SPPS INAUGURATION 30 OCTOBER 2009
SOL PLAATJE POWER STATION
SOL PLAATJE DAM
BETHLEHEM
. . . . . . IT IS NOT JUST ABOUT THE MEGAWATTS !!!
SPPS INAUGURATION 30 OCTOBER 2009
INTRODUCTION TO THE BETHLEHEM HYDRO PROJECT
. . . . . . IT IS NOT JUST ABOUT THE MEGAWATTS !!!
!! Welcome to the Bethlehem Hydro Inauguration Ceremony !!
Bethlehem Hydro is a unique project which has overcome several challenges and has
set a precedent in the development of small hydropower projects in South Africa
Some of the milestones achieved include:
• First commercial hydropower station implemented in South Africa in the last 22 years
• Obtaining the first water use license from the Department of Water Affairs under the
Water Act (No 36 of 1998) for an Independent Power Producer
• Obtaining a generation license from the National Electricity Regulator of South Africa
for operation as a first Independent Power Producer for hydropower
• Power Purchase Agreement with the Dihlabeng Local Municipality
• “Competing” on commercial terms with Eskom
• Kaplan turbines used in South Africa for the first time
• BEE partnership through Women in Oil and Energy South Africa (WOESA)
SPPS INAUGURATION 30 OCTOBER 2009
HISTORY OF BETHLEHEM HYDRO
. . . . . . IT IS NOT JUST ABOUT THE MEGAWATTS !!!
1999 Project identified by MBB Consulting Engineers following their previous
involvement in the development of the Freidenheim Hydropower Plant (1987)
2000 Preliminary study conducted by Nu Planet in order to determine viability of
potential scheme
2001 Request for grant funding through the Dutch Government (AIJ Pilot Program),
which was developed following the Kyoto Protocol’s Clean Development
Mechanism
2002 Feasibility Study and Environmental Impact Study undertaken by Ninham
Shand (now Aurecon) in association with BWG Hydro & Merz Mclellan.
Two schemes were identified, one along the Ash River and one at Saulspoort
Dam (now Sol Plaatje Dam)
2002 Project was judged viable which started the licensing process (Water Use
License, Generation License, ROD), most of which had to be obtained under
new Regulations (No precedent existed drafted from scratch)
2003 Bethlehem Hydro (Pty) Ltd was created as a special purpose vehicle to
develop the project
SPPS INAUGURATION 30 OCTOBER 2009
HISTORY OF BETHLEHEM HYDRO (..Cont)
. . . . . . IT IS NOT JUST ABOUT THE MEGAWATTS !!!
2005 Power Purchase Agreement drafted between Bethlehem Hydro and the
Bethlehem Municipality (No precedent existed drafted from scratch)
2005 Water Use License and Generation License granted to Bethlehem Hydro
2005 Aurecon (formerly Ninham Shand) in association with BWG Hydro & Merz
Mclellan appointed to undertake the detailed design of the schemes
2006 Prequalification for the supply of turbines followed by a Tender process,
Contract BH1, awarded to Boving Fouress Limited (India)
2006 Tender for Civil Work, Contract BH2, awarded to Eigenbau (Pty) Ltd
2007 Tender for Transmission Line, Contract BH3, awarded to EDS Electrical
2008 Delivery of Turbines to site
2009 Completion & Commissioning of the Sol Plaatje Plant
SPPS INAUGURATION 30 OCTOBER 2009
Organisations Involved
. . . . . . IT IS NOT JUST ABOUT THE MEGAWATTS !!!
Responsible for the management of the Ash River
Water Use License, License to Alter an Existing Dam
Generation License
Environmental Impact Assessment
Power Lines & Transformer to the Merino site
Power Purchase Agreement, Local Support, Land Acquisition
Loan for implementation
Funding & Support
SPPS INAUGURATION 30 OCTOBER 2009
Project Organogram
. . . . . . IT IS NOT JUST ABOUT THE MEGAWATTS !!!
Electrical
SubConsultant
BWG HYDRO
Mechanical
SubConsultant
Contract BH1
Supply of Turbines, Generators
and Auxiliary Equipment
Contract BH2
Civil Works & Erection of
Turbines, Generators & Auxiliary
Equipment
Contract BH3
Transmission Lines
SPPS INAUGURATION 30 OCTOBER 2009
Characteristics of the Sol Plaatje Power Station
. . . . . . IT IS NOT JUST ABOUT THE MEGAWATTS !!!
Sol Plaatje Dam Full Supply Level 1627.26 masl
Tailwater Level (Varies) 1616.50 masl
Gross Head 10.76 m
Rated Flow 25 m3/s
Maximum Flow 29 m3/s
Rated Generator 2.55 MW
Annual Generation Approx 19 GWhr/Ann
Load Factor (% time the plant runs at rated capacity) 80%
Lowest Founding Level below Tailwater 10 m
Weight of Generator 30 t
Diameter of Turbine 3.14 m
Turbine Type Full Kaplan
Construction Period 27 months
Total Cost (Approximated) R 40 Million
SPPS INAUGURATION 30 OCTOBER 2009
Power Station Details
. . . . . . IT IS NOT JUST ABOUT THE MEGAWATTS !!!
Dam Level
Tailwater
Level
Turbine
Generator
SPPS INAUGURATION 30 OCTOBER 2009
Power Station Details
. . . . . . IT IS NOT JUST ABOUT THE MEGAWATTS !!!
Dam
Tail water
Generating
Head
SPPS INAUGURATION 30 OCTOBER 2009
Capacity of the Plant
. . . . . . IT IS NOT JUST ABOUT THE MEGAWATTS !!!
The plant capacity is equivalent to 3 of these 18 000 ℓ water tankers going though
the turbine every 2 seconds
SPPS INAUGURATION 30 OCTOBER 2009
Construction Progress
. . . . . . IT IS NOT JUST ABOUT THE MEGAWATTS !!!
Original
Ground Level
Excavation
65% Hard
35% Soft
Approx 16m
SPPS INAUGURATION 30 OCTOBER 2009
Construction Progress (Excavation)
. . . . . . IT IS NOT JUST ABOUT THE MEGAWATTS !!!
May 2007
July 2007
October 2007
SPPS INAUGURATION 30 OCTOBER 2009
Construction Progress (Power Station)
. . . . . . IT IS NOT JUST ABOUT THE MEGAWATTS !!!
November
2007Turbine draft
tube
April 2008
July 2008December 2008
April 2009
SPPS INAUGURATION 30 OCTOBER 2009
Benefits of the Project (Sol Plaatje Site)
. . . . . . IT IS NOT JUST ABOUT THE MEGAWATTS !!!
Labour Relations
Total No. of Staff Employed 60
No. of staff from the Local Municipality 38
% of Local Staff used (including Sub-Contractors) 63%
Estimated No of Man-Days (Local Staff Only) 13 000
Boost to the Local Economy
Estimated Amount Spent on Local Suppliers R 2.5 Million
Estimated Amount Spent on Local Sub-Contractors R 0.4 Million
Other Amounts Spent in Local Economy (Accommodation,
Transport, Food, etc)R 0.3 Million
Occupational Health & Safety
Fatalities on Site None
Injuries leading to Permanent Disability None
Minor Injuries (Sprains, broken arm, etc.) 12
SPPS INAUGURATION 30 OCTOBER 2009
Lessons Learnt
. . . . . . IT IS NOT JUST ABOUT THE MEGAWATTS !!!
Geology Due to lack of funds at the initial stage of the project, limited
geological and geotechnical investigations were carried out which
caused some delay during construction
Design The actual project varies significantly from what was identified during
the feasibility stage due to design improvements and to maximise the
output
Timing Nearly three years were required for all licenses and agreements
before construction could commence
Cash Flow Cash flow is very important as lack of funds can create major delays
during the construction process
Contractors Having contractors with the right attitude contributed largely to this
success story
Teamwork Without a team effort, this project would not have been a success
SPPS INAUGURATION 30 OCTOBER 2009
The Way Forward
. . . . . . IT IS NOT JUST ABOUT THE MEGAWATTS !!!
Sol Plaatje 2.55 MW - Completed July / August 2009
Merino 3.4 MW – Completion expected in December 2009, commissioning
expected in early 2010
New Projects 8.5 MW & 3.5 MW - Feasibility Study underway. Commissioning
expected mid 2011
Future Projects? Other prospective sites have been identified and are currently being
pursued
THANK YOU