Slovenia: Installation of two Refuelling Stations (HRS) Investor: Centre of Excellence for...

3
Slovenia: Installation of two Refuelling Stations (HRS) Investor: Centre of Excellence for low-Carbon Technologies. Project objective: Setting up of two HRS – mobility application Launched in November 2011: public tender for HRS, production process by Air-Liquide, designing the location implementation, placement into final locations, opening and regular use in 2013

Transcript of Slovenia: Installation of two Refuelling Stations (HRS) Investor: Centre of Excellence for...

Page 1: Slovenia: Installation of two Refuelling Stations (HRS) Investor: Centre of Excellence for low-Carbon Technologies. Project objective: Setting up of two.

Slovenia: Installation of two Refuelling Stations (HRS)

Investor: Centre of Excellence for low-Carbon Technologies.

Project objective: Setting up of two HRS – mobility application

Launched in November 2011: public tender for HRS, production process by Air-Liquide, designing the location implementation, placement into final locations, opening and regular use in 2013

Page 2: Slovenia: Installation of two Refuelling Stations (HRS) Investor: Centre of Excellence for low-Carbon Technologies. Project objective: Setting up of two.

Supply warehousestorage equipment and connection of supplied hydrogen including pumping (explanatory) sites for hydrogen – the gas cylinders in bundlesstorage equipment and connection of nitrogen supplied in bundles of cylinders

Drive trainplant and equipment for filling hydrogen at 350 bar, open frame container dimensions 20‘‘

compression set for air and hydrogenhigh intermediate storage of hydrogen at 400 bar, fast-loadingcontrollerinstallation of charging vehicles with display

Process levelequipment to validate the hydrogen consumptionSupervisory leveldata storage

Hydrogen Refuelling Station (HRS)– technical equipment

Page 3: Slovenia: Installation of two Refuelling Stations (HRS) Investor: Centre of Excellence for low-Carbon Technologies. Project objective: Setting up of two.

Capacity filling up to 3 personal vehicles daily filling up to 1 minibus (8m) daily

Vehicle filling timeframe personal vehicle up to 10 min (between two fillings 20 min-buffer) minibus (8m) up to 30 min

The hydrogen purity degree 99,98 % - process requirements of vehicle fuel cell stack

HRS dimensions 2300 x 3500 x 2200 (w x l x h), standard frame

Hydrogen Refuelling Station (HRS)– characteristics