1 Small Diameter Bomb Small Diameter Bomb Increment I (SDB I) Precision Strike Association Annual Program Review 19 April 2006 Small Diameter Bomb Increment I (SDB I) Precision Strike Association Annual Program Review 19 April 2006 Col Dick Justice Commander, Miniature Munitions Systems Group richard.justice@eglin.af.mil

Transcript of Small Diameter Bomb - · PDF file2 Small Diameter Bomb SDB Increment I GBU ­39/B,...

Small Diameter Bomb 

Small Diameter Bomb Increment I (SDB I) 

Precision Strike Association Annual Program Review 

19 April 2006 

Small Diameter Bomb Increment I (SDB I) 

Precision Strike Association Annual Program Review 

19 April 2006 Col Dick Justice Commander, Miniature Munitions Systems Group [email protected]

Small Diameter Bomb

SDB Increment I GBU­39/B, BRU­61/A 

Mission: All­weather, Autonomous, Precision Strike Decrease Collateral Damage Increased Loadout for Multiple Strikes Per Sortie at Standoff Ranges 

Description: IM Compliant 250 Lb Class Multipurpose Warhead Diamond­back Wing Provides Increased Range 4­place Pneumatic Carriage System Cockpit Selectable Electronic Fuze ­ Impact, Height Of Burst, & Delay 

Guidance: INS/GPS Augmented by Differential GPS Anti­Jam GPS with SAASM 

Platforms: Threshold:  F­15E Objective:  F­22A, F­35, F­16, F­117, A­10, B­1, B­2, B­52, MQ­9

Small Diameter Bomb

SDB I Weapon System

Mission Planning 

Weapon 

Logistics 

Carriage 

Accuracy Support Infrastructure 

RSU 

DMS

Small Diameter Bomb 

4

Small Diameter Bomb Small Diameter Bomb 

13

Increased Loadout / Standoff

4 Weapons per 1760 Station 

Loadout Balanced vsWeapon Effects: 250 lb Class SDB I 

F­15E F­15E 

F­35 F­35 

B­1B B­1B 

F/A­22 F/A­22 

F­117 F­117 

B­2 B­2 

F­16 F­16 

B­52 B­52 

A­10 A­10 

MQ­9 MQ­9 

Standoff Ranges of 40nm+ 0  20  40  60 

20 

40 

60 

80 

60  40  20 

20 

40 

60 80  80 

100 

50 nm 45 nm 

50 nm 

Dow

n Range

 (nm) 

Penetration  Non­Penetration 

60 nm 

40 nm (ORD) 

±35 nm (ORD)

Small Diameter Bomb

SDB I Schedule

Prior Fiscal Years  FY 05  FY 06 

MS A (CAD) MS A (CAD) 

Contract Award 

MS C (LRIP) MS C (LRIP) 

L3/FR Awd 

MS B (SDD) MS B (SDD) 

Contractor I 

Contractor II 

01  02  03  04  F  M J  M D O  F  J  A J M J  M N  D 

FY 07 

Lot 1 

A A  F J  M N  D  A S 

Lot 2 

Seamless Verification 

L1 Awd ($18.8M) 

J  A J 

SVR 

O  O N  S 

IOT&E 

Full Rate Production Full Rate Production 

Seamless Verification 

OTRR 

L2 Awd  ($38.3M) 

CAD  SDD  Production 

F­15E RAA

Small Diameter Bomb

SDB I Schedule

OND  JFM  AMJ  JAS 

FY05  FY 06  FY 07  FY 08  FY 09  FY 10  FY 11  FY 12  FY 13 OND JFM  AMJ  JAS  OND JFM  AMJ  JAS  OND JFM  AMJ  JAS  OND JFM  AMJ  JAS  OND JFM  AMJ  JAS  OND JFM  AMJ  JAS  OND JFM  AMJ  JAS OND JFM  AMJ  JAS 

IOT&E L1 Awd 

L2 Awd L3/FR Awd 

L4 Awd L5 Awd 

L6 Awd Lot 7 L7 Awd 

Lot 8 L8 Awd L9 Awd 

Lot 5 Lot 4 

MS C (LRIP) Seamless Verification 

Lot 1 

Full Rate Production 

F­15E RAA Lot 2 

CDR 

MS C Prep  Lot 1 (100) ACTD 

L2 Awd  Lot 2 (100) L3 Awd  Lot 3 (100) 

L4 Awd  Lot 4 (100) 

LRIP Tech Maturation 

Super­Sonic SDB Capability 

Fit Checks/WT Req Analysis/IMV Planning 

Detailed Design Development, Integration, & Testing 

Tech Insertion  Lot 6 

Fielded Residuals 

COCOM Evaluation 

Focused Lethality Munition 

SDB I UAI (Carriage/Weapon) 

F­15E Suite 6 (Legacy Interface) F­15E Ext. Envelope (SER 05­03)

Pre­Contract Work

Other Aircraft Integration 

L1 Awd 

Sustaining Engineering Carriage/Weapon OFP (2 Yr Cycle) 

F­22A Integration Support 

Sub­Sonic SDB Capability OT&E 

MQ­9B (Legacy Interface) TBD 

F­16 Blk 30  SCU8 (Legacy Interface) F­16 Blk 40/50 M6.1+ (UAI Interface) 

F­35A Blk 3 (Legacy Interface) 

I n t e g r i t y  –  S e r v i c e  ­  E x c e l l e n c e 

IMV Tests 

Lot 3

Small Diameter Bomb

History...Why SDB I? Commander’s Intent: You Will Deliver Small Diameter Bomb (SDB) to the

Warfighter in FY06. Schedule Is Paramount

•Fewer Aircraft •Fewer Crews •…More Effect from Less

•Global News Coverage •Diminishing Sources •Changing Laws, Ops

•Tactics •Laws of Armed Conflict •“Combat” JAG

q  Increase Number of Kills Per Pass 

q  Enhance Weapon Stand­off Range 

q  Combat Effective in Adverse Weather 

q  Provide Weapon Penetration Capability 

q  Minimize Collateral Damage 

q  Provide Autonomous Target Attack 

q  Reduce Logistics Footprint 

q  Reduce Aircraft Generation Times 

q  Achieve Battlefield Effects Against q  Fixed Covered, 

q  Fixed Concealed, 

q  Fixed Hardened 

(JROC:  Feb 2005) P

P

P P

P P P P P P P P

Small Diameter Bomb 

•  C3 Sites –  Communication Facility 

–  Antenna, Park Drive SATCOM 

•  Air Defense Sites –  Radar, Revetted, EW/GCI Site 

–  Radar, Grill Pan 

•  POL Sites –  POL Refinery 

–  POL, Large Partially Underground Tanks 

•  Airfield Targets –  Aircraft, Fighter – Revetted 

–  Aircraft Shelter, Large Concrete Arch 

–  Airfield Maintenance Complex w/ Machine Tool

SDB I Target Set 

B

10 

Small Diameter Bomb

SDB I Target Set (Con’t) 

•  Infrastructure Targets 

–  Transformer Yard 

•  Missile Sites 

–  SCUD Missile in Travel Mode, Stationary 

–  BM­21 Rocket Launcher, 122mm, Stationary 

•  Artillery Sites 

–  ARTY, 152mm Towed Field Gun/Howitzer 

•  AAA Sites 

–  ZSU­23­4, Stationary

11 

Small Diameter Bomb

One F­15E Loadout with SDB I Kills This Airfield…Single Sortie

AOC 

AC  On Ramp 

POL Pumping Station 

Alert Revets 

Hardened AC Shelters 

Squadron Ops 

Wing HQ

12 

Small Diameter Bomb

“Small” Can be Lethal •  MMTD Warhead 

–  Small, Well­Placed, Well Designed Warheads Do Damage 

•  SDB I Size Warhead Test

13 

Small Diameter Bomb 

•  Development Portion of Seamless Verification Complete –  35 for 37 Successful Flight Tests (CAD & SDD) 

–  Insensitive Munitions Testing Completed –  IM Certified by AF 

–  Operational Testing Ongoing

SDB I Test Status

Bullet Impact 

Fragment Impact 

Slow Cook­Off 

Fast Cook­Off 

Sympathetic Detonation

14 

Small Diameter Bomb

SDB I Executive Summary

Status Criteria Requirement

$(24,000 Weapons) + $(2,000 Carriage Systems) 24,000 Weapons

AUPP Cost of $64K (BY01$) ($41K Objective)

F­15E ­ 12 Weapons F­22A ­ 8 Weapons

A/C Loadout

4QFY06 RAA F­15E Integration

17 Weapons for 14 Targets Weapon Effectiveness

40nm Range (40kft, 0.8m)

Thresholds

100% of Top­Level IERs Designated Critical. NAV Data From GPS to SDB I

Net­Ready (GPS Interoperability)

4 SDB Weapons per SDB I Carriage Weapon Loadout

Status Criteria Requirement KPPs

P

P < $30K

P 15 for 14

50nm

P

15 

Small Diameter Bomb

SDB I Meeting Commitments On Track for RAA 4QFY06