SOLAR POWER DEVELOPMENT – VGF OPTION UNDER JNNSM 1 Dr. Ashvini Kumar Director (Solar) Solar Energy...

25
SOLAR POWER DEVELOPMENT – VGF OPTION UNDER JNNSM 1 Dr. Ashvini Kumar Director (Solar) Solar Energy Corporation of India

Transcript of SOLAR POWER DEVELOPMENT – VGF OPTION UNDER JNNSM 1 Dr. Ashvini Kumar Director (Solar) Solar Energy...

Page 1: SOLAR POWER DEVELOPMENT – VGF OPTION UNDER JNNSM 1 Dr. Ashvini Kumar Director (Solar) Solar Energy Corporation of India.

SOLAR POWER DEVELOPMENT – VGF OPTION UNDER JNNSM

1

Dr. Ashvini KumarDirector (Solar)

Solar Energy Corporation of India

Page 2: SOLAR POWER DEVELOPMENT – VGF OPTION UNDER JNNSM 1 Dr. Ashvini Kumar Director (Solar) Solar Energy Corporation of India.

SOLAR ENERGY CORPORATION OF INDIA

A Government of India Enterprise under the

administrative control of MNRE.

Incorporated on 20th September 2011.

Under Section-25 of the Companies Act, 1956.

“Not for profit” company.

Authorised capital of Rs 2,000 Cores

2

Page 3: SOLAR POWER DEVELOPMENT – VGF OPTION UNDER JNNSM 1 Dr. Ashvini Kumar Director (Solar) Solar Energy Corporation of India.

SECI Activities

Apart from the mission activities SECI is doing the following projects. Solar PV power plants. Solar Mini/Micro Grids Solar Thermal Power Plants Solar Water Heaters Solar Roof-Top Systems Solar Home lighting and Solar Street lights Hybrid projects

1. Solar + Gas

2. Solar + Biomass

3. Solar + Hydro/Pump Storage R&D activities.

3

Broad mandate : Implementing & Monitoring agency of JNNSMfrom “Concept to Commissioning”

Page 4: SOLAR POWER DEVELOPMENT – VGF OPTION UNDER JNNSM 1 Dr. Ashvini Kumar Director (Solar) Solar Energy Corporation of India.

JNNSM Road Map

Application Segment Target for Phase I

(2010-13)

Cumulative Target for

Phase 2 (2013-17)

Cumulative Target for Phase 3

(2017-22)

Grid solar power (large plants, roof top & distribution grid plants)

1,100 MW 10,000 MW 20,000 MW

Off-grid solar applications

200 MW 1,000 MW 2,000 MW

Solar Thermal Collectors (SWHs, solar cooking/ cooling, Industrial process heat applications etc.)

7 million sq. meters

15 million sq. meters

20 million sq meters

Solar Lighting System 5 million 10 million 20 million

4

Page 5: SOLAR POWER DEVELOPMENT – VGF OPTION UNDER JNNSM 1 Dr. Ashvini Kumar Director (Solar) Solar Energy Corporation of India.

Regulatory measures- RPO/REC

Supporting grid connected projects to bring volumes and

reduce prices

Financial support for off-grid

Support R&D in India

Encourage manufacturing

HR development

Policy and Regulatory Support5

Page 6: SOLAR POWER DEVELOPMENT – VGF OPTION UNDER JNNSM 1 Dr. Ashvini Kumar Director (Solar) Solar Energy Corporation of India.

Ground Measurement of Solar RadiationAndhra Pradesh 6

Gujarat 11

Haryana 1

Madhya Pradesh 3

Karnataka 5

Rajasthan 12

Chhattisgarh 1

Ladakh 1

Maharashtra 3

Pudducherry 1

Tamil Nadu 6• C-WET is implementing the project for

setting up 51 ground monitoring stations

• Centralized data collection, analysis and calibration of measuring sensors

6

Page 7: SOLAR POWER DEVELOPMENT – VGF OPTION UNDER JNNSM 1 Dr. Ashvini Kumar Director (Solar) Solar Energy Corporation of India.

State InitiativesS. No

State Solar Specific Programme

1. Gujarat Announced – 968.5 MWCommissioned – 857 MW

2. Maharashtra Commissioned – 100 MW (includes 40 MW setup in Rajasthan under RPO).Under installation: 150 MW at Sakri/ Dhule

3. Karnataka Commissioned – 8 MW , Approved plan for 200 MWBids invited/allotted– 70 MW, Min. tariff – Rs. 7.94/unit Bids to be invited-130 MW

4. Rajasthan Tendered – 200 MW, 75 MW at Rs. 6.45/Unit awarded

5. Odisha Announced -50 MW Awarded – 25 MW, Minimum tariff – Rs. 7/unit

Page 8: SOLAR POWER DEVELOPMENT – VGF OPTION UNDER JNNSM 1 Dr. Ashvini Kumar Director (Solar) Solar Energy Corporation of India.

State Initiatives (2)

S. No

State Solar Specific Programme

6. Uttar Pradesh

Announced – 500 MW till March 2017 (10 yr PPA)First Phase – 200 MW

7. Andhra Pd. Policy announced in November 2012 for 1000 MW (1 – 5 MW, Rs.6.49/Unit)

8. Tamil Nadu Announced – 3000 MW Tendered-1000 MWBids received - 498 MW(60 MW bids < Rs 7: 200 MW bids - Rs 7 to 8; 141 MW bids between Rs 8 and Rs 10; 75 MW bids > Rs 10.

9. Madhya Pradesh

Awarded– 200 MWMinimum tariff – Rs. 7.90/unit (Alpha-20 MW), Rs 8.05/Unit (Welspun – 125MW)

Page 9: SOLAR POWER DEVELOPMENT – VGF OPTION UNDER JNNSM 1 Dr. Ashvini Kumar Director (Solar) Solar Energy Corporation of India.

Growth of Solar Capacity (MW)

2008-09 2009-10 2010-11 2011-12 2012-130

200

400

600

800

1000

1200

1400

1600

1800

3 11 36

936

1684

So

lar

Ca

pa

cit

y (

MW

)

State MWp %Gujarat 857.9 50.96Rajasthan 551.2 32.74Maharashtra 100.0 5.94Madhya Pradesh 37.3 2.22Andhra Pradesh 23.2 1.38Uttar Pradesh 17.4 1.03Tamil Nadu 17.1 1.01Jharkhand 16.0 0.95Karnataka 14.0 0.83Orissa 13.0 0.77Punjab 9.3 0.55Haryana 7.8 0.46A & N Island 5.1 0.30Uttarakhand 5.1 0.30Chhattisgarh 4.0 0.24Delhi 2.6 0.15West Bengal 2.1 0.12Lakshadweep 0.8 0.04

Page 10: SOLAR POWER DEVELOPMENT – VGF OPTION UNDER JNNSM 1 Dr. Ashvini Kumar Director (Solar) Solar Energy Corporation of India.

MNRE Strategy for Phase II10

Award of capacity to be spread out over Initial two years of plan period as: It facilitates planning for manufacturers as well as

developers Learning from prior development would be available for

subsequent bids Benefits of cost reduction could be achieved More states could come up the curve to participate in

the process Maximize chances of achieving targets within desired

timelines Preferably bidding process for allocation of target capacity to

end before 2015-16 Lower dependence on Bundling

Page 11: SOLAR POWER DEVELOPMENT – VGF OPTION UNDER JNNSM 1 Dr. Ashvini Kumar Director (Solar) Solar Energy Corporation of India.

Domestic Content – Key for Phase II

11

Development of 4-5 GW of manufacturing capacity is one of the objectives of JNNSM

Current manufacturing capacity (SPV): ~2000 MW (Module)

Cheaper international loans available with imported components

DCR conditions under schemes entailing direct funding support by Central Government could facilitate development of domestic manufacturing capacity base.

Page 12: SOLAR POWER DEVELOPMENT – VGF OPTION UNDER JNNSM 1 Dr. Ashvini Kumar Director (Solar) Solar Energy Corporation of India.

Policy Initiatives for Further Growth in Solar Power Capacities

• Policy hallmark during Phase 1 was bundling of solar power with cheap thermal power

• Phase 2 envisages to reach 10 GW utility scale solar power capacity by March 2017.

• 4 GW under central scheme and 6 GW under various State specific schemes.

• Other Schemes are• Grid Connected Roof Top Solar PV Power systems• CSP Pilot Projects

• Provision of Viability Gap Funding (VGF)

• Bundling is subject to availability of unallocated thermal power

12

Page 13: SOLAR POWER DEVELOPMENT – VGF OPTION UNDER JNNSM 1 Dr. Ashvini Kumar Director (Solar) Solar Energy Corporation of India.

Draft Features of VGF Scheme

Tariff to be paid to the developer : Rs.5.45/kWh, fixed for 25 years 10% less viz., Rs. 4.95/kWh for projects

availing benefit of Accelerated Depreciation

Payment of VGF up to 30% of project cost limited to Rs. 2.5 cr./

MW, through competitive bidding.

Developer’s equity Minimum Rs.1.5 cr./MW

Balance can be raised as Loan.

13

Page 14: SOLAR POWER DEVELOPMENT – VGF OPTION UNDER JNNSM 1 Dr. Ashvini Kumar Director (Solar) Solar Energy Corporation of India.

Release of VGF amount

VGF to be released in three tranches-

– 25% at the time of delivery of at least 50% of major equipment at site;

Weightage: Modules -40%PCUs -20%Switchgear & Transformer -20%

Mounting Structures-20%

14

Page 15: SOLAR POWER DEVELOPMENT – VGF OPTION UNDER JNNSM 1 Dr. Ashvini Kumar Director (Solar) Solar Energy Corporation of India.

Release of VGF amount

50% on successful commissioning;

Balance 25% after 1 year of commissioning meeting requirements of generation

If during PPA duration of 25 years:– the project fails to function at any time, or – its assets are sold, or – the project is dismantled,

SECI will have right to claim assets equal to VGF paid. Legal documentation to be prepared by SECI.

15

Page 16: SOLAR POWER DEVELOPMENT – VGF OPTION UNDER JNNSM 1 Dr. Ashvini Kumar Director (Solar) Solar Energy Corporation of India.

Min. & Max. Capacity

Min. Capacity of each project – 10 MW

Max. capacity – 50 MW

Max. 3 projects at different locations by one developer, subject to a max. of 100 MW.

Capacity will be the AC output at the project bus bar located within project premises.

16

Page 17: SOLAR POWER DEVELOPMENT – VGF OPTION UNDER JNNSM 1 Dr. Ashvini Kumar Director (Solar) Solar Energy Corporation of India.

Grid connectivity

Inter-connection with Transmission network of STU/CTU/any other Utility at level of 33 KV or above.  

Developer to submit along with Bid a letter from STU / CTU/ Transmission Utility confirming technical feasibility of connectivity of plant to substation.

Transmission of power up to interconnection point where metering is done for energy accounting, to be responsibility of Developer at own cost.

17

Page 18: SOLAR POWER DEVELOPMENT – VGF OPTION UNDER JNNSM 1 Dr. Ashvini Kumar Director (Solar) Solar Energy Corporation of India.

Grid connectivity (contd.)

Option of Pooling Point where more than one SPV projects may connect

Common Transmission Line (CTL) to further connect Pooling Point to the Interconnection/Metering point.CTL to be built and operated by the developer/any third party/by STU on behalf of developer.

Metering to be done at the Interconnection Point along with subsidiary meters at the Pooling Point to determine the generation by each project.

18

Page 19: SOLAR POWER DEVELOPMENT – VGF OPTION UNDER JNNSM 1 Dr. Ashvini Kumar Director (Solar) Solar Energy Corporation of India.

Tentative Schedule

No. Event Date

1 Request for Selection (RfS) notice May 2013

2 Receipt of applications against RfS

1st Week June 2013

3 Short-listing of projects based on applications received and evaluation of bids

Mid August 2013

4 Issue of Letter of Intent (LOI) 1st Week Sept 2013

6 Signing of PPA 1st Week Oct 2013

7 Financial Closure By April 2014

8 Commissioning of projects By December 2014

19

Page 20: SOLAR POWER DEVELOPMENT – VGF OPTION UNDER JNNSM 1 Dr. Ashvini Kumar Director (Solar) Solar Energy Corporation of India.

Pilot Solar Thermal Power Projects

• JNNSM document envisages setting up pilot projects to address issues related to optimization and use of improved/advanced technology options- Advanced technology configurations which could lead to cost

reduction through higher efficiency and CUF, and scale effect

- Reduction in water consumption and footprint land area in solar thermal projects

- Potential for replication in commercial projects soon after success of demonstration projects

- Potential for indigenous manufacturing

• MNRE constituted a multi-stakeholders Group in January 2011 to discuss and suggest technology configurations

Page 21: SOLAR POWER DEVELOPMENT – VGF OPTION UNDER JNNSM 1 Dr. Ashvini Kumar Director (Solar) Solar Energy Corporation of India.

Project Configurations and SitesBased on recommendations of the stakeholders group and site visits by experts, identified pilot projects to have the following configurations:

Project Configuration Identified sites and Broad Specifications

With hybrid coolingReduced (<= 30%) consumption of water

Bhadla (Rajasthan)Available Land Area: 150 haCapacity: 40 MW est. CUF: 29% est.

High operating temperature (>=500ºC)Higher efficiency

Charanka (Gujarat)Available Land Area: 140 haCapacity: 35 MW est. CUF : 30% est.

Large thermal storage(about 8 hours)

Terkuveerapandiyapuram (Tamil Nadu)Available Land Area: 160 haCapacity: 25 MW est. CUF : 45% est.

Large thermal storageBase load

Nennala (Andhra Pradesh)Available Land Area: 160 haCapacity: 20 MW est. CUF : 65% est.

Page 22: SOLAR POWER DEVELOPMENT – VGF OPTION UNDER JNNSM 1 Dr. Ashvini Kumar Director (Solar) Solar Energy Corporation of India.

Project Details Solar Energy Corporation of India to implement the project Target tariff of solar power – Rs 5.83/ Unit for 25 Years Project selection through ICB for viability gap funding Framework of Support

At least 20% of the project cost to come as equity from the project developer.

Debt portion could comprise of at the most 50% of the project cost from CTF / ADB;

The maximum amount of VGF would be upto 40% of the project cost.

Estimated project cost = Rs. 2,555 Crore NCEF Committee Chaired by Expenditure Secretary

approved the project with Rs. 1020 crore of support

Page 23: SOLAR POWER DEVELOPMENT – VGF OPTION UNDER JNNSM 1 Dr. Ashvini Kumar Director (Solar) Solar Energy Corporation of India.

Roof Top Solar PV Power Projects Grid connected Rooftop Projects to be supported by grant as

capital subsidy for self consumption of Solar Electricity and feeding extra power to grid whenever available.

Basic aim is to mitigate consumption of diesel.

The scheme is implemented in two modes, viz., Capital Grant @ 30% of project cost, and RESCO mode with some grant and a provision of tariff from the consumer.

Scheme is implemented by SECI through competitive bidding in select cities.

Project size to be 100 kW to 500 kW, however, aggregation of capacity from smaller projects is allowed.

Balance cost is to be met by the consumer.

Grid connectivity and metering is to be in accordance with CEA guidelines or SERC’s regulations.

Page 24: SOLAR POWER DEVELOPMENT – VGF OPTION UNDER JNNSM 1 Dr. Ashvini Kumar Director (Solar) Solar Energy Corporation of India.

Status of Implementation

• Phase-I already started with the following allocations: Chennai – 2 MW Bangalore – 2 MW Delhi – 1 MW Gurgaon – 0.5 MW

• Phase-II: Bids invited for a capacity of 11.1 MW: Jaipur – 3.1 MW Bhubaneswar – 1 MW Hyderabad – 2 MW Gurgaon – 1.5 MW NOIDA/ Gr. NOIDA – 1.5 MW Raipur – 2 MW

Page 25: SOLAR POWER DEVELOPMENT – VGF OPTION UNDER JNNSM 1 Dr. Ashvini Kumar Director (Solar) Solar Energy Corporation of India.

Thank You !

25