Software Project Management
-Web server development-
Ioana Jivet, CTI, 4th year
![Page 2: Software project management](https://reader033.fdocuments.net/reader033/viewer/2022051513/54576b3daf795900058b802a/html5/thumbnails/2.jpg)
Goal: develop a web server, along with a Graphical User Interface
Maximum duration: 1 month
Human resources: Team leader: Mihai Analysts: Andreea, Vlad Developers: Mihai, Cristina Testers: Mihai, Cristina
Project overview
![Page 3: Software project management](https://reader033.fdocuments.net/reader033/viewer/2022051513/54576b3daf795900058b802a/html5/thumbnails/3.jpg)
1. Requirements analysis – client meetings 2. System’s architectural design 3. Implementation 4. Testing 5. Delivery
Project phases
![Page 4: Software project management](https://reader033.fdocuments.net/reader033/viewer/2022051513/54576b3daf795900058b802a/html5/thumbnails/4.jpg)
Project phases
![Page 5: Software project management](https://reader033.fdocuments.net/reader033/viewer/2022051513/54576b3daf795900058b802a/html5/thumbnails/5.jpg)
Phase 1 – Requirements analysis
The requirements analysis phases includes gathering information from the clients, along with the definition of use case scenarios. A sub-phase represents the design of the architecture of the system.
Total time allocated: 9 days Assigned human resources: Andreea and Vlad
![Page 6: Software project management](https://reader033.fdocuments.net/reader033/viewer/2022051513/54576b3daf795900058b802a/html5/thumbnails/6.jpg)
Phase 2 - Implementation
![Page 7: Software project management](https://reader033.fdocuments.net/reader033/viewer/2022051513/54576b3daf795900058b802a/html5/thumbnails/7.jpg)
This phases consists of two sub-phases◦ 1. Back-end development and testing◦ 2. Front-end (GUI) development and testing
Before the 2nd milestone is reached, the integration of the two modules is done.
Total time allocated: 6 days Assigned human resources: Cristina and
Mihai
Phase 2 - Implementation
![Page 8: Software project management](https://reader033.fdocuments.net/reader033/viewer/2022051513/54576b3daf795900058b802a/html5/thumbnails/8.jpg)
Phase 3 - Testing
Four types of testing and a final bug report
Total time allocated: 3.5 days Assigned human resources: Cristina and
Mihai
![Page 9: Software project management](https://reader033.fdocuments.net/reader033/viewer/2022051513/54576b3daf795900058b802a/html5/thumbnails/9.jpg)
Phase 4 - Delivery
Delivery consists of two tasks: developing the install package and finalizing the documentation.
Total time allocated: 2 days Assigned human resources: Andreea and Vlad
![Page 10: Software project management](https://reader033.fdocuments.net/reader033/viewer/2022051513/54576b3daf795900058b802a/html5/thumbnails/10.jpg)
Project timeline
![Page 11: Software project management](https://reader033.fdocuments.net/reader033/viewer/2022051513/54576b3daf795900058b802a/html5/thumbnails/11.jpg)
Working calendar: 8:00 – 17:00, Mo-Fr; Sa and Su are free.
Total of working hours:
Working hours
![Page 12: Software project management](https://reader033.fdocuments.net/reader033/viewer/2022051513/54576b3daf795900058b802a/html5/thumbnails/12.jpg)
Open Proj is an easy to use project management software.
This tools allows you to rapidly define tasks, task flow, allocate resources and estimate completion time and costs.
Conclusions