Six week industrial training presentation BY GUPTA TARUN
Transcript of Six week industrial training presentation BY GUPTA TARUN
SIX WEEK INDUSTRIAL TRAINING PRESENTATION ON LAYING OF LINK
ROAD JHANDURI PARATHA NABOWN KM 0/0 TO 8/00
UNDER PMGSY (WORLD BANK ) PHASE -2 BLOCK DHARAMPUR
( PACKAGE NO-HP-11-82)
NAME –TARUN GUPTA
ME –INFRASTRUCTURE(CIVIL)
PMGSY PROFILE Pradhan Mantri Gram Sadak Yojana (PMGSY) was launched on
25th December 2000 as a fully funded Centrally Sponsored Scheme to provide all weather road connectivity in rural areas of the country.
The programme envisages connecting all habitations with a population of 500 persons and above in the plain areas and 250 persons and above in hill States, the tribal and the desert areas.
According to latest figures made available by the State
Governments under a survey to identify Core Network as part of the PMGSY programme, about 1.67 lakh Unconnected Habitations are eligible for coverage under the programme. This involves construction of about 3.71 lakh km. of roads for New Connectivity and 3.68 lakh km. under upgradation.
NAME OF BLOCK
CODE TOTAL NO. OF HABITATION
>1000 500-999 250-499 <250 TOTAL ELIGIBLE HABITATION
DHARMPUR
HP-11 8 - 458 - 8
•SUMMARY SHEET O F HABITATION BENEFITTED:
DISTRICT BLOCK PACKAGE NO.
NAME OF ROAD
LENGTH KM.
ORIGNAL VLAUE
MAINT.
SOLAN DHARMPUR
HP-11-82 PRATHA TO NABON
8.000 185.18 LACS 24.10LACS
AVG. CONSTRUCTION COST PER KM(Lacs)=23.15
TRANSECT WALK:
A walk along the suggested alignment by PIU with the communities, PRI and key informants to observe, to listen, and to ask questions which would enable identification of problems and collectively evolve solutions. The transect shall enable the PIU, to quickly learn about the social structure, issues pertaining to land, social impacts, soils, land use, and community assets and to triangulate data already available.
TOTAL NO. OF PEOPLE PRESENT IN TRANSECT WALK:MALE =55 FEMALE 33 TOTAL =88DEMOGRAPHIC INFO WHERE WALK WAS CONDUCTED KIAROO, GUTHAN,KALIND,DHAR (BOTH SIDES APPLE OCHARDS) IN DIFF. RD’SNO OF GOVT. EMPLOYE PRESENT=6NO. OF CONTRACTOR EMPLOYE PRESENT=NILNO. OF PARTICIPANT FROM MINORITY COMMUNITY SC=12 ST= - WOMEN=9
TRAFFIC SURVEYs.no Type of vehicle Day 1 Day 2 Day 3 Avg.1 Car, jeep, van 45 50 40 452 Tanker3 LCV 28 32 30 304 Minibus5 Minitruck 52 49 46 496 Tractor with
trailer72 64 68 68
7 Tractor without trailer
8 Cycle9 Hand cart10 Horse cart11 Pedestrians
CVPD 169 163 152 162TOTAL MOTORIZED VEHICLE PER DAY
197 195 184 192
TABLE-1.1: AVG 3-DAY TRAFFIC DATA
s.no Type of vehicle ADT AADT GROWTH RATE
1 Car,jeep,van 45 48 532 Tanker 03 LCV 30 32 364 Minibus 05 minitruck 49 52 586 Tractor with
trailer68 72 81
7 Tractor without trailer
8 Cycle9 Hand cart10 Horse cart11 pedestrians
CVPD 162 172 192TOTAL MOTORIZED VEHICLE PER DAY
192 204 228
TABLE-1.2: AVERAGE ANNUAL TRAFFIC DATA (BOTH WAYS)
DESIGN FOR COMMULATIVE ESAL Since it is a new road so that field authorities have collected and supplied the data from the
adjoining road in the year of traffic count 192 having two harvesting season. Assuming 50% of harvesting season so ADT during non harvesting season =192/2=96 AADT=VOLUME OF TRAFFIC IN YEAR/365 96 + (TRAFFIC VOL. COUNT*DAILY FACTOR*SEASONAL FACTOR) 365 AADT=96+ (1.2*96*75) = 120 365 ASSUMING 6% GROWTH RATE BEFORE TWO YEAR WHILE ROAD IS OPENED TO
TRAFFIC
AADT = 120(1+0.06)^2=135
COMMULATIVE ESAL OVER 10 YEARS @6 % GROWTH RATE: N=55,037 SO 55,037 fall in category T2 i.e. it fall in commutative ESAL application of 30000 to 60000
and against CBR value 0f 7-9% , a total crust thickness may be provided as per the pavement catalogues of IRC SP-72 -2007
The following specification has been recommended for this road section investigated under the study for the design of flexible pavement.
TOP LAYER PREMIX CARPET WITH TYPE B SEAL COAT
20 MM
BASE LAYER WBM GRADING 3 75 MMSUB BASE LAYER WBM 1 AND 2 (100+75 )MMTOTAL THICKNESS 270 MM
LAYOUT OF FLEXIBLE PAVEMENT:
o GSB having a compacted thickness of 100mm of CBR less than 20% o WBM GRADE 2 (63-45mm) having a single compacted layer thickness of 75 MM
o For surfacing and sealing wearing course , a suitable layer of open graded mix carpet (PMC) having a compacted thickness of 20mm with seal coat provide at the top of surface for smoothness of road.
GEOMETRIC DESIGNTERRAIN CLASSIFICATION CROSS SLOPE OF THE COUNTRY
PLAIN 0-10 % More than 1 in 10
ROLLING 10-25 % 1 in 10 to 1 in 4
MOUNTAINOUS 25-60 % 1 in 4 to 1 in 1.67STEEP >60 % < 1.67
S.N
O
NAME OF
ROAD
ROAD
LENGTH
(KM)
ROAD
CONNECTING TO
LAND
WIDT
H
ROAD
WIDT
H
C/O 8/00 VR 7.50 5.00
JHANDURI
TO
NABOOWN
ROAD
CLASSIFICATION
PLAIN
TERRAIN
ROLLING
TERRAIN
MOUNTAINOUS
TERRAIN
STEEP
TERRAIN
RULI
NG
MIN. RULI
NG
MIN. RULIN
G
MIN. RULI
NG
MIN
RURAL ROAD 50 40 40 35 25 20 25 20
DESIGN SPEED:
DESIGN SPEED (km/hr) SAFE STOPPING SIGHT DISTANCE
(m)
20 20
30 30
40 45
50 60
LONGITUDNAL AND TRNSVERSE SECTION
INTERSECTION
PAVEMENT MATERIAL
MATERIAL SOURCE LEAD (KM)STONE BAROTIWALA CRUSHER SITE 37.00
STONE AGGREGATE 10MM BAROTIWALA CRUSHER SITE 37.00
STONE AGGREGATE 20MM BAROTIWALA CRUSHER SITE 37.00
STONE AGGREGATE 40MM BAROTIWALA CRUSHER SITE 37.00
BITUMEN PANIPAT 190.00
CEMENT PARWANOO 34.00
SAND BHARWALA NADI 66.00
HUME PIPE
ANY OTHER
TABLE:SOURCE OF PAVEMENT MATERIALS
STATE-HIMACHAL PRADESH DISTRICT-SOLAN BLOCK-DHARMPURROAD FROM JHANDURI TO NABOWN ROAD
DESIGN OF PAVEMENT SECTIONEARTH-WORK
SUBGRADE GSB
WBM BASE COURSE
BITUMINOUSSURFACE
CROSS DRAINAGE WORK
SUBGRADE
CBR VALUE TEST RESULTUNSOAKED CBR TEST AT 2.5mm penetration 12.5% AT 5.0 mm penetration 14.0%
SOAKED CBR TEST
(AFTER 4 DAYS) AT 2.5mm penetration 6.8% AT 5.0 mm penetration 7.2%
Sub grade soil is an integral part of the road pavement structure as it provides the support to the pavement from beneath. The sub grade soil and its properties are important in the design of pavement structure. The main function of the sub grade is to give adequate support to the pavement and for this the sub grade should possess sufficient stability under adverse climatic and loading conditions. Therefore, it is very essential to evaluate the sub grade by conducting tests.
SUBRADE THICKNESS FOR RURAL ROAD=300 MM
Descrip
tion
&
location
Identificatio
n
and
classification
Gradation analysis % age Atterberg
Limit
Gravel sand Fine(silt /clay) L.L
%
P.L
%
PI
%
Km
0/600
Generally,coar
se
Grained soil of
group
symbol
GM/GC
42.8 32.8 24.4 23 20 3
Km
1/350
46.2 31.2 22.6 22 19 3
Km
2/750
43.7 31.5 24.8 24 20 4
Km
3/600
45.2 32.6 21.5 23 20 3
OMC
%
MDD
gm
10.5 2.03
10.0 2.05
9.5 2.02
10.0 2.05
SUPERELEVATION: ( Max. Super elevation for this project is 5.0% )
CAMBERTHIN BIYUMINOUS ROAD 3.0 % ( RAINFALL<
1000MM)
3.5 % ( RAINFALL>
1000MM)
GSB (GRANULAR SUB BASE) Granular sub-base (GSB) is constructed with well graded Granular
Soil, maintaining suitable moisture content and compacted in layers not exceeding 100mm. Compaction is done till required density is achieved as per the design. A well finished GSB will be free from movement (under compaction equipment), ridges, cracks or loose material.
GRADATION OF GSB MATERIAL:
IS SIEVE DESIGNATION % BY WEIGHT PASSING THE IS SIEVE
GRADING 1 GRADING 2 GRADING 3
75MM 100
53MM
26.5 MM 55-75 50-80 100
4.75 MM 10-30 15-35 25-45
0.075 MM <10 <10 <10
WATER BOUND MACADAM SUBBASE/BASE:
Providing,laying,spreading and compacting stone aggregates of specific size to water bound macadam specification including spreading in uniform thickness,hand packing, rolling with three wheel 80-100 KN static roller in stages to proper grade and camber ,applying and brooming,stone screening /binding material to fill up the interstics of coarse agg. ,watering and compacting to the required density grading 1 as per technical specification clause 404
IS SIEVE DESPERATION % BY WEIGHT PASSING IS SIEVE
GRAD. A GRAD. B GRAD. C
53 MM 100
37.5MM 97-100 100
26.5MM 97-100 100
19MM 67-81 97-100
9.5MM 56-70 67-79
4.75M 33-47 39-53 47-59
.425MM 10-19 12-21 12-21
.075MM 4-8 4-8 4-8
BITUMINOUS SURFACEBituminous layer is laid over the base course to ensure that rainwater does not damage the base, that moving traffic does not remove the metal and other material. The Bituminous layer also provides for dust free and comfortable riding.
CROSS DRAINAGE STRUCTURESThe pavement surface should be absolutely impermeable to prevent seepage of water into the pavement layers. Further, both the geometry and texture of pavement surface should help in draining out the water from the surface in less time.
S.NO CHAINAGE (KM) DESCRIPTION OF EXISTING STRUCTURES
TYPE SPAN/DIA(m) CONDITION
0/105 HUME PIPE 900 MM DIA GOOD
0/225 HUME PIPE 900 MM DIA GOOD
0/390 HUME PIPE 900 MM DIA GOOD
0/600 HUME PIPE 900 MM DIA GOOD
1/115 HUME PIPE 900 MM DIA GOOD
1/495 HUME PIPE 900 MM DIA GOOD
1/795 SLAB CULVERT 3 MTR. SPAN GOOD1/915 HUME PIPE 900 MM DIA GOOD1/960 HUME PIPE 900 MM DIA GOOD2/195 HUME PIPE 900 MM DIA GOOD2/390 HUME PIPE 900 MM DIA GOOD2/815 HUME PIPE 900 MM DIA GOOD3/00 SLAB CULVERT 3 MTR. SPAN GOOD
LIST AND CONDITION OF EXISTING CULVERT:
QUALITY MONITORING:
Efforts are made to ensure quality of rural roads under the Pradhan Mantri Gram Sadak Yojana. Rigorous tearing for quality of material and workmanship is to be carried out on all the road works. A three-tier quality control monitoring system has been adopted for these roads. While the executive engineer or the PIU is the first tier, the second tier is an independent state level agency. As the third tier, senior technical persons are engaged as National Quality Monitor (NQMs) to inspect road works in different states.
A 3-tier Quality Control System has been designed to ensure the quality of the road works. While the concerned Executive Engineer is the first tier, all the states have been requested to enlist the services of a State level independent Agency to verify the quality of the roads. On its part, the National Rural Roads Development Agency, an agency set up by the Ministry of Rural development, engages senior technical personnel as National Quality Monitors to inspect the road works.
Logo Sign Board And Other Road Furniture Immediately on starting the work, all the roads
under the PMGSY are required to have informatory Sign Board giving the particulars of the road work as well as the name of the contractor .
Road furniture like Km Stones, 200m Stones, Cautionary Signs etc. are to be provided on all roads constructed under Pradhan Mantri Gram Sadak Yojana.
SPECIAL THANKS TO A PERSON WWHO MADE PMGSY COME TRUE AND TOOK INDIA TO NEXT LEVEL OF DEVELOPMENT AND CONNECTIVITY.