Simplifying the ComplexMULTI‐BILLION DOLLAR GREENFIELD CONSTRUCTION
AND THE ROLE OF NETPOINT
PRESENTED BY:
Dan Molnar & Tim Mather
![Page 2: Simplifying the Complex - PMA Technologies · Simplifying the Complex MULTI‐BILLION DOLLAR GREENFIELD CONSTRUCTION ... MEET THE PRESENTER Dan has over 25 years in Capital Project](https://reader034.fdocuments.net/reader034/viewer/2022042920/5f65ef8b68774020ce362800/html5/thumbnails/2.jpg)
Dan Molnar, PMPProject Services Leader
Shire [email protected]
MEET THE PRESENTER
Dan has over 25 years in Capital Project and Program Management in the pharmaceutical industry. He has experience in phases of pharmaceutical capital management from concept development through licensure. He has directly supported projects within the US, Puerto Rico, and Ireland. He has also developed and maintain global portfolio management systems. In many of his roles he has deployed innovative and effective tools to facilitate communication throughout the organization. Currently, he is the Project Services Leader for a $1B+ biopharma greenfield program being constructed in Social Circle, Georgia.
2
![Page 3: Simplifying the Complex - PMA Technologies · Simplifying the Complex MULTI‐BILLION DOLLAR GREENFIELD CONSTRUCTION ... MEET THE PRESENTER Dan has over 25 years in Capital Project](https://reader034.fdocuments.net/reader034/viewer/2022042920/5f65ef8b68774020ce362800/html5/thumbnails/3.jpg)
Tim Mather, PMPChief Technology OfficerPMA Technologies LLC
MEET THE PRESENTER
Tim Mather is the CTO of PMA Technologies LLC and in this role provides leadership in the design and development team as well as the intellectual property efforts surrounding NetPoint. Tim is a PMP with an extensive background in project management, software development, and software marketing. Tim holds a Bachelor’s degree from Michigan State University, and pursued postgraduate study of Project Management at the University of Chicago. Tim blogs about planning and scheduling at visualizetheplan.com.
3
![Page 4: Simplifying the Complex - PMA Technologies · Simplifying the Complex MULTI‐BILLION DOLLAR GREENFIELD CONSTRUCTION ... MEET THE PRESENTER Dan has over 25 years in Capital Project](https://reader034.fdocuments.net/reader034/viewer/2022042920/5f65ef8b68774020ce362800/html5/thumbnails/4.jpg)
160 acre property comprised of 9 buildings arranged in a spine/node configuration encompassing over 1.2 million square feet of building area.
$1+ Billion Greenfield Plasma Protein Manufacturing Facility in Covington, GA
4
![Page 5: Simplifying the Complex - PMA Technologies · Simplifying the Complex MULTI‐BILLION DOLLAR GREENFIELD CONSTRUCTION ... MEET THE PRESENTER Dan has over 25 years in Capital Project](https://reader034.fdocuments.net/reader034/viewer/2022042920/5f65ef8b68774020ce362800/html5/thumbnails/5.jpg)
Lifesaving MissionTo expand global supply of life saving plasma‐derived therapies, including Gammagard Liquid (Immune Globulin intravenous) and Flexbumin (human serum albumin)
5
![Page 6: Simplifying the Complex - PMA Technologies · Simplifying the Complex MULTI‐BILLION DOLLAR GREENFIELD CONSTRUCTION ... MEET THE PRESENTER Dan has over 25 years in Capital Project](https://reader034.fdocuments.net/reader034/viewer/2022042920/5f65ef8b68774020ce362800/html5/thumbnails/6.jpg)
COVINGTON GEORGIA GREENFIELD
6
![Page 7: Simplifying the Complex - PMA Technologies · Simplifying the Complex MULTI‐BILLION DOLLAR GREENFIELD CONSTRUCTION ... MEET THE PRESENTER Dan has over 25 years in Capital Project](https://reader034.fdocuments.net/reader034/viewer/2022042920/5f65ef8b68774020ce362800/html5/thumbnails/7.jpg)
COMPLETED FACILITY
7
![Page 8: Simplifying the Complex - PMA Technologies · Simplifying the Complex MULTI‐BILLION DOLLAR GREENFIELD CONSTRUCTION ... MEET THE PRESENTER Dan has over 25 years in Capital Project](https://reader034.fdocuments.net/reader034/viewer/2022042920/5f65ef8b68774020ce362800/html5/thumbnails/8.jpg)
Completed Facility
Three separate buildings are dedicated to protein manufacturing, including upstream large scale human plasma fractionation, albumin purification to finished bulk, and immunoglobulin purification by chromatography with aseptic filling and packaging to final container.
Support facilities include a Central Utilities Building, warehouse with ambient storage, +5C final product storage, and ‐25C plasma freezer, wastewater pretreatment plant, and laboratory/administrative buildings.
8
![Page 9: Simplifying the Complex - PMA Technologies · Simplifying the Complex MULTI‐BILLION DOLLAR GREENFIELD CONSTRUCTION ... MEET THE PRESENTER Dan has over 25 years in Capital Project](https://reader034.fdocuments.net/reader034/viewer/2022042920/5f65ef8b68774020ce362800/html5/thumbnails/9.jpg)
COMPLEX MEP
9
![Page 10: Simplifying the Complex - PMA Technologies · Simplifying the Complex MULTI‐BILLION DOLLAR GREENFIELD CONSTRUCTION ... MEET THE PRESENTER Dan has over 25 years in Capital Project](https://reader034.fdocuments.net/reader034/viewer/2022042920/5f65ef8b68774020ce362800/html5/thumbnails/10.jpg)
DAN’S ROLE IN THE PROJECTProject Services Leader
01Member of Program Leadership TeamCustodian of Governance Contract/Program Scope
04Risk ManagementComprehensive Risk Management program maintained within start‐up teams. Periodic, Independent, Quantitative Analyses (via OPRA)
02Schedule ManagementTeam of 8 Schedulers maintaining 12 integrated schedules (at peak) maintain via P6. Intensive start‐up planning and tracking of 6 startup teams. Program level reporting via NetPoint.
05Change ManagementCustodian of Change Management processes.
03Cost ManagementTeam of 5 cost engineers maintaining 10 sub‐projects. Monthly cost reporting and spend forecasting. Executive report‐out.
10
![Page 11: Simplifying the Complex - PMA Technologies · Simplifying the Complex MULTI‐BILLION DOLLAR GREENFIELD CONSTRUCTION ... MEET THE PRESENTER Dan has over 25 years in Capital Project](https://reader034.fdocuments.net/reader034/viewer/2022042920/5f65ef8b68774020ce362800/html5/thumbnails/11.jpg)
Interactive planning for schedule development
Resource and portfolio planning
Program summarization and interface management
|
ROLE OF NETPOINT IN THE PROJECT
NetPoint was a valuable supplement to existing project controls processes and tools. There is “value‐add” use for NetPoint in almost all aspects of project management including:
Quantitative risk analysis
11
![Page 12: Simplifying the Complex - PMA Technologies · Simplifying the Complex MULTI‐BILLION DOLLAR GREENFIELD CONSTRUCTION ... MEET THE PRESENTER Dan has over 25 years in Capital Project](https://reader034.fdocuments.net/reader034/viewer/2022042920/5f65ef8b68774020ce362800/html5/thumbnails/12.jpg)
INTERACTIVE PLANNING
Throughout the course of the program (as with a large program) there was a need to reassess or address scheduling conflicts.
12
![Page 13: Simplifying the Complex - PMA Technologies · Simplifying the Complex MULTI‐BILLION DOLLAR GREENFIELD CONSTRUCTION ... MEET THE PRESENTER Dan has over 25 years in Capital Project](https://reader034.fdocuments.net/reader034/viewer/2022042920/5f65ef8b68774020ce362800/html5/thumbnails/13.jpg)
PROGRAM SUMMARIZATION
|
Prior to Utilization of NetPoint
Prior to utilization of NetPoint, Leadership level schedule reports were bar graphs with no insight to interaction between projects.
01
02
Post‐introduction• Interactions were clear• A critical path evident• Informed decision‐making made much easier
13
![Page 14: Simplifying the Complex - PMA Technologies · Simplifying the Complex MULTI‐BILLION DOLLAR GREENFIELD CONSTRUCTION ... MEET THE PRESENTER Dan has over 25 years in Capital Project](https://reader034.fdocuments.net/reader034/viewer/2022042920/5f65ef8b68774020ce362800/html5/thumbnails/14.jpg)
02PROGRAM SUMMARIZATION
14
![Page 15: Simplifying the Complex - PMA Technologies · Simplifying the Complex MULTI‐BILLION DOLLAR GREENFIELD CONSTRUCTION ... MEET THE PRESENTER Dan has over 25 years in Capital Project](https://reader034.fdocuments.net/reader034/viewer/2022042920/5f65ef8b68774020ce362800/html5/thumbnails/15.jpg)
LEVEL 2 – PROGRAM EXAMPLE
03
15
![Page 16: Simplifying the Complex - PMA Technologies · Simplifying the Complex MULTI‐BILLION DOLLAR GREENFIELD CONSTRUCTION ... MEET THE PRESENTER Dan has over 25 years in Capital Project](https://reader034.fdocuments.net/reader034/viewer/2022042920/5f65ef8b68774020ce362800/html5/thumbnails/16.jpg)
RESOURCE /PORTFOLIO PLANNING
04
Facility Start‐upFacility start‐up presented several challenges regarding resource prioritization• Readiness vs. Process Optimization• Site Initiatives vs. Corporate Initiatives
Assess Resource Impacts NetPoint was used to assess resource impacts and
to facilitate timing decisions
05
16
![Page 17: Simplifying the Complex - PMA Technologies · Simplifying the Complex MULTI‐BILLION DOLLAR GREENFIELD CONSTRUCTION ... MEET THE PRESENTER Dan has over 25 years in Capital Project](https://reader034.fdocuments.net/reader034/viewer/2022042920/5f65ef8b68774020ce362800/html5/thumbnails/17.jpg)
RESOURCE / PORTFOLIO PLANNING
05
17
![Page 18: Simplifying the Complex - PMA Technologies · Simplifying the Complex MULTI‐BILLION DOLLAR GREENFIELD CONSTRUCTION ... MEET THE PRESENTER Dan has over 25 years in Capital Project](https://reader034.fdocuments.net/reader034/viewer/2022042920/5f65ef8b68774020ce362800/html5/thumbnails/18.jpg)
Risk Analyses brought “in‐house” at the beginning of CQV
Initial assessments were conducted by independent consultants with various methods of model development
NetPoint served as base schedule for several of the analyses.
QUANTITATIVE RISK ANALYSIS
Program included periodic quantitative schedule risk analyses throughout its life‐cycle
Program has maintained its progress along the P50 schedule
• Activity IDs tied to P6 and Risk Register facilitated impact analyses 18
![Page 19: Simplifying the Complex - PMA Technologies · Simplifying the Complex MULTI‐BILLION DOLLAR GREENFIELD CONSTRUCTION ... MEET THE PRESENTER Dan has over 25 years in Capital Project](https://reader034.fdocuments.net/reader034/viewer/2022042920/5f65ef8b68774020ce362800/html5/thumbnails/19.jpg)
SCHEDULE RISK ANALYSIS – METHOD DESCRIPTION
Risk Registers
NetPoint (Single License SCR)
PrimaveraRisk Analysis
19
![Page 20: Simplifying the Complex - PMA Technologies · Simplifying the Complex MULTI‐BILLION DOLLAR GREENFIELD CONSTRUCTION ... MEET THE PRESENTER Dan has over 25 years in Capital Project](https://reader034.fdocuments.net/reader034/viewer/2022042920/5f65ef8b68774020ce362800/html5/thumbnails/20.jpg)
KEY IMPACTS OF NETPOINT
01Simplifying the ComplexConsolidation of logic‐driven data at a level easily understood at the executive level
04Facilitated Risk AnalysesUpload to P6 and integration into OPRA simplify risk mapping (especially during Qualification/Validation phases)
02Intuitive Analysis (even to scheduling novices)Visual float analysis helped team see impacts of schedule slippage and workarounds
05Expedited resource requirements assessments
03Easily Accessible via BYODQuestions on current status address quickly and accurately
20
![Page 21: Simplifying the Complex - PMA Technologies · Simplifying the Complex MULTI‐BILLION DOLLAR GREENFIELD CONSTRUCTION ... MEET THE PRESENTER Dan has over 25 years in Capital Project](https://reader034.fdocuments.net/reader034/viewer/2022042920/5f65ef8b68774020ce362800/html5/thumbnails/21.jpg)
Questions?Thank you!
![Page 22: Simplifying the Complex - PMA Technologies · Simplifying the Complex MULTI‐BILLION DOLLAR GREENFIELD CONSTRUCTION ... MEET THE PRESENTER Dan has over 25 years in Capital Project](https://reader034.fdocuments.net/reader034/viewer/2022042920/5f65ef8b68774020ce362800/html5/thumbnails/22.jpg)
Tim Mather, PMP Chief Technology Officer
Dan Molnar, PMPProject Services Leader
Shire [email protected]