1 Waterproof ODUHuawei Confidential

    Copyright Huawei Technologies Co., Ltd. All rights reserved. Page 47

  • 12

    3

    4

    5

    6

    1

    2

    3

    4

    The redundant of cable tie must be 5-10mm.

    Tools

    Note

    Procedure

    Bind IF cable to the cable ladder every 1m with cable ties.

    Cut off extra part of cable ties.

    Duration

    1.9.1B Bind IF Cable B 30 minutesMW Standard Operation Procedure for Axis Swap Project

    SN Task Description Operator

    1 2

    1.9.1 Waterproof ODUHuawei Confidential

    Copyright Huawei Technologies Co., Ltd. All rights reserved. Page 48

    1 2 3

    1 2

    3 4

    IF cable Cable tie

    Tools

    Diagonal pliers

    Materials

    1.9.1 Waterproof ODUHuawei Confidential

    Copyright Huawei Technologies Co., Ltd. All rights reserved. Page 48

  • 12

    3

    4

    5

    1

    2

    3

    4

    Grounding

    Point SN.Connecting Point for the Ground CablePosition of the Grounding Clip Tools

    Duration

    50minutes(Total)

    Procedure

    Determine where the grounding clip is installed on the IF cable

    MW Standard Operation Procedure for Axis Swap Project SN Task Description Operator

    1.9.2AGrounding Point of the IF

    CableC

    Note

    1.9.2 Grounding IF cable Huawei Confidential

    Copyright Huawei Technologies Co., Ltd. All rights reserved. Page 49

    Point SN.

    1The grounding point provided by the tower (if the tower

    provides no grounding point, fix the foot of the ground

    cable onto the tower)

    1 2 3

    4 5 6

    3

    The grounding point provided by the tower (if the tower

    provides no grounding point, fix the foot of the ground

    cable onto the tower)

    1 2

    3 4

    The place about 1 m away from the IF

    interface of the ODUCross screwdriver Paper knife Wire cutter

    2

    Materials

    The outdoor grounding bar (if there is no grounding bar

    but the outdoor wiring frame is well grounded, fix the foot

    of the ground cable onto the wiring frame)

    The place about 1 m away from the cable

    entry (when the outdoor wiring frame is

    longer than 20 meters)

    The middle point of the cable (when the

    cable on tower is longer than 60 meters)

    1.9.2 Grounding IF cable Huawei Confidential

    Copyright Huawei Technologies Co., Ltd. All rights reserved. Page 49

  • 12

    3

    4

    5

    6

    1

    2

    3

    MW Standard Operation Procedure for Axis Swap Project SN Task Description

    Fit the grounding clip where the sheath is stripped off on the IF cable, and then

    tighten the screws.

    Note

    The angle between the ground cable connected to the grounding clip and the IF

    cable canSNt exceed 15 degrees. Route the ground cable along the route of the IF

    cable.Strip the sheath off the IF cable according to the length of the grounding clip.

    Don't strip any shielding layer of the IF cable.

    C 50 minutes(Total)

    Procedure

    Determine where the grounding clip is installed on the IF cable. Strip the sheath off

    the IF cable according to the length of the grounding clip;

    1.9.2BPerform the Grounding of

    the IF Cable

    Operator Duration

    38mm

    1- 1- 1-

    1- 2- 2-

    1.9.2 Grounding IF cable Huawei Confidential

    Copyright Huawei Technologies Co., Ltd. All rights reserved. Page 50

    4

    1 2 3

    4 5 6

    1 2

    3 4

    5 6

    Tools

    Materials

    Ground cable of the IF cable

    Paper knife Cross screwdriver

    2-

    1.9.2 Grounding IF cable Huawei Confidential

    Copyright Huawei Technologies Co., Ltd. All rights reserved. Page 50

  • 12

    3

    4

    5

    6

    1

    2

    3 Don't strip any shielding layer of the IF cable.

    Strip the sheath off the IF cable according to the length of the grounding clip.

    Note

    Wrap the PVC tape on both ends tightly with cable tie. Then, cut off the redundant cable tie;

    Scratching patinting at seleced point on tower;

    Fix another end of grounding clamp to seleced point on tower after scratching patinting and

    bind the grounding cable to the tower.

    Wrap the connector with three layers of PVC tape 35 cm below the clip point. The wrapping

    directions of the three layers are from down to up, from up to down, and from down to up

    respectively ;

    The angle between the ground cable connected to the grounding clip and the IF cable can't

    exceed 15 degrees. Route the ground cable along the route of the IF cable.

    50 minutes(Total)

    Procedure

    Wrap one layer of PVC tape 35 cm up and below the clip point;

    Wrap the connector with three layers of waterproof tape 35 cm up and below the clip point.

    The wrapping directions of the three layers are from down to up, from up to down, and from

    down to up respectively;

    MW Standard Operation Procedure for Axis Swap Project SN Task Description Operator Duration

    1.9.2CPerform the Grounding of

    the IF Cable C

    1123

    123

    1 2 3

    4 5 6-

    6- 6-C

    1.9.2 Grounding IF cable Huawei Confidential

    Copyright Huawei Technologies Co., Ltd. All rights reserved. Page 51

    3

    4

    1 2 3

    4 5 6

    1 2

    3 4

    5 6

    PVC tape Waterproof tape

    Don't strip any shielding layer of the IF cable.

    Tools

    Cable tie (black)

    Materials

    Down

    6- 6-C

    1.9.2 Grounding IF cable Huawei Confidential

    Copyright Huawei Technologies Co., Ltd. All rights reserved. Page 51

  • 12

    3

    4

    5

    1

    2

    3

    4

    1 2 3

    MW Standard Operation Procedure for Axis Swap Project SN Task Description Operator Duration

    1.9.3A Affix Labels B 35minutes

    Tools

    Procedure

    Affix the labels to the cables according to the standards of the customer.

    Note

    Generally, affix the label 2 cm away from the connector. To avoid bending the cable

    or making the installation of other cables inconvenient, you can affix the label to other

    places.

    No handwritten labels are allowed.

    Marking pen

    1-A 1-

    1-C 1-

    1-E 1-

    1.9.3 Make Cable LabelsHuawei Confidential

    Copyright Huawei Technologies Co., Ltd. All rights reserved. Page 52

    1 2 3

    4 5 6

    1 2

    3 4

    5 6

    Marking pen

    Materials

    Label paper

    1-E 1-

    1.9.3 Make Cable LabelsHuawei Confidential

    Copyright Huawei Technologies Co., Ltd. All rights reserved. Page 52

  • 12

    3

    4

    5

    1

    2

    3

    4

    MW Standard Operation Procedure for Axis Swap Project SN Task Description Operator Duration

    1.9.3B Affix the L-Shape Label B 35 minutes

    Procedure

    Write on the label according to the standards of the customer.

    Determine where to affix the label.

    Affix the label to the cable.

    Note

    Generally, affix the label 2 cm away from the connector. To avoid bending the cable

    or making the installation of other cables inconvenient, you can affix the label to other

    places.

    Tools

    1 2

    3-A 3-

    1.9.3 Make Cable LabelsHuawei Confidential

    Copyright Huawei Technologies Co., Ltd. All rights reserved. Page 53

    1 2 3

    4 5 6

    1 2

    3 4

    5 6

    Marking pen Paper knife

    Materials

    Label paper

    1.9.3 Make Cable LabelsHuawei Confidential

    Copyright Huawei Technologies Co., Ltd. All rights reserved. Page 53

  • 12

    3

    4

    5

    1

    2

    3

    4

    After the power cables are installed, pull the power cables to ensure that they are

    fixed.

    Remove the bolt of the working ground busbar. Put the ring terminal of the black cable

    around the bolt, and then tighten the bolt ;

    Confirm that the capacity of the air breaker is equal to or greater than 15 A. Loosen

    the bolt that fixes the power cable on the air breaker, insert the core end terminal

    vertically into the jack of the terminal block, and then tighten the bolt.

    Note

    When connecting the power cable and ground cable to the DCDB, you should insulate

    the tools with insulation tape to avoid short circuit.

    Connect the power cables to the power interface on the PXC board. Then, tighten the

    screws to fix the power cable ;

    Route the power cables from the equipment side to the DCDB ;

    Cut the power cables to a proper length. Then, make the core end terminal (of the blue

    cable) and the ring terminal (of the black cable);

    Duration

    1.9.4Route and Install Power

    Cables of the IDUD 10 minutes

    MW Standard Operation Procedure for Axis Swap Project SN Task Description Operator

    Procedure

    GND Power Cable

    1-A 1-B 1-C

    1-D 1-E 2

    3 4 5

    1.9.4 Install power cableHuawei Confidential

    Copyright Huawei Technologies Co., Ltd. All rights reserved. Page 54

    4

    1 2 3

    4 5 6

    1 2

    3 4

    5 6

    Materials

    Power cable One ring terminal and one core end terminal

    Bundling tape PVC insulation tape

    Cross screwdriver Solid wrench Crimping pliers

    Paper knife Wire cutters Diagonal pliers

    Tools

    -48V Power Cable

    GND Power Cable3 4 5

    1.9.4 Install power cableHuawei Confidential

    Copyright Huawei Technologies Co., Ltd. All rights reserved. Page 54

  • 12

    3

    4

    5

    1

    2

    1 2 3

    4 5 6

    1 2

    Materials

    No cable ties or other sundries are left on the floor or in the cabinets.

    Tools

    Note

    No packing boxes or boards are placed at random on the installation field.

    Procedure

    Collect the tools and excessive cables on site

    Clear up the equipment room and the outdoors.

    MW Standard Operation Procedure for Axis Swap Project SN Task Description Operator Duration

    1. 10 Clear sites D 15 minutes

    1.10 Clear sitesHuawei Confidential

    Copyright Huawei Technologies Co., Ltd. All rights reserved. Page55

    1 2

    3 4

    1.10 Clear sitesHuawei Confidential

    Copyright Huawei Technologies Co., Ltd. All rights reserved. Page55

  • 12

    3

    4

    5

    1

    2

    3

    4

    1 2 3

    4 5 6

    Multimeter

    Note

    If the standard voltage of the input power is 48 V, the tested value of the voltage should range from 38.4 V to -

    57.6 V.

    If the standard voltage of the input power is 60 V, the tested value of the voltage should range from 48 V to 72

    V.

    The startup time of the equipment is about 3 to 5 minutes.

    Tools

    Before powering on the equipment, check the input voltage.Connect negative needle of the multimeter to air

    breaker, connect positive needle of the multimeter to grounding point. Make sure that the input voltage is within

    the range allowed by the equipment ;

    Turn on the air breaker of the power supply ;

    Turn on the system power switch of the PXC board on the IDU, and then the ODU power switch on the IF board.

    For details, see work procedure 1.11.2B

    Duration

    1.11A Power On the Equipment A 10 minutes(Total)MW Standard Operation Procedure for Axis Swap Project

    SN Task Description Operator

    Procedure

    1 2

    3-A 3-B

    1.11 Power-on EquipHuawei Confidential

    Copyright Huawei Technologies Co., Ltd. All rights reserved. Page56

    1 2

    3 4

    5 6

    Materials

    1.11 Power-on EquipHuawei Confidential

    Copyright Huawei Technologies Co., Ltd. All rights reserved. Page56

  • 12

    3

    4

    5

    1

    2

    3

    4

    1 2 3

    4 5 6

    Materials

    Tools

    If you move the toggle switch to the left (I), the equipment the powered on. If you move the toggle switch to the

    right (O), the equipment is powered off.

    Release the toggle switch.

    Note

    Procedure

    Pull out the toggle switch;

    Move the toggle switch to the left (I) or to the right (O);

    MW Standard Operation Procedure for Axis Swap Project SN Task Description Operator Duration

    1.11BOperate the Toggle Switch of the

    EquipmentA 10 minutes(Total)

    OffOn

    On Off

    1- 1-

    2 3

    1.11 Power-on EquipHuawei Confidential

    Copyright Huawei Technologies Co., Ltd. All rights reserved. Page57

    1 2

    3 4

    5 6

    1.11 Power-on EquipHuawei Confidential

    Copyright Huawei Technologies Co., Ltd. All rights reserved. Page57

  • 12

    3

    4

    5

    1

    2

    3

    4

    MW Standard Operation Procedure for Axis Swap Project SN Task Description Operator

    1.12AConfigure the Data-Log in to

    the Web LCTA

    Tools

    Note

    Duration

    15 minutes

    Procedure

    Use a network cable to connect the network port of the computer to the EHT port on

    the SCC board of the OptiX RTN 600.

    Modify the IP address and the subnet mask of the computer. Ensure that the IP

    address is in the network section of 129.9.0.0, and the subnet mask is 255.255.0.0.

    The IP address of 129.9.0.12 can be considered as an example.Double-click the icon of Web LCT to display the home page of the Web LCT. On the

    home page, enter the default user admin and password T2000. Then, click Login to

    display the NE list.

    Log in to the Web LCT as shown in the figure. In this case, the

    V2R6C03B01cSPC002 version is considered as an example.

    1.12 Config DataHuawei Confidential

    Copyright Huawei Technologies Co., Ltd. All rights reserved. Page 58

    1 2 3

    4 5 6

    1 2

    3 4

    5 6

    Tools

    laptop

    Materials

    1.12 Config DataHuawei Confidential

    Copyright Huawei Technologies Co., Ltd. All rights reserved. Page 58

  • 12

    3

    4

    5

    1

    2

    3

    4

    1 2 3

    MW Standard Operation Procedure for Axis Swap Project SN Task Description Operator Duration

    1.12BConfigure the Data-Search

    For the EquipmentA

    Click Add NE to add the NEs that are searched out to the NE list.

    15 minutes

    Procedure

    Click NE Search to display the Search NE window.

    Click End Search to search for NEs.

    Close the Seach NE window.

    Note

    Tools

    4 5 6

    1 2

    3 4

    5 6

    Materials

    1.12 Config DataHuawei Confidential

    Copyright Huawei Technologies Co., Ltd. All rights reserved. Page 59

  • 12

    3

    4

    5

    1

    2

    3

    4

    1 2 3

    Double-click the NE in the NE list or click NE Explorer to display the NE Explorer

    window.

    Note

    15 minutes

    Procedure

    Select the NE that you need to log in to, and then click NE Login to display the NE

    Login window.

    Enter the default user lct and password password. Then, click OK.

    Tools

    MW Standard Operation Procedure for Axis Swap Project SN Task Description Operator Duration

    1.12CConfigure the Data-Log In

    To the NEA

    1 2 3

    4 5 6

    1 2

    3 4

    5 6

    Materials

    1.12 Config DataHuawei Confidential

    Copyright Huawei Technologies Co., Ltd. All rights reserved. Page 60

  • 12

    3

    4

    5

    1

    2

    3

    4

    1 2 3

    After the NE ID is modified, the system is reset. Then, you should search for and log

    in to the NE again.

    Click Modify NE ID. Modify the NE ID according to the design document, and then

    click Apply.

    Note

    15 minutes

    Procedure

    Choose Configuration > NE Attribute in the Function Tree. Then, the NE Attribute

    page is displayed.

    Modify the NE name according to the design document, and then click Apply.

    Tools

    MW Standard Operation Procedure for Axis Swap Project SN Task Description Operator Duration

    1.12DConfigure the Data-Modify

    the Name and ID of the NEA

    1 2 3

    4 5 6

    1 2

    3 4

    5 6

    Materials

    1.12 Config DataHuawei Confidential

    Copyright Huawei Technologies Co., Ltd. All rights reserved. Page 61

  • 12

    3

    4

    5

    1

    2

    3

    4

    1 2 3

    MW Standard Operation Procedure for Axis Swap Project SN Task Description Operator Duration

    1.12EConfigure the Data-Add

    Logical BoardsA 15 minutes

    Procedure

    On the Slot Layout page, click Add Logical Boards to add all the logical boards.

    Tools

    Note

    1.12 Config DataHuawei Confidential

    Copyright Huawei Technologies Co., Ltd. All rights reserved. Page 62

    1 2 3

    4 5 6

    1 2

    3 4

    5 6

    Materials

    1.12 Config DataHuawei Confidential

    Copyright Huawei Technologies Co., Ltd. All rights reserved. Page 62

  • 12

    3

    4

    5

    1

    2

    3

    4

    If two IF boards form a 1+1 protection group, you only need to configure the working

    IF board and the ODU. That is, there is no need to configure the protection IF board.

    Set the IF work mode according to the design document, and click Apply.

    Set the Tx Frequency, T/R Spacing, and Tx Power according to the design

    document, and click Apply.

    Note

    15 minutes

    Procedure

    Choose Configuration > Link Configuration in the Function Tree. Then, the Link

    Configuration page is displayed.

    Choose IF/ODU Configuration. Click the IF board or ODU to be configured.

    Tools

    MW Standard Operation Procedure for Axis Swap Project

    SN Task Description Operator Duration

    1.12FConfigure the Data-

    Configure IF and RF

    Parameters

    A

    1.12 Config DataHuawei Confidential

    Copyright Huawei Technologies Co., Ltd. All rights reserved. Page 63

    1 2 3

    4 5 6

    1 2

    3 4

    5 6

    Materials

    1.12 Config DataHuawei Confidential

    Copyright Huawei Technologies Co., Ltd. All rights reserved. Page 63

  • 12

    3

    4

    5

    1

    2

    3

    4

    If two IF boards form a 1+1 protection group, you only need to configure the working

    IF board and the ODU. That is, there is no need to configure the protection IF board.

    Tools

    MW Standard Operation Procedure for Axis Swap Project

    SN Task Description Operator Duration

    1.12GConfigure the Data-

    Configure Cross-ConnectionsA 15 minutes

    Procedure

    Choose Configuration > Cross-Connection Configuration in the Function Tree.

    Then, the Cross-Connection Configuration page is displayed.

    Click New, and configure cross-connections according to the design document.

    Then, click OK.

    Note

    1.12 Config DataHuawei Confidential

    Copyright Huawei Technologies Co., Ltd. All rights reserved. Page 64

    1 2 3

    4 5 6

    1 2

    3 4

    5 6

    Materials

    1.12 Config DataHuawei Confidential

    Copyright Huawei Technologies Co., Ltd. All rights reserved. Page 64

  • 12

    3

    4

    5

    1

    2

    3

    4

    1 2 3

    Note

    15 minutes

    Procedure

    Choose Configuration > Clock > Clock Source Priority. Then, the System Clock

    Source Priority List is displayed.Modify the clock source priority list according to the design document, and then click

    Apply.

    Tools

    MW Standard Operation Procedure for Axis Swap Project SN Task Description Operator Duration

    1.12HConfigure the Data-

    Configure the System ClockA

    1.12 Config DataHuawei Confidential

    Copyright Huawei Technologies Co., Ltd. All rights reserved. Page 65

    1 2 3

    4 5 6

    1 2

    3 4

    5 6

    Materials

    1.12 Config DataHuawei Confidential

    Copyright Huawei Technologies Co., Ltd. All rights reserved. Page 65

  • 12

    3

    4

    5

    1

    2

    3

    4

    Procedure

    Choose Configuration > NE Time Synchronization in the Function Tree. Then, the

    NE Time Synchronization page is displayed.Right-click the NE that needs to be synchronized with the NM time. Then, click

    Synchronize with NM Time.

    When you are synchronizing the NE time, make sure that the system time of the

    computer connected to the equipment is the local time.

    Click Performance > NE Performance Monitor Time in the Function Tree, and then

    choose the NE to be monitored.

    Check 15-Minute or 24-House, and click Apply.

    Note

    MW Standard Operation Procedure for Axis Swap Project

    SN Task Description Operator Duration

    1.12I

    Configure the Data-Enable

    the 15-Minute/24-Hour

    Performance Monitoring

    Function of the Equipment

    A 15 minutes

    1 2 3

    4 5 6

    1 2

    3 4

    5 6

    Materials

    Tools

    1.12 Config DataHuawei Confidential

    Copyright Huawei Technologies Co., Ltd. All rights reserved. Page 66

  • 12

    3

    4

    5

    1

    2

    3

    4

    MW Standard Operation Procedure for Axis Swap Project

    SN Task Description Operator Duration

    1.12J

    Configure the Data-Set the

    Extended ECC to the

    Automatic Mode

    A 15 minutes

    Note

    When there are two to four sets of the OptiX RTN equipment at one station, you need

    to connect all the equipment through the cabinet-connecting ports.

    When multiple sets of equipment are connected through the EHT and EHT-HUB

    ports on the SCC board, you should avoid any loop of the equipment.

    Tools

    Procedure

    Use network cables to connect the EHT port and the EHT-HUB port of the SCC

    board on multiple sets of equipment, as shown in the figure.

    Choose Configuration > Communication > ECC Management. Then the ECC

    Management page is displayed.

    Double-click ECC Extended Mode. Then, select Automatic and click Apply.

    1 2 3

    4 5 6

    1 2

    3 4

    5 6

    Tools

    Materials

    1.12 Config DataHuawei Confidential

    Copyright Huawei Technologies Co., Ltd. All rights reserved. Page 67

  • 12

    3

    4

    5

    1

    2

    3

    4

    MW Standard Operation Procedure for Axis Swap Project SN Task Description Operator Duration

    1.14AAlign the

    AntennasPreparationsAC(BD)

    Note

    90 minutes(Total)

    Procedure

    Follow the microwave antenna alignment principle;

    Determine the voltage values of the design receive level of the ODU, according to the

    ODU RSI-Vbnc Curve and the microwave design document. (The ODU RSI-Vbnc

    Curve is delivered with the ODU).

    Tools3

    3.5

    4

    4.5

    R

    S

    S

    I

    V

    o

    l

    t

    a

    g

    e

    (

    V

    )

    Choose area

    1

    2- 2-

    1.14 Align AntennasHuawei Confidential

    Copyright Huawei Technologies Co., Ltd. All rights reserved. Page 68

    1 2 3

    4 5 6

    1 2

    3 4

    5 6

    Materials

    Design document

    Tools

    Multimeter

    -100 -90 -80 -70 -60 -50 -40 -30 -200

    0.5

    1

    1.5

    2

    2.5

    3

    3.5

    4

    4.5

    RSL(dBm)

    R

    S

    S

    I

    V

    o

    l

    t

    a

    g

    e

    (

    V

    )

    Choose area

    1.14 Align AntennasHuawei Confidential

    Copyright Huawei Technologies Co., Ltd. All rights reserved. Page 68

  • 12

    3

    4

    5

    1

    2

    3

    4

    MW Standard Operation Procedure for Axis Swap Project SN Task Description Operator Duration

    1.14BAlign the

    AntennasConnect

    multimeter

    AC(BD) 90 minutes(Total)

    Note

    Procedure

    Set the maximum voltage that the multimeter can detect to DC 20 V, fix the

    multimeter to the tower for easy observation. Then, observe the voltage value of the

    receive level when you align the antennas;

    Remove the waterproof cap of the ODU RSSI port, connect the BNC connector to

    the ODU RSSI port;

    Connect the multimeter to the wire which connect the BNC connectorthen protect the wire by PVC tape.

    20V

    1 2-

    2- 3-

    1.14 Align AntennasHuawei Confidential