LSSBB Number : LSSBB Passing Score : 800 Time Limit : 120 min File Version : 4.1 http://www.gratisexam.com/ Six Sigma LSSBB Questions & Answers Lean Six Sigma Black Belt Exam Version: 4.1 Six Sigma LSSBB Exam

Transcript of Six Sigma.NewQuestions.LSSBB.v2015-07-21.by.Tracy · Six Sigma LSSBB Questions & Answers Lean Six...

Page 1: Six Sigma.NewQuestions.LSSBB.v2015-07-21.by.Tracy · Six Sigma LSSBB Questions & Answers Lean Six Sigma Black Belt Exam Version: 4.1 Six Sigma LSSBB Exam. Exam A QUESTION 1 A _____

LSSBB

Number: LSSBBPassing Score: 800Time Limit: 120 minFile Version: 4.1

http://www.gratisexam.com/

Six Sigma LSSBB Questions & Answers

Lean Six Sigma Black Belt Exam

Version: 4.1Six Sigma LSSBB Exam

Page 2: Six Sigma.NewQuestions.LSSBB.v2015-07-21.by.Tracy · Six Sigma LSSBB Questions & Answers Lean Six Sigma Black Belt Exam Version: 4.1 Six Sigma LSSBB Exam. Exam A QUESTION 1 A _____

Exam A

QUESTION 1A ___________ is used primarily to track the stability of the average value of a metric of interest.

A. NP ChartB. Xbar-R ChartC. I-MR ChartD. C Chart

Correct Answer: BSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 2For her injection molding project a Belt needed to track the percentage of defectives of a particular sampleset so she used a ___________ to display the data?

A. Individual ChartB. C ChartC. Xbar ChartD. P Chart

Correct Answer: DSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 3Which of these graphs demonstrates conditions which would be sufficient to enable OCAP for the process?

A. Xbar ChartB. Time Series ChartC. NeitherD. Both

Correct Answer: ASection: (none)Explanation

Explanation/Reference:

QUESTION 4Control Charts were developed by Dr. Shewhart to track data over time. To detect Special Cause variationthe Control Charts use which of these?

A. Data shift analysisB. Outlier analysis methodsC. Center Line and Control LimitsD. None of the above

Correct Answer: CSection: (none)

Page 3: Six Sigma.NewQuestions.LSSBB.v2015-07-21.by.Tracy · Six Sigma LSSBB Questions & Answers Lean Six Sigma Black Belt Exam Version: 4.1 Six Sigma LSSBB Exam. Exam A QUESTION 1 A _____

Explanation

Explanation/Reference:Explanation:

QUESTION 5Common and ______________ Cause Variation are the focus of Statistical Process Control.

http://www.gratisexam.com/

A. UncommonB. OrdinaryC. SpecialD. Selective

Correct Answer: CSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 6Special Cause Variation falls into which two categories?

A. Natural & UnnaturalB. Short Term & Long TermC. Assignable & PatternD. Attribute & Discreet

Correct Answer: CSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 7Range Charts are the technique used to determine if Special Causes are occurring within the subgroups ofthe ______________.

A. HistogramsB. SPC ChartsC. NP ChartsD. Pareto Charts

Correct Answer: BSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 8

Page 4: Six Sigma.NewQuestions.LSSBB.v2015-07-21.by.Tracy · Six Sigma LSSBB Questions & Answers Lean Six Sigma Black Belt Exam Version: 4.1 Six Sigma LSSBB Exam. Exam A QUESTION 1 A _____

If the production is for higher volume and monitoring and the Mean and variability is to be monitored forfour machines producing product and the characteristic to be monitored is Variable Data, which SPC Chartis best to be selected?

A. Xbar-R ChartB. Individual-MR ChartC. NP ChartD. CUSUM Chart

Correct Answer: ASection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 9When a Belt Poka-Yoke's a defect out of the process entirely then she should track the activity with arobust SPC system on the characteristic of interest in the defect as an early warning system.

A. TrueB. False

Correct Answer: BSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 10Following the completion of a LSS project the Belt not only creates a Control Plan he also develops a_____________ so those involved in the process know what to do when the critical metrics move out ofspec.

A. Response PlanB. Call ListC. Chain-of-CommandD. Defect Analysis Plan

Correct Answer: ASection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 11The Control Limits width varies if the sample size varies for which type of chart?

A. P ChartsB. NP ChartsC. Xbar-R ChartsD. Time Series Charts

Correct Answer: ASection: (none)Explanation

Explanation/Reference:

Page 5: Six Sigma.NewQuestions.LSSBB.v2015-07-21.by.Tracy · Six Sigma LSSBB Questions & Answers Lean Six Sigma Black Belt Exam Version: 4.1 Six Sigma LSSBB Exam. Exam A QUESTION 1 A _____

Explanation:

QUESTION 12Which of these elements are not included in Implementation plans?

A. Work breakdown structureB. Risk management plansC. Cost/Benefit ratiosD. Planned audits of work completion

Correct Answer: CSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 13Upon completion and validation of an improvement to a process a Belt and the Project Team create aControl Plan that contains which of these?

A. Standard operating work description of the process changeB. Description of the monitoring system in place to assure continued complianceC. Summary of the targeted critical metrics for process performance measurementD. All of the above

Correct Answer: DSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 14How many experimental runs exist in a Full Factorial and fully randomized design for 4 factors with 2replicates for the Corner Points and no Center Points? The factors in the experiment are only at 2-levels.

A. 10B. 32C. 256D. 64

Correct Answer: BSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 15If an experiment has 5 factors and no replicates for a 2-level Experimental Design with 16 experimentalruns which statement is incorrect?

A. The Experimental Design is half-fractionalB. The Main Effects are confounded with only 4-way interactionsC. The Main Effects for the 5 factors are not aliased or confounded but the 2-way interactions are

confounded with the 3-way interactionsD. The experiment has 8 experimental runs with the first factor at the high level

Page 6: Six Sigma.NewQuestions.LSSBB.v2015-07-21.by.Tracy · Six Sigma LSSBB Questions & Answers Lean Six Sigma Black Belt Exam Version: 4.1 Six Sigma LSSBB Exam. Exam A QUESTION 1 A _____

Correct Answer: CSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 16Fractional Factorial, ____________and Response Surface Method are types of planned experiments.

A. Multi-Vari AnalysisB. Baldridge ChannelsC. One Factor at a Time or OFATD. Factorial Design

Correct Answer: DSection: (none)Explanation

Explanation/Reference:

QUESTION 17Relative to a Design of Experiments the term ________________ refers to variables being a linearcombination of each other.

A. Mirror ImageB. Directly ParallelC. CollinearD. None of the above

Correct Answer: CSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 18Which statement(s) are incorrect about Fractional Factorial Designs?

A. A Half Fractional Design for 5 factors has the same number of experimental runs as a Full FactorialDesign for 4 factors assuming no repeats or replicates or Center Points

B. Quarter Fractional experiments can exist for those with 4 factorsC. Resolution V design is desired while controlling costs of experimentationD. Half Fractional experiments do not exist for those designs with only 2 factors

Correct Answer: CSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 19If in an experiment all possible variable pairs sum to zero the design is Orthogonal.

A. TrueB. False

Page 7: Six Sigma.NewQuestions.LSSBB.v2015-07-21.by.Tracy · Six Sigma LSSBB Questions & Answers Lean Six Sigma Black Belt Exam Version: 4.1 Six Sigma LSSBB Exam. Exam A QUESTION 1 A _____

Correct Answer: ASection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 20Which Experimental Design typically is most associated with the fewest number of input variables orfactors in the design?

A. Fractional Factorial designB. Full Factorial designC. Simple Linear RegressionD. Response Surface Design

Correct Answer: DSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 21The method of Steepest Ascent guides you toward a target inside the original inference space.

A. TrueB. False

Correct Answer: BSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 22Situations where standardized work needs to be incorporated include all of these except_____________________.

A. Machines continually operating to reduce the labor cost per pieceB. Lack of a system to assure proper inventory levels at repair stationsC. Changeover instructions incompleteD. Process flow for the same product assembly taking various cycle time for completion

Correct Answer: ASection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 23The Lean toolbox includes all of these items except ________________.

A. Mistake ProofingB. Visual FactoryC. Design of ExperimentsD. Inventory Management

Page 8: Six Sigma.NewQuestions.LSSBB.v2015-07-21.by.Tracy · Six Sigma LSSBB Questions & Answers Lean Six Sigma Black Belt Exam Version: 4.1 Six Sigma LSSBB Exam. Exam A QUESTION 1 A _____

Correct Answer: CSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 24Questions that can be best answered by a Visual Factory include all of these except_____________________.

A. Are downtime issues easily noted?B. Can extra inventory be seen easily?C. Are unneeded tools or supplies easily noted?D. Are setups optimized for lower scrap levels?

Correct Answer: DSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 25If a Six Sigma project was to reduce repair station inventory and the team found the inventory was creepingup over time which Lean tools should be considered in the Control Phase to reestablish and sustain theproject success?

A. Review the Visual Factory to assure inventory in excess of desired visibleB. Improve the lighting to assure adequate visibilityC. Analyze data from supplier deliveriesD. Reword the standardized work instructions to use active verbs and not passive phrases

Correct Answer: ASection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 26When a Belt implements an improvement that is automated thus requiring no particular understanding foruse he has applied which Lean tool?

A. Mistake ProofingB. Kaizen EventC. 5SD. None

Correct Answer: ASection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 27Kaizens or Kaikakus and Six Sigma projects are intended to create incremental process improvementsversus breakthrough, significant improvements.

Page 9: Six Sigma.NewQuestions.LSSBB.v2015-07-21.by.Tracy · Six Sigma LSSBB Questions & Answers Lean Six Sigma Black Belt Exam Version: 4.1 Six Sigma LSSBB Exam. Exam A QUESTION 1 A _____

A. TrueB. False

Correct Answer: BSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 28Which of these items contribute to what is necessary for successful Kaizen events?

A. Analysis toolsB. Management supportC. Operator supportD. All of these answers are correct

Correct Answer: DSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 29Kanban establishes a means of monitoring production, conveyance and delivery information such thatefficient flow is established. The method used by Kanban is to require a _________ before anythingmoves.

A. Sign-offB. SignalC. Bell to ringD. Work order

Correct Answer: BSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 30When a Belt decides to use written procedures and visual controls to improve the consistency of the tasksthat must occur in the process he is improving he has utilized the _________________ activity of 5S.

A. SustainingB. SortingC. StandardizingD. Straightening

Correct Answer: CSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 31Fractional Factorial designs are used to reduce the ____________ because the number of runs has been

Page 10: Six Sigma.NewQuestions.LSSBB.v2015-07-21.by.Tracy · Six Sigma LSSBB Questions & Answers Lean Six Sigma Black Belt Exam Version: 4.1 Six Sigma LSSBB Exam. Exam A QUESTION 1 A _____

lowered.

A. Time and cost of experimentsB. Number of people involvedC. Number of data measurement pointsD. Output summary

Correct Answer: ASection: (none)Explanation

Explanation/Reference:

QUESTION 32Fractional Factorial Designs are used to analyze factors to model the output as a function of inputs ifHypothesis Testing in the Analyze Phase was inadequate to sufficiently narrow the factors that significantlyimpact the output(s).

A. TrueB. False

Correct Answer: ASection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 33A Factorial Experiment based on a Level 2 Design with 6 factors would require 16 runs to fully assess theinteractions.

A. TrueB. False

Correct Answer: BSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 34A Full Factorial experiment using a 3 level 3 factor approach has been proposed to test the viability of anextrusion machine experiment. How many treatment combinations will this approach involve?

A. 6B. 9C. 27D. 54

Correct Answer: CSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 35

Page 11: Six Sigma.NewQuestions.LSSBB.v2015-07-21.by.Tracy · Six Sigma LSSBB Questions & Answers Lean Six Sigma Black Belt Exam Version: 4.1 Six Sigma LSSBB Exam. Exam A QUESTION 1 A _____

Screening experiments are the proper choice when a Belt is faced with the situation of highly FractionalFactorial Designs.

A. TrueB. False

Correct Answer: ASection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 36A valid mathematical Regression represents all of the characteristics shown except___________________________.

A. The residuals when plotted follow a Normal DistributionB. The sum of the residuals is zeroC. All of the standardized residuals will be within ±3 Standard DeviationsD. Most standardized residuals are within ±2 Standard Deviations

Correct Answer: ASection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 37When a Belt conducts a Linear Correlation Analysis and finds that as an X increases the Y also increasethen he has proven a ______________ correlation.

A. NegativeB. PositiveC. MonomialD. Single alignment

Correct Answer: BSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 38A valid Multiple Linear Regression (MLR) is characterized by all of these except_______________________.

A. It is an assumption that the X's (inputs) are not correlated to each otherB. The X's (inputs) are assumed to be independent of each otherC. MLR is conducted based on a deliberate form of experimentationD. The Residuals from MLR analysis have to be Normally Distributed

Correct Answer: CSection: (none)Explanation

Explanation/Reference:Explanation:

Page 12: Six Sigma.NewQuestions.LSSBB.v2015-07-21.by.Tracy · Six Sigma LSSBB Questions & Answers Lean Six Sigma Black Belt Exam Version: 4.1 Six Sigma LSSBB Exam. Exam A QUESTION 1 A _____

QUESTION 39When doing Hypothesis Testing on Non-normal data Belts will use a ________________ to compare morethan two sample proportions to each other.

A. Z score TableB. Sakami TableC. Mean-to-Mode AnalysisD. Contingency Table

Correct Answer: CSection: (none)Explanation

Explanation/Reference:

QUESTION 40It would be more likely than not for a Belt conducting a Regression Analysis to find that the_______________________.

A. r2 value is smaller than the absolute value of rB. Correlation Coefficient equals r2C. Coefficient of Determination is less than r2D. Correlation Coefficient equals r divided by 2

Correct Answer: ASection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 41When a Belt properly analyzes the results of an experiment he must examine the Residuals in expectationof finding all of the following except _________.

A. Some Residuals higher than othersB. Some Residuals lower than othersC. All Residuals within 2 Standard Deviations of the MeanD. Residuals will represent a Linear Regression

Correct Answer: DSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 42Which of these might contribute to similar distributions having Unequal Variance?

A. Extreme tailsB. OutliersC. Multiple ModesD. All of the above

Correct Answer: DSection: (none)

Page 13: Six Sigma.NewQuestions.LSSBB.v2015-07-21.by.Tracy · Six Sigma LSSBB Questions & Answers Lean Six Sigma Black Belt Exam Version: 4.1 Six Sigma LSSBB Exam. Exam A QUESTION 1 A _____

Explanation

Explanation/Reference:

QUESTION 43A Belt working in a supply chain environment has to make a decision to change suppliers of critical rawmaterials for a new product upgrade. The purchasing manager is depending on the Belt's effort requiringthat the average cost of an internal critical raw material component be less than or equal to $4,200 in orderto stay within budget. Using a sample of 35 first article components, a Mean of the new product upgradeprice of $4,060, and a Standard Deviation of $98 was estimated. Select the answer that best states thePractical Problem.

A. If the average cost per component is $4,200 or less, then the purchase manager will introduce the newproduct upgrade with new components.

B. If the average cost per component is greater than $4,200, then the purchase manager will introduce thenew product upgrade with new components.

C. Only if the average cost per product upgrade is $4,060, will the purchase manager introduce newproduct upgrades with new components.

D. If the average cost per new product upgrade is less than $180, then the purchase manager willintroduce the new product upgrade with new components.

Correct Answer: CSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 44A Belt working in a supply chain environment has to make a decision to change suppliers of critical rawmaterials for a new product upgrade. The purchasing manager is depending on the Belt's effort requiringthat the average cost of an internal critical raw material component be less than or equal to $4,200 in orderto stay within budget. Using a sample of 35 first article components, a Mean of the new product upgradeprice of $4,060, and a Standard Deviation of $98 was estimated. The Alternative Hypothesis in the aboveexample is?

A. The Standard Deviation is equal to $300.B. The Mean is less than $4,320.C. The Mean is equal to $4,060.D. The Mean is less than $4,200.E. The Mean is greater than $ 4,200.

Correct Answer: ESection: (none)Explanation

Explanation/Reference:

QUESTION 45A Belt working in a supply chain environment has to make a decision to change suppliers of critical rawmaterials for a new product upgrade. The purchasing manager is depending on the Belt's effort requiringthat the average cost of an internal critical raw material component be less than or equal to $3,600 in orderto stay within budget. Using a sample of 42 first article components, a Mean of the new product upgradeprice of $3,200 and a Standard Deviation of $180 was estimated. Based on the data provided, the Z valuefor the data assuming a Normal Distribution is?

A. 1.11B. 2.22C. 4.30

Page 14: Six Sigma.NewQuestions.LSSBB.v2015-07-21.by.Tracy · Six Sigma LSSBB Questions & Answers Lean Six Sigma Black Belt Exam Version: 4.1 Six Sigma LSSBB Exam. Exam A QUESTION 1 A _____

D. 5.42

Correct Answer: BSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 46A Belt working in a supply chain environment has to make a decision to change suppliers of critical rawmaterials for a new product upgrade. The purchasing manager is depending on the Belt's effort requiringthat the average cost of an internal critical raw material component be less than or equal to $3,800 in orderto stay within budget. Using a sample of 38 first article components, a Mean of the new product upgradeprice of $3,680, and a Standard Deviation of $120 was estimated. In order to increase the Long Term Zvalue to 5, what is the maximum long term variation in pricing the Belt can accept for his upgraded criticalraw material component?

A. $6B. $12C. $24D. $48

Correct Answer: CSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 47Sally and Sara sell flower pots at their garage sale. Sally motivates Sara mentioning that they will sell aminimum of 15 pots per day if the outside temperature exceeds 60o F. From a sample, whose population isassumed to follow a Normal Distribution, taken for 30 days at 60 degrees or more an average of 13.6 potsper day were sold with a Standard Deviation of 0.7 pots. For the sales accomplished above, what testwould validate if they met their requirements?

A. F TestB. Test for Equal VarianceC. Chi Square TestD. One-Sample t-Test

Correct Answer: DSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 48Sally and Sara sell flower pots at their garage sale. Sally motivates Sara mentioning that they will sell aminimum of 15 pots per day if the outside temperature exceeds 60o F. From a sample, whose population isassumed to follow a Normal Distribution, taken for 30 days at 60 degrees or more an average of 13.6 potsper day were sold with a Standard Deviation of 0.7 pots. The statistical Degrees of Freedom for thisexample are?

A. 1B. 29C. 30D. 31

Page 15: Six Sigma.NewQuestions.LSSBB.v2015-07-21.by.Tracy · Six Sigma LSSBB Questions & Answers Lean Six Sigma Black Belt Exam Version: 4.1 Six Sigma LSSBB Exam. Exam A QUESTION 1 A _____

E. 2

Correct Answer: BSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 49Sally and Sara sell flower pots at their garage sale. Martha motivates Rose mentioning that they will sell aminimum of 16 pots per day if the outside temperature exceeds 60o F. From a sample, whose population isassumed to follow a Normal Distribution, taken for 30 days at 60 degrees or more an average of 15.2 potsper day were sold with a Standard Deviation of 0.6 pots. What is the Z value for this sales process?

A. 0.67B. 1.13C. 1.33D. 2.66

Correct Answer: CSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 50The relationship between a response variable and one or more independent variables is investigated andmodeled by use of __________________.

http://www.gratisexam.com/

A. X-Y MatrixB. Baldridge AssessmentC. Analysis of Variance (ANOVA)D. Critical X's Definition

Correct Answer: CSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 51An ANOVA used across many dependent variables could increase the Beta risk.

A. TrueB. False

Correct Answer: BSection: (none)Explanation

Page 16: Six Sigma.NewQuestions.LSSBB.v2015-07-21.by.Tracy · Six Sigma LSSBB Questions & Answers Lean Six Sigma Black Belt Exam Version: 4.1 Six Sigma LSSBB Exam. Exam A QUESTION 1 A _____

Explanation/Reference:Explanation:

QUESTION 52The Mann-Whitney test is a powerful test and is unique to situations from which of the choices listed?(Note: There are 2 correct answers).

A. Testing the identity of two populationsB. Focuses on equality of the Median of the two populationsC. Less powerful than the traditional "t-test"D. More widely applicable than the traditional "t-test"

Correct Answer: BDSection: (none)Explanation

Explanation/Reference:

QUESTION 53Assessing process proportion as opposed to evaluating a process with respect to a set target can be doneusing which of these?

A. Process proportion equals some value rangeB. Process proportion equals some desired valueC. Target is currentD. Proportion of the tail is equal

Correct Answer: BSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 54A Non-parametric Test should be used if just one distribution is not Normal out of the two or moregathered.

A. TrueB. False

Correct Answer: ASection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 55Contingency Tables are used to test for association, or dependency, between two or more classifications.

A. TrueB. False

Correct Answer: ASection: (none)Explanation

Page 17: Six Sigma.NewQuestions.LSSBB.v2015-07-21.by.Tracy · Six Sigma LSSBB Questions & Answers Lean Six Sigma Black Belt Exam Version: 4.1 Six Sigma LSSBB Exam. Exam A QUESTION 1 A _____

Explanation/Reference:

QUESTION 56A(n) ______________ is best used to compare a Machine 1 average quality characteristic to the samequality characteristic of Machine 2.

A. F testB. 1-Sample t-testC. 2-Sample t-testD. ANOVA test

Correct Answer: CSection: (none)Explanation

Explanation/Reference:

QUESTION 57A(n) ________________ has occurred when two inputs have a greater impact on a change in the outputthan either of the inputs has by itself.

A. DependencyB. Bimodal reactionC. InteractionD. Amplified effect

Correct Answer: CSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 58When conducting a Hypothesis Test using Continuous Data the proper sample size is influenced by theextent to which we need to assess a Difference to be detected and the inherent variation in the process.

A. TrueB. False

Correct Answer: ASection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 59The validity of the decision made with Hypothesis Testing is dependent upon all of these except___________________.

A. Beta riskB. Alpha riskC. Range of dataD. Sample size

Correct Answer: CSection: (none)

Page 18: Six Sigma.NewQuestions.LSSBB.v2015-07-21.by.Tracy · Six Sigma LSSBB Questions & Answers Lean Six Sigma Black Belt Exam Version: 4.1 Six Sigma LSSBB Exam. Exam A QUESTION 1 A _____

Explanation

Explanation/Reference:Explanation:

QUESTION 60Statistical Difference is the magnitude of difference or change required to distinguish between a truedifference, brought about by change or improvement, and one that could have occurred by chance.

A. TrueB. False

Correct Answer: ASection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 61To be an effective Lean Six Sigma practitioner one must understand the difference between___________________________.

A. ANOVA and the Analysis of VarianceB. Nonparametric tests and tests of Non-normal DataC. F-test and test of variances of 2 samplesD. Practical and Statistical significance

Correct Answer: DSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 62A Belt is analyzing data and upon creation of the graphical analysis sees multiple modes. One of theprimary reasons this could occur is because the process has experienced a ____________________.

A. Significant change from one shift to anotherB. Sizable Measurement System errorC. Catastrophic failure of some sortD. Any one of these

Correct Answer: DSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 63Time is always the metric on the horizontal scale of a(n) ___________ Chart.

A. ParetoB. XbarC. Multi-VariD. NP

Correct Answer: C

Page 19: Six Sigma.NewQuestions.LSSBB.v2015-07-21.by.Tracy · Six Sigma LSSBB Questions & Answers Lean Six Sigma Black Belt Exam Version: 4.1 Six Sigma LSSBB Exam. Exam A QUESTION 1 A _____

Section: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 64To properly analyze the variables impacting the output of a process we need to collect data that representsat least 80% of the variation in the process and assure ourselves we are collecting data from all three typesof variation which are _______________.

A. Within, Between and TemporalB. Within, Between and TemporaryC. Without, Above and BelowD. Induced, Natural and Unavoidable

Correct Answer: ASection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 65When the Inputs, X's, for your process are Normally Distributed about the Mean, the Outputs, Y's, willalways be Normally Distributed.

A. TrueB. False

Correct Answer: BSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 66On a _________________ a Belt screens variables, or various inputs, to analyze their relative impact onthe output of concern.

A. X-Y MatrixB. Weighted ScaleC. Multi-Vari ChartD. Poisson Chart

Correct Answer: CSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 67For a Normal Distribution as samples size increases the Range in Mean and Standard Deviation decreaserelative to the Mean and Standard Deviation of the population.

A. TrueB. False

Page 20: Six Sigma.NewQuestions.LSSBB.v2015-07-21.by.Tracy · Six Sigma LSSBB Questions & Answers Lean Six Sigma Black Belt Exam Version: 4.1 Six Sigma LSSBB Exam. Exam A QUESTION 1 A _____

Correct Answer: ASection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 68Some of the sources for different types of error that can be quantified using Statistical Analysis are___________________.

A. Error in samplingB. Bias in samplingC. Error in measurementD. All of these answers are correct

Correct Answer: DSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 69Since Normality is required if we intend to use the data collected as a predictive tool. To test for Normalityof data we must determine if the P-value is ___________.

A. Equal to 0.05B. Less than 0.05C. Greater than 0.05D. Greater than 0.5

Correct Answer: CSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 70The Normal Distribution is considered to be the most important distribution in statistics and, among otherthings is defined as having a total area under the curve of 1, is mounded and symmetrical and the Mean,Median and Mode are _____________.

A. All evenly divisible by 3B. Twice the Standard DeviationC. Within 10% of each otherD. The same number

Correct Answer: DSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 71Following process modifications, the Null Hypothesis states that no improvement to the process hasoccurred. If we discover the Null Hypothesis Test was rejected when it was false that would be a(n)________________________.

Page 21: Six Sigma.NewQuestions.LSSBB.v2015-07-21.by.Tracy · Six Sigma LSSBB Questions & Answers Lean Six Sigma Black Belt Exam Version: 4.1 Six Sigma LSSBB Exam. Exam A QUESTION 1 A _____

A. Alpha ErrorB. Type I ErrorC. Type II ErrorD. Type III Error

Correct Answer: CSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 72A statistical test or Hypothesis Test is performed to reject or fail to reject a stated hypothesis and itconverts the Practical Problem into a Statistical Problem.

A. TrueB. False

Correct Answer: ASection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 73A ___________ is used primarily to track the stability of the average value of a metric of interest.

A. NP ChartB. Xbar-R ChartC. I-MR ChartD. C Chart

Correct Answer: BSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 74For her injection molding project a Belt needed to track the percentage of defectives of a particular sampleset so she used a ___________ to display the data?

A. Individual ChartB. C ChartC. Xbar ChartD. P Chart

Correct Answer: DSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 75Which of these graphs demonstrates conditions which would be sufficient to enable OCAP for the process?

Page 22: Six Sigma.NewQuestions.LSSBB.v2015-07-21.by.Tracy · Six Sigma LSSBB Questions & Answers Lean Six Sigma Black Belt Exam Version: 4.1 Six Sigma LSSBB Exam. Exam A QUESTION 1 A _____

A. Xbar ChartB. Time Series ChartC. NeitherD. Both

Correct Answer: ASection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 76How many experimental runs exist in a Full Factorial and fully randomized design for 5 factors with 2replicates for the Corner Points and no Center Points? The factors in the experiment are only at 2-levels.

A. 10B. 128C. 256D. 64

Correct Answer: DSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 77If an experiment has 5 factors and no replicates for a 2-level Experimental Design with 16 experimentalruns which statement(s) are correct? (Note: There are 3 correct answers).

A. The Main Effects for the 5 factors are not aliased or confounded but the 2-way interactions areconfounded with the 3-way interactions

B. The Main Effects are confounded with only 4-way interactionsC. The Experimental Design is half-fractionalD. The experiment has 8 experimental runs with the first factor at the high levelE. The experiment has only 4 experimental runs with the 5th factor at the high level

Correct Answer: BCDSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 78With Measurement System Analysis we are concerned with two issues that impact the potential variabilityof the data. They are ____________ and Accuracy.

A. SpreadB. ReliabilityC. PrecisionD. Deflection

Correct Answer: CSection: (none)Explanation

Page 23: Six Sigma.NewQuestions.LSSBB.v2015-07-21.by.Tracy · Six Sigma LSSBB Questions & Answers Lean Six Sigma Black Belt Exam Version: 4.1 Six Sigma LSSBB Exam. Exam A QUESTION 1 A _____

Explanation/Reference:Explanation:

QUESTION 79An operator is measuring the distance between two points. Which is most likely to be influenced by theoperator?

A. Precision of the measurementB. Accuracy of the measurementC. Calibration of the instrumentD. All of these answers are correct

Correct Answer: DSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 80Accuracy can be assessed in several ways and a fairly accurate means of measurement is visualcomparison.

A. TrueB. False

Correct Answer: BSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 81Measurement __________ is defined as the difference between the observed and the expected values fora given set of data.

A. BreadthB. LinearityC. RangeD. Bias

Correct Answer: DSection: (none)Explanation

Explanation/Reference:

QUESTION 82Appropriate measures means that measurements are ______________.

A. RepresentativeB. SufficientC. ContextualD. RelevantE. All of these answers are correct

Correct Answer: E

Page 24: Six Sigma.NewQuestions.LSSBB.v2015-07-21.by.Tracy · Six Sigma LSSBB Questions & Answers Lean Six Sigma Black Belt Exam Version: 4.1 Six Sigma LSSBB Exam. Exam A QUESTION 1 A _____

Section: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 83A ___________ problem in the Measurement System suggests that there is a lack of consistency in themeasurement over time.

A. LinearityB. BiasC. StabilityD. Magnitude

Correct Answer: CSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 84An operator checks that all boxes being packed contain enough products to fill the box. However, each boxgetting filled has a different number of products in it. This is a Reproducibility problem, not a Repeatabilityproblem.

A. TrueB. False

Correct Answer: BSection: (none)Explanation

Explanation/Reference:

QUESTION 85In a good Measurement System the most variation will be with part-to-part measurements. What shouldyou do if the majority of variation is associated with the Gage R&R assuming the gage is technicallycapable?

A. Focus on fixing the Repeatability and Reproducibility of the measurement deviceB. Purchase a new machineC. Focus on trimming the Part-to-Part variationD. Run another MSA test with the machine

Correct Answer: ASection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 86What aspects of Measurement Systems Analysis (MSA) studies are applicable when the process used tomeasure does not damage the part?

A. Destructive variable gage R&R and Crossed StudyB. Destructive variable gage R&R and Nested Study

Page 25: Six Sigma.NewQuestions.LSSBB.v2015-07-21.by.Tracy · Six Sigma LSSBB Questions & Answers Lean Six Sigma Black Belt Exam Version: 4.1 Six Sigma LSSBB Exam. Exam A QUESTION 1 A _____

C. Nondestructive variable gage R&R and Crossed StudyD. Nondestructive variable gage R&R and Nested Study

Correct Answer: DSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 87Each of the items listed would impact the Process Capability for a process with a continuous output except___________________.

A. Shape of process data distribution (e.g. Normal Distribution)B. Process TechnologyC. Process Standard DeviationD. Seasonal variation in process

Correct Answer: BSection: (none)Explanation

Explanation/Reference:

QUESTION 88For Attribute Data, Process Capability is defined as the average proportion of nonconforming products.

A. TrueB. False

Correct Answer: ASection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 89The reported Cpk for a process with an average of 104 units, a spread of 18 units and upper and lowerspecification limits of 122 and 96 units would be?

A. 0.5B. 0.89C. 1.00D. 2.00

Correct Answer: BSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 90When we compare short-term and long-term Capability which of these is true?

A. Cp is better for the short termB. Both short-term and long-term performance are alike

Page 26: Six Sigma.NewQuestions.LSSBB.v2015-07-21.by.Tracy · Six Sigma LSSBB Questions & Answers Lean Six Sigma Black Belt Exam Version: 4.1 Six Sigma LSSBB Exam. Exam A QUESTION 1 A _____

C. Performance tends to improve over timeD. Cp is better for the long-term

Correct Answer: ASection: (none)Explanation

Explanation/Reference:

QUESTION 91What is the Ppk of a process with a spread of 24 units, an average of 68, an upper limit of 82 and a lowerlimit of 54?

A. 1.68B. 2.00C. 4.00D. 4.42

Correct Answer: CSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 92Relative to a Design of Experiments the term Collinear refers to variables being a ________________ ofeach other.

A. Linear combinationB. Directly parallelC. Mirror imageD. None of the above

Correct Answer: ASection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 93Which statement(s) are incorrect about Fractional Factorial Designs?

A. A Half Fractional Design for 5 factors has the same number of experimental runs as a Full FactorialDesign for 4 factors assuming no repeats or replicates or Center Points

B. Quarter Fractional experiments can exist for those with 4 factorsC. Resolution V design is desired while controlling costs of experimentationD. Half Fractional experiments do not exist for those designs with only 2 factors

Correct Answer: CSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 94Fractional Factorial, ____________and Response Surface Method are types of planned experiments.

Page 27: Six Sigma.NewQuestions.LSSBB.v2015-07-21.by.Tracy · Six Sigma LSSBB Questions & Answers Lean Six Sigma Black Belt Exam Version: 4.1 Six Sigma LSSBB Exam. Exam A QUESTION 1 A _____

A. Multi-Vari AnalysisB. Baldridge ChannelsC. One Factor at a Time or OFATD. Factorial Design

Correct Answer: DSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 95If in an experiment all possible variable pairs sum to zero the design is Orthogonal.

A. TrueB. False

Correct Answer: ASection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 96Which Experimental Design typically is most associated with the fewest number of input variables orfactors in the design?

A. Response Surface designB. Full Factorial designC. Simple Linear RegressionD. Fractional Factorial design

Correct Answer: ASection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 97The method of Steepest Ascent guides you toward a target inside the original inference space.

A. TrueB. False

Correct Answer: BSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 98The Lean toolbox includes all of the following items except __________.

A. Poke-YokeB. Standard Operating Procedures

Page 28: Six Sigma.NewQuestions.LSSBB.v2015-07-21.by.Tracy · Six Sigma LSSBB Questions & Answers Lean Six Sigma Black Belt Exam Version: 4.1 Six Sigma LSSBB Exam. Exam A QUESTION 1 A _____

C. KaizenD. 5S the work area

Correct Answer: BSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 99Questions that can be best answered by a Visual Factory include all of these except_____________________.

A. Are setups optimized for lower scrap levels?B. Can extra inventory be seen easily?C. Can changeover challenges be recognized?D. Are unneeded tools or supplies easily noted?

Correct Answer: ASection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 100Situations where standardized work needs to be incorporated include all of these except_____________________.

http://www.gratisexam.com/

A. Changeover instructions incompleteB. Lack of a system to assure proper inventory levels at repair stationsC. Machines continually operating to reduce the labor cost per pieceD. Process flow for the same product assembly taking various cycle time for completion "Leading the way

in IT Testing & Certification Tools" - www.testking.com 51 Six Sigma LSSBB Exam

Correct Answer: CSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 101If a Six Sigma project was to reduce changeover times and the team found the project success wasdecreasing over time since changeover times began to creep back up, which Lean tools should beconsidered in the Control Phase to reestablish and sustain the project success?

A. Improve the lighting to assure adequate visibilityB. Confirm a Visual Factory exists to assure proper communication of status of machinesC. Implement Kanbans to assure enough inventory for the process stepD. Reword the standardized work instructions to use active verbs and not passive phrases

Page 29: Six Sigma.NewQuestions.LSSBB.v2015-07-21.by.Tracy · Six Sigma LSSBB Questions & Answers Lean Six Sigma Black Belt Exam Version: 4.1 Six Sigma LSSBB Exam. Exam A QUESTION 1 A _____

Correct Answer: BSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 102Kaizens or Kaikakus and Six Sigma projects are intended to create breakthrough, significant processimprovement versus minor, incremental improvements.

A. TrueB. False

Correct Answer: ASection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 103Using this partial Z Table, how many units from a month's production run are expected to not satisfycustomer requirements for the following process?

Upper specification limit: 7.2 Lower specification limit: 4.3 Mean of the process: 5.9 Standard Deviation:0.65 Monthly production: 450 units

A. 3B. 7C. 10D. 12

Correct Answer: CSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 104Which of these items are not part of what is necessary for successful Kaizens?

A. Good lightingB. Management supportC. Operator supportD. Analysis tools

Correct Answer: ASection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 105When a Belt implements an improvement that is automated thus requiring no particular understanding foruse he has applied which Lean tool?

A. Mistake Proofing

Page 30: Six Sigma.NewQuestions.LSSBB.v2015-07-21.by.Tracy · Six Sigma LSSBB Questions & Answers Lean Six Sigma Black Belt Exam Version: 4.1 Six Sigma LSSBB Exam. Exam A QUESTION 1 A _____

B. Kaizen EventC. 5SD. None of the above

Correct Answer: ASection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 106Kanban establishes a means of monitoring production, conveyance and delivery information such thatefficient flow is established. The method used by Kanban is to require a _________ before anythingmoves.

A. Sign-offB. SignalC. Bell to ringD. Work order

Correct Answer: BSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 107For a Kanban to be successful which of these must occur?

A. Consistent cycle timesB. Fairly stable process demand of product or serviceC. Low defect rate of incoming product or serviceD. All of the above

Correct Answer: DSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 108Common and Special Cause ______________ are the focus of Statistical Process Control.

A. PredictionB. IdeationC. CapabilityD. Variation

Correct Answer: DSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 109Special Cause Variation falls into which two categories? (Note: There are 2 correct answers).

Page 31: Six Sigma.NewQuestions.LSSBB.v2015-07-21.by.Tracy · Six Sigma LSSBB Questions & Answers Lean Six Sigma Black Belt Exam Version: 4.1 Six Sigma LSSBB Exam. Exam A QUESTION 1 A _____

A. NaturalB. Short termC. AssignableD. Pattern

Correct Answer: CDSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 110Control Charts were developed by Dr. Shewhart to track data over time. To detect Special Cause variationthe Control Charts use which of these?

A. Data shift analysisB. Outlier analysis methodsC. Center Line and Control LimitsD. None of the above

Correct Answer: CSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 111If the production is for higher volume and monitoring and the Mean and variability is to be monitored forfour machines producing product and the characteristic to be monitored is Variable Data, which SPC Chartis best to be selected?

A. Xbar-R ChartB. Individual-MR ChartC. NP ChartD. CUSUM Chart

Correct Answer: ASection: (none)Explanation

Explanation/Reference:

QUESTION 112If you can Poka-Yoke a defect out of the process entirely then you do not need use SPC on thecharacteristic of interest in the defect.

A. TrueB. False

Correct Answer: ASection: (none)Explanation

Explanation/Reference:Explanation:

Page 32: Six Sigma.NewQuestions.LSSBB.v2015-07-21.by.Tracy · Six Sigma LSSBB Questions & Answers Lean Six Sigma Black Belt Exam Version: 4.1 Six Sigma LSSBB Exam. Exam A QUESTION 1 A _____

QUESTION 113Range Charts are the technique used to determine if ______________ are occurring within the subgroupsof the SPC Charts.

A. Common CausesB. Special inspectionsC. Unnatural forcesD. Special Causes

Correct Answer: DSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 114If a process has subgroups for Variable data and the process runs for a long period of time, then the bestpair of SPC Charts to use would be an Xbar and _________.

A. NP ChartB. Individuals ChartC. R ChartD. C Chart

Correct Answer: CSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 115The Control Limits width varies if the sample size varies for which type of chart?

A. P ChartsB. NP ChartsC. Xbar-R ChartsD. Time Series Charts

Correct Answer: ASection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 116Which of these elements are not included in Implementation plans?

A. Work breakdown structureB. Cost/Benefit ratiosC. Risk management plansD. Planned audits of work completion

Correct Answer: BSection: (none)Explanation

Page 33: Six Sigma.NewQuestions.LSSBB.v2015-07-21.by.Tracy · Six Sigma LSSBB Questions & Answers Lean Six Sigma Black Belt Exam Version: 4.1 Six Sigma LSSBB Exam. Exam A QUESTION 1 A _____

Explanation/Reference:Explanation:

QUESTION 117Following the completion of a LSS project the Belt not only creates a Control Plan he also develops a_____________ so those involved in the process know what to do when the critical metrics move out ofspec.

A. Response PlanB. Call ListC. Chain-of-CommandD. Defect Analysis Plan

Correct Answer: ASection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 118Six Sigma is a business improvement discipline whose fundamental view is based on a _________oriented approach of the business.

A. ProfitB. PerformanceC. ProcessD. Predatory

Correct Answer: BSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 119Much of the Six Sigma methodology is used to identify and remove causes for _____________ .

A. Process VariationB. Material CostsC. Excess InventoryD. Lost Sales

Correct Answer: ASection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 120When variation is removed from the output of a process then the process customer can have moreconfidence in the experience that results from the process.

A. TrueB. False

Correct Answer: ASection: (none)

Page 34: Six Sigma.NewQuestions.LSSBB.v2015-07-21.by.Tracy · Six Sigma LSSBB Questions & Answers Lean Six Sigma Black Belt Exam Version: 4.1 Six Sigma LSSBB Exam. Exam A QUESTION 1 A _____

Explanation

Explanation/Reference:Explanation:

QUESTION 121The distance between the Mean of a data set and the Point of Inflection on a Normal curve is called the_______________.

A. Curve SpreadB. Standard DeviationC. Numerical AverageD. Data Breadth

Correct Answer: BSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 122One of the foundations of Lean Six Sigma is the concept that the output of a process (Y) is influenced bythe process inputs (X's) and is commonly shown as which formula?

A. Y = Z(X2)B. Y = f(X3)C. Y = f(Xn)D. Y = g(X+ 1.5)

Correct Answer: CSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 123When we gather information for the Voice of the Business we are primarily interested in informationconcerning the _____________ of the business.

A. Advertising budgetB. Market shareC. ProfitabilityD. Ownership

Correct Answer: CSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 124When a Belt creates a Process Map she will use a __________________ to depict a decision pointrequiring a Yes or No decision.

A. CircleB. SquareC. Diamond

Page 35: Six Sigma.NewQuestions.LSSBB.v2015-07-21.by.Tracy · Six Sigma LSSBB Questions & Answers Lean Six Sigma Black Belt Exam Version: 4.1 Six Sigma LSSBB Exam. Exam A QUESTION 1 A _____

D. Rectangle

Correct Answer: CSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 125A Belt has determined that the inventory of repair parts at a rework station can be reduced by 45%.According to Cost of Poor Quality (COPQ) definitions inventory reduction would be considered_______________.

A. Soft SavingsB. COPQ efficiencyC. Median SavingsD. Hard Savings

Correct Answer: DSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 126Customers make their decisions based on Features, Integrity (of the seller) Delivery and ___________?

A. ColorB. Expense

http://www.gratisexam.com/

C. SeasonD. None

Correct Answer: BSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 127The Hardware Store ordered ten lawn mower from the manufacturer and just before shipping themanufacturer found one to have a motor that wouldn't start. For the manufacturer this would be categorizedas what type of cost?

A. Internal Failure CostsB. External Failure CostsC. Prevention CostsD. Appraisal Costs

Correct Answer: A

Page 36: Six Sigma.NewQuestions.LSSBB.v2015-07-21.by.Tracy · Six Sigma LSSBB Questions & Answers Lean Six Sigma Black Belt Exam Version: 4.1 Six Sigma LSSBB Exam. Exam A QUESTION 1 A _____

Section: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 128Cost of Poor Quality (COPQ) can be classified as Visible Costs and Hidden Costs. All these items areHidden Cost except __________________.

A. Lost Customer LoyaltyB. ReturnsC. Time Value of MoneyD. Late Delivery

Correct Answer: BSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 129Which of these are examples of business metrics or Key Performance Indicators commonly referred to asKPI's?

A. Cycle TimeB. DefectsC. No. of Units ReworkedD. Labor HoursE. All of these answers are correct

Correct Answer: ESection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 130When one speaks of 20% of something contributing 80% of the affect they are referring to what is knownas the _________________.

A. Shewhart ExampleB. Pareto PrincipleC. Balance EquationD. Connection Principle

Correct Answer: BSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 131Using this data calculate the percentage of DPU.

A. 2.74B. 3.23

Page 37: Six Sigma.NewQuestions.LSSBB.v2015-07-21.by.Tracy · Six Sigma LSSBB Questions & Answers Lean Six Sigma Black Belt Exam Version: 4.1 Six Sigma LSSBB Exam. Exam A QUESTION 1 A _____

C. 4.56D. 5.93

Correct Answer: BSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 132As a means of measuring the effects on other areas of a process as a result of changes in the primarymetric we also define and track ________________.

A. Parallel process metricsB. Secondary metricsC. Tertiary metricsD. Industry standards

Correct Answer: BSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 133Calculate the Rolled Throughput Yield of this process using this data. DatA. unit input: 1450, unit output:1390, defects repaireD. 320, scrap: 60

A. 71.33%B. 72.66%C. 73.79%D. 77.93%

Correct Answer: BSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 134"A calculated time frame that matches customer demand" is a definition of what Lean Principles term?

A. Value StreamB. Kaizen eventC. Takt timeD. Kanban

Correct Answer: CSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 135What dollar amount of savings would a project show if it reduced your outstanding Accounts Receivable by$1.4 million dollars to $5.3 million total and your organization's marginal cost of capital was 6.2%?

Page 38: Six Sigma.NewQuestions.LSSBB.v2015-07-21.by.Tracy · Six Sigma LSSBB Questions & Answers Lean Six Sigma Black Belt Exam Version: 4.1 Six Sigma LSSBB Exam. Exam A QUESTION 1 A _____

A. $43,400B. $86,800C. $117,500D. $328,600

Correct Answer: BSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 136Which Element of Waste best describes "the unnecessary movement of materials and goods"?

A. OverprocessingB. InventoryC. MotionD. Conveyance

Correct Answer: DSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 137A Belt rearranged the location of the parts inventory for a rework station locating the most often used partsto be within hand reach of the repair person. This rearrangement resulted in quicker repair times byeliminating one of seven major elements of waste which is the Waste of __________.

A. MotionB. ConveyanceC. InventoryD. Waiting

Correct Answer: ASection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 138The Japanese born function of a Kanban event utilizes a specific, step-by-step approach meant to bringabout major changes to a process.

A. TrueB. False

Correct Answer: BSection: (none)Explanation

Explanation/Reference:

QUESTION 139

Page 39: Six Sigma.NewQuestions.LSSBB.v2015-07-21.by.Tracy · Six Sigma LSSBB Questions & Answers Lean Six Sigma Black Belt Exam Version: 4.1 Six Sigma LSSBB Exam. Exam A QUESTION 1 A _____

The primary objective in removal of waste is to improve the Order Production Cycle where the time from_________________ to the time of receipt of payment is compressed.

A. Shift startB. Product developmentC. Receipt of an orderD. New fiscal year

Correct Answer: CSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 140Handling of warranty returns, process improvement team meetings and rework to meet customerexpectations are all examples of business costs that are classified as ________________ .

A. NuisanceB. Non-value AddC. NecessaryD. Unavoidable

Correct Answer: BSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 141At the very initiation of a project a Belt must develop a concise _______________ that states at a high levelthe area of concern and why it is important this issue be improved.

A. Business CaseB. Project DoctrineC. Management JustificationD. Process Owner Disclosure

Correct Answer: CSection: (none)Explanation

Explanation/Reference:

QUESTION 142The English words used for the 5S's are Sorting, Straightening, _____________ , __________ andSustaining. (Note: There are 2 correct answers).

A. ShapingB. ShiningC. StandardizingD. Signing

Correct Answer: BCSection: (none)

Page 40: Six Sigma.NewQuestions.LSSBB.v2015-07-21.by.Tracy · Six Sigma LSSBB Questions & Answers Lean Six Sigma Black Belt Exam Version: 4.1 Six Sigma LSSBB Exam. Exam A QUESTION 1 A _____

Explanation

Explanation/Reference:Explanation:

QUESTION 143An example of the waste of mismanaged Inventory is __________.

A. Capital costs of moneyB. Value decrease from aged inventoryC. Cost of storage spaceD. All of these answers are correct

Correct Answer: DSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 144In a Fishbone Diagram the 6M's stand for Methods, ____________, Machine, Man, Mother Nature andMaterials.

A. MeasurementsB. MergerC. ManagementD. Medical

Correct Answer: ASection: (none)Explanation

Explanation/Reference:

QUESTION 145The most appropriate type of FMEA for a product before going into manufacturing is a ___________FMEA.

A. DesignB. ConsumerC. SurveyD. Test Process

Correct Answer: ASection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 146Which one of the listed tools is frequently used to help drill down to possible causes once a FishboneDiagram is constructed?

A. 3 When AnalysisB. Skeleton DiagnosticC. Ishikawa Diagram

Page 41: Six Sigma.NewQuestions.LSSBB.v2015-07-21.by.Tracy · Six Sigma LSSBB Questions & Answers Lean Six Sigma Black Belt Exam Version: 4.1 Six Sigma LSSBB Exam. Exam A QUESTION 1 A _____

D. 5 Why Analysis

Correct Answer: DSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 147One of the primary deliverables from performing a SIPOC is to begin to understand which inputs have thegreatest affect on the ______________ outputs.

A. Management's desiredB. Supplier deliveredC. Process operatorD. Customer most valued

Correct Answer: DSection: (none)Explanation

Explanation/Reference:

QUESTION 148Two of the key deliverables for the Measure Phase are a robust description of the process and its flow andan assessment of the Management System.

A. TrueB. False

Correct Answer: BSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 149A valuable tool to use during the Measure Phase to show material and information flow throughout anentire process is the ______________ .

A. Value Stream MapB. FMEAC. Pareto ChartD. Standard Operating Procedure

Correct Answer: ASection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 150Which of the items listed do not define what an X-Y Diagram is?

A. Created for every projectB. Based on team's collective opinions

Page 42: Six Sigma.NewQuestions.LSSBB.v2015-07-21.by.Tracy · Six Sigma LSSBB Questions & Answers Lean Six Sigma Black Belt Exam Version: 4.1 Six Sigma LSSBB Exam. Exam A QUESTION 1 A _____

C. Updated whenever a parameter is changedD. Used to show each step in a processE. A living document throughout project lifecycle

Correct Answer: DSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 151The two types of data that are to be used in Statistical Analysis are Attribute and Variance.

A. TrueB. False

Correct Answer: BSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 152Early in a project a Belt will want to begin to identify and evaluate risk factors for the subject process andwill therefore begin building a(n) ______________.

A. SIPOCB. FMEAC. Business CaseD. Team charter

Correct Answer: BSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 153Data that can be measured on a continuum and has meaningful decimal subdivisions are __________data.

A. ContinuousB. SurplusC. DiscreteD. Variable

Correct Answer: ASection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 154Of the various types of data shown which is NOT representative of Variable Data.

A. Child's height is 4 foot 3 inches

Page 43: Six Sigma.NewQuestions.LSSBB.v2015-07-21.by.Tracy · Six Sigma LSSBB Questions & Answers Lean Six Sigma Black Belt Exam Version: 4.1 Six Sigma LSSBB Exam. Exam A QUESTION 1 A _____

B. Three employees wore hard hatsC. Car burned 2.7 gallons of gasolineD. Train was going 140 kilometers per hour

Correct Answer: BSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 155All the data points that represent the total set of information of interest is called the ________________ .

A. PopulationB. SampleC. FrameD. Spread

Correct Answer: ASection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 156A fundamental rule is that both Standard Deviation and Variance can be added.

A. TrueB. False

Correct Answer: BSection: (none)Explanation

Explanation/Reference:Explanation:

http://www.gratisexam.com/

QUESTION 157One of the methods of testing a Measurement System is to have at least two people take multiple readingsfrom the same instrument and of the same sample set to judge the Repeatability and Reproducibly. Thisapproach is called a ______________ study.

A. Correlation AnalysisB. Gage R & RC. BimodalD. Dual Attribute

Correct Answer: BSection: (none)Explanation

Page 44: Six Sigma.NewQuestions.LSSBB.v2015-07-21.by.Tracy · Six Sigma LSSBB Questions & Answers Lean Six Sigma Black Belt Exam Version: 4.1 Six Sigma LSSBB Exam. Exam A QUESTION 1 A _____

Explanation/Reference:Explanation:

QUESTION 158A natural logarithmic base is not required for which of these distributions for probability calculations?

A. WeibullB. BinomialC. PoissonD. Normal

Correct Answer: DSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 159Production Line 1 is able to complete 500 units per shift. Production Line 2 is able to finish 1,500 units pershift. Production Line 2 is 3 times faster than Production Line 1. This analysis is an example of______________ Scale Data.

A. NominalB. RatioC. OrdinalD. Interval

Correct Answer: BSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 160A dock worker for a feed supplier was tasked with assuring the proper weight in the feed bags as they leftthe dock. One of the columns listed the range of weight of the bags included in the studies. This requiredplotting a Histogram of the weight of the bags. While drawing the Histogram the x-axis contained a certainscale of data. Pick the scale of data that is appropriate for Histograms.

A. Ordinal Scale DataB. Interval Scale DataC. Nominal Scale DataD. Ration Scale Data

Correct Answer: BSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 161The _______ is the most frequently occurring value in a distribution of data.

A. MedianB. MeanC. Center Point

Page 45: Six Sigma.NewQuestions.LSSBB.v2015-07-21.by.Tracy · Six Sigma LSSBB Questions & Answers Lean Six Sigma Black Belt Exam Version: 4.1 Six Sigma LSSBB Exam. Exam A QUESTION 1 A _____

D. Mode

Correct Answer: DSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 162Use this data to calculate the Z Score. Average of: 92, Standard Deviation: 2, Upper Spec Limit:

A. 0.75B. 1.5C. 2.25D. 4.50

Correct Answer: DSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 163If a Belt needed to model the data for the number of weaves in section of carpet fabric she would use the_____________ Distribution approach.

A. PoissonB. ExtendedC. ExponentialD. Weibull

Correct Answer: ASection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 164When analyzing the behavior of our process to assess customer satisfaction we are concerned about boththe variation such that it stays within the spec limits and how well the Mean is __________________ theprocess requirements.

A. Balanced againstB. Over and aboveC. Twice as great asD. Centered relative to

Correct Answer: DSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 165Using this partial Z Table, how many units from a month's production run are expected to not satisfycustomer requirements for the following process? Upper specification limit: 8.4 Lower specification limit:

Page 46: Six Sigma.NewQuestions.LSSBB.v2015-07-21.by.Tracy · Six Sigma LSSBB Questions & Answers Lean Six Sigma Black Belt Exam Version: 4.1 Six Sigma LSSBB Exam. Exam A QUESTION 1 A _____

4.7 Mean of the process: 6.2 Standard Deviation: 2.2 Monthly production: 360 units

A. 8B. 13C. 28D. 57

Correct Answer: DSection: (none)Explanation

Explanation/Reference:

QUESTION 166A Full Factorial experiment using a 2 level 4 factor approach has been proposed to test the viability of anextrusion machine experiment. How many treatment combinations will this approach involve?

A. 8B. 16C. 32D. 64

Correct Answer: BSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 167Fractional Factorial Designs are used to analyze factors to model the output as a function of inputs ifHypothesis Testing in the Analyze Phase was inadequate to sufficiently narrow the factors that significantlyimpact the output(s).

A. TrueB. False

Correct Answer: ASection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 168Fractional Factorial designs are used to reduce the time and cost of experiments because the____________ has been lowered.

A. Number of data measurement pointsB. Number of runsC. People involvedD. Output summary

Correct Answer: BSection: (none)Explanation

Explanation/Reference:Explanation:

Page 47: Six Sigma.NewQuestions.LSSBB.v2015-07-21.by.Tracy · Six Sigma LSSBB Questions & Answers Lean Six Sigma Black Belt Exam Version: 4.1 Six Sigma LSSBB Exam. Exam A QUESTION 1 A _____

QUESTION 169A Factorial Experiment based on a Level 2 Design with 4 factors would require 16 runs to fully assess theinteractions.

A. TrueB. False

Correct Answer: ASection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 170Screening experiments are the proper choice when a Belt is faced with the situation of highly FractionalFactorial Designs.

A. TrueB. False

Correct Answer: ASection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 171A(n) ______________ is best used to compare a Machine 1 average quality characteristic to the samequality characteristic of Machine 2.

A. 1-Sample t-testB. 2-Sample t-testC. F testD. ANOVA test

Correct Answer: BSection: (none)Explanation

Explanation/Reference:

QUESTION 172When a Belt properly analyzes the results of an experiment he must examine the Residuals in expectationof finding all of the following except _________.

A. Some Residuals higher than othersB. Residuals will represent a Linear RegressionC. All Residuals within 2 Standard Deviations of the MeanD. Some Residuals lower than others

Correct Answer: BSection: (none)Explanation

Explanation/Reference:

Page 48: Six Sigma.NewQuestions.LSSBB.v2015-07-21.by.Tracy · Six Sigma LSSBB Questions & Answers Lean Six Sigma Black Belt Exam Version: 4.1 Six Sigma LSSBB Exam. Exam A QUESTION 1 A _____

QUESTION 173Choose those characteristics of a Simple Linear Regression (SLR) Analysis that are applicable.(Note: There are 3 correct answers).

A. The Correlation Coefficient is always greater than the Regression Coefficient in a SLRB. General Regression Analysis deals only with Continuous DataC. Non-linear Regressions can explain curvature when with more statistical confidence than Linear

RegressionsD. SLR can help quantify the significance of variation in X that influences the variation in Y via a

mathematical equationE. A Correlation does not explain causation but a Regression Analysis with a statistically valid

mathematical equation does explain causation

Correct Answer: ADESection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 174A valid Multiple Linear Regression (MLR) is characterized by all of these except?

A. It is an assumption that the X's (inputs) are not correlated to each otherB. The X's (inputs) are assumed to be independent of each otherC. The Residuals from MLR analysis have to be Normally DistributedD. MLR is conducted based on a deliberate form of experimentationE. It is not possible to evaluate interactions in a MLR analysis

Correct Answer: DSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 175The calculation of Column Total times Row Total divided by Grand Total yields expected values from whattype of chart?

A. Pareto ChartB. Sakami TableC. Contingency TableD. None

Correct Answer: CSection: (none)Explanation

Explanation/Reference:

QUESTION 176Contingency Tables are used to test for association, or dependency, between two or more classifications.

A. TrueB. False

Page 49: Six Sigma.NewQuestions.LSSBB.v2015-07-21.by.Tracy · Six Sigma LSSBB Questions & Answers Lean Six Sigma Black Belt Exam Version: 4.1 Six Sigma LSSBB Exam. Exam A QUESTION 1 A _____

Correct Answer: ASection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 177It would be more likely than not for a Belt conducting a Regression Analysis to find that the_______________________.

A. r2 value is smaller than the absolute value of rB. Correlation Coefficient equals r2C. Coefficient of Determination is less than r2D. Correlation Coefficient equals r divided by 2

Correct Answer: ASection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 178A valid mathematical Regression represents all of the characteristics shown except _________________.

A. All of the standardized residuals will be within ±3 Standard DeviationsB. The sum of the residuals is zeroC. The residuals when plotted follow a Normal DistributionD. Most standardized residuals are within ±2 Standard DeviationsE. The Residual is equal to the difference between the observed and predicted values

Correct Answer: ASection: (none)Explanation

Explanation/Reference:

QUESTION 179Which of these might contribute to similar distributions having Unequal Variance?

A. Extreme tailsB. OutliersC. Multiple ModesD. All of the above

Correct Answer: DSection: (none)Explanation

Explanation/Reference:

QUESTION 180A Belt working in a supply chain environment has to make a decision to change suppliers of critical rawmaterials for a new product upgrade. The purchasing manager is depending on the Belt's effort requiringthat the average cost of an internal critical raw material component be less than or equal to $4,200 in orderto stay within budget. Using a sample of 35 first article components, a Mean of the new product upgradeprice of $4,060, and a Standard Deviation of $98 was estimated. Select the answer that best states the

Page 50: Six Sigma.NewQuestions.LSSBB.v2015-07-21.by.Tracy · Six Sigma LSSBB Questions & Answers Lean Six Sigma Black Belt Exam Version: 4.1 Six Sigma LSSBB Exam. Exam A QUESTION 1 A _____

Practical Problem.

A. If the average cost per component is $4,200 or less, then the purchase manager will introduce the newproduct upgrade with new components

B. If the average cost per component is greater than $4,200, then the purchase manager will introduce thenew product upgrade with new components

C. Only if the average cost per product upgrade is $4,060, will the purchase manager introduce newproduct upgrades with new components

D. If the average cost per new product upgrade is less than $180, then the purchase manager willintroduce the new product upgrade with new components

Correct Answer: CSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 181A Belt working in a supply chain environment has to make a decision to change suppliers of critical rawmaterials for a new product upgrade. The purchasing manager is depending on the Belt's effort requiringthat the average cost of an internal critical raw material component be less than or equal to $4,200 in orderto stay within budget. Using a sample of 35 first article components, a Mean of the new product upgradeprice of $4,060, and a Standard Deviation of $98 was estimated. The Alternative Hypothesis in the aboveexample is?

A. The Standard Deviation is equal to $300B. The Mean is less than $4,320C. The Mean is equal to $4,060D. The Mean is less than $4,200E. The Mean is greater than $ 4,200

Correct Answer: ESection: (none)Explanation

Explanation/Reference:

QUESTION 182A Belt working in a supply chain environment has to make a decision to change suppliers of critical rawmaterials for a new product upgrade. The purchasing manager is depending on the Belt's effort requiringthat the average cost of an internal critical raw material component be less than or equal to $2,800 in orderto stay within budget. Using a sample of 55 first article components, a Mean of the new product upgradeprice of $2,240 and a Standard Deviation of $120 was estimated. Based on the data provided, the Z valuefor the data assuming a Normal Distribution is?

A. 2.33B. 4.67C. 6.48D. 8.28

Correct Answer: BSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 183

Page 51: Six Sigma.NewQuestions.LSSBB.v2015-07-21.by.Tracy · Six Sigma LSSBB Questions & Answers Lean Six Sigma Black Belt Exam Version: 4.1 Six Sigma LSSBB Exam. Exam A QUESTION 1 A _____

A Belt working in a supply chain environment has to make a decision to change suppliers of critical rawmaterials for a new product upgrade. The purchasing manager is depending on the Belt's effort requiringthat the average cost of an internal critical raw material component be less than or equal to $4,200 in orderto stay within budget. Using a sample of 35 first article components, a Mean of the new product upgradeprice of $4,060, and a Standard Deviation of $98 was estimated. In order to increase the Long Term Zvalue to 4, what is the maximum long term variation in pricing the Belt can accept for his upgraded criticalraw material component?

A. $20B. $35C. $70D. $110

Correct Answer: BSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 184Sally and Sara sell flower pots at their garage sale. Sally motivates Sara mentioning that they will sell aminimum of 15 pots per day if the outside temperature exceeds 60o F. From a sample, whose population isassumed to follow a Normal Distribution, taken for 30 days at 60 degrees or more an average of 13.6 potsper day were sold with a Standard Deviation of 0.7 pots. For the sales accomplished above, what testwould validate if they met their requirements?

A. F TestB. Test for Equal VarianceC. Chi Square TestD. One-Sample t-Test

Correct Answer: DSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 185Sally and Sara sell flower pots at their garage sale. Sally motivates Sara mentioning that they will sell aminimum of 15 pots per day if the outside temperature exceeds 60o F. From a sample, whose population isassumed to follow a Normal Distribution, taken for 30 days at 60 degrees or more an average of 13.6 potsper day were sold with a Standard Deviation of 0.7 pots. The statistical Degrees of Freedom for thisexample are?

A. 1B. 29C. 30D. 31E. 2

Correct Answer: BSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 186

Page 52: Six Sigma.NewQuestions.LSSBB.v2015-07-21.by.Tracy · Six Sigma LSSBB Questions & Answers Lean Six Sigma Black Belt Exam Version: 4.1 Six Sigma LSSBB Exam. Exam A QUESTION 1 A _____

Sally and Sara sell flower pots at their garage sale. Sally motivates Sara mentioning that they will sell aminimum of 22 pots per day if the outside temperature exceeds 60o F. From a sample, whose population isassumed to follow a Normal Distribution, taken for 30 days at 60 degrees or more an average of 18.2 potsper day were sold with a Standard Deviation of 0.9 pots. What is the Z value for this sales process?

A. 1.23B. 1.62C. 2.11D. 4.22

Correct Answer: DSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 187The relationship between a response variable and one or more independent variables is investigated andmodeled by use of which of these?

A. X-Y MatrixB. Baldridge AssessmentC. Critical X's DefinitionD. Analysis of Variance (ANOVA)

Correct Answer: DSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 188An ANOVA used across many dependent variables could increase the Beta risk.

A. TrueB. False

Correct Answer: BSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 189A Non-parametric Test should be used if just one distribution is not Normal out of the two or moregathered.

A. TrueB. False

Correct Answer: ASection: (none)Explanation

Explanation/Reference:

Page 53: Six Sigma.NewQuestions.LSSBB.v2015-07-21.by.Tracy · Six Sigma LSSBB Questions & Answers Lean Six Sigma Black Belt Exam Version: 4.1 Six Sigma LSSBB Exam. Exam A QUESTION 1 A _____

QUESTION 190The Mann-Whitney test is a powerful test and is unique to situations from which of the choices listed?(Note: There are 2 correct answers).

A. Testing the identity of two populationsB. Focuses on equality of the Median of the two populationsC. Less powerful than the traditional "t-test"D. More widely applicable than the traditional "t-test"

Correct Answer: BDSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 191Assessing process proportion as opposed to evaluating a process with respect to a set target can be doneusing one or more of these. (Note: There are 2 correct answers).

A. Process proportion equals some desired valueB. Process proportion equals some value rangeC. Target is currentD. When we deal with Attribute type dataE. Proportion of the tail is equal

Correct Answer: ADSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 192Following process modifications, the Null Hypothesis states that no improvement to the process hasoccurred. If we discover the Null Hypothesis Test was rejected when it was false that would be a(n)_______________.

A. Type I ErrorB. Type II ErrorC. Type III ErrorD. Alpha Error

Correct Answer: BSection: (none)Explanation

Explanation/Reference:

http://www.gratisexam.com/

QUESTION 193If the results from a Hypothesis Test are located in the "Region of Doubt" area, what can be concluded?

Page 54: Six Sigma.NewQuestions.LSSBB.v2015-07-21.by.Tracy · Six Sigma LSSBB Questions & Answers Lean Six Sigma Black Belt Exam Version: 4.1 Six Sigma LSSBB Exam. Exam A QUESTION 1 A _____

A. Rejection of the AlphaB. We fail to reject the Null HypothesisC. The test was conducted improperlyD. We reject the Null Hypothesis

Correct Answer: DSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 194When conducting a Hypothesis Test using Continuous Data the proper sample size is influenced only bythe extent to which we need to assess a Difference to be detected but not the inherent variation in theprocess.

A. TrueB. False

Correct Answer: BSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 195Statistical Difference is the magnitude of difference or change required to distinguish between a truedifference, brought about by change or improvement, and one that could have occurred by chance.

A. TrueB. False

Correct Answer: ASection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 196To be an effective Lean Six Sigma practitioner one must understand the difference between___________________________.

A. ANOVA and the Analysis of VarianceB. Nonparametric tests and tests of Non-normal DataC. Practical and Statistical significanceD. F-test and test of variances of 2 samples

Correct Answer: CSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 197The validity of the decision made with Hypothesis Testing is dependent upon all of the following except______________________.

Page 55: Six Sigma.NewQuestions.LSSBB.v2015-07-21.by.Tracy · Six Sigma LSSBB Questions & Answers Lean Six Sigma Black Belt Exam Version: 4.1 Six Sigma LSSBB Exam. Exam A QUESTION 1 A _____

A. Beta riskB. Range of dataC. Alpha riskD. Sample size

Correct Answer: BSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 198To establish a sample size that will allow the proper overlap of distributions we do which of these?

A. Multiply Alpha by 1.75B. Calculate one minus BetaC. Calculate Beta plus 2D. Multiply Beta by 3

Correct Answer: BSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 199Time is always the metric on the horizontal scale of a(n) ___________ Chart.

A. ParetoB. XbarC. Multi-VariD. NP

Correct Answer: CSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 200On a _________________ one can see a pattern from the graphed points such that conclusions can bedrawn about the largest family of Variation.

A. Multi-Vari ChartB. Weighted ScaleC. X-Y MatrixD. Poisson Chart

Correct Answer: ASection: (none)Explanation

Explanation/Reference:Explanation:

Page 56: Six Sigma.NewQuestions.LSSBB.v2015-07-21.by.Tracy · Six Sigma LSSBB Questions & Answers Lean Six Sigma Black Belt Exam Version: 4.1 Six Sigma LSSBB Exam. Exam A QUESTION 1 A _____

QUESTION 201For a batch manufacturing process, while assessing short term process variation, which variation category(ies) should one need to focus on? (Note: There are 2 correct answers).

A. Variation within consecutive piecesB. Variation among consecutive batchesC. Variation among groups of piecesD. Variation among the completed product

Correct Answer: ABSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 202When the Inputs, X's, for your process are Normally Distributed about the Mean, the Outputs, Y's, will beNormally Distributed.

A. TrueB. False

Correct Answer: BSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 203Some of the sources for different types of error that can be quantified using Statistical Analysis are which ofthese?

A. Error in samplingB. Bias in samplingC. Error in measurementD. All of the above

Correct Answer: DSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 204For a Normal Distribution as samples size increases the Range in Mean and Standard Deviation decreaserelative to the Mean and Standard Deviation of the population.

A. TrueB. False

Correct Answer: ASection: (none)Explanation

Explanation/Reference:Explanation:

Page 57: Six Sigma.NewQuestions.LSSBB.v2015-07-21.by.Tracy · Six Sigma LSSBB Questions & Answers Lean Six Sigma Black Belt Exam Version: 4.1 Six Sigma LSSBB Exam. Exam A QUESTION 1 A _____

QUESTION 205From this list select the best example of Bias in Sampling.

A. Testing the completeness of cooking a cake but the testers cannot agree on how to measure internaltemperature

B. Testing the sharpness of a razor blade while the sample of 500 are from the same model razorC. Testing the weight of participants at a wrestling event and only measuring those who finished second or

betterD. Testing a hand-held GPS models for durability using samples only from Nokia Model P120

Correct Answer: CSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 206The Central Limit Theorem says that as the sample size becomes large the sample Mean distribution willform a Normal Distribution, ____________________.

A. If the Measurement System is properly calibratedB. When the data is collected accuratelyC. If the shape is evenly spreadD. No matter what the shape of the population distribution of individuals

Correct Answer: DSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 207A statistical test or Hypothesis Test is performed to reject or fail to reject a stated hypothesis and itconverts the Practical Problem into a Statistical Problem.

A. TrueB. False

Correct Answer: ASection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 208An operator is measuring the distance between two points. Which is most likely to be influenced by theoperator?

A. Precision of the measurementB. Accuracy of the measurementC. Calibration of the instrumentD. All of these answers are correct

Correct Answer: DSection: (none)Explanation

Page 58: Six Sigma.NewQuestions.LSSBB.v2015-07-21.by.Tracy · Six Sigma LSSBB Questions & Answers Lean Six Sigma Black Belt Exam Version: 4.1 Six Sigma LSSBB Exam. Exam A QUESTION 1 A _____

Explanation/Reference:Explanation:

QUESTION 209Accuracy can be assessed in several ways and a fairly accurate means of measurement is visualcomparison.

A. TrueB. False

Correct Answer: BSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 210With Measurement System Analysis we are concerned with two issues that impact the potential variabilityof the data. They are _____________________.

A. Precision and AccuracyB. Reliability and RepeatabilityC. Error and SpreadD. Sensitivity and Deflection

Correct Answer: ASection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 211Measurement __________ is defined as the difference between the observed and the expected values fora given set of data.

A. BiasB. LinearityC. RangeD. Breadth

Correct Answer: ASection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 212A ___________ problem in the Measurement System suggests that there is a lack of consistency in themeasurement over time.

A. LinearityB. BiasC. StabilityD. Magnitude

Correct Answer: CSection: (none)

Page 59: Six Sigma.NewQuestions.LSSBB.v2015-07-21.by.Tracy · Six Sigma LSSBB Questions & Answers Lean Six Sigma Black Belt Exam Version: 4.1 Six Sigma LSSBB Exam. Exam A QUESTION 1 A _____

Explanation

Explanation/Reference:Explanation:

QUESTION 213In a good Measurement System the most variation will be with part-to-part measurements. What shouldyou do if the majority of variation is associated with the Gage R&R assuming the gage is technicallycapable?

A. Focus on fixing the Repeatability and Reproducibility of the measurement deviceB. Purchase a new machineC. Focus on trimming the Part-to-Part variationD. Run another MSA test with the machine

Correct Answer: ASection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 214An operator checks that all boxes being packed contain enough products to fill the box. However, each boxgetting filled has a different number of products in it. This is a Reproducibility problem, not a Repeatabilityproblem.

A. TrueB. False

Correct Answer: BSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 215Appropriate measures means that measurements are ______________.

A. RepresentativeB. SufficientC. ContextualD. RelevantE. All of these answers are correct

Correct Answer: ESection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 216What aspects of Measurement Systems Analysis (MSA) studies are applicable when the process used tomeasure does not damage the part?

A. Destructive variable gage R&R and Crossed StudyB. Destructive variable gage R&R and Nested StudyC. Nondestructive variable gage R&R and Crossed Study

Page 60: Six Sigma.NewQuestions.LSSBB.v2015-07-21.by.Tracy · Six Sigma LSSBB Questions & Answers Lean Six Sigma Black Belt Exam Version: 4.1 Six Sigma LSSBB Exam. Exam A QUESTION 1 A _____

D. Nondestructive variable gage R&R and Nested Study

Correct Answer: DSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 217Which item(s) listed would impact the Process Capability for a process with a continuous output? (Note:There are 4 correct answers).

A. Shape of process data distribution (e.g. Normal Distribution)B. Process TechnologyC. Process Standard DeviationD. Presence of Special Causes or solely Common CausesE. Seasonal variation in process

Correct Answer: ACDESection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 218The reported Cpk for a process with an average of 98 units, a spread of 16 units and upper and lowerspecification limits of 115 and 90 units would be?

A. 0.5B. 0.75C. 1.00D. 1.25

Correct Answer: CSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 219For Attribute Data, Process Capability is defined as the average proportion of nonconforming products.

A. TrueB. False

Correct Answer: ASection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 220When we compare short-term and long-term Capability which of these is true?

A. Cp is better for the short termB. Both short-term and long-term performance are alike

Page 61: Six Sigma.NewQuestions.LSSBB.v2015-07-21.by.Tracy · Six Sigma LSSBB Questions & Answers Lean Six Sigma Black Belt Exam Version: 4.1 Six Sigma LSSBB Exam. Exam A QUESTION 1 A _____

C. Performance tends to improve over timeD. Cp is better for the long-term

Correct Answer: ASection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 221What is the Ppk of a process with a spread of 24 units, an average of 68, an upper limit of 82 and a lowerlimit of 54?

A. 1.68B. 2.00C. 4.00D. 4.42

Correct Answer: CSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 222The Greek letter "sigma" is used by mathematicians to signify _____________.

A. Curve WidthB. Numerical AverageC. Standard DeviationD. Data Spread

Correct Answer: CSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 223Much of the Six Sigma methodology is used to identify and remove causes for _____________ .

A. Process VariationB. Material CostsC. Excess InventoryD. Lost Sales

Correct Answer: ASection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 224When variation is removed from the output of a process then the process customer can have moreconfidence in the experience that results from the process.

Page 62: Six Sigma.NewQuestions.LSSBB.v2015-07-21.by.Tracy · Six Sigma LSSBB Questions & Answers Lean Six Sigma Black Belt Exam Version: 4.1 Six Sigma LSSBB Exam. Exam A QUESTION 1 A _____

A. TrueB. False

Correct Answer: ASection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 225The distance between the Mean of a data set and the Point of Inflection on a Normal curve is called the_______________.

A. Curve SpreadB. Standard DeviationC. Numerical AverageD. Data Breadth

Correct Answer: BSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 226One of the foundations of Lean Six Sigma is the concept that the output of a process (Y) is influenced bythe process inputs (X's) and is commonly shown as which formula?

A. Y = Z(X2)B. Y = f(X3)C. Y = f(Xn)D. Y = g(X+ 1.5)

Correct Answer: CSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 227Those people who have a interest in the outputs of a process are known as _____________________.

A. StakeholdersB. Senior managementC. Co-workersD. Process owners

Correct Answer: ASection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 228A Process Map is created in order that a Belt can __________________.

Page 63: Six Sigma.NewQuestions.LSSBB.v2015-07-21.by.Tracy · Six Sigma LSSBB Questions & Answers Lean Six Sigma Black Belt Exam Version: 4.1 Six Sigma LSSBB Exam. Exam A QUESTION 1 A _____

A. Follow the product to the endB. Get the line people's names correctC. Capture all the activities comprising the processD. Manage the input inventory delivery schedule

Correct Answer: CSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 229Customers make their decisions based on Features, Integrity (of the seller) Delivery and ___________?

A. ColorB. ExpenseC. SeasonD. None

Correct Answer: BSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 230Sally bought a blender from her local appliance store. When she changed blades the blender would notfunction. For the manufacturer this would be categorized as what type of cost?

A. Internal Failure CostsB. External Failure CostsC. Prevention CostsD. Appraisal Costs

Correct Answer: BSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 231Cost of Poor Quality (COPQ) can be classified as Visible Costs and Hidden Costs. Which of these items isa Visible Cost?

A. Lost Customer LoyaltyB. Time Value of MoneyC. ReturnsD. Late Delivery

Correct Answer: CSection: (none)Explanation

Explanation/Reference:Explanation:

Page 64: Six Sigma.NewQuestions.LSSBB.v2015-07-21.by.Tracy · Six Sigma LSSBB Questions & Answers Lean Six Sigma Black Belt Exam Version: 4.1 Six Sigma LSSBB Exam. Exam A QUESTION 1 A _____

QUESTION 232A Belt has determined that the inventory of repair parts at a rework station can be reduced by 45%.According to Cost of Poor Quality (COPQ) definitions inventory reduction would be considered_______________.

A. Soft SavingsB. COPQ efficiencyC. Median SavingsD. Hard Savings

Correct Answer: DSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 233When one speaks of 20% of something contributing 80% of the affect they are referring to what is knownas the _________________.

A. Shewhart ExampleB. Connection PrincipleC. Balance EquationD. Pareto Principle

Correct Answer: DSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 234Using this data calculate the percentage of DPU.

Data: 763 defects, 18,000 units.

A. 2.12B. 3.42C. 4.24D. 5.72

Correct Answer: CSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 235Calculate the Rolled Throughput Yield of this process using this data.

Data: unit input: 1215, unit output: 1180, defects repaired: 184, scrap: 42

A. 80.85%B. 81.40%C. 82.23%D. 84.96%

Page 65: Six Sigma.NewQuestions.LSSBB.v2015-07-21.by.Tracy · Six Sigma LSSBB Questions & Answers Lean Six Sigma Black Belt Exam Version: 4.1 Six Sigma LSSBB Exam. Exam A QUESTION 1 A _____

Correct Answer: BSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 236"A calculated time frame that matches customer demand" is a definition of what Lean Principles term?

A. Value StreamB. Kaizen eventC. Takt timeD. Kanban

Correct Answer: CSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 237Which of these are examples of business metrics or Key Performance Indicators commonly referred to asKPI's?

A. Cycle TimeB. DefectsC. No. of Units ReworkedD. Labor HoursE. All of these answers are correct

Correct Answer: ESection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 238As a means of measuring the effects on other areas of a process as a result of changes in the primarymetric we also define and track ________________.

A. Parallel process metricsB. Secondary metricsC. Tertiary metricsD. Industry standards

Correct Answer: BSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 239What dollar amount of savings would a project show if it reduced your outstanding Accounts Receivable by$0.9 million dollars to $3.5 million total and your organization's marginal cost of capital was 5.7%?

Page 66: Six Sigma.NewQuestions.LSSBB.v2015-07-21.by.Tracy · Six Sigma LSSBB Questions & Answers Lean Six Sigma Black Belt Exam Version: 4.1 Six Sigma LSSBB Exam. Exam A QUESTION 1 A _____

A. $49,250B. $51,300C. $117,500D. $202,424

Correct Answer: BSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 240Handling of warranty returns, process improvement team meetings and rework to meet customerexpectations are all examples of business costs that are classified as ___________ .

A. NuisanceB. Non-value AddC. NecessaryD. Unavoidable

Correct Answer: BSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 241The Japanese born function of a Kaizen event utilizes a specific, step-by-step approach meant to bringabout major changes to a process.

A. TrueB. False

Correct Answer: ASection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 242The primary objective in removal of waste is to improve the Order Production Cycle where the time from_________________ to the time of receipt of payment is compressed.

A. Shift startB. Product developmentC. Receipt of an orderD. New fiscal year

Correct Answer: CSection: (none)Explanation

Explanation/Reference:Explanation:

Page 67: Six Sigma.NewQuestions.LSSBB.v2015-07-21.by.Tracy · Six Sigma LSSBB Questions & Answers Lean Six Sigma Black Belt Exam Version: 4.1 Six Sigma LSSBB Exam. Exam A QUESTION 1 A _____

http://www.gratisexam.com/