Site Induction - Doval · PDF file• Clearing and Grubbing ... Sign onto the Project Risk...
Transcript of Site Induction - Doval · PDF file• Clearing and Grubbing ... Sign onto the Project Risk...
Site Induction
Mount Cotton Road Wide Centreline (WCL) Works.
1
Mount Cotton Road Wide Centreline (WCL) Works
Project: A17- 008 Mount Cotton Road Wide Centreline (WCL) Works
Contractor: Doval Constructions QLD Pty LtdClient: Department of Transport and Main RoadsProject Start Date: August 2017Original Project End Date: April 2018Revised Project End Date: N/A
All personnel on site, including labour hire and sub-contractors shall follow all lawful instructions & directions given by:Project Manager: Ben Dyson Project Engineer: Andrew De LacySite Engineer / CQR: Bruce Fock-YatSite Engineer / CQR: Richard HooperSite Supervisor: Aaron ArmstrongSite Supervisor: Coby Roles
Scope of Works
Doval Constructions is undertaking the Mount Cotton Road Wide Centreline (WCL) Works, Mount Cotton.
Project elements include;
• Traffic Management
• Road Excavation
• Construction of Road Embankment
• New Culverts Constructions and Extensions
• Construction of Road Pavements
• Cement Modified Base
• Construction of Stormwater Culverts
• Soil Nailing and Shotcreting
• Landscaping
• Clearing and Grubbing
• Bitumen Surfacing
• Asphalt Surfacing
• Line marking
3
Inductions & Pre Start
NO WORK shall be carried out, including work by sub-contractors and labour hire,
unless you have:
• Completed a Site Specific Induction and
• Sign onto the Project Risk Assessment
• Sign onto the Daily Pre Start (Risk Assessment) and
• Sign onto the relevant SWMS(s) (if applicable)
If you arrive late for the Pre Start (Risk Assessment), it is your duty to report to the
site office, to contact the Site Supervisor on his mobile and familiarise yourself with the Pre Start (Risk Assessment) located in the site office.
It is your duty to ensure the Site Supervisor explains the Project Risk Assessment and Pre Start (Risk Assessment) to you!
4
Licenses & Competencies
NO WORKER, including subcontractors and/or labour hire workers, shall commence work on-site without obtaining a General Construction Safety Induction (Blue/White Card). Proof of attainment must be provided during the induction process.
If you are operating a vehicle on site (even driving your personal vehicle), a copy of your drivers licence is required.
NO WORKER, including subcontractors and/or labour hire workers, shall operate any plant requiring a high risk work licence without the required HRW licence.
All classes of high risk work as specified in Schedule 3, pg. 594 WHS Reg. 2011 requires a high risk work licence.
5
Licenses & Competencies
Heavy machinery operates on this site which presents a hazard with
high risk such as crushing, severing limbs and death.
Plant Operators shall not commence work without completing a Daily
Plant Pre Start Compliance Checklist
• Plant operators shall ensure anti-burst are fitted, and that safety
guards, emergency devices and warning devices are in place as
specified in the Plant Operators Manual.
No Plant shall be operated without a Doval Verification of
Competency (VOC). Plant Operators shall bring the following:
• Plant Operator Logbook and/or letter from previous employee
stating date, type of plant operated and duration (hours) and
• Certificate III Plant and/or Statement of Attainment from an
Industry School and/or Competency Assessment by an RTO
against the National Training Unit RIIMP0320B (excavator) etc.6
Licenses & Competencies
NO WORKER, including subcontractors and/or labour hire workers, shall use any plant on-site unless a Plant Verification of Competency (VOC) is provided or, if you currently do not hold a VOC for the plant to be used on site, a Doval VOC must be completed and verified by the Doval Site Supervisor.
NO WORKER, including subcontractors and/or labour hire workers, shall commence work without having signed-off on the Pre Start (Risk Assessment) DC_SF_004 and SWMS (where applicable).
ALL WORKERS verify that they are qualified and hold all the relevant licences to perform their role on site
7
8
Contacts List
Project Manager: Ben Dyson 0417 569 822
Project Engineer: Andrew De Lacy 0410 598 496
Site Engineer (CQR): Bruce Fock-Yat 0466 677 825
Site Engineer (CQR): Richard Hooper 0429 532 736
Site Supervisor: Aaron Armstrong 0404 568 146
Site Supervisor: Coby Roles 0449 947 457
WH&S Rep: Siva Moothan 0419 677 511
First Aid Officers: Aaron Armstrong 0404 568 146
Project start date: 15th August 2017
Original completion date: 17th April 2018
Project Duration
All Trucks and Powered Mobile Plant movements shall be coordinated through the designated UHF Channel (confirmed daily during the Pre-Start) or through an alternative process as communicated at the Pre Start (Risk Assessment).
All deliveries shall be organised through the Site Supervisor or Project Manager prior to arrival on site
Speed limit on site is <10 km/h where not on designated roadway
Staff parking is located near the site compound
If you would like more information on the WHS Committee or would like to join it, please see the Site Supervisor.
General Site Information
9
10 Site Rules
10
1. Do not start work without an Induction and Pre Start (Risk Assessment)Each site has its own unique hazards and work operations. Your Site Supervisor will ensure a Site Induction is completed on your first day on site.
In addition, a Pre Start (Risk Assessment) is carried out for your job/task prior to commencement of work. Make sure you understand the hazards, risks and controls so that you can work safely.
2. Follow all safety signs and proceduresFollow all safety signs and procedures e.g. site signage, traffic signage, Pre Start (Risk Assessment) and SWMS – control measures are put in place for your safety.
3. Wear your PPE on site at all times PPE is your last line of defence should you come into contact with a hazard on site. Wear your hard hat, safety boots and hi-viz vest as a minimum, along with any additional PPE required for the job/task being carried out.
10 Site Rules
11
4. Keep a tidy siteConstruction work is messy. Remember to keep your work area tidy throughout your shift to reduce the number of slip and trip hazards.
Always keep walkways open, especially high risk areas such as access and escape routes.
5. Do not put yourself or others at riskYou are responsible for your own behaviour. Construction sites are dangerous places to work. Make sure you remain safety aware throughout your shift.
All visitors shall be accompanied and escorted on-site at all times by a Doval employee who has received relevant Induction Training.
6. Never work in unsafe areas or cause an unsafe situationMake sure your work area is safe. Don’t work at height without suitable guard rails or other appropriate fall prevention. Don’t enter unsupported trenches. Always make sure you have safe access and egress. Don’t work below crane loads or other dangerous operations.
Powered mobile plant may only be used after a Verification of Competency ( VOC) has been conducted. Plant shall only cross roads upon authorisation from the Site Supervisor, together with full traffic control using qualified traffic controllers.
10 Site Rules
12
7. Report defects and near missesIf you notice a problem, don’t ignore it; report it immediately to your Site Supervisor. Action cannot be taken quickly if management are not aware of the problem, and the sooner problems are resolved the less chance for an accident to occur.
8. Never tamper with plant and equipmentAlways check your equipment against the Plant or Equipment Operators Manual to ensure you understand the safe operating requirements. Ensure all safety guards are present as per manufacturers specifications.
Never remove guards, guard rails or scaffold ties. Do not attempt to fix defective equipment unless you are competent to do so. Do not ever tamper with equipment without authorisation.
Site Rules
13
9. Provide adequate fencing & barricading
All workers, including labour hire and sub-contractors shall ensure their work area is
adequately fenced and barricaded. This is to prevent the public, including children from
being able to reasonably access the site and/or fall into penetrations, excavations
and/or trenches during the day, night or over weekends.
No worker may leave any penetration, excavation and/or trench unattended without
ensuring adequate barricading and/or fencing.
10. If in doubt – Ask
Better safe than sorry. Mistakes on construction sites can cost lives - don’t let it be yours. If you need help or further information speak to your Site Supervisor.
14
Site Security & BarricadingAll workers, including sub-contractors have a duty to ensure their work area is adequately fenced and barricaded to prevent the public, including children from being able to reasonably access the site and/or fall into penetrations, excavations and/or trenches during the day, night or over weekends. All penetrations, excavations and trenches shall be suitably barricaded. Pictures marked with red cross (X) demonstrates unacceptablebarricading!
Electrical shocks, which can lead to injuries such as heart failure and burns, are among the
major hazards associated with electric powered tools. Under certain conditions, even a small
amount of electric current can result in fibrillation of the heart and death.
The following general practices should be followed when using electric tools:
• Operate electric & power tools within their design limitations and ALWAYS in accordance
with manufacturers’ instructions.
• Ensure that cords from electric tools do not present a tripping hazard.
• Ensure extension leads are kept off the ground
• Do not use electric tools in damp or wet locations unless they are approved for that
purpose.
• Keep work areas well lighted when operating electric & power tools.
• Use appropriate PPE when using electric & power tools in accordance with
manufacturers instructions
Electric & Power Tools
15
• Angle grinders are one of the most dangerous tools in any
workplace. Most angle grinder injuries are from metal particles
lodging in the operator's eye.
• However the most serious injuries are from kickback, where
the disc is thrust back violently towards the operator.
• Discs can shatter or explode, sending pieces flying in all
directions.
• Because angle grinders are designed for grinding and not for
cutting, the use of cutting discs with angle grinders exposes
operators to even greater risks.
• 9” Grinders are not permitted under any circumstance
• Safety Glasses and full face shield shall be worn when
operating any grinders e.g. grinders, road saws etc.
Angle Grinders
16
• Safety glasses and full face shield shall be worn when
operating any cutting equipment e.g. grinders, road saw
etc.
• Gloves shall be worn as per operators manual
Double Eye Protection: Grinders and Saws
17
• Falls from ladders in the construction industry have
resulted in a significant number of serious and fatal
injuries, even when working at relatively low heights.
• While ladders are often considered to be the first option
when working at heights, they should only be used if safer
alternatives such as scaffolding, elevated work platforms
(EWP) or order pickers (commonly known as chariots) have
been assessed first and are not reasonably practicable for
the task.
• DO NOT USE any ladder on the construction site without
advising the Doval Site Supervisor
Ladders
18
The following signs shall be used on the project. Other signs may be introduced as deemed
necessary.
• Construction Site (Do Not Enter). These will be placed in prominent positions on fencing,
barricading etc.
• PPE signs. There will be general PPE signs (minimum requirements whilst on site) and task
specific signs. Task specific signs will be positioned where the task is being carried out.
• First Aid Signs (Above the First Aid Kit).
• Deep Excavation Signage (located at appropriate positions around the excavation).
• Road Signage (Refer to Traffic Management Plan for details of locations).
Signs are to be displayed in prominent positions. Signs shall be maintained in a good condition. All
workers shall comply with all site signage. Signage includes:
• Location of site access/egress
• Vehicle movements on and off site
• Temporary services distribution
• Emergency procedures including evacuation routes
Signage
19
Mandatory Signs
These signs specify that an instruction MUST be carried out. Symbols (or
pictograms) are identified in white on a blue circular background and indicate the
minimum standard of compliance required for the workplace where it is displayed.
The sign’s wording, if necessary, is in black lettering on the white
Signage
20
Prohibition Signs
These signs specify behaviour or actions, which are not permitted. The slash
should be depicted in red over the action symbol in black. The sign’s wording, if
necessary is in black lettering on the white background.
Signage
21
Warning (Caution) Signs
These signs are to warn of hazards or a hazardous condition that is not likely to be
life threatening. The hazard symbol should be black on a yellow background and a
triangle should be depicted around the hazard symbol. They are black on a yellow
background and indicate that caution is to be taken. The sign’s wording, if
necessary, is in black lettering on the yellow background.
Signage
22
Danger Signs
These signs are for warning when a hazard or a hazardous condition is likely to be
life threatening. The word ‘DANGER’ is in white featured inside a red ellipse inside
a black rectangle. The sign’s wording, if necessary is in black lettering on the
white background.
Fire Signs
These signs advertise the location of fire alarms and firefighting equipment. They
contain a white symbol and/or wording on a red background.
Signage
23
Emergency Information Signs
These signs indicate the location of, or direction to emergency related facilities
(first aid kits, exits, etc.). They feature a white symbol and/or wording on a green
background.
General Information Signs
These signs are not referenced in the Australian Standard AS1319 but are
available to communicate information of a general nature (e.g. housekeeping).
Signage
24
25
ALL Incidents and Hazards, or potential incidents and hazards, must be reported immediately to the Doval Site Supervisor, Project Engineer or Project Manager.
This includes anything related to Workplace Health and Safety, Environment, Quality, Cultural Heritage or any other area.
Incidents and Hazards will be discussed during the daily prestart where everyone will have the opportunity to raise any issues or concerns from the previous day.
Incidents and Potential Hazards
26
Cultural Heritage
As with all civil construction and ground disturbance works, care must taken to preserve our
Culturally Significant areas if they are uncovered. Care must be taken during excavation
and earthworks throughout the site. No significant cultural heritage has been highlighted
due to the project site being located on a Category 3 and 4. However, it should be noted
that even disturbed areas may have ‘residual cultural heritage significance, particularly
around know sites and sensitive landscape types, including wetlands and waterholes
Should material of Aboriginal and/or historical nature be discovered, STOP work and you
must contact Site Management immediately
FIND STOP NOTIFY MANAGE
Drugs, Alcohol, Bullying & Harassment
Bullying, harassment, intimidation, discrimination and threats are
not tolerated at Doval.
No alcohol or illicit drugs are permitted on this site.
The prescribed blood alcohol limit is 0.00%.
All Doval employees, client representatives, contractors,
consultants, business visitors and volunteers must be under the
prescribed limit for alcohol and other drugs when signing on for
work, in the workplace, rostered on duty, on call, or when formally
representing Doval or DTMR at any event or workplace.
Random Drug and Alcohol testing may take place at any time
Rehabilitation and return work strategies are outlined in Doval
Construction’s Drug and Alcohol Policy
27
28
When signing onto the Doval Pre Start (Risk Assessment) you shall be fit for work and able to perform your role. Fit for work applies when on duty, when rostered on call or when representing Doval or DTMR.
Workers shall immediately advise Doval’s Site Supervisor if they:• Reasonably believe they are unfit for work.• Have a condition, medical condition and/or taking medication that may affect their ability to
undertake their work in a safe and effective manner e.g. any medication that may cause drowsiness and/or affect cognitive and/or motor skills.
• Know or suspect that their colleague is unfit for work.• Make sure all our actions and behaviours are safe when performing our duties and follow all
rules, procedures, legislative (legal) requirements and approved safe methods of work• Have the necessary qualification, licence, permit or accreditation, if required, to use any resource
prior to using any resource.
Fit for Work?
29
There is a MANDATORY PPE requirement on all Doval Construction Sites.
This includes:
• Long Pants
• High-Vis Long Sleeve Shirt
• Steel Cap Boots
• Hard Hat
Task Specific PPE includes:
• Gloves
• Safety Glasses/Face Shield
• Hearing Protection
• Sunscreen
• Safety Harness
• Dust Mask
PPE
Materials Safety Data Sheets (SDS) and Hazardous
Substance Risk Assessments are available in the MSDS
folder located on site.
Workers shall read the SDS (MSDS) and associated
Chemicals Risk Assessment, and sign the Risk Assessment
before using any chemicals on site.
All work shall be in accordance with the instructions in the
SDS (MSDS)
Chemicals: Hazardous Substances & Dangerous Goods
30
31
Emergency Evacuation
If there is a need to evacuate the site for any reason
you will hear THREE BLASTS OF AN AIR HORN or
management moving around the site shouting
“EVACUATE! EVACUATE! EVACUATE”
The sites Evacuation Sign & Diagram is located in the
lunch room and site office.
You MUST immediately make your work area safe and
proceed to the EMERGENCY ASSEMBLY AREA at the
entrance of the Office Compound in a CALM and
ORDERLY manner
Do not re-enter the work site until cleared to do so by
management
32
Evacuation Sign & Diagram
33
Emergency Services
If Emergency Services are required on site, please notify Site
Management immediately and they will contact the relevant
authority
If the emergency is life threatening, phone 000, stating the
service required, your location, the nature of the emergency
and your contact details
You must notify Site Management that you have contacted the
emergency services as soon as possible
34
First Aid Personnel
Doval constructions has First Aid qualified staff
on site.
The Designated First Aid Officer on site is the
Project Supervisor –
AARON ARMSTRONG 0404 568 146
Contact your Site Supervisor if you require first
aid treatment.
First Aid and Emergency equipment is located at
the Site Office
35
Emergency Contact
List
Type Details Contact
Fire National Emergency / Redland Bay Fire Station
000 / 07 3829 1403
Police National Emergency / Redland Bay Police Station
000 / 07 3829 4111
Ambulance National Emergency / Wide Bay LASN* Do not call this number if you require medical assistance. In the case of an emergency, please dial 000
000 / * 07 3895 3911
Hospital Redland Hospital 07 3488 3111
RSPCA Animal Hospital
The Albert Animal Hospital
RSPCA Animal Shelter 07 3340 6500
07 3208 9233Veterinary Surgery Rochedale Veterinary Surgery 07 3341 3399
Biosecurity Queensland Fire Ant Management 13 25 23
Poisons Poisons, Drugs, Plants, Bites, Stings 13 11 26
Environmental Incident 1800 550 0337
Ergon 24 Hour Contact Loss of Supply/Emergencies 13 62 62
Other ContactsProject Manager
Ben Dyson 0417 569 822
Project EngineerAndrew DeLacy 0410 598 496
Site Engineer (CQR) Bruce Fock-Yat 0466 677 825Site Engineer (CQR) Richard Hooper 0429 532 736Site Supervisor Aaron Armstrong 0404 568 146First Aid Officer
Aaron Armstrong 0404 468 146
Fire Hazard
36
Actions on discovering a fire:
• Raise the alarm by shouting FIRE and give the LOCATION
e.g. “FIRE IN THE SITE OFFICE!”
• Put the fire out if safe to do so
• Fire extinguishers are available in all of the site sheds,
mobile plant and work vehicles
• Alert Site Management and dial 000
Exclusion ZonesDoval has set a minimum exclusion zone of 15m around all
powered mobile plant e.g. excavator, dozer, roller, trucks etc. All
workers have a duty to remain strictly outside the exclusion zone
of 15m, unless the distance is reduced by the Site Supervisor and
documented in the Pre Start (Risk Assessment).
When approaching the 15m exclusion zone STOP, LOOK, LISTEN,
THINK!
A worker, including sub-contractor and labour hire, may only
enter and/or pass through an exclusion zone if there is no
alternative route. Before entering and/or passing through an
exclusion zone eye contact shall be made with the plant operator,
who shall issue either a verbal or non-verbal (e.g. directional
hand signal) acknowledgement that it is safe to do so?
37
Some particular kinds of work require a PERMIT TO WORK,
which include:
• Excavation works
• Confined Spaces works
• Hot Works
No excavation shall be permitted without a Dial before you Dig
Permits To Work
38
39
Underground Services
Any person performing ground breaking tasks e.g. excavation
MUST familiarise themselves with Dial Before You Dig and as
built drawings contained within the Excavation Permit.
Should any underground services be struck:
• Stop all works
• If injured persons, call 000 immediately and provide
assistance only if trained to do so!
• Make the area safe, where reasonably practicable and if
it is safe to do so!
• Notify Site Management
• No Exceptions
40
Environmental
All personnel on site have a general duty of care towards the Environment and a duty to notify if any
environmental hazards are identified – present, imminent or foreseeable
Report any environmental controls that are defective, including sediment fences.
Do not allow contaminated water or chemicals from site to enter the waterways–
spill kits are available in the Chemical Storage Area.
Refuelling at least 25m away from a waterway using a self bunded refuelling truck.
Alternatively, provided near the Site Office Entrance are a designated refuelling area,
concrete wash-out area, and plant and equipment wash-down facilities.
41
Environmental
In the event of a non-conformance relating to a Environmental and Cultural Heritage Incidents,
it shall be notified, managed and reported .
Notified: The appropriate Administering Authority in accordance with the Approval
Conditions and relevant legislation. In addition, the Contractor is to notify the Administrator
of such Environmental and Cultural Heritage Incident.
Managed: To undertake immediate remedial actions to mitigate Environmental Harm or
further impacts. Within 40 business days an Environmental and Cultural Heritage Incident
Report must be provided.
Reported: All Environmental and Cultural Heritage Incident is included in the Quality Records.
42
Environmental and Incident Emergency Response
What are your environmental responsibilities?Examples of incidents include:
- An oil, fuel or chemical spill- Injuring or death of native wildlife- Discharges of sediment laden water- Excessive noise or dust generation
Contact the Environmental Officer “Terry Clark” and Project Manager immediately in the event of an actual or potential environmental incident.Cease all work in affected area (if required) and check the safety and account for all personnel.
Employ pollution containment measures and re-establish environmental controls.Ensure that there is a spill kit available on site at all times and that this spill kit is regularly maintained.
43
Site Environmental and Cultural Heritage Significance
44
Environmental Unplanned EventsGeneral Response Plan1) Evacuate (all non-essential personnel)2) Eliminate (sources of ignition, sparks, etc.)3) Stop and Coordinate (stop source of the incident (e.g. spill) and coordinate shut down of relevant
equipment, if possible.4) Notify (internal and external notifications)5) Identify (material (if unknown) and identify PPE, hazards and response procedures)6) Contain/Isolate (contain released material / incident using emergency response equipment and/or set up
perimeter to isolate area)7) Stabilise and Neutralise (neutralise / stabilise spilt material)8) Clean up (remove released materials, spill response materials)9) Evaluate10) Document11) Investigate and Remediate
45
Waste Disposal
General Waste is to be disposed immediately and appropriately in the skip bins
provided near the Site Office.
Please note the restrictions on general waste are:
• No Paint
• No Chemicals
• No Oils or Fuels
• No Asbestos
All of these restricted items must be disposed of in a controlled and compliant manner –ask your Site Supervisor!
46
HOUSEKEEPING AND WASTES Objective(s) Reduce waste volume, maximise recycling, reuse and recovery, prevent any construction waste/litter entering the environment.
Management Strategy
Minimise environmental impacts through appropriate controls and site inductions of employees and sub-contractors.
Responsibility (Role) TimingControl(s) Provide appropriate waste bins, type, volume and service frequency to accommodate anticipated
waste streams.
All loads arriving or leaving the site will be appropriately secured.
Provide information regarding waste management in site specific inductions, including waste separation and importance of securing vehicle loads.
Ensure licensed contractors are used to collect controlled wastes
Site Supervisor shall ensureappropriate waste disposal facility is readily available.
It is the responsibility of all working personnel to ensure good house keeping etiquettes is maintain .
Throughout duration of project
Performance Indicator(s)
Hazardous materials all appropriately disposed.
Recycling of all recyclable construction metal waste
Records kept of waste leaving site.Monitoring Daily inspection of work site to occur. Review of waste bins (% full, time to next service).
Waste volumes leaving site from waste contractors
Site Supervisor
Reporting Environmental incident reports. Project Manager Throughout project
Corrective Action(s)
Investigate cause of inappropriate waste disposal
Review cause of issue and develop response, such as variation to bin size, service schedule or waste separation awareness.
Implement controls
Project Manager/Supervisor Throughout project
Housekeeping and Wastes Management Strategy
47
Waste ManagementWhat are your environmental responsibilities?• Reuse/recycle waste where possible.
• Store all waste in secure receptacles or contained areas.
• Licensed transport and disposal contractors to be used as required.
• Environmental Officer is to be notified immediately if any potentially contaminated material is uncovered.
• Keep all work areas clean and tidy.
Smoking Restrictions
NO SMOKING within 10m of fuel storage zones,
site containers and offices
NO SMOKING whilst refuelling plant and vehicles
Some task specific restrictions may apply on the
work site and all directions given by site
management must be complied with
48
49
Site FaunaAll site personnel, including sub-contractors, are to familiarise themselves with the Species Management Program prior to any works in areas which may contain animal breeding places. Throughout the project extent of the Mount Cotton Road WCL Works there is a number of box culverts and pipe culverts which have created an ideal nesting and roosting habitat for colonial species such as Welcome Swallows, Koala, Large Forest Bat and Large-Footed Myotis. If any of these Fauna is located on site please report to the Project Supervisor or any of the Project Team Immediately.
50
Protection of Flora and FaunaWhat are your environmental responsibilities?• Where practicable, don’t park/place vehicles, plant, equipment and stockpiles
within the drip-lines of trees or in a manner which results in damage to vegetation.
• Stockpiling of material and the storage of hazardous substances and dangerous goods is not permitted
• Contact the Environmental Officer if any native animal is injured on site or requires removal from the site.
• Consult the Environmental Officer before any trees or shrubs are removed.• Any weeds removed to be disposed of at an appropriately licensed waste
disposal facility.
51
Species Management Program
For the Mount Cotton Road WCL Works, Doval will be operating under the “Species Management Program for tampering within animal breeding place(s) where there is a high risk impacts”.
The Project Manager (Andrew Delacy) will be responsible for the implementation of this plan, and if not available the Environmental Officer (Terry Clark) and/or the Fauna Spotter Catcher.
52
Environmental Permits and Approvals
Species Management Program has developed sets of management strategies and
protocols to be implemented for the Mount Cotton Road WCL Works.
- DTMR Metropolitan District - Species Management Program – Vespadelus
darlingtonii (Large Forest Bat), Myotis macropus (Large-footed Myotis) and
Hirundo neoxena (Welcome Swallow)
Transport Noise Management Code of Practice Volume 2 – Construction Noise and
Vibration
WSS/2013/726 – Riverine Protection Permit Exemption Requirements
WWBW01 – Code Self – Assessable Development – Minor Waterway Barrier Works
Part 3
WSS/2013/666 – Exemption Requirements for the Taking of Water without a Water
Entitlement under the Water Regulation 2002
Memorandum of Agreement in relation to Government Supported Transport
Infrastructure within the South East Queensland Koala Protected Area.
53
TERRESTRIAL FAUNA Objective(s) 1. To minimise the impact to fauna
2. To prevent the spread of introduced speciesManagement
StrategyEnsure impacts to fauna are minimised, and impacts outside the disturbance zone are avoided.
Species Management Program for Tampering with Animal Breeding Places approved by DEHP pursuant to the Nature Conservation (Wildlife Management) Regulation 2006. Nature Conservation (Koala) Conservation Plan 2006 and the South East Queensland Koala Conservation State Planning Regulatory Provisions
Responsibility (Role) TimingControl(s) Include identification of feral species in prominent locations
Include toolbox talks for site specific fauna information during project to ensure currency of information
Ensure no activities outside the works zone through clear delineation of the works area, and communication in site inductions
Ensure traffic is restricted to established tracks and roads, and speed limits observed.
Where excavations are created which may entrap fauna, suitable escape measures are put in place, and excavation are checked for fauna before backfilling.
Contact wildlife carer groups/vet for injured fauna
Domestic animals prohibited on-site
Ensure appropriate waste management (lidded bins), including food scraps, to reduce potential for feral species to become established on-site
Environmental Site Officer “Terry Clark” will be responsible for the management of fauna found on site.
Fauna Spotter Catcher will undertake a pre-clearing inspection, oversee all vegetation removal activities, undertake a post clearing survey and submit a report detailing their activities.
Throughout project duration
Performance Indicator(s)
No disturbance outside the disturbance zone
No injury or death of any fauna caused by vehicles or excavations
No injury or death of protected fauna.
No domestic animals on-siteMonitoring Daily inspection of work site to occur. Fauna Spotter Catcher
Reporting Sightings and incidents reported in weekly contractor/Project meetings. Injured native fauna to be reported to DTMR Environment and Heritage team
Corrective Action(s)
Investigate cause of incident
Review opportunities/constraints for further minimisation of potential incidents given work procedure parameters
Implement corrective measures prior to the recommencement of site works
Terry Clark in liaise with Doval will ensure the appropriate corrective action has been established.
Terrestrial Fauna Management Strategy
54
Dust
Dust suppression during construction is important not only to the environment but also to the
surrounding people, including workers on the construction site. The generation of dust can cause
detrimental effects to the health and amenity of neighbours and employees, reduced visibility on site,
increased wear on machinery and equipment and complaints from neighbours.
Dust Mitigation techniques shall be used on this site, including watering down of areas generating
excessive dust. If you are aware of an area generating excessive dust, let the site supervisor know.
55
DUST MANAGEMENTObjective(s) 1. To ensure the impacts of dust on adjacent areas , environment and the community are minimised.
Management Strategy
Dust issues managed principally by emission controls at source, and administrative controls during works.
Responsibility TimingControl(s) Area to be disturbed minimised. Clearance lots to be approved by Project Manager.
Where dust is identified as an issue, dust control measures will be implemented. These will primarily be the use of water carts, but may include surface treatments.
Vehicle movements controlled (Traffic Management Plan) and kept to established tracks and haul roads.
Dust awareness issues in environmental induction process
Site Supervisor is to ensure that adequate dust suppression control is implemented through methods such as water carts, and designated/managing side tracks.
Daily monitoring is required
Performance Indicator(s)
No complaints from adjacent commercial premises and/or community.
Monitoring Daily inspection of works sites to occur, including:
• visual check for dust crossing the site boundaries
• visual check of high potential dust areas, such as haul roads, stockpiles and operational areas.
• Stockpiles sites to be situated in areas where likely less prone to severely affect the surrounding community
Site Supervisor is to complete daily site checklist for monitoring dust generated on site.
Dailymonitoring is required.
Reporting Any complaints or incidents to be reported to project manager.
Corrective Action(s)
Investigate cause of excessive dust
Implement controls immediately (e.g. water carts)
Implement corrective measures prior to the recommencement of site works
Implement administrative controls if required, such as rescheduling of dust generating activities to more favourable weather conditions.
Project Manager and Site Supervisor is to ensure the propose control has been implemented.
Dust Management Strategy
56
Erosion and Sediment Control
Land disturbance associated with the construction, installation or maintenance of buildings, roads, sewerage or
other infrastructure creates the potential for increased levels of soil erosion and consequent sediment pollution
of waterways.
The ecological effects of sediment pollution in waterways include:
• smothering or burying the habitats of aquatic plants and animals
• clogging the gills of fish and other aquatic animals
• reducing the growth of aquatic plants due to reduced light penetration
Doval Constructions has an Approved Erosion and Sediment Control Plan in place on this site. Report any
environmental controls that are defective, including sediment fences.
57
SEDIMENT AND EROSION CONTROL
Objective(s) 1. To ensure that the effects of erosion and sedimentation on the environment and biological communities are minimised.
2. Minimise soil disturbance, degradation and erosion.Management
StrategyEnsure that direct impacts (land disturbance) are limited to the works area, and that secondary impacts do not impact adjacent areas.
Responsibility (Role) TimingControl(s) Disturbance area will be minimised and clearly demarcated.
Works will only be conducted within the works zone.
Vehicle movements will be restricted to the defined roads/tracks.
Where possible, works area will be designed to ensure stormwater runoff drains into the site.
Where runoff from the site is required, it will be via the longest flow path possible to ensure maximise sediment retention. Flows to undisturbed areas will be prioritised.
Where required, sediment controls will be put in place. These will include, but not be limited to, rock check dams, sediment basins, sediment fences and silt socks
Project Manager is to ensure that the all erosion and sediment controls devices has been implemented in accordance with the ESCP.
Performance Indicator(s)
No evidence of significant sediment deposition outside the works area. No evidence of significant rilling, gullies or other instances of run-off erosion.
Monitoring Daily inspection of work site to occur.
Sediment controls will be reviewed during site inspections and/or after significant rainfall. Review will include removal of accumulated sediments as required.
Site Supervisor is to ensure that allerosion and sediment control devices are fully operational.
After rainfallevent more than 10mm or excessive built up of silt in ESC devices.
Reporting Incident report for non-conformance of sediment control
Logging of sediment control structures - location and condition during weekly site inspection
Corrective Action(s) Investigate cause of sediment control failure
Review flow path and determine most appropriate controls are in place, additional controls which can be place in-stream and/or changes that can be made to flow path
Review similar controls on-site (even though these may not have failed) for similarities
Project Manager is to ensure the propose corrective measures has been implemented and established.
Sediment and Erosion Control
58
Fire Ants
This project is located within the Fire ant Biosecurity Zone 2
The movement of fire ant carriers shall be in accordance with the Biosecurity Act 2014 and all
activities will be undertaken in a way which minimises the associated biosecurity risks. Fire ants on the
Mount Cotton Road WCL will be managed in accordance with the legislative obligations under the
Biosecurity Regulations 2016. If required, a Biosecurity Instrument Permit from the Department of
Agriculture and Fisheries will be implemented.
Noise & Vibration Compliance Management PlanAnyone doing something that pollutes or might pollute the
environment should take all reasonable measures to prevent or
minimise environmental harm or nuisance.
It is important to be considerate of any road users as well as the
nearby residents and businesses residing along the Mount Cotton
Road within the project extent.
Site construction noises that is generated through machinery and
equipment must be kept to a minimum.
59
60
Noise & Vibration Compliance Management PlanA Noise and Vibration Compliance Management Plan (NVCMP) has been developed for the Mount Cotton
Road WCL. The plan details prevention and management measures for noise and vibration associated with
noise impacts of construction activities on potentially affected receivers, and contingency measures that may
be implemented if complaints are received.
This Noise & Vibration Management Plan details a range of mitigation measures designed to prevent the
following risks from occurring:
• Noise and Vibration affecting nearby properties
• Vibration affecting site structures including heritage listed items and adjacent facilities
• Complaints from adjacent community and neighbouring sites
The NVCMP has been prepared with reference to the Environmental Scoping Report and the Transport Noise
Management Code of Practice Volume 2 – Construction Noise and Vibration prepared by DTMR.
Noise monitoring shall be undertaken in accordance with the Noise Management Manual, DEHP, 2013
61
NOISE MANAGEMENTObjective(s) 1. To minimise the impacts of noise on the amenity of the surrounding areas.
2. Construction activities undertaken in accordance with Environmental Protection (Noise) Regulations 2008
3. Transport Noise Management Code of Practice Volume 2 – Construction Noise and Vibration
Management Strategy
Noise to be managed primarily through administrative and equipment controls during the construction phase.
Responsibility TimingControl(s) All equipment used during the construction phase to be regularly maintained to ensure
efficient operation;
Pre-start checks and maintenance schedules to ensure equipment performance is as required;
Noise-dampening equipment to be used on equipment with excessive noise generating characteristics;
Develop and implement a NVCMP as part f the EMP
Project Manager is to ensure that work activities susceptible to creating excessive noise is schedule outside hours of low potential impacts.
Allconstruction work to be completed within working hours 7:00am – 17:00pm
Performance Indicator(s)
No complaints from adjacent commercial premises and/or community.
Monitoring Daily inspection of works sites to occur
Service logs for equipment/machinery used on site
Site Supervisor is to conductdaily monitoring of noise impacts due to construction activity
Reporting Any complaints or incidents to be reported to project manager.
Corrective Action(s)
Investigate cause of excessive noise
Implement corrective measures prior to the recommencement of site works
Reschedule of noise-generating activities to reduce noise annoyance
The Project Manager is to ensure the proposed corrective action is implemented.
Noise Management Strategy
62
Noise and VibrationWhat are your environmental responsibilities?
•Do not start equipment prior to working hours.
Construction activities audible at any residential receptor are limited to the following hours:
• 7:00 am to 5:00 pm, Mondays to Saturdays• At no time on Sundays or public holidays
• Avoid unnecessary noise e.g. switch off machines when not in use.
• Be aware and respectful of residents and businesses in the vicinity of the site.
Tree Protection ZonesTree protection zones are essential to protecting the trees that are
to remain untouched within the construction boundaries. It is
imperative to ensure that damage does not occur to any of the
remaining trees. No clearing is to undertaken past the clearing
limits (survey pegs) without authorisation from DTMR.
63
Waterways
The works that are being undertaken
have the risk of affecting the Hilliards
Creek, Sandy Creek and surrounds. As
such it is imperative that all erosion and
sediment control measures are in place
and are in working order.
No personnel should be entering the
waterway.
64
Weeds
All Plant and Equipment moved to and from the
site MUST conform to DAF’s guidelines “Ways to
prevent Weed Seed Spread” and come with
Weed Hygiene Declaration forms. These forms
MUST be provided to Doval prior to starting
work. 65
The Metropolitan Region has reported on the Mount Cotton Road WCL Works 20
weed species to be a significant threat to the biodiversity. These are:
Alternanthera philoxeroides, Asparagus aethiopicus, Asparagus africanus,
Asparagus plumosus, Cabomba caroliniana, Chrysanthemoides monilifera,
Chrysanthemoides monilifera subsp. Rotundata, Cryptostegia grandiflora,
Eichhornia crassipes, Hymenachne amplexicaulis, Lantana camara, Opuntia
spp, Parthenium hysterophorus, Protasparagus densiflorus, Protasparagus
plumosus, Sagittaria platyphylla, Sterile Pussy Willow, Salvinia molesta and
Senecio madagascariencis
Weed Management
66
Whilst on-site, all vehicles must stay on the
designated access roads. Any plant, equipment or
vehicle that does traverse or utilise any area not
on a designated haul road must be washed down
prior to leaving site every time.
On leaving the site permanently, the plant,
equipment or vehicle must be washed down in the
site compound before leaving site.
67
NATIVE VEGETATION AND WEEDSObjective(s) 1. To minimise the disturbance to existing flora
2. To minimise the introduction and/or spread of weed speciesManagement
StrategyEnsure impacts to native vegetation are minimised, impacts outside the disturbance zone are avoided and appropriate management is in place to control spread / introduction of weeds.
Responsibility (Role) TimingControl(s) Ensure that any native vegetation clearing occurs within the limits of the clearing extent.
Ensure no activities outside the works zone through clear delineation of the works area, and communication in site inductions
Ensure traffic is restricted to established tracks and roads, and speed limits observed.
Ensure effective sediment and erosion control to reduce potential impacts to non-disturbance zone.
Ensure all plant and equipment coming to site has been cleaned for site access (weeds and seeds).
No fires on-site.
Site Supervisor
Performance Indicator(s)
No disturbance of vegetation communities outside the disturbance zone
No introduction of weed speciesMonitoring Daily inspection of work site and boundary to occur. Site Supervisor
Reporting Any accidental clearing of native vegetation to be reported to the PPA project representative and followed through with an incident report.
Corrective Action(s)
Investigate cause of incident
Implement corrective measures prior to the recommencement of site works
Review opportunities/constraints for further minimisation of potential incidents given work procedure parameters.
Project Manager shall ensure the proposed implementation measures is implemented
Native Vegetation and Weeds
68
Quality
Doval’s Quality Management Plan is available in the Site Office and Quality Policy
Statement is displayed in the Lunch and Meeting Rooms.
Doval Constructions’ Quality Assurance system includes inspection and test plans
which are signed off on completion of set tasks by competent persons.
Doval Constructions aims to:
• Be Customer focused by meeting customer expectations
• Have the right attitude by doing it right the first time
• Learn from our and others mistakes and implement changes
• COMPLY WITH ALL LEGISLATION
69
Project Management Plans
All the relevant information relating to this project/site can be found in the:
• Construction Safety Plan (CSMP)
• Emergency Response Plan (ERP)
• Environmental Management Plan
• Quality Management Plan
• Traffic Management Plan (TMP & associated TGS)
All staff and sub-contractors are encouraged to actively peruse, read and
familiarise themselves with the CSMP and other management plans prior to
work.
Management plans are available in the site office, or upon request to the
Site Supervisor or Project Manager.
Construction Safety Management Plan (CSMP)
The Construction Safety Management Plan (CSMP) provides the framework to enable
Doval Constructions to meet its legal requirements as specified in the WHS Act &
Regulation 2011, Codes of Practice and relevant Australian Standards, Environmental
Protection Act etc.
The CSMP provides the framework and tools whereby all workers (or workers
representatives) are encouraged to actively participate in the identification of hazards, assessment of risks and development of controls during the Pre Start (Risk Assessment).
Management plans are available in the site office, or upon request to the Site Supervisor or Project Manager.
70
Project Risk Assessment
The term Risk Assessment is the industry standard term for Hazard Identification, Risk
Assessment & Control.
The Project Manager and Site Supervisor shall conduct a Project Risk Assessment prior to the
commencement of the project, which shall incorporate the:
• Hazards to Client, Public and/or other affected entities
• Design Risk Assessment (typically from client)
• Build Risk Assessment
• Procurement Risk Assessment
• Any other Risk Assessment that is relevant to the project
All controls shall be based on the:
• Hierarchy of Control (HOC), together with
• Specific legal requirements.
71
Hierarchy of Control
All controls shall be based on the Hierarchy of Control (HOC), which shall be applied to all
hazards identified:
Elimination: Remove the hazard completely from the workplace or activity
Substitution: Replace a hazard with a less dangerous one (e.g. use of a less hazardous chemical)
Isolation: Separate people from the hazard (e.g. safety barrier)
Engineering: Redesign making a machine or work process safer (e.g. raise a bench to reduce bending)
Administrative: Developing SWMS, providing training, enforcing rules, signage to make a workplace safer (e.g.
induction training, highlighting specific hazards)
PPE: Personal Protective Equipment - Protective clothing and equipment (e.g. leather gloves, hard hats)
72
Legal Requirements
The projects specific legal requirements are summarised and/or referenced in the Project Risk
Assessment (Project WHS Legal Risk Register).
Access to specific legislation can be obtained by asking your Site Supervisor or Project
Manager e.g. WHS Act 2011, WHS Regulation 2011, Codes of Practice and relevant Australian
Standards.
73
SWMS All construction work as specified in Section 299, pg. 241 and Section 289, pg. 233 WHS Reg.
2011 requires a Safe Work Method Statement (SWMS).
The Project Risk Assessment (Project WHS Legal Risk Register DC_RE_001) provides essential
information to both the Site Supervisor and workers (or workers representatives) to properly
complete the Pre Start (Risk Assessment).
All sub-contractor SWMS for High Risk Work shall be approved and authorized by Doval prior to
commencement of any work using the SWMS Review Checklist DC_SF_068.
All SWMS including subcontractors shall be reviewed and validated as “fit for purpose” prior to
the specific job/task. This is to ensure all hazards have been identified, risks properly assessed
and controls appropriate – based on the Hierarchy of Control (HOC) and legal requirements.
Validation is required as a SWMS developed and signed-on for a job/task at the start of the
project cannot, in advance, reasonably predict the hazards and/or site specific conditions for
todays specific job/task and scope of work(s).
74
Pre Start (Risk Assessment)
The Project Risk Assessment (Project WHS Legal Risk Register DC_RE_001) provides essential
information to both the Site Supervisor and workers (or workers representatives) to properly
complete the Pre Start (Risk Assessment).
The Daily Pre Start (Risk Assessment) includes:
• Days planned job/tasks, together with activities
• Responsibility, accountability and authority (RAA)
• Validation of SWMS
• Identification of Hazards, Risks & Controls – not adequately covered by a SWMS
• Verification of Licences & Competencies
• Verification that Plant, Equipment & Hazardous Materials is “fit for purpose”
• Nomination of Permits & Compliance Checklists
SWMS that has not been validated for the job/task at the Pre Start (Risk Assessment) prior to
the specific job/task, is not legally compliant.
75
Responsibility, accountability and authority (RAA)
Responsibility, accountability and authority (RAA) is assigned in the Pre Start (Risk
Assessment).
The Projects Master Document Register DC_RE_005 designates the primary
responsibility, accountability and authority (RAA) for each element of the safety,
environment and quality management system - Integrated Management System
(IMS).
Assignment of RAA in the Master Document Register always takes precedence (or
priority) over RAA in Doval’s Management Plans e.g. Construction Safety
Management Plan (CSMP) and/or other documents. This provides site management
a tool for flexibility and efficiency in resourcing.
Ask your Project manager if you do not understand this explanation!
The Master Document Register DE_RE_005 can be accessed via the Site Supervisor or
Project Manager.
76
Legal Compliance Checklists
The Site Supervisor shall nominate competent persons, including sub-contractors
to assist in completing Legal Compliance Checklists, either prior to or during
works.
Do not commence work until all requirements stipulated in the relevant compliance
checklist(s) are satisfied.
77
78
Complete the Online Competency Test
Once you have completed and passed the on-line competency test (exam), ask your Site Supervisor to explain the Project Risk Assessment (WHS Legal Risk Register).
Do not commence work without having familiarised yourself with the Management plans (CSMP, EMP, QMP, ERP and SWMP) and Project Risk Assessments (Legal Risk Registers) – All workers shall sign-on to the Project Risk Assessments and management plans during the induction process.
Do not commence work without understanding and sign-on to the Daily Pre Start (Risk Assessment).
Do not commence work without understanding and sign-on to the relevant SWMS, as specified in the Daily Pre Start (Risk Assessment).