2

Events

50 years of CERN 29 Sep: LHC ring illumination 16 Oct: Open day at CERN: 32’000 visitors 19 Oct: Official ceremony with VIPs

CHEP Interlaken 27 Sep – 01 Oct Record-breaking attendance: more than 500 Lot of work… and lot of fun to see it all run

well

Page 3: Site report: CERN Helge Meinhard (at) cern ch HEPiX fall 2004 @ BNL.

3

Fabric Infrastructure and Operations (1)

Central Data Recording in full swing Experiment peaks of 120 MB/s, combined average 10

TB/day, 1.5 PB expected in 2004 Major problem with disk server stability

Finally whole batch, ie. 1200 disks (~20 % of our total disk count) replaced

Many stateful servers successfully quattorised (J. van Eldik)

Machine room refurbishment going on LHS of machine room now empty, all machines and

services moved to RHS and vault

Page 4: Site report: CERN Helge Meinhard (at) cern ch HEPiX fall 2004 @ BNL.

4

Page 5: Site report: CERN Helge Meinhard (at) cern ch HEPiX fall 2004 @ BNL.

5

Fabric Infrastructure and Operations (2)

New machines 400 Farm machines being installed, alleviating

pressure on batch farm Awaiting 75 disk servers (360 TB SATA, 3Ware

9500), plus 22 disk arrays (140 TB SATA, Infortrend, FC attachment)

System administration team taking over more specialised tasks and installations

Legato phased out, new machine for TSM coming

Page 6: Site report: CERN Helge Meinhard (at) cern ch HEPiX fall 2004 @ BNL.

6

Fabric Infrastructure and Operations (3)

Media migration to 9940 completed, evaluations of new tape drives coming

Purchasing for 2006…2008 becoming clearer

Lxbatch field-proving Quattor again and again (T. Kleinwort)

Preparing for LSF 6

Page 7: Site report: CERN Helge Meinhard (at) cern ch HEPiX fall 2004 @ BNL.

7

Architecture and Data Challenges (1)

Worked with FNAL on SL: SLC3 in final phase of certification Production-like systems for tests

Support from RedHat started in July OpenLab

Voltaire joined as contributing partner Project proposal on security Disk server studies: 4-way Itanium SIAB (Storage In

A Box), 2 x 3Ware 9500, 24 SATA disks: 750 MB/s read, 340 MB/s write, 350 MB/s read over 10GbE (J. Iven)

Page 8: Site report: CERN Helge Meinhard (at) cern ch HEPiX fall 2004 @ BNL.

8

Architecture and Data Challenges (2)

New Castor successfully tested in full chain

OpenAFS: High load on big servers revealed bugs CERN providing fixes to OpenAFS

Still investigating migration to krb5 Consolidated HEPiX scripts released

Page 9: Site report: CERN Helge Meinhard (at) cern ch HEPiX fall 2004 @ BNL.

9

Data Bases

Looking at Oracle 10g Strong collaboration with Oracle (2 Oracle

funded fellows in OpenLab) DataGuard (disaster recovery and scheduled

upgrades) Oracle Streams (replication)

Preparing for a high-availability Oracle cluster (RAC) running under Linux

POOL passed real test with 400 TB of data (D. Duellmann)

Page 10: Site report: CERN Helge Meinhard (at) cern ch HEPiX fall 2004 @ BNL.

10

Product Support (1)

Solaris 9 certification delayed, now targeted for end 2004 Moving target Debugging took longer than expected, as did writing NCM

components Solaris will be much more in line with Linux than before Will use software from Solaris Software Companion

Solaris security Certification machines compromised three times Awareness and requirements raised Considering Ipfilter, AV software, and automatic security

updates

Page 11: Site report: CERN Helge Meinhard (at) cern ch HEPiX fall 2004 @ BNL.

11

Product Support (2)

CVS services 100 projects, 14 GB of source code, 4 new

projects/month Some servers compromised by pserver exploit Finer control of Web-based access required

Monitoring migrating from UIMON to Lemon (M. Schröder)

Transition to new desktop support contract New contractor since 01 July

Licensing infrastructure (M. Schröder)

Page 12: Site report: CERN Helge Meinhard (at) cern ch HEPiX fall 2004 @ BNL.

12

User and Document Services

Procedure rolling for new supply contract for CERN desktops

InDiCo (conference management tool) passed field test at CHEP with highest marks

Cern Computer Newsletter changed: Dedicated pages on computing in every other issue of

CERN Courier More technical and CERN-specific info in online CNL

Page 13: Site report: CERN Helge Meinhard (at) cern ch HEPiX fall 2004 @ BNL.

13

Internet Services

Windows Terminal Server now production service (R. Gaspar)

SMS 2003 client deployed everywhere (R. Otto) > 100 new servers, Windows 2003 server Mail

Secure (SSL) services for imap, pop, smtp as an option

Accepting mail requires successful reverse DNS lookup and successful smtp connect

Listbox service renewal (R. Gaspar) Spam fighting, Exchange 2003 (R. Otto)

Page 14: Site report: CERN Helge Meinhard (at) cern ch HEPiX fall 2004 @ BNL.

14

Security

Many incidents Sasser worm, cvs breakin, Windows machines taken over by

intruders, Solaris problems, lxplus root compromised, … Lessons:

Tightening firewalls and patch handling Dual-boot machines are problematic Non-centrally managed machines are problematic

Visitors’ laptops are very non-centrally managed… Local Windows admin account forcefully secured by strong

password Viruses arrive at CERN faster than updated signatures P2P activities often the source of problems

Page 15: Site report: CERN Helge Meinhard (at) cern ch HEPiX fall 2004 @ BNL.

15

Miscellaneous

Grid Deployment moving ahead (I. Bird) 82 sites, 9000 CPUs in LCG2

ACB (Automatic Call-Back) on its way out Call-back and ‘0800’ numbers stopped in July Final switch-off end 2004

Pilot for IP telephony Beam studies for the LHC à la SETI:

LHC@home LCG service challenges (HEPiX Edinburgh) LCG MoU being prepared