SLUM ELECTRIFICATION AND LOSS REDUCTION PROJECT …documents.worldbank.org/curated/en/... · supply...
Transcript of SLUM ELECTRIFICATION AND LOSS REDUCTION PROJECT …documents.worldbank.org/curated/en/... · supply...
For Official Use Only
Page 1 of 21
SLUM ELECTRIFICATION AND LOSS REDUCTION PROJECT
Improved Electricity Access to Indian
Slum Dwellers Project
EEnnvviirroonnmmeennttaall aanndd SSoocciiaall MMaannaaggeemmeenntt FFrraammeewwoorrkk
AApprriill 22000077
Stakeholders involved:
E1643
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
For Official Use Only
Page 2 of 21
Table of Content 1. Background:................................................................................................... 3
2. Analysis of Issues and Anticipated Environmental Impact ............................. 4
3. Environment Baseline: ................................................................................... 4
4. Description of slum project site: ..................................................................... 4
5. Current commercial and industrial activities at the project sites:.................... 5
6. Environmental Aspects of Project .................................................................. 6
6.2. Sources and quality of water supply: ............................................................. 6
6.3. Waste water disposal and sanitation in project slums: ................................... 7
7. State of submergence during rain and cases of flood: ................................... 7
8. Layout plan of existing distribution lines as well as sub station sites: ............ 7
9. Records of environmental incidents and remedial steps taken : .................... 7
10. Fire & Shock Complaints: .............................................................................. 8
11. Analysis of Anticipated Environmental Impact(AEI) ....................................... 9
12. Environmental Management Plan ................................................................ 10
13. Institutional Structure for EMP Implementation, Monitoring and Reporting: . 18
For Official Use Only
Page 3 of 21
1. Background:
1.1. The United States Agency for International Development (USAID), in
cooperation with the International Copper Association (ICA), is implementing the
Slum Electrification and Loss reduction (SELR) Program, a three-year program
for regularizing electricity services in slum areas. In India, USAID is working in
cooperation with the World Bank’s Global Partnership for Output-Based Aid
(GPOBA), Reliance Infrastructure Limited (branded as Reliance Energy) and the
International Copper Promotion Council of India (ICPCI), to implement a pilot
program in the Shivajinagar slum cluster.
1.2. The objective of the project is to demonstrate the use of an output-based aid
(OBA) approach to make a significant difference to the level of access to safe and
adequate electricity supply in the Indian slum context. It is intended that a total of
26,250 connections will be subsidized. Of these, some 5,000 will be existing
customers that will benefit from upgrades to their connections. It is expected that
such an approach could be replicated in other major Indian cities, where slum
areas abound and access to legal and safe electricity remains elusive for many
slum dwellers. The project anticipates that Reliance Energy will undertake all
investments required to take electricity to the slum areas which include upgrades
to the network, drop lines from substation, meter panel and household meter.
GPOBA subsidy would be used to cover the portion of the cost of a new
connection, for regularization of connections and for providing safe internal
wiring. Regularization of connections addresses those connections which are
currently served by Reliance Energy informally or which do not have proper
internal wiring or rewiring between the meter box and the DU. This project also
addresses promotion of productive uses of energy to help ensure slum dwellers
are able to pay their bills by enhancing their ability to generate additional income.
This will maximize the socioeconomic benefits to the slum areas by having the
legal connection. Thus this project will include activities working with local
NGOs/CBOs to encourage the development of small business ventures and
commercial services that are made possible by the legal electricity connection.
Areas under this component may include micro-enterprise development, business
training, access to existing microfinance schemes, gender empowerment through
income generating activities etc.
1.3. The anticipated outcomes of the project would be:
1.3.1. Delivery of legal and safe electricity connections for 26,250 slum dwelling units
(DUs), which would include upgrades to utility network and substations,
installation of meters, and about 5,000 existing customers to have their wiring
upgraded.
1.3.2. Documentation of program outputs and results as well as economic and social
impact data (safety, efficiency, productive uses).
For Official Use Only
Page 4 of 21
1.3.3. Development of a replicable program model and subsidy scheme to implement
future slum electrification programs in India and elsewhere.
1.4. GPOBA, World Bank as part of their funding procedures has to undertake the
following tasks:
1.4.1. Financial due diligence of the private sector
1.4.2. Specify norms and procedures for bidding the contract
1.4.3. Environmental impact assessment and devise environmental management plan to
mitigate the impact.
1.5. World Bank mission visited the project area in Mumbai to assess key
environmental risks associated with this project. The mission advised to develop
an Environmental Management, and Monitoring Plan, which should include tasks
to be undertaken by Reliance to mitigate the environmental impact caused by the
project.
1.6. Reliance undertook feasibility study and carried out environmental impact
assessment of the sites under this project. Based on the environmental impact
envisaged, an environmental management and monitoring plan has been
developed.
2. Analysis of Issues and Anticipated Environmental Impact
2.1. As part of project preparation efforts, USAID commissioned a socio-economic
survey of the two target slum areas under the project. The survey captured
information on the demographics, literacy level, current income, willingness to
pay for the legal connections and current stock of appliances and equipment used
in the dwelling units.
2.2. Reliance team under guidance from World Bank also undertook Environmental
Impact Assessment of the 2 slum sites and has prepared an Environmental
Management Plan to mitigate the environmental impact of the project.
3. Environment Baseline:
3.1. The environment baseline study is undertaken to understand the present
environment situation of the project areas. Please find below the details of present
environmental status in the area.
4. Description of slum project site:
For Official Use Only
Page 5 of 21
4.1. The location map of Shivaji Nagar Area and the defined boundaries of the project
are indicated in the map below. The Shivaji Nagar site is situated on the eastern
suburb of Mumbai. It occupies an area of about 20 acres. Originally the area was
a creek surrounded by marshes. Due to the dumping activity, the area was also
used for agricultural purposes up till the 1960’s. The slums began mushrooming
in the 1970’s when the Shiv Sena corporator Shri.Ambarnath Patil won the
election. After the 1970’s due to the presence of the bone factory, the
slaughterhouse, the dumping yard the density maximized. As the land belongs to
the BMC and the Collectors office, the BMC marked rectangular plots for re-
housing the project-affected families. The leadership in this area has been
foresighted and the population as a vote bank has been successful in obtaining
substantial basic amenities for themselves. Prior to the railway linkage and road
linkages the significance of this area lay in its proximity to the dumping ground
and to the Deonar abattoir. The slum pocket has possibility of developing into a
satellite city of New Bombay, and it is likely to get transformed in the near future.
Figure 2: Shivaji Nagar Area
The area can be en-marked by following boundary limits,
Dumping Ground to the east of area.
Rehab Housing Compound to the west of area.
Ghatkopar Mankhurd Link Road to the south of area.
Nabhela Parekh Marg to the north of area. 5. Current commercial and industrial activities at the project sites:
For Official Use Only
Page 6 of 21
5.1. In Shivajinagar area, most of the structures are residential (83%, see Figure 4),
with ground floor (53%), ground floor +1 (37%) and balance are temporary shed
type structures.
Figure 4: Usage of Structures in Shivaji Nagar area
5.2. The primary commercial activities in this area are shops (52%) that deal in trading
of products and service (38%), which includes services of the barber, the
electrician, the mason. Some industrial activities carried out are: chappal (shoes)
manufacturing units, zari & embroidery works fabrication work, etc.
6. Environmental Aspects of Project 6.1. Shivajinagar is spread over more than 15 acres of land. The population of
Shivajinager area is around 2,00,000.
6.2. Sources and quality of water supply:
6.2.1. The drinking water to slums is supplied by Municipal Corporation of Greater
Mumbai (MCGM) through regular taps. The water supply system of these slums
is an integral part of water supply system of entire Mumbai City. Source of water
supply is from Bhatsa, Upper Vaitarna, Modak Sagar, Tansa, Vihar and Tulsi.
Main water pipelines are laid at a depth of 5 to 6 metres and hence there are less
chances of it getting damaged. The project during implementation may damage
individual drinking water pipeline, which is at shallow level. Measures will be
undertaken to mitigate this.
6.2.2. Main causes of contamination include, leaky joints in service connections, mixing
of sewerage and drainage system with water supply system, unclean suction and
over head tanks, deteriorating internal lining of water mains and seepage of
surface water to mains through lead joints. Fortunately, project does not envisage
these causes during implementation.
Use of Structure
Residential
Resi-cum-commercial
Commercial
Home basedmanufacture
Figure 1: Use of Structure
For Official Use Only
Page 7 of 21
6.3. Waste water disposal and sanitation in project slums: 6.3.1. Municipal Corporation of Greater Mumbai (MCGM) is the sole authority
responsible for wastewater disposal and sanitation in Mumbai. The sewage
pumping facility in the city has been divided into 7 service areas. Ghatokopar
service area caters the present project site of Shivaji Nagar.
6.3.2. MCGM also provides sanitation facilities to the slums. Under the Dattak Vasti
Yojana the following services are provided to them through CBOs.
6.3.2.1. Solid waste collection, handling and transporting the collected waste to the
designated areas.
6.3.2.2. Cleaning the open spaces around toilet blocks
6.3.2.3. Cleaning of toilet blocks and nearby drainages
6.3.3. The projects under consideration also do not envisage any effect on these
facilities.
7. State of submergence during rain and cases of flood: 7.1. In general, Mumbai is subjected to heavy flooding during the rainy season
depending upon the rate of rainfall and high tide or low tide timings. After June
2006 floods, care has been taken to uplift the electrical installation above flood
level. MCGM is already in process of implementing Mass water drainage system
for entire Mumbai under the project name ‘BRIMSTOWAD’. Under this project
laying of new drains, developing effective drainage system and deepening and
widening of nallas is planned for entire city. The indicative timeframe of the
project is 2007-2009 (Source: www.mcgm.gov.in/contents/subm64ssmno 145ver2eng.pdf)
8. Layout plan of existing distribution lines as well as sub station sites:
8.1. The layout plan of all existing distribution lines and sub-stations are attached as
Annexure.
9. Records of environmental incidents and remedial steps taken :
9.1. On 26th July 2005, the highest ever rain fall amounting to 944 mm was recorded
in period of 12 hours in Mumbai coupled with high tide at sea. This led to water
levels rising to unimaginable levels. Heavy down pour of this magnitude occurred
after 40 years in Mumbai region. Situation has become worst because
accumulated water could not be drained since drainage valves were closed
because of high tide in sea.
For Official Use Only
Page 8 of 21
Figure 5: Rainfall July 2005
9.2. During the deluge, many of electrical installations were submerged in the water.
This resulted in supply interruptions of longer hours. To mitigate the effects of
such deluge in future, the installations are raised at sufficient height. Every years
the levels of water logging is observed, and if required installations are raised.
10. Fire & Shock Complaints: 10.1. Table below shows the complaints received from the area considered under
project for last one year.
Nature of Complaint Numbers
Shivajinagar Area
Blast Sound 13
Cable/Wire/Jumper Burning 109
Cable Fault 23
Fire 113
No Supply 26
Shock 20
Short Circuit 19
Smoke 53
Sparking 118
Total 494
0
100
200
300
400
500
600
700
800
900
1,000 26th July 2005 27th July 2005
10:00 13:00 16:00 07:0004:0001:0022:0019:00
0.9 19.3
Normal Rainfal
667.7
768.8
885 896944.2
Previous Maximum: 575.6 mm
(Recorded on July 5th 1974)
Rainfall (in mm)
Time (in hours)
575
0
100
200
300
400
500
600
700
800
900
1,000 26th July 2005 27th July 2005
10:00 13:00 16:00 07:0004:0001:0022:0019:00
0.9 19.3
Normal Rainfal
667.7
768.8
885 896944.2
Previous Maximum: 575.6 mm
(Recorded on July 5th 1974)
Rainfall (in mm)
Time (in hours)
575
For Official Use Only
Page 9 of 21
10.2. The table above is extracted from centralized automated complaint logging
system. It is possible that many customers may have lodged the complaints for the
same instance. The effective actual complaints are about 30-40% less than the
actual.
10.3. Total actual fire complaints therefore works out to 110 numbers and total actual
shock complaints 27 numbers in a year.
11. Analysis of Anticipated Environmental Impact(AEI)
11.1. Following likely environmental impact are envisaged during implementation of
the project.
11.1.1. Health hazards incase of damage of drinking water pipe or drainage pipe during
cable laying excavation.
11.1.2. Noise pollution due to excavation equipments.
11.1.3. Road blockage caused due to development of trenches/earth removed during
excavation.
11.1.4. Fire hazard due to damage to the exiting live electrical cable.
11.1.5. Interruption to communication network, if communication cable is damaged
during excavation.
11.1.6. Damage to the exiting road surface during cable laying excavations.
11.1.7. Collapsing of walls during the clipping of meter to house cable or during internal
wiring.
11.1.8. Risk of spoiling the plantation due to excavation on edges of roads.
11.1.9. Oil leakage from transformer during replacement or due to improper handling.
11.1.10. Damage to the structures while transporting heavy equipments like
transformer.
11.1.11. Fugitive dust and smoke accumulation in confined spaces
For Official Use Only
Page 10 of 21
12. Environmental Management Plan
12.1. Based on the AEI, an environmental management plan has been prepared.
Sr.
No.
ASPECT Impact Cause Mitigation Monitoring
Plan
A: Environmental Aspects
1 Drinking
water
contamination
Health
hazards
Damage
to
drinking
water
pipes or
drainage
pipes
1. Arrange joint visit with
MCGM
authorities for site survey
before taking-
up the excavation.
2. Enquire with the near-by
residents
regarding existence of
water/drainage
pipes on the roads.
3. Take the test trenches before
starting
excavation along the road.
4. Keep the plumber on call
while
excavating to attain the
damages if any
immediately.
Divisional Head to visit randomly to
worksites once in fortnight.
Damages to be reported by Unit
Engineers in format EMP1.
EMP1 report to be reviewed in
Monitoring Committee meetings.
For Official Use Only
Page 11 of 21
Sr.
No.
ASPECT Impact Cause Mitigation Monitoring
Plan
2 Noise
Human
health
Due to use
of
machines
for
excavation
s
1. Since roads are small in
width, avoid
machines for excavation. Do
manual
excavations.
2. Inform people regarding
excavation so
that they can stay away if
possible.
Divisional Head to visit randomly to
worksites once in fortnight.
Complaints received regarding
‘Noise’ from project area to be
addressed by Divisional Head
3 Damage to
plants
Loss of
plantation
Excavatio
ns
touching
tress
1. Survey the plants along the cable-
laying route.
2. Keep safe distance from trees
while excavating.
3. Provide support for weak tress, if
any.
4. Re-plantation with suitable trees
as required
Divisional Head to visit randomly to
worksites once in fortnight.
Damages to be reported by Unit
Engineers in format EMP1.
EMP1 report to be reviewed in
Monitoring Committee meetings.
4 Oil leakage
from
transformer
Fire hazard
Contaminati
on of soil
and flow
into
drainage
Damage
to
transforme
r while
transportin
g
1. If the transportation routs are
narrow, remove the transformer
radiators and then transport.
2. Keep minimum oil, and top-up
when installed completely.
3. Arrest the oil leakage
immediately and remove oil and
dispose suitably.
Dy. Manager (O&M) to supervise the
Transformer replacement job
personally.
Damages to be reported by Unit
Engineers in format EMP1.
EMP1 report to be reviewed in
Monitoring Committee meetings.
For Official Use Only
Page 12 of 21
Sr.
No.
ASPECT Impact Cause Mitigation Monitoring
Plan
5 Fugitive dust
and smoke
accumulation
in confined
houses
Human
health
Space
constraints
1. Recommend installation of
exhaust fans through awareness
workshops.
2. Awareness workshop planned
under the project shall include
tips to avoid suffocation.
3. Initiate electric supply
disconnection, if directed by
appropriate authorities.
4. Recommend to provide dustbin
and dispose off the garbage in
MCGM Vans-to be covered
under awareness workshop.
Monitoring Committee to review the
workshop module before is goes live.
Divisional Head to keep records of
letters received from competent
authority for the project area and
follow-up the action taken.
B: Safety Aspects
6 Road
blockage
Movement
obstruction
Across
trenches/
earth
removed
from
trenches
1. Plan across trenches during
nighttime.
2. Use mild steel sheet to cover
the
trenches.
3. Transport of excess soil /
debris
immediately.
Where points (1) – (3) above are
not possible – document reasons
and ensure this documentation is
available for review by World
Bank.
Divisional Head to visit randomly to
worksites once in fortnight.
Unit Engineer to keep record of
debris lifted from these areas.
For Official Use Only
Page 13 of 21
Sr.
No.
ASPECT Impact Cause Mitigation Monitoring
Plan
7 Sparks due to
loose
connections
Fire hazards Improper
wiring,
partial
breaking
of wires
1. Ensure proper workmanship of
contractor executing wiring
works.
2. Train the contractor and his
wiremen on the correct
methodology.
3. Avoid using sharp edge metals
near wires.
4. Conduct safety workshop for
nearby residents.
Formats developed by independent
verification contractor to be used for
monitoring.
ICPCI to keep records of
contractor/wiremen training.
8 Cable fault Communica
tion failure
Damage
to
communic
ation
cable.
1. Plan joint visit with
communication agencies in the
area.
2. Collect drawings from
communication companies if
available.
3. Take test trenches.
Divisional Head to visit randomly to
worksites once in fortnight.
Damages to be reported by Unit
Engineers in format EMP1.
EMP1 report to be reviewed in
Monitoring Committee meetings.
9 Road damage Inconvenien
ce to
residents
Damage
to
road/path
ways
during
cable
lying.
1. Give prior intimation to nearby
residents.
2. Intimate MCGM regarding
excavation schedule.
3. Excavated roads to be resurfaced
within 48 hrs by-
a. Reliance Energy: Where the
excavation is on private
roads/pathways
b. MCGM: Where the road is a
public road and reinstatement
charges are paid to MCGM as
Divisional Head to review monthly
records of resurfacing works to be
done by Reliance Energy.
Unit Engineer to write letter to
MCGM for resurfacing the roads and
follow-up with them. Divisional Head
to review monthly records.
For Official Use Only
Page 14 of 21
Sr.
No.
ASPECT Impact Cause Mitigation Monitoring
Plan
per their policy.
4. Regular follow-up with MCGM
authorities for reinstatement.
10 Wall collapse Property
damage
Excavatio
ns
touching
wall /
vibration
of
excavation
machines
1. Survey the structures and mark
the excavation lines.
2. Keep safe distance from wall
while excavating.
3. Do not use mechanical
excavators on narrow roads.
4. Keep mason on call for repairs, if
any.
Divisional Head to visit randomly to
worksites once in fortnight.
Damages to be reported by Unit
Engineers in format EMP1.
EMP1 report to be reviewed in
Monitoring Committee meetings.
11 Wall collapse,
stairs collapse
Property
damage
Transporti
ng
equipment
damage
side by
objects if
roads are
narrow.
1. Carry out transportation route
survey.
2. Inform respective residence if
property is likely to damage.
3. Repair it immediately.
Prior permissions to be taken from
the house owner and assure him that
damages will be repaired by Reliance Energy.
Site Supervisor (Jr. Engineer) to
remain present while transporting
heavy equipments from narrow roads.
Report completion of Damages to
Divisional Head within 48 Hrs.
12 Short circuit Fire hazards Mishandli
ng of
electrical
wires/dam
age to
electrical
wire/hangi
ng wires
1. Safety awareness through the
workshops.
2. 24x7 complaint facility to lodge
fire complaints.
3. Vigilance visits every Six-month
for removal or unauthorized
wires.
Monitoring Committee to review
every month status of the workshop
conducted SRA and ICPCI.
Complaints of the project area to be
extracted on monthly basis from the
CMS database. Summary of Short
circuit, shocks and fire complaints to
be reviewed by Monitoring
For Official Use Only
Page 15 of 21
Sr.
No.
ASPECT Impact Cause Mitigation Monitoring
Plan
13 Electrical
shocks
Human
health
Mishandli
ng of
electrical
wires/dam
age to
electrical
wire/hangi
ng wires
1. Safety awareness through the
workshops.
2. 24x7 Complaint Facility to lodge
fire complaints.
3. Vigilance visits every Six-month
for removal or unauthorized
wires.
Committee.
Vigilance standard report (EMP2) to
be reviewed by Divisional Head
every Month.
For Official Use Only
Page 17 of 21
12.2. The table below gives the Severity, Scale, Probability and Duration (if happens)
of each of the Impact.
Sr.
No.
ASPECT Impact Severity Scale Probabil
ity
Duration
A: Environmental Aspects
1 Drinking
water
contamination
Health
hazards
Medium Local Unlikely Short
2 Noise
Human
health
Medium Local Likely Short
3 Damage to
plants
Loss of
plantation
Medium Local Unlikely Medium
4 Oil leakage
from
transformer
Fire hazard
Contaminati
on of soil
and flow
into
drainage
Medium Local Less
Likely
Short
5 Fugitive dust
and smoke
accumulation
in confined
spaces
Human
health
Medium Local Less
Likely
Short
B: Safety Aspects
6 Road
blockage
Movement
obstruction
Low Local Likely Short
7 Sparks due to
loose
connections
Fire hazards Medium Local Likely Short
8 Cable fault Communica
tion failure
Low Local Less
Likely
Short
9 Road damage Inconvenien
ce to
residents
Low Local Likely Short
10 Wall collapse Property
damage
Low Local Less
Likely
Short
11 Wall collapse,
stairs collapse
Property
damage
Low Local Less
Likely
Short
12 Short circuit Fire hazards Medium Local Likely Short
13 Electrical
shocks
Human
health
Medium Local Less
Likely
Medium
For Official Use Only
Page 18 of 21
13. Institutional Structure for EMP Implementation, Monitoring and Reporting:
13.1. During the visit, the mission already noted with satisfaction that Reliance Energy
has developed strong procedures and systems for planning and implementation of
environmental measures in its business operations. This systems and procedures
have been applied by Reliance Energy to its large operations such as power
generating facility near Mumbai. These procedures can easily be adopted for
Mumbai Supply Business.
13.2. Reliance Energy is ISO: 9001, Certified Company. All the procedures are well
documented. 24x7 manpower is available to deal with the complaints. The
average response time is 15 minutes. In addition to 24x7 staff, engineers are on
stand-by in rotation to deal with the emergences.
13.3. Reliance Energy have full-fledged Safety Department, which continuously
initiates the actions after occurrence of any accidents and also take measures to
avoid the recurrence in future.
13.4. For management of disasters, Reliance Energy has,
13.4.1. Disaster control rooms at each Divisional office and main control room at
Santacruz office.
13.4.2. Communication links with the Government and local administrations.
13.4.3. Raising of low level Installations
13.4.4. Stock availability of the equipments and spares to manage disasters.
13.4.5. Mobilization of external resources.
13.4.6. Team of senior management to oversee disasters and review preparedness.
13.5. The standard response plan is shown in figure below,
For Official Use Only
Page 19 of 21
Format EMP-1
Damage Reporting while carrying out works on SELR Project site
Title Details
Date of Incident:
Name of Reporting
Engineer:
Location of Incidence:
Description of Damage:
Intensity of Damage: Minor/Major
No. of Peoples affected:
Damage Rectified on:
Damage informed to
respective external
Authority? When?
Investigations:
Joint Visit of Reliance
Energy & Respective
Authority was arranged? If
no, specify reasons.
Enquires were made with
near-by-residence? If no,
specify reasons.
Test Trenches were taken?
Were they adequate?
Clearances maintained from
nearby structure/trees.
Was repairing men reported
in time? Reasons for delay.
Present Status of Damage:
Actions Initiated to avoid
recurrences
For Official Use Only
Page 20 of 21
Format EMP-2
Vigilance Raids
Summary Report
Report For the Week: ----------------- to -------------------
Slum/cluster Name
Unauthorized Connection removed from
Pillars Meter Cabin
Load in Amps
Wires Recovered
(Meters)
Cables Recovered (Meters)
For Official Use Only
Page 21 of 21
Format EMP-3
Divisional Head - Monthly review.
s.no Incident details Action required Target date for
action
When
completed
Points to be reviewed-
Review containing the summary of EMP-1 &2 formats and communication to
internal and external agencies along with action plan for future.
Legal and regulatory and other requirements if any with compliance report.
Inputs / outputs and financials if any (optional requirement can be put in the
review)
wb280099 E:\World Bank work\GPOBA Mumbai\Post Sept mtg\Docs for review\GPOBA-Mumbai-Env&SocialMF-final-post Sept mtg.doc
01/10/2008 7:41:00 AM