Single-Cavity Module Installation at MuCool Test Area
description
Transcript of Single-Cavity Module Installation at MuCool Test Area
Single-Cavity Module Installationat MuCool Test Area
Yağmur TorunMICE Collaboration Meeting
February 15, 2013
Y. Torun | MICE cm35 2
MTA 201-MHz Program Overview(Surface treatment, NF channel, MICE)
• 201-MHz MICE prototype cavity with SRF-like surface treatment (EP, HP rinse)– Conditioned to design gradient quickly– Demonstrated operation with curved Be windows– Somewhat reduced performance in fringe field of
solenoid– No surface damage seen on cavity interior– Some evidence for sparking in the coupler
• New design has been implemented– Radiation output measured (MICE detector
backgrounds)• Future
– Install/operate single-cavity vessel– Large diameter magnet (“coupling coil”) needed
for field configuration closer to MICE/cooling channel
February 15, 2013
Y. Torun | MICE cm35 3
201-MHz Single-Cavity Module
February 15, 2013
• MICE cavity in vacuum vessel for MTA test
• Components– 1st MICE cavity EP’ed
and now at Fermilab– Be windows ready– Tuner forks built– Ready for fabrication of
new couplers
Y. Torun | MICE cm35 4
201-MHz Single-Cavity Module
• Assembly/integration– Cavity and vessel at Lab-6– Clean room prepared– Plan in place for handling
and transport (R. Schultz, J. Volk)– Assembly fixture designed (A. DeMello)– Tuner control bench tested (P. Hanlet)
• Expect operation Summer 2013– beam test also under consideration
• Ultimately will be tested with the first Coupling Coil Magnet– Requires 6-month MTA shutdown
February 15, 2013
Y. Torun | MICE cm35 5
Current configuration
• Original prototype cavity still in the hall• was lifted onto platform during long
shutdown with shield wall out• using temporary forklift
• No vacuum vessel, air outside• end-plates for support
• Couplers already removed• one cut up for inspection
• To be lifted off platform• with new gantry crane
• span limited by entry maze• and rolled out through labyrinth on
casters• Rails will be reused for new module• Be windows will be transferred to new
cavity
February 15, 2013
Y. Torun | MICE cm35 6
Next -- Single-Cavity Vessel
February 15, 2013
Y. Torun | MICE cm35 7
Final layout -- RFCClite
February 15, 2013
Y. Torun | MICE cm35 8
Cavity in Lab-6
February 15, 2013
Y. Torun | MICE cm35 9
Vacuum Vessel in Lab-6
February 15, 2013
Y. Torun | MICE cm35 10
Module Transport
• Will bring into MTA hall through labyrinth• Vessel with heavily ribbed doors too wide for
labyrinth– Will remove and roll in doors separately– Put on thin cover plate to keep module interior clean
• Module on stand too tall for clean room and labyrinth– New “transport” stand is 10” shorter
• Tight fit – checked with laser scan data
February 15, 2013
Y. Torun | MICE cm35 11
MTA Hall Layout
February 15, 2013
Y. Torun | MICE cm35 12
Laser scan data
February 15, 2013
Y. Torun | MICE cm35 13
Through the Maze
February 15, 2013
On Operational Stand
On Transport Stand, thin doors
Y. Torun | MICE cm35 16
Cover Plate Transport
February 15, 2013
Y. Torun | MICE cm35 17
Lab 6 Clean Room
• Once doors removed & transport stand installed
• Cavity installation – Vertical– In Lab 6 clean room – Class 100– Insertion picture shown in clean room is old design– New design (A. DeMello) hot off the press– All mechanical assembly and RF testing in clean
room
February 15, 2013
Y. Torun | MICE cm35 18
Cavity handling
• Detailed procedure available from LBNL
February 15, 2013
Y. Torun | MICE cm35 19
Tuner installation
Initial concept – horizontal layout
February 15, 2013
Y. Torun | MICE cm35 20
Cavity installation
Vertical layout selected• Smaller footprint better suited
to available clean room space• Similar to MICE RFCC• Simplified (one-sided)
February 15, 2013
Y. Torun | MICE cm35 21
Insertion Fixture in Clean Room
February 15, 2013
Y. Torun | MICE cm35 22
Assembly in MTA Hall
• Remove transport stand, install operational stand
• In MTA Clean Room– Install doors– RF Couplers– Other vacuum hardware
February 15, 2013
Y. Torun | MICE cm35 23
Put on doors in MTA clean room
February 15, 2013
Y. Torun | MICE cm35 24
Rough schedule
February 15, 2013
Date complete
Task Calendar time
Aug operation with B 3 w
Jul operation at B=0 3 w
Jun RF commissioning 2 w
May LLRF measurements 3 d
instrumentation 3 d
compressed air plumbing 4 w
water plumbing 4 w
leak-check/pumpdown 2 d
RF plumbing 4 w
align/survey in place 1 d
lift onto platform 1 d
swap stands 1 d
Install couplers 1 d
install windows, cover plates 1 d
clean MTA clean rm 1 d
remove old cavity 3 d
May move big crane into MTA 1 d
Y. Torun | MICE cm35 25
Rough schedule
February 15, 2013
Date complete
Task Calendar time
Apr disassy/move MTA crane to MTA 1 d
move to MTA 1 w
replace cover plates 1 d
remove windows 1 d
coupler conditioning 2 w
mount couplers on conditioning stand 1 d
leak check 2 d
LLRF measurements 2 d
install couplers 1 d
coupler fabrication 8 w
install cover plates 1 d
LLRF measurements 1 w
test tuner control 2 w
install actuators 2 d
install windows 1 d
Date complete
Task Calendar time
remove windows 1 d
survey cavity in vessel 1 d
install cavity in vessel 1 w
remove cover plates 1 d
vessel into clean room 1 d
install tuning forks 1 d
tuning fork machining 1 w
Apr cavity on stand in clean rm 1 d
Y. Torun | MICE cm35 26
Rough schedule
February 15, 2013
Date complete Task Calendar time
Mar coupler conditioning stand 4 w
clean clean room and parts 3 d
disassy/move MTA crane to Lab6 1 d
cavity in Lab6 clean rm 1 d
replace cover plates 1 d
leak check 2 d
vacuum system 3 w
safety doc/review 4 w
diagnostics design/fab 6 w
Mar fixture design/fab 8 w
Feb flat cover plates 2 w
Lab6 clean rm prep 1 w
support stand mods 1 w
swap stands 1 d
survey vessel 1 d
transport stand 3 w
Y. Torun | MICE cm35 27
Other issues• Couplers
• preferable to test/condition before installation on cavity• couplers for prototype were conditioned at SNS on custom stand
• looking into locating leftover parts to it back together (R. Rimmer)• or designing a new stand
• Diagnostics• will build top plate with RF and vacuum pickups• acoustic sensors under test may be useful (P. Lane, P. Snopok)
• RF controls• plan in place to upgrade Linac 201-MHz station (R. Pasquinelli)
February 15, 2013
Y. Torun | MICE cm35 28
Outlook
• On track for results from operation of single-cavity module at MTA by cm37
• tight schedule and lots of work to do• resource availability critical
• Installation will provide valuable experience for MICE RFCC module assembly
• There may be an opportunity to test MICE RF phase measurement concept
February 15, 2013
Y. Torun | MICE cm35 29
Credits
• Most mechanical engineering material from Ryan Schultz (FNAL) & Allan DeMello (LBNL)
February 15, 2013