Smoke extraction in buildings

59
SMOKE EXTRACTION IN BUILDINGS Presented by Vysakh Manohar GATE-Chennai 12/25/21 1 Smoke Extraction In Buildings

description

 

Transcript of Smoke extraction in buildings

Page 1: Smoke extraction in buildings

Monday, April 10, 2023 Smoke Extraction In Buildings 1

SMOKE EXTRACTION IN BUILDINGS

Presented by

Vysakh Manohar

GATE-Chennai

Page 2: Smoke extraction in buildings

Monday, April 10, 2023 Smoke Extraction In Buildings 2

INTRODUCTION

• Effective smoke extraction in buildings has been one of the inevitable considerations in the building design as the number of buildings and the concern of people about the regular fire accidents in buildings are increasing much.

• This presentation includes a brief description about the different design consideration principles and methods to be taken care for the effective heat extraction in different types of buildings .

Page 3: Smoke extraction in buildings

Monday, April 10, 2023 Smoke Extraction In Buildings 3

What is smoke?

• By product of combustion or pyrolysis .• Mixture of liquid , solid particulate matter and

gaseous products.• It is a cocktail of carbon monoxide, carbon

dioxide ,HCL and HCN

Page 4: Smoke extraction in buildings

Monday, April 10, 2023 Smoke Extraction In Buildings 4

FIRE TIME LINE• 00.00- Household is asleep• 00.30- Fire ignites and grows in downstairs• 1.04- Fire spreads and smoke begins to fill

In the room.• 1.35- Smoke layer descends rapidly and temperature exceeds 88 deg• 1.50 – Smoke detector sounds an alarm.• 2.30- Temperature becomes 205 deg• 2.48- smoke pours into other rooms

Page 5: Smoke extraction in buildings

Monday, April 10, 2023 Smoke Extraction In Buildings 5

• 3.03-Temperature in the room becomes more than 260 deg

• 3.20-upstairs,corridors,all the rooms are filled with smoke

• 3.41- flashover occurs , temperature becomes 760 deg

• 3.50 –Two minutes after the alarm sound, only the second exit will be the way out

• 4.33- Flames will be apparent from the outside , the first evidence of fire visible from outside.

Page 6: Smoke extraction in buildings

Monday, April 10, 2023 Smoke Extraction In Buildings 6

• Will follow similar scenario in other location• The variations will be based on 1-fire size 2-size of building 3-flammable materials in the building 4-alarm systems 5-safety measures available

Page 7: Smoke extraction in buildings

Factors affected

1. Design fire size2. Stack and wind effects3. Temperature effect of fire4. HVAC and ventilation systems5. Climate6. Expansion of ducts

GETTING THE DESIGN RIGHT FROM THE BEGINNING

Page 8: Smoke extraction in buildings

Monday, April 10, 2023 Smoke Extraction In Buildings

COMMON SAFETY METHODS

• Use sprinklers• Smoke curtains• HVAC system incorporating F & S dampers.• Extraction fans• Alarm systems• Pressurisation

8

Page 9: Smoke extraction in buildings

Monday, April 10, 2023 Smoke Extraction In Buildings 9

HAZARDS OF DANGEROUS SMOKE• Impair visibility• Coughing,nausea,vomiting• Generation of high temperature• Irritation and respiratory problems• Bronchospasms and hypoxia• Inflict death if it contains dangerous gases• Even low concentration of CO can cause diminished

coordination and increased disorientation• Amount of oxygen is reduced- suffocation• Exacerbate corrosive nature of HCL

Page 10: Smoke extraction in buildings

Monday, April 10, 2023 Smoke Extraction In Buildings 10

Smoke Pathways

• Air and service ducts connecting floors

• HVAC/ventilation systems • Extract duct systems

• Gaps between wall and floor constructions

• Stairwells

• Lift shafts

Page 11: Smoke extraction in buildings

Monday, April 10, 2023 Smoke Extraction In Buildings 11

Need of smoke extraction

• for life safety and reducing property loss

• for fire fighter access

• To clear smoke after a fire –smoke purging

Page 12: Smoke extraction in buildings

Monday, April 10, 2023 Smoke Extraction In Buildings 12

Smoke extraction design objectives

• Effective protection of building occupants by maintaining tenable conditions on egress systems.

• Reliable and functional fire fighting controls used by firefighters to increase visibility and reduce heat exposure.

Page 13: Smoke extraction in buildings

Monday, April 10, 2023 Smoke Extraction In Buildings 13

Make up air routes

• External doors• Louvers in wall or roof• Central air plant configured to supply air• From adjacent unaffected areas

→avoid mixing of smoke and make up air→extraction points-avoid creation of “hole”

Page 14: Smoke extraction in buildings

Monday, April 10, 2023 Smoke Extraction In Buildings 14

Smoke Production and movement

• Amount of smoke produced is dependent on size of fire

• Path through which it goes• Plume height

Page 15: Smoke extraction in buildings

Monday, April 10, 2023 Smoke Extraction In Buildings 15

Fundamental design factors

1. Design fire size2. Smoke layer depth3. Identify smoke reservoirs4. Calculate smoke volume and temperature5. Minimum number of extract points6. Vent or fan size and fan temperature rating7. Inlet air8. Duct work

Page 16: Smoke extraction in buildings

Monday, April 10, 2023 Smoke Extraction In Buildings 16

Design fire size

• Fire starts small and becomes large• Vent area=2.5 % of floor area-otherwise

mechanical• 6 ac/hour is used often• Design fire size is greatly dependent on building

contents.• Based on the largest fire source• Cannot surely withstand post flash over

conditions

Page 17: Smoke extraction in buildings

Monday, April 10, 2023 Smoke Extraction In Buildings 17

Heat output of fire

• National bureau of standards in USA• Based on time-• safe escape time• brigade response time

Page 18: Smoke extraction in buildings

Monday, April 10, 2023 Smoke Extraction In Buildings 18

Acceptable smoke layer depth

• Smoke layer base should be above the people• 2.5 m-single storey• 3 m - upper storey of 2 storey

Page 19: Smoke extraction in buildings

Monday, April 10, 2023 Smoke Extraction In Buildings 19

Smoke reservoirs

• If smoke is held in a too large reservoir-lose buoyancy

• 2000 m^2 - natural extraction• 2600 m^2 -powered extraction• Smoke curtains can be used to reduce

horizontal spread

Page 20: Smoke extraction in buildings

Monday, April 10, 2023 Smoke Extraction In Buildings 20

Page 21: Smoke extraction in buildings

Monday, April 10, 2023 Smoke Extraction In Buildings 21

Smoke- volume, mass flow rate and temperature

• T=Q/m cp

• 1/3 is gained by building structure

Page 22: Smoke extraction in buildings

Monday, April 10, 2023 Smoke Extraction In Buildings 22

Minimum no of extract points

• M cr is not exceeded• No smoke need to travel more than 30 m to

extraction point

Page 23: Smoke extraction in buildings

Monday, April 10, 2023 Smoke Extraction In Buildings 23

Inlet air

• To make up the smoky gases• At least 1.5m beneath smoke layer• If natural inlet is given• Inlets should be away from the outlets• Inlet velocity should be less than 3 m/s

Page 24: Smoke extraction in buildings

Monday, April 10, 2023 Smoke Extraction In Buildings 24

Page 25: Smoke extraction in buildings

Monday, April 10, 2023 Smoke Extraction In Buildings 25

Ductwork

• Must be able to withstand anticipated temp- From the formula

• HVCA specification DW144• For sprinkled buildings• To limit fire spread -fire protection of steel ducts -construct from proprietary material - use fire and smoke dampers

Page 26: Smoke extraction in buildings

Monday, April 10, 2023 Smoke Extraction In Buildings 26

Fire resisting requirement of ductwork

• To prevent fire inside one duct to breaking out to other

compartment.

• To prevent fire from outside enter into duct and then enter another fire compartment

• To prevent fire from outside enter into duct and the break out into other compartment

Page 27: Smoke extraction in buildings

Monday, April 10, 2023 Smoke Extraction In Buildings 27

Page 28: Smoke extraction in buildings

Monday, April 10, 2023 Smoke Extraction In Buildings 28

Page 29: Smoke extraction in buildings

Monday, April 10, 2023 Smoke Extraction In Buildings 29

Performance criteria for fire resisting duct work

• Stability

• Integrity • Insulation

Page 30: Smoke extraction in buildings

Monday, April 10, 2023 Smoke Extraction In Buildings 30

Other things to be noted

• Duct must be able to retain at least 75% of its size after the smoke removal.

• Sound or thermal insulation should not be raised to ignition temperature.

• Fire stopping seals should be used• Buckling or collapse.

Page 31: Smoke extraction in buildings

Monday, April 10, 2023 Smoke Extraction In Buildings 31

Construction of fire resisting smoke extract ducts

a) galvanized steel duct with additional protection b) fire resisting boards(eg . calcium silicate) c)proprietary fire resistant ductwork eg : PROMATECT-H

Page 32: Smoke extraction in buildings

Monday, April 10, 2023 Smoke Extraction In Buildings 32

Protection of duct with fire resisting board

Page 33: Smoke extraction in buildings

Monday, April 10, 2023 Smoke Extraction In Buildings 33

Ductwork construction from fire resisting board

Page 34: Smoke extraction in buildings

Monday, April 10, 2023 Smoke Extraction In Buildings 34

Spreading of smoke

Page 35: Smoke extraction in buildings

Monday, April 10, 2023 Smoke Extraction In Buildings 35

Page 36: Smoke extraction in buildings

Monday, April 10, 2023 Smoke Extraction In Buildings 36

Page 37: Smoke extraction in buildings

Monday, April 10, 2023 Smoke Extraction In Buildings 37

Page 38: Smoke extraction in buildings

Monday, April 10, 2023 Smoke Extraction In Buildings 38

Design guide for different building types

• Multi-storey office and similar buildings• Warehouse• Underground car parks/basement• Atrium buildings• Shopping malls

Page 39: Smoke extraction in buildings

Monday, April 10, 2023 Smoke Extraction In Buildings 39

Multi storey office and similar buildings

• Phased evacuation• Evacuation time will be varying• Smoke should not spread• 1, smoke extraction• 2, pressurisation• The recirculation of air in normal hvac system

is prevented by dampers

Page 40: Smoke extraction in buildings

Monday, April 10, 2023 Smoke Extraction In Buildings 40

Page 41: Smoke extraction in buildings

Monday, April 10, 2023 Smoke Extraction In Buildings 41

Important design considerations

• The system is not for providing a smoke free layer

• Both supply and extract ducts should be having fire resistance equal to that of the floors /walls

• Exhaust fans should be able to run at the highest expected temperature

Page 42: Smoke extraction in buildings

Monday, April 10, 2023 Smoke Extraction In Buildings 42

• The power supply to the system must be duplicated

• The power and instrumentation cabling should be of fire resistant type

• Smoke and fire dampers should be having suitable specification-UL555s

class-I,II,III,IV

• in high storey buildings-wind pressure

Page 43: Smoke extraction in buildings

Monday, April 10, 2023 Smoke Extraction In Buildings 43

Ware houses

Page 44: Smoke extraction in buildings

Monday, April 10, 2023 Smoke Extraction In Buildings 44

Underground car parks/basement

Page 45: Smoke extraction in buildings

Monday, April 10, 2023 Smoke Extraction In Buildings 45

ATRIUM CONSTRUCTIONS

• Fully enclosed atrium

• Partially opened atrium

• Fully opened atrium

Page 46: Smoke extraction in buildings

Monday, April 10, 2023 Smoke Extraction In Buildings 46

Page 47: Smoke extraction in buildings

Monday, April 10, 2023 Smoke Extraction In Buildings 47

Fully enclosed atrium

Page 48: Smoke extraction in buildings

Monday, April 10, 2023 Smoke Extraction In Buildings 48

• Enclosures are 2 types

1- fire resisting enclosure-fire resisting glazing

2- enclosure of limited combustibility but not fire resisting

Page 49: Smoke extraction in buildings

Monday, April 10, 2023 Smoke Extraction In Buildings 49

Partially enclosed atrium

Page 50: Smoke extraction in buildings

Monday, April 10, 2023 Smoke Extraction In Buildings 50

Fully open atrium

Page 51: Smoke extraction in buildings

Monday, April 10, 2023 Smoke Extraction In Buildings 51

Shopping malls

Page 52: Smoke extraction in buildings

Monday, April 10, 2023 Smoke Extraction In Buildings 52

Extract from single shops

• Smoke is prevented to enter to mall area• Very large fans are not required• But complex and costly• Shops must be sprinkled• Combined duct work is used to reduce cost

Page 53: Smoke extraction in buildings

Monday, April 10, 2023 Smoke Extraction In Buildings 53

Extract from mall

Page 54: Smoke extraction in buildings

Monday, April 10, 2023 Smoke Extraction In Buildings 54

Channeling screens

Page 55: Smoke extraction in buildings

Monday, April 10, 2023 Smoke Extraction In Buildings 55

Limitations

• With high atriums there is a cut off point of mass flow rate of 150 to 250 kg/s-economically impractical.

• Temperature stratification

• Cooling effect

Page 56: Smoke extraction in buildings

Monday, April 10, 2023 Smoke Extraction In Buildings 56

Fire,smoke and building code agencies

• Industrial risk insurers (IRI)

• Southern building code congress inc(SBCCI)

• National fire protection association(NFPA)

• Underwriters Laboratories(UL)

• British standards(BS)

• National Building Standards(NBS)

Page 57: Smoke extraction in buildings

Monday, April 10, 2023 Smoke Extraction In Buildings 57

CONCLUSION

• By following discriminative approaches and methods needed for different types of buildings and constructions provided by the different approved agencies ,the threat from fire and smoke can be reduced to a considerable level.

Page 58: Smoke extraction in buildings

Monday, April 10, 2023 Smoke Extraction In Buildings 58

References

• Promat International Ltd• National Fire protection Association,Guide for

smoke and heat venting,NFPA-204 M• BS 5839: Fire Protection and alarm systems in

buildings,Part1 2002• Underwriters Laboratories,Leakage rated

dampers for use in smoke in control systems,UL555 S

Page 59: Smoke extraction in buildings

Monday, April 10, 2023 Smoke Extraction In Buildings 59

THANKING YOU ALL……..