Soo Compressed Air Distribution System W911XK-12-R-0012

description

Soo Compressed Air Distribution System. W911XK-12-R-0012. Unrestricted procurement The NAICS code is 236210, with a Small Business Size Standard of $33.5 million in average annual receipts. Competition. Section 00100 – Instructions for submission of proposals - PowerPoint PPT Presentation

Transcript of Soo Compressed Air Distribution System

Page 1: Soo Compressed Air Distribution System

Soo Compressed Air Distribution System

W911XK-12-R-0012

Page 2: Soo Compressed Air Distribution System

• Unrestricted procurement

• The NAICS code is 236210, with a Small Business Size Standard of $33.5 million in average annual receipts.

Competition

Page 3: Soo Compressed Air Distribution System

• Section 00100 – Instructions for submission of proposals– Volume I: Past Performance Information

• Original and 4 copies– Volume II: Technical Capability Information

• Original and 4 copies– Volume III: Pricing Information

• Original and 1 copy

What to Submit

Page 4: Soo Compressed Air Distribution System

• Completed by Offeror:– Exhibit A, Past Performance Relevancy– Exhibit B, Subcontractor Info & Consent

• Completed by references:– Exhibit C, Past Performance Reference– Must be sent from references only

• Volume I must NOT contain pricing information

Volume I Past Performance

Page 5: Soo Compressed Air Distribution System

• Technical Proposal Contents:– Key Project Personnel Capabilities and

Experience– Organization and Technical Approach– Schedule– Subcontracting Program Performance

Volume II must NOT contain pricing information

Volume II Technical Capability

Page 6: Soo Compressed Air Distribution System

• Key Project Personnel Capabilities and Experience – Provide a consolidated list of key personnel with name, position title

and description of project responsibility for each • Indicate whether each individual has had a significant role in any

of the project examples• If reassignment of personnel is considered possible, provide

alternate professionals for each assignment– Include prime contractor’s project manager and on-site general

superintendent responsible for construction• For each person provide a brief resume at the end of the section

– Offerors shall provide letters of commitment from all proposed key personnel not currently employed by the team members

Volume II must NOT contain pricing information

Volume IITechnical Capability

Page 7: Soo Compressed Air Distribution System

• Organization and Technical Approach– Describe subcontractor and manufacturer resources– Describe proposed management structure for team– Describe the technical approach– Describe team’s quality control approach

• Schedule– Provide a schedule in chart format that demonstrates a

clear understanding of the work and an ability to coordinate resources to meet the RFP requirements

Volume II must NOT contain pricing information

Volume IITechnical Capability

Page 8: Soo Compressed Air Distribution System

• Subcontracting Program Performance– Provide a subcontracting plan which contains separate

dollar and percentage subcontracting goals with all administrative elements developed for this specific project

Volume II must NOT contain pricing information

Volume IITechnical Capability

Page 9: Soo Compressed Air Distribution System

Contents:• SF 1442, signed by an authorized representative of

the company• Proposed prices of each line item• Section 0600, Representations and Certifications• Make sure your registration is current at:

– Central Contractor Registration -- www.ccr.gov– Online Representations and Certifications -- orca.bpn.gov

Volume IIIPricing Information

Page 10: Soo Compressed Air Distribution System

• Carefully review sections:– 00100, Instructions, Conditions & Notices to

Offerors• Due date/time, method of submission, etc.

– 00110, Proposal Preparation Instructions• Proposal contents, format, length, etc.

– 00120, Proposal Evaluation & Basis for Award

Proposal Preparation

Page 11: Soo Compressed Air Distribution System

• RFP includes Davis-Bacon Wage Determination MI113

• A bid guarantee is required, 20% of bid or $3 million, whichever is less

• Performance and Payment Bonds in 100% of the contract value must be provided within 10 days after award.

• Subcontracting Plans for large businesses – in accordance with DFARS 252.219-7003 (will be added in a future amendment)

Proposal Preparation

Page 12: Soo Compressed Air Distribution System

• Proposals must be submitted in accordance with the RFP instructions; NO faxed or e-mailed proposals will be accepted.

• Failure to submit a complete proposal may result in removal from consideration for award.

Proposal Preparation

Page 13: Soo Compressed Air Distribution System

• “Best Value” Award Basis– “Best Value” is defined as an award based on the

greatest overall benefit to the Government in response to the requirement. Award is based on other factors in addition to price.

• Technical Capability and Past Performance are of equal importance, and, when combined, are approximately equal to Price

Proposal Evaluation

Page 14: Soo Compressed Air Distribution System

Proposal Evaluation – Past Performance

Confidence Rating Description Substantial Confidence Based on the offeror’s recent/relevant performance

record, the Government has high expectation that the offeror will successfully perform the required effort.

Satisfactory Confidence Based on the offeror’s recent/relevant performance record, the Government has reasonable expectation that the offeror will successfully perform the required effort.

Limited Confidence Based on the offeror’s recent/relevant performance record, the Government has a low expectation that the offeror will successfully perform the required effort.

No Confidence Based on the offeror’s recent/relevant performance record, the Govermnent has no expectation that the offeror will successfully perform the required effort.

Unknown Confidence (Neutral)

No recent/relevant performance record is available or the offeror’s performance record is so sparse that no meaningful confidence assessment rating can be reasonably assigned.

Page 15: Soo Compressed Air Distribution System

• Proposals will be given technical capability risk ratings based on the offeror’s technical approach, proposed schedule, qualifications and other considerations as described in the sub-factors, elements and other considerations. The four sub-factors are as follows:

• Key Project Personnel Capabilities and Experience• Organization and Technical Approach• Schedule• Subcontracting Program Performance

• The sub-factors are listed in descending order of importance • Evaluation will be at the factor level (i.e. rating will be given

for Technical Capability as a whole)• Ratings are source-selection sensitive

Proposal Evaluation -Technical

Page 16: Soo Compressed Air Distribution System

Proposal Evaluation -Technical

Color Rating Description Blue Outstanding Proposal meets requirements and indicates an exceptional

approach and understanding of the requirements. Strengths far outweigh any weaknesses. Risk of unsuccessful performance is very low.

Purple Good Proposal meets requirements and indicates a thorough approach and understanding of the requirements. Proposal contains strengths which outweigh any weaknesses. Risk of unsuccessful performance is low.

Green Acceptable Proposal meets requirements and indicates an adequate approach and understanding of the requirements. Strengths and weaknesses are offsetting or will have little or no impact on contract performance. Risk of unsuccessful performance is no worse than moderate.

Yellow Marginal Proposal does not clearly meet requirements and has not demonstrated an adequate approach and understanding of the requirements. The proposal has one or more weaknesses which are not offset by strengths. Risk of unsuccessful performance is high.

Red Unacceptable Proposal does not meet requirements and contains one or more deficiencies. Proposal is not awardable.

Page 17: Soo Compressed Air Distribution System

• Proposals will be given past performance risk ratings based on the relevance of past performance reference questionnaire responses and the Government’s own past performance rating system (CCASS).

• The five sub-factors are as follows:• Management Effectiveness• Quality Control• Timely Performance• Compliance with Safety Standards• Compliance with Federal laws and regulations

• The sub-factors are listed in descending order of importance • Evaluation will be at the factor level (i.e. rating will be given

for Past Performance as a whole)• Ratings are source-selection sensitive

Proposal Evaluation – Past Performance

Page 18: Soo Compressed Air Distribution System

Proposal Evaluation – Past Performance

• RELEVANCE– VERY RELEVANT - Projects involved the magnitude of

effort and complexities similar to this project.– RELEVANT - Projects involved less magnitude of effort

and complexities similar to this project– SEMI-RELEVANT - Projects involved much less

magnitude of effort and complexities similar to this project.

– NOT RELEVANT – Projects involved none or significantly less magnitude of effort and complexities than what this solicitation requires.

– Relevancy may affect an offeror’s overall Past Performance rating

Page 19: Soo Compressed Air Distribution System

• The Contracting Officer will e-mail the Award Notice to the awardee

• An award notice including the contract price and awardee name and address will be posted to FedBizOpps (www.fbo.gov)

• No information regarding unsuccessful proposals will be released

Award Procedures

Page 20: Soo Compressed Air Distribution System

• All Plans and Specifications are posted at FedBizOpps.

• It is a prime contractor’s responsibility to provide its subcontractors with copies of the plans and specifications.

Plans andSpecifications

Page 21: Soo Compressed Air Distribution System

• The Government intends to award without discussions - do not anticipate a chance to make corrections or changes.

• Your first proposal will probably be your only proposal.

• Read the solicitation requirements carefully. • Consider using Section 00120 to “rate”

yourself before submitting the proposal - Is it complete?

Important Reminders

Page 22: Soo Compressed Air Distribution System

• All RFP amendments will be posted on FedBizOpps (FBO)

• Check FBO regularly for changes• Be sure to register at FBO – this is the “bidders

mailing list” and you will get automatic notices of changes in most cases

• Proposal are due 31 May 2012, no extension is anticipated

• After the proposal due date, no information will be available until award

Important Reminders

Page 23: Soo Compressed Air Distribution System

• Questions must be submitted via email to [email protected] no later than 21 May 2012.

• Submit questions to the Contracting Office only, do not call other Government personnel.

• Questions received late may be held and addressed after the RFP closing with those who submitted offers

• Questions and Answers will be posted to FedBizOpps.

Questions

Page 24: Soo Compressed Air Distribution System

Questions?