Six Month Report 2015 - Skanska · Infrastructure Development − Project portfolio’s net present...

34
Stockholm Bypass Tunnel, Kungens Kurva, Sweden Six Month Report 2015

Transcript of Six Month Report 2015 - Skanska · Infrastructure Development − Project portfolio’s net present...

Page 1: Six Month Report 2015 - Skanska · Infrastructure Development − Project portfolio’s net present value increased SEK 0.6 bn to SEK 5.9 bn year-to-date − Preferred bidder for

Stockholm Bypass Tunnel, Kungens Kurva, Sweden

Six Month Report 2015

Page 2: Six Month Report 2015 - Skanska · Infrastructure Development − Project portfolio’s net present value increased SEK 0.6 bn to SEK 5.9 bn year-to-date − Preferred bidder for

Six Month Report 2015

− Solid group results − Increased revenues − Improved profitability − Solid financial position

− Operating income SEK 2.5 bn (1.6) − 49% increase in local currency

− EPS SEK 4.22 (2.64)

− ROCE PD 15.3% (9.6)

− Continued positive market outlook

− Divestment of O&M in Argentina

2 July 23, 2015 Skanska Six Month Report 2015

Page 3: Six Month Report 2015 - Skanska · Infrastructure Development − Project portfolio’s net present value increased SEK 0.6 bn to SEK 5.9 bn year-to-date − Preferred bidder for

Tampa International Airport, Florida, U.S.

Construction

− Revenue SEK 66.9 bn (56.3)

− Order bookings SEK 58.3 bn (68.0) − Sweden and UK strong − Book-to-build, R-12: 99% − Cancellation in USA Building

− Operating income SEK 1.7 bn (1.7) − Solid performance in Sweden,

Finland, Poland and Czech Republic

− Write-down in one project in the U.S.

3 July 23, 2015 Skanska Six Month Report 2015

Page 4: Six Month Report 2015 - Skanska · Infrastructure Development − Project portfolio’s net present value increased SEK 0.6 bn to SEK 5.9 bn year-to-date − Preferred bidder for

BoKlok Lärlingen, Visby, Sweden

Residential Development

− Revenue SEK 6.6 bn (4.5) − 2,157 (1,540) homes sold − 1,876 (1,308) homes started

− Operating income SEK 631 M (349) − Good performance in Sweden and

Central Europe − Norway mixed

− Continued improved profitability − Operating margin 9.5% (7.8) − ROCE 10.7% (6.8)

4 July 23, 2015 Skanska Six Month Report 2015

Page 5: Six Month Report 2015 - Skanska · Infrastructure Development − Project portfolio’s net present value increased SEK 0.6 bn to SEK 5.9 bn year-to-date − Preferred bidder for

Queen Square, Bristol, UK

Commercial Property Development

− Divestments of SEK 2.4 bn (2.3)

− Gain from divestments SEK 856 M (408)

− 44 ongoing projects − SEK 15.6 bn in investment value − 52% pre-leasing rate − 54% completion rate − 7 project starts

− 166,000 sq m leased

5 July 23, 2015 Skanska Six Month Report 2015

Page 6: Six Month Report 2015 - Skanska · Infrastructure Development − Project portfolio’s net present value increased SEK 0.6 bn to SEK 5.9 bn year-to-date − Preferred bidder for

New Karolinska Solna, Stockholm, Sweden

Infrastructure Development

− Project portfolio’s net present value increased SEK 0.6 bn to SEK 5.9 bn year-to-date

− Preferred bidder for LaGuardia Airport

− Payments from project companies SEK 0.1 bn

6 July 23, 2015 Skanska Six Month Report 2015

Page 7: Six Month Report 2015 - Skanska · Infrastructure Development − Project portfolio’s net present value increased SEK 0.6 bn to SEK 5.9 bn year-to-date − Preferred bidder for

Malmö Live, Sweden

Power plant, U.S. 2,100

Bypass tunnel, Sweden 1,300

ESS, R&D facility, Sweden 1,200

Highway, Czech Republic 920

Boeing, paint facility, U.S. 730

Hospital, U.S. 510

Total bookings in Q2 28,058

7

New orders in Construction in Q2

7 July 23, 2015 Skanska Six Month Report 2015

SEK M

Page 8: Six Month Report 2015 - Skanska · Infrastructure Development − Project portfolio’s net present value increased SEK 0.6 bn to SEK 5.9 bn year-to-date − Preferred bidder for

Construction Order situation

8

0

50

100

150

200

Q3 Q4 Q12011

Q2 Q3 Q4 Q12012

Q2 Q3 Q4 Q12013

Q2 Q3 Q4 Q12014

Q2 Q3 Q4 Q12015

Q2

SEK bn

Order backlog

Order bookings,R-12Revenue,R-12Order bookingsper quarter

July 23, 2015 Skanska Six Month Report 2015

SEK bn

Jan–Jun 2015

Jan–Jun 2014

Jan–Dec 2014

Revenue 66.9 56.3 128.7 Order bookings 58.3 68.0 146.9 Order backlog 168.8 151.2 170.5 Latin American operations excluded from 1/1 2013

R-12 Book- to-build 99%

Page 9: Six Month Report 2015 - Skanska · Infrastructure Development − Project portfolio’s net present value increased SEK 0.6 bn to SEK 5.9 bn year-to-date − Preferred bidder for

Construction Order bookings

SEK bn

Jan–Jun 2015

Jan–Jun 2014

Book- to-build, R-12, %

Months of production

Sweden 16.2 13.4 114 12 Norway 5.5 8.4 82 8 Finland 3.2 3.7 85 11 Poland 4.1 5.1 86 8 Czech Republic 3.1 2.3 104 12 UK 13.8 9.4 141 24 USA Building 5.5 17.5 63 12 USA Civil 6.8 8.2 124 25 Total 58.3 68.0 99 15

9 July 23, 2015 Skanska Six Month Report 2015

Page 10: Six Month Report 2015 - Skanska · Infrastructure Development − Project portfolio’s net present value increased SEK 0.6 bn to SEK 5.9 bn year-to-date − Preferred bidder for

0

25

50

75

100

125

150

2.0

2.5

3.0

3.5

4.0

4.5

5.0

Q3 Q4 Q12011

Q2 Q3 Q4 Q12012

Q2 Q3 Q4 Q12013

Q2 Q3 Q4 Q12014

Q2 Q3 Q4 Q12015

Q2

Construction Income statement

10

Revenue

Operating margin

Revenue, R-12, SEK bn

July 23, 2015 Skanska Six Month Report 2015

SEK bn Jan–Jun

2015 Jan–Jun

2014 Jan–Dec

2014 Revenue 66.9 56.3 128.7 Gross income 4.8 4.5 10.3 Selling and administrative expenses -3.1 -2.8 -5.8 Operating income 1.7 1.7 4.5 Gross margin, % 7.1 7.9 8.0 Selling and administrative expenses, % -4.6 -5.0 -4.5 Operating margin, % 2.5 3.0 3.5

Operating margin, R-12, %

Latin American operations excluded from 1/1 2013

Page 11: Six Month Report 2015 - Skanska · Infrastructure Development − Project portfolio’s net present value increased SEK 0.6 bn to SEK 5.9 bn year-to-date − Preferred bidder for

Construction Income statement

11

Operating income, SEK M Operating margin, % Jan–Jun

2015 Jan–Jun

2014 Jan–Jun

2015 Jan–Jun

2014

Sweden 538 500 3.7 3.6

Norway 182 171 2.8 2.7 Finland 95 109 3.3 3.5 Poland 94 92 3.0 3.0 Czech Republic 17 -11 0.8 neg UK 205 217 2.4 3.1 USA Building 101 148 0.5 1.1 USA Civil 455 448 4.4 6.2 Total 1,687 1,674 2.5 3.0

July 23, 2015 Skanska Six Month Report 2015

Page 12: Six Month Report 2015 - Skanska · Infrastructure Development − Project portfolio’s net present value increased SEK 0.6 bn to SEK 5.9 bn year-to-date − Preferred bidder for

024681012

-15-10-505

1015

Q3 Q4 Q12011

Q2 Q3 Q4 Q12012

Q2 Q3 Q4 Q12013

Q2 Q3 Q4 Q12014

Q2 Q3 Q4 Q12015

Q2

Revenue

Operating margin

Operating margin, R-12, %

Residential Development Income statement, segment reporting

12 July 23, 2015 Skanska Six Month Report 2015

Revenue, R-12, SEK bn

SEK M

Jan–Jun 2015

Jan–Jun 2014

Jan–Dec 2014

Revenue 6,642 4,469 9,558 Gross income 937 609 1,204 Selling and administrative expenses -306 -262 -521 Income from joint ventures 0 2 0 Operating income 631 349 683 Gross margin, % 14.1 13.6 12.6 Selling and administrative expenses, % -4.6 -5.9 -5.5 Operating margin, % 9.5 7.8 7.1

Page 13: Six Month Report 2015 - Skanska · Infrastructure Development − Project portfolio’s net present value increased SEK 0.6 bn to SEK 5.9 bn year-to-date − Preferred bidder for

Residential Development Income statement

13

Operating income, SEK M1 Operating margin, %1

Jan–Jun 2015

Jan–Jun 2014

Jan–Jun 2015

Jan–Jun 2014

Sweden 441 204 11.0 8.9 Norway 82 53 7.1 10.1 Finland 70 64 6.2 6.9 Nordics 593 321 9.4 8.6 Central Europe2 38 28 11.3 3.9 Total 631 349 9.5 7.8

1 Development gain only, construction margin reported under Construction 2 Czech Republic, Poland and the UK

July 23, 2015 Skanska Six Month Report 2015

Page 14: Six Month Report 2015 - Skanska · Infrastructure Development − Project portfolio’s net present value increased SEK 0.6 bn to SEK 5.9 bn year-to-date − Preferred bidder for

0

1,000

2,000

3,000

4,000

5,000

Q3 Q4 Q12011

Q2 Q3 Q4 Q12012

Q2 Q3 Q4 Q12013

Q2 Q3 Q4 Q12014

Q2 Q3 Q4 Q12015

Q2

Homes

Residential Development Homes started and sold, R-12

14

Sold

Started

July 23, 2015 Skanska Six Month Report 2015

Homes started Homes sold Jan–Jun

2015 Jan–Jun

2014 Jan–Dec

2014 Jan–Jun

2015 Jan–Jun

2014 Jan–Dec

2014

1,876 1,308 2,846 2,157 1,540 3,274

Page 15: Six Month Report 2015 - Skanska · Infrastructure Development − Project portfolio’s net present value increased SEK 0.6 bn to SEK 5.9 bn year-to-date − Preferred bidder for

Residential Development Homes in production

July 23, 2015 Skanska Six Month Report 2015 15

0

1,000

2,000

3,000

4,000

5,000

6,000

7,000

Q3 Q4 Q12011

Q2 Q3 Q4 Q12012

Q2 Q3 Q4 Q12013

Q2 Q3 Q4 Q12014

Q2 Q3 Q4 Q12015

Q2

Homes

Unsoldcompleted

Unsold underconstruction

Sold underconstruction

Homes in production Of which sold, % Unsold

completed homes Jun 30, 2015 Jun 30, 2014 Jun 30, 2015 Jun 30, 2014 Jun 30, 2015 Jun 30, 2014

4,896 4,768 78 70 358 492

Page 16: Six Month Report 2015 - Skanska · Infrastructure Development − Project portfolio’s net present value increased SEK 0.6 bn to SEK 5.9 bn year-to-date − Preferred bidder for

Commercial Property Development Income statement, segment reporting

16

SEK M

Jan–Jun 2015

Jan–Jun 2014

Jan–Dec 2014

Revenue 2,659 2,585 10,228 Gross income 877 556 2,191 Selling and administrative expenses -316 -249 -526 Income from joint ventures and associated companies 6 5 35

Operating income 567 312 1,700 of which gain from divestments of properties1 856 408 1,989 of which write downs/reversal of write downs -50 -11 43

1 Additional gain included in eliminations 48 31 279

Development gain only, construction margin reported under Construction

July 23, 2015 Skanska Six Month Report 2015

Page 17: Six Month Report 2015 - Skanska · Infrastructure Development − Project portfolio’s net present value increased SEK 0.6 bn to SEK 5.9 bn year-to-date − Preferred bidder for

0

2

4

6

8

10

Q3 Q4 Q12011

Q2 Q3 Q4 Q12012

Q2 Q3 Q4 Q12013

Q2 Q3 Q4 Q12014

Q2 Q3 Q4 Q12015

Q2

Revenue fromdivestments,R-12

Operatingincome fromdivestments,R-12

SEK bn

Commercial Property Development Divestments

Sale of commercial properties

SEK M Sales price Capital gain

Year-to-date 2,429 856

17 July 23, 2015 Skanska Six Month Report 2015

Page 18: Six Month Report 2015 - Skanska · Infrastructure Development − Project portfolio’s net present value increased SEK 0.6 bn to SEK 5.9 bn year-to-date − Preferred bidder for

0

4,000

8,000

12,000

16,000

20,000

2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 Jun 30,2015

SEK M

Commercial Property Development Ongoing projects

18 July 23, 2015 Skanska Six Month Report 2015

Ongoing projects, total investment value upon completion

Investment value ongoing projects SEK bn

End of period

Upon completion

Market value

Occupancy rate, %

Degree of completion,

%

Wholly owned projects 8.0 14.4 18.5 55 54

Skanska’s share of projects in JV 0.7 1.3 1.7 18 52

of which equity investment 0.3 0.4

Total investment value 8.7 15.6 20.2 of which carrying amount 8.3 14.7

Page 19: Six Month Report 2015 - Skanska · Infrastructure Development − Project portfolio’s net present value increased SEK 0.6 bn to SEK 5.9 bn year-to-date − Preferred bidder for

Commercial Property Development Distribution of project portfolio

July 23, 2015 Skanska Six Month Report 2015 19

SEK bn Investment value upon completion Market value Ongoing projects 15.6 20.2 Ongoing projects end of period 8.7 Completed projects 3.3 4.2 Undeveloped land and development properties 6.1 6.4 Total 25.0 30.8

of which carrying amount 24.1

4.6 0.9

0.3 5.8

0

5

10

15

20

25

30

35

Ongoing projects Completed projects Undeveloped land anddevelopment properties

Total

Investment value end of period Additional investment value until completion Surplus value at completion

SEK bn

Page 20: Six Month Report 2015 - Skanska · Infrastructure Development − Project portfolio’s net present value increased SEK 0.6 bn to SEK 5.9 bn year-to-date − Preferred bidder for

0

50

100

150

200

250

300

350

400

Q3 Q4 Q12011

Q2 Q3 Q4 Q12012

Q2 Q3 Q4 Q12013

Q2 Q3 Q4 Q12014

Q2 Q3 Q4 Q12015

Q2

Leasing,quarterly

Leasing,R-12

000 sq m

Commercial Property Development Leasing

20

New leases of space were signed for 116,000 sq m in Q2

July 23, 2015 Skanska Six Month Report 2015

Page 21: Six Month Report 2015 - Skanska · Infrastructure Development − Project portfolio’s net present value increased SEK 0.6 bn to SEK 5.9 bn year-to-date − Preferred bidder for

Infrastructure Development Income statement

21 July 23, 2015 Skanska Six Month Report 2015

SEK M

Jan–Jun 2015

Jan–Jun 2014

Jan–Dec 2014

Revenue 54 35 163

Gross income -60 -77 -46

Selling and administrative expenses -77 -66 -128

Income from joint ventures 389 338 637

Operating income 252 195 463 of which gains from divestments of shares in projects – – 127

Page 22: Six Month Report 2015 - Skanska · Infrastructure Development − Project portfolio’s net present value increased SEK 0.6 bn to SEK 5.9 bn year-to-date − Preferred bidder for

Infrastructure Development Project portfolio

July 23, 2015 Skanska Six Month Report 2015 22

5.3 0.4 -0.1 0.3

0

1

2

3

4

5

6

7

Dec 31, 2014 Derisk/Time value

Investments/Divestments

Currency effect

Jun 30, 2015

Net present value of projects, SEK bn

5.9

SEK bn Jun 30, 2015 Jun 30, 2014 Dec 31, 2014

Present value of cash flow from projects 7.2 6.1 6.5 Net present value of projects 5.9 5.3 5.3 Carrying amount -3.6 -3.4 -3.2 Unrealized development gain 2.3 1.9 2.1 Cash flow hedge 1.7 1.3 1.8 Effect in unrealized Equity 4.0 3.2 3.9

Page 23: Six Month Report 2015 - Skanska · Infrastructure Development − Project portfolio’s net present value increased SEK 0.6 bn to SEK 5.9 bn year-to-date − Preferred bidder for

Group Income statement

23 July 23, 2015 Skanska Six Month Report 2015

1 Latin American operations included from 1/1 2013

SEK M

Jan–Jun 2015

Jan–Jun 2014

Jan–Dec 2014

Operating income from business streams 3,137 2,530 7,358 Central1 -603 -901 -1,608 Eliminations -34 -48 16 Operating income 2,500 1,581 5,766 Net financial items -244 -125 -293 Income after financial items 2,256 1,456 5,473 Taxes -519 -363 -1,365 Profit for the period 1,737 1,093 4,108

Earnings per share, SEK 4.22 2.64 9.98

Tax rate, % 23 25 25

Page 24: Six Month Report 2015 - Skanska · Infrastructure Development − Project portfolio’s net present value increased SEK 0.6 bn to SEK 5.9 bn year-to-date − Preferred bidder for

-6

-4

-2

0

2

4

6

8

Q3 Q4 Q12011

Q2 Q3 Q4 Q12012

Q2 Q3 Q4 Q12013

Q2 Q3 Q4 Q12014

Q2 Q3 Q4 Q12015

Q2

SEK bn

Cash flowfrombusinessoperations,quarterly

R-12

Group Cash flow

24 July 23, 2015 Skanska Six Month Report 2015

SEK bn

Jan–Jun 2015

Jan–Jun 2014

Jan–Dec 2014

Cash flow from operations -2.2 -2.8 3.7 Net strategic investments 0.0 0.1 0.1 Dividend etc. -3.0 -2.7 -2.9 Cash flow before change in interest-bearing receivables and liabilities -5.2 -5.5 0.9

Page 25: Six Month Report 2015 - Skanska · Infrastructure Development − Project portfolio’s net present value increased SEK 0.6 bn to SEK 5.9 bn year-to-date − Preferred bidder for

0

2

4

6

8

10

12

14

16

18

0

5

10

15

20

25

Q3 Q4 Q12011

Q2 Q3 Q4 Q12012

Q2 Q3 Q4 Q12013

Q2 Q3 Q4 Q12014

Q2 Q3 Q4 Q12015

Q2

% SEK bn

Free workingcapital, SEK bn

Average freeworking capital/Constructionrevenue, R-12, %

Free working capital, end of Q2, SEK bn

Construction Free working capital

25 July 23, 2015 Skanska Six Month Report 2015

Latin American operations excluded from 1/1 2013

Page 26: Six Month Report 2015 - Skanska · Infrastructure Development − Project portfolio’s net present value increased SEK 0.6 bn to SEK 5.9 bn year-to-date − Preferred bidder for

02468

101214

Q3 Q4 Q12011

Q2 Q3 Q4 Q12012

Q2 Q3 Q4 Q12013

Q2 Q3 Q4 Q12014

Q2 Q3 Q4 Q12015

Q2

Operating net financial assets/liabilities, SEK bn

Group Financial position

26 July 23, 2015 Skanska Six Month Report 2015

SEK bn

Jun 30 2015

Jun 30 2014

Dec 31 2014

Total assets 93.9 86.6 92.8 Equity attributable to equity holders 21.1 19.3 21.4 Interest-bearing net receivables (+)/net debt (-) -3.9 -5.3 0.7 Operating net financial assets/liabilities 2.8 0.8 8.4 Capital employed, closing balance 36.3 34.9 36.8 Equity/assets ratio, % 22.4 22.4 23.1

Page 27: Six Month Report 2015 - Skanska · Infrastructure Development − Project portfolio’s net present value increased SEK 0.6 bn to SEK 5.9 bn year-to-date − Preferred bidder for

Group Change in financial position

27 July 23, 2015 Skanska Six Month Report 2015

SEK bn Jan–Jun

2015 Jan–Jun

2014 Jan–Dec

2014 Opening balance interest-bearing net receivables 0.7 1.0 1.0 Cash flow before change in interest-bearing receivables and liabilities -5.2 -5.5 0.9 Change in pension liability 0.2 -0.8 -2.0 Other changes 0.4 0.1 0.8 Change in interest-bearing net receivables -4.6 -6.2 -0.3 Closing balance interest-bearing net receivables/net debt -3.9 -5.3 0.7 Pension liability, net 4.1 3.2 4.4 Interest-bearing debt co-ops 2.7 2.9 3.2 Operating net financial assets/liabilities 2.8 0.8 8.4

Page 28: Six Month Report 2015 - Skanska · Infrastructure Development − Project portfolio’s net present value increased SEK 0.6 bn to SEK 5.9 bn year-to-date − Preferred bidder for

Group Change in equity

28 July 23, 2015 Skanska Six Month Report 2015

SEK bn Jan–Jun

2015 Jan–Jun

2014 Jan–Dec

2014

Opening balance 21.4 21.4 21.4 Dividend to shareholders -2.8 -2.6 -2.6 Other changes in equity not included in total comprehensive income for the year -0.1 -0.1 -0.1 Profit for the period 1.7 1.2 3.9

Other comprehensive income Translation differences 0.4 0.4 1.5 Effects of remeasurements of pensions 0.2 -0.8 -1.8 Effects of cash flow hedges 0.3 -0.2 -0.8 Closing balance 21.1 19.3 21.4

Page 29: Six Month Report 2015 - Skanska · Infrastructure Development − Project portfolio’s net present value increased SEK 0.6 bn to SEK 5.9 bn year-to-date − Preferred bidder for

Group Investments and capital employed

29 July 23, 2015 Skanska Six Month Report 2015

-8-6-4-202468

10

Q3 Q4 Q12011

Q2 Q3 Q4 Q12012

Q2 Q3 Q4 Q12013

Q2 Q3 Q4 Q12014

Q2 Q3 Q4 Q12015

Q2

SEK bn

Investments,quarterly

Divestments,quarterly

Net investments,R-12

SEK bn Jan–Jun

2015 Jan–Jun

2014 Jan–Dec

2014 Capital employed in: Residential Development 8.5 11.1 10.4 Commercial Property Development 17.2 13.9 15.0 Infrastructure Development 2.1 2.1 1.9 Total in Development Streams 27.8 27.1 27.3

Page 30: Six Month Report 2015 - Skanska · Infrastructure Development − Project portfolio’s net present value increased SEK 0.6 bn to SEK 5.9 bn year-to-date − Preferred bidder for

Świnna Poręba reservoir, Kraków, Poland

Market outlook Construction

30

− Overall a positive market outlook

− Nordic countries − Strong building market in Sweden,

mixed in Norway − Good civil market. Norway strong

with fierce competition, Sweden strong, Finland weak

− Other European countries − UK and Polish market strong − Czech and Slovak Republics

continues to improve

− North America − The U.S. continues to be a good

market, but with fierce competition

July 23, 2015 Skanska Six Month Report 2015

Page 31: Six Month Report 2015 - Skanska · Infrastructure Development − Project portfolio’s net present value increased SEK 0.6 bn to SEK 5.9 bn year-to-date − Preferred bidder for

Norra Djurgårdsstaden, Stockholm, Sweden

− Nordic countries − Sweden very strong − Norway mixed − Finland weak

− Central Europe − Volumes and prices continues

to increase

Market outlook Residential Development

31 July 23, 2015 Skanska Six Month Report 2015

Page 32: Six Month Report 2015 - Skanska · Infrastructure Development − Project portfolio’s net present value increased SEK 0.6 bn to SEK 5.9 bn year-to-date − Preferred bidder for

Stockholm New, Sweden

− General − Tenants: Strong demand, vacancy

rates low − Investors: Strong demand, valuations

attractive

− Nordic countries − High interest from investors and low

vacancy rates in Sweden

− Central Europe − High demand in Poland and improving

in other parts of Central Europe

− North America − Strong investor appetite and good

tenant demand

Market outlook Commercial Property Development

32 July 23, 2015 Skanska Six Month Report 2015

CD Day September 28

Page 33: Six Month Report 2015 - Skanska · Infrastructure Development − Project portfolio’s net present value increased SEK 0.6 bn to SEK 5.9 bn year-to-date − Preferred bidder for

LaGuardia, New York, U.S.

Market outlook Infrastructure Development

33 July 23, 2015 Skanska Six Month Report 2015

− All countries − Continued improving potential

for PPPs in the U.S., but competition is considerable

− Norwegian market improving − Thin pipeline in the other

markets

Page 34: Six Month Report 2015 - Skanska · Infrastructure Development − Project portfolio’s net present value increased SEK 0.6 bn to SEK 5.9 bn year-to-date − Preferred bidder for

34 July 23, 2015 Skanska Six Month Report 2015