CHAPTER -I Introduction The definition of a slum varies from one form to another depending on the background or country from which an individual comes from. Someone from a rich country may define slums as old run down buildings, whereas someone from a poor country will define slums as un-serviced haphazard constructions . The universal definition of a slum as found in the dictionary is said to be a heavily populated urban area characterized by substandard housing and filth . Slums are seen as a purely physical phenomenon. Slums are populated by two groups of people, the poor and the strangers . Since in slums there is a lack of cleanliness, serious diseases can spread easily and quickly. Slum inhabitants go through many problems, a few being they lack of public transit, constant migration, lack of water, no sewage or solid waste facilities, pollution, and shelter shortages . They also face poor ventilation, due to a lack of windows and electricity. They also tend to establish homes on unused land that is usually privately owned or government owned land. Therefore a concise definition for a slum would be a crowded urban area, marked by poverty, where living conditions are very bad and in poor condition . Defining and measuring slums 1

Transcript of Slum Rehablitiaion Report

Page 1: Slum Rehablitiaion Report

CHAPTER -I

Introduction

The definition of a slum varies from one form to another depending on the background or

country from which an individual comes from. Someone from a rich country may define

slums as old run down buildings, whereas someone from a poor country will define slums as

un-serviced haphazard constructions . The universal definition of a slum as found in the

dictionary is said to be a heavily populated urban area characterized by substandard housing

and filth . Slums are seen as a purely physical phenomenon. Slums are populated by two

groups of people, the poor and the strangers . Since in slums there is a lack of cleanliness,

serious diseases can spread easily and quickly. Slum inhabitants go through many problems, a

few being they lack of public transit, constant migration, lack of water, no sewage or solid

waste facilities, pollution, and shelter shortages . They also face poor ventilation, due to a lack

of windows and electricity. They also tend to establish homes on unused land that is usually

privately owned or government owned land. Therefore a concise definition for a slum would

be a crowded urban area, marked by poverty, where living conditions are very bad and in

poor condition .

Defining and measuring slums

The problem with measuring slums start with the lack of an agreed definition. As a result ,

enumeration of slums has not yet been incorporated within mainstream monitoring

instruments, such as natural population censuses, demographic and health surveys, and global

surveys. Some surveys provide proxies or related variables ‘such as proportion of

unauthorized housing’ pr ‘proportion of squatters’ . Participatory poverty assessments in least

developed countries (LDCs) generally provide only qualitative information on urban poverty.

The generic definition suggest that a slum is :

…..a contiguous settlement where the inhabitants are characterized as having inadequate

housing and basic seervices. A slum is often not recognized by the public authorities as an

integral or equal part of the city.

Other similar definitions are provided in many policy documents; for example the cities

alliance action plan describes slum as follows:

1

Page 2: Slum Rehablitiaion Report

Slums are neglected part of cities where housing and living conditions are appalingly

poor.Slums range from high density, squalid central city tenements to spontaneous squatter

settlements without legal recognition of rights, sprawling at the edge of cities. Slums have

various names, favelas, kampungs. Bidonvilles, tugorios yet share the same miserable

conditions.

These general definition met the common perception of what a slum is ; yet, as it stands ,

they are not associated with operational definitions that would enable one to ascertain whether

or not a particular area is a slum.

In practice what has happened when it has been necessary to operationalize the concept is that

areas have been designated specifically as slums, usually by planners making impromptu

surveys or following popular usage. This was the case during the Housing Reform in U.K.

and subsequently in many other countries.More recently, definitions developed in 1993 in

India use housing conditions and availability of facilities as the main basis for defining areas

as slums- areas with dense, poorly built or mostly temporary housing, with inadequate

sanitary and water facilities.

Clearly, it would be better for a number of purposes to have a more universal and objective

definition- particularly when global measurement and MDG targets are involved. Yet, the

most important indicators associated with UN-Habitat work- slums, insecure tenure, and

poverty- are terms that do not have clear or universally agreed definitions.

Efforts to propose a more ‘quantitative’ definition of slums have been only recently started,

not only because of divergent opinions as to what constitutes the key determinants of slums,

but because of several features of the concept:

(i) Slums are too complex to define according to one single parameter.

(ii) Slums are a relative concept and what is considered as a slum in one city will be

regarded as adequate in another city- even in the same country.

(iii) Local variations in slums are too wide to define to define a iuniversally applicable

criteria.

(iv) Slums change too fast to render any criterion valid for a reasonable long duration of

time.

2

Page 3: Slum Rehablitiaion Report

(v) The spatial natire of slums means that the size of particular slum areas is vulnerable to

changes in jurisdiction or spatial aggregation.

What is agreed is that slums like poverty, and secure tenure are multi dimensional in nature.

Some of the characteristics of slum such as access to physical services or density, can bne

clearly defined, and others, such as social capital, cannot. Even with well defined indicators,

measurement can be very problematic, and acceptable benchmarks are not easy to establish.

3

Page 4: Slum Rehablitiaion Report

Characteristics of Slums

A review of the definitions used by national and local governments, statistical offices,

institutions involved in issues and public perceptions reveals the following attributes of slums.

Lack of Basic Services

Lack of Basic Services is one of the most frequently mentioned characteristics of slum

definitions worldwide. Lack of access to sanitation facilities and safe water resources is the

most important feature, sometimes supplemented by absence of waste collection systems,

electricity supply, surfaced roads and foothpaths, street lighting and rainwater drainage.

Substandard housing or illegal and inadequate building structures

Many cities have bulding standards that set minimum requirements for residential buildings.

Slum areas are associated with a high number of substandard housing structures, often built

with non permanent materials unsuitable for housing given local conditions of climate and

location. Factors contributing to a structure being considered substandard are, for example,

earthen floors, mud-and-wattle walls or straw roofs. Various space and dwelling placement

bylaws may also be extensively violated.

Overcrowding and high density

Overcrowding is associated with low space per person, high occupancy rates, cohabitation by

different families and a high number of single-room units. Many slum dwelling unita are

overcrowded, with five or more persons sharing a one room unit used for cooking, sleeping

and living.

Unhealthy living conditions and hazardous locations

Unhealthy living conditions are the result of lack of basic services, with visible, open sewers,

lack of pathways, uncontrolled dumping of waste, polluted environments etc. Houses may be

build on hazardous locations or land unsuitable for settlement, such as floodplains, proximity

to industrial plants with toxic emissions or waste disposal sites, and on areas subject to

landslip. The layout of the settlement may be hazardous because of a lack of access ways and

high density of dilapidated structures.

4

Page 5: Slum Rehablitiaion Report

Insecure tenure; irregular or informal settlements

A number of definition consider lack of security of tenure as a central characteristics of slums,

and regard lack of any formal document entitling the occupant to occupy the land or prima

facie evidence of illegality and slum occupation. Informal or unplanned settlements are often

regarded as synonyms with slums. Many definitions emphasize informality of occupation and

non-compliance of settlements with land use plans. The main factors contributing to non-

compliance are settlements built on land reserved for non-residential purposes, or which are

invasions of non-urban land.

Poverty and social exclusion

Income or capability poverty is considered, with some exceptions, as a central characteristic

of slum areas. It is not seem as inherent characteristic of slums, but as a cause land, to a large

extant, consequence of slum conditions. Slum conditions are physical and statutory

manifestations that create barriers to human and social development. Furthermore, slums are

areas of social exclusion that are often perceived to have high levels of crime and other

measures of social dislocation.In some definitions, such areas are associated with certain

vulnerable groups of population, such as immigrants, internally displaced persons or ethnic

minorities.

Minimum settlement size

Many slum definitions also require some minimum settlement size for an area to be

considered as slum, so that slum constitutes a distinct precinct and is not a single dwelling.

Examples are the municipal slum definition of Kolkata that requires a minimum of 700 square

meters to be occupied by huts, or the Indian census definition, which requires atleast 300

people or 60 households living in a settlement cluster.

The experience of ‘ living in a slum’, according to slum dwellers consist of a combination of

these multiple dimensions, not only one. Many slum areas show only few of these negative

attributes, while the worst may have them all. The ‘worst type of slum household’ is prone to

all of the above disadvantages, which, to an extant, also constitute some of the main obstacles

that have to be overcome in realizing the right to adequate housing; one that has no services,

has poor-quality housing on fragile land, does not have secure tenure and where the occupants

5

Page 6: Slum Rehablitiaion Report

are poor, marginalized and belong to a vulnerable group. Less badly affected households may

carry one or more of these burdens.

6

Page 7: Slum Rehablitiaion Report

CHAPTER –II

SLUM DYNAMICS : CONDITIONS AND CHALLENGES

Situation Understanding

The concept of Slum Dynamics was developed based on the understanding of the lives of the

slum residents. The existing situation with regards to land tenure in the slums, occupation and

income of the slum residents, education, health, women and girls, children and adult males

was understood to develop this concept.

Land Status

The slum dwellers live in a constant fear of being evicted. In most cases

they have paid a middlemen for the land, which does not have legal title.

The city does not provide affordable housing with legal land title. The slum

dwellers cannot leverage any credit by using the house or land as

acceptable collateral. They cannot pay taxes even if they want to because

taxation gives them legal status. In short, lack of legal land tenure convert

the slum dwellers into secondary citizens of the city.

Basic Services

Slums do not have basic services. The ambiguity of land title and legal

status prevents provision of formal infrastructure. As a result, political

patronage becomes an alternative for planned development. Even when

they want to pay for these services, they are unable to get water, drainage

or sanitation. They have to make do with public toilets and water supply

with all associated problems. Even when they keep their houses clean,

they do not have option for solid waste removal from the slum settlement.

Occupation

Majority of the slum residents are first generation migrants from the rural

areas. They possess skills that do not have any significant market in the

cities. They have to learn new skills, which require long-term investment of

time and resources, which they do not have. Their only option remains is 7

Page 8: Slum Rehablitiaion Report

getting engaged in occupations that are unskilled and menial, and where

the incomes are low. These are also casual jobs. Irregularity of

employment and no address of employment disqualify most of them from

accessing credit for small businesses. Even, the land title for the house not

being there, they are unable to offer collateral for any credit. Unscrupulous

companies too take advantage of the ignorance of slum residents and

cheat them. The banking in the formal sector does not welcome

disbursement of small loan amounts to the slum residents as that is quite

expensive for these organisations. Hence, the slum residents are forced to

borrow from usurious moneylenders.

Education

Majority of children in slums are first generation students, whose parents

may be illiterate. They do not get the parental support or guidance

required for coping with formal education. They lack learning materials.

Moreover, children from slums are not “properly” clothed. Shortage of

water prevents cleanliness. These factors, when compared to those of

other children attending school, leads to a condescending attitude from

teachers who label them as underachievers. Children from slums are

looked down upon. These reasons lead to a high failure and dropout rate.

For girls, formal schooling is more difficult because traditional attitudes do

not favour long-term education.

Even those few who manage to secure a college degree are disillusioned

when they fail to get employment. They then have to learn a new earning

skill. This leads to a belief that 12 or 15 years of formal education are a

waste of resources.

Lack of formal education closes opportunities for technical education,

making learning of formal earning skills difficult. Consequently, a majority

is forced to join the informal sector doing menial work.

Health

8

Page 9: Slum Rehablitiaion Report

Health is a major economic issue for slum residents. The unhealthy

physical environment leads to sickness, which leads to costs for continuing

medical treatment, which leads to reduction of workdays and economic

loss. Economic loss leads to inability to invest in clean environment. The

vicious cycle continues.

Treatment at government hospitals is apparently cheaper, but is

inconvenient to the slum residents because of time lost in waiting for the

treatment and often, indifferent attitude of the medical staff. Instead, they

prefer more expensive private treatment.

Low education and ignorance leads to continuation of wrong beliefs and

unscientific attitude towards health. The outcome is incomplete

immunisation, insufficient gynaecological check up during pregnancy,

unsafe deliveries at home and improper post-natal care of mothers and

children especially in terms of diet and immunisation. Incomplete

tuberculosis (TB) and malaria treatment leads to recurrences and relapses.

The need for fast cures helps propagate the myth that expensive

treatment is good treatment

Women and Girls

Women and girls in slums have a poor quality of life. The lack of basic

services affects them the most. They have to spend considerable time

collecting potable water and getting rid of wastewater. Having to defecate

in open spaces is a health and social hazard. Looking after children who

are frequently sick, husbands who do not earn adequately and can be

drunk and trying to ensure that the family gets a meal every day. Women

are most disadvantaged in slums.

Girls have to look after younger siblings when both parents go to work.

Combined with a traditional bias against educating girls they are often not

sent to school or drop out at an early stage. Girls do not have the

exposure to everyday city life situations, which men, women and young

men have. As a result they are often anxiety prone and stressed.9

Page 10: Slum Rehablitiaion Report

Children

The unhealthy and polluted environment, lack of immunisation,

malnutrition and absence of educational exposure affects children in

slums. Sadly, their physical, emotional and intellectual growth is stunted

from a very early age.

Men and Youth

Men in slums have inadequate earning skills leading to low incomes and

an inability to provide adequate resources for household expenses. This

leads to frustration, which is often expressed through escapism in

addiction of various types. The need to provide an adequate quality of life

combined with a lack of formal earning skills forces the option of extra

legal activities.

The youth are frustrated, as they do not have the opportunities that their better-off

peers have. This results in a cynical and diffident attitude, which becomes a handicap during

adulthood

Brief of Problem

It is imperative to keep in mind that the right to shelter has been recognized world over. As

such, in any urban development policy, the needs of those living in slums and slummish-type

settlements have to get priority. Proper rehabilitation is vital when relocation is planned. City

development has to be integrated with social and economic development, not just for the rich

but for the poor too. This should not be forgotten by the urban planners, whether in India or

elsewhere.

The main problem arise after regulatory framework is of finance and implementation

mechanism of the decisioins by various bodies. The poverty also needs to be addressed as it is

a result of unemployment leading to social offenses and crimes. A holistic solution is desired

to vanish poverty and slums as both of these are directly linked with economic growth of the

nation.

10

Page 11: Slum Rehablitiaion Report

CHAPTER – III

METHODOLOGY

Vanishing Poverty and Slums in India

Western media headlines as usual are as follows – twenty five percent of Indians live on less

than a dollar a day and seventy percent live on less than two dollars a day. The forgoing was

the headline of May 9, 2005 in a major international newspaper. Others headlines are not any

less mischievous. These are all meaningless analysis. It does not reflect that same amount of

money has differing values in different places. A more acceptable and bit accurate description

of incomes in countries is Purchase Power Parity (PPP), which is, pricing identical products

and services as needed by the local population in different countries, thus establishing a new

11

Page 12: Slum Rehablitiaion Report

and a more equitable exchange rate. The foregoing is applicable mostly to tradable goods. The

PPP will put India’s GDP at $3.7 Trillion. This will raise daily monies of twenty five percent

of Indians at the lowest rung of the society to seven dollars. The latter is still low but is much

higher than the Western media would like to project. The forgoing is not the point; the point is

that poverty is a major shame in India’s otherwise decent, scientifically advanced, peace

loving and at times turbulent image. Poverty creates slums and slums breed hopelessness and

crime. Hence it needs to be tackled as an integral part of economic development.

The key question that arises - Is the current hype in economical development in India alter

landscape for the very poor?

The answer is that, not much will change in next 20 to 25 years. The real impact will be felt

later than twenty-five years. That is when 8% growth trajectory will take the PPP daily

income of the very poor in India from seven dollars to forty dollars. By then, a $20 Trillion

GDP economy (PPP basis) and $600 billion in exports (year 2001 basis) will add one hundred

and fifty million jobs, of which forty to fifty million will go to the very poor segment of the

society. This general prosperity will not only put food on the table but will add to better

living, better housings etc. In the intervening period of 25 years, rising income levels will

definitely add to the exodus from the slums to planned living areas. The forgoing also requires

massive governmental effort to house people properly.

Let us examine this issue of poverty and slums in Indian cities and its relationship to the

betterment of economic conditions of the masses, a bit further?

What Causes Slums in the Cities in the First Place?

It is vicious cycle of population growth, opportunities in the cities (leading to migration to the

cities), poverty with low incomes, tendency to be closer to work hence occupying any land in

the vicinity etc. The key reason out of all is the slow economic progress. After independence

in 1947, commercial and industrial activity needed cheap labor in the cities. Plentiful was

available in the rural area. They were encouraged to come to cities and work. People, who

migrated to the cities and found work, brought their cousins and rest of the families to the

cities. Unable to find housing and afford it, they decided to build their shelter closer to work.

12

Page 13: Slum Rehablitiaion Report

First, one shelter was built, then two and then two thousand and then ten thousand and on and

on. Conniving governments provided electricity and drinking water. Politicians looked at the

slums as vote bank. They organized these unauthorized dwellers into a political force; hence

slums took a bit of a permanent shape. More slums developed as more population moved to

the cities. By mid sixties Mumbai, Kolkata, Delhi, Chennai and all other large cities dotted

with slums.

Very poor people live in slums. They are not the only one dwelling there. Fairly well to do

people also reside there. They are either offspring of the slum dwellers that found education

and an occupation. They have prospered but are unable to find affordable housing, hence have

continued to stay in the shantytowns. Others are avoiding paying rent and property taxes. The

latter is more often the case. It is not unusual that in the dirtiest of slums, where misery

prevails that TV sets, refrigerators and radios are also blaring music. This is quite a contrast

from the image which one gets in the media or from the opportunist politicians.

India’s capital of Delhi has a million and a half out of fourteen million living in slums.

Mumbai is worst with greater percentage living in slums. Other big urban centers have done

no better. Newly built cities like Chandigarh and surrounding towns where shantytowns could

have been avoided altogether have now slums. The forgoing is India’s shame despite huge

progress.

How will the growing Economy impact Poverty and the Slum dwellers?

As stated above, 8% growth rate of Indian economy will push per capita GDP to $2,000

level in about twenty to twenty-five years (PPP per capita GDP will be much higher). The

forgoing presupposes that the population does not explode in the near future but continue a

healthy 1.5 to 2% growth. That is where the magic equilibrium of prosperity and desire to

live a better life begins. These two together usually vanish poverty and slums. With

availability of affordable housing and jobs, slum dwelling is the last thought on people’s

mind.

On the other hand if the above does not happen then slums dwellers will triple in 25 years

and so will the poverty. Delhi will have four and a half million-slum dwellers. Kolkata and

Mumbai will have even bigger numbers. India’s shame will have no end. To avoid that,

India’s economy has to remain at a high state of growth. Jobs created by the economic

13

Page 14: Slum Rehablitiaion Report

growth, hence higher incomes are key criteria for poverty reduction and slums elimination.

The forgoing together with the current urban renewal in progress in the urban areas today

will give cities in India a new look. Higher incomes will create a demand for in-expensive

housing, which will have to be met with innovative use of land and building techniques.

Government provided housing would be a great failure as it has been elsewhere in the world.

Instead sufficient cash has to be placed in the people’s hands together with in-expensive land

that people’s housing program become efficient and affordable. In addition slum living has to

be made unattractive with land taxes and denial of social services. Slum colonies, which opt

out of current hopelessness, should get a better deal in housing which replaces the slums.

This followed with rapidly growing rural economy will kill migration. That will also reduce

pressure on housing.

No single policy has ever brought an end to poverty and slums. It is a concerted effort and

better policies, which will end it. No country in the world has ever been able to end poverty

and slums completely. That includes the richest nation of the world – USA. The point is that

if economy progresses and special effort is made to uplift the poor, poverty and slums will be

overtaken by better economic conditions of the people.

INTEGRATED SLUM DEVELOPMENT (ISD) : NEED FOR REHABILITATION

ConceptDuring 1990-91 period, ISD was developed from a theoretical framework to an

implementable programme based on the past personal experience and understanding the lives

of slum residents. Up to the 1990s, the existing development paradigm of central planning

considered slum residents as passive recipients of developmental inputs and not as active

participants in the development processes affecting them. This welfare approach to slum

development had created an overall feeling that the slum residents were inferior citizens of the

city and hence the government had to take the burden of developing the slums. From an

activist’s viewpoint, there was a greater concern; that slum residents themselves were

internalising this attitude, leading to decreased self-esteem and a diffident attitude. The ISD

concept was developed assuming that the slum residents themselves were willing to be active 14

Page 15: Slum Rehablitiaion Report

participants in their own development process.

The critical need was to create opportunities through which slum residents became active

change agents of development. It was thought that meeting the basic developmental needs of

health, education, economic betterment and physical services in a tangible manner could

create the opportunities/options for the slum dwellers. It would enhance their quality of life

and in this proactive process bring about change and enhance the self-image of slum residents.

The ISD was conceptualised with programmes that would enable the slum residents to realise

their potential by:

i) Increasing their management and technical expertise,

ii) Nurturing leadership, and

iii) Enhancing their self-esteem and self-confidence

It was believed that these three activities would start a virtuous dynamic cycle of actions for

development. The intervention would begin with improvement in skills and capacities, that

would lead to improvement in quality of life, that would enhance their self worth, which

would lead to critical reflection and finally to more actions for development. This framework

provided design and structure of ISD. Based on that, a Frame of Reference (FOR) was

prepared. The main components in ISD’s (FOR) were:

i) To address all development needs of health, education, economic

betterment, physical upgradation and human aspirations,

ii) Slum residents would be participants by paying, deciding and

implementing,

iii) Development processes would proactively effect women,

iv) Partnerships with concerned institutions and individuals, and

i) Values of integrity, quality, sensitivity would be inherent.

15

Page 16: Slum Rehablitiaion Report

Origin of Slums

Almost without exception, slum formation principally originated from four types of rapid

urban population expansion that were primarily triggered by:

1. Rural-urban migration;

2. Natural growth;

3. Combination of natural and migratory growth;

4. Population displacement following armed conflicts or internal strife and violence.

Adittionally, in some cities, demographic forces were compounded by urban specific

transformation processes with clear segregational implications, such as inner-city

deterioration, gentrification and counter urbanization.

16

Page 17: Slum Rehablitiaion Report

Surges in urban population and the ofthen-related spatial segregation of urban population

segments on socio-economic and ethnic grounds have been problematic for a variety of

reasons, the utmost being:

A relatively long period of laissez-faire attitude on the part of urban authorities

towards illegal occupation of urban lands and commensurate flouting of building

regulations and/or urban zoning prescriptions;and

A general failure of housing and land markets to provide for the land and housing

requirements of rapidly growing urban low-income populations in a timely fashion

and in efficient numbers and locations.

17

Page 18: Slum Rehablitiaion Report

18

Statewise Slum Population in 2001

1.In case of Himachal Pradesh, Sikkim, Arunachal Pradesh, Nagaland, Manipur, Mizoram, Daman & Diu, Dadra & Nagar Haveli and Lakshdweep no slum population has been reported at the Census of India - 2001 Note: 2.Delhi includes eleven census towns and Uttar Pradesh one.

3. Seven towns, one each in Bihar,Maharashtra and Meghalaya, two each in Gujarat and Madhya Pradesh include population of outgrowths/urban agglomeration.

Source:

Census of India 2001 (Provisional Population Totals)

http://www.niua.org/indiaurbaninfo/tablenew/table5.htm[4/4/2009 8:29:29 PM]

Page 19: Slum Rehablitiaion Report

Operational definition of slums

The operational definition of slum that has been recently recommended [by a United Nations

Expert Group Meeting (EGM) held in Nairobi from 28 to 30 October 2002] for future

international usage defines a slum as an area that combines, to various extants, the following

characteristics [restricted to the physical and legal characteristics of the settlement, and

excluding the more difficult social dimensions:

inadequate access to safe water;

inadequate access to sanitation and other infrastructure;

poor structural quality of housing;

overcrowding;

insecure residential status.

The proposed indicators and threshold in Table are based on MDG indicators, where

possible. These indicators are provisional and subject to international field testing for

appropriateness. Robustness and compliance with available sources, before reliable baseline

global estimates of the numbers of people living in slums are obtained. It is also intended that

local modification of indicators should be used as long as they are applied consistently over

time.

19

Page 20: Slum Rehablitiaion Report

Various Indicators and parameters as per MDG

20

Page 21: Slum Rehablitiaion Report

Characteristic Indicator Definition

Access to water Inadequate drinking water supply A settlement has inadequate drinking water supply if less than 50% of (adjusted MDG indicator 30) households have an improved water supply.

household connection access to public stand-pipe rainwater collection

with at least 20 liters/person/day available within an acceptable collection distance.

Access to sanitation Inadequate sanitation A settlement has inadequate sanitation if less than 50% have improved sanitation. ( MDG Indicator 31) The factors are considered :

public sewer; septic tank; pour-flush latrine; ventilated improved pit-latrine

The excreta disposal system is considered adequate if it is private or shared by a maximum of two households.

Structural quality of housing a.Location Proportion of households on or near a hazardous site. The following locations should be considered :

housing in geologically hazardous zones(landslide/earthquake and flood areas); housing on or under garbage mountaions; housing around high-industrial pollution areas; housing around other unprotected high risk zones(eg airports, energy transmission

lines)

b.Permanency of structures Proportion of households living in temporary or/and dilapidated structures. The following

factors should be considered when placing a housing unit in these categories:

quality of construction (eg material used for wall, floor and roof);

compliance with local building codes, standards and bylaws.

Overcrowding Overcrowding Proportion of households with more than 2 persons per room. The alternative is to set a

Minimum standard for floor area per person(eg 5 square meters)

Security of tenure Security of tenure (MDG 32) Factors are:

Proportion of households with formal title deeds to both land and residence.

Proportion of households with formal title deeds to either one land or residence.

Proportion of households with enforceable agreements or any document as a

proof

Of tenure arrangement.

Note: ‘well’ and ‘springs’ are considered acceptable sources in the original MDG indicator but are almost

certain to be polluted in urban areas.

Sources: adapted from UN-habitat 2002a, 2002b

21

Page 22: Slum Rehablitiaion Report

22

Page 23: Slum Rehablitiaion Report

23

Page 24: Slum Rehablitiaion Report

24

Page 25: Slum Rehablitiaion Report

25

Page 26: Slum Rehablitiaion Report

26

Page 27: Slum Rehablitiaion Report

Current scenario in India

As regards India, the people living in slums, squatter settlements and refugee colonies

comprise 30 to 32 per cent of the urban population. Mumbai, Kolkata, and Delhi have a large

segment of this population and improving their conditions has been a matter of concern for

the State governments. As per present estimates, Maharashtra had the highest slum population

(around 18 to 20 million) followed by Andhra Pradesh (10 million) and West Bengal and U.

P. (around 8 to 9 million).

Obviously, the high population growth in these metropolises has put tremendous pressure on

the local authorities, incapable of handling huge influx. Around 35 per cent of the population

of Kolkata lives in slums while it is around 50 per cent in Mumbai. Apart from the total slum

population of both Mumbai and Kolkata, which is over 8-9 million (or 16-18 lakh families),

there are about another 4 million squatter settlements.

In the last few years, schemes such as the National Slum Development Project (NSDP) and

Valmike Ambedkar Awas Yojana (VAMBAY) have made a big dent towards upgradation

of urban slums by providing physical amenities and looking after social needs. In 2005-06,

the two schemes were combined to form a new scheme called “Integrated Housing & Slum

Development Programme” (IHSDP), which undertakes slum development in a holistic

manner.

With resources becoming a major problem, the Union Government formulated the Jawaharlal

Nehru Urban Renewal Mission (JNNURM), launched in December 2005. The project

envisages Rs 50,000-crore Central assistance and will be implemented in 63 cities, including

28 million plus cities over a seven-year period. The rationale being that individual cities are

currently inefficient both in raising resources to meet their needs and in governance.

At the same time, a significant amount is to be earmarked for basic services for the urban

poor, which gives hope of a significant change in the living conditions of these dwellers. In

fact, it is gratifying to note that the JNNURM would have one submission on basic services.

However, while decentralization has been accepted in letter and spirit, the JNNURM has

indicated once again that the ‘Centre knows best’ approach would be followed, which is a

27

Page 28: Slum Rehablitiaion Report

cause for concern. It needs to be stressed that development of city infrastructure should

emerge after a debate between all the stakeholders, including slum dwellers, who constitute

around 35 per cent of the population.

Another aspect that has perturbed a section of sociologists, planners and social activists is the

demand for urban land to measure up to global standards so that investment flows into high-

end sectors. If slum lands are taken away and flats constructed for them, how will the poor

carry on their trade and earn their livelihood? The Mission is silent about this.

It goes without saying that the challenge of slum development is indeed quite critical thanks

to the dimension of the problem and resources needed to accomplish the task. As is generally

agreed, “plans and programmes drawn up by the Government so far have not effectively hit

the target”.

As has been emphasized repeatedly by experts, the involvement of NGOs and the private

sector is a must for upgradation of settlements to yield effective results. Various Five-Year

Plan documents have explicitly recognized the importance of involving NGOs in the

planning, implementation of anti-poverty and minimum needs programme. These include

environmental improvement of slum areas.

A beginning has already been made in Dharavi area of Mumbai. Each resident family is

being given a 225 sq. ft. apartment free of cost, with a portion of the surplus land being used

for commercial purposes. The Maharashtra government has taken a commendable initiative

as its Slum Rehabilitation Scheme, started in 1991, has gained momentum in the last five-

seven years. According to reports, “so far 280 Slum Rehabilitation Schemes have been

completed, providing self-contained rehabilitation tenements to about 62,000 families of

slum dwellers. And 626 schemes are at various stages of completion and will provide for

decent housing for another 162,000 families of slum dwellers”.

In another exemplary instance, 96 pavement dweller families of Ritchie Street, Chennai have

been rehabilitated in multi-storied buildings. They moved into their new apartments in

February 2001. This was possible thanks to the efforts of CODIAC, an NGO and an Rs 60

lakhs interest-free loan from German donor agency EZE and HUDCO’s loan of Rs 25,000 to

each family.

28

Page 29: Slum Rehablitiaion Report

In Kolkata, evicted squatters have been rehabilitated in an area (Nonadanga) and given

apartments at very low cost. Around 300 families who had formed a cooperative are now

enjoying the privacy of an apartment (of around 250 sq. ft). Such initiatives are needed in

many other cities, so that squatters can live a dignified existence. Slums need to be upgraded

with minimum facilities of water, sanitation, education and health.

Characteristics of WSS

Water Supply Sanitation

1.Type of source 1. Type of Infrastructure

2. Distance 2. Distance

3. Exclusivity of use 3. Exclusivity of use

4. Quality of water 4. Cleanliness

5. Adequacy, Timeliness 5. Privacy, odor

6. Quality of Services 6. Services

29

Page 30: Slum Rehablitiaion Report

30

Page 31: Slum Rehablitiaion Report

National Slum Policy Even after 55 years of independence, the country does not have a National Slum Policy

thought 30 percent of population is living in slum areas. Slums are the products of lack of

systematic national policies and bad governance, a fundamental lack of political will and a

callous indifference to human suffering on the part of the power elites. The Ministry of Urban

Development and Poverty Alleviation, Government of India finalized the National Slum

Policy Draft in April 1999. The Ministry received comments upto the 3rd December 2001.

Till date the Government of India had not announced the National Slum Policy. Slum

population was 40.3 million in 2001 Census, that is, about 14.2 percent of the total urban

population of India.

Critical Review of the Policy

1. "Inclusive" Approach to Definition of Slum/Informal Settlement

The Draft Policy follows the Census definition. The Census definition is partial because of

the exclusion of towns with less than 50,000 population, and slum clusters, which are not

formally or informally recognized if the population was less than 300. The Draft Policy is left

to the State and Union Territory in laying down the norms/criteria for categorizing an area as

under-serviced settlements. Now there is a need to bring about an amendment in the Central

Act in lieu of the lieu of the new Policy. Though the definition of slum has always referred to

area and living conditions, in India slum are identified on the basis of the nature of house

construction and the availability of basic amenities such as drinking water, drainage and

sanitation. The Draft National Policy has to deal with the insanitary, disoraganised, and

overcrowded collection of mostly hutments spread in the midst of cities and towns, described

by the United Nations as a menace to health and an affront to human dignity.

2. Listing and Registration

a. Comprehensive Listing of Slums/Informal Settlements

b. Registration of slum dwellers

c. Identity Card

31

Page 32: Slum Rehablitiaion Report

d. Basic Service Eligibility: water, sanitation, electricity, health, etc

e. Other Entitlements: Schemes for economic support, credit, pensions, insurance etc

Registering Authority clearly specified. Registration and issue of the identity card should be

time bound.

3. De-listing

The sustainable level of basic services (including responsibility for provision of services and

accountability) and socio-economic indicators should be given in the Policy. Otherwise it

may lead to confusion.

4. Classification of Land Status/Tenability

The Classification of land not only on the basis of tenability and Private land and public land.

The issue of whether a settlement existence is against public interest shall be decided by the

District Magistrate in consultation with the Urban Local bodies and technical experts, after

giving full opportunity to the resident community to express their views in a public hearing.

The factors determining the untenability of slums and public interest have not been defined

clearly in the policy. The District Magistrate is supposed to take the decision in consultation

with Urban Local Bodies. Even though the residents community can give their views in the

public hearing. Public Hearing is not the Government's responsibility. Slum Dwellers have no

stakeholder status. It is left to the discretion of the District Magistrate.

5. Granting of Tenure

The Government should provide freehold plots to slum dwellers. This means that the slum

dwellers will also be the owners (with condition for right to transfer) of the plot and there

would be no Government lease. Government has to formulate policy to earmark certain lands

for slum dwellers. In the Draft National Slum Policy there is no percentage of allocation

specified.

6. Resettlement Rehabilitation

The policy does not speak clearly about the land use and tenability of the alternative site in

accordance with the prevailing Master Plan. It should be particularly made sure that the

alternative site is tenable and full tenure rights are provided immediately to resettlers. In the

resettled place at least 50 square meter of land per individual family is needed for providing

32

Page 33: Slum Rehablitiaion Report

basic amenities. In addition to the residential area a similar area has to be provided for roads,

drainage, sewerage, community hall, children's playground, primary school, Creche facility,

health centre etc, in these zones. The issue of slum eviction and resettlement is linked to the

wider question of poverty and the related issue of the powerlessness and lack of entitlement to

and accessibility of basic social and physical vulnerability in terms of caste, ethnicity, gender,

mental and physical disability, ageing and problems relating to children.

Forced evictions, which are viewed by the UN as a gross violation of human rights, are

almost exclusively reserved for the poor and the socially excluded, and almost always

exacerbate the situation. Need to find local approaches to relocation, through negotiation and

the search for constructive solutions, can solve problems that forced evictions only worsen?

In short, forced evictions should be seen as a failure of public policy, and the lack of pro-

poor developmental perspective.

7. Planning for Integration

The Draft policy stresses about improvement and insitu upgradation to be made possible

through modification. The modification like conversion of the mixed use land occupation

will further squeeze working class residential lands into smaller pockets within the cities. The

policy will further go in favor of commercialization of land that is presently for residential

purposes.

As the policy has to deal with the people as much as with the area, policy makers may have

noted that there is little upward movement of slum-dwellers even in a State with good

economic growth. Cases of absorption of residents in better neighborhoods are exceptions and

not the rule, as most migrants enter slums not with an idea of a transitory arrangement.

Individual economic growth has takenplace in the slums of metropolitan cities, but with this,

an ambition to become slumlords sanctioned by political patronage to create vote banks rather

than a desire to shift to a better locality, catches the slum residents. The distinction as slums of

hope; and slums of despair is not relevant in India as the self-eliminating process contained in

the slums of hope is not present.

Urban slums in India are not considered temporary shelters or a stopgap arrangement by the

newcomers to the cities to prepare for proper housing, but have become permanent homes for

many generations for many families. The national policy must proceed on the premise that the

33

Page 34: Slum Rehablitiaion Report

earlier attempts at the relocation of slum-dwellers have not succeeded in many places.

8. Environmental Improvement

For providing the physical infrastructure development like water supply, Sanitation, Pedestrian

and Vehicular access ways, Storm Water Drains, Electricity and Solid Waste collection, the

Draft Policy emphasizes the contracting out to the NGO and other Private Companies. The

services are as per the Local Bodies Act are mandatory duties.

9. Improving Access to Social Services-Health services, education, Child

Labour and Child Rights, Public Distribution System

Benefit-incidence studies have shown that a disproportionate share of the benefits of health

and education programs accrue to the non slum people, often because the facilities are located

closer to the non slum and the non-slum people make more use of the facilities because of the

income effect, i.e., they are richer. Government social service subsidies are not well targeted

and, consequently, are not efficient at redistributing income. The Policy is silent about how

the social services are going to deliver effectively. One of the strategies as mentioned in the

policy, is Demand for the service. Who will mobilise the community to demand services.

Private Sector partnership means profit. How can the poor slum dwellers benefit from the

private sector.

To improve the quality of life of these residents, slum policy should contain clauses to

enhance educational, health and moral standards. This requires coordination among

Ministries/Departments concerned. Compulsory schooling and a ban on child labour and

child marriage, for instance, must form part of the policy to be implemented, and an

atmosphere discouraging gambling, drinking and prostitution has to be created. Without this,

mere restructuring/relocation will not help. Any place can develop slum conditions unless the

occupants are mentally freed from a slum atmosphere.

10. Municipal Services to be brought under Consumer Protection Act

If the Municipal Services is to be brought under Consumer protection Act, there is a need for

the amendment in the Consumer Protection Act. Sustainability and efficiency of

interventions is enhanced where the same organization (Urban Local Bodies) has

responsibility for implementation, operation and maintenance of services, and where

34

Page 35: Slum Rehablitiaion Report

institutional capacity for the same is in place. In India, this is in line with the 74th

Constitutional Amendment, which mandates local government with responsibility for urban

poverty reduction. However Municipal Corporations were found to be unreliable in

maintenance of assets and services. There is need for a clear strategy, agreed during initial

planning, with clarity on the financial management of services and clearly defined operation

and maintenance systems, especially for such things as cleaning and maintenance of roads,

drains and latrines.

11. Economic Empowerment

A. Financial Services for the Poor: Surveys of some of India's urban slums are reported to

indicate that 40-50 percent of slum households are living just below the poverty line while 11

percent are living just above it. The remaining 30-40 percent of slum dwellers lives well

above the poverty line. Conversely, it is estimated that only 40-60 percent of the urban poor

lives in slums or squatter settlements. The balance lives on pavements (close to sources of

income), overcrowded tenements, or commute daily to and from periurban areas. The

implication of this fragmented pattern of location of urban poor makes it difficult to target

without risk of some degree of leakage of benefits to the non-poor.

B. Economic Support/Enterprise Development: The poorest of the poor are the least likely to

benefit from vocational training, which is not targeted. Typical vocational training programs

are supply driven and particularly prone to capture. Provision of one time training in isolation

of financial support is unlikely to impact livelihoods. Lack of post-training financial support

as the key constraint to using skills gained through vocational training. The type of training

offered conforms to sex stereotypes.

In the present context of globalisation, liberalisation, Structural adjustments and

privatisation of essential services, the slum dwellers are facing hardship. A vast majority of

the homeless people, slum dwellers and pavement dwellers are from Dalit and Tribal

communities. Women, especially singly women, and children are the worst affected because

of the globalisation process.

35

Page 36: Slum Rehablitiaion Report

12. Financing Sustainable Slum Improvement & Services

Draft Policy seems to reinforce and strengthen the role of private builders and financial

lobbies in controlling almost all the housing activities in India. For Financing Sustainable

Slum Improvement one of the recommendation is user charges. How can slum dwellers pay

user charges for the various facilities. The Government has given a low priority to provision

for shelter as reflected in the declining direct public investment on housing in the successive

Five Year Plans. It fails even to propose any viable alternative for providing and improving

the housing condition of the homeless people in the country.

13.Improving Creditworthiness of Slum Dwellers

Reforming subsidy and Rational use of Subsidy are the suggestions of World Bank and WTO.

The subsidy aspect is not feasible in our country. The poor often do not have the financial

resources to buy houses. Reviewing the housing finance system, including the access of the

poor to credit and targeted subsidies for housing, could also create opportunities for the poor.

14. Strengthening Municipal Governance and Management

The main problem in the Municipal Governance and Management are the lack of Municipal

managerial capability and financial capacity and, perhaps more importantly, the lack of

political and bureaucratic commitment to cost recovery and long term maintenance in

upgraded slums areas. The Policy does not address these issues.

Mainly due to lack of coordination between the different agencies responsible for providing

various infrastructures. In the Urban local Bodies there is a differential financial and

institutional capacity. The poorer municipalities found it very difficult to participate in the

slum development programme. Another Strategy to strengthen the Municipal Governance is

the Partnership development. Barriers to a participatory approach are likely when working

with Municipal Corporations. This is due to a rigid and hierarchical management and to lack

of experience with participatory techniques and methodologies. A significant gap in

perceptions between senior government staff ( policy makers) and field staff exists.

One of the components in the Strengthening Municipal Governance and Management is

establishment of Community Development unit in each and every local body (Sec. 14. d).

36

Page 37: Slum Rehablitiaion Report

Community Development is the most complex and difficult component in slum development.

This is due to three main factors: a) institutional constraints, when working through

Government b) the role and characteristics of Neighborhood Committees and c) the difficult

and unpredictable nature of Community Development itself.

Community Development components are prone to capture by the middle class and are often

not available to slum dwellers. Despite similar inputs being given, the impact of community

development varies from slum to slum, much more than it does with infrastructure provision.

Community Development interventions need to be slum-specific and flexible.

15. Shelter Upgradation

The Draft National Slum Policy advocates almost exclusively slum upgrading. As an

alternative to "removal", slum upgrading is likely to find immense political support.

However, there is no empirical or conceptual basis to justify upgrading as a long-term,

durable solution to the slum problem as there are no paradigms endorsing the notion that a

large percentage of the urban population must live in a small and marginal proportion of the

urban landscape simply because this option has been considered to be a misplaced one in a

just society.

16. Monitoring and Evaluation (M&E)

There is a provision in the policy to ensure participation of the community in monitoring

and to use response as a constructive resource for improvement (Sec. 16). But in reality

there are monitoring constraints for the participation of the poor and political influence in

both project implementation and monitoring.

In the Draft policy there are 14 steps mentioned. None of them have a time frame. There is a

need for a Central Act. But the policy is emphasizing all States that have not formulated a

Slum Act should consider formulating and notifying an Act, which reflects the current Policy

principles and guidelines. There is need for guidelines for laws relating to encroachments on

Government land to be revised and modified in the light of the National Slum Policy.

Issues: The immediate steps provided in the Draft policy is meant only for the States and

Urban Local Bodies. No specific steps are mentioned for the Central Government and it's

various bodies like HUDCO etc.

37

Page 38: Slum Rehablitiaion Report

Lacunae in Draft Policy

It was not based on a scientific research data base of existing slum settlement conditions,

resources and people's struggles.

It looks at housing as merely "shelter, buildings, housing-stock", that required capital

investment.

It primarily favoured the corporate sector, builders, construction firms, and real-estate

developers and was against the interests of the slum dwellers.

It abolished the State Policy and programme of subsidised/free housing and land for the

weaker sections and espoused a "free market policy".

While the Policy did address the Scheduled Castes, Tribes, Landless labourers and Women,

the strategies were so identified that affordable groups, upper classes and the commercial

sector would benefit.

It reiterated the political and policy thinking on land housing of the World Ban and its

related International Institutions.

The Draft National policy is expected to provide a new approach to an old problem evolved in

the recognition of the fact that slum residents are a major and important contributors to city

resources and form an indispensable sector, providing various kinds of skilled and unskilled

services to enrich city life and facilitate its functions. Without significant improvements in the

legal, regulatory and financial systems, the problem of slum and squatter settlements is only a

glimpse of the future. The problems of slum dwellers have multiplied in India demanding

some immediate and determined action so as to integrate the slum population with its

neighbourhood and remove the conditions that make these areas what they are today. A Draft

National Slum policy is not just a housing policy for providing shelter. One of the positive

things in the policy is they accepted that 'Much of the slum development is still "trial-and-

error" (Sec.16)

38

Page 39: Slum Rehablitiaion Report

SLUM REHABILITATION SCHEMES

Three types of SLUM REHABILITATION SCHEMES are permissible.

These types are as per the provisions of different sections of Development Control

Regulations (DCR) under which they are approved. viz.

* under provisions of DCR 33(10) also called in-situ scheme

* under provisions of section 3.11 also called PAP scheme

* under provisions of DCR 33(14) also called transit scheme

33.10 scheme

In the schemes approved under the provisions of this DC regulation, the slums are

rehabilitated on the same site.

3.11 scheme

In the schemes approved under the provisions of this DC regulation, an owner of vacant

unencumbered land can use it for construction of PAP tenements for which he is compensated

by TDR for land and for construction.

33.14 scheme

In this scheme, the landowner is allowed to consume the existing FSI potential of the land,

owned by him. The additional potential of 1.5 for suburbs, 1.66 for difficult area & 1.00 for

islandcity (only for government or public sector plots) is granted under this scheme.

The developer constructs transit tenements out of a prescribed part of this additional potential.

The balance of the additional potential is allowed as free sale component.

Special Appendix IV dealing with slum rehabilitation schemes.

1. DCR 33(10) & 33(14) exclusively deal with slum rehabilitation.

2. Incentive commercial FSI of 5% granted to the society of slum dwellers or an NGO if the

project is run by them.

3. One Balwadi and welfare center and society office each of 20.90 sq.mt areas is to be

provided for every 100 rehab tenements or part thereof.

4. Area of Balwadi, welfare center, society office & common passage upto 2.0 m wide is

allowed free of FSI in rehab building.

5. These areas and area of eligible religious structure, other social infrastructure like school,

dispensary, gymnasium run by public authority or charitable trust as well as incentive

39

Page 40: Slum Rehablitiaion Report

commercial area in addition to FSI for rehabilitation tenements are termed as Rehabilitation

component.

6. Sale component equal to 0.75 times the rehabilitation component in city areas; equal to

rehabilitation component in suburbs and extended suburbs and equal to 1.33 times the

rehabilitation component in difficult areas is allowed.

7. Maximum permissible FSI to be consumed at any site shall be restricted to 2.5 and balance

can be claimed as TDR, to be sold in open market.

8. Minimum density on plot shall be 500 tenements per net hectare.

9. All the activities existing in the slum even if non-conforming with the zone of the area shall

be allowed to be relocated.

10. All reservation plots upto 500 sq.mt. in area under slum shall be cleared of slums and the

slum dwellers shall be relocated elsewhere.

11. Plots reserved for non-buildable reservations and encumbered with slums shall be cleared

if the area is less than 500 sq.mt. or they are encumbered to an extent less than 25%.

12. Special concessions in building requirements are granted. Viz. Relaxations in open space

requirement; Relaxations in room size requirement.

SALIENT FEATURES

Features of Schemes

1. Every slum structure existing prior to 01/01/1995 is treated as protected structure.

2. Every slum dweller whose name appears in the electoral rolls as on 01/01/1995 and who

continues to stay in the slum is eligible for rehabilitation.

3. Every eligible residential slum structure is provided with an alternative tenement

admeasuring 225.00 sq. ft. preferably at the same site, irrespective of the area of slum

structure.

4. Every eligible slum structure that is being used for commercial purposes is granted an

alternative tenement having area equal to the structure subject to an upper limit of 225.00 sq.

ft.

5. A minimum of 70% of eligible slum dwellers in a slum pocket come together to form a co-

operative housing society for implementation of Slum Rehabilitation Scheme. (SRS)

40

Page 41: Slum Rehablitiaion Report

6. The underlying land is used as a resource for the SRS.

7. The slum dwellers appoint a developer for execution of SRS.

8. The developer puts in resources in the form of money, men and material for construction of

free houses for the slum dwellers.

9. The developer is compensated for his efforts in the form of free sale component.

10. The developers are allowed to construct tenements for sale in the open market. The area

allowed for sale in the open market is equal to the area of tenements constructed for

Rehabilitation of slum dwellers.

Project Example:

Dharavi Redevelopment Project

1. Introduction: Dharavi is the largest and highly populated slum pocket in Asia. Govt. of

Maharashtra has accepted the proposal submitted by Architect, Mr. Mukesh Mehta for the

redevelopment of Dharavi which, after suitable modifications, will be implemented through

the Slum Rehabilitation Authority (SRA), according to the norms of S. R. Act of 1971.

2. Development Plan: According to SRA norms, the slum dweller whose name appear in the

voters list as on 01.01.1995 & who is actual occupant of the hutment is eligible for

rehabilitation. Each family will be allotted a self contained house of 225 sq.ft. carpet area free

of cost. The eligible slum dwellers appearing in Annexure II certified by the Competent

Authority will be included in the Rehabilitation scheme. Eligible slum dwellers will be given

rehab tenement in Dharavi.

3. Transit Tenements: During the implementation of this project, Dharavi residents will be

provided with transit tenements, in close proximity of Dharavi or in Dharavi itself. The

developer will bear the cost on account of rent of the transit tenements but the cost of

expenditure of consumables like water, electricity, telephone etc. will have to be borne by the

slum dwellers.

4. Sustainable Development: The development plan for Dharavi has many amenities in it;

viz. wider roads, electricity, ample water supply, playgrounds, schools, colleges, medical

centers, socio-cultural centers etc. For proper implementation, Dharavi has been divided into

41

Page 42: Slum Rehablitiaion Report

10 sectors and sectors will be developed by different developers. The total duration of this

project is excepted to be of 5 to 7 years. Rehabilitation building will be of 7 storeys.

5. Development Procedure: After considering the redevelopment plan, a detailed plane table

survey has been carried out to know the ground realities. Also, consent of the slum dwellers to

join this project is being obtained. After obtaining suggestions & objectives from the public

for the revised development plan, the same will be finalized by Govt. For each sector a

detailed sectoral plan will be prepared by the selected developer in consultation with

SRA.This will be placed before the public for suggestion/objectives and then finalized after

due amendments.

6. Appointment of the Developer: Global tenders will be invited from developers for this

project. The developer will be evaluated technically and financially by a Committee headed

by the Chief Secretary of Government of Maharashtra. Each developer is required to explain

his development strategy in his sector and obtain objectives & suggestions from the residents

before starting the development process.

7. Development of local Industrial units: Taking into consideration the various industrial

units in Dharavi, it is being proposed that, non-polluting industrial / businesses will be

retained in Dharavi itself. All the established businesses and manufacturing units will be

encouraged and will be provided with modern technical and economical strategies for

sustainable development

42

Page 43: Slum Rehablitiaion Report

Correlation Analysis on International Level

How did US Tackled its Slums?

US had its share of poverty and slums in around the immigrant dominated cities. New York

and Boston had great amount of poverty and slums at the turn of the twentieth century. These

slums were further worsened with the arrival of newly liberated African-American population

from Deep South. The era pictures give a glimpse of everyday life and it is not pretty. People

without job and with no prospects crowded cities in the North. A new word, Ghetto was

coined, which described these places. Immigrant from different background or race crowded

together and gave rise to Ghettos. At that time US did not have control over its economy and

Civil War debt and additional monies borrowed to rehabilitate agriculture and commerce after

the Civil War was unpaid. As twentieth century progressed a concerted effort was made to

clean up the Ghettos and push people inland with free grant of land and promise of prosperity.

Industrial Revolution, which was slow in reaching America from Europe, finally arrived. And

it made the difference. It provided the much-needed jobs to the immigrants and colored. Also,

free land in the West gave rise to food self-sufficiency and paying off of all Civil War and

post Civil War debts. First World War gave US economy a boost and America joined the

select group of countries of Europe in prosperity. Poverty by the end of the Second World

War was a thing of the past. In just fifty years, i.e. by 1950, US were nation of 160 million

souls, all prosperous and all well employed (forget the habitual lazy). That does not mean that

all the Ghettos disappeared. They continued to exist. They exist today, but on a much lower

scale. These are not eyesores.

One critical factors which vanished slums and poverty in US was quadrupling of the US

economy from 1900 to 1940. A free wheeling economy created industrial giants and a super

rich class. Need for war material during the WWII resulted in creation of huge industrial

infrastructure and innovation. Post war reconstruction in Europe added greater impetus to the

economy. General well being of the people living in the poorer section of the cities

dramatically improved. US raced ahead of Europe and are still ahead, 60 years after the

WWII. In most cities, ghettos disappeared or shrunk. Urban renewal and building boom in last

sixty years has completely changed the landscape of the country.

43

Page 44: Slum Rehablitiaion Report

There is a parallel here. Poverty and slums in India are at the same level as they were in

beginning of the twentieth century in America. Economic growth over fifty years vanished

them. The same is possible in India if the economy sustains the 8% growth trajectory.

Slums and the Great Briton

Great Briton was a great big slum before they became a colonial power in the nineteenth

century. For eight hundred years prior, until 1800s, Great Briton was an agrarian society,

where the lord lived happily in his Manor and Castles and the masses lived in a great squalor.

Slums were everywhere. London had the biggest slums. Colonization brought prosperity and

prosperity brought in a huge effort to improve the lot of the people and clean up of the cities.

That is when the unemployed and slum dwellers were pushed to newly developing industrial

hubs of Sheffield, Birmingham, Liverpool and Manchester. Compared to that Delhi, Kolkata

were heavens. First slums in Kolkata appeared in 1850-70 as a result of systematic destruction

of textile industry in Bengal and destruction of trading infrastructure in and around Kolkata.

Slums elsewhere followed.

It took all the Victorian age from 1825 to 1900 to vanish poverty and slums in England.

Their GDP multiplied 8 times over this period. British factories produced goods and services

which were sold at profit in the in the colonies. Work for everybody in England was the

cornerstone of building well-serviced cities.

The point is that vanishing poverty and slums follow closely with economic development.

Faster the economic development, sooner will the poverty vanish and with it, the slums.

How did China handle its Poverty and Slums?

Chinese had a unique way of making slums disappear from its urban centers. Permit system to

live in a city or in a particular neighborhood was introduced just after the Communist took

control in 1949. That means that great rural population migration to the urban areas in search

of jobs was arrested. In addition the war ravaged eastern provinces where rural population had

moved to the cities and into the slums, were emptied out. Nobody questioned Mao Tse Tung’s

wisdom; hence he had a free hand. People were permitted to return to their homes in the cities

only after proof of their residency had been established. Outsiders were sent back to their own

homes and land in the rural area. Future residency in the cities was permitted on a permit

44

Page 45: Slum Rehablitiaion Report

basis only. Hence major problem of unplanned urban squatting was prevented. Even today the

foregoing policy continues. The FDI built cities of Guangdong province carry on with the

permit system established in 1949. In order to move there, a person has to have a job and

place to reside. The latter could be a factory provided bunk bed. This prevents urban squat.

The above is no comparison to how poverty was vanished in UK, US and elsewhere. Major

economic progress in last 20 years has re-invigorated the cities with investment and

reconstruction. Whether the same is true in the China’s rural areas is a debatable issue. China

likes to pretend that poverty has been vanished.

Urban Renewal In India

Urban renewal is in progress in India in a big way for the last 50 years. The British starved

cities in India of the funds for two hundred years. They only built regal palaces for

themselves in Delhi, Shimla and Kolkota. No new monies was made available to the people

to renew and rebuild, hence Moghul Delhi presented a decaying and a rundown look, when

they finally left India in 1947. The problem got compounded with migration of people from

rural areas. Expanding industry and commerce needed them hence migration was

encouraged. Thus urban slums and squatting began in a big way. Today, some estimates

place 10 to 15% of Delhi population as slum dwellers. Slums in Kolkata predate Delhi

slums. So do the Mumbai slums. They all began the same way – people’s livelihood was

destroyed or they were invited to work in factories without adequate housing. The problem

grew acute with huge population growth after 1950. From 1950 to today, cities lacked funds

to renew themselves and help build additional housing. People lacked adequate jobs hence

are caught in the poverty cycle.

Only recently a huge building and construction boom has started in all cities in India.

Whereas governments are concentrating on building infrastructure and industrial base,

private construction is building work places, shopping districts and housing for the middle

class. The poor and slum dwellers are not there in any building equation. Cheap housing

projects are lowest in the category. Hence slum dwelling has become a way of life.

45

Page 46: Slum Rehablitiaion Report

How Long the Poor have to wait?

If the experience elsewhere is a guide then poverty, slums and urban squat will be a vanishing

phenomenon, if the rapid economic progress keeps its pace. Today we would have smaller of

the slums, had economic policies of the present were in place 50 years back. Only now, all

signs point to a rapidly rising GDP together with rising per capita GDP. With rise in income

level, tendency to head to the slums has lessened. Die-hard slum dwellers that wish to pay no

taxes and spend nothing on housing will most certainly continue to stay there. Others will

prefer to move out. This is a normal phenomenon. It happened in US and elsewhere. It will

happen in India too. An economic equilibrium has not been reached in the society yet, where

enough money in people’s pocket will persuade them to vacate the slums. This won’t we

reached for another 20 to 25 years. By about middle of this period with increased availability

of housing and higher incomes, the growth in slum dwelling will be arrested. Decline will

begin only when much higher incomes are reached (as stated above), provided India does not

make the mistake of regularizing the slums/bustees with land tenure on tenable land and other

amenities. That is a sure fire method to keep the slums going. People will always wait for free

grant of land ownership even if these grants never materialize. Even the possibility of this

ever happening in a distant future will keep the slum dwellers in the slums.

.

46

Page 47: Slum Rehablitiaion Report

CHAPTER – IV

CONCLUSIONS

I VARIOUS REQUIREMENTS FOR SLUM DEVELOPMENT

Slum Development has four sectors and eight programmes that are

separate functional units but have intrinsic linkages. These programmes

address specific needs in the slum and are designed to be dynamic. All

programmes presuppose:

i) Tangible measurable actions and results,

ii) Community participation,

iii) Time bound management by CBO,

iv) Payment for services, and

v) Linkages with existing government/private initiatives.

ISD could start with any programme, either singly or in combination

depending on the need in the slum and availability of resources. There are

four sectors of the ISD, as listed below:

1 Services Sector - Community Health Programme

- Non-Formal Education Programme

2 Livelihood Sector - Skill Imparting Programme

- Savings and Credit Programme

- Income Generation Programme

3 Infrastructure Sector - Physical Upgradation Programme

4 Participation Sector - Community Participation Programme

- Partnerships

47

Page 48: Slum Rehablitiaion Report

Goals and Objectives of the Services Sector

Programmes Goal Objectives Community Health Programme

To improve overall health status through preventive and curative community based methods

Awareness about prevention and cure of common illness· Community health services

through slum based health workers and OPD

· Reduce maternal and infant mortality

· Address specific illness such as TB and Malaria

· Linkages with government health systems for referrals

· Demystify health belief Non Formal Education Programme

To increase the education status by making critical innovative interventions

Increasing enrolment and decreasing dropout rate

· Enable children cope with school curriculum

· Use of Innovative teaching methods

· Involve parents and community in children’s education

· Increase education levels amongst dropout and non-school going children especially girls

· Increase literacy levels amongst adult residents.

48

Page 49: Slum Rehablitiaion Report

Goals and Objectives of the Livelihood Sector

Programmes Goal ObjectivesSkill Imparting Programme To increase and reinforce

earning skills of slum residents

· Identify and Increase earning skills

· Impart and enable training for acquiring skills

· Create support for practising these skills

Savings & Credit Programme To enable savings and access to formal credit and reduce dependence on usurious money lenders

To create savings options of for affordable amounts· To form a credible

savings society· To have a credible and

transparent record keeping system

· To offer fast and affordable credit

· To facilitate capacity building of SHGs and practitioner NGOs.

· To strengthen the movement for using micro-credit as a tool to empowerment.

Income Generation Programme

To increase options and infrastructure for increasing incomes

To identify market based income generation options

· To build capacities for these skills (Human and Institutional Support)

· To set up institutions that can independently undertake IG operations

· To mobilise financial assistance, programmes and other resources from banks, Govt.,voluntary organisations.

49

Page 50: Slum Rehablitiaion Report

Goals and Objectives of the Infrastructure Sector

Programmes Goal ObjectivesPhysical Upgradation Programme

To ensure that every household has access to basic services

To facilitate access to basic services such as water, drainage, and toilets on a household basis,· To facilitate paved roads, street lighting and solid waste management· Housing after infrastructure· To ensure maintenance of household and common services

Goals and Objectives of the Participation Sector

Programmes Goal ObjectivesCommunity Participation Programme

· To enable long-term sustenance of ISD through community participation in implementation, management and financial contribution.

To create technical, managerial and leadership capacities · To enable and nurture community based institutions that can sustain relevant ISD initiatives.

· Partnerships To integrate municipal, state and NGO/Private Sector initiatives.

Reduce duplication of efforts· Proactive synergetic working methods that lead to attainment of objectives· Holistic approach to development

50

Page 51: Slum Rehablitiaion Report

II PROGRAMMES NEED TO BE INITIATED

Awareness among residents towardsi) education

ii) health

iii) nutrition

iv) employment

Community Health Programme (CHP)i) A 24-hour access to health consultation/services through the CHWs,

ii) An OPD where basic health services will be available,

iii) A comprehensive mother and child cared programme consisting of gynaecological care

and immunisation during pregnancy, enabling safer deliveries and postnatal care and

complete immunisation of children,

iv) Referrals to government and municipal clinics,

v) TB Control, and

vi) Awareness about preventive health methods.

There will be nutrition support inputs for Pregnant and Lactating Mothers (PLM) and TB

patients to change food habits and ensure compliance to check – ups, immunisation and

treatment. Residents would pay for consultation at the dispensary, conveyance costs during

referrals and nutrition support.

Non Formal Education Programme (NFEP)

The activities in the education programme are:

i) Pre-school nursery classes with a curriculum that would prepare children cope with

primary education,

ii) Supplementary classes with a curriculum that would enable children cope with regular

school curriculum, and

iii)Special classes for non-school going and dropout children.

51

Page 52: Slum Rehablitiaion Report

The residents would pay monthly fees for balghar (pre-school), supplementary and special

classes and for conveyance costs for outings of the children. There have been regular

interactions with the parents through meetings and family visits.

Skill Imparting Programme (SKI)

A pressing need of the residents is to acquire skills that were marketable. Various types of

courses to impart such skills will be conducted in the slum. These are:

i) Tailoring and embroidery,

ii)Electric gadget repairing,

iii) Scooter repairing,

iv) Computer typing,

v) Electrician,

vi) Plumber etc

The tailoring and embroidery course has been run from 1993. The participants have been

women and adolescent girls who use these skills at home or for earning. The course has also

provided an important forum for the adolescent girls to discuss their anxieties relating to

marriage, marital home and sex. Like other programmes, for this also, the participants pay

monthly fees and bear material costs.

52

Page 53: Slum Rehablitiaion Report

III Case Study of Chandigarh:Basic Services To The Urban Poor

Introduction

In Chandigarh, more than one fifth of population reside in slums, squatters and other

rehabilitated colonies. Their contribution to city’s economy has been also been growing over

the period. In the absence of developed land and clear policy to address their problems, the

poor suffer from many inadequacies in terms of access to basic services, socio- economic

needs. It is necessary, therefore, to articulate policies and programmes to mainstream the slum

communities with the city, both in terms of infrastructure provision and social and economic

development.

Population below Poverty Line

As per the available data, the number of people living below the poverty line was 94485 as

per census 2001 and fresh survey is in the process in U.T., Chandigarh in rural and urban

sectors.

SOCIAL COMPOSITION OF POPULATION

Year Number of the poor*

1999 / 00 94485 (in 3/2000)

2004 /05 (Estimated) Fresh survey under process.

*Below poverty line

Growth of Slums and Slum Population

Chandigarh city is characterized by a very significant presence of the urban poor, with a

growing poverty profile. Slum settlements have multiplied over decades and the living

conditions of the poor have not improved. Environmental decline, vehicular pollution,

inadequate basic services and infrastructure in the poor settlements hit the poor hardest. Slums

are scattered around the city on its periphery, with high population densities and the number

of people inhabiting them estimated to be around 1.5 lacs. It is estimated that more than 90%

of these slums are on govt. land, and the rest on lands belonging to various farmers. Poverty

has a visible gender dimension too. The incidence of poverty among women is higher and

female-headed households constitute the poorest of poor. The number of slums and slum

53

Page 54: Slum Rehablitiaion Report

population in the city has been increasing at a faster pace over the decades. The slum

population is emerging on the out- skirting of city as detailed below:

1. Colony No.5 located in Sector 50 area of which is under development. This is the biggest

slum area of city.

2. Colony No.4 located near Industrial Area, Ph.I near Sukhna choe, which is being polluted

by open defication.

3. Bapu Dham Colony is located in northern eastern area Chandigarh near Timber Market,

Sec.26.

4. Janta & Kumhar Colony is located in Sector 25.

5. Lal Bahadur Shashtri slum is located in Sector 56 area on border to S.A.S.Nagar (Pb.).

6. Rajiv colony slum is located in Sector 38 (W) area.

Socio-economic Characteristics of slum population

Communities

Slum population in Chandigarh is not much heterogeneous in character – because Hindus are

in majority besides very less population of Muslims having migrated from U.P. and Bihar. A

language predominantly spoken in slums in Chandigarh is Hindi. These people have migrated

to Chandigarh in search of job. These workers are mostly engaged on construction work. The

mason, fitter, electricians and helpers are their main profession. Actually there is demographic

shift, the original professional work just carpenter, mason etc. have migrated to Gulf or

European country where people from U.P. and Bihar have shifted to Chandigarh to take lead

in construction work/activity, but Chandigarh Administration and Municipal Corporation used

to make efforts from time to time to provide protected water supply, common toilet block,

sanitation etc. Every slum in Chandigarh is provided with potable water supply as stand post

as well as community toilet block and mobile toilet vanes. But with increasing pace of

migration of slum population in Chandigarh, even then open defecation in certain area not

ruled out. Now Municipal Corporation has made elaborated arrangement to provide sulbh

sauchalyas in colony No.5 and 4 to eliminate open defecation from city.

Even Health Department Is also always on palm to avoid to any epidemic because usage of

raw fruit, unhygienic meat, cold drink by the slum people. Even because of lack of civic sense

54

Page 55: Slum Rehablitiaion Report

by slum dwellers, the task of controlling the epidemic is very daunting. The status of water

supply and sewer for slum is as under :

ACCESS OF THE SLUM DEVELLERS TO BASIC SERVICES

Year Number of slum % of slum dwellers having access to dwellers Water supply

Drainage System

Waste service collection

1991 0.5 lac 100% 70% 70%

2001 1.25 lac 100% 75% 80%

2005 1.5 lac 100% 80% 90%

Environmental Conditions and Health Status

The environmental conditions in slums are no doubt poor and lack basic civic amenities.

Earlier studies have recorded that the common diseases prevalent in slums in Chandigarh

are gastro-enteritis & dysentery, liver, Typhoid. To overcome these hazards health

infrastructure have been geared up by distributing medicines and chlorine tablets and

preventing hygienic conditions.

Basic Infrastructure

Access of slum population to basic services is a key indicator of the quality of life in

slums in particular and the city in general.

55

Page 56: Slum Rehablitiaion Report

IV Working Model

Initially, the project scope is defined and the appropriate methods for completing the project

are determined. Following this step, the durations for the various tasks necessary to complete

the work are listed and grouped into a work breakdown structure. The logical dependencies

between tasks are defined using an activity network diagram that enables identification of the

critical path. Float or slack time in the schedule can be calculated using project management

software. Then the necessary resources can be estimated and costs for each activity can be

allocated to each resource, giving the total project cost. At this stage, the project plan may be

optimized to achieve the appropriate balance between resource usage and project duration to

comply with the project objectives. Once established and agreed, the plan becomes what is

known as the baseline. Progress will be measured against the baseline throughout the life of

the project. Analyzing progress compared to the baseline is known as earned value

management.

The inputs of the project planning phase include Project Charter and the Concept Proposal.

The outputs of the Project Planning phase include the Project Requirements, the Project

Schedule, and the Project Management Plan.

Proposal for bulding houses for slum rehabilitation:

(i) Ten Buildings may be constructed having 10 floors with 20 households each of 225 sq.

feet area mounting to 200 houses per building.

(ii) Total roof area covered around 6000 sq. feet n Grand area of 1200 sq. feet.

(iii) Solar panel installed on roof of the buildings for supply of electricity to households.

(iv)Rain water harvesting system to ensure regular supply of water.

(v) Kitchen waste fed to biomass treatment plant and natural gas obtained would be supplied

in households and bathroom waste to water treatment plant for recycling.

(vi)Grievance committee should take care of any conflicts between residents.

(vii) Federation would take care of carious facilities granted and their proper use and report

any illegal action.

56

Page 57: Slum Rehablitiaion Report

Finance Pooling other than Govt.

(i) NGO or any PPP may take the project to make it financially viable and contribution

from residents by awareness among them.e.g. HUDCO.

(ii) Venture Capital Funds

(iii) Houses may be allotted with a nominal token money and rest of the amount may be

recovered in monthly installment with a very soft interest and term of 20 years.

(iv) Relaxation or grace period may be given till the person receives training.

(v) Ration cards and voter cards may be given for other privileges.

(vi) Leasing to Private Partner for commercial establishments.

(vii) Real Estate Investments by People on resale of plots.

Planning, Monitoring and Evaluation

(i) The annual plan mentions the type of resource persons required and duration of their

training. It also mentions the type and nature of involvement of the government and

other NGOs

(ii) When all the programme plans are ready, they are presented to the whole team, where

the integration of activities and programmes is clarified, and, everybody is aware of the

year’s activities and the method of implementation and monitoring.

(iii) The annual plans, with the local workers and co-ordinators would be made.

(iv)Involvement of local workers and other co-ordinators, and linkages of a single

component with other programmes and activities

(v) Two types of monitoring meetings are held every month in which monitoring formats

with relevant data are presented. One type is the monitoring at the field/activity/

programme level, where the local workers fill and present their forms. The second type

is at the sector level where the co-ordinators report the work done to the core team.

(vi) At the end of the year, the year’s work is evaluated in a participatory method, where

major modifications are suggested, which are then incorporated into the next year’s

annual planning.

57

Page 58: Slum Rehablitiaion Report

(vii) Encourage local participation.

V Flat Design

58

Page 59: Slum Rehablitiaion Report

VI CRITICAL PATH METHOD – ACTIVITY ON NODE

59

Page 60: Slum Rehablitiaion Report

The learnings or Recommendations:

60

Page 61: Slum Rehablitiaion Report

I Alternative Policy-Regulatory Framework

An Alternative Housing Policy as seen from the point of view of the slum dwellers

themselves. Firstly, it is clear that the vast majority of the city's population (77%) lives in

sub-standard or non-existent housing.

Secondly, the density in the slum clusters has increased six-fold in the last 25 years.

This policy will have the following components:

(i) Locate land within a one kilometre radius of the existing slum whose land use can

be appropriately notified as 'residential'.

(ii) Allot one plot of 50 Sq.m. to each family on leasehold basis on payment of a fee

not exceeding Rs. 10,000 per plot.

(iii) Provide connections to basic urban services (water, electricity, sewerage,

roads, drainage, dispensaries, schools) at the rate of Rs. 200 per Sq.m.

(iv)Supply services through public agencies, and not contractors, according to realistic

urban norms.

(v) Charge fees for supply of services on a monthly basis as per public policy.

(vi)Make available housing loans of up to Rs. 50,000 on easy terms against mortgage

of land.

Such a policy will provide security of tenure to enable investments in proper housing;

leave the earning capacity and available services of the household undisturbed;

maintain investment within the earning capacity of the family;

allow the entrepreneurial spirit of the people free rein;

give an adequate return on investment to public agencies; and

enhance the value additions in the quality of life in the city as a whole.

61

Page 62: Slum Rehablitiaion Report

II Implementation:

(i) The planning, targets, budget and scheduling are realistic and generally attained because

residents, grassroots implementers and co-ordinators have been involved in decision-making.

(ii) As the budget and other resources available are known at the beginning of the year, there

is considerable confidence in implementing activities.

(iii) The amount of learning and self-confidence amongst co-ordinators and local workers is

considerable because the amount of work inputs and outputs seen are ‘black and white’, that

is transparent. This perhaps is the crucial aspect of the monitoring process amongst local

workers. Women, who may have studied up to class 7 or 10, working as health workers or

teachers, are involved in preparing an annual plan with a monitoring format, which is

regularly filled by them. This generates an enormous amount of self worth because their

achievements are recognised in very concrete terms.

(iv) A very effective management system is learnt and evolved, which has been found useful

in not only implementing activities and programmes, but in other aspects of daily living.

(v) Considerable amount of data is generated which enables better monitoring,

implementation and planning.

(vi) A sense of fulfilment, of having done work to one’s best ability is created which augurs

well for individuals and organisations in the short and long term.

(vii) For such a system to work, values of openness, trust and concern are of paramount

importance amongst all persons involved in various Slum Development programmes.

(vii) Partnerships and Participation in Slum Development.

III Mechanism:

The thread that holds System together is the inbuilt mechanism that facilitates partnership and

participation. Participation of residents has been for:

(i) Selection of qualitative and quantitative aspects and changes in Slum Development

programmes,

(ii) Selection of local workers,

(iii) Quantity of monetary contribution by residents,

(iv) Selection of ISD centres and

(v) Leadership and functioning of CBOs.

62

Page 63: Slum Rehablitiaion Report

IV Partnerships in Slum Development :

Partnerships with the Urban Local Bodies (ULBs), NGOs, State Government, private sector,

voluntary organisations, academic institutions and students. The partnerships have been in the

areas of:

(i) Slum Development programme and activity implementation,

(ii) Capacity building,

(iii) Evaluation and review and

(iv) Research.

V Sustainable Partnerships in Slum Development because:

(i) Structures that facilitate collaborative initiatives,

(ii) Proactive facilitation and integration of different objectives of the partners,

(iii) Acceptance and accommodation of differing working styles of the partners,

(iv) Recognition of efforts put in by all the partners,

(v) Sustainable processes that enhance partnerships established, and

(vi) Objectives of the partners are met.

Poverty, slums and urban squat are not going to go away in next 20 to 25 years. Reversal of

this phenomenon will begin after sufficient economic progress had been made. Eight percent

GDP growths is a good sign. With quadrupled GDP in 25 years, there is a good chance that

the new and upcoming generation may stay away from slum dwelling. It may take another 25

years before the slums are vacated.

Though the draft Slum Policy pretends to be pro-poor. This advocacy is more pretentious to

help the urban poor. But in practice it helps in increasing the prosperity, well being and illegal

income of PBIGs. The grass root struggle organizations in the country are well aware that this

draft has been designed contrary to providing land at an affordable rate to the urban working

class..

63

Page 64: Slum Rehablitiaion Report

CHAPTER – V

LIMITATIONS

1. Risk Analysis has not been covered as quantification is beyond scope as various risk

factors comes into play whrn yisualisation of such a project comes to ground reality.

2. Failure to collect and analyse data that would yield a quantitative assessment of the

relationship between time and cost of rehabilitation.

3. Old and out of date data as available on internet and other sources, as the slum

population is migrating and is easily influenced by other factors inhibiting accuracy

levels of data.

4. Long term treatment effects have not been dealt.

64

Page 65: Slum Rehablitiaion Report

BIBLIOGRAPHY

1. www.google.com

2. www.sra.gov.in

3. The Challenge of Slums : Global Report on Human Settlements 2003

4. http://merachandigarh.in/panchkula-news/slum_dwellers_flat_huda_panchkula.html

5. https://jnnurmmis.nic.in/writereaddata/Sanctions/IHSDP/.../IHSDP-10.PDF

6. www.spaceofdemocracy.org/.../Node%20workshop%20Pradeep%20 Abstract .doc

7. www.unescoihe.org/Integrated%20urban%20 slum %20infrastructure%20 developmen t

8. www. development inpractice.org/.../role-government-and-ngos- slum - development -

situation-dhaka-city

9. www.tn.gov.in/gorders/maws/maws_e_87_2010_D.pdf

10. http://eau.sagepub.com/cgi/content/abstract/13/2/45

11. www.homeless-international.org

12. www.sparcindia.org and www.nirman.org

13. www.sdinet.org - for more information about SDI

14. http://www.economist.com/World/asia/displayStory.cfm?story_id=5636460

65