Single-Cavity Module Installation at MuCool Test Area

29
Single-Cavity Module Installation at MuCool Test Area Yağmur Torun MICE Collaboration Meeting February 15, 2013

description

Single-Cavity Module Installation at MuCool Test Area. Yağmur Torun MICE Collaboration Meeting February 15, 2013. MTA 201-MHz Program Overview (Surface treatment, NF channel, MICE). 201-MHz MICE prototype cavity with SRF-like surface treatment (EP, HP rinse) - PowerPoint PPT Presentation

Transcript of Single-Cavity Module Installation at MuCool Test Area

Page 1: Single-Cavity Module Installation at  MuCool  Test Area

Single-Cavity Module Installationat MuCool Test Area

Yağmur TorunMICE Collaboration Meeting

February 15, 2013

Page 2: Single-Cavity Module Installation at  MuCool  Test Area

Y. Torun | MICE cm35 2

MTA 201-MHz Program Overview(Surface treatment, NF channel, MICE)

• 201-MHz MICE prototype cavity with SRF-like surface treatment (EP, HP rinse)– Conditioned to design gradient quickly– Demonstrated operation with curved Be windows– Somewhat reduced performance in fringe field of

solenoid– No surface damage seen on cavity interior– Some evidence for sparking in the coupler

• New design has been implemented– Radiation output measured (MICE detector

backgrounds)• Future

– Install/operate single-cavity vessel– Large diameter magnet (“coupling coil”) needed

for field configuration closer to MICE/cooling channel

February 15, 2013

Page 3: Single-Cavity Module Installation at  MuCool  Test Area

Y. Torun | MICE cm35 3

201-MHz Single-Cavity Module

February 15, 2013

• MICE cavity in vacuum vessel for MTA test

• Components– 1st MICE cavity EP’ed

and now at Fermilab– Be windows ready– Tuner forks built– Ready for fabrication of

new couplers

Page 4: Single-Cavity Module Installation at  MuCool  Test Area

Y. Torun | MICE cm35 4

201-MHz Single-Cavity Module

• Assembly/integration– Cavity and vessel at Lab-6– Clean room prepared– Plan in place for handling

and transport (R. Schultz, J. Volk)– Assembly fixture designed (A. DeMello)– Tuner control bench tested (P. Hanlet)

• Expect operation Summer 2013– beam test also under consideration

• Ultimately will be tested with the first Coupling Coil Magnet– Requires 6-month MTA shutdown

February 15, 2013

Page 5: Single-Cavity Module Installation at  MuCool  Test Area

Y. Torun | MICE cm35 5

Current configuration

• Original prototype cavity still in the hall• was lifted onto platform during long

shutdown with shield wall out• using temporary forklift

• No vacuum vessel, air outside• end-plates for support

• Couplers already removed• one cut up for inspection

• To be lifted off platform• with new gantry crane

• span limited by entry maze• and rolled out through labyrinth on

casters• Rails will be reused for new module• Be windows will be transferred to new

cavity

February 15, 2013

Page 6: Single-Cavity Module Installation at  MuCool  Test Area

Y. Torun | MICE cm35 6

Next -- Single-Cavity Vessel

February 15, 2013

Page 7: Single-Cavity Module Installation at  MuCool  Test Area

Y. Torun | MICE cm35 7

Final layout -- RFCClite

February 15, 2013

Page 8: Single-Cavity Module Installation at  MuCool  Test Area

Y. Torun | MICE cm35 8

Cavity in Lab-6

February 15, 2013

Page 9: Single-Cavity Module Installation at  MuCool  Test Area

Y. Torun | MICE cm35 9

Vacuum Vessel in Lab-6

February 15, 2013

Page 10: Single-Cavity Module Installation at  MuCool  Test Area

Y. Torun | MICE cm35 10

Module Transport

• Will bring into MTA hall through labyrinth• Vessel with heavily ribbed doors too wide for

labyrinth– Will remove and roll in doors separately– Put on thin cover plate to keep module interior clean

• Module on stand too tall for clean room and labyrinth– New “transport” stand is 10” shorter

• Tight fit – checked with laser scan data

February 15, 2013

Page 11: Single-Cavity Module Installation at  MuCool  Test Area

Y. Torun | MICE cm35 11

MTA Hall Layout

February 15, 2013

Page 12: Single-Cavity Module Installation at  MuCool  Test Area

Y. Torun | MICE cm35 12

Laser scan data

February 15, 2013

Page 13: Single-Cavity Module Installation at  MuCool  Test Area

Y. Torun | MICE cm35 13

Through the Maze

February 15, 2013

Page 14: Single-Cavity Module Installation at  MuCool  Test Area

On Operational Stand

Page 15: Single-Cavity Module Installation at  MuCool  Test Area

On Transport Stand, thin doors

Page 16: Single-Cavity Module Installation at  MuCool  Test Area

Y. Torun | MICE cm35 16

Cover Plate Transport

February 15, 2013

Page 17: Single-Cavity Module Installation at  MuCool  Test Area

Y. Torun | MICE cm35 17

Lab 6 Clean Room

• Once doors removed & transport stand installed

• Cavity installation – Vertical– In Lab 6 clean room – Class 100– Insertion picture shown in clean room is old design– New design (A. DeMello) hot off the press– All mechanical assembly and RF testing in clean

room

February 15, 2013

Page 18: Single-Cavity Module Installation at  MuCool  Test Area

Y. Torun | MICE cm35 18

Cavity handling

• Detailed procedure available from LBNL

February 15, 2013

Page 19: Single-Cavity Module Installation at  MuCool  Test Area

Y. Torun | MICE cm35 19

Tuner installation

Initial concept – horizontal layout

February 15, 2013

Page 20: Single-Cavity Module Installation at  MuCool  Test Area

Y. Torun | MICE cm35 20

Cavity installation

Vertical layout selected• Smaller footprint better suited

to available clean room space• Similar to MICE RFCC• Simplified (one-sided)

February 15, 2013

Page 21: Single-Cavity Module Installation at  MuCool  Test Area

Y. Torun | MICE cm35 21

Insertion Fixture in Clean Room

February 15, 2013

Page 22: Single-Cavity Module Installation at  MuCool  Test Area

Y. Torun | MICE cm35 22

Assembly in MTA Hall

• Remove transport stand, install operational stand

• In MTA Clean Room– Install doors– RF Couplers– Other vacuum hardware

February 15, 2013

Page 23: Single-Cavity Module Installation at  MuCool  Test Area

Y. Torun | MICE cm35 23

Put on doors in MTA clean room

February 15, 2013

Page 24: Single-Cavity Module Installation at  MuCool  Test Area

Y. Torun | MICE cm35 24

Rough schedule

February 15, 2013

Date complete

Task Calendar time

Aug operation with B 3 w

Jul operation at B=0 3 w

Jun RF commissioning 2 w

May LLRF measurements 3 d

instrumentation 3 d

compressed air plumbing 4 w

water plumbing 4 w

leak-check/pumpdown 2 d

RF plumbing 4 w

align/survey in place 1 d

lift onto platform 1 d

swap stands 1 d

Install couplers 1 d

install windows, cover plates 1 d

clean MTA clean rm 1 d

remove old cavity 3 d

May move big crane into MTA 1 d

Page 25: Single-Cavity Module Installation at  MuCool  Test Area

Y. Torun | MICE cm35 25

Rough schedule

February 15, 2013

Date complete

Task Calendar time

Apr disassy/move MTA crane to MTA 1 d

move to MTA 1 w

replace cover plates 1 d

remove windows 1 d

coupler conditioning 2 w

mount couplers on conditioning stand 1 d

leak check 2 d

LLRF measurements 2 d

install couplers 1 d

coupler fabrication 8 w

install cover plates 1 d

LLRF measurements 1 w

test tuner control 2 w

install actuators 2 d

install windows 1 d

Date complete

Task Calendar time

remove windows 1 d

survey cavity in vessel 1 d

install cavity in vessel 1 w

remove cover plates 1 d

vessel into clean room 1 d

install tuning forks 1 d

tuning fork machining 1 w

Apr cavity on stand in clean rm 1 d

Page 26: Single-Cavity Module Installation at  MuCool  Test Area

Y. Torun | MICE cm35 26

Rough schedule

February 15, 2013

Date complete Task Calendar time

Mar coupler conditioning stand 4 w

clean clean room and parts 3 d

disassy/move MTA crane to Lab6 1 d

cavity in Lab6 clean rm 1 d

replace cover plates 1 d

leak check 2 d

vacuum system 3 w

safety doc/review 4 w

diagnostics design/fab 6 w

Mar fixture design/fab 8 w

Feb flat cover plates 2 w

Lab6 clean rm prep 1 w

support stand mods 1 w

swap stands 1 d

survey vessel 1 d

transport stand 3 w

Page 27: Single-Cavity Module Installation at  MuCool  Test Area

Y. Torun | MICE cm35 27

Other issues• Couplers

• preferable to test/condition before installation on cavity• couplers for prototype were conditioned at SNS on custom stand

• looking into locating leftover parts to it back together (R. Rimmer)• or designing a new stand

• Diagnostics• will build top plate with RF and vacuum pickups• acoustic sensors under test may be useful (P. Lane, P. Snopok)

• RF controls• plan in place to upgrade Linac 201-MHz station (R. Pasquinelli)

February 15, 2013

Page 28: Single-Cavity Module Installation at  MuCool  Test Area

Y. Torun | MICE cm35 28

Outlook

• On track for results from operation of single-cavity module at MTA by cm37

• tight schedule and lots of work to do• resource availability critical

• Installation will provide valuable experience for MICE RFCC module assembly

• There may be an opportunity to test MICE RF phase measurement concept

February 15, 2013

Page 29: Single-Cavity Module Installation at  MuCool  Test Area

Y. Torun | MICE cm35 29

Credits

• Most mechanical engineering material from Ryan Schultz (FNAL) & Allan DeMello (LBNL)

February 15, 2013