SMILE Engineering Transportation Challenge Weekend 2009.

26
SMILE Engineering Transportation Challenge Weekend 2009

Transcript of SMILE Engineering Transportation Challenge Weekend 2009.

SMILE Engineering

Transportation Challenge Weekend

2009

Objective• As hired consultants, your team will

design and construct a crane prototype that can lift a Maglev train car onto the magnetic guideway track.

Background• There’s a growing need for quicker and

more efficient methods for moving people and goods.

• Researchers have turned to using electromagnetic rails and trains: magnetic levitation or Maglev

• One of the key principles in maglev design is reduced friction (which means reduced costs)

Engineering Process

• Identify the problem • Preliminary Design• Design Refinement • Construction • Test • Redesign for changes• Retest

Crane Specifications

1) Lifting Mechanism of Crane:

• Boom: must move right & left and up & down.

• Hydraulics must be used for lifting load.

• Use string for the cable. – The cable must have a winder (roller)

mechanism that allows the lifting hook to go up and down.

2) Rotating Mechanism of Crane:

• Boom rotation by mechanical means – not by directly turning with your fingers. – Turntable at base of crane. – Rotation is controlled by a gear system (allows

boom to turn right and left).

• You are allowed to hold down the base with fingers while operating the controls.– *Hint: The counterweight is the most important

part of the mechanism used to balance the crane during lifting operations.

Maglev Car Specifications

• Your Maglev car design must accommodate:

– A hook-up device (i.e. paperclip) for attachment to crane on the top of the car

– Magnetic stripping on the bottom of the car

– A red line across the front for testing

When testing your Maglev car:

• You may use your fingers to attach and detach your Maglev car to and from your crane.

• It must operate without being pushed, touched, or interfered with once in place at the starting position on the track

I. First Task:Design Process

• 10:15-11:30 AM

• Discuss and sketch out prototypes for your ideal crane and maglev designs.

• Construction should begin only after the design has been perfected and all members of the group have agreed.

Design Process cont.

• Biggest Challenge:– Combining many different design needs

into one result

**Remember that you will have to compromise with one another and probably make changes to your designs along the way.

Design Process cont.

• When designing the Maglev, keep in mind:– 1) Balance (very important!)– 2) Placement and size of magnets– 3) Drag and aerodynamics– 4) Friction

**Look in your packet for details

II. Second TaskConstruction

• 12:25-2:15 PM AND 3:00-5:00 PM

Construction cont.• Division of Labor

– Two people:• 1) Maglev Car• 2) Rotation of Base (crane)

– Two people:• 1) Hydraulics to raise boom• 2) Boom

– Two people:• 1) Crank to turn base• 2) Crank to raise and lower boom string w/ load

Construction cont.• You can use the tracks at any time to

test out your design.

• When your Maglev car is ready, you can have a trial run down the track to make any last minute adjustments to your design.

Tracking Cost

• Before you start building the crane and maglev car, figure out the cost. • Modify your design if necessary.• Purchase extra materials, if needed, but be sure to keep track.

III. Third Task:Testing

• 6:00-8:00 PM

Testing cont.

• There will be two tracks:– 1) Stopwatch track

– 2) Technology (IMU) track

**You will be testing your prototypes on BOTH tracks.

Testing cont.

• When you are ready to test:

– 1) Bring your crane and maglev car over to the Stopwatch Track

– 2) Two people will operate the crane (one holds the base and the other operates)

– 3) The other members will stand along the track at the markers with stopwatches

Testing cont.

– 4) Record data

– 5) Repeat process for a total of 3 trials

– 6) Go back to your group table to graph data and answer questions

Testing cont.– 7) Take your Maglev car to the Technology

(IMU) Track

– 8) Remove your hook and place the IMU on your car (using the Velcro) – even distribution!

– 9) Do a test run and look at the graph that the computer produces

Testing cont.

– 10) Sketch the graph in your packet

– 11) Compare to the other graph that you made and answer questions.

When you’re done…

• You will display your graphs and question sheet next to the prototype at your table.

SAFETY

• All tools at the tool table are to be used at the tool table.

• Utility knives are to be used ONLY by adults at the tool table.

• Safety glasses must be worn at the tool table.

TEAMWORK

• Failure is an essential step towards success. Don’t be discouraged when something you worked on doesn’t work the

first time. Just try again!