Site Analysis Checklist
-
Upload
sarathirv6 -
Category
Documents
-
view
215 -
download
11
description
Transcript of Site Analysis Checklist
Senior Project
Site Analysis Checklist
Section 1 Site Data
Section 2 Encroachments
Section 3 Local Jurisdiction & Zoning
Section 4 Site Access
Section 5 Site Drainage
Section 6 Environmental
Section 7 Public Utilities
a. Waterb. Sanitary Sewerc. Storm Sewer
Section 8 Private Utilities
a. Electricityb. Telephonec. Gas
Section 9 Geotechnical
Section 10 Topography
Section 11 Permitting/Fees
Milwaukee School of EngineeringDepartment of Architectural Engineering & Building Construction
Prepared by Prof. Michael Emmer
1
Senior Project
Date of Visit: _______________ Follow-up Visit: __________________
Project Name: ______________
Construction Manager or Design-Build Firm: ___________________________
Address of Project: _______________________________________________
_______________________________________________
_______________________________________________
CodeLocation and
Characteristics of the Site Site Remarks and Requirements
1.1 City, County, State
1.2 What is the description and area of the site?
1.3 What is the proximity to U.S., State, and local highways
1.4 What is the anticipated cost of the site?
1.5 What are the typical land uses of the overall area surrounding the site?
1.6 What is the existing use of the site?
1.7 What are the past uses of the site?
1.8 Is rail service available to the site? Required?
Milwaukee School of EngineeringDepartment of Architectural Engineering & Building Construction
Prepared by Prof. Michael Emmer
2
Senior Project
Code Encroachments Site Remarks and Requirements
2.1 Is a recent title report available for the site?
2.2 Are there any existing roads on the site?
2.3 What are the setback requirements?
2.4 Are there any utility easements/pipelines on the
site?
2.5 If so, who is responsible for the relocations?
2.6 Are there any known cemeteries, grave sites, or historic building sites on the
property?
2.7 Has the site been surveyed? Has the survey been checked
and verified?
Milwaukee School of EngineeringDepartment of Architectural Engineering & Building Construction
Prepared by Prof. Michael Emmer
3
Senior Project
Code Local Jurisdiction and Zoning
Site Remarks and Requirements
3.1 Is the property fully within the city limits?
3.2 Is it desirable or required to be included in the city limits
for utility service?
3.3 Will the property require annexation? If so, who is
responsible for the annexation process?
Describe the annexation process exhibits required,
time frame, and fees required, if any.
3.4 What is the current zoning classification? Is the property
properly zoned?
3.5 What percent of the site can be developed?
3.6 What are the landscaping requirements?
3.7 If rezoning is required, describe exhibits and/or fees required, rezoning process,
and time frame.3.8 What entity is responsible for
rezoning?
3.9 What is the zoning of adjacent properties? Provide
zoning map if available.
3.10 Provide local jurisdiction contact names and telephone
numbers
Milwaukee School of EngineeringDepartment of Architectural Engineering & Building Construction
Prepared by Prof. Michael Emmer
4
Senior Project
Code Site Access Site Remarks and Requirements
4.1 How many access points will be available to the property?
4.2 Are there any restrictions for access? Highway off/on
ramps? DOT restrictions?
4.3 Adjacent Roads• Location of Existing
Roads?• Condition of Existing
Roads?• Capacity of Existing
Roads?• Distance to the nearest
interstate interchange?• Upgrade requirements
(any geometric restrictions with respect to site access)?
• Who is responsible for improvements?
• Developer cost to upgrade existing roads?
• Who has jurisdiction over access control and permitting?
4.4 What are time requirements to complete the improvements?
4.5 Will site owner be responsible for future road improvements?
Milwaukee School of EngineeringDepartment of Architectural Engineering & Building Construction
Prepared by Prof. Michael Emmer
5
Senior Project
Code Site Drainage Site Remarks and Requirements
5.1 Is the property in a floodway? Floodplain?
5.2 Are there any creeks or drainage ditches on the
property?
5.3 Does the adjacent property drain onto or across the
property?
5.4 What are the drainage characteristics of the
property, and how does it drain to adjacent property?
5.5 Is On-site detention or retention required?
5.6 Are there any easements that require drainage?
Milwaukee School of EngineeringDepartment of Architectural Engineering & Building Construction
Prepared by Prof. Michael Emmer
6
Senior Project
Code Environmental Site Remarks or Requirements
6.1 Identify governing agency or agencies.
6.2 Are there any obvious environmental factors which
may affect the proposed project?
6.3 Does the site have any formal wetlands on it? Endangered
species? Historic sites?
6.4 What studies will be required? Has a Phase I been
performed on the site?
6.5 Have any studies already been prepared?
6.6 Additional Comments?
Milwaukee School of EngineeringDepartment of Architectural Engineering & Building Construction
Prepared by Prof. Michael Emmer
7
Senior Project
Code Public Utilities Site Remarks or Requirements
Water
7a.1 What is the name of the utility providing the water?
7a.2 What is the local capacity, surplus capacity, and pressure of the water
system?7a.2.1 Has a pressure and/or flow
test been conducted? If so, what are the results?
7a.3 What is the location, size, and capacity of the existing water
mains?7a.4 Are off-site extensions
required? If yes, who is responsible for design and
construction?7a.5 Are there any connections
fees, pro rata charges, etc. (other than meter charges) for connecting to existing water mains? If so, how are they determined and how much
are they?7a.6 What are the local utility
company’s rates for water?
7a.7 What are the requirements for fire protection?
7a.8 Are there any utilities buried on the site?
7a.9 Is the site large enough to support mound or septic?
Milwaukee School of EngineeringDepartment of Architectural Engineering & Building Construction
Prepared by Prof. Michael Emmer
8
Senior Project
Code Public Utilities Site Remarks or Requirements
Sanitary Sewer
7b.1 What is the name of the utility which will provide connection
service?7b.2 Is their existing sewer on
site?
7b.3 What is the size, location, and capacity of the closest main?
7b.4 Will a lift station be required? Who is responsible for design
and construction?7b.5 Are there any connection
fees, pro rata charges, area charges, etc. for connecting to existing main lines? If so,
how are they determined and how much are they
7b.5 Are there any connections fees, pro rata charges, etc.
(other than meter charges) for connecting to existing water mains? If so, how are they determined and how much
are they?7b.6 How does the utility company
calculate rates for sanitary water?
a. Is it based on water usage alone?
b. Can the rate be on actual meter flow?
c. What are the local utility company’s rates for sanitary sewer?
Milwaukee School of EngineeringDepartment of Architectural Engineering & Building Construction
Prepared by Prof. Michael Emmer
9
Senior Project
Code Private Utilities Site Remarks or Requirements
Electricity – If more than one utility company can provide power to the site, provide this section to each company.
8a.1 What is the name of the utility company which will serve the
site? Contact?8a.2 Is there any existing primary
distribution feeder with sufficient capacity available at
the site?8a.3 What is the location of the
power source? Is it overhead or underground? Will it need
to be relocated?8a.4 Is there an existing primary
distribution feeder with sufficient capacity available at the site to provide a second source of power? (A second feed can be from a different
transformer at the same substation. Preferably, a
second feed would be from a substation on a different
transmission line.)8a.5 With two power sources
available at the site, will the utility company provide a
looped primary service with manual transfer switches up
to and including transformers?
8a.6 Will one or both feeds require the installation of a substation
or transmission extension?8a.7 Will the utility company
provide, own, and maintain transformers for primary or
secondary services?8a.8 Will there be any cost to the
developer to bring one or two feeds to the site?
Milwaukee School of EngineeringDepartment of Architectural Engineering & Building Construction
Prepared by Prof. Michael Emmer
10
Senior Project
8a.9 Will there be any on-site easements required?
8a.10 Provide one line for existing transmission and distribution facilities with the proposed
switch locations line extension, and substation installations that might be
required.8a.11 Provide information on
rebates available for use on high efficiency equipment or load management problems
or other rebates that might be available for industrial or
commercial service.
Milwaukee School of EngineeringDepartment of Architectural Engineering & Building Construction
Prepared by Prof. Michael Emmer
11
Senior Project
Code Private Utilities Site Remarks or Requirements
Telephone, Cable, & Data
8b.1 What is the telephone company which will be
providing service? Contact?
8b.2 Is their sufficient capacity available? Fiber optic?
8b.3 What is the nearest main trunk location in relation to the
site?
8b.4 Are there any costs to the developer to bring service to
the site and estimated construction time to extend
the service?
8b.5 Are there any on-site easements required?
8b.6 Are there any connection fees?
8b.7 What are the local telephone company service rates and
options?
8b.8 What company will be providing the cable TV line?
8b.9 Will any other special telephone equipment be
required?
Milwaukee School of EngineeringDepartment of Architectural Engineering & Building Construction
Prepared by Prof. Michael Emmer
12
Senior Project
Code Private Utilities Site Remarks or Requirements
Gas
8c.1 Is natural gas available to the site?
8c.2 What utility provides natural gas? Contact?
8c.3 What is the location of the nearest main in relation to the
site?
8c.4 Are there any costs to the developer to bring gas service
to the site?
8c.5 Are there any connection fees?
8c.6 What are the local gas company service rates?
8c.7 If no natural gas is available, is propane available?
8c.8 Are there any special requirements for propane
storage and which agency is the jurisdictional authority?
Milwaukee School of EngineeringDepartment of Architectural Engineering & Building Construction
Prepared by Prof. Michael Emmer
13
Senior Project
Code Geotechnical Site Remarks or Requirements
9.1 Has a geotechnical investigation been prepared?
9.2 What type of soil is typically found on the proposed site? Are there any soils reports
available near the property?
9.3 Is their any evidence of unusual soil conditions? Has
the site been filled?
9.4 Is there any unusual material stockpiled on the site?
9.5 Have test borings been done? Has the report been
analyzed? Are more test pits or borings needed?
Milwaukee School of EngineeringDepartment of Architectural Engineering & Building Construction
Prepared by Prof. Michael Emmer
14
Senior Project
Code Topographic Site Remarks or Requirements
10.1 What are the maximum and minimum elevations on the
site?
10.2 How severe are the existing slopes?
10.3 What is the primary existing vegetation on the site?
10.4 Is a recent topographical map available? Please provide a
USGS map and other topographical maps if
available.
10.5 What are the landscape requirements? Does the city
have an existing tree ordinance?
Milwaukee School of EngineeringDepartment of Architectural Engineering & Building Construction
Prepared by Prof. Michael Emmer
15
Senior Project
Code Permitting & Fees Site Remarks or Requirements
11.1 Identify the permitting procedures, cost, the
anticipated time frame, and the agencies responsible for
the following:
11.2 Site Plan
11.3 Preliminary/Final Plat
11.4 Engineering Plans (Are the required with the Plat
Submittal?)
11.5 Zoning
11.6 Building Permit
11.7 Drainage/Flood Plain
11.8 Impact Fees
11.9 Traffic Impact Fee
11.10 Curb Cuts/Site Access
11.11 What agencies will review the project? City, Town, County,
and/or State?
Milwaukee School of EngineeringDepartment of Architectural Engineering & Building Construction
Prepared by Prof. Michael Emmer
16
Senior Project
Construction Site Checklist
Approved Project Budget
Approved Project Schedule
Contracts
• General Contractor or Construction Manager
• Architect
• Engineers
Payment and Performance Bonds (if necessary)
Construction Inspector
• Independent Testing Agency
Builder’s Risk Insurance
• Any special insurance requirements (if applicable)
Review Title Insurance Coverage
Approved Plans and Specifications
Permits
• Site/Grading
• Demolition
• Early Start Foundation
Review Lease Status (if applicable)
Off-site improvement agreements
Utility agreements/bonds
Milwaukee School of EngineeringDepartment of Architectural Engineering & Building Construction
Prepared by Prof. Michael Emmer
17
Senior Project
Hard Cost Assumptions
Project Name: ____________________________________________________
Prepared by: _____________________________________________________
Reviewed by: _____________________________________________________
Building Square Footage: _____________________
Lump Sum Unit CostSite Development/Drainage: $ Or $ SF
Mass Excavation $ Or $ SFDrainage $ Or $ SF
Utilities $ Or $ SF
Lump Sum Unit CostShell Construction: $ Or $ SF
Shell $ Or $ SF$ Or $ SF$ Or $ SF$ Or $ SF$ Or $ SF$ Or $ SF
Lump Sum Unit CostFinish Out: $ Or $ SF
Office $ Or $ SFWarehouse $ Or $ SF
$ Or $ SF$ Or $ SF$ Or $ SF$ Or $ SF
Lump Sum Unit CostLandscape/Irrigation: $ Or $ SF
Milwaukee School of EngineeringDepartment of Architectural Engineering & Building Construction
Prepared by Prof. Michael Emmer
18
Senior Project
$ Or $ SF
Lump Sum Unit CostMulti-Tenant Package: $ Or $ SF
Demising Walls $ Or $ SFSplit Electrical Service $ Or $ SF
Smoke Evacuation $ Or $ SFFire Alarm $ Or $ SF
Fire Protection $ Or $ SFLouvers/Overhead Doors $ Or $ SF
$ Or $ SF
Lump Sum Unit CostArchitectural & Engineering: $ Or $ SF
Architectural $ Or $ SFStructural $ Or $ SF
MEP $ Or $ SFCivil $ Or $ SF
Landscape $ Or $ SFGeotechnical $ Or $ SF
Environmental $ Or $ SFAcoustical $ Or $ SF
Lighting $ Or $ SFInterior Design $ Or $ SF
Furnishings $ Or $ SFSpecial Consultant $ Or $ SFSpecial Consultant $ Or $ SF
Lump Sum Unit CostA & E – Reimbursable: $ Or $ SF
$ Or $ SF
Lump Sum Unit CostTesting Consultants $ Or $ SF
Materials Testing $ Or $ SFRoof Inspection $ Or $ SF
Other $ Or $ SF
Milwaukee School of EngineeringDepartment of Architectural Engineering & Building Construction
Prepared by Prof. Michael Emmer
19
Senior Project
Lump Sum Unit CostImpact Fees $ Or $ SF
$ Or $ SF
Lump Sum Unit CostContingency $ Or $ SF
Milwaukee School of EngineeringDepartment of Architectural Engineering & Building Construction
Prepared by Prof. Michael Emmer
20