SMOV3B

SMOV3B PROGRESS

As of 20 March

TIPS 21Mar02Carl Biagetti/NISD

Page 2: SMOV3B SMOV3B PROGRESS As of 20 March TIPS 21Mar02 Carl Biagetti/NISD.

TIPS 21Mar02Carl Biagetti

Page 2

SMOV3B

LAUNCH: 01 Mar. 2002, 06:22 a.m., ESTRELEASE: 09 Mar. 2002, 05:03 a.m., EST

SM3b installations with priorities Italics indicates SMOV verification activities.

1. Reaction Wheel (RWA)2. Solar Array III and Diode Boxes3. Power Control Unit (PCU)4. ACS5. NCS/ESM/Radiator/CPL

7. MLI Bays 5&6

Not installed 6. Gyros 7. MLI Bays 7&8

Page 3: SMOV3B SMOV3B PROGRESS As of 20 March TIPS 21Mar02 Carl Biagetti/NISD.

TIPS 21Mar02Carl Biagetti

Page 3

SMOV3B

SMOV3b PLAN

• MEASURE/MONITOR NEW SPACECRAFT BEHAVIOR• POINTING, THERMAL, POWER

• RECOMMISSION EXISTING SIs• STIS, WFPC2

• COMMISSION NEW SIs• ACS

• Science/EROs in early April

• REVIVE NICMOS• VIA NCS COOLDOWN• Science/EROs in mid/late April

Page 4: SMOV3B SMOV3B PROGRESS As of 20 March TIPS 21Mar02 Carl Biagetti/NISD.

TIPS 21Mar02Carl Biagetti

Page 4

SMOV3B

SMOV3b PLAN THROUGH MARCHTask Name

WFPC2 SCIENCE ENABLE

SM3B MISSION

BRIGHT EARTH AVOIDANCE (BEA)

HST RELEASE

HST RELEASE

(PCS1) FHST FOV TEST

STIS NOISE TEST (POST-BASELINE)

(PCS2) GYRO BIAS DETERMINATION

(PCS3) ATTITUDE INITIALIZATION

(PCS4) FHST/FHST ALIGNMENT

9002 ACS02 - ACS LOAD & DUMP ON-BOARD MEMORY

8949 (WFPC2/1) WFPC2 PROTECT DECON

8957 STIS01 STIS CCD FUNCTIONAL

8994 (FGS01) GUIDE STAR ACQ (FGS 1&3)

8999 (FGS06) PRE-NCS JITTER TEST

9003 ACS03 - ACS SCIENCE DATA BUFFER CHECK

9006 ACS06 - ACS CCD TEMP SET POINT DETERM

8958 STIS02A PRE-NCS IMAGE QUALITY

8959 STIS03 STIS MAMA DARK vs. TEMP

8963 STIS 7 CCD BIAS IMAGES

8964 STIS08 CCD DARKS

8968 (PCS08) VEH DISTURB TEST (ACS FW & NCS ACT)

9005 ACS05 - ACS CCD FUNCTIONAL

8961 STIS05 FIRST END-BEA TEST

8960 STIS04A PRE-NCS JITTER TEST

FGS/FHST HV OFF

NCS FILL PROCEDURE

8967V1 NCS01 START NCS CPL

STIS MAMA HV RESTRICTION

8967 NCS01 NCS ACTIVATION & NICMOS COOLDOWN

8968 VDT visits 31-33

8947 ACS05 ACS DAILY TEST

8961 STIS05 SECOND END-BEA TEST

8945 NCIMOS10 - NICMOS TEMP STABILITY

8958 STIS02B POST-NCS IMAGE QUAL CHK

BEA COMPLETE

8968 VEHICLE DIST'B'CE TEST (+V3)

8968 VEHICLE DIST'B'CE TEST (-V1)

9013 ACS13 - ACS COARSE ALIGNMENT

STIS CCD SCIENCE ENABLE

8950 (WFPC2/2) WFPC2 UVMON, COOL-DOWN, CONTAM MON, FOCUS CHK

8952 (WFPC2/5) WFPC2 FLAT FIELD CALIBRATION

8951 (WFPC2/4) WFPC2 LYMAN ALPHA CHECK

NICMOS "HOT" ATTITUDE

8960 STIS04B POST-NCS JITTER TEST

8944 NICMOS01 FW TESTS 1-7

3/27

3/9

3/9

3/22

3/22

3/22

3/22

F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S

Mar 3, '02 Mar 10, '02 Mar 17, '02 Mar 24, '02 M

Page 5: SMOV3B SMOV3B PROGRESS As of 20 March TIPS 21Mar02 Carl Biagetti/NISD.

TIPS 21Mar02Carl Biagetti

Page 5

SMOV3B

SMOV - so far BEA completes today

ACS – on schedule and nominal

STIS – on schedule & nominal 2nd end bea test removed

WFPC2 – on schedule & nominal (in PROTECT DECON) 23MAR - Cooldown and UV monitor to begin

NICMOS – Nominal Cooling down NCS fails first two start-up attempts => 2 day delay Cooldown rate is uncertain as of (20mar)

FGS – Nominal BEA science

Page 6: SMOV3B SMOV3B PROGRESS As of 20 March TIPS 21Mar02 Carl Biagetti/NISD.

TIPS 21Mar02Carl Biagetti

Page 6

SMOV3B

MAJOR SMOV MILESTONES (UPDATED AS OF 20 MARCH)

Release 09 March

NICMOS Cooldown 18-27 (tbd) March (NOMINAL 10-DAY COOLDOWN)

STIS Basic GO Science 22 March (No MAMA during initial NICMOS cooldown)

WFPC2 Cooldown 22 March

WFPC2 GO Science 26 March

ACS ALIGN 22 March – 7 April (may be accelerated 2-3 days)

ACS EROs 08-11 April “ “ “

ACS Basic GO Science (CCD) 11 April “ “ “

NICMOS Filter Wheel Test 28 March – 04 April (may be delayed ~ 1 week)

NICMOS Alignment (PAM adjust) 05 April – 12 April “ “ “

NICMOS EROs 20-24 April “ “ “

NICMOS Basic GO Science 20 April (without fine aperture locations)

SMOV Complete 27 July (ACS/NIC coronographs enabled)