SITE BASED MANAGEMENT PLAN - edqdad.dsdip.qld.gov.au

29
PLANNING & INVESTIGATION REPORT SITE BASED MANAGEMENT PLAN TASK NUMBER: LS-009 JANUARY 2017

Transcript of SITE BASED MANAGEMENT PLAN - edqdad.dsdip.qld.gov.au

PLANNING & INVESTIGATION REPORT

SITE BASED MANAGEMENT PLAN

TASK NUMBER: LS-009

JANUARY 2017

LS-009 Page 2 of 29 Date issued: 27/01/2017 - Rev: 1.0

Approval Register

Date

Submitted by Project Manager: C. Sutcliffe 23/12/2016

LoganWIA Internal Review N/A

Editorial Review N/A

Program Review 25/01/2017

Controlled Document – Change Register

Revision Section

Changed Change Description Initial Date

A All Submission of draft report CS 23/12/2016

B All Council Treatment and EMS team review comments CS 11/01/2017

C All Program Review comments CS 25/01/2017

1 All Finalise report for development application AH 27/1/2017

2

3

4

5

LS-009 Page 3 of 29 Date issued: 27/01/2017 - Rev: 1.0

TABLE OF CONTENTS

1. INTRODUCTION ............................................................................................................................ 5

1.1 Scope ......................................................................................................................................... 5

1.2 Associated documents ................................................................................................................ 5

1.3 Site description ........................................................................................................................... 6

1.4 Process description .................................................................................................................... 7

2. ENVIRONMENTAL MANAGEMENT .............................................................................................. 9

2.1 Environmental authority .............................................................................................................. 9

2.2 Effluent volumes ....................................................................................................................... 10

2.3 Effluent release targets ............................................................................................................. 10

2.4 Environmental incidents ............................................................................................................ 11

2.5 Notification and reporting .......................................................................................................... 12

2.5.1 Incident reporting .................................................................................................................. 12

2.5.2 Exception reporting ............................................................................................................... 12

2.5.3 Annual reporting ................................................................................................................... 12

2.5.4 Record keeping .................................................................................................................... 12

3. MONITORING .............................................................................................................................. 13

3.1.1 WWTP monitoring and inspection ......................................................................................... 13

3.1.2 Receiving environment monitoring ........................................................................................ 13

4. SITE BASED ENVIRONMENTAL CONTROLS ............................................................................ 14

4.1 Element 1: General operation and maintenance ...................................................................... 15

4.2 Element 2: Water quality management .................................................................................... 17

4.3 Element 3: Air quality (odour and dust emissions) ................................................................... 19

4.4 Element 4: Noise emissions .................................................................................................... 21

4.5 Element 5: Waste management .............................................................................................. 23

4.6 Element 7: Hazardous materials handling and storage ............................................................ 25

4.7 Element 8: Wetland management ........................................................................................... 27

5. REFERENCES ............................................................................................................................. 29

TABLES

Table 1-1: Site location Details ................................................................................................................... 6

Table 2-1: WWTP flows ............................................................................................................................10

Table 2-2: Release quality Characteristics- at outlet to WWTP (prior to wetlands) ......................................10

Table 2-3: Release quality characteristics- at Logan River outfall...............................................................11

FIGURES

Figure 1-1: Process schematic diagram...................................................................................................... 8

LS-009 Page 4 of 29 Date issued: 27/01/2017 - Rev: 1.0

ACRONYMS AND ABBREVIATIONS

AMTD Average Middle Thread Distance

ADWF Average Dry Weather Flow

Council Logan City Council

DEHP Department of Environment and Heritage Protection

DNRM Department of Natural Resources and Mines

DSS Desired Standards of Service

EA Environmental Authority

EIR Environmental Incident Report

EMS Environmental Management System

EP Equivalent Persons

ERA Environmentally Relevant Activity

HAZMAT Hazardous Materials

IEMS Integrated Environmental Management System

LoganWIA Logan Water Infrastructure Alliance

MBR Membrane Bioreactor

PLC Programmable Logic Controls

PWWF Peak Wet Weather Flow

SBMP Site Based Management Plan

SDS Safety Data Sheet

SCADA Supervisory control and data acquisition

WWTP Wastewater Treatment Plant

LS-009 Page 5 of 29 Date issued: 27/01/2017 - Rev: 1.0

1. INTRODUCTION

The Logan Water Infrastructure Alliance (LoganWIA) on behalf of Logan City Council (Council) has developed

this site Based Management Plan (SBMP) for the Cedar Grove Waste Water Treatment Plant (WWTP), located

at Cedar Grove Road, Dennis Road and Rogers Road in Cedar Grove QLD (the site).

Stage 1 of the WWTP has a total design capacity of 20,000 equivalent persons (EP). This is defined as an

Environmentally Relevant Activity (ERA) 63(1)(e) as defined under Schedule 2 of the Environmental Protection

Regulation 2008, and may only be conducted under the terms and conditions of the of the Environmental

Authority (EA) (approval in progress). This SBMP has been developed and will be implemented to ensure

compliance with the likely EA conditions for the site.

1.1 Scope

This Site Based Management Plan (SBMP) provides a structured framework to:

address site environmental objectives and standards

identify potential environmental harm that may occur from operation of the site

establish documented management measures

identify extraordinary factors that may cause environmental harm, and establish

response / contingency plans

ensure that all persons working on the site are aware of the environmental risks and trained in

application of management measures and contingency plans

implement monitoring of environmental performance to ensure effectiveness of measures and

contingency plans, as required

ensure accurate and reliable record keeping to assist with internal and external communication of

environmental performance

ensure periodic review of environmental performance to guide continual improvement.

This SBMP is a preliminary document and will be updated to reflect the conditions of the EA for the WWTP,

when approved.

1.2 Associated documents

Associated plans/programs for the Cedar Grove WWTP are as follows:

Netserv Treatment Operations Management Plan (incorporating the Water Quality Release

Improvement Plan)

NetServ Recycled Water Management Plan (incorporating the Contaminant and Release

Reduction Strategy)

Water NetServ Sewer Overflow Management Plan (Logan City Council 2014)

Wastewater Overflow Abatement Strategy ( LWA 2014)

LS-009 Page 6 of 29 Date issued: 27/01/2017 - Rev: 1.0

Sewerage Overflow Management Strategy (LWA 2010)

Further plans that will be developed for the Cedar Grove WWTP, or will be adapted from existing

Council plans to include Cedar Grove WWTP are expected to include:

- Waste Management Plan

- Emergency Response Plan

- Wetland Management Plan.

1.3 Site description

The site is located along Cedar Grove Road, Dennis Road and Rogers Road in Cedar Grove. The Cedar

Grove WWTP site has a total area of approximately 203.9 hectares (ha) which is made up of six land parcels

owned by Council as outlined in Table 1-1.

A pipeline leading from the Cedar Grove WWTP to the Logan River will traverse Lot 200 on RP200030, a

freehold property owned by Queensland Bulk Water Supply Authority (trading as Seqwater) (refer to Table 1-

1).

Table 1-1: Site location Details

Lot on Plan Address Lot Size Land Tenure Land Owner

Lot 1 on RP25779 Dennis Road, Cedar Grove 38.39 ha Freehold land Council

Lot 2 on RP25779 Dennis Road, Cedar Grove 40.34 ha Freehold land Council

Lot 3 on RP25779 Rogers Road, Cedar Grove 25.49 ha Freehold land Council

Lot 4 on RP25779 Rogers Road, Cedar Grove 25.34 ha Freehold land Council

Lot 5 on RP25779 441-489 Cedar Grove Road, Cedar Grove, Logan City

31.43 ha Freehold land Council

Lot 66 on W3123 Dennis Road, Cedar Grove, Logan City

42.89 ha Freehold land Council

Lot 200 on RP200030

104 Couldery Court, Cedar Grove, Logan City (pipeline access only)

9.45 ha Freehold land

Queensland Bulk Water Supply Authority (trading as Seqwater)

Logan River adjacent to Lot 200 on RP200030

Logan River N/A Unallocated State Land

DNRM

A Council road reserve (Rogers Road) also exists through the site, leading to a lot which is held in trust by

Seqwater. Cedar Grove Road forms the southern boundary to the site, while the Logan River forms the

northern and part of the western boundary. Cedar Grove village lies southeast of the site, and agricultural land

lies beyond the boundaries in all other directions. The site is largely cleared of woody vegetation and is

currently used for grazing of cattle.

LS-009 Page 7 of 29 Date issued: 27/01/2017 - Rev: 1.0

1.4 Process description

The proposed WWTP will be a Membrane Bioreactor (MBR) process. The following elements are proposed:

An inlet works, including fine screening and grit removal

A bypass system which will divert flows above 5 x ADWF around the WWTP, after screening

A two basin bioreactor with an integrated four membrane train MBR system capable of processing

instantaneous flows up to 5 x ADWF

A chemical storage and dosing facility for alum, sodium hypochlorite, caustic and citric acid

Bioreactor and membrane aeration blowers inside a blower building

An aerated sludge storage tank for pre-thickened waste activated sludge from the bioreactors

A biosolids dewatering facility comprising a high performance decanter centrifuge or screw press and

polymer batching and dosing system in a sludge dewatering building.

A dewatered biosolids temporary storage and load-out facility

A control building

An odour control system to remove and treat odour from the inlet works structure and at influent flow

splitter at the head of the bioreactors

A generator unit to supply backup power to the plant

A compressed air system to supply the pneumatic actuated valves and any other pneumatic items.

A constructed surface flow wetland is proposed to be installed at the site to provide additional treatment and

in particular, nutrient removal from the effluent. The wetlands will total 10.2 ha in area, constructed over three

stages, each stage comprising 2 cells of 1.7 ha each as shown in Attachment 1. Based on existing growth

projections, cells would be constructed in 2019, 2022 and 2025. Cells will be planted with a range of suitable

wetland species.

All flows treated through the MBR will be discharged to a constructed wetland system. This system will also

be design to accommodate peak wet weather flows of up to 6.5 x ADWF, which is above the adopted peak

wet weather flows (PWWF) of 1000L/EP which has been adopted for new developments in Council’s Desired

Standards of Service (DSS).

A schematic diagram of the WWTP process is presented in Figure 1-1.

LS-009 Page 8 of 29 Date issued: 27/01/2017 - Rev: 1.0

Figure 1-1: Process schematic diagram

LS-009 Page 9 of 29 Date issued: 27/01/2017 - Rev: 1.0

2. ENVIRONMENTAL MANAGEMENT

This SBMP forms part of the overarching Wastewater Services Integrated Environmental Management System

(IEMS) for Council. The IEMS documents Council’s approach for managing potential environmental impacts

of Council’s products, services and activities across the water business. All site operations and management

measures are to be carried out in a manner consistent with the IEMS.

Council’s IEMS incorporates the following:

Environmental Policy

Environmental Aspects and Impacts

Objectives, Targets and Programs

Resources, Roles, Responsibility and Authority

Competence, Training and Awareness

Communication

Documentation

Control of documents

Operational control

Emergency preparedness and response

Monitoring and Measurement

Evaluation and compliance

Nonconformity, corrective action and preventative action

Control of records

Internal and external audits

Management review including continuous Improvement of the EMS.

The SBMP is the guiding document for the site–specific environmental management controls and procedures

adopted as part of the operation of the Cedar Grove WWTP. The SBMP contains references to other

documents including procedures, plans, manuals and registers that are maintained as a part of the IEMS.

2.1 Environmental authority

The operation of the Cedar Grove WWTP and attached wastewater network is classified as the following

Environmentally Relevant Activity (ERA) under the Environmental Protection Act 1994:

ERA 63 (1e) – Sewage Treatment: operating sewage treatment works other than no-release works, with a

total daily peak design capacity of more than 10,000 but not more than 50,000Equivalent Persons.

Under the provisions of the Environmental Protection Act 1994, an Environmental Authority (EA) for carrying

out the ERA is required. The EA will include series of conditions that must be complied with to ensure that

potential impacts on the environment are minimised during the life of the ERA. This SBMP will be updated

once the EA has been issued, to reflect the requirements of the conditions.

LS-009 Page 10 of 29 Date issued: 27/01/2017 - Rev: 1.0

2.2 Effluent volumes

Daily design flows will be based on Councils DSS. Average annual flows are calculated based on inflow data

collected from Flagstone WWTP, which are approximately 1.1 x ADWF. Table 2-1 summarises the design

capacity of the Cedar Grove WWTP.

Table 2-1: WWTP flows

Criteria Criteria number

ADWF 165 L/EP

PWWF 1,000 L/EP

Design Capacity 20,000 EP

Design Capacity ADWF 3.3 ML/d

Design capacity PWWF 16.5ML/d

Annual average flow 1,324 ML/year

2.3 Effluent release targets

The following effluent release targets are proposed for the WWTP.

Table 2-2: Release quality characteristics- at outlet to WWTP (prior to wetlands)

Quality Characteristic Weekly

Min Median1

Long term 50th

percentile2 Max Frequency

BOD5 (mg/L) 10 30 Every 2 weeks

Suspended Solids (mg/L) 10 30 Every 2 weeks

Ammonia (mg/L) 1 3 Every 2 weeks

Total Nitrogen (mg/L) 3 9 Every 2 weeks

Total Phosphorous (mg/L) 1 3 Every 2 weeks

pH (pH units) 6.5 8.5 Every 2 weeks

Dissolved Oxygen (mg/L) 2.0 Every 2 weeks

Faecal Coliforms (cfu/100mL) 150 600 Every 2 weeks

Enterococci (cfu/100mL) 35 Every 2 weeks

1Median means median of 5 consecutive samples taken over 28 hours

2Long term 50th percentile means the median value of the measured values over a rolling one-year period

LS-009 Page 11 of 29 Date issued: 27/01/2017 - Rev: 1.0

Table 2-3: Release quality characteristics- at Logan River outfall

Quality Characteristic Long term

50th percentile1

Max Annual Mass

Load23 Frequency

Total Nitrogen mg/L 1 Every 2 weeks

Total Nitrogen (kg/year) 1323.0 Annual calculation

Total Phosphorous (mg/L) 0.5 Every 2 weeks

Total Phosphorous (kg/year) 662.5 Annual Calculation

Free Chlorine (mg/L) 0.5 Every 2 weeks if chlorination is proposed

1Long term 50th percentile means the median value if the measured values over a rolling one-year period

2Annual Dry Weather Mass Load Limit (kg) = Design Average Flow (ML per day) x 365 x long term median (50th percentile) concentration (mg/L)

3Design Average Flow =1.1 x Average Dry Weather Flow

2.4 Environmental incidents

Whilst all best efforts are made by operators to prevent pollution, at times environmental incidents can still

occur which may cause environmental harm or nuisance. In such instances, Council must respond in

accordance with the EP Act Duty to Notify of Environmental Harm, which states that:

While carrying out an activity if a person becomes aware of an event that causes serious or material

environmental harm the person has a duty to notify the employer / administering authority.

As such, in the event of an environmental incident in which environmental harm or nuisance is suspected; for

example, a dry weather bypass, major WWTP process upset or a sewage overflow that has the potential to

impact on the environment, the following notification procedure is to be followed.

During work hours

1. The operator must notify their Supervisor as soon as practically possible via telephone, but no later

than 24 hours after initially becoming aware of an incident where environmental harm may be caused

or threatened.

2. The Supervisor must in turn notify the Environmental Management Systems Team via telephone (3412

4335) and the Treatment Program Leader and provide the following details:

the incident details and location specifics;

the contact details of the relevant supervisor on-site; and

a short summary of the situation.

3. The Environmental Management Systems team will investigate the incident in conjunction with the on-

site supervisor, record relevant information and carry out the necessary stakeholder notifications and

regulatory reporting on behalf of Council where required.

4. The Treatment Program Leader will oversee corrective actions and notify Workplace Health & Safety

if required.

LS-009 Page 12 of 29 Date issued: 27/01/2017 - Rev: 1.0

After work hours

1. The operator must notify their supervisor on-call as soon as practically possible via telephone, but no

later than 24 hours after initially becoming aware of an incident where environmental harm may be

threatened.

2. The on-call supervisor must in turn notify the Environmental Management Systems Team via

telephone and provide the details of the incident (as per work hours procedure). Environmental

Management Systems Team After Hours Number: 3412 4335. (The phone will be diverted to the on-

call Environmental Management Systems Team Member). The Treatment Program Leader is also to

be notified.

3. The Environmental Management Systems team will investigate the incident in conjunction with the on-

site supervisor, record relevant information and carry out the necessary stakeholder notifications and

regulatory reporting on behalf of Council where required.

4. The Treatment Program Leader will oversee corrective actions and notify Workplace Health & Safety

if required.

2.5 Notification and reporting

2.5.1 Incident reporting

Where the incident is deemed to be notifiable (as defined in the Environmental Protection Act 1994 as ‘an

event that causes or threatens serious or material environmental harm’, then a duty to notify DEHP exists. In

this instance, the on-call Environmental Management Systems Team member will undertake notification as

soon as practicable, after becoming aware of any site based emergency or notifiable incident. Written

notifications shall be completed through the DEHP’s, Duty to Notify of Environmental Harm, EM468 Notice.

An Environmental Investigation Report (EIR) will be provided to the DEHP within 14 days following the initial

notification of an emergency or incident

Reporting procedures for all notifications and reporting to the DEHP will be followed. Qualified/trained persons

to carry out all notifications.

2.5.2 Exception reporting

In the event of exceedance of any licensed limit, the exceedance will be notified to DEHP in writing by the

Environmental Management Systems Team, within 28 days of completion of laboratory analysis in the form of

a monthly exceedance report.

2.5.3 Annual reporting

An annual report detailing compliance with conditions of the Environmental Authority will be supplied to DEHP

on or before the anniversary date of the Environmental Authority each year.

2.5.4 Record keeping

All records are required to be maintained for a minimum of 5 years.

Operational records, monitoring results and any corrective actions undertaken, will be made available upon

request, to the DEHP.

LS-009 Page 13 of 29 Date issued: 27/01/2017 - Rev: 1.0

3. MONITORING

3.1.1 WWTP monitoring and inspection

Effluent quality will be monitored every two weeks as per EA requirements when issued.

Monitoring of WWTP performance and compliance with required effluent quality criteria will be undertaken in

accordance with the latest edition of the DEHP Water Quality Sampling Manual with analysis of monitoring

samples conducted at the Council NATA accredited Laboratory or alternative NATA accredited facility.

Other monitoring will include:

Daily site inspections of the site, WWTP, systems and controls including:

- Site security

- Accessible pipework, pumps, fittings and connections

- The treatment process and tanks

- Chemical and waste storage areas

- Vehicle wash-down area

- Waste oil collection station

- Workshops

- Odour control units

- Stormwater diversion and/or conveyance systems

- Alarms, telemetry, PLC and SCADA controls

- Stormwater diversion and/or conveyance systems

- Tanks, bunds and chemical storage areas

- Waste storage areas

- Spill kits and HAZMAT boxes.

Daily monitoring of inflows and effluent release volumes

Weekly inspection of wetlands including inlets, outlets, vertical risers, plant coverage and weeds

Operational monitoring as required on-site by WWTP operators to help ensure that the wastewater

treatment process is operating as required.

3.1.2 Receiving environment monitoring

Council participates in the funding of the Healthy Waterways and Catchments’ Ecosystem Health Monitoring

Program. This replaces the requirement for a Receiving Environment Monitoring Program.

LS-009 Page 14 of 29 Date issued: 27/01/2017 - Rev: 1.0

4. SITE BASED ENVIRONMENTAL CONTROLS

Through assessment of the operational aspects and impacts, the following elements have been developed to

manage the identified risks:

Element 1: General Operation and Management

Element 2: Water Quality Management

Element 3: Air Quality (Odour and Dust Emissions)

Element 4: Noise Emissions

Element 5: Waste Management

Element 6: Hazardous Materials Handling and Storage

Element 7: Wetland Management.

Each element includes the following key components:

Impact: a description of the environmental impact of activities associated with the element

Objectives/Targets: the environmental objectives to be achieved to comply with the rationale and

applicable environmental legislation

Control Measures: measures to be implemented to achieve the stated objectives and to ensure

impact mitigation

Monitoring: requirements for measuring compliance against performance indicators and providing

measurement frequency

Record Keeping: requirements over the life of the SBMP

Reporting and Review: responsibilities for reporting monitoring results and reviewing management

measures

Corrective Actions/Contingency: measures to be undertaken where non-compliance with

performance indicator is demonstrated.

LS-009 Page 15 of 29 Date issued: 27/01/2017 - Rev: 1.0

4.1 Element 1: General operation and maintenance

Impacts

The operation of Cedar Grove WWTP has the potential to cause environmental harm through the release of pollutants to the environment.

Objectives / Targets

The WWTP is operated in a manner that considers the sensitivity of the surrounding environment and prevents and/or minimises the likelihood of environmental harm.

Compliance with this SBMP, associated management plans and the conditions of the EA.

Control Measures

A valid environmental authority is held pursuant to the EP Act to lawfully operate the site.

A copy of the EA, this SBMP and associated management plans is maintained and available onsite, at all times.

All plant and equipment is maintained and operated in a proper and efficient manner and in accordance with manufacturer specifications.

Monitoring instruments, equipment and measuring devices are calibrated, operated and maintained in accordance with manufacturer specifications.

Alarm, telemetry, programmable logic controls (PLC) and supervisory control and data acquisition (SCADA) systems are installed and maintained. All alarms operate without mains power.

The daily operation and maintenance of the WWTP will only be carried out by persons with relevant experience, qualifications and training. New employees are provided with adequate training and experience prior to full operational responsibility.

The daily operation and maintenance of the WWTP is carried out in accordance with relevant Standard Operating Procedures and the Site Based Management Plan.

Only authorised persons are permitted to access the site. All contractors and visitors to the WWTP undergo a site induction. All visitors are to be accompanied by Council employees when on the site.

Appropriately qualified staff are on call to deal with incidents 24 hours/day.

Contingencies in place for emergency situations include:

Alarm, PLC, SCADA and telemetry systems

Duty and standby equipment and assets

Generator with automatic operation in the event of power failure

Site security

Emergency Response Plan.

Monitoring

Routine inspections, monitoring and maintenance of all plant, equipment and components of the site shall be undertaken regularly, including, but not limited to:

Site security fencing/gate

Visual inspections of all accessible pipework and fittings

The treatment process and effluent / recycled water storage tanks

Chemical and waste storage areas

Vehicle wash-down area

Wasteoil collection station

Workshops

Odour control units

All pumps infrastructure and connections

Stormwater diversion and/or conveyance systems.

Monitoring will be undertaken of treatment process performance through water quality assessments at various locations throughout the site as required.

LS-009 Page 16 of 29 Date issued: 27/01/2017 - Rev: 1.0

Record Keeping

Maintain records of equipment inspections, calibration and any repairs and/or maintenance actions undertaken.

Maintain records of any site inductions, employee training and competencies.

All complaints, monitoring and remediation measures are recorded and available to the regulatory authorities upon request. This should include details of corrective actions and/or repairs undertaken.

Reporting and Review

Notify the Environmental Management Systems Team and Treatment Program Manager as soon as practicable after becoming aware of any site based emergency or notifiable environmental incident. The EMS team will be responsible for written notifications of environmental incidents.

Operational records, monitoring results and any corrective actions undertaken, will be available upon request, to the DEHP.

All operational procedures and management plans will be reviewed annually.

Corrective Actions / Contingency

The applicable corrective actions will be implemented following any emergency or incident affecting the site. These will include:

Implement appropriate mitigation measures as determined by a suitably qualified person to prevent future non-compliance

Implement the corrective action(s) as required within the agreed timeframe in consultation with the process team

Complete and follow through with all relevant validation monitoring or actions to confirm that the nominated corrective actions have been effective

Ensure close out of all corrective actions, including documenting through the appropriate processes.

Where it is found a Contingency or Corrective Action is insufficient, further investigation and reporting to take place.

LS-009 Page 17 of 29 Date issued: 27/01/2017 - Rev: 1.0

4.2 Element 2: Water quality management

Impacts

Short and long term impacts on Logan River water quality and aquatic ecosystems through:

Waterway pollution due to non-compliant effluent quality release

Spills and leaks of potential contaminants.

Objectives / Targets

No release of contaminants to receiving environment outside of EA criteria.

Prevent and/or minimise unnecessary effluent bypasses. By-pass events only occur for flows that are in excess of 5 x ADWF. All flow from a by-pass event as a minimum treated by fine screening and grit removal and directed through a wetland cell prior to release.

Compliance with the Environmental Protection (Water) Policy 2009 and the requirements of this SBMP and associated management plans.

Effluent releases occur only from the nominated discharge location (W2), defined as the point of release via the outfall pipe located 81km adopted middle thread distance (AMTD) Logan River, downstream of the Cedar Grove Weir.

Effluent release occurs at the nominated quantities and release quality characteristics as specified in the EA.

Stormwater infrastructure is maintained in good working order. Compliance with:

Netserv Treatment Operations Management Plan (incorporating the Water Quality Release Improvement Plan)

NetServ Recycled Water Management Plan (incorporating the Contaminant and Release Reduction Strategy)

NetServ Treatment Operations Management Plan

Logan Water Alliance Wastewater Overflow Abatement Strategy (2014)

Emergency Response Plan (ERP) (to be prepared).

Control Measures

Treated effluent is only discharged at discharged point W2. The maximum permitted quantities of effluent are as per Table 2-1.

Effluent release limits prior to entry to the wetland at point W1 must comply with the release quality characteristics as per Tables 2-2.

The total mass load of Total Nitrogen and Total Phosphorus released from release point W2 is less than or equal to the mass specified in Table 2-3, calculated annually.

Wash-down of vehicles /plant is only to occur in the vehicle wash-down area.

Clean stormwater is diverted around the site.

Site drainage from any potentially contaminated areas is directed to appropriately designed and sized treatment/detention devices prior to discharge off site.

Wetlands are managed in accordance with the Wetland Management Plan and Element 7 of this SBMP

Monitoring equipment, telemetry, SCADA, PLCs and alarms are installed at appropriate locations to effectively operate and control the site.

Regular communications are maintained between site and network crews to ensure the site is capable of treating influent flows.

By-pass flow events shall only occur for flows that are in excess of 5 x ADWF and will undergo, primary treatment by fine screening and grit removal prior to release to wetlands.

Defects with site plant and equipment are repaired as soon as practicable to prevent sewage spills and leakages and the discharge of out of specification effluent.

Monitoring

Routine inspections, maintenance and monitoring of all site plant, equipment and components, including but not limited to:

Pump infrastructure and connections

Site pipe work and fittings

Bypass system

LS-009 Page 18 of 29 Date issued: 27/01/2017 - Rev: 1.0

Alarms, telemetry, PLC and SCADA controls

Stormwater diversion and/or conveyance systems.

Monitoring of treatment process performance through water quality assessments at various locations throughout the site.

Daily volume of treated effluent discharge is determined or estimated using a flow meter.

Effluent Quality at points W1 and W2 monitored in accordance with the frequencies specified in Tables 2-2 and 2-3.

All sampling and analysis is undertaken in accordance with methods prescribed in the latest edition of the DEHP’s Water Quality Sampling Manual.

All monitoring instrumentation, equipment is calibrated, operated and maintained in accordance with manufacturer’s specifications.

All sample analysis is carried out by a NATA accredited laboratory, except as otherwise authorised by the DEHP.

Record Keeping

Maintain records of all inspections and monitoring conducted at the site.

Maintain records of determined or estimated daily volume of contaminants releases to waters. Maintain records of any bypasses of effluent including date, duration, cause and actions taken.

Maintain records of any uncontrolled release of contaminants reasonably likely to cause environmental harm.

Maintain records of equipment inspections and any repairs and/or maintenance actions undertaken. Maintain all records for a period of at least 5 years.

Reporting and Review

Reporting of exceedance of any licensed limit to DEHP in writing, by a qualified person, within 28 days of completion of laboratory analysis (monthly exceedance report).

Reporting procedures for all notifications and reporting to the DEHP will be followed. Qualified/trained persons to carry out all notifications.

Notify the Environmental Management Systems Team and Treatment Program Manager as soon as practicable after becoming aware of any site based emergency or notifiable environmental incident. The EMS team will be responsible for written notifications of environmental incidents.

Operational records, monitoring results and any corrective actions undertaken will be available upon request, to the DEHP.

All operational procedures and management plans are reviewed annually.

Corrective Actions / Contingency

Contingencies in place include:

Alarm, PLC, SCADA and telemetry systems

Duty and standby equipment and assets

Generator

Spill kits

Emergency Response Plan.

The applicable corrective actions will be implemented in consultation with the process team following any emergency or incident affecting the site.

Corrective actions will be:

Determined by a suitably qualified person

Implemented within the agreed timeframe

Completed and followed through with all relevant validation monitoring or actions to confirm that the nominated corrective actions have been effective

Closed out, including documentation through the appropriate processes.

Where it is found a Contingency or Corrective Action is insufficient, further investigation and reporting shall take place

LS-009 Page 19 of 29 Date issued: 27/01/2017 - Rev: 1.0

4.3 Element 3: Air quality (odour and dust emissions)

Impacts

Local air quality impacts and odour nuisance affecting surrounding neighborhood.

Objectives / Targets

The WWTP is operated in a manner that considers the sensitivity of the surrounding environment and prevents the release of dust and odour emissions resulting in amenity impacts to sensitive receptors.

No odour or dust complaints from local residents or any sensitive place.

Comply with conditions of the EA, the Environmental Protection (Air) Policy 2008 and requirements of this SBMP and associated management plans.

Control Measures

The Odour Control Facility housing the inlet works shall be properly maintained and filters cleaned up as per the manufacturer’s specifications or as necessary.

The site shall be inspected on a daily basis.

Any sewage or sludge with the potential to cause odour issues shall be appropriately removed or cleaned up as soon as practicable.

Bins shall be covered and emptied routinely.

Chemicals are to be used in designated areas only, with adequate ventilation to ensure dispersal of fumes.

Refuelling activities shall only occur in designated areas, and fuel and oil storage areas will be maintained and operated to minimise emissions to the atmosphere via leakages or spills.

Any chemical of fuel leaks or spills shall be cleaned up as soon as practicable to prevent odour emissions.

Any maintenance tasks identified by the daily inspections shall be completed within the nominated timeframes

Monitoring

Daily routine inspections of:

Tanks, bunds and chemical storage areas

Odour Control Facility

Waste storage areas.

If requested by the DEHP, dust and / or particulate monitoring will be carried out.

Any dust/particulate monitoring shall be conducted in accordance with either Australian Standards, AS3580.10-1991 or AS3580.9.6-2003 or a method permitted by the DEHP’s Air Quality Sampling Manual at a dust sensitive place downwind from the site as requested by the DEHP.

Record Keeping

Maintain records of all inspections and monitoring conducted at the site.

Maintain records of equipment inspections and any repairs and/or maintenance actions undertaken.

Maintain all records of complaints received including complainant details, investigations/monitoring results conducted and corrective actions (including repairs and maintenance) undertaken.

Maintain all records for a period of at least 5 years.

Reporting and Review

Notify the Environmental Management Systems Team and Treatment Program Manager as soon as practicable after becoming aware of any site based emergency or notifiable environmental incident. The EMS team will be responsible for written notifications of environmental incidents.

Provide records to the DEHP upon request.

All dust and/or particulate matter monitoring results shall be provided to the DEHP within 14 days of receipt of analytical data.

LS-009 Page 20 of 29 Date issued: 27/01/2017 - Rev: 1.0

Corrective Actions / Contingency

Should complaints about air quality be received, Council shall undertake investigations and if complaint is validated, undertake corrective actions as required.

Actions shall include:

Visit the location of the complainant(s) to determine appropriate mitigation measures and the validity of the complaint

Identify the source(s) of the excessive dust or odour emissions

Implement appropriate corrective actions as determined by a suitably qualified person to prevent future non-compliance in consultation with the process team

Undertake relevant validation monitoring of air impurity concentrations at nominated locations, if requested by the DEHP

Complete and follow through with all relevant validation monitoring or actions to confirm that the nominated corrective actions have been effective

Ensure close out of all corrective actions, including documenting through the appropriate processes.

Where it is found a Contingency or Corrective Action is insufficient, further investigation and reporting shall take place.

LS-009 Page 21 of 29 Date issued: 27/01/2017 - Rev: 1.0

4.4 Element 4: Noise emissions

Impacts

Noise nuisance affecting surrounding neighborhood.

Objectives / Targets

The WWTP is operated in a manner that considers the sensitivity of the surrounding environment and prevents the release of noise emissions resulting in amenity impacts to sensitive receptors.

No noise complaints from nearby noise sensitive places.

Comply with conditions of the EA, the Environmental Protection (Noise) Policy 2008 and requirements of this SBMP and associated management plans.

Control Measures

Where practicable, noise emitting processes are to be enclosed within an insulated structure to prevent or minimise the emission of nuisance noise.

Where required, noise emitting plant and equipment shall be fitted with noise minimisation devices.

Regular inspection and maintenance of devices shall be undertaken to assess their performance against designed standards.

The site is inspected on a daily basis.

The site is operated and maintained in accordance with the SBMP and Standard Operating Procedures.

Any maintenances tasks identified by the daily inspections shall be completed within the nominated timeframes

Monitoring

Routine inspections shall be undertaken to monitor plant operation and inspect equipment and components. Inspections shall include the identification of unusual or offensive noise and vibration which may cause nuisance to surrounding land users.

If requested by the DEHP, noise monitoring shall be undertaken to investigate any complaint of noise nuisance. Monitoring shall include:

LA10, adj, 10mins

LA1, adj, 10mins

The level and frequency of occurrence of impulsive or tonal noise

Atmospheric conditions including wind speed and direction

Effects due to extraneous factors such as traffic noise

Location, date and time of recording.

The method of measurement and reporting of noise will comply with the latest edition of the DEHP’s Noise Measurement Manual.

Record Keeping

Maintain records of all inspections and monitoring conducted at the site.

Maintain records of equipment inspections and any repairs and/or maintenance actions undertaken.

Maintain all records of complaints received including complainant details, investigations/monitoring results conducted and corrective actions (including repairs and maintenance) undertaken.

Maintain all records for a period of at least 5 years.

Reporting and Review

Provide records to the DEHP upon request.

Notify the Environmental Management Systems Team and Treatment Program Manager as soon as practicable after becoming aware of any site based emergency or notifiable environmental incident. The EMS team will be responsible for written notifications of environmental incidents.

Following a noise monitoring request by the DEHP, monitoring results shall be provided to the DEHP within 14 days following the receipt of results.

LS-009 Page 22 of 29 Date issued: 27/01/2017 - Rev: 1.0

Corrective Actions / Contingency

Should complaints about noise nuisance be received, Council shall undertake investigations and if complaint is validated, undertake corrective actions as required.

Actions shall include:

Visit the location of the complainant(s) to determine appropriate mitigation measures and the validity of the complaint

Identify the source(s) of the excessive noise emissions

Implement appropriate corrective actions as determined by a suitably qualified person to prevent future non-compliance in consultation with the process team

Undertake relevant noise validation monitoring at nominated locations, if requested by the DEHP

Complete and follow through with all relevant validation monitoring or actions to confirm that the nominated corrective actions have been effective

Ensure close out of all corrective actions, including documenting through the appropriate processes.

Where it is found a Contingency or Corrective Action is insufficient, further investigation and reporting shall take place.

LS-009 Page 23 of 29 Date issued: 27/01/2017 - Rev: 1.0

4.5 Element 5: Waste management

Impacts

Improper management of waste may lead to contamination of the environment or public nuisance.

Objectives / Targets

Avoid, reduce, reuse, recycle, recover, treat and dispose of waste appropriately.

Effectively manage waste to prevent air, water and soil pollution at the site and site surrounds.

Comply with conditions of the EA, the Waste Reduction and Recycling Act (2011) and requirements of this SBMP and the Waste Management Plan (to be prepared).

Control Measures

Appropriately, handle, store and dispose of all wastes at the site.

Regular inspection shall be undertaken of waste storage areas.

Wastes shall be stored correctly in relevant storage areas or receptacles. Appropriate waste bins are to be provided for different types of waste produced at the site.

Any maintenance tasks identified by the daily inspections shall be completed within the nominated timeframes

Wastes are regularly removed offsite by an appropriately licensed contractor to be disposed at a suitable waste disposal facility.

A Waste Management Plan is developed which details the types and quantities of waste generated on the site, the storage and on site management requirements and provisions for transport and disposal of wastes.

Special provisions for disposal of Regulated Waste

Regulated waste is stored, transported and disposed of as per the requirements of the EA and the Environmental Protection Regulation 2008.

Sludge, screenings and grit are dewatered prior to transport and disposal by a licensed regulated waste contractor to a licensed site.

Sludge / Biosolids are regularly removed offsite by a licensed regulated waste removal contractor.

Waste tracking procedures are maintained for all trackable wastes.

Monitoring

Routine daily inspections shall be undertaken of the site to ensure waste is being appropriately stored and handled.

Regular inspections of site (and site surrounds if necessary) to ensure no uncontrolled waste has been released.

Record Keeping

Maintain records of all inspections and monitoring conducted at the site.

Maintain records of equipment inspections and any repairs and/or maintenance actions undertaken.

Maintain records of wastes removed from site including type of waste and volume.

Maintain copies of Waste Tracking Forms of all trackable regulated waste collected from the site.

Reporting and Review

Notify the Environmental Management Systems Team and Treatment Program Manager as soon as practicable after becoming aware of any site based emergency or notifiable environmental incident. The EMS team will be responsible for written notifications of environmental incidents.

Provide waste records to the DEHP upon request.

LS-009 Page 24 of 29 Date issued: 27/01/2017 - Rev: 1.0

Corrective Actions / Contingency

The applicable corrective actions will be implemented should there be a non-compliance with the stated performance indicators.

Corrective actions will be:

Determined by a suitably qualified person

Implemented within the agreed timeframe

Completed in consultation with the process team and followed through with all relevant validation monitoring or actions to confirm that the nominated corrective actions have been effective

Closed out, including documentation through the appropriate processes.

Where it is found a Contingency or Corrective Action is insufficient, further investigation and reporting shall take place.

LS-009 Page 25 of 29 Date issued: 27/01/2017 - Rev: 1.0

4.6 Element 7: Hazardous materials handling and storage

Impacts

Improper storage, handling and use of hazardous substances at the site may result in impacts to human health and the surrounding environment.

Objectives / Targets

No release of chemicals or other hazardous or dangerous material due to inappropriate handling and storing procedures.

Effective management of the safe storage, handling and disposal of dangerous and/or hazardous materials in accordance with:

SBMP and Standard Operating Procedures

Conditions of the EA

Applicable Safety Data Sheet (SDS)

Relevant Standard Operating procedures

Work Health and Safety Regulation 2011.

Spillage of chemicals and fuels is contained within an onsite containment system and controlled in a manner that prevents environmental harm.

Control Measures

All dangerous or hazardous substances storage tanks shall be contained within an impervious bunded containment areas with a capacity to hold at least 110% of the largest storage tank plus 10% of the second largest storage tank within the bund, and preferably undercover.

All dangerous or hazardous substances storage drums shall be stored within an impervious bunded containment areas with a capacity of the bund sufficient to hold at least 25% of the maximum design storage volume within the bund, and preferably undercover.

Tanker loading / unloading areas shall be on impervious hardstand and bunded so that the capacity of the bund is sufficient to contain 100% of the largest compartment of the tanker using the area.

A fire proof bunded cabinet shall be provided for smaller amounts of dangerous or hazardous substances.

Stormwater diversion and/or conveyance systems shall be in place to prevent stormwater intrusion into or across hazardous or dangerous material storage areas.

Chemicals shall be used in designated areas only, with adequate bunding to prevent the release of contaminated flows into stormwater or onto land.

An up-to-date and accurate register of chemical and other hazardous materials shall be available onsite at all times. This register is to include an emergency contacts list.

All applicable SDSs shall be available and accessible onsite at all times.

A collection sump shall be provided in the floor of all permanent bunding to facilitate the removal of liquids. The bund floor is to be graded so that the fall is towards the sump.

Required Personal Protection Equipment (PPE) shall be worn as recommended by the SDS when handling hazardous substances.

Spills kits and HAZMAT boxes shall be available and readily accessible at all locations where chemical spills may occur and shall be restocked following each use.

All site staff shall be trained in the use of spill kits.

All plant and equipment cleaning and maintenance shall be conducted in designated areas which include relevant containment systems and controls to prevent contamination.

Monitoring

Regular inspections of hazardous storage and containment areas to ensure spills or leaks have not occurred, and to ensure the integrity of the containment area is not compromised.

Regular inspections of stormwater diversion and/or conveyance systems for signs of contamination.

Regular inspections of spill kits and HAZMAT boxes to ensure they are fully stocked and ready for use.

LS-009 Page 26 of 29 Date issued: 27/01/2017 - Rev: 1.0

Record Keeping

Maintain records of all inspections and monitoring conducted at the site.

Maintain records of equipment inspections and any repairs and/or maintenance actions undertaken.

Maintain all records for a period of at least 5 years.

Reporting and Review

Reporting procedures for all notifications and reporting to the DEHP will be followed. Qualified/trained persons to carry out all notifications.

Notify the Environmental Management Systems Team and Treatment Program Manager as soon as practicable after becoming aware of any site based emergency or notifiable environmental incident. The EMS team will be responsible for written notifications of environmental incidents.

Operational records, monitoring results and any corrective actions undertaken, will be available upon request, to the DEHP.

All operational procedures and management plans are reviewed annually.

Corrective Actions / Contingency

Contingencies in place include:

Spill kits to ensure fast and effective response

SDS and HAZMAT box

Bunding of chemical storage areas

Bunding of generator

Bunding of chemical dosing units and storage tanks

Bunding of diesel tank storage

Chemical spill response procedures

Emergency Response Plan.

Defects with site plant and equipment are repaired as soon as practicable to prevent chemical spills / leakage.

The applicable corrective actions will be implemented following any emergency or incident affecting the site.

These will include:

Implement appropriate mitigation measures as determined by a suitably qualified person to prevent future non-compliance

Implement the corrective action(s) as required within the agreed timeframe

Complete and follow through with all relevant validation monitoring or actions to confirm that the nominated corrective actions have been effective

Ensure close out of all corrective actions, including documenting it through the appropriate processes.

Where it is found a Contingency or Corrective Action is insufficient, further investigation and reporting to take place.

LS-009 Page 27 of 29 Date issued: 27/01/2017 - Rev: 1.0

4.7 Element 8: Wetland management

Impacts

Inadequate management of wetland conditions leading to poor effluent quality and impacts on the receiving environment of the Logan River.

Objectives / Targets

Operation of wetlands in accordance with designer’s specifications.

Effluent quality achieved as specified in Table 2-3.

>90% plant coverage maintained within wetlands.

Control Measures

Wetlands are to be managed in accordance with this SBMP and the Wetland Management Plan (to be developed following detailed design)

Wetlands are to be constructed, staged and sized in accordance with wetland design.

Flows are to be delivered to wetland cells evenly, avoiding stagnant areas or variations in flow velocities.

Levels of water in the wetland are monitored daily and maintained within the optimum range identified in the design, other than during peak wet weather flow events. (300mm to 600mm depth)

Weed removal shall be undertaken as required, manually or using herbicides, as appropriate to the location and type of weed. If herbicides are used, these are to be applied in accordance with requirements indicated on the label i.e. approved for use over water.

Monitoring

Daily monitoring of water levels and flow velocities

Weekly inspection of outlets and inlets and vertical risers

Weekly check for dieback, plant coverage and presence of weeds

Monthly photographic monitoring of plant coverage from fixed photo-monitoring points

Record Keeping

Maintain records of all inspections and monitoring conducted at the site.

Maintain records of equipment inspections and any repairs and/or maintenance actions undertaken.

Maintain all records for a period of at least 5 years.

Reporting and Review

Reporting procedures for all notifications and reporting to the DEHP will be followed. Qualified/trained persons to carry out all notifications.

Notify the Environmental Management Systems Coordinator and Treatment Program Manager, as soon as practicable, after becoming aware of any site based emergency or notifiable environmental incident. The EMS team will be responsible for written notifications of environmental incidents.

Operational records, monitoring results and any corrective actions undertaken, will be available upon request, to the DEHP.

All operational procedures and management plans are reviewed annually.

LS-009 Page 28 of 29 Date issued: 27/01/2017 - Rev: 1.0

Corrective Actions / Contingency

The applicable corrective actions will be implemented following any emergency or incident affecting the site. These will include:

Implement appropriate mitigation measures as determined by a suitably qualified person to prevent future non-compliance.

Implement the corrective action(s) in consultation with the process team as required within the agreed timeframe.

Complete and follow through with all relevant validation monitoring or actions to confirm that the nominated corrective actions have been effective.

Ensure close out of all corrective actions, including documenting it through the appropriate processes.

Where it is found a Contingency or Corrective Action is insufficient, further investigation and reporting to take place.

LS-009 Page 29 of 29 Date issued: 27/01/2017 - Rev: 1.0

5. REFERENCES

Netserv Treatment Operations Management Plan (incorporating the Water Quality Release Improvement

Plan [WQRIP])

NetServ Recycled Water Management Plan (incorporating the Contaminant and Release Reduction

Strategy)

Water NetServ Sewer Overflow Management Plan (2014)

Logan Water Alliance Wastewater Overflow Abatement Strategy (2014)

Logan Water Alliance Sewerage Overflow Management Strategy (2010)